SlideShare a Scribd company logo
1 of 4
Download to read offline
1 | P a g e
CHINMAY KORGAONKAR
Chinmay Korgaonkar
SYNCROLIFT (shiplift)
General Overview
A syncrolift is a system to lift ships and other vessels out of the water for dry
docking operations. The system consists of a platform on which the vessel is
moved vertically, which is then lifted by a set of synchronized winches. The
load distribution on the platform is calculated considering the load of the cradle
and the supporting blocks & trestles. Placing the blocks at the centreline is
always preferred to avoid uneven distribution of load on the winches. Trestles
are placed on the platform as per the position I or position II of the docking plan,
The block or cradle arrangement is, in general, to be such as to ensure that the
pressure on the hull of a docked ship is not greater than that for which its
structure is suitable. by using synchronous electric motors for hoisting, the
uneven loading can be avoided while raising and lowering the vessel which
minimizes the risk of damage to the platform or the hull during the operation
This system is suitable for certain geographical locations where the difference
between the tides is not extensive and it is also important to consider the costal
sedimentation in the region
2 | P a g e
CHINMAY KORGAONKAR
Working mechanism
The platform is movable which can be adjusted as to contour or inclination and
it can be raised and lowered in adjusted position which is accomplished by the
use of synchronous motors which can be operated independently for adjusting
the platform and simultaneously for adjusting the floor, raising and lowering the
adjusted platform.
The side walls are constructed in any desired manner but mostly a series of piers
is preferred and piers are spaced apart at a suitable distance to define a series of
alcoves which house the parts of the platform lifting mechanism
The platform consists of multiple parallel transversely extending keel supporting
beams and multiple intermediate floor sections. The beams are spaced apart a
distance equal to the distance between centres of the alcoves and they are
supported at their ends by hoisting mechanism. The web beam has a bracket
each of which houses the journals of multiple groove pulley.
A cable is passed about this pulley and another pulley supported by brackets on
channel beams seated on the top of the pier. The cable has one end anchored to a
channel and the other end wounded on a drum mounted on the dock and each
cable drum is driven by its independent synchronous motor, The motors at any
one beam position can be operated independently of the other motors of the
system to wind or unwind the cables on the drums to raise or lower the beam.
Fig.2 (Lifting platform)
3 | P a g e
CHINMAY KORGAONKAR
Because of this arrangement, the several beams of the floor can be raised to
different heights so that the beams will lie along any predetermined keel contour
or angle, to the end that each beam of the floor will contact a ship's keel
simultaneously when all of the beams are raised together by simultaneous
operation of all of the synchronous motors.
The web beams are joined together to form a floor by means of the intermediate
floor sections. These comprise pairs of transversely spaced, longitudinally
extending beams held in spaced relation by bridge members. The floor sections
are secured to the beams so as to permit the beams to have relative vertical
movement, to prevent swaying of beams.
Each of the beams carries a trestle or a pair of bilge blocks upon its upper
surface, with the blocks of the pair being on opposite sides of the centre of the
beam. The trestles can be moved to desirable position no matter what the
elevation of the beam may be. This gives the operator the freedom to present the
floor to the plan of the keel and hull of an incoming ship
When the ship is floated into the slip the platform may be moved upwardly to
make precise contact with the ship along the length of the keel to raise the ship
without changing the trim position and without imposing undue stress on any
part of the system and the hull
Lifting platform also includes upper timber decking components supported on
the upper surfaces of beams. Additionally, the platform include rail members for
supporting a movable hydraulically operated lifting bogie which is used to
transfer the vessel from the ship lift platform to the work bay.
4 | P a g e
CHINMAY KORGAONKAR
To transfer the vessel between the ship lift platform and the berth or reverse, the
trestles are lifted up by the hydraulic lifting cylinders of the bogies. The lift
cylinders of the bogies are connected to three hydraulic fluid-beds. The vessel
will rest on a three-point support with uniform loads for each cylinder within a
hydraulic bed.
The fluid-bed can also be used during launching or lifting of the vessels. To lift
a vessel using fluid bed, the trestles will be positioned on the platform while the
bogies remain under the trestles. The bogies are suitable for underwater use. The
platform will be lowered and the bogies, in ‘Fluid-Bed’ mode, will go under
water. In this case, the trestles rest on the hydraulic cylinders of the bogies. By
keeping the hydraulic lifting system in operation during launching or lifting,
deformations of the shiplift platform are compensated and the vessels rest on the
hydraulic beds with uniform load distributions inside each bed.

