SlideShare a Scribd company logo
1 of 4
Download to read offline
Name: Ethan Gros
School: Michigan State University
Major: Electrical Engineering
DTE Department: Distribution Operations
1
Expectation for Internship: Work on designing and developing
circuits throughout the Detroit Area.
Garfield’s Smart Fault Indicators
2
Objective:
 Group of Interns developed an interactive display of Garfield substation’s circuits that used
the live readings from the Smart Fault Indicators
Execution:
 Used PI Process Book
 To re-draw Garfield’s
Network Bank Diagrams
and Secondary Cable
Diagrams.
 To create live current
readings displays
 To create buttons that
linked the Network Bank
Diagrams to the
Secondary Cable
Diagrams.
Conclusion:
 By creating these drawings with the live current reading other engineers can go
and look at where problems are occurring in Garfield’s Circuits.
Figure 1: Garfield’s Smart Fault Indicator Diagram of Network Bank 83 T
Future Plans for the Charlotte Substation
3
Objective:
 Plan to convert the old cables, substation
and network banks into new 13.2 kV in order
to make the circuits more cost effective.
Execution:
 Used ESRI
 To removed an entire substation’s
circuits
 To re-routed the cable so that it was
more cost effective
 To determined where network banks
were need today and which network
banks could be converted.
 To re-route circuits to other substations.
Conclusion:
 Through completing this project and creating some CU Estimates the engineers will be able to
get better estimate on how much the project would cost DTE Energy to implement in the
future.
Figure 2: Charlotte Circuits and Network banks in ESRI
David Stott Building 13.2 kV
4
Objective:
 Determine two circuits that could be routed to a
the high riser building.
Execution:
 Used conduit maps and ESRI
 To find what circuits
 To find what routes.
 To find length
 One-line diagrams and Area Load Analysis
 Determine whether the circuit could handle
the added load of the new building.
Conclusion:
 CU Estimates were created to convey the cost.
 Through the completion of this project a work
order would be created.
Figure 3: David Stott Building

More Related Content

What's hot

Present project
Present projectPresent project
Present project
Xun Eiei
 
A multi cell 21-level hybrid multilevel inverter synthesizes a reduced number...
A multi cell 21-level hybrid multilevel inverter synthesizes a reduced number...A multi cell 21-level hybrid multilevel inverter synthesizes a reduced number...
A multi cell 21-level hybrid multilevel inverter synthesizes a reduced number...
Asoka Technologies
 
A New Family of Step-up Hybrid Switched- Capacitor Integrated Multilevel Inve...
A New Family of Step-up Hybrid Switched- Capacitor Integrated Multilevel Inve...A New Family of Step-up Hybrid Switched- Capacitor Integrated Multilevel Inve...
A New Family of Step-up Hybrid Switched- Capacitor Integrated Multilevel Inve...
Asoka Technologies
 
Development of wind and solar based ac microgrid with power quality improveme...
Development of wind and solar based ac microgrid with power quality improveme...Development of wind and solar based ac microgrid with power quality improveme...
Development of wind and solar based ac microgrid with power quality improveme...
Asoka Technologies
 

What's hot (17)

Present project
Present projectPresent project
Present project
 
Generation of Higher Number of Voltage Levels by Stacking Inverters of Lower ...
Generation of Higher Number of Voltage Levels by Stacking Inverters of Lower ...Generation of Higher Number of Voltage Levels by Stacking Inverters of Lower ...
Generation of Higher Number of Voltage Levels by Stacking Inverters of Lower ...
 
Transforming, testing and explaining smart grid models
Transforming, testing and explaining smart grid modelsTransforming, testing and explaining smart grid models
Transforming, testing and explaining smart grid models
 
A Simplified Space Vector Pulse-Width Modulation Scheme for Three-Phase Casca...
A Simplified Space Vector Pulse-Width Modulation Scheme for Three-Phase Casca...A Simplified Space Vector Pulse-Width Modulation Scheme for Three-Phase Casca...
A Simplified Space Vector Pulse-Width Modulation Scheme for Three-Phase Casca...
 
