REVERSE MORRIS TRUST
RATEPAYER VALUE
VS.
SHAREHOLDER GAIN
A Review of The Failed Entergy – ITC Transaction
March 18, 2014
NARUC Accounting and Finance Meeting
Victor Prep, P.E. & Byron Watson, CFA
© 2014, Energy & Resource Consulting Group, LLC
Denver, Colorado
www.ergconsulting.com
INTRODUCTION
• Victor Prep, P.E. – Executive Consultant at ERG
– BSME from OU, MBA from Wharton, Registered P.E. in PA, CO, and LA,
Retired Nuclear Submarine Naval Officer
• Byron Watson, CFA – Senior Consultant at ERG
– BSEE from SMU, MBA in Finance from Emory University, Chartered
Financial Analyst (CFA®)
• The Council of the City of New Orleans Exercises Primary Retail
Jurisdiction Over two of Entergy Corporation Inc.’s (Entergy)
Operating Subsidiaries in Orleans Parish, Louisiana
– Entergy New Orleans, Inc. (ENO)
– Entergy Louisiana, LLC (ELL)
• Members of ERG Serve as Regulatory Advisors to the Council of the
City of New Orleans
– Directly Involved with the Entergy - ITC Transaction at Both the Local and
FERC Level
© 2014, Energy & Resource Consulting Group, LLC 2
ITC TRANSACTION OVERVIEW
• The Transaction was a Proposed Entergy Divestiture/Spin-off
of its Six Operating Companies’ Transmission Assets & a
Merger of the Spun-off Assets with International Transmission
Company, Inc. of Novi, Michigan (ITC)
• The Transaction used a Merger & Acquisition (M&A)
Technique Called a Reverse Morris Trust (RMT).
• The Proposed Transaction was the First Attempt to Use the
RMT in Divesting Assets Within the US Electric and Gas Utility
Industry.
3© 2014, Energy & Resource Consulting Group, LLC
SUMMARY OF REGULATORY
CONCERNS
• FERC Regulatory Construct Increases Retail Revenue Requirement
• Loss of Jurisdictional Control by State Regulators of Transmission
Ratemaking & Oversight of Transmission Function
– Only Retail CCN Approval Preserved
– Section 206 Rate Challenge Only
• Transfer of Risk from Entergy and ITC Shareholders to Retail Ratepayers
– FERC Forward Looking FRP Process
• Value and Ownership of Gains Monetized by Transaction
– Ratepayers versus Shareholders
• Lack of Demonstrable Quantifiable Ratepayer Benefits
• Major Storm Restoration Concerns
• Transfer of Intellectual Capital
• Experience of ITC in Previous Acquisitions
• Shareholder Gain at the Expense of Ratepayers
4© 2014, Energy & Resource Consulting Group, LLC
THE PROPOSED TRANSACTION
5© 2014, Energy & Resource Consulting Group, LLC
PARTIES TO THE TRANSACTION
• Entergy Corporation
– Six Vertically Structured Operating Companies
• ENO, ELL, Entergy Gulf States, LLC, Entergy Texas, Inc., Entergy Mississippi, Inc.
& Entergy Arkansas, Inc.
– Four Mid-South States
• Arkansas, Louisiana, Mississippi & Texas
– Five Retail Jurisdictions
• Arkansas, Louisiana, Mississippi, New Orleans & Texas
• ITC Holdings Corp. – An Independent Transmission Focused
Company
– Created in 2003 Through Predecessor (Formally DTE Energy Transmission)
– Transmission Service in Seven Midwestern States Through Subsidiaries
• ITC Transmission, ITC Midwest, ITC Great Plains & Michigan Electric
Transmission Company
6© 2014, Energy & Resource Consulting Group, LLC
STATED RATIONALE
FOR THE TRANSACTION
7
• Improved Network
Reliability
• Increased Investment in
Transmission Network
(Reduced Costs Through
Less Congestion)
• Improved O&M Efficiency
• Singular Focus on
Transmission
ITC
• Enhanced Financial
Flexibility
– Benefit to Other Ongoing
Required Investments
– Better Access to Capital
– Credit Quality Protection
• Improved Earnings and
Dividend Growth
ENTERGY
© 2014, Energy & Resource Consulting Group, LLC
UNSTATED RATIONALE
• Entergy’s Concerns with an Ongoing DOJ Anti-Trust
Investigation Regarding Operation of Its Transmission System
• Creation of Enhanced Value for Entergy Shareholders
– Failed Attempt to Divest Wholesale Nuclear Assets
• Offload Significant Required Future Investments in
Transmission
• Capture and Monetize Higher Rates Through FERC Regulatory
Construct (Regulatory Forum Shopping)
• Approximate Doubling of Size of ITC
8© 2014, Energy & Resource Consulting Group, LLC
TRANSACTION APPROVALS
• The Six Entergy Operating Companies (OPCOS) and ITC Filed Joint
Applications in 2012 for Retail Regulator Approval of the
Transaction
– Louisiana Public Service Commission (LPSC)
– Public Utility Commission of Texas (PUCT)
– Arkansas Public Service Commission (APSC)
– Mississippi Public Service Commission (MPSC)
– Council of the City of New Orleans (CNO)
• Transaction Also Required Approval from
– FERC
– Department of Justice (DOJ)
– Federal Trade Commission (FTC)
– Internal Revenue Service (IRS)
– ITC’s Shareholders
9© 2014, Energy & Resource Consulting Group, LLC
TRANSACTION STRUCTURE
• ITC Proposed to Establish an ITC Subsidiary in Each of
the Four States to Provide Wholesale Transmission
Service to Entergy OPCOS Under FERC Jurisdiction
• Creation of Wholly Owned ITC Subsidiary - ITC
MidSouth, LLC With Four Operating Subsidiaries
– ITC Arkansas, LLC
– ITC Louisiana, LLC
– ITC Mississippi, LLC
– ITC Texas, LLC
10© 2014, Energy & Resource Consulting Group, LLC
WHAT IS A REVERSE MORRIS TRUST?
11© 2014, Energy & Resource Consulting Group, LLC
WHAT IS A REVERSE MORRIS TRUST?
• An M&A Technique to Avoid Corporate Taxes
– A Series of Transactions Whose End Result is the
Transfer/Sale of a Portion of a Company’s Assets to a New
Owner
• In This Case - Transfer of Entergy OPCO Transmission
Assets to ITC
– Avoids Corporate Taxes on Gains
– Consideration Paid is the Acquirer’s Stock
– The Net Book Value of the Transmission Assets Remain the
Same for Entergy and ITC as New Owner
12© 2014, Energy & Resource Consulting Group, LLC
SIMPLE REPRESENTATION OF RMT
(Please See Appendix for Detailed Steps)
13© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION OVERVIEW
14© 2014, Energy & Resource Consulting Group, LLC
RMT HISTORICAL EVOLUTION
• Challenged by IRS (Commissioner vs. Mary Archer W.
Morris Trust, 1966)
– Morris Trust Received a Favorable Ruling – Creating a
Loophole for Companies to Avoid Taxes when Divesting
Assets
• Several IRS Published and Private Rulings Also Approved Morris
Trust Transactions
• Congress Sought to Limit the RMT in 1997
– IRS Code Section 255(e) Resulted in the “50% Rule”
– Limits RMTs and the Degree of Leverage that Can be Used
Related to the Majority Ownership Between the “Seller”
and “Buyer” Entities in the Merger
15© 2014, Energy & Resource Consulting Group, LLC
LIMITATIONS IN MONETIZING A SPIN-OFF
• Debt/Equity and Debt/Debt Swaps are Equally
Available to the Seller
• A Monetizing Spin-Off Allows a Seller to Spin Off a
Subsidiary on a Fully Tax-Free Basis While De-
Leveraging to a Significant Extent
• The Tax Basis of the Subsidiary Determines Upstream
Cash or Push Down Debt on a Tax-Free Basis
– Any Incremental Cash/Debt Would Trigger a Taxable Gain
16© 2014, Energy & Resource Consulting Group, LLC
THE “50% TEST”
• The Selling Company Must Own More than 50% of
the Ultimate Merged Company
• Shareholders of Seller Must Receive Over 50% of the
Vote and Value of the Newly-Formed Entity in the
Merger
– “Vote and Value” – Shares in the Newly-Formed
Entity Owned by the Seller Shareholders by Virtue
of Equity Positions in the Buyer
17© 2014, Energy & Resource Consulting Group, LLC
THE “50% TEST”
• Dilution of Seller Shareholders by Post-Transaction
Equity Issuances Within Two Years of the Transaction
by the Surviving Entity Will be Counted for Purposes
of the “50% Test”
• Acquiring Company Usually Must be Smaller than
Seller
– In the End - Acquiring Company Must Own Less than 50%
of the Merged Company
18© 2014, Energy & Resource Consulting Group, LLC
CORPORATE GOVERNANCE
• Notwithstanding the 50% Requirement – the Buyer
in a Reverse Morris Trust Acquisition Can Retain
Effective Control Over the Board of Directors and
Senior Management of the Surviving Entity
• Proposed RMT Structures Should Receive an IRS
Ruling Confirming Tax-Free Treatment
19© 2014, Energy & Resource Consulting Group, LLC
WHY THE USE OF A RMT STRUCTURE?
• Entergy and ITC Claimed That the Motivation for
Using an RMT was to Make the Transaction “Tax
Free”
– Asset Value is Not Reset to Fair Market Value
– Accumulated Deferred Income Tax (ADIT) is Not Re-
measured
• Other Benefits to Entergy and ITC Shareholders
– Escape State Regulation Except for CCN Requirements
– Retain All of the Gain of the Transaction
20© 2014, Energy & Resource Consulting Group, LLC
REGULATORY CONCERNS OVER
ENTERGY - ITC TRANSACTION
21© 2014, Energy & Resource Consulting Group, LLC
