Interface Management
A Systemic Approach for Major Projects
David Tain, MSc. P.Eng., PMP
©Septentrion Strategic Solutions Ltd.
Table of Contents
Uncertainties
©Septentrion Strategic Solutions Ltd.
Defining Interfaces
Interfaces and Systems
Understanding Interfaces
Elements to Consider when Managing Project Interfaces
Interface Management Processes using the PMI framework
Case Study: Oil Sands Megaproject in Alberta
 Final Considerations - Key Takeaways
Interface - Definitions
Uncertainties
©Septentrion Strategic Solutions Ltd.
Interface: A boundary point where an interdependence
exists and a transfer of responsibility occurs
Interface
Interface
Interface
Interface Interface
Interfaces and Systems
Uncertainties
©Septentrion Strategic Solutions Ltd.
Modern Project Interface Management originates from the
influence of systems thinking in project management:
• System: Assemblage of elements (people , things, information,
etc.) grouped together to achieve a particular system objective
• Systems are logically broken down in sub-systems
• Sub-systems are formed by subsets
A project is formed 3 subsystems:
1. Project Lifecycle
2. Management Levels
3. Operational Framework
Subsystem 1: Project Lifecycle
Uncertainties
©Septentrion Strategic Solutions Ltd.
FEL-1 ExecutionFEL-3 Operations
Detailed
Engineering Construction CSU
FEL-2
Project Gates & Phases
CSU - Engagement and Interfaces in Time
Subsystem 2: Management Levels
Uncertainties
©Septentrion Strategic Solutions Ltd.
The Project
Level II: Middle
Management
Level III: Technical
Management
Level I: Senior
Management
The Business Environment
Coordinates project
technical core and buffers it
from the outside world
Provide Strategy and deal
with business environment
Responsible for the
technical content of the
project
Competitors
Government
Suppliers
Community
groups
Media
Regulator
Agencies
Economic
Climate
Subsystem 3: Project Operational Framework
Uncertainties
©Septentrion Strategic Solutions Ltd.
At the outside of the project:
• Project definition
• Operations and Maintenance
• Sales / Marketing
• Relationships with outside groups
• Ensuring adequate manpower and resources
• Ensuring adequate flow of fund
At the inside of the project:
• Realizing the desired project definition (adequate scope and budget,
quality parameters, etc.)
• Creating the project organization (organizational structure,
contractual relationships, information management, control
procedures, etc)
• Mitigating external disruptions from the environment (e.g.: timely
acquisition of material, handling relationships with unions, obtaining
regulatory approvals, informing management of financial needs)
• Logistics (e.g.: project facilities, transportation, communications, etc)
Understanding Interfaces – Traditional Approach
Uncertainties
©Septentrion Strategic Solutions Ltd.
Time Direction
Some Traditional Classifications of Interfaces:
 Analyze project / organizations based on their configuration
• Internal / external
• Organizational, contractual and physical (focus on construction projects)
• Human / Technical
• Tangible / Intangible – Hard / Soft
 Problems:
• Room for ambiguity promotes silo-based behaviors conflicts emerge
based on territoriality / positioning
• Difficulty in adapting to changes associated to:
&
Understanding Interfaces – Contingency Theory Approach
Uncertainties
©Septentrion Strategic Solutions Ltd.
Contingency School of Organization
(Organizational Theory + Project Management)
Considers 1-the nature of interrelationships in the project and 2- time:
Pooled Sequential Reciprocal
Classification
Static Interfaces
Dynamic Interfaces
Group
Understanding Interfaces – Static Interfaces
Uncertainties
©Septentrion Strategic Solutions Ltd.
Static Interface: Relationship between permanent subgroups  basic project
structure
 A project relies on at least 3 subgroups:
Pooled Interdependence  Resources are shared / Matrix Organization
Project
Direction
Project
Management
Functional
Management
Planning and
Control
Area 1 Area 2 Area 3 Engineering SCM CM Estimation Cost control Scheduling ReportingHSE
Coordination Mechanisms: Policies, plans, procedures
Etc.
Understanding Interfaces – Dynamic Interfaces
Uncertainties
©Septentrion Strategic Solutions Ltd.
Dynamic Interface: Relationship depends on how the project develops
It considers two elements:
 project lifecycle
 the pattern of activity interdependence
Sequential Interdependence  Stakeholders follow
each other
Example of coordination mechanisms: Schedule
Reciprocal Interdependence  Stakeholders must continuously interact
 Cyclical nature – units performance is mutually dependent
 Require lots of horizontal coordination
 Rely on personal contact
 Example: SCM & Engineering:
 SCM depends on engineering to understand what to buy.
 Engineering depends on SCM to continue the design based on the market availability
Understanding Interfaces – Dynamic Interfaces (Cont.)
Uncertainties
©Septentrion Strategic Solutions Ltd.
Group Interdependence  Results and knowledge are built
upon progressive interactions of the stakeholders
• convergent in nature
• Relies on Personal contact
Example of coordination mechanisms: Scheduled and
unscheduled group Meetings
Pooled + Sequential + Reciprocal
FEL-1 ExecutionFEL-3 Operations
