SlideShare a Scribd company logo
1 of 71
THE RETURN OF STATISTICALTHE RETURN OF STATISTICAL
PAY FACTORSPAY FACTORS
CalAPA Fall Conference
March 20 - 21, 2019
Ontario, CA
Tony Limas
Granite Construction Inc.
Today’s DiscussionToday’s Discussion
• BackgroundBackground
• Testing and CertificationTesting and Certification
• Mix Design RequirementsMix Design Requirements
• QC & Acceptance Testing (NPF)QC & Acceptance Testing (NPF)
• Quality Control PlanQuality Control Plan
• Statistical Pay Factor RequirementsStatistical Pay Factor Requirements
• Verification TestingVerification Testing
• Dispute ResolutionDispute Resolution
• AcceptanceAcceptance
• QuestionsQuestions
22
BACKGROUNDBACKGROUND
BackgroundBackground
• CT QC/QA Specifications ceased forCT QC/QA Specifications ceased for
Superpave Pilot ProjectsSuperpave Pilot Projects
• Superpave Pilot Projects CompletedSuperpave Pilot Projects Completed
• Ready for Statistical Pay Factor (SPF) PilotReady for Statistical Pay Factor (SPF) Pilot
Projects (1 construction season)Projects (1 construction season)
44
CT Specifications (Old vs New)CT Specifications (Old vs New)
• Old QC/QA SpecsOld QC/QA Specs
• MethodMethod
• Standard ProcessStandard Process
• QC/QA ProcessQC/QA Process
Both Standard and QC could include Method CompactionBoth Standard and QC could include Method Compaction
• New SpecsNew Specs
• SuperPave Specs w/o Statistical Pay Factors (Standard)SuperPave Specs w/o Statistical Pay Factors (Standard)
• SuperPave Specs w Statistical Pay FactorsSuperPave Specs w Statistical Pay Factors
Both could include Method CompactionBoth could include Method Compaction
55
Elements of the “Ideal” SPFElements of the “Ideal” SPF
SpecificationSpecification
• Reproducible Test MethodsReproducible Test Methods
• Well Understood Variability (standardWell Understood Variability (standard
deviation)deviation)
• Existence of Strong Relationships betweenExistence of Strong Relationships between
Tests (Measured Properties) and PavementTests (Measured Properties) and Pavement
PerformancePerformance
7
PWL and Seller’s Risk
S
(n=1)
PWL
Risk
(α)
0.20 5.0 95 5%
7 SH$ %LQGHURQWHQW
4.6 5.0 5.4
8SSHU/ LP LW/ RZHU/ LP LW
Mean
5.0%
2.5%2.5%
47.5%
Target Value + 0.40
NTS
Target Value/Mean
TESTING AND CERTICATI0NTESTING AND CERTICATI0N
Quality Control TestingQuality Control Testing
• QC - Testing performed by Contractor toQC - Testing performed by Contractor to
control product properties and determinecontrol product properties and determine
the quality of the product being producedthe quality of the product being produced
• Non Pay Factor MaterialNon Pay Factor Material
• Pay Factor MaterialPay Factor Material
Acceptance TestingAcceptance Testing
• Testing performed by Engineer toTesting performed by Engineer to
determine properties of the materialdetermine properties of the material
being producedbeing produced
• Optional TestingOptional Testing
• Non Pay Factor Quality CharacteristicsNon Pay Factor Quality Characteristics
Verification TestingVerification Testing
• Testing performed to verify theTesting performed to verify the
contractors QC test results for paymentcontractors QC test results for payment
• Performed by OwnerPerformed by Owner
Dispute Resolution TestingDispute Resolution Testing
• Testing performed by Independent 3Testing performed by Independent 3rdrd
party to resolve difference betweenparty to resolve difference between
contractor QC and owner Verificationcontractor QC and owner Verification
test resultstest results
Materials Tester CertificationMaterials Tester Certification
RequirementsRequirements
Must be Certified to Perform Test for QualityMust be Certified to Perform Test for Quality
Characteristics with Pay FactorsCharacteristics with Pay Factors
• IA CertificationIA Certification
• JTC CertificationJTC Certification
MIX DESIGN REQUIRMENTSMIX DESIGN REQUIRMENTS
Mix Design Requirements Type AMix Design Requirements Type A
• No change from 2018 StandardNo change from 2018 Standard
SpecificationsSpecifications
• Air voidsAir voids
• GyrationsGyrations
• Voids in Mineral AggregateVoids in Mineral Aggregate
• Dust ProportionDust Proportion
• Hamburg Wheel TrackHamburg Wheel Track
• Moisture SusceptibilityMoisture Susceptibility
1515
Mix Design Requirements RHMAMix Design Requirements RHMA
• No Change from 2018 Standard SpecificationsNo Change from 2018 Standard Specifications
• Air voidsAir voids
• GyrationsGyrations
• Voids in Mineral AggregateVoids in Mineral Aggregate
• Dust ProportionDust Proportion
• Hamburg Wheel TrackHamburg Wheel Track
• Moisture SusceptibilityMoisture Susceptibility
1616
Hamburg/TSR Testing RequirementsHamburg/TSR Testing Requirements
• Required for mix verification hot dropRequired for mix verification hot drop
• Required for PSUERequired for PSUE
• Material sampled at PlantMaterial sampled at Plant
• Not required during production beyondNot required during production beyond
PSUEPSUE
1717
QALITY CONTROL andQALITY CONTROL and
ACCEPTANCE TESTINGACCEPTANCE TESTING
Quality Control Non-Pay FactorsQuality Control Non-Pay Factors
• Gradations (except No. 8 and 200Gradations (except No. 8 and 200
sieves)sieves)
• Sand EquivalentSand Equivalent
• Moisture ContentMoisture Content
• Crushed ParticlesCrushed Particles
• Los Angeles RattlerLos Angeles Rattler
1919
Quality Control Non-Pay FactorsQuality Control Non-Pay Factors
• Flat and Elongated ParticlesFlat and Elongated Particles
• Fine Aggregate AngularityFine Aggregate Angularity
• HMA Moisture ContentHMA Moisture Content
• Voids in Mineral AggregateVoids in Mineral Aggregate
• Dust ProportionDust Proportion
2020
Quality Control Non-Pay FactorsQuality Control Non-Pay Factors
• Except for smoothness if 2 consecutive non-Except for smoothness if 2 consecutive non-
pay factor QC test results or any 3 QC testpay factor QC test results or any 3 QC test
results for 1 days production do not complyresults for 1 days production do not comply
with the materials specifications:with the materials specifications:
• Stop HMA ProductionStop HMA Production
• Notify the EngineerNotify the Engineer
• Take Corrective ActionTake Corrective Action
• Demonstrate Compliance Before ResumingDemonstrate Compliance Before Resuming
WorkWork
2121
Quality Control Non-PayQuality Control Non-Pay
FactorsFactors
• Multiple sieves out of complianceMultiple sieves out of compliance
considered 1 failed gradationconsidered 1 failed gradation
• Go – No Go DecisionGo – No Go Decision
• Material not subject rejectionMaterial not subject rejection
• Material not subject to penaltyMaterial not subject to penalty
Acceptance Testing Non-PayAcceptance Testing Non-Pay
FactorFactor
• Optional testing performed by EngineerOptional testing performed by Engineer
to verify compliance with Non-Payto verify compliance with Non-Pay
Factor Quality CharacteristicsFactor Quality Characteristics
