Content
• Introduction
• Definitions
• Requirement of Insulations
• Determination of Line Insulation
• BIL & Insulation Level Selection of Various Equipment
• Selection of lighting arrestor
• Procedure for Insulation
• Data Required for Insulation Coordination Study
Introduction
• The selection of suitable values for the insulation levels of the various
components in any electrical system and their arrangement in a rational
manner is called insulation coordination.
• The insulation level of an apparatus is defined as that combination of
voltage values (both power frequency and impulse) which characterize it
insulation with regard to its capability of withstanding the dielectric stress
• In its simplest form, Insulation Coordination is 'The selection of insulation
strength’
Contd…
• The overall aim of insulation coordination is to reduce to an economically
and operationally acceptable level the cost and disturbance caused by
insulation failure. In insulation coordination method, the insulation of the
various parts of the system must be so graded that flash over if occurs it
must be at intended points.
Insulation Coordination- Defination
• The selection of the insulation strength of equipment in relation to the voltages,
which can appear on the system for which the equipment is intended and taking
into account the service environment and the characteristics of the available
protective devices
• Or
• Selection of the dielectric strength of equipment in relation to the operating
voltages and over-voltages which can appear on the system for which the
equipment is intended, taking into account the service environment and the
characteristics of thE available preventing and protective devices.
An Example of Insulation Coordination
• Tower Type- Steel
• Shielding wire – yes
• Line BIL – 1050KV
• Transformer BIL-850KV
• Breaker BIL – 1050 KV
• 900 KV
• Arrester
Requirement of Insulation
• Highest Power Frequency System Voltage
• The AC power network has different nominal
power frequency voltage level like 400V, 3.3KV,
6.6k, etc. When the system is lightly loaded the
power frequency voltage at the receiving end of
the line rises
• The equipment of the power system is designed
and tested to withstand under highest power
frequency system voltage (440 V, 3.6K, 7.2K,etc.)
without internal or external insulation failure
Contd…
• Transient Overvoltage Surge
• The transient over voltage surges in the
power system can be caused by lightning,
switching, restrikes travelling waves, etc. The
surge of the power system has the high peak,
high rate of rising and last for a few
tens/hundreds of microseconds and are
therefore called the transients.
BIL & insulation level selection of various
equipment's
• For each system
voltage basic
impulse insulation
level has been fixed
by most of the
national and
international
standards.
Contd…
• The major substation equipment viz, transformers, breakeis. isolating switches,
current trans formers, potential transformers are manufactured for the same
insulation level, expect where transformers may be manufacturing for a lower
step of insulation level in consideration of the economy possible.
• Sometimes, where the lightning arresters are installed right on the terminals of
transformers, some of the substation equipment may fall outside the protective
zone determined from the Withstand level of the equipment. discharge voltage of
the lightning arresters and the distance between the equipment and the lightning
arrester, and
Selection of lighting Arrestors.
• For simplify, the process of making an arrester application may be reduced to seven
steps.
• To determine the magnitude of the power frequency phase to ground voltage
expected at the proposed arrester location during phase to ground fault, or other
abnormal conditions which cause higher voltages to ground than normal
• To make a tentative selection of the power frequency voltage rating of the arrester.
This selection may have to be reconsidered after step (6) ls completed.
Power System Over-Voltages
• The power frequency voltage which may appear across an arrester becomes greater than
maximum operating phase to ground voltage for one or more of the following reasons :
1. System Fault
2. Regulation
3. Over spaced
4. Switching Transients
5. Interaction of transformer magnetizing reactance and line capacitance
6. Use of salient pole machine without damper winding
Contd…
• For the purpose of selection of voltage rating of lightning arrester three
types of earthling are considered viz.
1. Effectively earthed
2. Non Effectively earthed and
3. Isolated natural I. Effectively earthed system
Data Required for Insulation Coordination
Study
• The data collected for a study is dependent on the purpose of the study , but the
following are example of required data.
1. Collect BIL, CFO data of all insulation
2. Collect Arrester characteristics and installed location if applicable
3. Obtain one line diagram of system with distances between all insulators and
arresters
4. Insulator counts and locations in particular if a switching study is the goal.
5. Ground resistances where possible.
Thank you

