SlideShare a Scribd company logo
1 of 3
Download to read offline
1
Shipbuilding Contract: What can go wrong?
By David Seah, LLB London
Contractual risks in shipbuilding projects begin when the parties first
make contact. Things that could go wrong at this stage include a letter of
intent which may eventually be construed as invalid1. Also, issues could
arise involving breach of confidentiality2 and intellectual property rights.3
Upon the effective date of contract, the parties may exchange refund
and payment guarantees which could be unenforceable4, or find issues
with option agreement for additional vessels5.
During the production phase, arguments concerning approval of plans
and drawings could involve the buyer’s delays during the approval process
and its comments to the plans and drawings6. Other disputes could
concern variations,7 delays8, quality of workmanship, late inspection9,
over-inspection and interference.
All this inevitably could lead to delays and this will be compounded
further if, in order to win the project, the shipbuilder had created an
illusion of on-time delivery by developing a schedule with the completion
date as a reference point and working backwards. In such circumstances,
any subsequent rush to accelerate the project may result in construction
shortcomings, thus adding to more delays.
Subcontractors could also join in the fray through disputes concerning
shortcoming in quality, workmanship, late completion or late delivery of
work and equipment respectively, and non-compliance with contract
specification. As subcontractor’s delays (except for those that are related
to buyer supplies) are at shipbuilder’s risk, any delays caused by their
shortcomings above will be at the shipbuilder's expense.
1 RTS Flexible Systems Ltd v Molkerei Alois Muller GmbH & Co. KG [2010] UKSC 14.
2 Seager v. Copydex [1967] 2 All ER 415., Saltman Engineering Co. Ltd v Campbell
Engineering Co. Ltd (1948) 65 RPC 203.
3 Salt Ship Design AS v. Prysmian Powerlink SRL [2021] EWHC 2633 (Comm).
4 See footnote 14, infra.
5 Haugland Tankers v RMK Marine [2005] EWHC 321 (Comm).
6 Cenargo Ltd v Empresa v Nacional Bazan de Construcciones Navales Militares SA
[2001] EWHC 543 (QB), [2002] EXCA Civ 524 QBD (Comm).
7 McAlpine Humberoak Ltd v McDermott International Inc [1992] CILL 747., Blue Circle
Industries Plc v Holland Dredging Co (UK) Limited (1987) 37 BLR 40.
8 Zhoushan Jinhaiwan v Golden Exquisite Inc & 2 others [2014] EWHC 4050 (Comm).
9 Per footnote 7.
2
During testing and sea trials, the vessel could be found wanting in
performance criteria relating to speed, fuel consumption, deadweight
deficiency, and cubic capacity, resulting in liquidated damage and possible
termination of contract where performance does not comply with specified
allowable margins.
In the event of delayed delivery10, the buyer will be entitled to
liquidated damages and also to terminate the contract after a “drop-dead
date”11. When this happens, they could encounter allegations that the
buyer got the drop-dead date wrong as some of the delays were due to the
buyer’s default, thus the buyer has wrongfully repudiated the contract12.
Where the vessel does not comply with contract specification, the
buyer could refuse to accept delivery. Conversely, a shipbuilder could
disagree and contend that the buyer's refusal to take delivery of a vessel
was totally unjustified. Even when the vessel is finally delivered, it may
be premature to celebrate as the parties may have to reckon with post-
delivery warranty issues13.
In cases when buyers or shipbuilders call on the refund and payment