Novel symmetric modular hybrid multilevel inverter with reduced number of sem...
Novel symmetric modular hybrid multilevel inverter with reduced number of sem...Novel symmetric modular hybrid multilevel inverter with reduced number of sem...
Novel symmetric modular hybrid multilevel inverter with reduced number of sem...
 
A generalized multilevel inverter topology with reduction of total standing v...
A generalized multilevel inverter topology with reduction of total standing v...A generalized multilevel inverter topology with reduction of total standing v...
A generalized multilevel inverter topology with reduction of total standing v...
 
A multi cell 21-level hybrid multilevel inverter synthesizes a reduced number...
A multi cell 21-level hybrid multilevel inverter synthesizes a reduced number...A multi cell 21-level hybrid multilevel inverter synthesizes a reduced number...
A multi cell 21-level hybrid multilevel inverter synthesizes a reduced number...
 
resume
resumeresume
resume
 
Design of Low Power Energy Efficient Carry Select Adder Using CMOS Technology
Design of Low Power Energy Efficient Carry Select Adder Using CMOS TechnologyDesign of Low Power Energy Efficient Carry Select Adder Using CMOS Technology
Design of Low Power Energy Efficient Carry Select Adder Using CMOS Technology
 
A Variable DC Link based Novel Multilevel Inverter Topology for Low Voltage A...
A Variable DC Link based Novel Multilevel Inverter Topology for Low Voltage A...A Variable DC Link based Novel Multilevel Inverter Topology for Low Voltage A...
A Variable DC Link based Novel Multilevel Inverter Topology for Low Voltage A...
 
jey new resume
jey new resumejey new resume
jey new resume
 
A New Family of Step-up Hybrid Switched- Capacitor Integrated Multilevel Inve...
A New Family of Step-up Hybrid Switched- Capacitor Integrated Multilevel Inve...A New Family of Step-up Hybrid Switched- Capacitor Integrated Multilevel Inve...
A New Family of Step-up Hybrid Switched- Capacitor Integrated Multilevel Inve...
 
An efficient modified cuk converter with fuzzy based maximum power point trac...
An efficient modified cuk converter with fuzzy based maximum power point trac...An efficient modified cuk converter with fuzzy based maximum power point trac...
An efficient modified cuk converter with fuzzy based maximum power point trac...
 
Poulomi_Chaudhuri-CV.PDF
Poulomi_Chaudhuri-CV.PDFPoulomi_Chaudhuri-CV.PDF
Poulomi_Chaudhuri-CV.PDF
 
Network analysis in gis
Network analysis in gisNetwork analysis in gis
Network analysis in gis
 
Cv md tarik chowdhury
Cv md tarik chowdhuryCv md tarik chowdhury
Cv md tarik chowdhury
 
Development of wind and solar based ac microgrid with power quality improveme...
Development of wind and solar based ac microgrid with power quality improveme...Development of wind and solar based ac microgrid with power quality improveme...
Development of wind and solar based ac microgrid with power quality improveme...
 

Viewers also liked

Tour of ukai on 21-Feb-2015
Tour of ukai on 21-Feb-2015Tour of ukai on 21-Feb-2015
Tour of ukai on 21-Feb-2015
Krunal Bhuvir
 
Hora de juego diagnóstico
Hora de juego diagnósticoHora de juego diagnóstico
Hora de juego diagnóstico
Hidriss
 

Viewers also liked (13)

Mr.brownreferen (1)
Mr.brownreferen (1)Mr.brownreferen (1)
Mr.brownreferen (1)
 
A Brief History of the NFL
A Brief History of the NFLA Brief History of the NFL
A Brief History of the NFL
 
Efecto matrix con photoshop
Efecto matrix con photoshopEfecto matrix con photoshop
Efecto matrix con photoshop
 
Peol fiori case study
Peol fiori case studyPeol fiori case study
Peol fiori case study
 