More Related Content

What's hot

Power Electronics
Power Electronics Power Electronics
Power Electronics Mirza Baig
 
Simple Disconnector Switch (DS) Testing for Switchyard Equipment
Simple Disconnector Switch (DS) Testing for Switchyard EquipmentSimple Disconnector Switch (DS) Testing for Switchyard Equipment
Simple Disconnector Switch (DS) Testing for Switchyard EquipmentSARAVANAN A
 
Power System Protection
Power System ProtectionPower System Protection
Power System ProtectionRahul Mehra
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1Siswoyo Edo
 
Circuit Breaker : Types
Circuit Breaker : TypesCircuit Breaker : Types
Circuit Breaker : TypesRidwanul Hoque
 
Electrical Machine II -lecture#1_introduction
Electrical Machine II -lecture#1_introductionElectrical Machine II -lecture#1_introduction
Electrical Machine II -lecture#1_introductionmsdevildead
 
Types of starters of 3 phase induction motor
Types of starters of 3 phase induction motorTypes of starters of 3 phase induction motor
Types of starters of 3 phase induction motormpsrekha83
 
Measurement of resistance
Measurement of resistanceMeasurement of resistance
Measurement of resistanceANKUR GHEEWALA
 
STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION AND DISTRIBUTION IN BANG...
STUDY OF  ELECTRICAL POWER GENERATION,  TRANSMISSION AND DISTRIBUTION IN BANG...STUDY OF  ELECTRICAL POWER GENERATION,  TRANSMISSION AND DISTRIBUTION IN BANG...
STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION AND DISTRIBUTION IN BANG...Tania Marzia
 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability SANTOSH GADEKAR
 
Resistance,bundled conductor,skin effect,proximity effect
Resistance,bundled conductor,skin effect,proximity effectResistance,bundled conductor,skin effect,proximity effect
Resistance,bundled conductor,skin effect,proximity effectvishalgohel12195
 

What's hot (20)

Transformer
TransformerTransformer
Transformer
 
Power Electronics
Power Electronics Power Electronics
Power Electronics
 
Lightning arresters
Lightning arrestersLightning arresters
Lightning arresters
 
Simple Disconnector Switch (DS) Testing for Switchyard Equipment
Simple Disconnector Switch (DS) Testing for Switchyard EquipmentSimple Disconnector Switch (DS) Testing for Switchyard Equipment
Simple Disconnector Switch (DS) Testing for Switchyard Equipment
 
Power System Protection
Power System ProtectionPower System Protection
Power System Protection
 
Power system protection topic 1
Power system protection topic 1Power system protection topic 1
Power system protection topic 1
 
Protection and Switchgear
Protection and SwitchgearProtection and Switchgear
Protection and Switchgear
 
Circuit Breaker : Types
Circuit Breaker : TypesCircuit Breaker : Types
Circuit Breaker : Types
 
Low voltage switchgear ppt
Low voltage switchgear pptLow voltage switchgear ppt
Low voltage switchgear ppt
 
Electrical Machine II -lecture#1_introduction
Electrical Machine II -lecture#1_introductionElectrical Machine II -lecture#1_introduction
Electrical Machine II -lecture#1_introduction
 
Motor drives
Motor drivesMotor drives
Motor drives
 
Types of starters of 3 phase induction motor
Types of starters of 3 phase induction motorTypes of starters of 3 phase induction motor
Types of starters of 3 phase induction motor
 
Measurement of resistance
Measurement of resistanceMeasurement of resistance
Measurement of resistance
 
Lightning arrester
Lightning arresterLightning arrester
Lightning arrester
 
HVDC vs HVAC ppt
HVDC vs HVAC pptHVDC vs HVAC ppt
HVDC vs HVAC ppt
 
Get Knowledge About Switchgear
Get Knowledge About SwitchgearGet Knowledge About Switchgear
Get Knowledge About Switchgear
 
Megger
MeggerMegger
Megger
 
STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION AND DISTRIBUTION IN BANG...
STUDY OF  ELECTRICAL POWER GENERATION,  TRANSMISSION AND DISTRIBUTION IN BANG...STUDY OF  ELECTRICAL POWER GENERATION,  TRANSMISSION AND DISTRIBUTION IN BANG...
STUDY OF ELECTRICAL POWER GENERATION, TRANSMISSION AND DISTRIBUTION IN BANG...
 