CUSTOMER REVENUE REQUIREMENTS
• Transmission Cost of Service Changes with Assets Regulated
by the FERC
– ROE Would Have Increased to 12.38%
– State Jurisdictional ROEs in Range of 10.2 – 11.1%
• Capital Structure and Rate of Return Changes with the
Transaction
– 60% Equity & 40% Debt Capital Structure
– Funded by Corporate Debt at 6.5% APR
– ITC Would Itself be Highly Levered
• Prospective Forward Test Year
• Reduced Regulatory Lag Especially with Large Planned
Investment
22© 2014, Energy & Resource Consulting Group, LLC
LOSS OF RETAIL REGULATORY
JURISDICTION
• Transfer of Risk From Entergy Shareholders to Ratepayers
– Transmission Planning and Expansion
– Storm Operations and Restoration
– Rate Setting and Prudency of Investments Reviewed at FERC
• Lack of Enforceable Commitment to Improve Service Quality
• No Integrated Resource Planning With Transmission
• No Constraints on Aggressive Transmission Construction and
Significant Spending
• O&M Cost Concerns Based Upon Experiences with ITC in Other
Jurisdictions
• Requirement to Challenge ITC’s Actions at FERC
• No Ability of Entergy OPCOS to Challenge ITC’s Rates for Five Years
– Only Section 206 Challenges to Rates Available at FERC by State Regulators
23© 2014, Energy & Resource Consulting Group, LLC
NO QUANTIFIABLE DEMONSTRATION
OF RATEPAYER BENEFITS
• No Supportable Analytical Cost Benefit Analysis was Provided
to Retail Regulators
• No Incremental Benefit Ascertained - Above the Benefits
Anticipated from Entergy Transmission Ownership in the
Midcontinent Independent Transmission System Operator
(MISO) RTO
• Questionable Weighted Average Cost of Capital (WACC)
Assumptions/Projections for Comparison Purposes
• Ignored Ability of OPCOS to Refinance Existing Embedded
Debt at Lower Incremental Costs
• Increased Cost in Retail Revenue Requirements for
Transmission Function
• Adopted Entergy’s Five Year Transmission Plan
– Future Studies to Determine Additional Commitments
24© 2014, Energy & Resource Consulting Group, LLC
SHAREHOLDERS KEEP GAINS
• Entergy – ITC Transaction Essentially Monetized Value of FERC
Construct vs. Traditional Asset Recovery with Retail Regulation
– All New Value is Created Through Regulatory Forum Shopping
– Funding Equity Return of 12.38% Through Debt Issuance at [6.5%]
• All Retail Regulators’ Staff Concluded That Transaction Created
Significant Gain to Entergy Shareholders
– Estimated $2 to 4 billion Goodwill as Proxy for Step-up in Asset Value
• 1.8 to 4 Times Book Value of Assets Being Spun Off
• No Sharing of Gain With Ratepayers
25© 2014, Energy & Resource Consulting Group, LLC
TOO LITTLE TOO LATE
• Following Stiff Regulatory Opposition, Entergy & ITC Proposed a
Series of Rate Mitigation Plans
– Insufficient to Offset Costs and Risks to Ratepayers
– WACC & Incremental Cost of Debt Issues
– Ill Defined Structure
– Large Portion of Mitigation Plan Based on “Difficult to Quantify” Benefits
to Ratepayers
• Green Jobs and Economic Stimulus
• More Reliable Transmission Network
– Yet Entergy Consistently Maintained That its Existing Network Met All Reliability
Standards
• Rewarded for Use of the Same Transmission Construction Plan as Entergy to
Benchmark Benefits in MISO
– Ratepayers Would Bear all Risk of Insufficient Mitigation
• Regulator Staff & Intervenors Saw Each Plan as Failing to
Compensate Ratepayers for Increased Costs and Risks
26© 2014, Energy & Resource Consulting Group, LLC
OBSERVATIONS
• Proposed Transaction Using the RMT Would Eliminate
Corporate Taxes and Maintain the Transmission Assets and
ADIT at Book Value
• Very Significant Gain to Entergy Shareholders not Shared With
Ratepayers
– The Very Structure and Basis for the Transaction Contrary to Such
Concept
• Significant Increased Costs to Ratepayers Without
Demonstrable Benefits
• Complete Loss of Retail Jurisdiction
• Shifting of Risks from Shareholders to Ratepayers
27© 2014, Energy & Resource Consulting Group, LLC
REGULATORY OUTCOMES OF
PROPOSED TRANSACTION
• All Retail Regulators’ Staff Recommended Against Finding the
Transaction in the Public Interest
• Substantially all Intervenors Recommended Against the
Transaction
– Stakeholders
– Large Industrial Customers
– Trade Groups
• Outcome
– MPSC Found the Transaction “Not in the Public Interest” on December
10, 2013 in Well Reasoned & Supported Decision
– Entergy & ITC Withdrew Joint Application Before all Retail Regulators &
FERC in December 2013
28© 2014, Energy & Resource Consulting Group, LLC
OBSERVATIONS – QUOTES
• The evidence indicates that the applicants have downplayed the significant
benefits to shareholders and overplayed any benefits to ratepayers. . . . There
is also conclusive evidence that ETI’s shareholders, not customers, are the
primary beneficiaries of the transaction. - PUCT Docket 41223, Proposed
Findings of Facts.
• …the value of Entergy’s shareholders stock would be enhanced significantly
with the proposed transaction. . . .There is no benefit to retail customers from
increasing the cost of service related to the transmission function by
transferring the regulatory oversight to FERC and significantly increasing Texas
customers’ cost for the same transmission service. - Michael P. Gorman on
Behalf of Texas Industrial Energy Consumers.
• ITC Holdings is building a house of cards that is constructed with high leverage
and inflated FERC-approved ROEs. - William B. Marcus, on Behalf of The
Arkansas Attorney General.
• The effect of ITC’s use of double leverage financing coupled with its proposed
rate construct is to charge customers more than the actual financing costs and
to inflate the returns accruing to stockholders. - J. Bertram Solomon on Behalf
of Arkansas Electric Energy Consumers, Inc.
29© 2014, Energy & Resource Consulting Group, LLC
OBSERVATIONS – QUOTES
• What is the magic that’s being done here that takes an asset -- a sleepy utility asset and
turns it into something that's so much sexier and more valuable? It's things like higher
ROEs on a uniform basis. It's things like incentives for doing the things to push certain
policies that are pushed by the federal government. It's routine awards of CWIP,
construction work in progress, awards for abandoned plant. If they don't actually finish
a project, they get to recover the costs they spent trying to do it; fictional capital
structures; capital structures that don't have anything to do with what's real for
ratemaking purposes, and back-leverage of the parent company, which you will see
later, that actually takes what looks to be already a high ROE and turns them into
recoveries north of 20 percent.– Philip Oldham, Counsel for Occidental Chemical
Corporation.
• We're talking about the use of this mechanism in order to transfer money to the Entergy
shareholders and create a larger platform with ITC who has a particular vision. And I
will say that vision will be presented to you in great detail in this case, a vision of a
national super highway grid [that] pushes certain policies that are not consistent with
the public interest in Texas . . . .– Id.
Q&A
30© 2014, Energy & Resource Consulting Group, LLC
APPENDIX
DETAILED RMT STEPS OF THE ENTERGY
ITC TRANSACTION
31© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 1
LLC IS CREATED
32© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 2
ENTERGY ISSUES DEBT
33© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 3
ENTERGY PAYS OFF EXISTING DEBT
34© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 4
ENTERGY REDEEMS PREFERRED STOCK
35© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 5
ENTERGY CREATES WIRES SUBSIDIARY
36© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 6
WIRE SUBS ISSUE DEBT
37© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 7
OPERATING COMPANIES BECOME LLC
38© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 7A
CONTRIBUTION OF TRANSMISSION COMPANIES
39© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 8
OPERATING COS PAY EXISTING DEBT
40© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 9
WIRE SUBS TO ENTERGY
41© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 10
LLC RECEIVES TRANSMISSION ASSETS
42© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 11
WIRE SUBS TO ENTERGY
43© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 12
SPIN OFF LLC
44© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 13
REDEEM ENTERGY NOTES
45© 2014, Energy & Resource Consulting Group, LLC
ITC TRANSACTION – STEP 14
MERGE LLC AND WIRE SUBS
46© 2014, Energy & Resource Consulting Group, LLC