Acceptance Testing Non-Pay FactorAcceptance Testing Non-Pay Factor
• Except for smoothness if 2 consecutive non-Except for smoothness if 2 consecutive non-
pay factor QC test results or any 3 QC testpay factor QC test results or any 3 QC test
results for 1 days production do not complyresults for 1 days production do not comply
with the materials specifications:with the materials specifications:
• Notify ContractorNotify Contractor
• Contractor stop HMA ProductionContractor stop HMA Production
• Contractor Take corrective ActionContractor Take corrective Action
• Contractor Demonstrate compliance beforeContractor Demonstrate compliance before
resuming Workresuming Work
2424
Acceptance Testing Non-PayAcceptance Testing Non-Pay
FactorFactor
• Multiple sieves out of compliance considered 1 failedMultiple sieves out of compliance considered 1 failed
gradationgradation
• Engineer will notify Contractor of failing AcceptanceEngineer will notify Contractor of failing Acceptance
TestsTests
• Go No-Go DecisionGo No-Go Decision
• Material not subject rejectionMaterial not subject rejection
• Material not subject to penaltyMaterial not subject to penalty
QUALITY CONTROL PLANQUALITY CONTROL PLAN
ContractoContractor Quality Control Planr Quality Control Plan
• Per Quality Control ManualPer Quality Control Manual
RequirementsRequirements
• Prepared by ContractorPrepared by Contractor
• Approved by EngineerApproved by Engineer
2727
Quality Control PlanQuality Control Plan
• Purpose of PlanPurpose of Plan
• Keep process in controlKeep process in control
• Quickly determine when the process has gone outQuickly determine when the process has gone out
of controlof control
• Planned response to correct deficiencies bringingPlanned response to correct deficiencies bringing
the process back into controlthe process back into control
•
2828
QC Staffing RequirementsQC Staffing Requirements
Field Compaction Requirement QC Staffing Level
Excluding QC Manager (see note
3)
Method Compaction 3 (See note 1)
Density Testing 4 (see Note 2
2929
(1) One HMA inspector at the plant, one at the site of placement, a third(1) One HMA inspector at the plant, one at the site of placement, a third
where the contractor deems necessarywhere the contractor deems necessary
(2) One HMA inspector at the plant, one at the site of placement(2) One HMA inspector at the plant, one at the site of placement
performing density testing, one additional at the site of placement, and aperforming density testing, one additional at the site of placement, and a
forth where the contractor deems necessaryforth where the contractor deems necessary
(3)The contractor must provide a qualified sampler to pull the Engineers(3)The contractor must provide a qualified sampler to pull the Engineers
verification samples of HMA and density cores. The contractor must splitverification samples of HMA and density cores. The contractor must split
the HMA samples into four parts, provide three parts to the Engineer andthe HMA samples into four parts, provide three parts to the Engineer and
keep one. This person may be one of the required staff. The contractorskeep one. This person may be one of the required staff. The contractors
portion may not be used for QC testing.portion may not be used for QC testing.
STATISTICAL PAY FACTORSTATISTICAL PAY FACTOR
REQUIRMENTSREQUIRMENTS
Statistical Pay FactorsStatistical Pay Factors
• 20 Sublots per Lot20 Sublots per Lot
• 750 tons/sublot750 tons/sublot
• 15,000 tons per Lot15,000 tons per Lot
• Maximum Bonus 5%Maximum Bonus 5%
New Lot Required When:New Lot Required When:
• 20 Sublots are completed20 Sublots are completed
• JMF ChangesJMF Changes
• Material source changesMaterial source changes
• Work Suspended (unsatisfactory Performance)Work Suspended (unsatisfactory Performance)
• Production stops for 30 daysProduction stops for 30 days
• Contractor delayContractor delay
• Seasonal work stoppageSeasonal work stoppage
• Phases of work (ramps etc.)Phases of work (ramps etc.)
Type A Quality Characteristic’sType A Quality Characteristic’s
With Pay FactorsWith Pay Factors
Quality Characteristic Test method Tolerance Weight
No. 8 Sieve AASHTO T 27/30 Per Gradation 0.05
No. 200 Sieve AASHTO T 27/30 Per Gradation 0.10
Asphalt Binder Content
AASHTO T 308
(Method A)
± 0.40 0.25
Air Voids Content at Ndesign AASHTO T 269 ± 1.5 0.20
Density of Core (% of max
theoretical density)
AASHTO T 275
(Method A)
AAHTO T 209
(Method A)
92.0 - 96.0 0.40
3333
RHMA Quality Characteristic’sRHMA Quality Characteristic’s
With Pay FactorsWith Pay Factors
Quality Characteristic Test Method Tolerance Weight
No. 8 Sieve AASHTO T 27/30 Per Gradation 0.05
No. 200 Sieve AASHTO T 27/30 Per Gradation 0.10
Asphalt Binder Content
AASHTO T 308
(Method A)
± 0.45 0.25
Air Voids Content at Ndesign AASHTO T 269 ± 1.8 0.20
Density of Core (% of max
theoretical density)
AASHTO T 275
(Method A)
AAHTO T 209
(Method A)
91.0 – 96.0 0.40
3434
QC Sampling and TestingQC Sampling and Testing
• Contractor Obtains Random SamplesContractor Obtains Random Samples
3535
Gradation 1/750 Tons
Binder Content 1/750 Tons
Air Voids 1 /1500 Tons
Relative density 1 core/250 tons (3 cores/750 tons)
QC Sampling and TestingQC Sampling and Testing
Contractor Sampling Locations
• Plant (drum, silo, drag slat)
• Truck (plant, field)
• Windrow (plant or field)
• Behind Paver
• May be different than Verification
sample location
3636
Production Star-Up EvaluationProduction Star-Up Evaluation
(PSUE)(PSUE)
• 750 ton minimum tonnage
• Perform PSUE “light” when PSUE is within
45 days of date on approved (signed) CEM
3513
• If production stops for 30 to 60 days
perform PSUE “light”
• If production stops for 60 days perform full
PSUE
• In all cases, if PSUE fails do not proceed to
production
3737
QC Sampling and TestingQC Sampling and Testing
• Sampling and Testing NotesSampling and Testing Notes
• GradationGradation
• Binder ContentBinder Content
• Air VoidsAir Voids
• Relative densityRelative density
3838
QC Sampling and Testing NotesQC Sampling and Testing Notes
• Gradations
• 1 Gradation test every 750 tons
• Results based on single Gradation test
• Test results reported to whole number
with exception to the No. 200 sieve
• Test results for No. 200 sieve reported
to 0.1
3939
QC Sampling and Testing NotesQC Sampling and Testing Notes
• Binder Content
• 1 Ignition Oven Binder test every 750
tons
• Results based on single test
• Test results reported to 0.01
4040
QC Sampling and Testing NotesQC Sampling and Testing Notes
• Air Voids
• 1 Air Void test every 1500 tons
• Based on average of 3 briquettes and
minimum  2 Gmm (RICE) replicates
• Briquettes and Gmm obtained from one
random sample taken every 1500 tons
• Test results reported to 0.10%
4141
QC Sampling and Testing NotesQC Sampling and Testing Notes
