SlideShare a Scribd company logo
1 of 13
VADODARA HALOL TOLL ROAD
SUBMITTED BY :
SOURABH MOREY AH19155
NEERAJ NAMDEV AH19158
DEEPAM PATIDAR AH19169
RAHUL VISHWAKARMA AH19188
RAJAT RAGUWANSHI AH19192
INTRODUCTION
• The Vadodara Halol Toll Road (VHTR) was one of the first State Highway widening projects developed on a Public Private
Partnership.
• Vadodara Halol Toll Road was operated and maintained by VHTRL, a special purpose vehicle, promoted by (Government of
Gujarat) GoG and (Infrastructure leasing and finiacial service) ILF&S.
• The VHTR project is developed under the Built, Own, Operate and Transfer (BOOT) basis.
• Consortium of Punj Lloyd Limited and IRCON International Limited as contractors.
• The actual revenues as a proportion of the projected revenues had fallen from 63% to 34% during the three years of operation.
• TRC (Toll revenue committee ) has options of increasing rates for MAV or increasing rates for all vehicles or increasing rates for
(Multi-axle vehicle ) MAV and restructuring finance.
• Each option has been evaluated in terms of impact on traffic and revenue and the cost incurred.
• On the basis of this evaluation, it is recommended that VHTRL should increase rates for MAV and restructure its financing.
SITUATIONALANALYSIS
• VHTRL was jointly promoted by GoG and IL&FS for developing and implementing Vadodara Halol Road Project.
• Vadodara-Halol Road had gained importance because of growing industrialization in Halol.
• The project attained completion on Sep 15, 2000 and the commercial operations began on Oct 24, 2000.
• VHTRL manages, operates and maintains the road for 30 years starting from 2000.
• The actual revenue has been less than the expected revenue and an appropriate action has to be taken.
• The actual revenue has been less than the expected revenue and an appropriate action has to be taken. According to the projected
cash flows, VHTRL may have to shut down their operations by mid 2003 owing to the losses they would suffer.
• The total debt carried is Rs 1058.3 million with the average cost of borrowing as 15.52%.
• The dilemma faced by Toll Review Committee is how to increase the revenue and reduce the cost so as to make the project
sustainable. During the two rounds of TRC meeting, the company collected additional information and these inputs were further
examined.
• VHTRL is currently undercharging the MAVs and hence revision of rates may be needed (Refering Exhibit – 4,5,6)
• Exhibit 7 and 8 explains how the financing structure of the project can be improved to reduce the borrowing cost of the project.
PROBLEM STATEMENT
• VHTRL needs to increase revenue and/or reduce cost to sustain the project.
Option
1. Increase rates for MAV
2.Increase rates for All Vehicles
3.Increase rates for MAV and Financial Restructuring
1. Increase rates for MAV:
 Impact on Traffic and Revenue
• It is suggested to increase average rates for MAV to Rs 4.8205 per km. Exhibit 4 shows the average rates for MAV at different toll
roads in the country. From Exhibit 5, the current average rate for MAV in Vadodara-Halol Toll Road is Rs 2.9/km, which is lesser
than the average toll rates charged in the country.
• To achieve the average rate of Rs 4.8205 per km, the revised toll rates for MAVs are mentioned in the Exhibit 6.
• So most of the MAVs are travelling long distance, there could be a possibility that the MAVs would use the alternative path NH8
after the price increase.
• Assuming Diesel Rate of Rs. 18/litre (2002 price) and the average fuel efficiency of MAVs at 15kms/litre, the average fuel savings
of an MAV for travelling 50 kilometres lesser is Rs 60.
• The effective savings would be more since travelling through Vadodara-Halol road and bypassing Ahmedabad would save time and
the vehicle doesn’t have to go through the crowded city.
• The total savings on offer are more than the increase in toll rates. It is thus, safe to assume that the total traffic of MAVs will not
reduce after the toll rates are increased.
• The total revenue would increase by 11.33%. Hence, the projected cash flow of 2003-04 would increase from Rs. 90 millions to Rs.
