SlideShare a Scribd company logo
1 of 12
Download to read offline
TRIRIGA Capital Projects
System Requirements
Project Schedule
June 4, 2015
Release 5
Version 1.0
Release 5
Version 1.0 Page ii
Document Revision History
Version Revision Summary Author Date
Release 5
1.0
Managing Project Schedules Paul Tubinis
Erin Gross
Release 5
Version 1.0 Page iii
Contents
1 Project Requirements Overview .......................................................................................... 4
1.1 Background ...................................................................................................................... 4
1.2 Purpose, Scope and Objectives ........................................................................................ 4
1.3 Roles and Responsibilities ............................................................................................... 4
2 Assumptions, Constraints, and Dependencies, .................................................................... 6
2.1 Assumptions..................................................................................................................... 6
2.2 Constraints........................................................................................................................ 6
2.3 Dependencies ................................................................................................................... 6
3 Functional Capabilities ........................................................................................................ 6
4 Data Elements ...................................................................................................................... 7
5 Screenshots by Tab Exhibit ................................................................................................. 8
5.1 Schedule Tab.................................................................................................................... 8
5.2 Schedule Tab #2............................................................................................................... 9
5.3 Logic from original build for tracking schedule variance................................................ 9
5.4 Schedule TRIRIGA Work Flow from original configuration........................................ 11
6 Approvals and Signoff....................................................................................................... 11
Release 5
Version 1.0 Page 4
1 Project Requirements Overview
ECM presently is using spreadsheets to track the progress of Capital Projects for FDD. ECM had
been given the opportunity in 2011 to use TRIRIGA as the web enabled tool to track Capital
Projects and report to leadership on the status of Capital Projects using a report from TRIRIGA
application to support the monthly IPR process. Approximately 90 projects were input into
TRIRIGA and were actively tracked criteria including cost, schedule and other high level details.
1.1 Background
The requirements were started in February of 2012. It took approximately 6 months for the phase
one functionality to be completed. Due to multiple factors the ability to use TRIRIGA to track
projects was stopped in 2013. The TRIRIGA platform and applications were upgraded and the
entire configuration for ECM to use TRIRIGA to track Capital Projects was no longer available.
This removal of the technology platform for managing Requests for Project and day to day
activities of a project once it has been funded has forced the ECM team to use spreadsheets,
emails and other manual tools and files to manage complex business process associated with
WHS projects.
ECM at any time can have 75-100 projects either in the construction phase or in the investigating
the requests that have been made by the different Agencies.
1.2 Purpose, Scope and Objectives
ECM has a monthly process known as the IPR report that uses gantt chart capabilities to look at
the original baseline date and changes to the project schedule. The data for this report includes
the ability to portray Schedule Variance’ PoP, SPI and other key project points from schedule
maintenance.
1.3 Roles and Responsibilities
POC Agency Role
Greg Parker FSD/PCD/PMO PMO Program Manager
Mike Stebbing FSD/EECM/PCD Stakeholder (SME)
Paul Tubinis NET TRIRIGA (SME)
Faizullah Khattak FSD/FFD/FBSO COR
Adetutu Bosede EISTD Application Development Manager
Aaron Foster EITSD IFSA Project Manager
Erin Gross FBSO TRIRIGA Assistant Business Analyst
Release 5
Version 1.0 Page 5
Release 5
Version 1.0 Page 6
2 Assumptions, Constraints, and Dependencies,
2.1 Assumptions
TRIRIGA application set has the capability to manage complex project data.
2.2 Constraints
2.3 Dependencies
The system must be able to upload documents.
The system Gantt chart capabilities are required to function in the system. At this time this
function does not work in TRIRIGA Business Processes
ECM has a monthly process known as the IPR report that uses gantt chart capabilities to look at
the original baseline date and changes to the project schedule. The data for this report includes
the ability to portray Schedule Variance’ PoP, SPI and other key project points from schedule
maintenance.
3 Functional Capabilities
Req. # Requirement Comments Priority
Date
Rvwd
1 Ability to pick project templates
on the schedule tab. There will
be 4 different templates.
2 Ability to have the system check
project status based on a date in
time to support the monthly IPR
process
3 Produce IPR Green, Yellow, Red
Report
Release 5
Version 1.0 Page 7
4 Data Elements
Review/
Revise
# Data Element Label Type Required? Format Default
Value
Description
Schedule Tab
Probable
move to
when we do
the schedule
5.1 Add a field titled:
“Project % Complete”
Calculated
Probable
move to
when we do
the schedule
5.2 Add a field titled:
“Schedule Variance”
Calculated Values:
TBD
Probable
move to
when we do
the schedule
5.5 Add a field titled:
“SPI”
Calculated Calculations:
Earned Value
Planned Value
Probable
move to
when we do
the schedule
5.6 Add a field titled:
“PoP”
Calculated Calculated from
“Planned Start” to that of
the “Planned End”
Release 5
Version 1.0 Page 8
5 Screenshots by Tab Exhibit
5.1 Schedule Tab
Release 5
Version 1.0 Page 9
5.2 Schedule Tab #2
5.3 Logic from original build for tracking schedule variance
The decision tree for calculating the baseline schedule variance is as follows:
After the upload of the project is initiated (or an upload to update the project) the system runs a
number of work flows in the back ground. One of those workflows runs the following number of
checks against Planning, Design, and Construction tasks associated to the Project.
1. If there is no base line end date in the tasks it maps an "Incomplete Data" value to the
field, if there is a value in all the tasks it move to the next validation;
Release 5
Version 1.0 Page 10
2. If the Project status is Cancelled, Close-Out, or On-hold the field is set to "NOT
APPLICABLE"; if the validation fails, and the Project status is anything but the aforementioned,
it moves to the next validation;
3. If there is no value in the Project Actual Start Date the field is set to "Not
APPLICABLE", if there is a value, it moves to the next validation;
4. If there is a value in the Construction Task's Actual Start date:
4.1 And the Base Line Start Date is less than the Actual Start date the field is mapped
with "DELAYED"
4.2 And the Base Line Start Date is greater than the Actual Start Date the field is
mapped with "ON SCHEDULE"
5. If there is a value in the Design Task Actual End date:
5.1 And the Base Line Start Date is less than the Actual Start date the field is mapped
with "DELAYED"
5.2 And the Base Line Start Date is greater than the Actual Start Date the field is
mapped with "ON SCHEDULE"
6. If there is a Value in the Planning task Actual Start Date:
6.1 And the Base Line Start Date is less than the Actual Start date the field is mapped
with "DELAYED"
6.2 And the Base Line Start Date is greater than the Actual Start Date the field is
mapped with "ON SCHEDULE"
Release 5
Version 1.0 Page 11
5.4 Schedule TRIRIGA Work Flow from original configuration
6 Approvals and Signoff
Digitally signing this document below constitutes my concurrence.
Release 5
Version 1.0 Page 12
Government Manager Approval (digital signature)
Digitally signing this document below constitutes my concurrence.
Application Development Manager Approval (digital signature)