Detailed
Engineering Construction CSU
FEL-2
Pooled + Sequential +
Reciprocal + Group
Predominant Interrelations during Development and Execution
Why is it essential to identify and control project interfaces?
Uncertainties
©Septentrion Strategic Solutions Ltd.
E=3
Imax = 3
E=5
Imax = 10
E=10
Imax = 45
E=20
Imax = 190
Imax =
𝑬 ∗(𝑬−𝟏)
𝟐
Project Complexity = f (interacting parts, uncertainty)
 Project complexity increases with amount of interfaces!!!
Possible amount of Interactions (Imax) as a function of Project Elements (E):
Why is it essential to identify and control project interfaces?
Uncertainties
©Septentrion Strategic Solutions Ltd.
Elements to Consider when Managing Project Interfaces
Uncertainties
©Septentrion Strategic Solutions Ltd.
Keep static interfaces clearly defined
 Define and agree all static subsystems (technical definition, organization, project infrastructure, etc.)
Dynamic interfaces are the most important ones  the clock is ticking!!!
 Early subsystems have a managerial dominance over subsequent ones (E.g. Design over Construction)
 Errors in early subsystems have a snowball effect in the subsequent ones
Level of control will vary depending on the stage of the project
 Personnel issues (conflicts, leadership, etc) will evolve and need to be moderated considering project
phase
Planning must be incremental
 Building bases for the next phase
 Details added as project advances
Major changes require their own distinctive Total Management
 Changing project phases is a major event and needs to be treated as such!
Remember:
The Main Challenge in Interface
Management is Human Interactions
Interface Management Processes using the PMI framework
Uncertainties
©Septentrion Strategic Solutions Ltd.
Interface management must follow a lifecycle approach, with well
defined processes
Initiating /
Identification
Planning Execution Closing
Monitoring & Control
Interface Initiation
Uncertainties
©Septentrion Strategic Solutions Ltd.
Objective: Interfaces are identified and interface management overall
strategy is defined based on the characteristics of the project
 Appointment of the Interface Manager & Interface Coordinators
 Establishment of an official definition of interface in the project
 Interface identification based on Project Basic documents (Bulk identification)
• Project Work Breakdown Structure (WBS)
• Contracts
• Specifications
• Interviews
 Quantify interfaces & preliminary identify risks
• Creation of the Interface Responsibility Matrix (IRM)
 Draft Interface Management Plan  identification and coordination of static and
dynamic interfaces
Interface Planning
Uncertainties
©Septentrion Strategic Solutions Ltd.
Objective: Refine interfaces information, allocate to corresponding parties
and determine communication protocols
• Refinement of the Interface Responsibility Matrix (as design is more
advanced)  eliminate unnecessary interfaces / identify new ones
• Allocation of interfaces into work packages
• Incorporation of interfaces in the project schedule (first pass)
• Integrate to schedule logic  future interface agreements
• Finalization of the Interface Management Plan, including:
• Define project interfaces & Interface lifecycle
• Define Interface Management organization
• Identify / define documents to capture interfaces in all ambits (e.g.:
communications plan, RACI matrix, BLTs, etc.)
• Define Conflict resolution process
• Define Monitoring & control strategy (tools, frequency, details, etc)
Warning!!
***Interface management plan should be part of contractual
documents***
Interface Execution
Uncertainties
©Septentrion Strategic Solutions Ltd.
Objective: Formal transfer of the interface to the appropriate parties
and drive them to closure
• Creation of formal Interface Documents
• Obtain full commitment from interfaced parties
• Align interfaces with a specific project activities / integrate them to the
schedule
Example: Interrelation Supplier S1 & constr. Contractor 1
(project Execution phase)
Interface Execution (Cont.)
Uncertainties
©Septentrion Strategic Solutions Ltd.
Interface Closure
Uncertainties
©Septentrion Strategic Solutions Ltd.
Objective: satisfy all requirements of the interface as indicated in the
Interface document.
 Information provided on time and in the format agreed
 Interface document closed  interface ceases to exist
 Subsequent activities continue
Interfaces Monitoring and Control
Uncertainties
©Septentrion Strategic Solutions Ltd.
Objective: Ensure a continuous visibility of the interface / enhance its
timely resolution
Monitoring starts as soon as an interface is identified
• The monitoring and control strategy will depend on the size and
complexity of the project
• Interface register
 Leading indicators (e.g.: look ahead) combined with lagging indicators
(performance of the interfaces)
Warning: In large projects, specialized software may be necessary to
integrate and optimize interfaces. It is very difficult to rely on
conventional tools (e.g.: MS Excel, Access, etc.):
• Interfaces can be significant (e.g. a $10B project can easily have over
5,000 interfaces)
• High potential for changes as project advances  scope reallocations,
planning adjustments, start-up strategies, etc.
Interface Monitoring & Control
Uncertainties