guarantee respectively, they may still face serious technical and legal
challenges.14
While the majority of shipbuilding disputes are resolved through
negotiated settlement, mediation, classification society or expert
determination, there are still those that end up in arbitration or the
courts. Even at this juncture, there may be challenges concerning
jurisdiction or the seat of arbitration15and others.
In such a situation, the ultimate results could be rather unpredictable.
This is particularly so in cases (a) of ambiguity, (b) where judicial
10 Taking into account permissible and possibly concurrent delays.
11 Stocznia Gdynia Sa V Gearbulk Holdings Ltd, [2009] EWCA CIV 75.
12 Jiangsu Guoxin Corporation Ltd (Formerly Known as Sainty Marine Corporation Ltd)
v Precious Shipping Public Co. Ltd [2020] EWHC 1030 (Comm). Note also, Adyard Abu
Dhabi v SD Marine Services [2011] EWHC 848 (Comm), where shipbuilder unsuccessfully
invoked the prevention principle.
13 Neon Shipping Inc v Foreign Economic 7 Technical Corporation Co. of China and
others [2016] EWHC 399 (Comm).
14 CIMC Raffles Offshore (Singapore) Limited and Yantai CIMC Raffles Offshore Limited
v Schahin Holding [2013] EWCA Civ 644., Rainy Sky S. A. v Kookmin Bank [2011]
UKSC 50, [2010] EWCA Civ 582., Sea-Cargo Skips As v State Bank of India [2013]
EWHC 177., Wuhan Ocean and Nantong v Schiffahrts-Gesellschaft [2012] EWHC 3104
(Comm)., Meritz Fire and Marine Insurance Co Ltd v (1) Jan de Nul NV and(2) Codralux
SA [2010] EWHC 3362 (Comm), [2011] EWCA Civ 827., WS Tankship II BV v Kwangju
Bank Ltd [2011] EWHC 3103., Carey Value Added SL v Grupo Urvasco SA 2010 EWHC
1905 (Comm)., Sea Emerald SA v Prominvestbank [2008] EWHC 1979 (Comm).,
Stocznia Gdynia SA v Gearbulk Holdings Ltd [2008] EWHC 944 (Comm).
15 Sulamerica Cia Nacional De Seguros S.A. and others v Enesa Engenharia S.A. and
others [2012] EWCA Civ 638.
3
decisions remain divided on the correct application of the law16, and (c) in
cases which depend substantially on the judicial interpretation of the text
in one or more clauses in the contract.
The journey will be tedious as such proceedings can last many years,
and in one particular case involving a pipelay vessel, about ten years.
Ultimately, the effectiveness of enforcing the arbitration award or
judgement against the losing party will depend on whether that party is
still solvent and if otherwise, whether there will be enforcement issues in
its country of residence.
Yet all is not gloomy if steps are taken from the very beginning, to
identify, avoid or minimise not only contractual, but also technical and
other associated risks.
https://www.linkedin.com/in/seahdavid
20 Mar 2022
The writer read law at the university of London and was admitted as a
barrister of Lincoln’s Inn. His transactional expertise in shipbuilding
contracts and related ancillary agreements is derived from prior experience
as in-house shipyard lawyer, involvement with subsea marine construction
contracts and as on-site counsel in an FDPSO conversion project.
DISCLAIMER
THIS ARTICLE IS BASED ON THE RESEARCH AND PRACTICAL
EXPERIENCE OF THE AUTHOR AND IS MEANT FOR GENERAL
READING AND EDUCATIONAL PURPOSE. IT IS NOT INTENDED TO
PROVIDE LEGAL ADVICE AND MUST NOT BE TREATED AS A
SUBSTITUTE FOR SPECIFIC LEGAL ADVICE OR RELIED UPON
UNDER ANY CIRCUMSTANCES. THE WRITER AND PUBLISHER
DOES NOT GUARANTEE THE ACCURACY OF THE INFORMATION
IN THIS ARTICLE AND HEREBY DISCLAIM RESPONSIBILITY FOR
ANY LOSSES OR DAMAGES WHATSOEVER AND HOWSOEVER
INCURRED THROUGH THE USE OF INFORMATION IN THIS
ARTICLE
16 Especially in consequential loss, refund or payment guarantees, and delays claims.