More Related Content

What's hot

JAR 23 and FAR 23 Comparison
JAR 23 and FAR 23 ComparisonJAR 23 and FAR 23 Comparison
JAR 23 and FAR 23 ComparisonJio Gayon
 
Railway Electrification - Traction
Railway Electrification - TractionRailway Electrification - Traction
Railway Electrification - TractionSUDIN BISWAS
 
10. contaminated runways
10. contaminated runways10. contaminated runways
10. contaminated runwayschococrispis37
 
RoRo Gemileri ve yükleme boşaltma
RoRo Gemileri ve yükleme boşaltmaRoRo Gemileri ve yükleme boşaltma
RoRo Gemileri ve yükleme boşaltmaSevilay Can
 
Railway Training Report
Railway Training ReportRailway Training Report
Railway Training ReportVishal Singh
 
Lesson 1 Ship Characteristics
Lesson 1 Ship CharacteristicsLesson 1 Ship Characteristics
Lesson 1 Ship CharacteristicsGuilherme Azevedo
 
Emu car shed ghaziabad
Emu car shed ghaziabadEmu car shed ghaziabad
Emu car shed ghaziabadAbhishek Singh
 
B737 NG Flight controls
B737 NG Flight controlsB737 NG Flight controls
B737 NG Flight controlstheoryce
 
Air brake system in indian railways
Air brake system in indian railwaysAir brake system in indian railways
Air brake system in indian railwaysRamkumar Niluroutu
 
Ship tonnage measurement
Ship tonnage measurementShip tonnage measurement
Ship tonnage measurementFurqon Hanief
 
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7Aayush Singhal
 
Atot day 1 rev 1.01
Atot day 1 rev 1.01Atot day 1 rev 1.01
Atot day 1 rev 1.01glenaunzo
 
RAILWAY WORKSHOP TRANING PPT
RAILWAY WORKSHOP TRANING  PPTRAILWAY WORKSHOP TRANING  PPT
RAILWAY WORKSHOP TRANING PPTSahil arora
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...haxxo24
 

What's hot (20)

JAR 23 and FAR 23 Comparison
JAR 23 and FAR 23 ComparisonJAR 23 and FAR 23 Comparison
JAR 23 and FAR 23 Comparison
 
Gemide Atık Oluşumu ve Bertarafı
Gemide Atık Oluşumu ve BertarafıGemide Atık Oluşumu ve Bertarafı
Gemide Atık Oluşumu ve Bertarafı
 
Railway Electrification - Traction
Railway Electrification - TractionRailway Electrification - Traction
Railway Electrification - Traction
 
10. contaminated runways
10. contaminated runways10. contaminated runways
10. contaminated runways
 
RoRo Gemileri ve yükleme boşaltma
RoRo Gemileri ve yükleme boşaltmaRoRo Gemileri ve yükleme boşaltma
RoRo Gemileri ve yükleme boşaltma
 
Railway Training Report
Railway Training ReportRailway Training Report
Railway Training Report
 
Lesson 1 Ship Characteristics
Lesson 1 Ship CharacteristicsLesson 1 Ship Characteristics
Lesson 1 Ship Characteristics
 
Loco bogies clw
Loco bogies clwLoco bogies clw
Loco bogies clw
 
Emu car shed ghaziabad
Emu car shed ghaziabadEmu car shed ghaziabad
Emu car shed ghaziabad
 
B737 NG Flight controls
B737 NG Flight controlsB737 NG Flight controls
B737 NG Flight controls
 
Air brake system in indian railways
Air brake system in indian railwaysAir brake system in indian railways
Air brake system in indian railways
 
Gemi İnşaatı - 03 - Endaze, Fribord ve Tonaj
Gemi İnşaatı - 03 - Endaze, Fribord ve TonajGemi İnşaatı - 03 - Endaze, Fribord ve Tonaj
Gemi İnşaatı - 03 - Endaze, Fribord ve Tonaj
 
Bmbs apm working system
Bmbs apm working systemBmbs apm working system
Bmbs apm working system
 
Ship tonnage measurement
Ship tonnage measurementShip tonnage measurement
Ship tonnage measurement
 
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
Aayush_loco report-PNEUMATIC SYSTEMS IN WAG-7
 
Atot day 1 rev 1.01
Atot day 1 rev 1.01Atot day 1 rev 1.01
Atot day 1 rev 1.01
 
Landing Gear
Landing GearLanding Gear
Landing Gear
 
double bottom structure
double bottom structuredouble bottom structure
double bottom structure
 
RAILWAY WORKSHOP TRANING PPT
RAILWAY WORKSHOP TRANING  PPTRAILWAY WORKSHOP TRANING  PPT
RAILWAY WORKSHOP TRANING PPT
 
South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...South east central railway (secr) bilaspur mechanical vocational training rep...
South east central railway (secr) bilaspur mechanical vocational training rep...
 

