 OBJECTIVE AND PRINCIPLE OF STEAM BLOWING
 STEPS INVOLVED IN STEAM BLOWING ( WITH PATH DIAGRAM)
 PROCEDURE OF PRE-STEP STEAM BLOWING
 PROCEDURE OF MAIN STEP STEAM BLOWING
 COMPLETION CRITERIAN OF STEAM BLOWING
 PHOTOS OF SIPAT U # 1 STEAM BLOWING
STEAM BOWING PROCEDURE OF STAGE # 1
OBJECTIVE
The purpose of steam line blowing is to remove pipe slag, weld bead deposits and other foreign
material from the main and reheat steam systems prior to turbine operation. The cleaning is
accomplished by subjecting the piping systems to heating, blowing steam and cooling cycles in
sufficient number and duration until clean steam is obtained.
PRINCIPLE OF STEAM BLOWING
To ensure that sufficient cleaning forces are applied to the piping, the steam momentum
during the steam blow must be equal to or greater than the steam momentum at normal
maximum load condition. The Cleaning Force Ratio (CFR) is typically used to evaluate if
satisfactory blow conditions are obtained.
CFR = ( vb / vmcr ) x ( Fb / Fmcr )2 > 1.00
Where vb = specific volume at steam blowing condition
vmcr = specific volume at maximum load condition
Fb = steam mass flow rate at blowing condition
Fmcr = steam mass flow rate at maximum load condition
STEPS OF STEAM BLOWING
PRE STEP # 1 : Separator – SH - main steam line- Temporary pipe - martyr valve - tailpipe to
atmosphere.
PRE STEP # 2 : Separator - main steam line- HPBP – CRH Line – CRH Isolator - martyr valve -
tailpipe to atmosphere.
MAIN STEP # 1
: Separator-SH-main steam line-MSV-temporary pipe with martyr-valveNRV-CRH-
RH-HRH-LP Bypass valve-temporary pipe-tailpipe to atmosphere
MAIN STEP # 2
: Separator-SH-main steam line-MSV-temporary pipe with martyr-valve-NRV-CRH-RH-
HRH-IPT Stop Valve-temporary pipe-target-tailpipe to atmosphere
PRE STEP
PROCEDURE
 Start the Boiler as per normal working principle
 Raise the Seaprator Pressure to 40 Ksc
 At 40 Ksc Shut all Fuel Burners in service
 Stop The BRP Pump
 Open The Martyr Valve
 Let the pressure fall to 20 Ksc
 Close The Martyr Valve
COMPLETION CRITERIA
Clean White Smoke to be observed at the Exhaust of Tail Pipe
NOTE :
CFR < 1.0 AND NO TARGET PLATE IS TO BE USED DURING THIS STEP
First Blow at every Step to be given at much reduced pressure to check the temporary piping
healthiness
MAIN STEP
PROCEDURE
 Start the Boiler as per normal working principle
 Raise the Seaprator Pressure to 80 Ksc ( SH O/L Temp : 370
o
C)
 At 80 Ksc Shut all Fuel Burners in service
 Stop The BRP Pump
 Open The Martyr Valve
 Let the pressure fall to 40 Ksc
 Close The Martyr Valve
 Maintain the Separator Storage Tank Level
 Light The Boiler For Next Blowing
NOTE :
CFR > 1.0 AND NO TARGET PLATE IS TO BE USED DURING THIS STEP
First Blow at every Step to be given at much reduced pressure to check the temporary piping
healthiness
COMPLETION CRITERIAN
 No impacts with an diameter larger than 1 mm
 Not more than 4 impacts with an diameter larger than 0.5 mm
 Not more than 10 impacts with an diameter of 0.2 to 0.5 mm
A Target Plate is used to access the impacts of particle during steam Blowing. Steam Blowing
will be declared when
Final
SH
Final
SH
ESV
ESV
Martyr V/v
Martyr V/v
HP
Bypass
CRH Line
CRH NRV CRH Drain
Pot
RH O/L Hdr
HRH Line
MSV
LP
Bypass
IP SV
Open Close Martyr Valve
Steam Blow Line
Temporary Line
Pre Step # 1 : MS Line Steam Blowing
Final
SH
Final
SH
ESV
ESV
Martyr V/v
Martyr V/v
HP
Bypass
MS Line
CRH NRV CRH Drain
Pot
RH O/L Hdr
HRH Line
MSV
MSV
LP
Bypass
IP SV
Open Close Martyr Valve
Steam Blow Line
Temporary Line
Pre Step # 1 : MS Line Steam Blowing
LPBP V/ v
Final
SH
Final
SH
ESV
ESV
Martyr V/v
Martyr V/v
HP
Bypass
MS Line
CRH Line
CRH NRV CRH Drain
Pot
RH O/L Hdr
HRH Line
MSV
MSV
LP
Bypass
IP SV
Open Close Martyr Valve
Steam Blow Line
Temporary Line
Pre Step # 2 : HPBP / CRH Line Steam Blowing
Final
SH
Final
SH
ESV
ESV
Martyr V/v
Martyr V/v
HP
Bypass
MS Line
CRH Line
CRH NRV CRH Drain
Pot
RH O/L Hdr
HRH Line
MSV
MSV
LP
Bypass
IP SV
Open Close Martyr Valve
Steam Blow Line
Temporary Line
Main Step # 1 : HRH Line Steam Blowing
Final
SH
Final
SH
ESV
ESV
Martyr V/v
Martyr V/v
HP
Bypass
MS Line
CRH Line
CRH NRV CRH Drain
Pot
RH O/L Hdr
HRH Line
MSV
MSV
LP
Bypass
IP SV
Open Close Martyr Valve
Steam Blow Line
Temporary Line
Main Step # 2 :LPBP Line Steam Blowing
BRP
TO DRAIN HDR
FROM FEED WATER
BLR FILL PUMP
CHEM CLEANING SYS
CRH DRAIN LINE
SH COMMN DRAIN LINE
SH D.S.H. No1
ECO MIXING LINK
STORAGE TANK
MIXING PIECE
FLASH TANK
WR
ZR
WATER CIRCULATION SYSTEM
Sample Cooler
Blow Down Tan
Click
Here
TO ECO
To
Separator
From
Separator
From
Separator
FLASH
TANK
WR
ZR
From Storage Tank
Condensor
From Service Water
To Station Drain
Condensor
To D/A Floor
Modification # 1
Modification # 2
Dummy
Temporary Connection

