High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
Hot-Mix-Plant-Calibration.ppt
1. Title or Name of presentation March 23 Page 1
HM Plant Calibration,
Laying, Compaction,
and Testing
BY
CHANDRA SEKHAR PASUPULETI
2. Title or Name of presentation March 23 Page 2
Objective
What is calibration of Hot Mix Plant
How to do the calibration
How to set the crushing pattern
Various steps to take care of good Laying,
compaction.
The Factors affecting the compaction
Quality control
3. Title or Name of presentation March 23 Page 3
HM PLANT
CALIBRATION
4. Title or Name of presentation March 23 Page 4
HOT MIX PLANT
5. Title or Name of presentation March 23 Page 5
What is calibration?
The calibration of HM plant is not only checking the
weighing scales, setting up appropriate cold bin feeding
as well as crusher quarry are also comes under this
chapter. Because…..
HM plant calibration
6. Title or Name of presentation March 23 Page 6
Plant capacity:
• Plant capacity = f(Pug mill size)
• Hourly rate = f(batch size, cycle time)
• What else affect the plant capacity??
(Here, output is plant capacity)
Input Process Output
HM plant calibration
7. Title or Name of presentation March 23 Page 7
Input:
• Material storage
• Cold feed
• Dryer
• Screening unit
• Hot bin setting
• Environmental conditions etc
HM plant calibration
8. Title or Name of presentation March 23 Page 8
Material storage:
• Proper stacking
• Protection from rain and foreign matters etc.
HM plant calibration
9. Title or Name of presentation March 23 Page 9
What is cold bin and hot bin?
Cold feed
• Cold bin aggregate
Sizes : 28 mm, 20 mm, 10 mm, Q/D
• Hot bin aggregate
Sizes : 16-24 mm, 8–16 mm, 4–8 mm, 0-4
mm, R/Filler
Which of the above two is base for mix design?
HM plant calibration
10. Title or Name of presentation March 23 Page 10
HM plant calibration
How to fix the cold bin feeding?
Individual grading
Blending
Calibration of cold feeders
11. Title or Name of presentation March 23 Page 11
Individual gradation and blending
1. Correct sampling and number of samples
2. Careful grading and blending to fix the necessary
proportions.
E:presentation 27.07.06plant calibrationindividual
grading.xls
HM plant calibration
12. Title or Name of presentation March 23 Page 12
Calibration of cold feeder:
• Cold feeding =
f(conveyer belt speed, gate opening)
• Conveyer belt speed (s), m/sec
• Select any one size
• Check the moisture content (w), %
• Keep the gate opening at certain scale
HM plant calibration
13. Title or Name of presentation March 23 Page 13
• Run the plant and take the material collected in
1 m length of belt, take the weight (Wm),kg.
• Dry weight (Wd) = Wm / (1+w) per m
• material per second, W = Wd X s
• Determine the ‘W ’ for different openings.
HM plant calibration
14. Title or Name of presentation March 23 Page 14
• Establish a graphical relation b/n gate opening
vs. dry weight of material delivered per second
• Do the same for all sizes
• From the graphs select the required opening to
feed different sizes as per the mix design
blending proportions.
E:presentation 27.07.06plant calibrationindividual
grading.xls
HM plant calibration
15. Title or Name of presentation March 23 Page 15
Relation ships established:
1. 28mm: y = 0.0043x - 2.2363, R2 = 0.9967
2. 20mm: y = 0.0047x - 5.4685, R2 = 0.9985
3. 10mm: y = 0.0033x - 0.5832, R2 = 0.9984
4. Q/dust: y = 0.0035x - 0.125, R2 = 0.9992
Where y = opening size and
x = weight in gm
HM plant calibration
16. Title or Name of presentation March 23 Page 16
Say, required production is 100 ton /h,
Total mix = 100 ton.
Total aggregate, if bitumen is 4.5%
= 100-100*.045 = 95.5 ton
Based on blending proportions are:
40 mm : 0 % 20 mm = 36%
10 mm = 23% C/Dust = 41%
HM plant calibration
17. Title or Name of presentation March 23 Page 17
20mm required per hour = 95.5*0.36 = 34.4 ton
Belt run in 1 h = 1.3920*60*60 m = 5011.2 m
Material required per meter run = 34.4/5011.2 = 6865
gm
Therefore, from eq.2,
gate opening, y = 0.0047x6865 - 5.4685 = 27
Likewise gate openings for all the sizes can be
calculated.
HM plant calibration
18. Title or Name of presentation March 23 Page 18
HOT BIN PROPORTIONING:
• It is very much necessary to set the hot bin
openings in such a way that all the cold feed
material is consumed at any point of time.
Procedure:
• Empty all the hot bins cleanly and close.
• Close all the cold feed, and release only one size.