More Related Content

What's hot

P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsInSync Conference
 
Introduction to Primavera Reflections
Introduction to Primavera ReflectionsIntroduction to Primavera Reflections
Introduction to Primavera Reflectionsp6academy
 
Primavera short cuts or smart cuts in p6-advance
Primavera  short cuts or smart cuts in p6-advancePrimavera  short cuts or smart cuts in p6-advance
Primavera short cuts or smart cuts in p6-advanceASHISH KUMAR SINGH
 
Building Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectBuilding Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectRelu Rosenberg
 
Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Sagar Tilwani
 
Microsoft Project and Portfolio Management
Microsoft Project and Portfolio ManagementMicrosoft Project and Portfolio Management
Microsoft Project and Portfolio ManagementDavid J Rosenthal
 
MS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouMS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouCA Technologies
 
Implementation plan template
Implementation plan templateImplementation plan template
Implementation plan templateMarc Luker
 
Project planningchecklist
Project planningchecklistProject planningchecklist
Project planningchecklistbakul_kaushik
 
Microsoft project 2013
Microsoft project 2013Microsoft project 2013
Microsoft project 2013Jipin Nakarmi
 
Practical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersPractical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersSteve Gladstone
 
Project management with ms project 2007
Project management with ms project 2007Project management with ms project 2007
Project management with ms project 2007Fasil Ayele
 
Project system overview
Project system overviewProject system overview
Project system overviewAmlan Sarkar
 

What's hot (20)

Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....Introduction, development and analysis of banana curve in project management....
Introduction, development and analysis of banana curve in project management....
 