©Septentrion Strategic Solutions Ltd.
Example of Interface Management Monitoring & Controlling Strategy in
a large project
Report Generation
Project Schedule
Dynamic IA Reporting
(look-ahead)
Overdue
Overdue in
Less than x
days
Overdue in
> x days
Closed
IA generation Tool
Case Study: Oil Sands Mega Project
Uncertainties
©Septentrion Strategic Solutions Ltd.
Project: 120,000 bbld Production Facility
Location: Northern Alberta
• 3 Main EPC Contractors
• 6 Fabrication and Construction Contractors
• Engineering and Module Fabrication in
multiple locations within in 3 continents
Initial Estimate (end of FEL3): $4B (2008)
Interim Estimate (30% Construction): ~$7B (2012)
TIC: over $12B (2015)
What Happened??
Case Study: Oil Sands Mega Project (Cont.)
Uncertainties
©Septentrion Strategic Solutions Ltd.
The Promise: An Innovative & Efficient Interface
Management System
Interface Management Team was assembled during FEL-3
o Interface Manager
o Interface Coordinators allocated to different project areas
Module of Planning Software adapted to manage interfaces:
o Friendly user interface for Interface Agreement creation
o Easy integration of IAs with the schedule
Interface management team identified all interfaces prior detailed
engineering design phase
o Interface Responsibility Matrix
o Interface Coordinators estimated and created initial Interface
Agreements
Interface Management Plan created and approved the end of FEL-3
Case Study: Oil Sands Mega Project (Cont.)
Uncertainties
©Septentrion Strategic Solutions Ltd.
The Reality:
Interface Management strategy and plan not fully included in contract
documents
 IM process was rolled-out to contractors after contract award
Insufficient contractual provisions for IM in sub-contractors and consultants
(logistics, support, personnel)
Contractors added change orders with additional fees associated to risks management
Different attitudes / reactions towards IM (especially LS contactors)
Weak Governance
IM function managed by Engineering Consultant involved in the design with
“oversight” support from client  Conflict of Interests
Interfaces negotiated by client in silos  contracts awarded in different times
Problems in enforcing IAs  Engineering Consultant managing Interfaces did not
have any contractual leverage over other consultant or construction companies
Case Study: Oil Sands Mega Project (Cont.)
Uncertainties
©Septentrion Strategic Solutions Ltd.
The Reality:
Issues with the IM Management Tool
The modified tool was a prototype
Module is originally designed for Contract Management, not capable to
manage with multiple interrelations
Poor support from software provider / insufficient IT Scope definition
Reports had to be manually generated by 1 super user (bottleneck) relying
on Excel tools (Macros)
Interface Coordinators (Project Engineers with no experience in facilitation/
courses delivery) became trainers for contractors designated personnel
Neglected management of Dynamic Interfaces
 Only Engineering and Construction interfaces were visible to the IM Team
No jurisdiction of IM team over client internal processes
Interfaces with external stakeholders poorly managed:
Multiple issues with regulators and Government
Key fabrication & transportation strategy had to be modified
Case Study: Oil Sands Mega Project (Cont.)
Uncertainties
©Septentrion Strategic Solutions Ltd.
The Reality:
Deficient project integration
Different contract architectures  different performance and progress metrics
IAs were never linked to the schedule
Project has multiple schedules from each consultant / contractor
Integrated schedule never produced
Deficient Conflict Management Strategy
High turnover in IM team due to conflicts with client and sub-contractors
Conflict Management process was designed and implemented late in the project
IM function removed from engineering consultant and transferred to competitor
in the project
Organizational Deficiencies
IM seen with different levels of importance in the project  “Power struggles”
Inadequate legitimization: IM seen as an “interference” in the Project
The devil is in the details
Final Considerations – Key takeaways
Uncertainties
©Septentrion Strategic Solutions Ltd.
Early identification is critical for the success of an interface
Traditional approaches based on project configuration are insufficient to identify and
manage interfaces
Identify and understand interdependences: Clearly define static interfaces & Manage
Dynamic Interfaces
Each interface needs to be managed by tangible mechanisms
Interface management strategy needs to be adapted to the size and complexity of the
project
Large projects require specific interface Management Strategies
Do not neglect a lifecycle approach to manage interfaces  Select a framework and adapt
it to the characteristics of your project!!
Implement a clear governance for interface Management across the project and the
organization
And always Remember:
Interfaces
Thank You!
Uncertainties
©Septentrion Strategic Solutions Ltd.
For more information about strategies to unlock value in your organization or projects,
visit us at:
www.septentrioncanada.com
©Septentrion Strategic Solutions Ltd.
Septentrion Management Capsules ®
Ideas to unlock value and enhance competitiveness in your organization