More Related Content

Similar to steam_blowing.pdf

Sample Question and answer for power plants
Sample Question and answer for power plantsSample Question and answer for power plants
Sample Question and answer for power plantsVikeshgond2
 
Obra Presentaton Ash Handling Sysytem 28032023.pptx
Obra Presentaton Ash Handling Sysytem 28032023.pptxObra Presentaton Ash Handling Sysytem 28032023.pptx
Obra Presentaton Ash Handling Sysytem 28032023.pptxmrujjavalsinghvarana
 
Industrial Istrumentation
Industrial IstrumentationIndustrial Istrumentation
Industrial Istrumentationzmagical
 
660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliariesAshvani Shukla
 
ESP PPT NABINAGAR.pptx
ESP PPT NABINAGAR.pptxESP PPT NABINAGAR.pptx
ESP PPT NABINAGAR.pptxKhemantOd
 
Psv scenario-and-calculation
Psv scenario-and-calculationPsv scenario-and-calculation
Psv scenario-and-calculationChingLuh Nike
 
UNIT 1 SCTN_Vacuum Fundamentals_011.pptx
UNIT 1 SCTN_Vacuum Fundamentals_011.pptxUNIT 1 SCTN_Vacuum Fundamentals_011.pptx
UNIT 1 SCTN_Vacuum Fundamentals_011.pptxAwnishTripathi4
 
Prvs 2. asme section i fired vessel rev4
Prvs   2. asme section i fired vessel rev4Prvs   2. asme section i fired vessel rev4
Prvs 2. asme section i fired vessel rev4David Alexandre
 
Fluid mechanics Lab Report
Fluid mechanics Lab ReportFluid mechanics Lab Report
Fluid mechanics Lab ReportMuhammad Bilal
 
PSV Calculation and Philosophy.pdf
PSV Calculation and Philosophy.pdfPSV Calculation and Philosophy.pdf
PSV Calculation and Philosophy.pdfmitesh979351
 
Boiler feed and pump sizing c-b and grundfos july 2016(1)
Boiler feed and pump sizing   c-b and grundfos july 2016(1)Boiler feed and pump sizing   c-b and grundfos july 2016(1)
Boiler feed and pump sizing c-b and grundfos july 2016(1)lorenzo Monasca
 
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptxCNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptxRishabh Sirvaiya
 
40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter
40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter
40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow MeterEmerson Exchange
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPSManohar Tatwawadi
 

Similar to steam_blowing.pdf (20)

Sample Question and answer for power plants
Sample Question and answer for power plantsSample Question and answer for power plants
Sample Question and answer for power plants
 
I&C Technical Note
I&C Technical NoteI&C Technical Note
I&C Technical Note
 
Obra Presentaton Ash Handling Sysytem 28032023.pptx
Obra Presentaton Ash Handling Sysytem 28032023.pptxObra Presentaton Ash Handling Sysytem 28032023.pptx
Obra Presentaton Ash Handling Sysytem 28032023.pptx
 
Hplpbp
HplpbpHplpbp
Hplpbp
 
Industrial Istrumentation
Industrial IstrumentationIndustrial Istrumentation
Industrial Istrumentation
 