More Related Content

What's hot

Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)
Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)
Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)ELSCC
 
Virtual organization
Virtual organizationVirtual organization
Virtual organizationBana Maani
 
Supplier Information and Lifecycle Management
Supplier Information and Lifecycle ManagementSupplier Information and Lifecycle Management
Supplier Information and Lifecycle ManagementTradeshift
 
Holacracy as an alternative to organisations governance
Holacracy as an alternative to organisations governanceHolacracy as an alternative to organisations governance
Holacracy as an alternative to organisations governanceLuis Borges Gouveia
 
The Future of Procurement Technology with Hugo Evans of A.T. Kearney
The Future of Procurement Technology with Hugo Evans of A.T. KearneyThe Future of Procurement Technology with Hugo Evans of A.T. Kearney
The Future of Procurement Technology with Hugo Evans of A.T. KearneyScout RFP
 
Achieving a Single View of Business – Critical Data with Master Data Management
Achieving a Single View of Business – Critical Data with Master Data ManagementAchieving a Single View of Business – Critical Data with Master Data Management
Achieving a Single View of Business – Critical Data with Master Data ManagementDATAVERSITY
 
Ppt on supplier consolidation
Ppt on supplier consolidationPpt on supplier consolidation
Ppt on supplier consolidationSahil Khambhati
 
Operations Management Processes and Supply Chains Global 11th Edition Krajews...
Operations Management Processes and Supply Chains Global 11th Edition Krajews...Operations Management Processes and Supply Chains Global 11th Edition Krajews...
Operations Management Processes and Supply Chains Global 11th Edition Krajews...Callahanne
 
Final Ford Presentation
Final Ford PresentationFinal Ford Presentation
Final Ford Presentationajayjagtap67
 
Analyst field reports on top 20 multi domain MDM solutions - Aaron Zornes (NY...
Analyst field reports on top 20 multi domain MDM solutions - Aaron Zornes (NY...Analyst field reports on top 20 multi domain MDM solutions - Aaron Zornes (NY...
Analyst field reports on top 20 multi domain MDM solutions - Aaron Zornes (NY...Aaron Zornes
 
Johnson and Johnson Case Competition RU Team J
Johnson and Johnson Case Competition RU Team JJohnson and Johnson Case Competition RU Team J
Johnson and Johnson Case Competition RU Team JShekhar Gurnani
 
Introduction to DCAM, the Data Management Capability Assessment Model - Editi...
Introduction to DCAM, the Data Management Capability Assessment Model - Editi...Introduction to DCAM, the Data Management Capability Assessment Model - Editi...
Introduction to DCAM, the Data Management Capability Assessment Model - Editi...Element22
 
Product Management And Service Delivery Process - FlackVentures Example
Product Management And Service Delivery Process - FlackVentures ExampleProduct Management And Service Delivery Process - FlackVentures Example
Product Management And Service Delivery Process - FlackVentures ExampleKate Pynn
 
Data Governance — Aligning Technical and Business Approaches
Data Governance — Aligning Technical and Business ApproachesData Governance — Aligning Technical and Business Approaches
Data Governance — Aligning Technical and Business ApproachesDATAVERSITY
 
Successful Shared Services Implementation
Successful Shared Services ImplementationSuccessful Shared Services Implementation
Successful Shared Services ImplementationRegional Health
 
Smart erp solutions oracle cloud services overview - 2021 - 2022
Smart erp solutions   oracle cloud services overview - 2021 - 2022Smart erp solutions   oracle cloud services overview - 2021 - 2022
Smart erp solutions oracle cloud services overview - 2021 - 2022Smart ERP Solutions, Inc.
 