• Run the material at certain opening for certain time.
HM plant calibration
19. Title or Name of presentation March 23 Page 19
• Let all the material screen through various sizes of
screens in the drum
• Check the material collected in different bins
• Take the weights of each bin.
• Calculate the % of material collected in each bin.
HM plant calibration
20. Title or Name of presentation March 23 Page 20
Cold feed vs. Hot bins
0 – 4
(6.4+38.2=
44.6)
28 mm (0 %)
4 – 8
(7.5+1.9+1.4
=10.8)
8 – 16
(9.1+25.8=
34.9)
16 – 24
(0 + 8.3 =
8.3)
20 mm (36%)
Q/Dust (41%)
10 mm (23%)
R/Filler
(1.4)
7.5% 92.5%
5.4% 71.7% 22.9%
27.7% 32.6% 39.6%
3.4%
93.3%
3.3 %
21. Title or Name of presentation March 23 Page 21
Therefore, hot bin proportions to be set at
• 16 – 24 = 8.3%
• 8 – 16 = 34.9%
• 4 – 8 = 10.8 %
• 0 - 4 = 44.6 %
• R/Filler = 1.4%
These are the proportions, according to the cold bin
feeding
Set the crusher production to meet cold feed or
vise versa
Cold feed vs. Hot bins
22. Title or Name of presentation March 23 Page 22
Summary of Advantages of calibration:
•No overflow from hot bin
•No segregation in the mix
•Increases the production capacity
•Correct job mix
•Balance with quarry production
•Reduction in re_handling
HM plant calibration
23. Title or Name of presentation March 23 Page 23
Laying, Compaction,
and Testing
24. Title or Name of presentation March 23 Page 24
Laying and compaction of the mix is the process to
which all the other operations are directed.
Planning and preparation
Prime coat / Tack coat
Paver: It spreads the mixture in a uniform layer of
desired thickness and shape, or finishes the layer to the
desired elevation and cross section, ready for
compaction.
Laying
25. Title or Name of presentation March 23 Page 25
Laying
Paver:
Working speed, width, thickness
Various forces acting on the screed
To achieve better compaction and level with paver
•The forces acting on the screed must be constant
To take care of these forces
•Material feeding in the hopper must be consistent
and adequate.
26. Title or Name of presentation March 23 Page 26
Laying
Paver:
•Material should be dumped with uniform thickness
•Sensor forces and the compacting forces on the
screed should not be vary
Starting wooden blocks may be used to set the paver
initially.
Maximum size of the aggregate must be 1/3 of
compacted thickness
Screed heaters also should be used initially, but not
during the paving
27. Title or Name of presentation March 23 Page 27
Laying
Trucks:
Take care of hydraulic oil leakages
Tarpaulin should be used during cool weather and long
hauling. The procedure to spread the tarpaulin also
important.
Backing of loaded trucks to the paver.
Truck must be totally loaded at a time.
Trucks must be clean and free from foreign materials
before loading.
Trucks may be coated with some releasing agents to
avoid the sticking of mixture.
28. Title or Name of presentation March 23 Page 28
Laying
Visual inspections:
Is there any blue smoke on the mix ( in the truck)
Shape of the mix in the truck (dome, flat)
Rate of temperature decrease in the mix
Dull appearance of the mix
Contamination of the mix at the bottom due to excess of
releasing agents. Bleeding may occur due to this.
29. Title or Name of presentation March 23 Page 29
Laying
Joints:
These are the main causes of early distresses due to
poor density at joints.
Joint in the first lift and second lift should not be
coincided.
Transverse joints must be vertically cut before starting
from there.
Rolling must be parallel to the joint.
150mm increments of roller from the old pavement.
30. Title or Name of presentation March 23 Page 30
Laying
Longitudinal joints must be treated carefully be
cleaning, tack coating and then over lap of paver about
25mm at least.
Coarse aggregates near the joints must be removed
and wasted.
Hot longitudinal joints generally have no problems.
31. Title or Name of presentation March 23 Page 31
Compaction – general mechanism
General mechanism:
Compaction = f( Compressive force, restricting force
incl. confinement)
32. Title or Name of presentation March 23 Page 32
Compaction
Factors affecting compaction:
1. Mix properties and characteristics of the
ingredients.
2. Environmental condition
3. Lift thickness
4. Sub grade base
33. Title or Name of presentation March 23 Page 33
Compaction
1. Mix properties and characteristics of the
ingredients:
Effect of maximum size of aggregate
Texture, contact area of aggregate
Grading type (Open grade may need more effort)
Crushed or natural aggregate
Compaction temperature should be more than 85oC
34. Title or Name of presentation March 23 Page 34
Compaction
1. Mix properties and characteristics of the
ingredients:
Rolling at less than 85oC will rather reduce the density
Temperatures of various construction activities must be
established
35. Title or Name of presentation March 23 Page 35
Compaction
2. Environmental conditions:
Wind velocity,
Humidity,
Ambient temperature
Temperature of the surface on which paving to be done.