More Related Content

What's hot

Download⚡PDF❤ Project Management Metrics KPIs and Dashboards A Guide to Mea...
Download⚡PDF❤ Project Management Metrics  KPIs  and Dashboards A Guide to Mea...Download⚡PDF❤ Project Management Metrics  KPIs  and Dashboards A Guide to Mea...
Download⚡PDF❤ Project Management Metrics KPIs and Dashboards A Guide to Mea...moerbouthererrt
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementMohamed Loey
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsThink For A Change
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management OverviewDavidMcLachlan1
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full courseMarten Schoonman
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management FundamentalsOxfordCambridge
 
Project time management
Project time managementProject time management
Project time managementJivan Nepali
 
Oil and Gas Project Management Training Solutions
Oil and Gas Project Management Training SolutionsOil and Gas Project Management Training Solutions
Oil and Gas Project Management Training SolutionsESI14
 
Worley Parsons Overview Sept 09
Worley Parsons Overview Sept 09Worley Parsons Overview Sept 09
Worley Parsons Overview Sept 09rosalyndru
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technipignitetribes
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baronignitetribes
 
Civil Construction Project Management Powerpoint Presentation Slides
Civil Construction Project Management Powerpoint Presentation SlidesCivil Construction Project Management Powerpoint Presentation Slides
Civil Construction Project Management Powerpoint Presentation SlidesSlideTeam
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project managementMohamed Amin
 

What's hot (20)

Download⚡PDF❤ Project Management Metrics KPIs and Dashboards A Guide to Mea...
Download⚡PDF❤ Project Management Metrics  KPIs  and Dashboards A Guide to Mea...Download⚡PDF❤ Project Management Metrics  KPIs  and Dashboards A Guide to Mea...
Download⚡PDF❤ Project Management Metrics KPIs and Dashboards A Guide to Mea...
 
Project Execution
Project ExecutionProject Execution
Project Execution
 
PMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project ManagementPMP Lecture 1: Introduction to Project Management
PMP Lecture 1: Introduction to Project Management
 
Scope of work
Scope of workScope of work
Scope of work
 
project management
project managementproject management
project management
 
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
Project Controls Expo 13th Nov 2013 - "From Cost Plan To Bid Evaluation To Co...
 
Statement of-work
Statement of-workStatement of-work
Statement of-work
 
Epc presentation robert foxpresentation
Epc presentation robert foxpresentationEpc presentation robert foxpresentation
Epc presentation robert foxpresentation
 
Project Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management ConceptsProject Management Foundations Course 101 - Project Management Concepts
Project Management Foundations Course 101 - Project Management Concepts
 
8.0 Project Quality Management Overview
8.0 Project Quality Management Overview8.0 Project Quality Management Overview
8.0 Project Quality Management Overview
 
Practical Project Management - full course
Practical Project Management - full coursePractical Project Management - full course
Practical Project Management - full course
 
Project Management Fundamentals
Project Management FundamentalsProject Management Fundamentals
Project Management Fundamentals
 
Project time management
Project time managementProject time management
Project time management
 
Oil and Gas Project Management Training Solutions
Oil and Gas Project Management Training SolutionsOil and Gas Project Management Training Solutions
Oil and Gas Project Management Training Solutions
 
Worley Parsons Overview Sept 09
Worley Parsons Overview Sept 09Worley Parsons Overview Sept 09
Worley Parsons Overview Sept 09
 
Process Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by TechnipProcess Related, Mechanical and Piping Workshop by Technip
Process Related, Mechanical and Piping Workshop by Technip
 
Project Control Practical Way by Herve Baron
Project Control Practical Way by Herve BaronProject Control Practical Way by Herve Baron
Project Control Practical Way by Herve Baron
 
Project Resource Management
Project Resource ManagementProject Resource Management
Project Resource Management
 
Civil Construction Project Management Powerpoint Presentation Slides
Civil Construction Project Management Powerpoint Presentation SlidesCivil Construction Project Management Powerpoint Presentation Slides
Civil Construction Project Management Powerpoint Presentation Slides
 
Fundamentals of project management
Fundamentals of project managementFundamentals of project management
Fundamentals of project management
 

Similar to Interface Management: A Systemic Approach for Projects and Organizations

Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project ManagementMostafa Ewees
 
About this research note Technology Insight notes descr.docx
About this research note Technology Insight notes descr.docxAbout this research note Technology Insight notes descr.docx
About this research note Technology Insight notes descr.docxransayo
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project ManagementUW Madison
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1Aconex
 
Chap3 2007 Cisa Review Course
Chap3 2007 Cisa Review CourseChap3 2007 Cisa Review Course
Chap3 2007 Cisa Review CourseDesmond Devendran
 
1.1 introduction to real estate project management
1.1 introduction to real estate project management1.1 introduction to real estate project management
1.1 introduction to real estate project managementIrefuser1
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time ManagementSabrinaScott22
 
Communications Management PlanProject NameTable of Contents.docx
Communications Management PlanProject NameTable of Contents.docxCommunications Management PlanProject NameTable of Contents.docx
Communications Management PlanProject NameTable of Contents.docxclarebernice
 