• Relative Density Gauge Testing
• Non Nuclear Gauge allowed
• Correlation to cores not required
4242
QC Sampling and Testing NotesQC Sampling and Testing Notes
• Relative Density Based on
Cores/Gmm
• 1 test every 750 tons
• 1 core/250 tons (3/750 tons)
• 4 inch cores
• Use Average of 3 cores and average of 3
Gmm’s to determine percent relative density
• Test results reported to 0.10
4343
QC Sampling and Testing NotesQC Sampling and Testing Notes
• Relative Density Gmm
Requirements
• Run minimum 3 Gmm on 1st
day of production
• Following 1st
day of production contractor will
run min. 1 Gmm/day and use running average
of 3 most recent Gmm to determine relative
density
4444
QC Test (Pay Factors)QC Test (Pay Factors)
• Contractor enters QC test
results in HMA SPF program to
determine Quality Factor(s)
• Determine individual and
composite Quality Factors
• Submits SPF results to
Engineer daily 4545
QC Test Quality FactorsQC Test Quality Factors
• If composite or individual Quality factor is
less than 0.90 or 0.75 for No. 8 sieve
contractor:
• Stops work
• Notifies the Engineer in writing
• Takes corrective action before resuming
production
• Documents all steps taken on CEM Form
4646
VERIFICATION TESTINGVERIFICATION TESTING
Engineer Verification TestingEngineer Verification Testing
• Engineer Obtains Random SamplesEngineer Obtains Random Samples
4848
Gradation Verification ratio 1:5 (3 sublots/lot min.)Verification ratio 1:5 (3 sublots/lot min.)
Binder Content Verification ratio 1:5 (3 sublots/lot min.)Verification ratio 1:5 (3 sublots/lot min.)
Air Voids Verification ratio 1:5 (3 sublots/lot min.)Verification ratio 1:5 (3 sublots/lot min.)
Relative Density Verification ratio 1:5 (3 sublots/lot min.)Verification ratio 1:5 (3 sublots/lot min.)
Engineer Verification TestingEngineer Verification Testing
• Engineer Sampling locations
• Plant (drum, silo, drag slat)
• Truck (plant or field)
• Windrow (plant or Field)
• Behind Paver
• May be different than QC sample
location
4949
Engineer Verification Testing NotesEngineer Verification Testing Notes
• GradationGradation
• Binder ContentBinder Content
• Air VoidsAir Voids
• Relative densityRelative density
5050
Engineer Verification Testing NotesEngineer Verification Testing Notes
• Gradations
• Results based on single Gradation test
• Test results reported to whole number
with exception to the No. 200 sieve
• Test results for No. 200 sieve reported
to 0.1
5151
Engineer Verification Testing NotesEngineer Verification Testing Notes
• Binder Content
• Results based on single testResults based on single test
• Test results reported to 0.01
5252
Engineer Verification Testing NotesEngineer Verification Testing Notes
• Air Voids
• Based on average of 3 replicate
briquettes and 2 Gmm replicates
• Gmm from random sample taken from
same sublot as briquette material
5353
Engineer Verification Testing NotesEngineer Verification Testing Notes
• Relative Density
• Based on pavement cores and Gmm
• 4 inch cores
• 1 core/250 tons (3/750 tons)
• Use Average of 3 cores and average of
min. 2 replicate Gmm’s to determine
percent Relative Density
• Run Gmm on material from sublot with
verification cores
5454
Verification CriteriaVerification Criteria
Used to Compare QC Data to
Verification Data to verify that
contractors QC test results are
acceptable as a basis of payment
•F-testF-test
•T-testT-test
•Allowable Test Difference (ATD)Allowable Test Difference (ATD)
5555
VerificationVerification
F-testF-test
• A statistical test that is used to determine
whether two populations having normal
distribution have the same variances or
standard deviation
• If F-test is passed use Rule 1 for to determine the
Degrees of Freedom for T-test
• If F-test fails use Rule 2 for to determine the
Degrees of Freedom for T-test
5656
VerificationVerification
T-testT-test
•The t-test is a type of inferential statistic used
to determine if there is significant difference
between the means of two groups of data
indicating that the test results are statically
not from the same population
5757
VerificationVerification
Allowable Test Differences (ATD)
When the contractors data is not verified by the
T-test and the QC and verification means are
within the following allowable differences the
material is considered to be verified
5858
Item ATD
Gradation ≤ 1.0 percent
Binder Content ≤ 0.1 percent
Air Voids ≤ 0.2 percent
Relative Density ≤ 0.5 percent
Verification TestingVerification Testing
• Engineer provides Verification Test
Results to Contractor within 5
Business Days of Completion of
Lot?
5959
Verification TestingVerification Testing
• If material is not verified isolate
material related to non-Verification
– Reject Material
– Terminate Lot
• Recalculate pay factor for
remaining sublots using QC Data
without QC test data representing
rejected material 6060
Verification TestingVerification Testing
• Prior to resuming production on
next Lot:
• Take corrective Action
• Demonstrate compliance
6161
DIPUTE RESOLUTIONDIPUTE RESOLUTION
Dispute ResolutionDispute Resolution
• Notify Engineer and Submit copies of
paperwork including work sheets used
to determine the disputed test results
within 3 business days of receiving the
Engineers test results
6363
6. Dispute Resolution6. Dispute Resolution
• Mix Design Verification Hot Drop
• Production Start-up Evaluation
(PSUE)
• Production
• Verification Testing
• Acceptance Testing 6464
Dispute Resolution ProcessDispute Resolution Process
• Review of Sampling Procedures
• Review Test Report and Calculations
• Witness Tester and Laboratory
Operations
• Contractors Testing
• Engineers Testing
• Independent Third Party performs
Testing using Split Referee Samples
6565
Dispute Resolution TestingDispute Resolution Testing
• Use Split Samples from Verification
samples
• 4 Way Split Samples
• 1 sample Engineer Verification
• 1 Sample Contractor (Information
Only)
• 2 Samples Dispute Resolution
• Retained by Engineer
• Contractor assist with all sampling
6666
Dispute Resolution GradationDispute Resolution Gradation
• If No.8 or No. 200 sieves are
not verified both sieves are
evaluated for dispute testing
6767
Dispute CoresDispute Cores
• In addition to Verification cores:
• Take 3 additional cores for each 250
tons
• 2 cores for Engineer
• 1 core for Contractor (information
only)
• Core locations aligned longitudinally
1-2 feet apart
6868
ACCEPTANCEACCEPTANCE
Acceptance (Pay Factor Material)Acceptance (Pay Factor Material)
• Contractors Sampling, Inspection and Test ResultsContractors Sampling, Inspection and Test Results
CompleteComplete
• QC Test Results VerifiedQC Test Results Verified
• Engineer Visually Inspects PavementEngineer Visually Inspects Pavement
• Composite Pay Factor  0.90Composite Pay Factor  0.90
• Individual Pay Factors  90 or 0.75Individual Pay Factors  90 or 0.75 7070
QUESTIONS?QUESTIONS?