Point Of View Category Management v1.0 final
Point Of View Category Management v1.0 finalPoint Of View Category Management v1.0 final
Point Of View Category Management v1.0 finalMarjolein Dijkshoorn
 

What's hot (20)

Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)
Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)
Indirect Procurement - Mr. Ashwani Singh (Watson Pharma)
 
Virtual organization
Virtual organizationVirtual organization
Virtual organization
 
IT Supply Chain Management
IT Supply Chain ManagementIT Supply Chain Management
IT Supply Chain Management
 
Supplier Information and Lifecycle Management
Supplier Information and Lifecycle ManagementSupplier Information and Lifecycle Management
Supplier Information and Lifecycle Management
 
Holacracy as an alternative to organisations governance
Holacracy as an alternative to organisations governanceHolacracy as an alternative to organisations governance
Holacracy as an alternative to organisations governance
 
The Future of Procurement Technology with Hugo Evans of A.T. Kearney
The Future of Procurement Technology with Hugo Evans of A.T. KearneyThe Future of Procurement Technology with Hugo Evans of A.T. Kearney
The Future of Procurement Technology with Hugo Evans of A.T. Kearney
 
Achieving a Single View of Business – Critical Data with Master Data Management
Achieving a Single View of Business – Critical Data with Master Data ManagementAchieving a Single View of Business – Critical Data with Master Data Management
Achieving a Single View of Business – Critical Data with Master Data Management
 
Ppt on supplier consolidation
Ppt on supplier consolidationPpt on supplier consolidation
Ppt on supplier consolidation
 
(추천오라클힌트교육)해시조인, Hash join, use_hash, ordered
(추천오라클힌트교육)해시조인, Hash join, use_hash, ordered(추천오라클힌트교육)해시조인, Hash join, use_hash, ordered
(추천오라클힌트교육)해시조인, Hash join, use_hash, ordered
 
Operations Management Processes and Supply Chains Global 11th Edition Krajews...
Operations Management Processes and Supply Chains Global 11th Edition Krajews...Operations Management Processes and Supply Chains Global 11th Edition Krajews...
Operations Management Processes and Supply Chains Global 11th Edition Krajews...
 
Final Ford Presentation
Final Ford PresentationFinal Ford Presentation
Final Ford Presentation
 
Analyst field reports on top 20 multi domain MDM solutions - Aaron Zornes (NY...
Analyst field reports on top 20 multi domain MDM solutions - Aaron Zornes (NY...Analyst field reports on top 20 multi domain MDM solutions - Aaron Zornes (NY...
Analyst field reports on top 20 multi domain MDM solutions - Aaron Zornes (NY...
 
Johnson and Johnson Case Competition RU Team J
Johnson and Johnson Case Competition RU Team JJohnson and Johnson Case Competition RU Team J
Johnson and Johnson Case Competition RU Team J
 
Introduction to DCAM, the Data Management Capability Assessment Model - Editi...
Introduction to DCAM, the Data Management Capability Assessment Model - Editi...Introduction to DCAM, the Data Management Capability Assessment Model - Editi...
Introduction to DCAM, the Data Management Capability Assessment Model - Editi...
 
Product Management And Service Delivery Process - FlackVentures Example
Product Management And Service Delivery Process - FlackVentures ExampleProduct Management And Service Delivery Process - FlackVentures Example
Product Management And Service Delivery Process - FlackVentures Example
 
Data Governance — Aligning Technical and Business Approaches
Data Governance — Aligning Technical and Business ApproachesData Governance — Aligning Technical and Business Approaches
Data Governance — Aligning Technical and Business Approaches
 
Successful Shared Services Implementation
Successful Shared Services ImplementationSuccessful Shared Services Implementation
Successful Shared Services Implementation
 
Business Chemistry
Business ChemistryBusiness Chemistry
Business Chemistry
 
Smart erp solutions oracle cloud services overview - 2021 - 2022
Smart erp solutions   oracle cloud services overview - 2021 - 2022Smart erp solutions   oracle cloud services overview - 2021 - 2022
Smart erp solutions oracle cloud services overview - 2021 - 2022
 
Point Of View Category Management v1.0 final
Point Of View Category Management v1.0 finalPoint Of View Category Management v1.0 final
Point Of View Category Management v1.0 final
 

Viewers also liked

small details that sweeten your day
small details that sweeten your daysmall details that sweeten your day
small details that sweeten your dayjudithplanes
 
Наталья Самоукина. «Старший возраст: жизнь и карьера»
Наталья Самоукина. «Старший возраст: жизнь и карьера»Наталья Самоукина. «Старший возраст: жизнь и карьера»
Наталья Самоукина. «Старший возраст: жизнь и карьера»Tatyana Drozdova
 
Кирилл Романов. Откуда берутся клиенты. StandUP Marketing, 16/10/2014
Кирилл Романов. Откуда берутся клиенты. StandUP Marketing, 16/10/2014Кирилл Романов. Откуда берутся клиенты. StandUP Marketing, 16/10/2014
Кирилл Романов. Откуда берутся клиенты. StandUP Marketing, 16/10/2014SPECIA
 
Dem lot sinh hoc cho lon
Dem lot sinh hoc cho lonDem lot sinh hoc cho lon
Dem lot sinh hoc cho lonPhở Phở
 
Rahat Javed_original
Rahat Javed_originalRahat Javed_original
Rahat Javed_originalRahat Javed
 
Quality management introduction
Quality management introductionQuality management introduction
Quality management introductionselinasimpson2801
 
renewable energies
renewable energiesrenewable energies
renewable energiesserzan2000
 
RESUME_2015_GALLEGO
RESUME_2015_GALLEGORESUME_2015_GALLEGO
RESUME_2015_GALLEGORyan Gallego
 
PR Partner: Трансформация PR и маркетинга с помощью Pressfeed
PR Partner: Трансформация PR и маркетинга с помощью PressfeedPR Partner: Трансформация PR и маркетинга с помощью Pressfeed
PR Partner: Трансформация PR и маркетинга с помощью PressfeedSPECIA
 
OhioHappenings1-27-17
OhioHappenings1-27-17OhioHappenings1-27-17
OhioHappenings1-27-17Jared Shank
 

Viewers also liked (14)

small details that sweeten your day
small details that sweeten your daysmall details that sweeten your day
small details that sweeten your day
 
Наталья Самоукина. «Старший возраст: жизнь и карьера»
Наталья Самоукина. «Старший возраст: жизнь и карьера»Наталья Самоукина. «Старший возраст: жизнь и карьера»
Наталья Самоукина. «Старший возраст: жизнь и карьера»
 