100.2 millions.
 Impact on Cost Incurred
• The rate increase would lead to an increased cash flow of around Rs 10 million per year.
• But the total inflow of Rs. 113.11 million is still substantially behind the 7.6 projected total outflow of Rs 250 million per year
(projected for 2003-04).
• Hence, this change alone will not help us in sustaining the business over time.
2. Increase rates for All Vehicles:
 Impact on Traffic and Revenue
• The smaller vehicles (2 wheelers, 3 wheelers, Car, etc) are much more price sensitive and increasing the rates for the smaller
vehicles would make them use the service road more often.
• On one hand, increasing the rates would increase the revenue, but on the other hand, the number of vehicles travelling would
reduce leading to reduction in total revenue.
• Hence, the total revenue from the smaller vehicles would nearly remain the same.
• Increasing the toll rates for the MAV would increase the revenue as discussed above. This option is not recommended because
of uncertainty of revenue involved in this case.
 Impact on Cost Incurred
• The cost incurred would still be considerably higher than the inflows, i.e., cost incurred as per the projected cash flows is Rs
255.45 million as compared to inflows of Rs 130.86 million.
3. Increase rates for MAVs and Financial Restructuring:
 Impact on Traffic and Revenue
• As discussed in Option 1, there will be an increase in the total revenue when the toll rates for MAVs are increased. It is also
critical to reduce the cost of borrowing of the project as increasing the revenue alone isn’t enough for sustaining the project.
• Also, selling hoarding rights would add to the revenue.
 Impact on Cost Incurred
• The current financing structure of the project involves Debt/Equity Ratio of 1.924 and average cost of debt if 15.52% (Exhibit 3
- table 3,4)
• The total interest charges incurred by the project forms the majority part of the total outflows of the project.
• It is of great importance to restructure the financing aspect of the project to reduce the debt burden. It should attract private
equity to reduce the debt burden.
• Also, refinancing the debt would help in reducing the average cost of borrowing. A considerable amount of early debt has been
picked up at more than 15% rate of interest, e.g, ILF&S has 16% rate of interest. It is recommended to restructure Debt/Equity
ratio to 1:1 and refinance the debt which has high rate of interest.
• Exhibit 7 shows the current projected interest burden and Exhibit 8 shows the projected interest burden after the
financing is restructured.
• These changes will make the project profitable.
• RECOMMENDATION - VHRTC would be benefitted if they increase the toll rates for MAVs and
restructure financing. This would help them improve their financial situation and sustain the project.
Action Plan
• Issue appropriate notifications regarding revision of toll rates.
• Approach private equity investors to attract private investment to the project.
• Negotiate with lenders to refinance the existing debt.
• Float RFP (REQUEST FOR PROPASAL ) for hoarding rights.
EXHIBIT 1. Abbreviation
VHTRL – Vododara Halol Toll Road Company Limited
GoG- Government of Gujarat
IL&FS – Infrastructure leasing & Financial Services
TRC – Toll Review Committee
MAV – Multi Axle vechile
REP – Request for proposal
Exhibit 3: Current Financing of the project
Exhibit 4: Toll Rates for MAVs of other Projects
Exhibit 5: Determine the ratios of Three-Axle, Four-Axle and Five-Axle vehicles
Percentage of revenue which comes from these vehicles is as follows (Exhibit 3, table 5 – toll structure):
Three-Axle: 71.2%
Four-Axle: 21.5%
Five-Axle: 7.3%
Present Toll Rates (Rs): (table 7 )
Three-Axle: 85
Four-Axle: 105
Five-Axle: 125
If we solve using the above information, we get the average ratio of the MAVs as:
Three-Axle : Four-Axle : Three-Axle :: 24 : 6 : 1
E.g. For every Three-Axle MAV, we have 6 numbers of Four Axle MAV and 24 numbers of Three-Axle
Total – 24+6 +1 = 31
Case Study on - Vadodara halol Toll road
Case Study on - Vadodara halol Toll road