More Related Content

Similar to Statistical Pay Factors in California highway construction

QA,QC INSPECTOR ANANDA RAM PRASATH.V RESUME
QA,QC INSPECTOR ANANDA RAM PRASATH.V RESUMEQA,QC INSPECTOR ANANDA RAM PRASATH.V RESUME
QA,QC INSPECTOR ANANDA RAM PRASATH.V RESUMEAnanda Ram Prasath
 
QA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrenceQA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrenceSimon Lawrence
 
Saivs Sand Casting & Machining
Saivs Sand Casting & MachiningSaivs Sand Casting & Machining
Saivs Sand Casting & Machininghuhangcheng
 
Quality management system system
Quality management system systemQuality management system system
Quality management system systemAbhijith Parashar
 
GMP Training: Process validation
GMP Training: Process validation GMP Training: Process validation
GMP Training: Process validation Dr. Amsavel A
 
RESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORRESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORMohsin Iqubal
 
AS Brochure Warehouse Inspection 2016
AS Brochure Warehouse Inspection 2016AS Brochure Warehouse Inspection 2016
AS Brochure Warehouse Inspection 2016AS International
 
Solar Webinar PPT.pptx Renewable green energyenergy
Solar Webinar PPT.pptx Renewable green energyenergySolar Webinar PPT.pptx Renewable green energyenergy
Solar Webinar PPT.pptx Renewable green energyenergykrishnamohan286280
 
Kevin Alba-Resume cv
Kevin Alba-Resume cvKevin Alba-Resume cv
Kevin Alba-Resume cvKevin Alba
 
SUPPLIER QUALIFICATION CASE STUDY
SUPPLIER QUALIFICATION CASE STUDYSUPPLIER QUALIFICATION CASE STUDY
SUPPLIER QUALIFICATION CASE STUDYBuen Guido
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction Thanigaivel Asokan
 
Validation of pharmaceutical industries
Validation of pharmaceutical industriesValidation of pharmaceutical industries
Validation of pharmaceutical industriesPrima Ramadhani
 

Similar to Statistical Pay Factors in California highway construction (20)

05 qa
05 qa05 qa
05 qa
 
ppt1.pdf
ppt1.pdfppt1.pdf
ppt1.pdf
 
QA,QC INSPECTOR ANANDA RAM PRASATH.V RESUME
QA,QC INSPECTOR ANANDA RAM PRASATH.V RESUMEQA,QC INSPECTOR ANANDA RAM PRASATH.V RESUME
QA,QC INSPECTOR ANANDA RAM PRASATH.V RESUME
 
Commercial Grade Item Dedication
Commercial Grade Item DedicationCommercial Grade Item Dedication
Commercial Grade Item Dedication
 
Nagarajan Saravanan
Nagarajan SaravananNagarajan Saravanan
Nagarajan Saravanan
 
QA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrenceQA/QC Engineer - simon lawrence
QA/QC Engineer - simon lawrence
 
Saivs Sand Casting & Machining
Saivs Sand Casting & MachiningSaivs Sand Casting & Machining
Saivs Sand Casting & Machining
 
Quality management system system
Quality management system systemQuality management system system
Quality management system system
 
GMP Training: Process validation
GMP Training: Process validation GMP Training: Process validation
GMP Training: Process validation
 
RESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTORRESUME FOR QC INSPECTOR
RESUME FOR QC INSPECTOR
 
AS Brochure Warehouse Inspection 2016
AS Brochure Warehouse Inspection 2016AS Brochure Warehouse Inspection 2016
AS Brochure Warehouse Inspection 2016
 
Quality r (2) (2)
Quality r (2) (2)Quality r (2) (2)
Quality r (2) (2)
 
Quality r (2) (2)
Quality r (2) (2)Quality r (2) (2)
Quality r (2) (2)
 
Solar Webinar PPT.pptx Renewable green energyenergy
Solar Webinar PPT.pptx Renewable green energyenergySolar Webinar PPT.pptx Renewable green energyenergy
Solar Webinar PPT.pptx Renewable green energyenergy
 
Ikram _CV.
Ikram _CV.Ikram _CV.
Ikram _CV.
 
