Wernick deliver contemporary modular buildings in the UK - education, healthcare, leisure and commercial buildings can be produced in a quality-controlled factory setting and delivered to the customer to provide a timely accommodation solution. These slides look at recent projects (2019) and the advantages of choosing a modular building versus a 'traditional' building.
Organic Name Reactions for the students and aspirants of Chemistry12th.pptx
Wernick Buildings - Delivering Offsite Construction Across the Supply Chain
1. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Delivering offsite construction across the supply chain
2. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Wernick Buildings
Part of the Wernick Group, est in 1934
Owned and run by the Wernick family
Over 700 members of staff across the UK
2018 turnover of £120m
Head office in Wickford, Essex
Manufacturing facility in Port Talbot, South
Wales
Turnkey design and build service for
relocatable and permanent modular
buildings
3. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Manufacturing facility
9 acre factory site, with 125,00sqft factory
Producing 750-1200sqm of modular buildings
per week
Modules manufactured under ISO 9001 and
ISO14001 standards
4. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Historical perception and todays challenge
5. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Offsite revolution – is the time now right for offsite and
modular to become mainstream?
6. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Wernick Swiftplan®
The future of modular buildings?
7. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Key benefits of Swiftplan®
Up to 50% shorter build times
Lower cost compared to traditional construction
Programme certainty
Factory conditions improve accuracy and quality
DFMA with near zero waste for modular production
Less noise, waste and disruption to site
Fully non-combustible wall panel system
Improved health and safety
Higher thermal mass compared to traditional light
gauge steel modular
8. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Cross laminated timber (CLT) floor
Welded hot rolled steel frame
Swiftplan® Module Design – 6 storey capability
Non-combustible wall panels
9. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Module lengths from 6m to 15m long
Maximised internal ceiling heights
3300mm to underside of structure
3600mm to underside of soffit
Swiftplan Module Design – 6 storey capability
Clear internal spans to 12m
10. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Digital design – BIM & 3D Revit
MEP
11. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Digital design – BIM & 3D Revit
12. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
DFMA – Design for manufacture and assembly
13. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
DFMA – Design for manufacture and assembly
Rapidplan® (launched 2000)
12m x 3.6m lower floor module
506 individual components
(excluding fixing and adhesives)
14. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Swiftplan® (launched 2018)
12m x 3.6m lower floor module
66 individual components
(excluding fixing and adhesives)
87% reduction in
Components used!
DFMA – Design for manufacture and assembly
15. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Two storey 1,000sqm
office block
24 no. Swiftplan modules,
plus portal frame lobby
Breeam Excellent
Case Study - Wernick Group Head Office, Essex
16. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Specific Active Office
17. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Specific Active Office
18. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Specific Active Office
Lots of photos
19. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Building Energy
U values: Floor 0.12 W/m2k
Walls 0.18 W/m2k
Roof 0.15 W/m2k
Windows 1.6 W/m2k
Air permeability 3.2 m3/hr.m2 @ 50Pa
PV generation 10kw
Building emission rate 8.07 KgCO2/m2 per year
Achieved EPC “A” 14
20. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Energy – Thermographic survey of the Swiftplan system
21. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Waste materials
Breeam Excellent target 19kg/m2
Wickford Head Office: 1,000sqm two storey office
Module manufacture: 262 kg = 0.262 kg/m2
Factory module fit out: 4,071 kg = 4.071 kg/m2
Site fit out: 11,080 kg = 11.08 kg/m2
Total waste generated = 15.151 kg/m2
Percentage of waste recycled
and diverted from landfill = 98%
22. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Total project cost £2.175m (£2,175/m2)
Fees (planning, design, BR etc.) 1.0%
Site prelims 4.0%
Modular building (factory) 40%
Modular site fit out 26%
MEP 13%
Delivery & Install 3.5%
External & site works 9.0%
Breeam excellent upgrade 3.5%
23. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Total project cost £2.175m (£2,175/m2)
Fees (planning, design, BR etc.) 1.0%
Site prelims 4.0%
Modular building (factory) 40%
Modular site fit out 26%
MEP 13%
Delivery & Install 3.5%
External & site works 9.0%
Breeam excellent upgrade 3.5%
24. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Case Study – Swansea University lecture block
Two storey 2,700sqm
lecture block
60 no. Swiftplan
modules
16 week site fitout
programme
25. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Early Engagement
Active office 2018
26. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Concept
design
Planning
Detailed
design
Appoint
Contractors
Concept
design
Choose
modular
contractor
Planning
Detailed
design
Early Engagement
27. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Design
External shot
28. Presentation for Supply Chain Sustainability School – Nov 2019
Andy King – Deputy Managing Director
®
Programme
Enquiry received – December 2018
Order placed – March 2019
Start on site – June 2019
Module delivery – June 2019
Handover – November 2019