More Related Content

What's hot

Delhi metro rail corporation project
Delhi metro rail corporation projectDelhi metro rail corporation project
Delhi metro rail corporation projectVimal Maurya
 
BRT System in Delhi
BRT System in DelhiBRT System in Delhi
BRT System in DelhiJaspal Singh
 
Urban housing scenario and rental housing in india
Urban housing scenario and rental housing in indiaUrban housing scenario and rental housing in india
Urban housing scenario and rental housing in indiapadamatikona swapnika
 
Role of transportation in urban development
Role of transportation in urban developmentRole of transportation in urban development
Role of transportation in urban developmentSiddhi Vakharia
 
Delhi Mumbai Industrial Corridor
Delhi Mumbai Industrial CorridorDelhi Mumbai Industrial Corridor
Delhi Mumbai Industrial CorridorVishal Dedhia
 
Road Development and Maintenance of Rural Areas
Road Development and Maintenance of Rural AreasRoad Development and Maintenance of Rural Areas
Road Development and Maintenance of Rural AreasAmit Yadav
 
Eco City Development towards Developing Low Carbon Society
Eco City Development towards Developing Low Carbon SocietyEco City Development towards Developing Low Carbon Society
Eco City Development towards Developing Low Carbon SocietyMD. SAIDUR RAHMAN
 
Transportation problem with relevance to indian cities
Transportation problem with relevance to indian citiesTransportation problem with relevance to indian cities
Transportation problem with relevance to indian citiesSailish Cephas
 
Government of India Ministry of Road Transport & Highways
Government of India Ministry of Road Transport & HighwaysGovernment of India Ministry of Road Transport & Highways
Government of India Ministry of Road Transport & HighwaysSanjitBakshi2
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase IKaran Shah
 
NON-MOTORIZED TRANSPORT - UTTIPEC
NON-MOTORIZED TRANSPORT - UTTIPECNON-MOTORIZED TRANSPORT - UTTIPEC
NON-MOTORIZED TRANSPORT - UTTIPECParomita Roy
 
Case study of feasibility study of mrts
Case study of feasibility study of mrtsCase study of feasibility study of mrts
Case study of feasibility study of mrtsDivyarajsinh Chudasama
 

What's hot (20)

Transit oriented Development
Transit oriented DevelopmentTransit oriented Development
Transit oriented Development
 
Delhi metro rail corporation project
Delhi metro rail corporation projectDelhi metro rail corporation project
Delhi metro rail corporation project
 
BRT System in Delhi
BRT System in DelhiBRT System in Delhi
BRT System in Delhi
 
Urban housing scenario and rental housing in india
Urban housing scenario and rental housing in indiaUrban housing scenario and rental housing in india
Urban housing scenario and rental housing in india
 
Role of transportation in urban development
Role of transportation in urban developmentRole of transportation in urban development
Role of transportation in urban development
 
Delhi Mumbai Industrial Corridor
Delhi Mumbai Industrial CorridorDelhi Mumbai Industrial Corridor
Delhi Mumbai Industrial Corridor
 
Perspective plan
Perspective planPerspective plan
Perspective plan
 
Housing Policies- Lalit kumar
Housing Policies- Lalit kumarHousing Policies- Lalit kumar
Housing Policies- Lalit kumar
 
Road Development and Maintenance of Rural Areas
Road Development and Maintenance of Rural AreasRoad Development and Maintenance of Rural Areas
Road Development and Maintenance of Rural Areas
 
Eco City Development towards Developing Low Carbon Society
Eco City Development towards Developing Low Carbon SocietyEco City Development towards Developing Low Carbon Society
Eco City Development towards Developing Low Carbon Society
 
Sustainable Transportation
Sustainable TransportationSustainable Transportation
Sustainable Transportation
 
Transportation problem with relevance to indian cities
Transportation problem with relevance to indian citiesTransportation problem with relevance to indian cities
Transportation problem with relevance to indian cities
 
Government of India Ministry of Road Transport & Highways
Government of India Ministry of Road Transport & HighwaysGovernment of India Ministry of Road Transport & Highways
Government of India Ministry of Road Transport & Highways
 
Project finance ppt final
Project finance ppt finalProject finance ppt final
Project finance ppt final
 
Mumbai metro project Phase I
Mumbai metro project Phase IMumbai metro project Phase I
Mumbai metro project Phase I
 
NON-MOTORIZED TRANSPORT - UTTIPEC
NON-MOTORIZED TRANSPORT - UTTIPECNON-MOTORIZED TRANSPORT - UTTIPEC
NON-MOTORIZED TRANSPORT - UTTIPEC
 