Resume
ResumeResume
Resume
 
Kevin Alba-Resume cv
Kevin Alba-Resume cvKevin Alba-Resume cv
Kevin Alba-Resume cv
 
SUPPLIER QUALIFICATION CASE STUDY
SUPPLIER QUALIFICATION CASE STUDYSUPPLIER QUALIFICATION CASE STUDY
SUPPLIER QUALIFICATION CASE STUDY
 
Quality control in construction
Quality control in construction Quality control in construction
Quality control in construction
 
Validation of pharmaceutical industries
Validation of pharmaceutical industriesValidation of pharmaceutical industries
Validation of pharmaceutical industries
 

More from California Asphalt Pavement Association

National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...California Asphalt Pavement Association
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...California Asphalt Pavement Association
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024California Asphalt Pavement Association
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansCalifornia Asphalt Pavement Association
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolCalifornia Asphalt Pavement Association
 

More from California Asphalt Pavement Association (20)

Reducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industryReducing carbon footprint in the asphalt pavement industry
Reducing carbon footprint in the asphalt pavement industry
 
Industry perspective on cold in-place recycling
Industry perspective on cold in-place recyclingIndustry perspective on cold in-place recycling
Industry perspective on cold in-place recycling
 
UCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologiesUCPRC perspective on the use of in-place asphalt recycling technologies
UCPRC perspective on the use of in-place asphalt recycling technologies
 
Caltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavementsCaltrans view on recycling of in-place asphalt pavements
Caltrans view on recycling of in-place asphalt pavements
 
Update on the latest research with regard to RAP
Update on the latest research with regard to RAPUpdate on the latest research with regard to RAP
Update on the latest research with regard to RAP
 
Pavement quality focus for local agencies in California
Pavement quality focus for local agencies in CaliforniaPavement quality focus for local agencies in California
Pavement quality focus for local agencies in California
 
National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...National perspective on asphalt technology and trends from the Asphalt Paveme...
National perspective on asphalt technology and trends from the Asphalt Paveme...
 
Utilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixesUtilizing reclaimed plastics in asphalt pavement mixes
Utilizing reclaimed plastics in asphalt pavement mixes
 
Pavement Maintenance tools and technology update
Pavement Maintenance tools and technology updatePavement Maintenance tools and technology update
Pavement Maintenance tools and technology update
 
Presentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiativePresentation by Caltrans on the department's eTicketing initiative
Presentation by Caltrans on the department's eTicketing initiative
 
Update on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industryUpdate on eTicketing technologies for the asphalt pavement industry
Update on eTicketing technologies for the asphalt pavement industry
 
Asphalt industry EPD benchmarking update 2024
Asphalt industry EPD benchmarking update  2024Asphalt industry EPD benchmarking update  2024
Asphalt industry EPD benchmarking update 2024
 
Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024Women of Asphalt California Branch update 2024
Women of Asphalt California Branch update 2024
 
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
CalAPA Spring Asphalt Pavement Conference presentation on the City & County P...
 
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial IntelligenceCalAPA Spring Conference 2024 presentation on Artificial Intelligence
CalAPA Spring Conference 2024 presentation on Artificial Intelligence
 
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
Caltrans District 8 Update for the CalAPA Spring Asphalt Conference 2024
 
Joint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials techniciansJoint Training & Certification Program for construction materials technicians
Joint Training & Certification Program for construction materials technicians
 
EPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt PlantEPD Pointers at the Asphalt Plant
EPD Pointers at the Asphalt Plant
 
EPD Benchmarks and lessons learned
EPD Benchmarks and lessons learnedEPD Benchmarks and lessons learned
EPD Benchmarks and lessons learned
 
National perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD toolNational perspective on Environmental Product Declarations & the NAPA EPD tool
National perspective on Environmental Product Declarations & the NAPA EPD tool
 

Recently uploaded

Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineeringmalavadedarshan25
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSKurinjimalarL3
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escortsranjana rawat
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx959SahilShah
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
9953056974 Call Girls In South Ex, Escorts (Delhi) NCR.pdf
 
Internship report on mechanical engineering
Internship report on mechanical engineeringInternship report on mechanical engineering
Internship report on mechanical engineering
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICSAPPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
APPLICATIONS-AC/DC DRIVES-OPERATING CHARACTERISTICS
 
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
★ CALL US 9953330565 ( HOT Young Call Girls In Badarpur delhi NCR
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
(MEERA) Dapodi Call Girls Just Call 7001035870 [ Cash on Delivery ] Pune Escorts
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Application of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptxApplication of Residue Theorem to evaluate real integrations.pptx
Application of Residue Theorem to evaluate real integrations.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