Unit 1 Power System Stability
Unit 1 Power System Stability Unit 1 Power System Stability
Unit 1 Power System Stability
 
Resistance,bundled conductor,skin effect,proximity effect
Resistance,bundled conductor,skin effect,proximity effectResistance,bundled conductor,skin effect,proximity effect
Resistance,bundled conductor,skin effect,proximity effect
 

Similar to BIL and Insulation Coordination Study Guide

Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.Parth Patel
 
Insulation coordination
Insulation coordinationInsulation coordination
Insulation coordinationsarunkutti
 
Design of Electrical Installation of Buildings.ppt
Design of Electrical Installation of Buildings.pptDesign of Electrical Installation of Buildings.ppt
Design of Electrical Installation of Buildings.pptSameeraShaman
 
ETAP - Arcflash analysis & mitigation methods
ETAP - Arcflash analysis &  mitigation  methodsETAP - Arcflash analysis &  mitigation  methods
ETAP - Arcflash analysis & mitigation methodsHimmelstern
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxayazkhan261
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxayazkhan261
 
6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordinationRui Zhang
 
Presentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperPresentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperJyoti Rawat
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1anuphowlader1
 
Superior Tray Systems Inc.: Introduction to the Technical and Safety Aspects ...
Superior Tray Systems Inc.: Introduction to the Technical and Safety Aspects ...Superior Tray Systems Inc.: Introduction to the Technical and Safety Aspects ...
Superior Tray Systems Inc.: Introduction to the Technical and Safety Aspects ...Beatrice Wong, MBA
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodinationmichaeljmack
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordinationmichaeljmack
 
SOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsxSOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsxMohanakumarMP3
 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisPower System Operation
 
10.Electrical and Equipment Safety (1).ppt
10.Electrical and Equipment Safety (1).ppt10.Electrical and Equipment Safety (1).ppt
10.Electrical and Equipment Safety (1).pptazmatdbg3
 
10.Electrical and Equipment Safety.ppt
10.Electrical and Equipment Safety.ppt10.Electrical and Equipment Safety.ppt
10.Electrical and Equipment Safety.pptRajaMannar6
 
10.Electrical and Equipment Safety.ppt
10.Electrical and Equipment Safety.ppt10.Electrical and Equipment Safety.ppt
10.Electrical and Equipment Safety.pptanu200770
 

Similar to BIL and Insulation Coordination Study Guide (20)

Insulation coordination.
Insulation coordination.Insulation coordination.
Insulation coordination.
 
Insulation coordination
Insulation coordinationInsulation coordination
Insulation coordination
 
Design of Electrical Installation of Buildings.ppt
Design of Electrical Installation of Buildings.pptDesign of Electrical Installation of Buildings.ppt
Design of Electrical Installation of Buildings.ppt
 
ETAP - Arcflash analysis & mitigation methods
ETAP - Arcflash analysis &  mitigation  methodsETAP - Arcflash analysis &  mitigation  methods
ETAP - Arcflash analysis & mitigation methods
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptx
 
PPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptxPPT_1_Electrical services_By group no. 1.pptx
PPT_1_Electrical services_By group no. 1.pptx
 
6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination6654882 presentation-on-insulation-co ordination
6654882 presentation-on-insulation-co ordination
 
Presentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapperPresentation on Dehar power house(DPH), slapper
Presentation on Dehar power house(DPH), slapper
 
Phase 4
Phase 4Phase 4
Phase 4
 
Switchgear and protection lecture 1
Switchgear and protection lecture 1Switchgear and protection lecture 1
Switchgear and protection lecture 1
 
Superior Tray Systems Inc.: Introduction to the Technical and Safety Aspects ...
Superior Tray Systems Inc.: Introduction to the Technical and Safety Aspects ...Superior Tray Systems Inc.: Introduction to the Technical and Safety Aspects ...
Superior Tray Systems Inc.: Introduction to the Technical and Safety Aspects ...
 
