SlideShare a Scribd company logo
1 of 39
Bajaj Energy Pvt. Ltd.
2×45 MW IPP
Unit: Barkhera
WELCOME
BEPL Barkhera
“CFBC Boiler Operation”
Present by
Subodh kandwal
BOILER DEFINITION
A Boiler is a device used for generating steam for
Power generation , process use or heating purposes.
According to IBR Act 1923,a boiler is a closed pressure
vessel with capacity exceeding 22.75 Liters used for
generating steam under pressure.
BOILER CONFIGURATION
• Natural Circulation, Single Drum, Top Supported, Balanced Draft, Tower
Type, Membrane Panel Constructed, Outdoor Unit Equipped with Two
Cyclones, having Economizer and Tubular Airpreheater as back end heat
traps and 2x 60% Draught Plant (Primary Air fan, Secondary Air Fan and
Induced Draught Fan).
Water & Steam Circuit (Schematic Diagram)
In general the heat absorbing parts subject to internal pressure in a boiler will
be called as pressure parts. The main pressure parts in a boiler are as follows
:-
– Drums
– Water walls
– Super heaters
– Economizers
– Evaporators
– Screen Tubes
• First pass:-The Drum, Down comers, evaporators, economizer, water
wall headers and water walls will form the circulation system and cover
the furnace zone, in which the water is converted into steam-water
mixture at the same temperature, by absorbing the radiant heat in the
furnace zone. The furnace walls form the enclosure to the first pass.
• Second pass:-The second pass enclosures, in which the temperature of
the water is raised to the required level by a combination of radiation &
convection process. Economiser coils are located in the second pass. Along
with Tubular type Air Pre Heater.
Copyright © 2014 Bajaj Energy Pvt. Ltd. 6
• The down comers carry the water from the drum to the bottom ring
headers. The water at high temperature flows through the furnace
walls from the headers. Heat transfer takes place through the
water wall tubes and the fluid raises to the top headers from where
the steam-water mixture is transmitted to the drum.
• The drum provides the necessary space for locating the steam
separating equipments for separation of steam from mixture of
steam and water. It also serves as a reservoir for the supply of water
to circulation system to avoid possible starvation during operation.
• Super heaters are used to raise the steam temperature above the
saturation temperature by absorbing heat from flue gas to increase
the cycle efficiency. For utility boilers which are meant for power
generation, the super heater outlet temperature is limited to 535 ̊C
due to metallurgical considerations.
• Economizers are used to absorb heat from the flue gases and add
this as sensible heat to the feed water before water enters the
evaporation circuit of the boiler.
Copyright © 2014 Bajaj Energy Pvt. Ltd. 7
Types of water circulation in boiler
The water circulation in the boiler may be
natural circulation due to density difference or
by force circulation with the help of pumps.
• Natural circulation
• Forced circulation
Natural Circulation type Steam Generator (Basic Circuit
Diagram)
pressure
density
Critical pressure
221.2bar
water
steam
Density difference
Density vs pressure curve
Types of Fluidised Bed Combustion Boilers
There are three basic types of fluidised bed combustion boilers:
1. Atmospheric classic Fluidised Bed Combustion System
(AFBC)
2. Pressurised Fluidised Bed Combustion System (PFBC).
3. Circulating (fast) Fluidised Bed Combustion system(CFBC)
Deepak Rana, Bajaj Energy Ltd - Barkhera
Circulating (fast) Fluidised Bed Combustion system(CFBC)
This CFBC technology utilizes the fluidized bed principle in which crushed (6 –
12 mm size) fuel and limestone are injected into the furnace or combustor.
The particles are suspended in a stream of upwardly flowing air (60-70% of
the total air), which enters the bottom of the furnace through air distribution
nozzles. The fluidising velocity in circulating beds ranges from 3.7 to 9 m/sec.
The balance of combustion air is admitted above the bottom of the furnace as
secondary air.
Since limestone is used as particle bed, control of sulfur dioxide and nitrogen oxide
emissions in the combustion chamber is achieved without any additional control
equipment. This is one of the major advantages over conventional boilers.
Deepak Rana, Bajaj Energy Ltd - Barkhera
Circulating Fluidized Bed
At the bottom of the boiler furnace
there is a bed of inert material. Bed is
where the coal or fuel spreads. Air
supply is from under the bed at high
pressure. This lifts the bed material and
the coal particles and keeps it in
suspension. The coal combustion takes
place in this suspended condition. This
is the Fluidized bed.
Special design of the air nozzles at the
bottom of the bed allows air flow
without clogging. Primary air fans
provide the preheated Fluidizing air.
Secondary air fans provide pre-heated
Combustion air. Nozzles in the furnace
walls at various levels distribute the
Combustion air in the furnace
Deepak Rana, Bajaj Energy Ltd - Barkhera
Circulating Fluidized Bed
At the bottom of the boiler furnace there is a
bed of inert material. Bed is where the coal
or fuel spreads. Air supply is from under the
bed at high pressure. This lifts the bed