10-н сар
10-н сар10-н сар
10-н сар
 
Las tic y sus implicaciones
Las tic y sus implicacionesLas tic y sus implicaciones
Las tic y sus implicaciones
 
Tour of ukai on 21-Feb-2015
Tour of ukai on 21-Feb-2015Tour of ukai on 21-Feb-2015
Tour of ukai on 21-Feb-2015
 
Ansiedad en niños
Ansiedad en niñosAnsiedad en niños
Ansiedad en niños
 
Surgical infection
Surgical infectionSurgical infection
Surgical infection
 
Urology 4 hydronephrosis
Urology 4 hydronephrosisUrology 4 hydronephrosis
Urology 4 hydronephrosis
 
Setting up an email engine using amazon ses (vmokhsa technologies pvt. ltd.)
Setting up an email engine using amazon ses (vmokhsa technologies pvt. ltd.)Setting up an email engine using amazon ses (vmokhsa technologies pvt. ltd.)
Setting up an email engine using amazon ses (vmokhsa technologies pvt. ltd.)
 
Hora de juego diagnóstico
Hora de juego diagnósticoHora de juego diagnóstico
Hora de juego diagnóstico
 
Ansiedad proyecto
Ansiedad proyectoAnsiedad proyecto
Ansiedad proyecto
 

Similar to Ethan Gros - DTE Presentation

WPT FinalProgressReport
WPT FinalProgressReportWPT FinalProgressReport
WPT FinalProgressReport
Nadeem Qandeel
 
THE DESIGN AND IMPLEMENTATION OF A FOUR – WAY TRAFFIC LIGHT
THE DESIGN AND IMPLEMENTATION OF A FOUR – WAY TRAFFIC LIGHT THE DESIGN AND IMPLEMENTATION OF A FOUR – WAY TRAFFIC LIGHT
THE DESIGN AND IMPLEMENTATION OF A FOUR – WAY TRAFFIC LIGHT
Stephen Achionye
 
Balaguru.G_ Senior Electrical Designer
Balaguru.G_ Senior Electrical DesignerBalaguru.G_ Senior Electrical Designer
Balaguru.G_ Senior Electrical Designer
Bala G
 
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Aodhgan Gleeson
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final Report
Jeff Ge
 
Jordan_Gilmer_Resume
Jordan_Gilmer_ResumeJordan_Gilmer_Resume
Jordan_Gilmer_Resume
Jordan Gilmer
 
DTE Summer Internship Summary
DTE Summer Internship SummaryDTE Summer Internship Summary
DTE Summer Internship Summary
Ethan Gros
 

Similar to Ethan Gros - DTE Presentation (20)

WPT FinalProgressReport
WPT FinalProgressReportWPT FinalProgressReport
WPT FinalProgressReport
 
Mr. jagadeesh electrical design engineer
Mr. jagadeesh electrical design engineerMr. jagadeesh electrical design engineer
Mr. jagadeesh electrical design engineer
 
THE DESIGN AND IMPLEMENTATION OF A FOUR – WAY TRAFFIC LIGHT
THE DESIGN AND IMPLEMENTATION OF A FOUR – WAY TRAFFIC LIGHT THE DESIGN AND IMPLEMENTATION OF A FOUR – WAY TRAFFIC LIGHT
THE DESIGN AND IMPLEMENTATION OF A FOUR – WAY TRAFFIC LIGHT
 
Balaguru.G_ Senior Electrical Designer
Balaguru.G_ Senior Electrical DesignerBalaguru.G_ Senior Electrical Designer
Balaguru.G_ Senior Electrical Designer
 
2
22
2
 
Final Year Project Report. (Management of Smart Electricity Grids)
Final Year Project Report. (Management of Smart Electricity Grids)Final Year Project Report. (Management of Smart Electricity Grids)
Final Year Project Report. (Management of Smart Electricity Grids)
 
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
Modeling and Simulation of an electrical micro-grid using MATLAB Simulink Sum...
 