Кирилл Романов. Откуда берутся клиенты. StandUP Marketing, 16/10/2014
Кирилл Романов. Откуда берутся клиенты. StandUP Marketing, 16/10/2014Кирилл Романов. Откуда берутся клиенты. StandUP Marketing, 16/10/2014
Кирилл Романов. Откуда берутся клиенты. StandUP Marketing, 16/10/2014
 
Dem lot sinh hoc cho lon
Dem lot sinh hoc cho lonDem lot sinh hoc cho lon
Dem lot sinh hoc cho lon
 
Rahat Javed_original
Rahat Javed_originalRahat Javed_original
Rahat Javed_original
 
Quality management introduction
Quality management introductionQuality management introduction
Quality management introduction
 
Tips
TipsTips
Tips
 
renewable energies
renewable energiesrenewable energies
renewable energies
 
RESUME_2015_GALLEGO
RESUME_2015_GALLEGORESUME_2015_GALLEGO
RESUME_2015_GALLEGO
 
Cloxacillin sodium 7081-44-9-api-manufacturer-suppliers
Cloxacillin sodium 7081-44-9-api-manufacturer-suppliersCloxacillin sodium 7081-44-9-api-manufacturer-suppliers
Cloxacillin sodium 7081-44-9-api-manufacturer-suppliers
 
Socialización
SocializaciónSocialización
Socialización
 
PR Partner: Трансформация PR и маркетинга с помощью Pressfeed
PR Partner: Трансформация PR и маркетинга с помощью PressfeedPR Partner: Трансформация PR и маркетинга с помощью Pressfeed
PR Partner: Трансформация PR и маркетинга с помощью Pressfeed
 
OhioHappenings1-27-17
OhioHappenings1-27-17OhioHappenings1-27-17
OhioHappenings1-27-17
 
IT Proposal
IT ProposalIT Proposal
IT Proposal
 

Similar to Reverse Morris Trust (ITC Transaction) Presentation Slides - ERG Consluting

Action Items to Prepare for 2015 Proxy Season
Action Items to Prepare for 2015 Proxy SeasonAction Items to Prepare for 2015 Proxy Season
Action Items to Prepare for 2015 Proxy SeasonWinston & Strawn LLP
 
Emes investor presentation for citi 1v1 2014 3
Emes investor presentation for citi 1v1 2014 3Emes investor presentation for citi 1v1 2014 3
Emes investor presentation for citi 1v1 2014 3ScutifyNewsBits
 
Bus 475 week 4 knowledge check
Bus 475 week 4 knowledge checkBus 475 week 4 knowledge check
Bus 475 week 4 knowledge checkTransweb E Tutors
 
Accounting & Auditing Update
Accounting & Auditing UpdateAccounting & Auditing Update
Accounting & Auditing UpdateCohen and Company
 
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A) - ...
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A) - ...Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A) - ...
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A) - ...The Capital Network
 
Delaware Business Law
Delaware Business Law Delaware Business Law
Delaware Business Law CT
 
AAP presentation 2010 trends
AAP presentation 2010 trendsAAP presentation 2010 trends
AAP presentation 2010 trendsHampton Resources
 
2014 Annual Accounting Update for Private Enterprises
2014 Annual Accounting Update for Private Enterprises2014 Annual Accounting Update for Private Enterprises
2014 Annual Accounting Update for Private EnterprisesWelch LLP
 
Sponsor lunch presentation december 2016
Sponsor lunch presentation december 2016Sponsor lunch presentation december 2016
Sponsor lunch presentation december 2016The Capital Network
 
Proxy Season Recap – Trends and Lessons from 2014
Proxy Season Recap – Trends and Lessons from 2014Proxy Season Recap – Trends and Lessons from 2014
Proxy Season Recap – Trends and Lessons from 2014Winston & Strawn LLP
 
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A)
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A)Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A)
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A)The Capital Network
 
Profile for Marc T Artino CPA
Profile for Marc T Artino CPAProfile for Marc T Artino CPA
Profile for Marc T Artino CPAMarc Artino, CPA
 
Know Your Valuation For Equity Compensation (And Avoid the Perils of a 409A)
Know Your Valuation For Equity Compensation (And Avoid the Perils of a 409A)Know Your Valuation For Equity Compensation (And Avoid the Perils of a 409A)
Know Your Valuation For Equity Compensation (And Avoid the Perils of a 409A)The Capital Network
 
Natural Resource Partners - April 2014 Presentation
Natural Resource Partners - April 2014 PresentationNatural Resource Partners - April 2014 Presentation
Natural Resource Partners - April 2014 PresentationCompany Spotlight
 
Celp june 2015 investor presentation final
Celp june 2015 investor presentation finalCelp june 2015 investor presentation final
Celp june 2015 investor presentation finalCypressEnergy
 
Naptp new outline presentation 5 18 2015 v4
Naptp new outline presentation 5 18 2015 v4Naptp new outline presentation 5 18 2015 v4
Naptp new outline presentation 5 18 2015 v4CypressEnergy
 
Ensv january new
Ensv january newEnsv january new
Ensv january newAdam Martin
 
Ilminster - Charity Seminar 2016
Ilminster - Charity Seminar 2016Ilminster - Charity Seminar 2016
Ilminster - Charity Seminar 2016PKF Francis Clark
 
Enservco - Corporate Presentation
Enservco - Corporate PresentationEnservco - Corporate Presentation
Enservco - Corporate PresentationCompany Spotlight
 

Similar to Reverse Morris Trust (ITC Transaction) Presentation Slides - ERG Consluting (20)

Action Items to Prepare for 2015 Proxy Season
Action Items to Prepare for 2015 Proxy SeasonAction Items to Prepare for 2015 Proxy Season
Action Items to Prepare for 2015 Proxy Season
 
Emes investor presentation for citi 1v1 2014 3
Emes investor presentation for citi 1v1 2014 3Emes investor presentation for citi 1v1 2014 3
Emes investor presentation for citi 1v1 2014 3
 
Bus 475 week 4 knowledge check
Bus 475 week 4 knowledge checkBus 475 week 4 knowledge check
Bus 475 week 4 knowledge check
 
Accounting & Auditing Update
Accounting & Auditing UpdateAccounting & Auditing Update
Accounting & Auditing Update
 
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A) - ...
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A) - ...Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A) - ...
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A) - ...
 