material and the coal particles and keeps it
in suspension. The coal combustion takes
place in this suspended condition. This is the
Fluidized bed.
Special design of the air nozzles at the
bottom of the bed allows air flow without
clogging. Primary air fans provide the
preheated Fluidizing air. Secondary air fans
provide pre-heated Combustion air. Nozzles
in the furnace walls at various levels
distribute the Combustion air in the furnace
Circulation
Fine particles of partly burned coal, ash and bed material are carried along with the
flue gases to the upper areas of the furnace and then into a cyclone. In the cyclone the
heavier particles separate from the gas and falls to the hopper of the cyclone. This
returns to the furnace for recirculation. Hence the name Circulating Fluidized Bed
combustion. The hot gases from the cyclone pass to the heat transfer surfaces and go
out of the boiler.
Bed Material
To start with the bed material is sand. Some portion is lost in the ash during the
operation and this has to be made-up. In coal fired boilers the ash from the coal itself
will be the makeup material. When firing bio fuels with very low ash content sand will
be the makeup bed material. For high Sulphur coals Limestone addition to the bed
material reduces SO2 emissions.
CFBC uses crushed coal of 3 to 6 mm size. This requires only a crusher not a
pulverizer. From storage hoppers Conveyer and feeders transport the coal to feed
chutes in the furnace. Start up is by oil burners in the furnace. Ash spouts in the
furnace remove the ash from the bottom of the furnace.
Deepak Rana, Bajaj Energy Ltd - Barkhera
Deepak Rana, Bajaj Energy Ltd - Barkhera
• Type of Cyclone:-
• 1. Hot cyclone ( Temp around 800-850 degree)
• 2. cold cyclone (Temp around 400-450 degree)
• 3. U Beam cyclone (Temp around similar to bed temp.)
• Hot Cyclone:- Hot cyclone generally use for low volatile matter and high
ash content coal. It helps during low reactivity as heat absorbed by hot
cyclone helps to burn this type of fuel.
• Cold Cyclone:- Cold Cyclone generally use for high volatile matter and low
ash content coal.
• U Beam Cyclone:- This type of cyclone is generally used for High volatile
matter and low ash content coal.
Deepak Rana, Bajaj Energy Ltd - Barkhera
In general the heat absorbing parts subject to internal pressure in a boiler
will be called as pressure parts. The main pressure parts in a boiler are as
follows :-
– Drums
– Water walls
– Super heaters
– Economizers
– Evaporators
– Screen Tubes
• The Drum, Down comers, evaporators, economizer, water wall headers
and water walls will form the circulation system and cover the furnace
zone, in which the water is converted into steam-water mixture at the
same temperature, by absorbing the radiant heat in the furnace zone.
The furnace walls form the enclosure to the first pass.
• The second pass enclosures, in which the temperature of the water is
raised to the required level by a combination of radiation & convection
process. Economiser coils are located in the second pass. Along with
Tubular type Air Pre Heater.
Deepak Rana, Bajaj Energy Ltd - Barkhera
• The drum provides the necessary space for locating the steam separating
equipments for separation of steam from mixture of steam and water. It
also serves as a reservoir for the supply of water to circulation system to
avoid possible starvation during operation.
• The down comers carry the water from the drum to the bottom ring
headers. The water at high temperature flows through the furnace walls
from the headers. Heat transfer takes place through the water wall tubes
and the fluid raises to the top headers from where the steam-water
mixture is transmitted to the drum.
• Super heaters are used to raise the steam temperature above the
saturation temperature by absorbing heat from flue gas to increase the
cycle efficiency. For utility boilers which are meant for power generation,
the super heater outlet temperature is limited to 535 ̊C due to
metallurgical considerations.
• Economizers are used to absorb heat from the flue gases and add this as
sensible heat to the feed water before water enters the evaporation circuit
of the boiler.
Deepak Rana, Bajaj Energy Ltd - Barkhera
 Induced Draught (ID) Fan :
 Secondary Air (SA) Fan :
Starting PA Fans:
For starting of the PA Fan, SA fan should be running for the last
5min with SA flow more than 6kg/cm2.
• Ensure CO Vent is Open, Before starting PA fan, check the physical
condition of the valve in the field also.
• Ensure supply and control power is on, all bearings with proper
lubrication, free movement of the dampers and cleanness of the
area.
• Ensure fluidizing air line to siphon are is open condition.
• Ensure proper oxygen and CO level at Economiser inlet. Before
starting of PA fan CO level at economiser inlet shell be less than
300ppm and oxygen at PA duct should be grater than 18%
• Drum level is normal and boiler air protection is ok.
• Ensure inlet and outlet dampers of PA Fans are closed condition.
• Start one PA fan and instruct site operator to observe any abnormal
sound / vibration / abnormal heating / rubbing of the rotating parts.
Copyright © 2014 Bajaj Energy Pvt. Ltd. 21
• Primary Air (PA) Fan :