P6 Version 7 Tricks and Traps
P6 Version 7 Tricks and TrapsP6 Version 7 Tricks and Traps
P6 Version 7 Tricks and Traps
 
S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6S Curves Made Easy With Primavera P6
S Curves Made Easy With Primavera P6
 
Introduction to Primavera Reflections
Introduction to Primavera ReflectionsIntroduction to Primavera Reflections
Introduction to Primavera Reflections
 
Primavera short cuts or smart cuts in p6-advance
Primavera  short cuts or smart cuts in p6-advancePrimavera  short cuts or smart cuts in p6-advance
Primavera short cuts or smart cuts in p6-advance
 
Building Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms ProjectBuilding Formulas And Dashboard In Ms Project
Building Formulas And Dashboard In Ms Project
 
Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera Importance of Microsoft Project and Primavera
Importance of Microsoft Project and Primavera
 
Mech 202 Project 2 Report
Mech 202 Project 2 ReportMech 202 Project 2 Report
Mech 202 Project 2 Report
 
Microsoft Project and Portfolio Management
Microsoft Project and Portfolio ManagementMicrosoft Project and Portfolio Management
Microsoft Project and Portfolio Management
 
MS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for YouMS Project Integration: Tips, Tricks and What's New for You
MS Project Integration: Tips, Tricks and What's New for You
 
Implementation plan template
Implementation plan templateImplementation plan template
Implementation plan template
 
Project planningchecklist
Project planningchecklistProject planningchecklist
Project planningchecklist
 
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
071913 Rufran's Primavera Scheduling Tips & Tricks 05-13
 
Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3Oracle Primavera Team member 8.3
Oracle Primavera Team member 8.3
 
Microsoft project 2013
Microsoft project 2013Microsoft project 2013
Microsoft project 2013
 
Practical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project ManagersPractical Use of Microsoft Project for Project Managers
Practical Use of Microsoft Project for Project Managers
 
Project management with ms project 2007
Project management with ms project 2007Project management with ms project 2007
Project management with ms project 2007
 
Project system overview
Project system overviewProject system overview
Project system overview
 
080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1 080613 Mega-Project Schedule Integration & Management RCF Method-1
080613 Mega-Project Schedule Integration & Management RCF Method-1
 
Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01Loading cost in primavera schedule using resources and expenses r01
Loading cost in primavera schedule using resources and expenses r01
 

Similar to FBSO_IFSA_Requirements_Capital Projects Project SCHEDULE Release 5

VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxjessiehampson
 
project time management
 project time management project time management
project time managementHira Atiq
 
FBSO_IFSA_Requirements_Capital Projects_V12
FBSO_IFSA_Requirements_Capital Projects_V12FBSO_IFSA_Requirements_Capital Projects_V12
FBSO_IFSA_Requirements_Capital Projects_V12Erin T Gross
 
No matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxNo matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxhenrymartin15260
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management ProjectMary Stevenson
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptxTecnicoItca
 
Implementation plan template
Implementation plan templateImplementation plan template
Implementation plan templateMarc Luker
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentAcumen
 
Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Nzar Braim
 
Pmbok guide-6th-errata
Pmbok guide-6th-errataPmbok guide-6th-errata
Pmbok guide-6th-errataStiawan Adhi
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docxjeanettehully
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.pptssusere57332
 

Similar to FBSO_IFSA_Requirements_Capital Projects Project SCHEDULE Release 5 (20)

Session 5 4th edition PMP
Session 5 4th edition PMPSession 5 4th edition PMP
Session 5 4th edition PMP
 
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docxVoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
VoIP Implementation WBSTask NameDurationStart DateEnd DatePredeces.docx
 
project time management
 project time management project time management
project time management
 
FBSO_IFSA_Requirements_Capital Projects_V12
FBSO_IFSA_Requirements_Capital Projects_V12FBSO_IFSA_Requirements_Capital Projects_V12
FBSO_IFSA_Requirements_Capital Projects_V12
 
08 ch06
08 ch0608 ch06
08 ch06
 
No matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docxNo matter how hard we try, planning is not perfect, and sometimes .docx
No matter how hard we try, planning is not perfect, and sometimes .docx
 