PSCAD Final Report
PSCAD Final ReportPSCAD Final Report
PSCAD Final Report
 
Jordan_Gilmer_Resume
Jordan_Gilmer_ResumeJordan_Gilmer_Resume
Jordan_Gilmer_Resume
 
Amplitude Modulation Circuit Implementation for use in a Communication Course...
Amplitude Modulation Circuit Implementation for use in a Communication Course...Amplitude Modulation Circuit Implementation for use in a Communication Course...
Amplitude Modulation Circuit Implementation for use in a Communication Course...
 
Design of management dashboard (smart electric grids)
Design of management dashboard (smart electric grids)Design of management dashboard (smart electric grids)
Design of management dashboard (smart electric grids)
 
FinalReport
FinalReportFinalReport
FinalReport
 
DTE Summer Internship Summary
DTE Summer Internship SummaryDTE Summer Internship Summary
DTE Summer Internship Summary
 
S2-R2
S2-R2S2-R2
S2-R2
 
CV_SIG_DES_MG_Dastagir 07_11_2016
CV_SIG_DES_MG_Dastagir 07_11_2016CV_SIG_DES_MG_Dastagir 07_11_2016
CV_SIG_DES_MG_Dastagir 07_11_2016
 
Jaydeep_Resume
Jaydeep_ResumeJaydeep_Resume
Jaydeep_Resume
 
SEM 6th final 1
SEM 6th final 1SEM 6th final 1
SEM 6th final 1
 
Power Supply Management System Of A Small Satellite By Wajid
Power Supply Management System Of A Small Satellite By WajidPower Supply Management System Of A Small Satellite By Wajid
Power Supply Management System Of A Small Satellite By Wajid
 
Impact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on GridImpact of Electric Vehicle Integration on Grid
Impact of Electric Vehicle Integration on Grid
 
Complete cdr report sample for telecommunication engineers
Complete cdr report sample for telecommunication engineersComplete cdr report sample for telecommunication engineers
Complete cdr report sample for telecommunication engineers
 

Ethan Gros - DTE Presentation

  • 1. Name: Ethan Gros School: Michigan State University Major: Electrical Engineering DTE Department: Distribution Operations 1 Expectation for Internship: Work on designing and developing circuits throughout the Detroit Area.
  • 2. Garfield’s Smart Fault Indicators 2 Objective:  Group of Interns developed an interactive display of Garfield substation’s circuits that used the live readings from the Smart Fault Indicators Execution:  Used PI Process Book  To re-draw Garfield’s Network Bank Diagrams and Secondary Cable Diagrams.  To create live current readings displays  To create buttons that linked the Network Bank Diagrams to the Secondary Cable Diagrams. Conclusion:  By creating these drawings with the live current reading other engineers can go and look at where problems are occurring in Garfield’s Circuits. Figure 1: Garfield’s Smart Fault Indicator Diagram of Network Bank 83 T
  • 3. Future Plans for the Charlotte Substation 3 Objective:  Plan to convert the old cables, substation and network banks into new 13.2 kV in order to make the circuits more cost effective. Execution:  Used ESRI  To removed an entire substation’s circuits  To re-routed the cable so that it was more cost effective  To determined where network banks were need today and which network banks could be converted.  To re-route circuits to other substations. Conclusion:  Through completing this project and creating some CU Estimates the engineers will be able to get better estimate on how much the project would cost DTE Energy to implement in the future. Figure 2: Charlotte Circuits and Network banks in ESRI
  • 4. David Stott Building 13.2 kV 4 Objective:  Determine two circuits that could be routed to a the high riser building. Execution:  Used conduit maps and ESRI  To find what circuits  To find what routes.  To find length  One-line diagrams and Area Load Analysis  Determine whether the circuit could handle the added load of the new building. Conclusion:  CU Estimates were created to convey the cost.  Through the completion of this project a work order would be created. Figure 3: David Stott Building