Operation of HGG
Pre- Start-Up Checks For Burner Start-Up
• Opening/closing of air slide damper for all the burners are smooth with
complete travel.
• Verify cooling air to scanners and peep holes are available.
• Verify the operation of fuel oil control valve opening and closing.
• All instruments for measurement of oil pressure, flow and temperature are
in service.
• Burner Start Up Procedure:
• Starts any one of the oil pump and maintain the rated oil pressure >10
kg/cm2
• Before starting the burner, the pre-interlocks, main interlocks purge
interlocks & oil firing permissive are to be satisfied as per BMS logic like as:
• LDO pressure > 6kg/cm2
• Atomising air pressure >7kg/cm2
• LPG Pressure >1kg/cm2
• Combustion air flow > 15TPH
• Differential across the HGG <25 mmWC
Copyright © 2014 Bajaj Energy Pvt. Ltd. 23
• Burner Start PB Operated
• Following Cycle will be initiated:
• Step – 1
• LPG Gas valve will open and LPG Timer 35 secs count started Atomizing
Air Valve will Open, Igniter Energized and Igniter Timer 15 secs count
started. Oil valve will Open 5 secs after Start command And Flame is ON.
• Step – 2
• Ignition Timer Over and Igniter De-Energized, LPG Valve closes after 35
sec timer is over.
• The Main burner is lighted up keeping oil flow around 150 kg/hr.
• In case the Oil does not catch fire during this period the whole sequence
is to start again.
• The combustion air damper is to be adjusted to the predetermined “air-
fuel oil ratio” for efficient combustion and to keep the flame healthy.
• Keep dilution air quantity sufficient to maintain HGG outlet gas
temperature at around 350 ̊C initially
• start raising the oil flow till it reaches around 900 kg/hr. Open
dilution air damper such that HGG outlet gas temperature rises
gradually and does not exceed 850 ̊C in any case
• Both HGGs should not be started together. After approximately 15
minutes of stabilised operation of one HGG, second should be
started.
• Start Boiler feed pump for maintaining Drum level.
• Initially, Superheater drain valves are kept open, along with drum
and Superheater vent valves. When drum pressure exceeds 2
kg/cm², drum vent valve and Superheater vent valves should be
closed.
• Once drum pressure reaches approx. 5 kg/cm², Superheater
drain valves are kept partially open for allowing steam flow
through the Superheaters.
• At approximately 8 to 10 kg/cm² drum pressure, close all S/H
drains and partially open start up vent valves such that drum
pressure increase is kept within permissible gradient 2 kg/cm²
(g) per minute.
• This will allow steam flow through the super-heaters and final
steam temperature will also increase as per requirement.
Copyright © 2014 Bajaj Energy Pvt. Ltd. 27
• During pressure raising the water level will
normally rise to the top of gauge glasses as steam
pressure is increased. This is due to expansion in
volume of water due to heat transfer and
circulation.
• The excess water from system should be removed
by blow down.
• While giving the blow-down, do not keep the
blow-down valves open for more than 20
seconds. The blow-down normally should be
given with quick open/close operation
• Main fuel (coal) is charged after temperature of bed material exceeds
ignition temperature(550 deg. c) of the fuel and all other boiler
interlocks are fulfilled.
• Due to cold fuel, initially there is slight "dip" in bed temperature. If
coal combustion has been established. Take another coal feeder into
service adjust PA and SA as per Requirement. after the bed
temperature exceeds 700°C, gradually reduce the oil flow to about
250 kg/hr and then smoothly trip the HGGs one after another. Now
both coal feeder in service and maintain bed temperature<800deg.
And raise main steam pressure.
• Once the fuel firing through both the streams is established and HGGs
switched off. The HGG Bypass damper should be opened gradually.
combustion and dilution damper closed.
Deepak Rana, Bajaj Energy Ltd - Barkhera
• When main steam pressure came 25kg/cm2. First,
open by-pass valve of main steam stop valve.
• Allow steam to flow for sufficient time to warm up
main steam piping.
• Open main steam stop valve and subsequently
close by-pass valve.
• Now steam charged up to CSDH.
 Safety Valves :
Boiler Trip Logics
Protection conditions Alarm Value Trip value Remarks
1. Furnace Pr very HI >50 mmwc >100 mmwc PA,SA, CF TRIP, selected ID trip.
2. Furnace Pr very low <-80 mmwc <-150 mmwc Both ID fans trips if both are
running
3. Furnace pr. Very low <-80 mmwc <-250 mmwc After selected ID trips and
another
ID fan running.
4. Drum level Very HI >64% >74% ONLY PA TRIP, selected ID trip.
5. Drum level Very low <30% <10% ONLY PA TRIP, selected ID trip.
6. Total PA flow< minimum <20 Kg/sec <15 Kg/Sec ONLY DCF TRIP
7. Bed height very low <800 mm <500 mm ONLY DCF TRIP
8. Bed height very high >1200 mmwc >1400 mmwc ONLY DCF TRIP
9. Both ID fans tripped
10. MFT operated ONLY DCF TRIP
NOT IN GRAPHICS
Deepak Rana, Bajaj Energy Ltd - Barkhera
Remark if any
• Total PA flow once reach above 20 kg/sec then it reduced to below 15 kg/sec then only DCF will trip.
•Bed height once reaches above 1000mm then it reduced to below 600mm then only DCF will trip.
Thanks to you all