Statistical Pay Factors in California highway construction

  • 1. THE RETURN OF STATISTICALTHE RETURN OF STATISTICAL PAY FACTORSPAY FACTORS CalAPA Fall Conference March 20 - 21, 2019 Ontario, CA Tony Limas Granite Construction Inc.
  • 2. Today’s DiscussionToday’s Discussion • BackgroundBackground • Testing and CertificationTesting and Certification • Mix Design RequirementsMix Design Requirements • QC & Acceptance Testing (NPF)QC & Acceptance Testing (NPF) • Quality Control PlanQuality Control Plan • Statistical Pay Factor RequirementsStatistical Pay Factor Requirements • Verification TestingVerification Testing • Dispute ResolutionDispute Resolution • AcceptanceAcceptance • QuestionsQuestions 22
  • 4. BackgroundBackground • CT QC/QA Specifications ceased forCT QC/QA Specifications ceased for Superpave Pilot ProjectsSuperpave Pilot Projects • Superpave Pilot Projects CompletedSuperpave Pilot Projects Completed • Ready for Statistical Pay Factor (SPF) PilotReady for Statistical Pay Factor (SPF) Pilot Projects (1 construction season)Projects (1 construction season) 44
  • 5. CT Specifications (Old vs New)CT Specifications (Old vs New) • Old QC/QA SpecsOld QC/QA Specs • MethodMethod • Standard ProcessStandard Process • QC/QA ProcessQC/QA Process Both Standard and QC could include Method CompactionBoth Standard and QC could include Method Compaction • New SpecsNew Specs • SuperPave Specs w/o Statistical Pay Factors (Standard)SuperPave Specs w/o Statistical Pay Factors (Standard) • SuperPave Specs w Statistical Pay FactorsSuperPave Specs w Statistical Pay Factors Both could include Method CompactionBoth could include Method Compaction 55
  • 6. Elements of the “Ideal” SPFElements of the “Ideal” SPF SpecificationSpecification • Reproducible Test MethodsReproducible Test Methods • Well Understood Variability (standardWell Understood Variability (standard deviation)deviation) • Existence of Strong Relationships betweenExistence of Strong Relationships between Tests (Measured Properties) and PavementTests (Measured Properties) and Pavement PerformancePerformance
  • 7. 7 PWL and Seller’s Risk S (n=1) PWL Risk (α) 0.20 5.0 95 5% 7 SH$ %LQGHURQWHQW 4.6 5.0 5.4 8SSHU/ LP LW/ RZHU/ LP LW Mean 5.0% 2.5%2.5% 47.5% Target Value + 0.40 NTS Target Value/Mean
  • 9. Quality Control TestingQuality Control Testing • QC - Testing performed by Contractor toQC - Testing performed by Contractor to control product properties and determinecontrol product properties and determine the quality of the product being producedthe quality of the product being produced • Non Pay Factor MaterialNon Pay Factor Material • Pay Factor MaterialPay Factor Material
  • 10. Acceptance TestingAcceptance Testing • Testing performed by Engineer toTesting performed by Engineer to determine properties of the materialdetermine properties of the material being producedbeing produced • Optional TestingOptional Testing • Non Pay Factor Quality CharacteristicsNon Pay Factor Quality Characteristics
  • 11. Verification TestingVerification Testing • Testing performed to verify theTesting performed to verify the contractors QC test results for paymentcontractors QC test results for payment • Performed by OwnerPerformed by Owner
  • 12. Dispute Resolution TestingDispute Resolution Testing • Testing performed by Independent 3Testing performed by Independent 3rdrd party to resolve difference betweenparty to resolve difference between contractor QC and owner Verificationcontractor QC and owner Verification test resultstest results
  • 13. Materials Tester CertificationMaterials Tester Certification RequirementsRequirements Must be Certified to Perform Test for QualityMust be Certified to Perform Test for Quality Characteristics with Pay FactorsCharacteristics with Pay Factors • IA CertificationIA Certification • JTC CertificationJTC Certification
  • 14. MIX DESIGN REQUIRMENTSMIX DESIGN REQUIRMENTS
  • 15. Mix Design Requirements Type AMix Design Requirements Type A • No change from 2018 StandardNo change from 2018 Standard SpecificationsSpecifications • Air voidsAir voids • GyrationsGyrations • Voids in Mineral AggregateVoids in Mineral Aggregate • Dust ProportionDust Proportion • Hamburg Wheel TrackHamburg Wheel Track • Moisture SusceptibilityMoisture Susceptibility 1515
  • 16. Mix Design Requirements RHMAMix Design Requirements RHMA • No Change from 2018 Standard SpecificationsNo Change from 2018 Standard Specifications • Air voidsAir voids • GyrationsGyrations • Voids in Mineral AggregateVoids in Mineral Aggregate • Dust ProportionDust Proportion • Hamburg Wheel TrackHamburg Wheel Track • Moisture SusceptibilityMoisture Susceptibility 1616
  • 17. Hamburg/TSR Testing RequirementsHamburg/TSR Testing Requirements • Required for mix verification hot dropRequired for mix verification hot drop • Required for PSUERequired for PSUE • Material sampled at PlantMaterial sampled at Plant • Not required during production beyondNot required during production beyond PSUEPSUE 1717
  • 18. QALITY CONTROL andQALITY CONTROL and ACCEPTANCE TESTINGACCEPTANCE TESTING
  • 19. Quality Control Non-Pay FactorsQuality Control Non-Pay Factors • Gradations (except No. 8 and 200Gradations (except No. 8 and 200 sieves)sieves) • Sand EquivalentSand Equivalent • Moisture ContentMoisture Content • Crushed ParticlesCrushed Particles • Los Angeles RattlerLos Angeles Rattler 1919
  • 20. Quality Control Non-Pay FactorsQuality Control Non-Pay Factors • Flat and Elongated ParticlesFlat and Elongated Particles • Fine Aggregate AngularityFine Aggregate Angularity • HMA Moisture ContentHMA Moisture Content • Voids in Mineral AggregateVoids in Mineral Aggregate • Dust ProportionDust Proportion 2020
  • 21. Quality Control Non-Pay FactorsQuality Control Non-Pay Factors • Except for smoothness if 2 consecutive non-Except for smoothness if 2 consecutive non- pay factor QC test results or any 3 QC testpay factor QC test results or any 3 QC test results for 1 days production do not complyresults for 1 days production do not comply with the materials specifications:with the materials specifications: • Stop HMA ProductionStop HMA Production • Notify the EngineerNotify the Engineer • Take Corrective ActionTake Corrective Action • Demonstrate Compliance Before ResumingDemonstrate Compliance Before Resuming WorkWork 2121
  • 22. Quality Control Non-PayQuality Control Non-Pay FactorsFactors • Multiple sieves out of complianceMultiple sieves out of compliance considered 1 failed gradationconsidered 1 failed gradation • Go – No Go DecisionGo – No Go Decision • Material not subject rejectionMaterial not subject rejection • Material not subject to penaltyMaterial not subject to penalty
  • 23. Acceptance Testing Non-PayAcceptance Testing Non-Pay FactorFactor • Optional testing performed by EngineerOptional testing performed by Engineer to verify compliance with Non-Payto verify compliance with Non-Pay Factor Quality CharacteristicsFactor Quality Characteristics