Delaware Business Law
Delaware Business Law Delaware Business Law
Delaware Business Law
 
AAP presentation 2010 trends
AAP presentation 2010 trendsAAP presentation 2010 trends
AAP presentation 2010 trends
 
2014 Annual Accounting Update for Private Enterprises
2014 Annual Accounting Update for Private Enterprises2014 Annual Accounting Update for Private Enterprises
2014 Annual Accounting Update for Private Enterprises
 
Sponsor lunch presentation december 2016
Sponsor lunch presentation december 2016Sponsor lunch presentation december 2016
Sponsor lunch presentation december 2016
 
Proxy Season Recap – Trends and Lessons from 2014
Proxy Season Recap – Trends and Lessons from 2014Proxy Season Recap – Trends and Lessons from 2014
Proxy Season Recap – Trends and Lessons from 2014
 
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A)
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A)Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A)
Know Your Valuation for Equity Compensation (And Avoid the Perils of 409A)
 
Profile for Marc T Artino CPA
Profile for Marc T Artino CPAProfile for Marc T Artino CPA
Profile for Marc T Artino CPA
 
Know Your Valuation For Equity Compensation (And Avoid the Perils of a 409A)
Know Your Valuation For Equity Compensation (And Avoid the Perils of a 409A)Know Your Valuation For Equity Compensation (And Avoid the Perils of a 409A)
Know Your Valuation For Equity Compensation (And Avoid the Perils of a 409A)
 
Natural Resource Partners - April 2014 Presentation
Natural Resource Partners - April 2014 PresentationNatural Resource Partners - April 2014 Presentation
Natural Resource Partners - April 2014 Presentation
 
Celp june 2015 investor presentation final
Celp june 2015 investor presentation finalCelp june 2015 investor presentation final
Celp june 2015 investor presentation final
 
Naptp new outline presentation 5 18 2015 v4
Naptp new outline presentation 5 18 2015 v4Naptp new outline presentation 5 18 2015 v4
Naptp new outline presentation 5 18 2015 v4
 
Truro - Charity Seminar 2016
Truro - Charity Seminar 2016Truro - Charity Seminar 2016
Truro - Charity Seminar 2016
 
Ensv january new
Ensv january newEnsv january new
Ensv january new
 
Ilminster - Charity Seminar 2016
Ilminster - Charity Seminar 2016Ilminster - Charity Seminar 2016
Ilminster - Charity Seminar 2016
 
Enservco - Corporate Presentation
Enservco - Corporate PresentationEnservco - Corporate Presentation
Enservco - Corporate Presentation
 