PM-1 Overview.ppt
PM-1 Overview.pptPM-1 Overview.ppt
PM-1 Overview.pptnatisil1
 
(Fall2016)Lecture2.pptx
(Fall2016)Lecture2.pptx(Fall2016)Lecture2.pptx
(Fall2016)Lecture2.pptxgarkapifye
 
Research Paper On Primavera
Research Paper On PrimaveraResearch Paper On Primavera
Research Paper On PrimaveraGina Buck
 
Project management - Indian Business Academy
Project management - Indian Business AcademyProject management - Indian Business Academy
Project management - Indian Business AcademyGajjala vivekananda
 
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)Nurhazman Abdul Aziz
 
Module 3 - IDP.ppt
Module 3 - IDP.pptModule 3 - IDP.ppt
Module 3 - IDP.pptRAJESH S
 
Project Management
Project ManagementProject Management
Project Managementirfan ali
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfTanzeelShahid5
 

Similar to Interface Management: A Systemic Approach for Projects and Organizations (20)

Definition Of Project Management
Definition Of Project ManagementDefinition Of Project Management
Definition Of Project Management
 
About this research note Technology Insight notes descr.docx
About this research note Technology Insight notes descr.docxAbout this research note Technology Insight notes descr.docx
About this research note Technology Insight notes descr.docx
 
Introduction To Project Management
Introduction To Project ManagementIntroduction To Project Management
Introduction To Project Management
 
Mega project not mega problems session 1
Mega project not mega problems session 1Mega project not mega problems session 1
Mega project not mega problems session 1
 
Chap3 2007 Cisa Review Course
Chap3 2007 Cisa Review CourseChap3 2007 Cisa Review Course
Chap3 2007 Cisa Review Course
 
Project Management Introduction
Project Management IntroductionProject Management Introduction
Project Management Introduction
 
1.1 introduction to real estate project management
1.1 introduction to real estate project management1.1 introduction to real estate project management
1.1 introduction to real estate project management
 
Scope and Time Management
Scope and Time ManagementScope and Time Management
Scope and Time Management
 
Communications Management PlanProject NameTable of Contents.docx
Communications Management PlanProject NameTable of Contents.docxCommunications Management PlanProject NameTable of Contents.docx
Communications Management PlanProject NameTable of Contents.docx
 
PM-1 Overview.ppt
PM-1 Overview.pptPM-1 Overview.ppt
PM-1 Overview.ppt
 
(Fall2016)Lecture2.pptx
(Fall2016)Lecture2.pptx(Fall2016)Lecture2.pptx
(Fall2016)Lecture2.pptx
 
Lec 1 (2).pdf
Lec 1 (2).pdfLec 1 (2).pdf
Lec 1 (2).pdf
 
Research Paper On Primavera
Research Paper On PrimaveraResearch Paper On Primavera
Research Paper On Primavera
 
Pm Student Ho
Pm Student HoPm Student Ho
Pm Student Ho
 
Project management - Indian Business Academy
Project management - Indian Business AcademyProject management - Indian Business Academy
Project management - Indian Business Academy
 
Project Management Fundamentals Course
Project Management Fundamentals CourseProject Management Fundamentals Course
Project Management Fundamentals Course
 
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
Lessons From IT and Non-IT Projects (by Peter W. G. Morris)
 
Module 3 - IDP.ppt
Module 3 - IDP.pptModule 3 - IDP.ppt
Module 3 - IDP.ppt
 
Project Management
Project ManagementProject Management
Project Management
 
Lecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdfLecture 2 30-01-2020.pdf
Lecture 2 30-01-2020.pdf
 

Recently uploaded

Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingCIToolkit
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...AgileNetwork
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Reviewthomas851723
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sectorthomas851723
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineeringthomas851723
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentationmintusiprd
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Roomdivyansh0kumar0
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixCIToolkit
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Nehwal
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentationcraig524401
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insightWayne Abrahams
 

Recently uploaded (13)

sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Servicesauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
sauth delhi call girls in Defence Colony🔝 9953056974 🔝 escort Service
 
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes ThinkingSimplifying Complexity: How the Four-Field Matrix Reshapes Thinking
Simplifying Complexity: How the Four-Field Matrix Reshapes Thinking
 
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
ANIn Gurugram April 2024 |Can Agile and AI work together? by Pramodkumar Shri...
 
LPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations ReviewLPC Operations Review PowerPoint | Operations Review
LPC Operations Review PowerPoint | Operations Review
 
LPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business SectorLPC Warehouse Management System For Clients In The Business Sector
LPC Warehouse Management System For Clients In The Business Sector
 
Introduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-EngineeringIntroduction to LPC - Facility Design And Re-Engineering
Introduction to LPC - Facility Design And Re-Engineering
 
Fifteenth Finance Commission Presentation
Fifteenth Finance Commission PresentationFifteenth Finance Commission Presentation
Fifteenth Finance Commission Presentation
 
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With RoomVIP Kolkata Call Girl Rajarhat 👉 8250192130  Available With Room
VIP Kolkata Call Girl Rajarhat 👉 8250192130 Available With Room
 
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency MatrixUnlocking Productivity and Personal Growth through the Importance-Urgency Matrix
Unlocking Productivity and Personal Growth through the Importance-Urgency Matrix
 
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
Pooja Mehta 9167673311, Trusted Call Girls In NAVI MUMBAI Cash On Payment , V...
 