More Related Content

What's hot

Shipping and arbitration: Insights from the Black Sea countries
Shipping and arbitration: Insights from the Black Sea countriesShipping and arbitration: Insights from the Black Sea countries
Shipping and arbitration: Insights from the Black Sea countriesEugene Tkachenko
 
Hague visby article 1-3
Hague   visby article 1-3Hague   visby article 1-3
Hague visby article 1-3Manu Singh
 
Outline of Conventions and Legislation applicable to Bills of Lading in the UK
Outline of Conventions and Legislation applicable to Bills of Lading in the UKOutline of Conventions and Legislation applicable to Bills of Lading in the UK
Outline of Conventions and Legislation applicable to Bills of Lading in the UKAmarinder Singh Brar
 
History of the Bill of Lading : An Overview
History of the Bill of Lading : An OverviewHistory of the Bill of Lading : An Overview
History of the Bill of Lading : An OverviewSamantha Masters
 
Forwarding agent, haulier, clean bill of
Forwarding agent, haulier, clean bill ofForwarding agent, haulier, clean bill of
Forwarding agent, haulier, clean bill ofHakimi Sha'ari
 

What's hot (13)

Bill of lading
Bill of ladingBill of lading
Bill of lading
 
Chap07
Chap07Chap07
Chap07
 
Bill of-lading
Bill of-ladingBill of-lading
Bill of-lading
 
Shipping and arbitration: Insights from the Black Sea countries
Shipping and arbitration: Insights from the Black Sea countriesShipping and arbitration: Insights from the Black Sea countries
Shipping and arbitration: Insights from the Black Sea countries
 
Shipping and Shipping Terms
Shipping and Shipping TermsShipping and Shipping Terms
Shipping and Shipping Terms
 
Maritime
MaritimeMaritime
Maritime
 
Hague visby article 1-3
Hague   visby article 1-3Hague   visby article 1-3
Hague visby article 1-3
 
Panel discussion
Panel discussionPanel discussion
Panel discussion
 
Outline of Conventions and Legislation applicable to Bills of Lading in the UK
Outline of Conventions and Legislation applicable to Bills of Lading in the UKOutline of Conventions and Legislation applicable to Bills of Lading in the UK
Outline of Conventions and Legislation applicable to Bills of Lading in the UK
 
History of the Bill of Lading : An Overview
History of the Bill of Lading : An OverviewHistory of the Bill of Lading : An Overview
History of the Bill of Lading : An Overview
 
Hague visby rules
Hague visby rulesHague visby rules
Hague visby rules
 
Bill of lading
Bill of ladingBill of lading
Bill of lading
 
Forwarding agent, haulier, clean bill of
Forwarding agent, haulier, clean bill ofForwarding agent, haulier, clean bill of
Forwarding agent, haulier, clean bill of
 

Similar to Shipbuilding Contract: What can go wrong?

Assessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation CostAssessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation CostJessica Navarro
 
Delay Disputes - Decommissioning
Delay Disputes - DecommissioningDelay Disputes - Decommissioning
Delay Disputes - DecommissioningMichael Davar
 
SatelliteFinance_SpecialReport_Key Considerations in Hosted Payloads
SatelliteFinance_SpecialReport_Key Considerations in Hosted PayloadsSatelliteFinance_SpecialReport_Key Considerations in Hosted Payloads
SatelliteFinance_SpecialReport_Key Considerations in Hosted PayloadsAaron Shourie
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterSeanGibbs12
 
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.GE 94
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Francis Ho
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 CompleteJohn Ashton
 
Risk in FIDIC contracts
Risk in FIDIC contracts Risk in FIDIC contracts
Risk in FIDIC contracts Paul Gogulski
 
Legal Aspects of Charter Parties – Basic Issues by Alex Pinto
Legal Aspects of Charter Parties – Basic Issues by Alex PintoLegal Aspects of Charter Parties – Basic Issues by Alex Pinto
Legal Aspects of Charter Parties – Basic Issues by Alex Pintocmmindia2017
 
Shipping E-Brief Autumn 2014
Shipping E-Brief Autumn 2014Shipping E-Brief Autumn 2014
Shipping E-Brief Autumn 2014Ince & Co
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFrancis Ho
 
Liquidated Damages post Cavendish v Makdessi
Liquidated Damages post Cavendish v MakdessiLiquidated Damages post Cavendish v Makdessi
Liquidated Damages post Cavendish v MakdessiAdam Ramlugon
 
Fi dic silver book
Fi dic silver bookFi dic silver book
Fi dic silver bookmoodlyd
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsEversheds Sutherland
 
Fidelity_Surety_July_2009 (1)
Fidelity_Surety_July_2009 (1)Fidelity_Surety_July_2009 (1)
Fidelity_Surety_July_2009 (1)Pamela McGovern
 

Similar to Shipbuilding Contract: What can go wrong? (20)

Assessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation CostAssessing Loss And Expenses Claim By Prolongation Cost
Assessing Loss And Expenses Claim By Prolongation Cost
 
Delay Disputes - Decommissioning
Delay Disputes - DecommissioningDelay Disputes - Decommissioning
Delay Disputes - Decommissioning
 
Student ID Number 150578905
Student ID Number 150578905Student ID Number 150578905
Student ID Number 150578905
 
SatelliteFinance_SpecialReport_Key Considerations in Hosted Payloads
SatelliteFinance_SpecialReport_Key Considerations in Hosted PayloadsSatelliteFinance_SpecialReport_Key Considerations in Hosted Payloads
SatelliteFinance_SpecialReport_Key Considerations in Hosted Payloads
 
Against all odds
Against all odds Against all odds
Against all odds
 
February 2019 newsletter
February 2019 newsletterFebruary 2019 newsletter
February 2019 newsletter
 
UK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 NewsletterUK Adjudicators February 2022 Newsletter
UK Adjudicators February 2022 Newsletter
 
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
Risks of non compliance of cl.19.7 cl.20 under BPVOY4.
 