Reverse Morris Trust (ITC Transaction) Presentation Slides - ERG Consluting

  • 1. REVERSE MORRIS TRUST RATEPAYER VALUE VS. SHAREHOLDER GAIN A Review of The Failed Entergy – ITC Transaction March 18, 2014 NARUC Accounting and Finance Meeting Victor Prep, P.E. & Byron Watson, CFA © 2014, Energy & Resource Consulting Group, LLC Denver, Colorado www.ergconsulting.com
  • 2. INTRODUCTION • Victor Prep, P.E. – Executive Consultant at ERG – BSME from OU, MBA from Wharton, Registered P.E. in PA, CO, and LA, Retired Nuclear Submarine Naval Officer • Byron Watson, CFA – Senior Consultant at ERG – BSEE from SMU, MBA in Finance from Emory University, Chartered Financial Analyst (CFA®) • The Council of the City of New Orleans Exercises Primary Retail Jurisdiction Over two of Entergy Corporation Inc.’s (Entergy) Operating Subsidiaries in Orleans Parish, Louisiana – Entergy New Orleans, Inc. (ENO) – Entergy Louisiana, LLC (ELL) • Members of ERG Serve as Regulatory Advisors to the Council of the City of New Orleans – Directly Involved with the Entergy - ITC Transaction at Both the Local and FERC Level © 2014, Energy & Resource Consulting Group, LLC 2
  • 3. ITC TRANSACTION OVERVIEW • The Transaction was a Proposed Entergy Divestiture/Spin-off of its Six Operating Companies’ Transmission Assets & a Merger of the Spun-off Assets with International Transmission Company, Inc. of Novi, Michigan (ITC) • The Transaction used a Merger & Acquisition (M&A) Technique Called a Reverse Morris Trust (RMT). • The Proposed Transaction was the First Attempt to Use the RMT in Divesting Assets Within the US Electric and Gas Utility Industry. 3© 2014, Energy & Resource Consulting Group, LLC
  • 4. SUMMARY OF REGULATORY CONCERNS • FERC Regulatory Construct Increases Retail Revenue Requirement • Loss of Jurisdictional Control by State Regulators of Transmission Ratemaking & Oversight of Transmission Function – Only Retail CCN Approval Preserved – Section 206 Rate Challenge Only • Transfer of Risk from Entergy and ITC Shareholders to Retail Ratepayers – FERC Forward Looking FRP Process • Value and Ownership of Gains Monetized by Transaction – Ratepayers versus Shareholders • Lack of Demonstrable Quantifiable Ratepayer Benefits • Major Storm Restoration Concerns • Transfer of Intellectual Capital • Experience of ITC in Previous Acquisitions • Shareholder Gain at the Expense of Ratepayers 4© 2014, Energy & Resource Consulting Group, LLC
  • 5. THE PROPOSED TRANSACTION 5© 2014, Energy & Resource Consulting Group, LLC
  • 6. PARTIES TO THE TRANSACTION • Entergy Corporation – Six Vertically Structured Operating Companies • ENO, ELL, Entergy Gulf States, LLC, Entergy Texas, Inc., Entergy Mississippi, Inc. & Entergy Arkansas, Inc. – Four Mid-South States • Arkansas, Louisiana, Mississippi & Texas – Five Retail Jurisdictions • Arkansas, Louisiana, Mississippi, New Orleans & Texas • ITC Holdings Corp. – An Independent Transmission Focused Company – Created in 2003 Through Predecessor (Formally DTE Energy Transmission) – Transmission Service in Seven Midwestern States Through Subsidiaries • ITC Transmission, ITC Midwest, ITC Great Plains & Michigan Electric Transmission Company 6© 2014, Energy & Resource Consulting Group, LLC
  • 7. STATED RATIONALE FOR THE TRANSACTION 7 • Improved Network Reliability • Increased Investment in Transmission Network (Reduced Costs Through Less Congestion) • Improved O&M Efficiency • Singular Focus on Transmission ITC • Enhanced Financial Flexibility – Benefit to Other Ongoing Required Investments – Better Access to Capital – Credit Quality Protection • Improved Earnings and Dividend Growth ENTERGY © 2014, Energy & Resource Consulting Group, LLC
  • 8. UNSTATED RATIONALE • Entergy’s Concerns with an Ongoing DOJ Anti-Trust Investigation Regarding Operation of Its Transmission System • Creation of Enhanced Value for Entergy Shareholders – Failed Attempt to Divest Wholesale Nuclear Assets • Offload Significant Required Future Investments in Transmission • Capture and Monetize Higher Rates Through FERC Regulatory Construct (Regulatory Forum Shopping) • Approximate Doubling of Size of ITC 8© 2014, Energy & Resource Consulting Group, LLC
  • 9. TRANSACTION APPROVALS • The Six Entergy Operating Companies (OPCOS) and ITC Filed Joint Applications in 2012 for Retail Regulator Approval of the Transaction – Louisiana Public Service Commission (LPSC) – Public Utility Commission of Texas (PUCT) – Arkansas Public Service Commission (APSC) – Mississippi Public Service Commission (MPSC) – Council of the City of New Orleans (CNO) • Transaction Also Required Approval from – FERC – Department of Justice (DOJ) – Federal Trade Commission (FTC) – Internal Revenue Service (IRS) – ITC’s Shareholders 9© 2014, Energy & Resource Consulting Group, LLC
  • 10. TRANSACTION STRUCTURE • ITC Proposed to Establish an ITC Subsidiary in Each of the Four States to Provide Wholesale Transmission Service to Entergy OPCOS Under FERC Jurisdiction • Creation of Wholly Owned ITC Subsidiary - ITC MidSouth, LLC With Four Operating Subsidiaries – ITC Arkansas, LLC – ITC Louisiana, LLC – ITC Mississippi, LLC – ITC Texas, LLC 10© 2014, Energy & Resource Consulting Group, LLC
  • 11. WHAT IS A REVERSE MORRIS TRUST? 11© 2014, Energy & Resource Consulting Group, LLC
  • 12. WHAT IS A REVERSE MORRIS TRUST? • An M&A Technique to Avoid Corporate Taxes – A Series of Transactions Whose End Result is the Transfer/Sale of a Portion of a Company’s Assets to a New Owner • In This Case - Transfer of Entergy OPCO Transmission Assets to ITC – Avoids Corporate Taxes on Gains – Consideration Paid is the Acquirer’s Stock – The Net Book Value of the Transmission Assets Remain the Same for Entergy and ITC as New Owner 12© 2014, Energy & Resource Consulting Group, LLC
  • 13. SIMPLE REPRESENTATION OF RMT (Please See Appendix for Detailed Steps) 13© 2014, Energy & Resource Consulting Group, LLC
  • 14. ITC TRANSACTION OVERVIEW 14© 2014, Energy & Resource Consulting Group, LLC
  • 15. RMT HISTORICAL EVOLUTION • Challenged by IRS (Commissioner vs. Mary Archer W. Morris Trust, 1966) – Morris Trust Received a Favorable Ruling – Creating a Loophole for Companies to Avoid Taxes when Divesting Assets • Several IRS Published and Private Rulings Also Approved Morris Trust Transactions • Congress Sought to Limit the RMT in 1997 – IRS Code Section 255(e) Resulted in the “50% Rule” – Limits RMTs and the Degree of Leverage that Can be Used Related to the Majority Ownership Between the “Seller” and “Buyer” Entities in the Merger 15© 2014, Energy & Resource Consulting Group, LLC
  • 16. LIMITATIONS IN MONETIZING A SPIN-OFF • Debt/Equity and Debt/Debt Swaps are Equally Available to the Seller • A Monetizing Spin-Off Allows a Seller to Spin Off a Subsidiary on a Fully Tax-Free Basis While De- Leveraging to a Significant Extent • The Tax Basis of the Subsidiary Determines Upstream Cash or Push Down Debt on a Tax-Free Basis – Any Incremental Cash/Debt Would Trigger a Taxable Gain 16© 2014, Energy & Resource Consulting Group, LLC
  • 17. THE “50% TEST” • The Selling Company Must Own More than 50% of the Ultimate Merged Company • Shareholders of Seller Must Receive Over 50% of the Vote and Value of the Newly-Formed Entity in the Merger – “Vote and Value” – Shares in the Newly-Formed Entity Owned by the Seller Shareholders by Virtue of Equity Positions in the Buyer 17© 2014, Energy & Resource Consulting Group, LLC
  • 18. THE “50% TEST” • Dilution of Seller Shareholders by Post-Transaction Equity Issuances Within Two Years of the Transaction by the Surviving Entity Will be Counted for Purposes of the “50% Test” • Acquiring Company Usually Must be Smaller than Seller – In the End - Acquiring Company Must Own Less than 50% of the Merged Company 18© 2014, Energy & Resource Consulting Group, LLC
  • 19. CORPORATE GOVERNANCE • Notwithstanding the 50% Requirement – the Buyer in a Reverse Morris Trust Acquisition Can Retain Effective Control Over the Board of Directors and Senior Management of the Surviving Entity • Proposed RMT Structures Should Receive an IRS Ruling Confirming Tax-Free Treatment 19© 2014, Energy & Resource Consulting Group, LLC
  • 20. WHY THE USE OF A RMT STRUCTURE? • Entergy and ITC Claimed That the Motivation for Using an RMT was to Make the Transaction “Tax Free” – Asset Value is Not Reset to Fair Market Value – Accumulated Deferred Income Tax (ADIT) is Not Re- measured • Other Benefits to Entergy and ITC Shareholders – Escape State Regulation Except for CCN Requirements – Retain All of the Gain of the Transaction 20© 2014, Energy & Resource Consulting Group, LLC
  • 21. REGULATORY CONCERNS OVER ENTERGY - ITC TRANSACTION 21© 2014, Energy & Resource Consulting Group, LLC