Selective Coodination
Selective CoodinationSelective Coodination
Selective Coodination
 
Short Circuit, Protective Device Coordination
Short Circuit, Protective Device CoordinationShort Circuit, Protective Device Coordination
Short Circuit, Protective Device Coordination
 
SOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsxSOLAR PART 2 (1)-SHOW.ppsx
SOLAR PART 2 (1)-SHOW.ppsx
 
SOLAR PART 2 (1).pptx
SOLAR PART 2 (1).pptxSOLAR PART 2 (1).pptx
SOLAR PART 2 (1).pptx
 
Short-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash AnalysisShort-Circuit Protective Device Coordination & Arc Flash Analysis
Short-Circuit Protective Device Coordination & Arc Flash Analysis
 
10.Electrical and Equipment Safety (1).ppt
10.Electrical and Equipment Safety (1).ppt10.Electrical and Equipment Safety (1).ppt
10.Electrical and Equipment Safety (1).ppt
 
10.Electrical and Equipment Safety.ppt
10.Electrical and Equipment Safety.ppt10.Electrical and Equipment Safety.ppt
10.Electrical and Equipment Safety.ppt
 
10.Electrical and Equipment Safety.ppt
10.Electrical and Equipment Safety.ppt10.Electrical and Equipment Safety.ppt
10.Electrical and Equipment Safety.ppt
 
Mod5part1
Mod5part1Mod5part1
Mod5part1
 

Recently uploaded

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Serviceranjana rawat
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...roncy bisnoi
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)Suman Mia
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Christo Ananth
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSISrknatarajan
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSSIVASHANKAR N
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escortsranjana rawat
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...ranjana rawat
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlysanyuktamishra911
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college projectTonystark477637
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxAsutosh Ranjan
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxupamatechverse
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performancesivaprakash250
 

Recently uploaded (20)

College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINEDJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
DJARUM4D - SLOT GACOR ONLINE | SLOT DEMO ONLINE
 
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
(RIA) Call Girls Bhosari ( 7001035870 ) HI-Fi Pune Escorts Service
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)Software Development Life Cycle By  Team Orange (Dept. of Pharmacy)
Software Development Life Cycle By Team Orange (Dept. of Pharmacy)
 
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
Call for Papers - Educational Administration: Theory and Practice, E-ISSN: 21...
 
UNIT-III FMM. DIMENSIONAL ANALYSIS
UNIT-III FMM.        DIMENSIONAL ANALYSISUNIT-III FMM.        DIMENSIONAL ANALYSIS
UNIT-III FMM. DIMENSIONAL ANALYSIS
 
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLSMANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
MANUFACTURING PROCESS-II UNIT-5 NC MACHINE TOOLS
 
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur EscortsCall Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
Call Girls Service Nagpur Tanvi Call 7001035870 Meet With Nagpur Escorts
 
Roadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and RoutesRoadmap to Membership of RICS - Pathways and Routes
Roadmap to Membership of RICS - Pathways and Routes
 
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Isha Call 7001035870 Meet With Nagpur Escorts
 
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
(ANVI) Koregaon Park Call Girls Just Call 7001035870 [ Cash on Delivery ] Pun...
 
Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024Water Industry Process Automation & Control Monthly - April 2024
Water Industry Process Automation & Control Monthly - April 2024
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
KubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghlyKubeKraft presentation @CloudNativeHooghly
KubeKraft presentation @CloudNativeHooghly
 
result management system report for college project
result management system report for college projectresult management system report for college project
result management system report for college project
 
Coefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptxCoefficient of Thermal Expansion and their Importance.pptx
Coefficient of Thermal Expansion and their Importance.pptx
 
Introduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptxIntroduction to IEEE STANDARDS and its different types.pptx
Introduction to IEEE STANDARDS and its different types.pptx
 
UNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its PerformanceUNIT - IV - Air Compressors and its Performance
UNIT - IV - Air Compressors and its Performance
 