Intermediate public transport (ipt)
Intermediate public transport (ipt)Intermediate public transport (ipt)
Intermediate public transport (ipt)
 
HRIDAY Scheme.pptx
HRIDAY Scheme.pptxHRIDAY Scheme.pptx
HRIDAY Scheme.pptx
 
Case study of feasibility study of mrts
Case study of feasibility study of mrtsCase study of feasibility study of mrts
Case study of feasibility study of mrts
 
Intersection designs ppt
Intersection designs pptIntersection designs ppt
Intersection designs ppt
 

Similar to Case Study on - Vadodara halol Toll road

Ravi sharma put20278 transport policies and acts
Ravi sharma put20278 transport policies and actsRavi sharma put20278 transport policies and acts
Ravi sharma put20278 transport policies and actsRavi Sharma
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnershipAnkit GAJJAR
 
Funding Recommendations for Oregon’s Public Roads Network
Funding Recommendations for Oregon’s Public Roads NetworkFunding Recommendations for Oregon’s Public Roads Network
Funding Recommendations for Oregon’s Public Roads NetworkChilin Xiao
 
Road Funding in South Africa
Road Funding in South AfricaRoad Funding in South Africa
Road Funding in South AfricaTristan Wiggill
 
Business Fleet Africa March 2023.pdf
Business Fleet Africa March 2023.pdfBusiness Fleet Africa March 2023.pdf
Business Fleet Africa March 2023.pdfTristan Wiggill
 
Analysis of Sources of Finances for Indian Railways and Futureroadmap
Analysis of Sources of Finances for Indian Railways and FutureroadmapAnalysis of Sources of Finances for Indian Railways and Futureroadmap
Analysis of Sources of Finances for Indian Railways and FutureroadmapSudiksha Joshi
 
Public private partnership in development of road network
Public private partnership in development of road networkPublic private partnership in development of road network
Public private partnership in development of road networkGokul K Prasad
 
Pakistan budget summary 2015 by IRCOCA
Pakistan budget summary 2015 by IRCOCAPakistan budget summary 2015 by IRCOCA
Pakistan budget summary 2015 by IRCOCAAziza Faryal
 
GCC Capital Expenditure Expected to Rise in 2013
GCC Capital Expenditure Expected to Rise in 2013GCC Capital Expenditure Expected to Rise in 2013
GCC Capital Expenditure Expected to Rise in 2013QNB Group
 
Doing Business In The Middle East
Doing Business In The Middle EastDoing Business In The Middle East
Doing Business In The Middle EastJeremiah Josey
 
· From the case studies, Case 1.1 and Case 5.1, explain two of t.docx
· From the case studies, Case 1.1 and Case 5.1, explain two of t.docx· From the case studies, Case 1.1 and Case 5.1, explain two of t.docx
· From the case studies, Case 1.1 and Case 5.1, explain two of t.docxoswald1horne84988
 
union budget 2012-13(energy sector)
union budget 2012-13(energy sector)union budget 2012-13(energy sector)
union budget 2012-13(energy sector)millgaydil
 

Similar to Case Study on - Vadodara halol Toll road (20)

Infra on Roads
Infra on RoadsInfra on Roads
Infra on Roads
 
Union budget fy12
Union budget fy12Union budget fy12
Union budget fy12
 
Toll ppt
Toll pptToll ppt
Toll ppt
 
Ravi sharma put20278 transport policies and acts
Ravi sharma put20278 transport policies and actsRavi sharma put20278 transport policies and acts
Ravi sharma put20278 transport policies and acts
 
Public private partnership
Public private partnershipPublic private partnership
Public private partnership
 
HIGHWAYS
HIGHWAYS HIGHWAYS
HIGHWAYS
 
Funding Recommendations for Oregon’s Public Roads Network
Funding Recommendations for Oregon’s Public Roads NetworkFunding Recommendations for Oregon’s Public Roads Network
Funding Recommendations for Oregon’s Public Roads Network
 
Budget 2015
Budget 2015Budget 2015
Budget 2015
 
Road Funding in South Africa
Road Funding in South AfricaRoad Funding in South Africa
Road Funding in South Africa
 