  • 22. CUSTOMER REVENUE REQUIREMENTS • Transmission Cost of Service Changes with Assets Regulated by the FERC – ROE Would Have Increased to 12.38% – State Jurisdictional ROEs in Range of 10.2 – 11.1% • Capital Structure and Rate of Return Changes with the Transaction – 60% Equity & 40% Debt Capital Structure – Funded by Corporate Debt at 6.5% APR – ITC Would Itself be Highly Levered • Prospective Forward Test Year • Reduced Regulatory Lag Especially with Large Planned Investment 22© 2014, Energy & Resource Consulting Group, LLC
  • 23. LOSS OF RETAIL REGULATORY JURISDICTION • Transfer of Risk From Entergy Shareholders to Ratepayers – Transmission Planning and Expansion – Storm Operations and Restoration – Rate Setting and Prudency of Investments Reviewed at FERC • Lack of Enforceable Commitment to Improve Service Quality • No Integrated Resource Planning With Transmission • No Constraints on Aggressive Transmission Construction and Significant Spending • O&M Cost Concerns Based Upon Experiences with ITC in Other Jurisdictions • Requirement to Challenge ITC’s Actions at FERC • No Ability of Entergy OPCOS to Challenge ITC’s Rates for Five Years – Only Section 206 Challenges to Rates Available at FERC by State Regulators 23© 2014, Energy & Resource Consulting Group, LLC
  • 24. NO QUANTIFIABLE DEMONSTRATION OF RATEPAYER BENEFITS • No Supportable Analytical Cost Benefit Analysis was Provided to Retail Regulators • No Incremental Benefit Ascertained - Above the Benefits Anticipated from Entergy Transmission Ownership in the Midcontinent Independent Transmission System Operator (MISO) RTO • Questionable Weighted Average Cost of Capital (WACC) Assumptions/Projections for Comparison Purposes • Ignored Ability of OPCOS to Refinance Existing Embedded Debt at Lower Incremental Costs • Increased Cost in Retail Revenue Requirements for Transmission Function • Adopted Entergy’s Five Year Transmission Plan – Future Studies to Determine Additional Commitments 24© 2014, Energy & Resource Consulting Group, LLC
  • 25. SHAREHOLDERS KEEP GAINS • Entergy – ITC Transaction Essentially Monetized Value of FERC Construct vs. Traditional Asset Recovery with Retail Regulation – All New Value is Created Through Regulatory Forum Shopping – Funding Equity Return of 12.38% Through Debt Issuance at [6.5%] • All Retail Regulators’ Staff Concluded That Transaction Created Significant Gain to Entergy Shareholders – Estimated $2 to 4 billion Goodwill as Proxy for Step-up in Asset Value • 1.8 to 4 Times Book Value of Assets Being Spun Off • No Sharing of Gain With Ratepayers 25© 2014, Energy & Resource Consulting Group, LLC
  • 26. TOO LITTLE TOO LATE • Following Stiff Regulatory Opposition, Entergy & ITC Proposed a Series of Rate Mitigation Plans – Insufficient to Offset Costs and Risks to Ratepayers – WACC & Incremental Cost of Debt Issues – Ill Defined Structure – Large Portion of Mitigation Plan Based on “Difficult to Quantify” Benefits to Ratepayers • Green Jobs and Economic Stimulus • More Reliable Transmission Network – Yet Entergy Consistently Maintained That its Existing Network Met All Reliability Standards • Rewarded for Use of the Same Transmission Construction Plan as Entergy to Benchmark Benefits in MISO – Ratepayers Would Bear all Risk of Insufficient Mitigation • Regulator Staff & Intervenors Saw Each Plan as Failing to Compensate Ratepayers for Increased Costs and Risks 26© 2014, Energy & Resource Consulting Group, LLC
  • 27. OBSERVATIONS • Proposed Transaction Using the RMT Would Eliminate Corporate Taxes and Maintain the Transmission Assets and ADIT at Book Value • Very Significant Gain to Entergy Shareholders not Shared With Ratepayers – The Very Structure and Basis for the Transaction Contrary to Such Concept • Significant Increased Costs to Ratepayers Without Demonstrable Benefits • Complete Loss of Retail Jurisdiction • Shifting of Risks from Shareholders to Ratepayers 27© 2014, Energy & Resource Consulting Group, LLC
  • 28. REGULATORY OUTCOMES OF PROPOSED TRANSACTION • All Retail Regulators’ Staff Recommended Against Finding the Transaction in the Public Interest • Substantially all Intervenors Recommended Against the Transaction – Stakeholders – Large Industrial Customers – Trade Groups • Outcome – MPSC Found the Transaction “Not in the Public Interest” on December 10, 2013 in Well Reasoned & Supported Decision – Entergy & ITC Withdrew Joint Application Before all Retail Regulators & FERC in December 2013 28© 2014, Energy & Resource Consulting Group, LLC
  • 29. OBSERVATIONS – QUOTES • The evidence indicates that the applicants have downplayed the significant benefits to shareholders and overplayed any benefits to ratepayers. . . . There is also conclusive evidence that ETI’s shareholders, not customers, are the primary beneficiaries of the transaction. - PUCT Docket 41223, Proposed Findings of Facts. • …the value of Entergy’s shareholders stock would be enhanced significantly with the proposed transaction. . . .There is no benefit to retail customers from increasing the cost of service related to the transmission function by transferring the regulatory oversight to FERC and significantly increasing Texas customers’ cost for the same transmission service. - Michael P. Gorman on Behalf of Texas Industrial Energy Consumers. • ITC Holdings is building a house of cards that is constructed with high leverage and inflated FERC-approved ROEs. - William B. Marcus, on Behalf of The Arkansas Attorney General. • The effect of ITC’s use of double leverage financing coupled with its proposed rate construct is to charge customers more than the actual financing costs and to inflate the returns accruing to stockholders. - J. Bertram Solomon on Behalf of Arkansas Electric Energy Consumers, Inc. 29© 2014, Energy & Resource Consulting Group, LLC
  • 30. OBSERVATIONS – QUOTES • What is the magic that’s being done here that takes an asset -- a sleepy utility asset and turns it into something that's so much sexier and more valuable? It's things like higher ROEs on a uniform basis. It's things like incentives for doing the things to push certain policies that are pushed by the federal government. It's routine awards of CWIP, construction work in progress, awards for abandoned plant. If they don't actually finish a project, they get to recover the costs they spent trying to do it; fictional capital structures; capital structures that don't have anything to do with what's real for ratemaking purposes, and back-leverage of the parent company, which you will see later, that actually takes what looks to be already a high ROE and turns them into recoveries north of 20 percent.– Philip Oldham, Counsel for Occidental Chemical Corporation. • We're talking about the use of this mechanism in order to transfer money to the Entergy shareholders and create a larger platform with ITC who has a particular vision. And I will say that vision will be presented to you in great detail in this case, a vision of a national super highway grid [that] pushes certain policies that are not consistent with the public interest in Texas . . . .– Id. Q&A 30© 2014, Energy & Resource Consulting Group, LLC
  • 31. APPENDIX DETAILED RMT STEPS OF THE ENTERGY ITC TRANSACTION 31© 2014, Energy & Resource Consulting Group, LLC
  • 32. ITC TRANSACTION – STEP 1 LLC IS CREATED 32© 2014, Energy & Resource Consulting Group, LLC
  • 33. ITC TRANSACTION – STEP 2 ENTERGY ISSUES DEBT 33© 2014, Energy & Resource Consulting Group, LLC
  • 34. ITC TRANSACTION – STEP 3 ENTERGY PAYS OFF EXISTING DEBT 34© 2014, Energy & Resource Consulting Group, LLC
  • 35. ITC TRANSACTION – STEP 4 ENTERGY REDEEMS PREFERRED STOCK 35© 2014, Energy & Resource Consulting Group, LLC
  • 36. ITC TRANSACTION – STEP 5 ENTERGY CREATES WIRES SUBSIDIARY 36© 2014, Energy & Resource Consulting Group, LLC
  • 37. ITC TRANSACTION – STEP 6 WIRE SUBS ISSUE DEBT 37© 2014, Energy & Resource Consulting Group, LLC
  • 38. ITC TRANSACTION – STEP 7 OPERATING COMPANIES BECOME LLC 38© 2014, Energy & Resource Consulting Group, LLC
  • 39. ITC TRANSACTION – STEP 7A CONTRIBUTION OF TRANSMISSION COMPANIES 39© 2014, Energy & Resource Consulting Group, LLC
  • 40. ITC TRANSACTION – STEP 8 OPERATING COS PAY EXISTING DEBT 40© 2014, Energy & Resource Consulting Group, LLC
  • 41. ITC TRANSACTION – STEP 9 WIRE SUBS TO ENTERGY 41© 2014, Energy & Resource Consulting Group, LLC
  • 42. ITC TRANSACTION – STEP 10 LLC RECEIVES TRANSMISSION ASSETS 42© 2014, Energy & Resource Consulting Group, LLC
  • 43. ITC TRANSACTION – STEP 11 WIRE SUBS TO ENTERGY 43© 2014, Energy & Resource Consulting Group, LLC
  • 44. ITC TRANSACTION – STEP 12 SPIN OFF LLC 44© 2014, Energy & Resource Consulting Group, LLC
  • 45. ITC TRANSACTION – STEP 13 REDEEM ENTERGY NOTES 45© 2014, Energy & Resource Consulting Group, LLC
  • 46. ITC TRANSACTION – STEP 14 MERGE LLC AND WIRE SUBS 46© 2014, Energy & Resource Consulting Group, LLC