Edd guidance 13 tcm155-198278
Edd guidance 13 tcm155-198278Edd guidance 13 tcm155-198278
Edd guidance 13 tcm155-198278
 
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
Olswang Construction Law Masterclass - October 2014 - Liqudated Damages and P...
 
Assignment 1 Complete
Assignment 1 CompleteAssignment 1 Complete
Assignment 1 Complete
 
Risk in FIDIC contracts
Risk in FIDIC contracts Risk in FIDIC contracts
Risk in FIDIC contracts
 
Legal Aspects of Charter Parties – Basic Issues by Alex Pinto
Legal Aspects of Charter Parties – Basic Issues by Alex PintoLegal Aspects of Charter Parties – Basic Issues by Alex Pinto
Legal Aspects of Charter Parties – Basic Issues by Alex Pinto
 
Shipping E-Brief Autumn 2014
Shipping E-Brief Autumn 2014Shipping E-Brief Autumn 2014
Shipping E-Brief Autumn 2014
 
FIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power ProjectsFIDIC SIlver Book in Power Projects
FIDIC SIlver Book in Power Projects
 
Liquidated Damages post Cavendish v Makdessi
Liquidated Damages post Cavendish v MakdessiLiquidated Damages post Cavendish v Makdessi
Liquidated Damages post Cavendish v Makdessi
 
George horsington
George horsingtonGeorge horsington
George horsington
 
Fi dic silver book
Fi dic silver bookFi dic silver book
Fi dic silver book
 
Time Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contractsTime Bars and their enforceability in English law EPC contracts
Time Bars and their enforceability in English law EPC contracts
 
Fidelity_Surety_July_2009 (1)
Fidelity_Surety_July_2009 (1)Fidelity_Surety_July_2009 (1)
Fidelity_Surety_July_2009 (1)
 

Recently uploaded

如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书Fs Las
 
Arbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaArbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaNafiaNazim
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptjudeplata
 
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top BoutiqueAndrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top BoutiqueSkyLaw Professional Corporation
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSDr. Oliver Massmann
 
Essentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmmEssentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmm2020000445musaib
 
如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书Fir L
 
Indemnity Guarantee Section 124 125 and 126
Indemnity Guarantee Section 124 125 and 126Indemnity Guarantee Section 124 125 and 126
Indemnity Guarantee Section 124 125 and 126Oishi8
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书FS LS
 
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书Fs Las
 
Ricky French: Championing Truth and Change in Midlothian
Ricky French: Championing Truth and Change in MidlothianRicky French: Championing Truth and Change in Midlothian
Ricky French: Championing Truth and Change in MidlothianRicky French
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书Fir sss
 
The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...James Watkins, III JD CFP®
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书srst S
 
Introduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusionIntroduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusionAnuragMishra811030
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书Fir L
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书Sir Lt
 

Recently uploaded (20)

如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
如何办理(USF文凭证书)美国旧金山大学毕业证学位证书
 
Arbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in IndiaArbitration, mediation and conciliation in India
Arbitration, mediation and conciliation in India
 
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.pptFINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
FINALTRUEENFORCEMENT OF BARANGAY SETTLEMENT.ppt
 
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
Russian Call Girls Service Gomti Nagar \ 9548273370 Indian Call Girls Service...
 
Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
Russian Call Girls Rohini Sector 6 💓 Delhi 9999965857 @Sabina Modi VVIP MODEL...
 
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top BoutiqueAndrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
Andrea Hill Featured in Canadian Lawyer as SkyLaw Recognized as a Top Boutique
 
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTSVIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
VIETNAM – LATEST GUIDE TO CONTRACT MANUFACTURING AND TOLLING AGREEMENTS
 
Essentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmmEssentials of a Valid Transfer.pptxmmmmmm
Essentials of a Valid Transfer.pptxmmmmmm
 
如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书如何办理提赛德大学毕业证(本硕)Teesside学位证书
如何办理提赛德大学毕业证(本硕)Teesside学位证书
 
Indemnity Guarantee Section 124 125 and 126
Indemnity Guarantee Section 124 125 and 126Indemnity Guarantee Section 124 125 and 126
Indemnity Guarantee Section 124 125 and 126
 