Business Fleet Africa March 2023.pdf
Business Fleet Africa March 2023.pdfBusiness Fleet Africa March 2023.pdf
Business Fleet Africa March 2023.pdf
 
Union Budget 2012 - 13 Review
Union Budget 2012 - 13 ReviewUnion Budget 2012 - 13 Review
Union Budget 2012 - 13 Review
 
Analysis of Sources of Finances for Indian Railways and Futureroadmap
Analysis of Sources of Finances for Indian Railways and FutureroadmapAnalysis of Sources of Finances for Indian Railways and Futureroadmap
Analysis of Sources of Finances for Indian Railways and Futureroadmap
 
Public private partnership in development of road network
Public private partnership in development of road networkPublic private partnership in development of road network
Public private partnership in development of road network
 
illuminati
illuminatiilluminati
illuminati
 
Pakistan budget summary 2015 by IRCOCA
Pakistan budget summary 2015 by IRCOCAPakistan budget summary 2015 by IRCOCA
Pakistan budget summary 2015 by IRCOCA
 
Liftng, Cost Recovery and Performance of Oil & Gas Non-Tax-Revenue
Liftng, Cost Recovery and Performance of Oil & Gas Non-Tax-RevenueLiftng, Cost Recovery and Performance of Oil & Gas Non-Tax-Revenue
Liftng, Cost Recovery and Performance of Oil & Gas Non-Tax-Revenue
 
GCC Capital Expenditure Expected to Rise in 2013
GCC Capital Expenditure Expected to Rise in 2013GCC Capital Expenditure Expected to Rise in 2013
GCC Capital Expenditure Expected to Rise in 2013
 
Doing Business In The Middle East
Doing Business In The Middle EastDoing Business In The Middle East
Doing Business In The Middle East
 
· From the case studies, Case 1.1 and Case 5.1, explain two of t.docx
· From the case studies, Case 1.1 and Case 5.1, explain two of t.docx· From the case studies, Case 1.1 and Case 5.1, explain two of t.docx
· From the case studies, Case 1.1 and Case 5.1, explain two of t.docx
 
union budget 2012-13(energy sector)
union budget 2012-13(energy sector)union budget 2012-13(energy sector)
union budget 2012-13(energy sector)
 

Recently uploaded

MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docxPoojaSen20
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introductionMaksud Ahmed
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTiammrhaywood
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityGeoBlogs
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionSafetyChain Software
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfsanyamsingh5019
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfakmcokerachita
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Sapana Sha
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxSayali Powar
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...EduSkills OECD
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppCeline George
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application ) Sakshi Ghasle
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptxVS Mahajan Coaching Centre
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfUmakantAnnand
 

Recently uploaded (20)

MENTAL STATUS EXAMINATION format.docx
MENTAL     STATUS EXAMINATION format.docxMENTAL     STATUS EXAMINATION format.docx
MENTAL STATUS EXAMINATION format.docx
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
microwave assisted reaction. General introduction
microwave assisted reaction. General introductionmicrowave assisted reaction. General introduction
microwave assisted reaction. General introduction
 
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPTECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
ECONOMIC CONTEXT - LONG FORM TV DRAMA - PPT
 
Paris 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activityParis 2024 Olympic Geographies - an activity
Paris 2024 Olympic Geographies - an activity
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Mastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory InspectionMastering the Unannounced Regulatory Inspection
Mastering the Unannounced Regulatory Inspection
 
Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
Sanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdfSanyam Choudhary Chemistry practical.pdf
Sanyam Choudhary Chemistry practical.pdf
 
Class 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdfClass 11 Legal Studies Ch-1 Concept of State .pdf
Class 11 Legal Studies Ch-1 Concept of State .pdf
 
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111Call Girls in Dwarka Mor Delhi Contact Us 9654467111
Call Girls in Dwarka Mor Delhi Contact Us 9654467111
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptxPOINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
POINT- BIOCHEMISTRY SEM 2 ENZYMES UNIT 5.pptx
 
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
Presentation by Andreas Schleicher Tackling the School Absenteeism Crisis 30 ...
 
URLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website AppURLs and Routing in the Odoo 17 Website App
URLs and Routing in the Odoo 17 Website App
 
Hybridoma Technology ( Production , Purification , and Application )
Hybridoma Technology  ( Production , Purification , and Application  ) Hybridoma Technology  ( Production , Purification , and Application  )
Hybridoma Technology ( Production , Purification , and Application )
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions  for the students and aspirants of Chemistry12th.pptxOrganic Name Reactions  for the students and aspirants of Chemistry12th.pptx
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
 
Concept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.CompdfConcept of Vouching. B.Com(Hons) /B.Compdf
Concept of Vouching. B.Com(Hons) /B.Compdf
 

Case Study on - Vadodara halol Toll road

  • 1. VADODARA HALOL TOLL ROAD SUBMITTED BY : SOURABH MOREY AH19155 NEERAJ NAMDEV AH19158 DEEPAM PATIDAR AH19169 RAHUL VISHWAKARMA AH19188 RAJAT RAGUWANSHI AH19192
  • 2. INTRODUCTION • The Vadodara Halol Toll Road (VHTR) was one of the first State Highway widening projects developed on a Public Private Partnership. • Vadodara Halol Toll Road was operated and maintained by VHTRL, a special purpose vehicle, promoted by (Government of Gujarat) GoG and (Infrastructure leasing and finiacial service) ILF&S. • The VHTR project is developed under the Built, Own, Operate and Transfer (BOOT) basis. • Consortium of Punj Lloyd Limited and IRCON International Limited as contractors. • The actual revenues as a proportion of the projected revenues had fallen from 63% to 34% during the three years of operation. • TRC (Toll revenue committee ) has options of increasing rates for MAV or increasing rates for all vehicles or increasing rates for (Multi-axle vehicle ) MAV and restructuring finance. • Each option has been evaluated in terms of impact on traffic and revenue and the cost incurred. • On the basis of this evaluation, it is recommended that VHTRL should increase rates for MAV and restructure its financing.
  • 3. SITUATIONALANALYSIS • VHTRL was jointly promoted by GoG and IL&FS for developing and implementing Vadodara Halol Road Project. • Vadodara-Halol Road had gained importance because of growing industrialization in Halol. • The project attained completion on Sep 15, 2000 and the commercial operations began on Oct 24, 2000. • VHTRL manages, operates and maintains the road for 30 years starting from 2000. • The actual revenue has been less than the expected revenue and an appropriate action has to be taken. • The actual revenue has been less than the expected revenue and an appropriate action has to be taken. According to the projected cash flows, VHTRL may have to shut down their operations by mid 2003 owing to the losses they would suffer. • The total debt carried is Rs 1058.3 million with the average cost of borrowing as 15.52%. • The dilemma faced by Toll Review Committee is how to increase the revenue and reduce the cost so as to make the project sustainable. During the two rounds of TRC meeting, the company collected additional information and these inputs were further examined. • VHTRL is currently undercharging the MAVs and hence revision of rates may be needed (Refering Exhibit – 4,5,6) • Exhibit 7 and 8 explains how the financing structure of the project can be improved to reduce the borrowing cost of the project.
  • 4. PROBLEM STATEMENT • VHTRL needs to increase revenue and/or reduce cost to sustain the project. Option 1. Increase rates for MAV 2.Increase rates for All Vehicles 3.Increase rates for MAV and Financial Restructuring 1. Increase rates for MAV:  Impact on Traffic and Revenue • It is suggested to increase average rates for MAV to Rs 4.8205 per km. Exhibit 4 shows the average rates for MAV at different toll roads in the country. From Exhibit 5, the current average rate for MAV in Vadodara-Halol Toll Road is Rs 2.9/km, which is lesser than the average toll rates charged in the country. • To achieve the average rate of Rs 4.8205 per km, the revised toll rates for MAVs are mentioned in the Exhibit 6. • So most of the MAVs are travelling long distance, there could be a possibility that the MAVs would use the alternative path NH8 after the price increase. • Assuming Diesel Rate of Rs. 18/litre (2002 price) and the average fuel efficiency of MAVs at 15kms/litre, the average fuel savings of an MAV for travelling 50 kilometres lesser is Rs 60. • The effective savings would be more since travelling through Vadodara-Halol road and bypassing Ahmedabad would save time and the vehicle doesn’t have to go through the crowded city. • The total savings on offer are more than the increase in toll rates. It is thus, safe to assume that the total traffic of MAVs will not reduce after the toll rates are increased. • The total revenue would increase by 11.33%. Hence, the projected cash flow of 2003-04 would increase from Rs. 90 millions to Rs. 100.2 millions.