660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries660 mw turbo generator &amp; its auxiliaries
660 mw turbo generator &amp; its auxiliaries
 
ESP PPT NABINAGAR.pptx
ESP PPT NABINAGAR.pptxESP PPT NABINAGAR.pptx
ESP PPT NABINAGAR.pptx
 
Vacumn new
Vacumn newVacumn new
Vacumn new
 
Vacuum
VacuumVacuum
Vacuum
 
Psv scenario-and-calculation
Psv scenario-and-calculationPsv scenario-and-calculation
Psv scenario-and-calculation
 
PUMPS.ppt
PUMPS.pptPUMPS.ppt
PUMPS.ppt
 
The Science and Economics of Multiphase Flow
The Science and Economics of Multiphase FlowThe Science and Economics of Multiphase Flow
The Science and Economics of Multiphase Flow
 
UNIT 1 SCTN_Vacuum Fundamentals_011.pptx
UNIT 1 SCTN_Vacuum Fundamentals_011.pptxUNIT 1 SCTN_Vacuum Fundamentals_011.pptx
UNIT 1 SCTN_Vacuum Fundamentals_011.pptx
 
Prvs 2. asme section i fired vessel rev4
Prvs   2. asme section i fired vessel rev4Prvs   2. asme section i fired vessel rev4
Prvs 2. asme section i fired vessel rev4
 
Fluid mechanics Lab Report
Fluid mechanics Lab ReportFluid mechanics Lab Report
Fluid mechanics Lab Report
 
PSV Calculation and Philosophy.pdf
PSV Calculation and Philosophy.pdfPSV Calculation and Philosophy.pdf
PSV Calculation and Philosophy.pdf
 
Boiler feed and pump sizing c-b and grundfos july 2016(1)
Boiler feed and pump sizing   c-b and grundfos july 2016(1)Boiler feed and pump sizing   c-b and grundfos july 2016(1)
Boiler feed and pump sizing c-b and grundfos july 2016(1)
 
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptxCNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
CNG Technical & Hydrogen Blending in Natural Gas pipeline.pptx
 
40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter
40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter
40 CFR 98 Tier 4 Greenhouse Gas Reporting with Stack Emissions Flow Meter
 
Steam Turbine Performance in TPS
Steam Turbine Performance in TPSSteam Turbine Performance in TPS
Steam Turbine Performance in TPS
 

Recently uploaded

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingrakeshbaidya232001
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...ranjana rawat
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxpranjaldaimarysona
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxupamatechverse
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINESIVASHANKAR N
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...Call Girls in Nagpur High Profile
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Christo Ananth
 

Recently uploaded (20)

Porous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writingPorous Ceramics seminar and technical writing
Porous Ceramics seminar and technical writing
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
(SHREYA) Chakan Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Esc...
 
Processing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptxProcessing & Properties of Floor and Wall Tiles.pptx
Processing & Properties of Floor and Wall Tiles.pptx
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Introduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptxIntroduction to Multiple Access Protocol.pptx
Introduction to Multiple Access Protocol.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINEMANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
MANUFACTURING PROCESS-II UNIT-2 LATHE MACHINE
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...Booking open Available Pune Call Girls Koregaon Park  6297143586 Call Hot Ind...
Booking open Available Pune Call Girls Koregaon Park 6297143586 Call Hot Ind...
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANJALI) Dange Chowk Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
Call for Papers - African Journal of Biological Sciences, E-ISSN: 2663-2187, ...
 