Board Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch PresentationBoard Diversity Initiaive Launch Presentation
Board Diversity Initiaive Launch Presentation
 
Reflecting, turning experience into insight
Reflecting, turning experience into insightReflecting, turning experience into insight
Reflecting, turning experience into insight
 
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICECall Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance  VVIP 🍎 SERVICE
Call Girls Service Tilak Nagar @9999965857 Delhi 🫦 No Advance VVIP 🍎 SERVICE
 

Interface Management: A Systemic Approach for Projects and Organizations

  • 1. Interface Management A Systemic Approach for Major Projects David Tain, MSc. P.Eng., PMP ©Septentrion Strategic Solutions Ltd.
  • 2. Table of Contents Uncertainties ©Septentrion Strategic Solutions Ltd. Defining Interfaces Interfaces and Systems Understanding Interfaces Elements to Consider when Managing Project Interfaces Interface Management Processes using the PMI framework Case Study: Oil Sands Megaproject in Alberta  Final Considerations - Key Takeaways
  • 3. Interface - Definitions Uncertainties ©Septentrion Strategic Solutions Ltd. Interface: A boundary point where an interdependence exists and a transfer of responsibility occurs Interface Interface Interface Interface Interface
  • 4. Interfaces and Systems Uncertainties ©Septentrion Strategic Solutions Ltd. Modern Project Interface Management originates from the influence of systems thinking in project management: • System: Assemblage of elements (people , things, information, etc.) grouped together to achieve a particular system objective • Systems are logically broken down in sub-systems • Sub-systems are formed by subsets A project is formed 3 subsystems: 1. Project Lifecycle 2. Management Levels 3. Operational Framework
  • 5. Subsystem 1: Project Lifecycle Uncertainties ©Septentrion Strategic Solutions Ltd. FEL-1 ExecutionFEL-3 Operations Detailed Engineering Construction CSU FEL-2 Project Gates & Phases CSU - Engagement and Interfaces in Time
  • 6. Subsystem 2: Management Levels Uncertainties ©Septentrion Strategic Solutions Ltd. The Project Level II: Middle Management Level III: Technical Management Level I: Senior Management The Business Environment Coordinates project technical core and buffers it from the outside world Provide Strategy and deal with business environment Responsible for the technical content of the project Competitors Government Suppliers Community groups Media Regulator Agencies Economic Climate
  • 7. Subsystem 3: Project Operational Framework Uncertainties ©Septentrion Strategic Solutions Ltd. At the outside of the project: • Project definition • Operations and Maintenance • Sales / Marketing • Relationships with outside groups • Ensuring adequate manpower and resources • Ensuring adequate flow of fund At the inside of the project: • Realizing the desired project definition (adequate scope and budget, quality parameters, etc.) • Creating the project organization (organizational structure, contractual relationships, information management, control procedures, etc) • Mitigating external disruptions from the environment (e.g.: timely acquisition of material, handling relationships with unions, obtaining regulatory approvals, informing management of financial needs) • Logistics (e.g.: project facilities, transportation, communications, etc)
  • 8. Understanding Interfaces – Traditional Approach Uncertainties ©Septentrion Strategic Solutions Ltd. Time Direction Some Traditional Classifications of Interfaces:  Analyze project / organizations based on their configuration • Internal / external • Organizational, contractual and physical (focus on construction projects) • Human / Technical • Tangible / Intangible – Hard / Soft  Problems: • Room for ambiguity promotes silo-based behaviors conflicts emerge based on territoriality / positioning • Difficulty in adapting to changes associated to: &
  • 9. Understanding Interfaces – Contingency Theory Approach Uncertainties ©Septentrion Strategic Solutions Ltd. Contingency School of Organization (Organizational Theory + Project Management) Considers 1-the nature of interrelationships in the project and 2- time: Pooled Sequential Reciprocal Classification Static Interfaces Dynamic Interfaces Group
  • 10. Understanding Interfaces – Static Interfaces Uncertainties ©Septentrion Strategic Solutions Ltd. Static Interface: Relationship between permanent subgroups  basic project structure  A project relies on at least 3 subgroups: Pooled Interdependence  Resources are shared / Matrix Organization Project Direction Project Management Functional Management Planning and Control Area 1 Area 2 Area 3 Engineering SCM CM Estimation Cost control Scheduling ReportingHSE Coordination Mechanisms: Policies, plans, procedures Etc.
  • 11. Understanding Interfaces – Dynamic Interfaces Uncertainties ©Septentrion Strategic Solutions Ltd. Dynamic Interface: Relationship depends on how the project develops It considers two elements:  project lifecycle  the pattern of activity interdependence Sequential Interdependence  Stakeholders follow each other Example of coordination mechanisms: Schedule Reciprocal Interdependence  Stakeholders must continuously interact  Cyclical nature – units performance is mutually dependent  Require lots of horizontal coordination  Rely on personal contact  Example: SCM & Engineering:  SCM depends on engineering to understand what to buy.  Engineering depends on SCM to continue the design based on the market availability