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
如何办理密德萨斯大学毕业证(本硕)Middlesex学位证书
 
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
如何办理(SFSta文凭证书)美国旧金山州立大学毕业证学位证书
 
Ricky French: Championing Truth and Change in Midlothian
Ricky French: Championing Truth and Change in MidlothianRicky French: Championing Truth and Change in Midlothian
Ricky French: Championing Truth and Change in Midlothian
 
如何办理佛蒙特大学毕业证学位证书
 如何办理佛蒙特大学毕业证学位证书 如何办理佛蒙特大学毕业证学位证书
如何办理佛蒙特大学毕业证学位证书
 
The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...The Active Management Value Ratio: The New Science of Benchmarking Investment...
The Active Management Value Ratio: The New Science of Benchmarking Investment...
 
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
如何办理(UoM毕业证书)曼彻斯特大学毕业证学位证书
 
Introduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusionIntroduction to Corruption, definition, types, impact and conclusion
Introduction to Corruption, definition, types, impact and conclusion
 
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
如何办理新加坡南洋理工大学毕业证(本硕)NTU学位证书
 
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书 如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
如何办理(MSU文凭证书)密歇根州立大学毕业证学位证书
 
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No AdvanceRohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
Rohini Sector 25 Call Girls Delhi 9999965857 @Sabina Saikh No Advance
 

Shipbuilding Contract: What can go wrong?