Similar to Syncrolift: An Overview of Ship Lifting Systems

Introducing the Pillar Boat
Introducing the Pillar BoatIntroducing the Pillar Boat
Introducing the Pillar BoatJohn Huenefeld
 
Types of cranes
Types of cranesTypes of cranes
Types of cranesZiad Salem
 
Hoisting ...05.12.10.wo.vid
Hoisting ...05.12.10.wo.vid Hoisting ...05.12.10.wo.vid
Hoisting ...05.12.10.wo.vid Vivek mc
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railwayKHUSHBU SHAH
 
Engineering plant facilities 05 mechanics vertical transportation
Engineering plant facilities 05 mechanics vertical transportationEngineering plant facilities 05 mechanics vertical transportation
Engineering plant facilities 05 mechanics vertical transportationLuis Cabrera
 
5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stressesMani Vel
 
5-180501044424.pdf
5-180501044424.pdf5-180501044424.pdf
5-180501044424.pdfRijuDasgupta
 
MATERIALHANDELINGNOTES FOR ENGINEERINGSE
MATERIALHANDELINGNOTES FOR ENGINEERINGSEMATERIALHANDELINGNOTES FOR ENGINEERINGSE
MATERIALHANDELINGNOTES FOR ENGINEERINGSE006kaustavdey
 
Material handling equipments
Material handling equipmentsMaterial handling equipments
Material handling equipmentsSULAKSHYA GAUR
 
Tds 04-06 floating-wind-measurement-platform-a00
Tds 04-06 floating-wind-measurement-platform-a00Tds 04-06 floating-wind-measurement-platform-a00
Tds 04-06 floating-wind-measurement-platform-a00Antonis Daskalakis
 

Similar to Syncrolift: An Overview of Ship Lifting Systems (20)

Introducing the Pillar Boat
Introducing the Pillar BoatIntroducing the Pillar Boat
Introducing the Pillar Boat
 
Electric Overhead cranes
Electric Overhead cranes Electric Overhead cranes
Electric Overhead cranes
 
Types of crane
Types of craneTypes of crane
Types of crane
 
Presentation on electric cranes
Presentation on electric cranesPresentation on electric cranes
Presentation on electric cranes
 
Types of cranes
Types of cranesTypes of cranes
Types of cranes
 
Construction Equipment -Crane - Hoisting equipment
Construction Equipment -Crane - Hoisting equipmentConstruction Equipment -Crane - Hoisting equipment
Construction Equipment -Crane - Hoisting equipment
 
bucket.pdf
bucket.pdfbucket.pdf
bucket.pdf
 
L&H International
L&H InternationalL&H International
L&H International
 
Name 409 marine engineering ii steering system
Name 409 marine engineering ii steering systemName 409 marine engineering ii steering system
Name 409 marine engineering ii steering system
 
Hoisting ...05.12.10.wo.vid
Hoisting ...05.12.10.wo.vid Hoisting ...05.12.10.wo.vid
Hoisting ...05.12.10.wo.vid
 
Chapter 5 Introduction to railway
Chapter 5 Introduction to railwayChapter 5 Introduction to railway
Chapter 5 Introduction to railway
 
25 sems and maritime transport
25   sems and maritime transport25   sems and maritime transport
25 sems and maritime transport
 
Engineering plant facilities 05 mechanics vertical transportation
Engineering plant facilities 05 mechanics vertical transportationEngineering plant facilities 05 mechanics vertical transportation
Engineering plant facilities 05 mechanics vertical transportation
 
Belt conveyor _2_
Belt conveyor _2_Belt conveyor _2_
Belt conveyor _2_
 
Hoisting
HoistingHoisting
Hoisting
 
5.track or permanent way and track stresses
5.track or permanent way and track stresses5.track or permanent way and track stresses
5.track or permanent way and track stresses
 
5-180501044424.pdf
5-180501044424.pdf5-180501044424.pdf
5-180501044424.pdf
 
MATERIALHANDELINGNOTES FOR ENGINEERINGSE
MATERIALHANDELINGNOTES FOR ENGINEERINGSEMATERIALHANDELINGNOTES FOR ENGINEERINGSE
MATERIALHANDELINGNOTES FOR ENGINEERINGSE
 
Material handling equipments
Material handling equipmentsMaterial handling equipments
Material handling equipments
 
Tds 04-06 floating-wind-measurement-platform-a00
Tds 04-06 floating-wind-measurement-platform-a00Tds 04-06 floating-wind-measurement-platform-a00
Tds 04-06 floating-wind-measurement-platform-a00
 