  • 12. Understanding Interfaces – Dynamic Interfaces (Cont.) Uncertainties ©Septentrion Strategic Solutions Ltd. Group Interdependence  Results and knowledge are built upon progressive interactions of the stakeholders • convergent in nature • Relies on Personal contact Example of coordination mechanisms: Scheduled and unscheduled group Meetings Pooled + Sequential + Reciprocal FEL-1 ExecutionFEL-3 Operations Detailed Engineering Construction CSU FEL-2 Pooled + Sequential + Reciprocal + Group Predominant Interrelations during Development and Execution
  • 13. Why is it essential to identify and control project interfaces? Uncertainties ©Septentrion Strategic Solutions Ltd. E=3 Imax = 3 E=5 Imax = 10 E=10 Imax = 45 E=20 Imax = 190 Imax = 𝑬 ∗(𝑬−𝟏) 𝟐 Project Complexity = f (interacting parts, uncertainty)  Project complexity increases with amount of interfaces!!! Possible amount of Interactions (Imax) as a function of Project Elements (E):
  • 14. Why is it essential to identify and control project interfaces? Uncertainties ©Septentrion Strategic Solutions Ltd.
  • 15. Elements to Consider when Managing Project Interfaces Uncertainties ©Septentrion Strategic Solutions Ltd. Keep static interfaces clearly defined  Define and agree all static subsystems (technical definition, organization, project infrastructure, etc.) Dynamic interfaces are the most important ones  the clock is ticking!!!  Early subsystems have a managerial dominance over subsequent ones (E.g. Design over Construction)  Errors in early subsystems have a snowball effect in the subsequent ones Level of control will vary depending on the stage of the project  Personnel issues (conflicts, leadership, etc) will evolve and need to be moderated considering project phase Planning must be incremental  Building bases for the next phase  Details added as project advances Major changes require their own distinctive Total Management  Changing project phases is a major event and needs to be treated as such! Remember: The Main Challenge in Interface Management is Human Interactions
  • 16. Interface Management Processes using the PMI framework Uncertainties ©Septentrion Strategic Solutions Ltd. Interface management must follow a lifecycle approach, with well defined processes Initiating / Identification Planning Execution Closing Monitoring & Control
  • 17. Interface Initiation Uncertainties ©Septentrion Strategic Solutions Ltd. Objective: Interfaces are identified and interface management overall strategy is defined based on the characteristics of the project  Appointment of the Interface Manager & Interface Coordinators  Establishment of an official definition of interface in the project  Interface identification based on Project Basic documents (Bulk identification) • Project Work Breakdown Structure (WBS) • Contracts • Specifications • Interviews  Quantify interfaces & preliminary identify risks • Creation of the Interface Responsibility Matrix (IRM)  Draft Interface Management Plan  identification and coordination of static and dynamic interfaces
  • 18. Interface Planning Uncertainties ©Septentrion Strategic Solutions Ltd. Objective: Refine interfaces information, allocate to corresponding parties and determine communication protocols • Refinement of the Interface Responsibility Matrix (as design is more advanced)  eliminate unnecessary interfaces / identify new ones • Allocation of interfaces into work packages • Incorporation of interfaces in the project schedule (first pass) • Integrate to schedule logic  future interface agreements • Finalization of the Interface Management Plan, including: • Define project interfaces & Interface lifecycle • Define Interface Management organization • Identify / define documents to capture interfaces in all ambits (e.g.: communications plan, RACI matrix, BLTs, etc.) • Define Conflict resolution process • Define Monitoring & control strategy (tools, frequency, details, etc) Warning!! ***Interface management plan should be part of contractual documents***
  • 19. Interface Execution Uncertainties ©Septentrion Strategic Solutions Ltd. Objective: Formal transfer of the interface to the appropriate parties and drive them to closure • Creation of formal Interface Documents • Obtain full commitment from interfaced parties • Align interfaces with a specific project activities / integrate them to the schedule Example: Interrelation Supplier S1 & constr. Contractor 1 (project Execution phase)
  • 21. Interface Closure Uncertainties ©Septentrion Strategic Solutions Ltd. Objective: satisfy all requirements of the interface as indicated in the Interface document.  Information provided on time and in the format agreed  Interface document closed  interface ceases to exist  Subsequent activities continue
  • 22. Interfaces Monitoring and Control Uncertainties ©Septentrion Strategic Solutions Ltd. Objective: Ensure a continuous visibility of the interface / enhance its timely resolution Monitoring starts as soon as an interface is identified • The monitoring and control strategy will depend on the size and complexity of the project • Interface register  Leading indicators (e.g.: look ahead) combined with lagging indicators (performance of the interfaces) Warning: In large projects, specialized software may be necessary to integrate and optimize interfaces. It is very difficult to rely on conventional tools (e.g.: MS Excel, Access, etc.): • Interfaces can be significant (e.g. a $10B project can easily have over 5,000 interfaces) • High potential for changes as project advances  scope reallocations, planning adjustments, start-up strategies, etc.