  • 1. 1 Shipbuilding Contract: What can go wrong? By David Seah, LLB London Contractual risks in shipbuilding projects begin when the parties first make contact. Things that could go wrong at this stage include a letter of intent which may eventually be construed as invalid1. Also, issues could arise involving breach of confidentiality2 and intellectual property rights.3 Upon the effective date of contract, the parties may exchange refund and payment guarantees which could be unenforceable4, or find issues with option agreement for additional vessels5. During the production phase, arguments concerning approval of plans and drawings could involve the buyer’s delays during the approval process and its comments to the plans and drawings6. Other disputes could concern variations,7 delays8, quality of workmanship, late inspection9, over-inspection and interference. All this inevitably could lead to delays and this will be compounded further if, in order to win the project, the shipbuilder had created an illusion of on-time delivery by developing a schedule with the completion date as a reference point and working backwards. In such circumstances, any subsequent rush to accelerate the project may result in construction shortcomings, thus adding to more delays. Subcontractors could also join in the fray through disputes concerning shortcoming in quality, workmanship, late completion or late delivery of work and equipment respectively, and non-compliance with contract specification. As subcontractor’s delays (except for those that are related to buyer supplies) are at shipbuilder’s risk, any delays caused by their shortcomings above will be at the shipbuilder's expense. 1 RTS Flexible Systems Ltd v Molkerei Alois Muller GmbH & Co. KG [2010] UKSC 14. 2 Seager v. Copydex [1967] 2 All ER 415., Saltman Engineering Co. Ltd v Campbell Engineering Co. Ltd (1948) 65 RPC 203. 3 Salt Ship Design AS v. Prysmian Powerlink SRL [2021] EWHC 2633 (Comm). 4 See footnote 14, infra. 5 Haugland Tankers v RMK Marine [2005] EWHC 321 (Comm). 6 Cenargo Ltd v Empresa v Nacional Bazan de Construcciones Navales Militares SA [2001] EWHC 543 (QB), [2002] EXCA Civ 524 QBD (Comm). 7 McAlpine Humberoak Ltd v McDermott International Inc [1992] CILL 747., Blue Circle Industries Plc v Holland Dredging Co (UK) Limited (1987) 37 BLR 40. 8 Zhoushan Jinhaiwan v Golden Exquisite Inc & 2 others [2014] EWHC 4050 (Comm). 9 Per footnote 7.
  • 2. 2 During testing and sea trials, the vessel could be found wanting in performance criteria relating to speed, fuel consumption, deadweight deficiency, and cubic capacity, resulting in liquidated damage and possible termination of contract where performance does not comply with specified allowable margins. In the event of delayed delivery10, the buyer will be entitled to liquidated damages and also to terminate the contract after a “drop-dead date”11. When this happens, they could encounter allegations that the buyer got the drop-dead date wrong as some of the delays were due to the buyer’s default, thus the buyer has wrongfully repudiated the contract12. Where the vessel does not comply with contract specification, the buyer could refuse to accept delivery. Conversely, a shipbuilder could disagree and contend that the buyer's refusal to take delivery of a vessel was totally unjustified. Even when the vessel is finally delivered, it may be premature to celebrate as the parties may have to reckon with post- delivery warranty issues13. In cases when buyers or shipbuilders call on the refund and payment guarantee respectively, they may still face serious technical and legal challenges.14 While the majority of shipbuilding disputes are resolved through negotiated settlement, mediation, classification society or expert determination, there are still those that end up in arbitration or the courts. Even at this juncture, there may be challenges concerning jurisdiction or the seat of arbitration15and others. In such a situation, the ultimate results could be rather unpredictable. This is particularly so in cases (a) of ambiguity, (b) where judicial 10 Taking into account permissible and possibly concurrent delays. 11 Stocznia Gdynia Sa V Gearbulk Holdings Ltd, [2009] EWCA CIV 75. 12 Jiangsu Guoxin Corporation Ltd (Formerly Known as Sainty Marine Corporation Ltd) v Precious Shipping Public Co. Ltd [2020] EWHC 1030 (Comm). Note also, Adyard Abu Dhabi v SD Marine Services [2011] EWHC 848 (Comm), where shipbuilder unsuccessfully invoked the prevention principle. 13 Neon Shipping Inc v Foreign Economic 7 Technical Corporation Co. of China and others [2016] EWHC 399 (Comm). 14 CIMC Raffles Offshore (Singapore) Limited and Yantai CIMC Raffles Offshore Limited v Schahin Holding [2013] EWCA Civ 644., Rainy Sky S. A. v Kookmin Bank [2011] UKSC 50, [2010] EWCA Civ 582., Sea-Cargo Skips As v State Bank of India [2013] EWHC 177., Wuhan Ocean and Nantong v Schiffahrts-Gesellschaft [2012] EWHC 3104 (Comm)., Meritz Fire and Marine Insurance Co Ltd v (1) Jan de Nul NV and(2) Codralux SA [2010] EWHC 3362 (Comm), [2011] EWCA Civ 827., WS Tankship II BV v Kwangju Bank Ltd [2011] EWHC 3103., Carey Value Added SL v Grupo Urvasco SA 2010 EWHC 1905 (Comm)., Sea Emerald SA v Prominvestbank [2008] EWHC 1979 (Comm)., Stocznia Gdynia SA v Gearbulk Holdings Ltd [2008] EWHC 944 (Comm). 15 Sulamerica Cia Nacional De Seguros S.A. and others v Enesa Engenharia S.A. and others [2012] EWCA Civ 638.
  • 3. 3 decisions remain divided on the correct application of the law16, and (c) in cases which depend substantially on the judicial interpretation of the text in one or more clauses in the contract. The journey will be tedious as such proceedings can last many years, and in one particular case involving a pipelay vessel, about ten years. Ultimately, the effectiveness of enforcing the arbitration award or judgement against the losing party will depend on whether that party is still solvent and if otherwise, whether there will be enforcement issues in its country of residence. Yet all is not gloomy if steps are taken from the very beginning, to identify, avoid or minimise not only contractual, but also technical and other associated risks. https://www.linkedin.com/in/seahdavid 20 Mar 2022 The writer read law at the university of London and was admitted as a barrister of Lincoln’s Inn. His transactional expertise in shipbuilding contracts and related ancillary agreements is derived from prior experience as in-house shipyard lawyer, involvement with subsea marine construction contracts and as on-site counsel in an FDPSO conversion project. DISCLAIMER THIS ARTICLE IS BASED ON THE RESEARCH AND PRACTICAL EXPERIENCE OF THE AUTHOR AND IS MEANT FOR GENERAL READING AND EDUCATIONAL PURPOSE. IT IS NOT INTENDED TO PROVIDE LEGAL ADVICE AND MUST NOT BE TREATED AS A SUBSTITUTE FOR SPECIFIC LEGAL ADVICE OR RELIED UPON UNDER ANY CIRCUMSTANCES. THE WRITER AND PUBLISHER DOES NOT GUARANTEE THE ACCURACY OF THE INFORMATION IN THIS ARTICLE AND HEREBY DISCLAIM RESPONSIBILITY FOR ANY LOSSES OR DAMAGES WHATSOEVER AND HOWSOEVER INCURRED THROUGH THE USE OF INFORMATION IN THIS ARTICLE 16 Especially in consequential loss, refund or payment guarantees, and delays claims.