steam_blowing.pdf

  • 1.  OBJECTIVE AND PRINCIPLE OF STEAM BLOWING  STEPS INVOLVED IN STEAM BLOWING ( WITH PATH DIAGRAM)  PROCEDURE OF PRE-STEP STEAM BLOWING  PROCEDURE OF MAIN STEP STEAM BLOWING  COMPLETION CRITERIAN OF STEAM BLOWING  PHOTOS OF SIPAT U # 1 STEAM BLOWING STEAM BOWING PROCEDURE OF STAGE # 1
  • 2. OBJECTIVE The purpose of steam line blowing is to remove pipe slag, weld bead deposits and other foreign material from the main and reheat steam systems prior to turbine operation. The cleaning is accomplished by subjecting the piping systems to heating, blowing steam and cooling cycles in sufficient number and duration until clean steam is obtained. PRINCIPLE OF STEAM BLOWING To ensure that sufficient cleaning forces are applied to the piping, the steam momentum during the steam blow must be equal to or greater than the steam momentum at normal maximum load condition. The Cleaning Force Ratio (CFR) is typically used to evaluate if satisfactory blow conditions are obtained. CFR = ( vb / vmcr ) x ( Fb / Fmcr )2 > 1.00 Where vb = specific volume at steam blowing condition vmcr = specific volume at maximum load condition Fb = steam mass flow rate at blowing condition Fmcr = steam mass flow rate at maximum load condition
  • 3. STEPS OF STEAM BLOWING PRE STEP # 1 : Separator – SH - main steam line- Temporary pipe - martyr valve - tailpipe to atmosphere. PRE STEP # 2 : Separator - main steam line- HPBP – CRH Line – CRH Isolator - martyr valve - tailpipe to atmosphere. MAIN STEP # 1 : Separator-SH-main steam line-MSV-temporary pipe with martyr-valveNRV-CRH- RH-HRH-LP Bypass valve-temporary pipe-tailpipe to atmosphere MAIN STEP # 2 : Separator-SH-main steam line-MSV-temporary pipe with martyr-valve-NRV-CRH-RH- HRH-IPT Stop Valve-temporary pipe-target-tailpipe to atmosphere
  • 4. PRE STEP PROCEDURE  Start the Boiler as per normal working principle  Raise the Seaprator Pressure to 40 Ksc  At 40 Ksc Shut all Fuel Burners in service  Stop The BRP Pump  Open The Martyr Valve  Let the pressure fall to 20 Ksc  Close The Martyr Valve COMPLETION CRITERIA Clean White Smoke to be observed at the Exhaust of Tail Pipe NOTE : CFR < 1.0 AND NO TARGET PLATE IS TO BE USED DURING THIS STEP First Blow at every Step to be given at much reduced pressure to check the temporary piping healthiness
  • 5. MAIN STEP PROCEDURE  Start the Boiler as per normal working principle  Raise the Seaprator Pressure to 80 Ksc ( SH O/L Temp : 370 o C)  At 80 Ksc Shut all Fuel Burners in service  Stop The BRP Pump  Open The Martyr Valve  Let the pressure fall to 40 Ksc  Close The Martyr Valve  Maintain the Separator Storage Tank Level  Light The Boiler For Next Blowing NOTE : CFR > 1.0 AND NO TARGET PLATE IS TO BE USED DURING THIS STEP First Blow at every Step to be given at much reduced pressure to check the temporary piping healthiness
  • 6. COMPLETION CRITERIAN  No impacts with an diameter larger than 1 mm  Not more than 4 impacts with an diameter larger than 0.5 mm  Not more than 10 impacts with an diameter of 0.2 to 0.5 mm A Target Plate is used to access the impacts of particle during steam Blowing. Steam Blowing will be declared when
  • 7.
  • 8.
  • 9.
  • 10.
  • 11.
  • 12.
  • 13. Final SH Final SH ESV ESV Martyr V/v Martyr V/v HP Bypass CRH Line CRH NRV CRH Drain Pot RH O/L Hdr HRH Line MSV LP Bypass IP SV Open Close Martyr Valve Steam Blow Line Temporary Line Pre Step # 1 : MS Line Steam Blowing Final SH Final SH ESV ESV Martyr V/v Martyr V/v HP Bypass MS Line CRH NRV CRH Drain Pot RH O/L Hdr HRH Line MSV MSV LP Bypass IP SV Open Close Martyr Valve Steam Blow Line Temporary Line Pre Step # 1 : MS Line Steam Blowing LPBP V/ v
  • 14. Final SH Final SH ESV ESV Martyr V/v Martyr V/v HP Bypass MS Line CRH Line CRH NRV CRH Drain Pot RH O/L Hdr HRH Line MSV MSV LP Bypass IP SV Open Close Martyr Valve Steam Blow Line Temporary Line Pre Step # 2 : HPBP / CRH Line Steam Blowing
  • 15. Final SH Final SH ESV ESV Martyr V/v Martyr V/v HP Bypass MS Line CRH Line CRH NRV CRH Drain Pot RH O/L Hdr HRH Line MSV MSV LP Bypass IP SV Open Close Martyr Valve Steam Blow Line Temporary Line Main Step # 1 : HRH Line Steam Blowing
  • 16. Final SH Final SH ESV ESV Martyr V/v Martyr V/v HP Bypass MS Line CRH Line CRH NRV CRH Drain Pot RH O/L Hdr HRH Line MSV MSV LP Bypass IP SV Open Close Martyr Valve Steam Blow Line Temporary Line Main Step # 2 :LPBP Line Steam Blowing
  • 17. BRP TO DRAIN HDR FROM FEED WATER BLR FILL PUMP CHEM CLEANING SYS CRH DRAIN LINE SH COMMN DRAIN LINE SH D.S.H. No1 ECO MIXING LINK STORAGE TANK MIXING PIECE FLASH TANK WR ZR WATER CIRCULATION SYSTEM Sample Cooler Blow Down Tan Click Here TO ECO To Separator From Separator From Separator
  • 18. FLASH TANK WR ZR From Storage Tank Condensor From Service Water To Station Drain Condensor To D/A Floor Modification # 1 Modification # 2 Dummy Temporary Connection