BIL and Insulation Coordination Study Guide

  • 1. BIL and Insulation Coordination Bilal Alam Department of Electrical Engineering ZH collage of Engineering and Technology AMU, Aligarh
  • 2. Content • Introduction • Definitions • Requirement of Insulations • Determination of Line Insulation • BIL & Insulation Level Selection of Various Equipment • Selection of lighting arrestor • Procedure for Insulation • Data Required for Insulation Coordination Study
  • 3. Introduction • The selection of suitable values for the insulation levels of the various components in any electrical system and their arrangement in a rational manner is called insulation coordination. • The insulation level of an apparatus is defined as that combination of voltage values (both power frequency and impulse) which characterize it insulation with regard to its capability of withstanding the dielectric stress • In its simplest form, Insulation Coordination is 'The selection of insulation strength’
  • 4. Contd… • The overall aim of insulation coordination is to reduce to an economically and operationally acceptable level the cost and disturbance caused by insulation failure. In insulation coordination method, the insulation of the various parts of the system must be so graded that flash over if occurs it must be at intended points.
  • 5. Insulation Coordination- Defination • The selection of the insulation strength of equipment in relation to the voltages, which can appear on the system for which the equipment is intended and taking into account the service environment and the characteristics of the available protective devices • Or • Selection of the dielectric strength of equipment in relation to the operating voltages and over-voltages which can appear on the system for which the equipment is intended, taking into account the service environment and the characteristics of thE available preventing and protective devices.
  • 6. An Example of Insulation Coordination • Tower Type- Steel • Shielding wire – yes • Line BIL – 1050KV • Transformer BIL-850KV • Breaker BIL – 1050 KV • 900 KV • Arrester
  • 7. Requirement of Insulation • Highest Power Frequency System Voltage • The AC power network has different nominal power frequency voltage level like 400V, 3.3KV, 6.6k, etc. When the system is lightly loaded the power frequency voltage at the receiving end of the line rises • The equipment of the power system is designed and tested to withstand under highest power frequency system voltage (440 V, 3.6K, 7.2K,etc.) without internal or external insulation failure
  • 8. Contd… • Transient Overvoltage Surge • The transient over voltage surges in the power system can be caused by lightning, switching, restrikes travelling waves, etc. The surge of the power system has the high peak, high rate of rising and last for a few tens/hundreds of microseconds and are therefore called the transients.
  • 9. BIL & insulation level selection of various equipment's • For each system voltage basic impulse insulation level has been fixed by most of the national and international standards.
  • 10. Contd… • The major substation equipment viz, transformers, breakeis. isolating switches, current trans formers, potential transformers are manufactured for the same insulation level, expect where transformers may be manufacturing for a lower step of insulation level in consideration of the economy possible. • Sometimes, where the lightning arresters are installed right on the terminals of transformers, some of the substation equipment may fall outside the protective zone determined from the Withstand level of the equipment. discharge voltage of the lightning arresters and the distance between the equipment and the lightning arrester, and
  • 11. Selection of lighting Arrestors. • For simplify, the process of making an arrester application may be reduced to seven steps. • To determine the magnitude of the power frequency phase to ground voltage expected at the proposed arrester location during phase to ground fault, or other abnormal conditions which cause higher voltages to ground than normal • To make a tentative selection of the power frequency voltage rating of the arrester. This selection may have to be reconsidered after step (6) ls completed.
  • 12. Power System Over-Voltages • The power frequency voltage which may appear across an arrester becomes greater than maximum operating phase to ground voltage for one or more of the following reasons : 1. System Fault 2. Regulation 3. Over spaced 4. Switching Transients 5. Interaction of transformer magnetizing reactance and line capacitance 6. Use of salient pole machine without damper winding
  • 13. Contd… • For the purpose of selection of voltage rating of lightning arrester three types of earthling are considered viz. 1. Effectively earthed 2. Non Effectively earthed and 3. Isolated natural I. Effectively earthed system
  • 14. Data Required for Insulation Coordination Study • The data collected for a study is dependent on the purpose of the study , but the following are example of required data. 1. Collect BIL, CFO data of all insulation 2. Collect Arrester characteristics and installed location if applicable 3. Obtain one line diagram of system with distances between all insulators and arresters 4. Insulator counts and locations in particular if a switching study is the goal. 5. Ground resistances where possible.