  • 23. Interface Monitoring & Control Uncertainties ©Septentrion Strategic Solutions Ltd. Example of Interface Management Monitoring & Controlling Strategy in a large project Report Generation Project Schedule Dynamic IA Reporting (look-ahead) Overdue Overdue in Less than x days Overdue in > x days Closed IA generation Tool
  • 24. Case Study: Oil Sands Mega Project Uncertainties ©Septentrion Strategic Solutions Ltd. Project: 120,000 bbld Production Facility Location: Northern Alberta • 3 Main EPC Contractors • 6 Fabrication and Construction Contractors • Engineering and Module Fabrication in multiple locations within in 3 continents Initial Estimate (end of FEL3): $4B (2008) Interim Estimate (30% Construction): ~$7B (2012) TIC: over $12B (2015) What Happened??
  • 25. Case Study: Oil Sands Mega Project (Cont.) Uncertainties ©Septentrion Strategic Solutions Ltd. The Promise: An Innovative & Efficient Interface Management System Interface Management Team was assembled during FEL-3 o Interface Manager o Interface Coordinators allocated to different project areas Module of Planning Software adapted to manage interfaces: o Friendly user interface for Interface Agreement creation o Easy integration of IAs with the schedule Interface management team identified all interfaces prior detailed engineering design phase o Interface Responsibility Matrix o Interface Coordinators estimated and created initial Interface Agreements Interface Management Plan created and approved the end of FEL-3
  • 26. Case Study: Oil Sands Mega Project (Cont.) Uncertainties ©Septentrion Strategic Solutions Ltd. The Reality: Interface Management strategy and plan not fully included in contract documents  IM process was rolled-out to contractors after contract award Insufficient contractual provisions for IM in sub-contractors and consultants (logistics, support, personnel) Contractors added change orders with additional fees associated to risks management Different attitudes / reactions towards IM (especially LS contactors) Weak Governance IM function managed by Engineering Consultant involved in the design with “oversight” support from client  Conflict of Interests Interfaces negotiated by client in silos  contracts awarded in different times Problems in enforcing IAs  Engineering Consultant managing Interfaces did not have any contractual leverage over other consultant or construction companies
  • 27. Case Study: Oil Sands Mega Project (Cont.) Uncertainties ©Septentrion Strategic Solutions Ltd. The Reality: Issues with the IM Management Tool The modified tool was a prototype Module is originally designed for Contract Management, not capable to manage with multiple interrelations Poor support from software provider / insufficient IT Scope definition Reports had to be manually generated by 1 super user (bottleneck) relying on Excel tools (Macros) Interface Coordinators (Project Engineers with no experience in facilitation/ courses delivery) became trainers for contractors designated personnel Neglected management of Dynamic Interfaces  Only Engineering and Construction interfaces were visible to the IM Team No jurisdiction of IM team over client internal processes Interfaces with external stakeholders poorly managed: Multiple issues with regulators and Government Key fabrication & transportation strategy had to be modified
  • 28. Case Study: Oil Sands Mega Project (Cont.) Uncertainties ©Septentrion Strategic Solutions Ltd. The Reality: Deficient project integration Different contract architectures  different performance and progress metrics IAs were never linked to the schedule Project has multiple schedules from each consultant / contractor Integrated schedule never produced Deficient Conflict Management Strategy High turnover in IM team due to conflicts with client and sub-contractors Conflict Management process was designed and implemented late in the project IM function removed from engineering consultant and transferred to competitor in the project Organizational Deficiencies IM seen with different levels of importance in the project  “Power struggles” Inadequate legitimization: IM seen as an “interference” in the Project
  • 29. The devil is in the details Final Considerations – Key takeaways Uncertainties ©Septentrion Strategic Solutions Ltd. Early identification is critical for the success of an interface Traditional approaches based on project configuration are insufficient to identify and manage interfaces Identify and understand interdependences: Clearly define static interfaces & Manage Dynamic Interfaces Each interface needs to be managed by tangible mechanisms Interface management strategy needs to be adapted to the size and complexity of the project Large projects require specific interface Management Strategies Do not neglect a lifecycle approach to manage interfaces  Select a framework and adapt it to the characteristics of your project!! Implement a clear governance for interface Management across the project and the organization And always Remember: Interfaces
  • 31. For more information about strategies to unlock value in your organization or projects, visit us at: www.septentrioncanada.com ©Septentrion Strategic Solutions Ltd. Septentrion Management Capsules ® Ideas to unlock value and enhance competitiveness in your organization