Project Plan For A Project Management Project
Project Plan For A Project Management ProjectProject Plan For A Project Management Project
Project Plan For A Project Management Project
 
Project-Management.pptx
Project-Management.pptxProject-Management.pptx
Project-Management.pptx
 
Implementation plan template
Implementation plan templateImplementation plan template
Implementation plan template
 
Taming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule AssessmentTaming an Unruly Schedule with the 14 Point Schedule Assessment
Taming an Unruly Schedule with the 14 Point Schedule Assessment
 
Charter template 17.01.15
Charter template 17.01.15Charter template 17.01.15
Charter template 17.01.15
 
Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management Developing project objectives and Execution plan in Economy management
Developing project objectives and Execution plan in Economy management
 
Pmbok guide-6th-errata
Pmbok guide-6th-errataPmbok guide-6th-errata
Pmbok guide-6th-errata
 
Pmbok guide-6th-errata
Pmbok guide-6th-errataPmbok guide-6th-errata
Pmbok guide-6th-errata
 
Agile Project LifeCycle
Agile Project LifeCycleAgile Project LifeCycle
Agile Project LifeCycle
 
Schedule Training
Schedule TrainingSchedule Training
Schedule Training
 
Session 8 4th edition PMP
Session 8 4th edition PMPSession 8 4th edition PMP
Session 8 4th edition PMP
 
tcc primavera
tcc primaveratcc primavera
tcc primavera
 
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docxRunning Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT      .docx
Running Head PROJECT PLAN-BUSINESS REQUIREMENT DOCUMENT .docx
 
Schedule_Module_V.10.ppt
Schedule_Module_V.10.pptSchedule_Module_V.10.ppt
Schedule_Module_V.10.ppt
 