  • 5.  Impact on Cost Incurred • The rate increase would lead to an increased cash flow of around Rs 10 million per year. • But the total inflow of Rs. 113.11 million is still substantially behind the 7.6 projected total outflow of Rs 250 million per year (projected for 2003-04). • Hence, this change alone will not help us in sustaining the business over time. 2. Increase rates for All Vehicles:  Impact on Traffic and Revenue • The smaller vehicles (2 wheelers, 3 wheelers, Car, etc) are much more price sensitive and increasing the rates for the smaller vehicles would make them use the service road more often. • On one hand, increasing the rates would increase the revenue, but on the other hand, the number of vehicles travelling would reduce leading to reduction in total revenue. • Hence, the total revenue from the smaller vehicles would nearly remain the same. • Increasing the toll rates for the MAV would increase the revenue as discussed above. This option is not recommended because of uncertainty of revenue involved in this case.  Impact on Cost Incurred • The cost incurred would still be considerably higher than the inflows, i.e., cost incurred as per the projected cash flows is Rs 255.45 million as compared to inflows of Rs 130.86 million.
  • 6. 3. Increase rates for MAVs and Financial Restructuring:  Impact on Traffic and Revenue • As discussed in Option 1, there will be an increase in the total revenue when the toll rates for MAVs are increased. It is also critical to reduce the cost of borrowing of the project as increasing the revenue alone isn’t enough for sustaining the project. • Also, selling hoarding rights would add to the revenue.  Impact on Cost Incurred • The current financing structure of the project involves Debt/Equity Ratio of 1.924 and average cost of debt if 15.52% (Exhibit 3 - table 3,4) • The total interest charges incurred by the project forms the majority part of the total outflows of the project. • It is of great importance to restructure the financing aspect of the project to reduce the debt burden. It should attract private equity to reduce the debt burden. • Also, refinancing the debt would help in reducing the average cost of borrowing. A considerable amount of early debt has been picked up at more than 15% rate of interest, e.g, ILF&S has 16% rate of interest. It is recommended to restructure Debt/Equity ratio to 1:1 and refinance the debt which has high rate of interest. • Exhibit 7 shows the current projected interest burden and Exhibit 8 shows the projected interest burden after the financing is restructured. • These changes will make the project profitable. • RECOMMENDATION - VHRTC would be benefitted if they increase the toll rates for MAVs and restructure financing. This would help them improve their financial situation and sustain the project.
  • 7. Action Plan • Issue appropriate notifications regarding revision of toll rates. • Approach private equity investors to attract private investment to the project. • Negotiate with lenders to refinance the existing debt. • Float RFP (REQUEST FOR PROPASAL ) for hoarding rights. EXHIBIT 1. Abbreviation VHTRL – Vododara Halol Toll Road Company Limited GoG- Government of Gujarat IL&FS – Infrastructure leasing & Financial Services TRC – Toll Review Committee MAV – Multi Axle vechile REP – Request for proposal
  • 8.
  • 9. Exhibit 3: Current Financing of the project
  • 10. Exhibit 4: Toll Rates for MAVs of other Projects
  • 11. Exhibit 5: Determine the ratios of Three-Axle, Four-Axle and Five-Axle vehicles Percentage of revenue which comes from these vehicles is as follows (Exhibit 3, table 5 – toll structure): Three-Axle: 71.2% Four-Axle: 21.5% Five-Axle: 7.3% Present Toll Rates (Rs): (table 7 ) Three-Axle: 85 Four-Axle: 105 Five-Axle: 125 If we solve using the above information, we get the average ratio of the MAVs as: Three-Axle : Four-Axle : Three-Axle :: 24 : 6 : 1 E.g. For every Three-Axle MAV, we have 6 numbers of Four Axle MAV and 24 numbers of Three-Axle Total – 24+6 +1 = 31