  • 24. Acceptance Testing Non-Pay FactorAcceptance Testing Non-Pay Factor • Except for smoothness if 2 consecutive non-Except for smoothness if 2 consecutive non- pay factor QC test results or any 3 QC testpay factor QC test results or any 3 QC test results for 1 days production do not complyresults for 1 days production do not comply with the materials specifications:with the materials specifications: • Notify ContractorNotify Contractor • Contractor stop HMA ProductionContractor stop HMA Production • Contractor Take corrective ActionContractor Take corrective Action • Contractor Demonstrate compliance beforeContractor Demonstrate compliance before resuming Workresuming Work 2424
  • 25. Acceptance Testing Non-PayAcceptance Testing Non-Pay FactorFactor • Multiple sieves out of compliance considered 1 failedMultiple sieves out of compliance considered 1 failed gradationgradation • Engineer will notify Contractor of failing AcceptanceEngineer will notify Contractor of failing Acceptance TestsTests • Go No-Go DecisionGo No-Go Decision • Material not subject rejectionMaterial not subject rejection • Material not subject to penaltyMaterial not subject to penalty
  • 27. ContractoContractor Quality Control Planr Quality Control Plan • Per Quality Control ManualPer Quality Control Manual RequirementsRequirements • Prepared by ContractorPrepared by Contractor • Approved by EngineerApproved by Engineer 2727
  • 28. Quality Control PlanQuality Control Plan • Purpose of PlanPurpose of Plan • Keep process in controlKeep process in control • Quickly determine when the process has gone outQuickly determine when the process has gone out of controlof control • Planned response to correct deficiencies bringingPlanned response to correct deficiencies bringing the process back into controlthe process back into control • 2828
  • 29. QC Staffing RequirementsQC Staffing Requirements Field Compaction Requirement QC Staffing Level Excluding QC Manager (see note 3) Method Compaction 3 (See note 1) Density Testing 4 (see Note 2 2929 (1) One HMA inspector at the plant, one at the site of placement, a third(1) One HMA inspector at the plant, one at the site of placement, a third where the contractor deems necessarywhere the contractor deems necessary (2) One HMA inspector at the plant, one at the site of placement(2) One HMA inspector at the plant, one at the site of placement performing density testing, one additional at the site of placement, and aperforming density testing, one additional at the site of placement, and a forth where the contractor deems necessaryforth where the contractor deems necessary (3)The contractor must provide a qualified sampler to pull the Engineers(3)The contractor must provide a qualified sampler to pull the Engineers verification samples of HMA and density cores. The contractor must splitverification samples of HMA and density cores. The contractor must split the HMA samples into four parts, provide three parts to the Engineer andthe HMA samples into four parts, provide three parts to the Engineer and keep one. This person may be one of the required staff. The contractorskeep one. This person may be one of the required staff. The contractors portion may not be used for QC testing.portion may not be used for QC testing.
  • 30. STATISTICAL PAY FACTORSTATISTICAL PAY FACTOR REQUIRMENTSREQUIRMENTS
  • 31. Statistical Pay FactorsStatistical Pay Factors • 20 Sublots per Lot20 Sublots per Lot • 750 tons/sublot750 tons/sublot • 15,000 tons per Lot15,000 tons per Lot • Maximum Bonus 5%Maximum Bonus 5%
  • 32. New Lot Required When:New Lot Required When: • 20 Sublots are completed20 Sublots are completed • JMF ChangesJMF Changes • Material source changesMaterial source changes • Work Suspended (unsatisfactory Performance)Work Suspended (unsatisfactory Performance) • Production stops for 30 daysProduction stops for 30 days • Contractor delayContractor delay • Seasonal work stoppageSeasonal work stoppage • Phases of work (ramps etc.)Phases of work (ramps etc.)
  • 33. Type A Quality Characteristic’sType A Quality Characteristic’s With Pay FactorsWith Pay Factors Quality Characteristic Test method Tolerance Weight No. 8 Sieve AASHTO T 27/30 Per Gradation 0.05 No. 200 Sieve AASHTO T 27/30 Per Gradation 0.10 Asphalt Binder Content AASHTO T 308 (Method A) ± 0.40 0.25 Air Voids Content at Ndesign AASHTO T 269 ± 1.5 0.20 Density of Core (% of max theoretical density) AASHTO T 275 (Method A) AAHTO T 209 (Method A) 92.0 - 96.0 0.40 3333
  • 34. RHMA Quality Characteristic’sRHMA Quality Characteristic’s With Pay FactorsWith Pay Factors Quality Characteristic Test Method Tolerance Weight No. 8 Sieve AASHTO T 27/30 Per Gradation 0.05 No. 200 Sieve AASHTO T 27/30 Per Gradation 0.10 Asphalt Binder Content AASHTO T 308 (Method A) ± 0.45 0.25 Air Voids Content at Ndesign AASHTO T 269 ± 1.8 0.20 Density of Core (% of max theoretical density) AASHTO T 275 (Method A) AAHTO T 209 (Method A) 91.0 – 96.0 0.40 3434
  • 35. QC Sampling and TestingQC Sampling and Testing • Contractor Obtains Random SamplesContractor Obtains Random Samples 3535 Gradation 1/750 Tons Binder Content 1/750 Tons Air Voids 1 /1500 Tons Relative density 1 core/250 tons (3 cores/750 tons)
  • 36. QC Sampling and TestingQC Sampling and Testing Contractor Sampling Locations • Plant (drum, silo, drag slat) • Truck (plant, field) • Windrow (plant or field) • Behind Paver • May be different than Verification sample location 3636
  • 37. Production Star-Up EvaluationProduction Star-Up Evaluation (PSUE)(PSUE) • 750 ton minimum tonnage • Perform PSUE “light” when PSUE is within 45 days of date on approved (signed) CEM 3513 • If production stops for 30 to 60 days perform PSUE “light” • If production stops for 60 days perform full PSUE • In all cases, if PSUE fails do not proceed to production 3737
  • 38. QC Sampling and TestingQC Sampling and Testing • Sampling and Testing NotesSampling and Testing Notes • GradationGradation • Binder ContentBinder Content • Air VoidsAir Voids • Relative densityRelative density 3838
  • 39. QC Sampling and Testing NotesQC Sampling and Testing Notes • Gradations • 1 Gradation test every 750 tons • Results based on single Gradation test • Test results reported to whole number with exception to the No. 200 sieve • Test results for No. 200 sieve reported to 0.1 3939
  • 40. QC Sampling and Testing NotesQC Sampling and Testing Notes • Binder Content • 1 Ignition Oven Binder test every 750 tons • Results based on single test • Test results reported to 0.01 4040
  • 41. QC Sampling and Testing NotesQC Sampling and Testing Notes • Air Voids • 1 Air Void test every 1500 tons • Based on average of 3 briquettes and minimum 2 Gmm (RICE) replicates • Briquettes and Gmm obtained from one random sample taken every 1500 tons • Test results reported to 0.10% 4141