Recently uploaded

Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxpurnimasatapathy1234
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacingjaychoudhary37
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...Soham Mondal
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Dr.Costas Sachpazis
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Microscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptxMicroscopic Analysis of Ceramic Materials.pptx
Microscopic Analysis of Ceramic Materials.pptx
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
microprocessor 8085 and its interfacing
microprocessor 8085  and its interfacingmicroprocessor 8085  and its interfacing
microprocessor 8085 and its interfacing
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
OSVC_Meta-Data based Simulation Automation to overcome Verification Challenge...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
Sheet Pile Wall Design and Construction: A Practical Guide for Civil Engineer...
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
🔝9953056974🔝!!-YOUNG call girls in Rajendra Nagar Escort rvice Shot 2000 nigh...
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 

Syncrolift: An Overview of Ship Lifting Systems

  • 1. 1 | P a g e CHINMAY KORGAONKAR Chinmay Korgaonkar SYNCROLIFT (shiplift) General Overview A syncrolift is a system to lift ships and other vessels out of the water for dry docking operations. The system consists of a platform on which the vessel is moved vertically, which is then lifted by a set of synchronized winches. The load distribution on the platform is calculated considering the load of the cradle and the supporting blocks & trestles. Placing the blocks at the centreline is always preferred to avoid uneven distribution of load on the winches. Trestles are placed on the platform as per the position I or position II of the docking plan, The block or cradle arrangement is, in general, to be such as to ensure that the pressure on the hull of a docked ship is not greater than that for which its structure is suitable. by using synchronous electric motors for hoisting, the uneven loading can be avoided while raising and lowering the vessel which minimizes the risk of damage to the platform or the hull during the operation This system is suitable for certain geographical locations where the difference between the tides is not extensive and it is also important to consider the costal sedimentation in the region
  • 2. 2 | P a g e CHINMAY KORGAONKAR Working mechanism The platform is movable which can be adjusted as to contour or inclination and it can be raised and lowered in adjusted position which is accomplished by the use of synchronous motors which can be operated independently for adjusting the platform and simultaneously for adjusting the floor, raising and lowering the adjusted platform. The side walls are constructed in any desired manner but mostly a series of piers is preferred and piers are spaced apart at a suitable distance to define a series of alcoves which house the parts of the platform lifting mechanism The platform consists of multiple parallel transversely extending keel supporting beams and multiple intermediate floor sections. The beams are spaced apart a distance equal to the distance between centres of the alcoves and they are supported at their ends by hoisting mechanism. The web beam has a bracket each of which houses the journals of multiple groove pulley. A cable is passed about this pulley and another pulley supported by brackets on channel beams seated on the top of the pier. The cable has one end anchored to a channel and the other end wounded on a drum mounted on the dock and each cable drum is driven by its independent synchronous motor, The motors at any one beam position can be operated independently of the other motors of the system to wind or unwind the cables on the drums to raise or lower the beam. Fig.2 (Lifting platform)
  • 3. 3 | P a g e CHINMAY KORGAONKAR Because of this arrangement, the several beams of the floor can be raised to different heights so that the beams will lie along any predetermined keel contour or angle, to the end that each beam of the floor will contact a ship's keel simultaneously when all of the beams are raised together by simultaneous operation of all of the synchronous motors. The web beams are joined together to form a floor by means of the intermediate floor sections. These comprise pairs of transversely spaced, longitudinally extending beams held in spaced relation by bridge members. The floor sections are secured to the beams so as to permit the beams to have relative vertical movement, to prevent swaying of beams. Each of the beams carries a trestle or a pair of bilge blocks upon its upper surface, with the blocks of the pair being on opposite sides of the centre of the beam. The trestles can be moved to desirable position no matter what the elevation of the beam may be. This gives the operator the freedom to present the floor to the plan of the keel and hull of an incoming ship When the ship is floated into the slip the platform may be moved upwardly to make precise contact with the ship along the length of the keel to raise the ship without changing the trim position and without imposing undue stress on any part of the system and the hull Lifting platform also includes upper timber decking components supported on the upper surfaces of beams. Additionally, the platform include rail members for supporting a movable hydraulically operated lifting bogie which is used to transfer the vessel from the ship lift platform to the work bay.
  • 4. 4 | P a g e CHINMAY KORGAONKAR To transfer the vessel between the ship lift platform and the berth or reverse, the trestles are lifted up by the hydraulic lifting cylinders of the bogies. The lift cylinders of the bogies are connected to three hydraulic fluid-beds. The vessel will rest on a three-point support with uniform loads for each cylinder within a hydraulic bed. The fluid-bed can also be used during launching or lifting of the vessels. To lift a vessel using fluid bed, the trestles will be positioned on the platform while the bogies remain under the trestles. The bogies are suitable for underwater use. The platform will be lowered and the bogies, in ‘Fluid-Bed’ mode, will go under water. In this case, the trestles rest on the hydraulic cylinders of the bogies. By keeping the hydraulic lifting system in operation during launching or lifting, deformations of the shiplift platform are compensated and the vessels rest on the hydraulic beds with uniform load distributions inside each bed.