FBSO_IFSA_Requirements_Capital Projects Project SCHEDULE Release 5

  • 1. TRIRIGA Capital Projects System Requirements Project Schedule June 4, 2015 Release 5 Version 1.0
  • 2. Release 5 Version 1.0 Page ii Document Revision History Version Revision Summary Author Date Release 5 1.0 Managing Project Schedules Paul Tubinis Erin Gross
  • 3. Release 5 Version 1.0 Page iii Contents 1 Project Requirements Overview .......................................................................................... 4 1.1 Background ...................................................................................................................... 4 1.2 Purpose, Scope and Objectives ........................................................................................ 4 1.3 Roles and Responsibilities ............................................................................................... 4 2 Assumptions, Constraints, and Dependencies, .................................................................... 6 2.1 Assumptions..................................................................................................................... 6 2.2 Constraints........................................................................................................................ 6 2.3 Dependencies ................................................................................................................... 6 3 Functional Capabilities ........................................................................................................ 6 4 Data Elements ...................................................................................................................... 7 5 Screenshots by Tab Exhibit ................................................................................................. 8 5.1 Schedule Tab.................................................................................................................... 8 5.2 Schedule Tab #2............................................................................................................... 9 5.3 Logic from original build for tracking schedule variance................................................ 9 5.4 Schedule TRIRIGA Work Flow from original configuration........................................ 11 6 Approvals and Signoff....................................................................................................... 11
  • 4. Release 5 Version 1.0 Page 4 1 Project Requirements Overview ECM presently is using spreadsheets to track the progress of Capital Projects for FDD. ECM had been given the opportunity in 2011 to use TRIRIGA as the web enabled tool to track Capital Projects and report to leadership on the status of Capital Projects using a report from TRIRIGA application to support the monthly IPR process. Approximately 90 projects were input into TRIRIGA and were actively tracked criteria including cost, schedule and other high level details. 1.1 Background The requirements were started in February of 2012. It took approximately 6 months for the phase one functionality to be completed. Due to multiple factors the ability to use TRIRIGA to track projects was stopped in 2013. The TRIRIGA platform and applications were upgraded and the entire configuration for ECM to use TRIRIGA to track Capital Projects was no longer available. This removal of the technology platform for managing Requests for Project and day to day activities of a project once it has been funded has forced the ECM team to use spreadsheets, emails and other manual tools and files to manage complex business process associated with WHS projects. ECM at any time can have 75-100 projects either in the construction phase or in the investigating the requests that have been made by the different Agencies. 1.2 Purpose, Scope and Objectives ECM has a monthly process known as the IPR report that uses gantt chart capabilities to look at the original baseline date and changes to the project schedule. The data for this report includes the ability to portray Schedule Variance’ PoP, SPI and other key project points from schedule maintenance. 1.3 Roles and Responsibilities POC Agency Role Greg Parker FSD/PCD/PMO PMO Program Manager Mike Stebbing FSD/EECM/PCD Stakeholder (SME) Paul Tubinis NET TRIRIGA (SME) Faizullah Khattak FSD/FFD/FBSO COR Adetutu Bosede EISTD Application Development Manager Aaron Foster EITSD IFSA Project Manager Erin Gross FBSO TRIRIGA Assistant Business Analyst
  • 6. Release 5 Version 1.0 Page 6 2 Assumptions, Constraints, and Dependencies, 2.1 Assumptions TRIRIGA application set has the capability to manage complex project data. 2.2 Constraints 2.3 Dependencies The system must be able to upload documents. The system Gantt chart capabilities are required to function in the system. At this time this function does not work in TRIRIGA Business Processes ECM has a monthly process known as the IPR report that uses gantt chart capabilities to look at the original baseline date and changes to the project schedule. The data for this report includes the ability to portray Schedule Variance’ PoP, SPI and other key project points from schedule maintenance. 3 Functional Capabilities Req. # Requirement Comments Priority Date Rvwd 1 Ability to pick project templates on the schedule tab. There will be 4 different templates. 2 Ability to have the system check project status based on a date in time to support the monthly IPR process 3 Produce IPR Green, Yellow, Red Report
  • 7. Release 5 Version 1.0 Page 7 4 Data Elements Review/ Revise # Data Element Label Type Required? Format Default Value Description Schedule Tab Probable move to when we do the schedule 5.1 Add a field titled: “Project % Complete” Calculated Probable move to when we do the schedule 5.2 Add a field titled: “Schedule Variance” Calculated Values: TBD Probable move to when we do the schedule 5.5 Add a field titled: “SPI” Calculated Calculations: Earned Value Planned Value Probable move to when we do the schedule 5.6 Add a field titled: “PoP” Calculated Calculated from “Planned Start” to that of the “Planned End”
  • 8. Release 5 Version 1.0 Page 8 5 Screenshots by Tab Exhibit 5.1 Schedule Tab
  • 9. Release 5 Version 1.0 Page 9 5.2 Schedule Tab #2 5.3 Logic from original build for tracking schedule variance The decision tree for calculating the baseline schedule variance is as follows: After the upload of the project is initiated (or an upload to update the project) the system runs a number of work flows in the back ground. One of those workflows runs the following number of checks against Planning, Design, and Construction tasks associated to the Project. 1. If there is no base line end date in the tasks it maps an "Incomplete Data" value to the field, if there is a value in all the tasks it move to the next validation;
  • 10. Release 5 Version 1.0 Page 10 2. If the Project status is Cancelled, Close-Out, or On-hold the field is set to "NOT APPLICABLE"; if the validation fails, and the Project status is anything but the aforementioned, it moves to the next validation; 3. If there is no value in the Project Actual Start Date the field is set to "Not APPLICABLE", if there is a value, it moves to the next validation; 4. If there is a value in the Construction Task's Actual Start date: 4.1 And the Base Line Start Date is less than the Actual Start date the field is mapped with "DELAYED" 4.2 And the Base Line Start Date is greater than the Actual Start Date the field is mapped with "ON SCHEDULE" 5. If there is a value in the Design Task Actual End date: 5.1 And the Base Line Start Date is less than the Actual Start date the field is mapped with "DELAYED" 5.2 And the Base Line Start Date is greater than the Actual Start Date the field is mapped with "ON SCHEDULE" 6. If there is a Value in the Planning task Actual Start Date: 6.1 And the Base Line Start Date is less than the Actual Start date the field is mapped with "DELAYED" 6.2 And the Base Line Start Date is greater than the Actual Start Date the field is mapped with "ON SCHEDULE"
  • 11. Release 5 Version 1.0 Page 11 5.4 Schedule TRIRIGA Work Flow from original configuration 6 Approvals and Signoff Digitally signing this document below constitutes my concurrence.
  • 12. Release 5 Version 1.0 Page 12 Government Manager Approval (digital signature) Digitally signing this document below constitutes my concurrence. Application Development Manager Approval (digital signature)