  • 42. QC Sampling and Testing NotesQC Sampling and Testing Notes • Relative Density Gauge Testing • Non Nuclear Gauge allowed • Correlation to cores not required 4242
  • 43. QC Sampling and Testing NotesQC Sampling and Testing Notes • Relative Density Based on Cores/Gmm • 1 test every 750 tons • 1 core/250 tons (3/750 tons) • 4 inch cores • Use Average of 3 cores and average of 3 Gmm’s to determine percent relative density • Test results reported to 0.10 4343
  • 44. QC Sampling and Testing NotesQC Sampling and Testing Notes • Relative Density Gmm Requirements • Run minimum 3 Gmm on 1st day of production • Following 1st day of production contractor will run min. 1 Gmm/day and use running average of 3 most recent Gmm to determine relative density 4444
  • 45. QC Test (Pay Factors)QC Test (Pay Factors) • Contractor enters QC test results in HMA SPF program to determine Quality Factor(s) • Determine individual and composite Quality Factors • Submits SPF results to Engineer daily 4545
  • 46. QC Test Quality FactorsQC Test Quality Factors • If composite or individual Quality factor is less than 0.90 or 0.75 for No. 8 sieve contractor: • Stops work • Notifies the Engineer in writing • Takes corrective action before resuming production • Documents all steps taken on CEM Form 4646
  • 48. Engineer Verification TestingEngineer Verification Testing • Engineer Obtains Random SamplesEngineer Obtains Random Samples 4848 Gradation Verification ratio 1:5 (3 sublots/lot min.)Verification ratio 1:5 (3 sublots/lot min.) Binder Content Verification ratio 1:5 (3 sublots/lot min.)Verification ratio 1:5 (3 sublots/lot min.) Air Voids Verification ratio 1:5 (3 sublots/lot min.)Verification ratio 1:5 (3 sublots/lot min.) Relative Density Verification ratio 1:5 (3 sublots/lot min.)Verification ratio 1:5 (3 sublots/lot min.)
  • 49. Engineer Verification TestingEngineer Verification Testing • Engineer Sampling locations • Plant (drum, silo, drag slat) • Truck (plant or field) • Windrow (plant or Field) • Behind Paver • May be different than QC sample location 4949
  • 50. Engineer Verification Testing NotesEngineer Verification Testing Notes • GradationGradation • Binder ContentBinder Content • Air VoidsAir Voids • Relative densityRelative density 5050
  • 51. Engineer Verification Testing NotesEngineer Verification Testing Notes • Gradations • Results based on single Gradation test • Test results reported to whole number with exception to the No. 200 sieve • Test results for No. 200 sieve reported to 0.1 5151
  • 52. Engineer Verification Testing NotesEngineer Verification Testing Notes • Binder Content • Results based on single testResults based on single test • Test results reported to 0.01 5252
  • 53. Engineer Verification Testing NotesEngineer Verification Testing Notes • Air Voids • Based on average of 3 replicate briquettes and 2 Gmm replicates • Gmm from random sample taken from same sublot as briquette material 5353
  • 54. Engineer Verification Testing NotesEngineer Verification Testing Notes • Relative Density • Based on pavement cores and Gmm • 4 inch cores • 1 core/250 tons (3/750 tons) • Use Average of 3 cores and average of min. 2 replicate Gmm’s to determine percent Relative Density • Run Gmm on material from sublot with verification cores 5454
  • 55. Verification CriteriaVerification Criteria Used to Compare QC Data to Verification Data to verify that contractors QC test results are acceptable as a basis of payment •F-testF-test •T-testT-test •Allowable Test Difference (ATD)Allowable Test Difference (ATD) 5555
  • 56. VerificationVerification F-testF-test • A statistical test that is used to determine whether two populations having normal distribution have the same variances or standard deviation • If F-test is passed use Rule 1 for to determine the Degrees of Freedom for T-test • If F-test fails use Rule 2 for to determine the Degrees of Freedom for T-test 5656
  • 57. VerificationVerification T-testT-test •The t-test is a type of inferential statistic used to determine if there is significant difference between the means of two groups of data indicating that the test results are statically not from the same population 5757
  • 58. VerificationVerification Allowable Test Differences (ATD) When the contractors data is not verified by the T-test and the QC and verification means are within the following allowable differences the material is considered to be verified 5858 Item ATD Gradation ≤ 1.0 percent Binder Content ≤ 0.1 percent Air Voids ≤ 0.2 percent Relative Density ≤ 0.5 percent
  • 59. Verification TestingVerification Testing • Engineer provides Verification Test Results to Contractor within 5 Business Days of Completion of Lot? 5959
  • 60. Verification TestingVerification Testing • If material is not verified isolate material related to non-Verification – Reject Material – Terminate Lot • Recalculate pay factor for remaining sublots using QC Data without QC test data representing rejected material 6060
  • 61. Verification TestingVerification Testing • Prior to resuming production on next Lot: • Take corrective Action • Demonstrate compliance 6161
  • 63. Dispute ResolutionDispute Resolution • Notify Engineer and Submit copies of paperwork including work sheets used to determine the disputed test results within 3 business days of receiving the Engineers test results 6363
  • 64. 6. Dispute Resolution6. Dispute Resolution • Mix Design Verification Hot Drop • Production Start-up Evaluation (PSUE) • Production • Verification Testing • Acceptance Testing 6464
  • 65. Dispute Resolution ProcessDispute Resolution Process • Review of Sampling Procedures • Review Test Report and Calculations • Witness Tester and Laboratory Operations • Contractors Testing • Engineers Testing • Independent Third Party performs Testing using Split Referee Samples 6565
  • 66. Dispute Resolution TestingDispute Resolution Testing • Use Split Samples from Verification samples • 4 Way Split Samples • 1 sample Engineer Verification • 1 Sample Contractor (Information Only) • 2 Samples Dispute Resolution • Retained by Engineer • Contractor assist with all sampling 6666
  • 67. Dispute Resolution GradationDispute Resolution Gradation • If No.8 or No. 200 sieves are not verified both sieves are evaluated for dispute testing 6767
  • 68. Dispute CoresDispute Cores • In addition to Verification cores: • Take 3 additional cores for each 250 tons • 2 cores for Engineer • 1 core for Contractor (information only) • Core locations aligned longitudinally 1-2 feet apart 6868
  • 70. Acceptance (Pay Factor Material)Acceptance (Pay Factor Material) • Contractors Sampling, Inspection and Test ResultsContractors Sampling, Inspection and Test Results CompleteComplete • QC Test Results VerifiedQC Test Results Verified • Engineer Visually Inspects PavementEngineer Visually Inspects Pavement • Composite Pay Factor 0.90Composite Pay Factor 0.90 • Individual Pay Factors 90 or 0.75Individual Pay Factors 90 or 0.75 7070