36. Title or Name of presentation March 23 Page 36
Compaction
3. Lift thickness:
To get better compaction thickness should be more or
less in bituminous mixes??
.
37. Title or Name of presentation March 23 Page 37
Compaction
4. Sub grade base and confinement:
These must be good enough to take the forces of
vertical and horizontal to get better compaction
.
38. Title or Name of presentation March 23 Page 38
Compaction
Cold weather paving:
Need to take the following precautions:
• Lift thickness
• Mix temperature
• Hauling distance
• Plant speed
• Number of rollers
• Distance b/n roller and paver
• Paver speed
• Insulate the trucks
39. Title or Name of presentation March 23 Page 39
Compaction
Rollers: Should be self-propelled
Steel wheeled static roller
Pneumatic roller
Vibratory roller
40. Title or Name of presentation March 23 Page 40
Compaction
Steel wheeled static roller
Min. wt. 9 ton for heavy duty works
Wt. Can be changed by adding/removing ballasts
Can be used for break down , intermediate, and finished
rolling.
Should be free from grooves, pits, worn etc.
Position power wheel and tiller wheel (Normal and
steep grade pavements)
41. Title or Name of presentation March 23 Page 41
Compaction
Steel wheeled static roller:
Advantages of power wheel moving ahead.
• Higher diameter
• Heavier relatively
42. Title or Name of presentation March 23 Page 42
Compaction
Pneumatic roller:
Wheels oscillates
Same effect on the pavement like traffic.
Can be used for break down, intermediate, and also to
condition the asphalt surface.
Conditioning helps in reducing permeability and
increase the resistance to abrasion.
Tyre pressure should not be vary more than 35 Kpa
43. Title or Name of presentation March 23 Page 43
Compaction
Pneumatic roller:
Sub grade must be good enough as the pressure
exerted would be more than the static steel wheel
roller.
For rolling
Min wt per wheel. : 1360 to 1590
Min dia : 510 mm
Tyre inflation pressure : 486 to 517 Kpa
44. Title or Name of presentation March 23 Page 44
Compaction
Pneumatic roller:
For conditioning
• Min wt. Per wheel : 680
• Min dia : 380 mm
• Tyre inflation pressure : 345 - 415 Kpa
Kneading type rolling can be performed for more
than two weeks also, which will increase the surface
performance and not at all density.
45. Title or Name of presentation March 23 Page 45
Compaction
Vibratory roller:
• Weight
• Frequency
• Amplitude
How vibrations are created in the roller?
• Off-centric load
46. Title or Name of presentation March 23 Page 46
Compaction
Vibratory roller:
What is frequency?
• No of cycles per minute
• More the spinning speed more the load exerted,
more the eccentric load more the load exerted.
47. Title or Name of presentation March 23 Page 47
Compaction
Vibratory roller:
Amplitude
• More the eccentric load more the amplitude,
more the impact load
• Keep the speed and the frequncy matched to get
better surface.
• At least 10 vibrations per feet
48. Title or Name of presentation March 23 Page 48
Compaction
Vibratory roller:
• For thin layers – low amplitude – max frequency
• For thick layers – high amplitude – max
frequency
49. Title or Name of presentation March 23 Page 49
FOR ANY ROLLER. INCREASE THE NUMBER
OF PASSES BY INCREASING SPEED,
WILL NEVER GIVE THE BETTER COMPACTION
Compaction
IRRESPECTIVE OF ROLLER TYPE,
THE SPEED SHOULD BE : 5 – 8 KMPH
50. Title or Name of presentation March 23 Page 50
Where to control the quality?
• Plant
• Field – before laying
• Field – after laying
Quality Control
51. Title or Name of presentation March 23 Page 51
What is to be controlled at plant?
• In coming material quality check
• Cold-bin and hot-bin proportioning
• Gradation
• Bitumen content
• Temperature
Quality Control
52. Title or Name of presentation March 23 Page 52
Quality Control
Control tests at site?
• Temperature check at various operations.
• Paving and compaction by paver
• Thick ness
• Levels
• Fixing of censer with compaction factor
• Rolling (number of passes need to be established)
53. Title or Name of presentation March 23 Page 53
Quality Control
Tests on finished surface?
• Levels (+ 6 )
• Density ( Min : 98%)
• Surface un evenness
• Roughness
54. Title or Name of presentation March 23 Page 54
Quality Control
Inspection and Test Plan (ITP)
bitum mix designlaying com distressDBM ITP.xls
55. Title or Name of presentation March 23 Page 55
THAN Q
ANY QUESTIONS ?????