More Related Content

What's hot

Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesBoben Anto Chemmannoor
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operationNitin Patel
 
Thermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingThermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingManohar Tatwawadi
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protectionanujkumarsingh79
 
Unit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownUnit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownAshvani Shukla
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergenciesManohar Tatwawadi
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineManohar Tatwawadi
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations Ashish Kumar Jain
 
AFBC BOILERS PERFORMANCE IMPROVEMENT
AFBC BOILERS PERFORMANCE IMPROVEMENTAFBC BOILERS PERFORMANCE IMPROVEMENT
AFBC BOILERS PERFORMANCE IMPROVEMENTManohar Tatwawadi
 
Feed water and condensate heaters
Feed water and condensate heatersFeed water and condensate heaters
Feed water and condensate heatersManohar Tatwawadi
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsSHIVAJI CHOUDHURY
 
Case studies in boiler vibration and BFP cavitation by k.k.parthiban
Case studies in boiler vibration and BFP cavitation by k.k.parthibanCase studies in boiler vibration and BFP cavitation by k.k.parthiban
Case studies in boiler vibration and BFP cavitation by k.k.parthibanVENUS ENERGY AUDIT SYSTEM
 
Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation Sawan Vaja
 
Improve plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlImprove plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlHossam Zein
 
Cfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenanceCfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenancePichai Chaibamrung
 

What's hot (20)

Hp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbinesHp/ lp bypass system for steam turbines
Hp/ lp bypass system for steam turbines
 
Unit shutdown procedure operation
Unit shutdown procedure operationUnit shutdown procedure operation
Unit shutdown procedure operation
 
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
FURNACE SAFEGUARD SUPERVISORY SYSTEM (FSSS)
 
Boiler Operation
Boiler OperationBoiler Operation
Boiler Operation
 
Thermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations TrainingThermal Power Plant Simulator Operations Training
Thermal Power Plant Simulator Operations Training
 
Boiler Reheater protection
Boiler Reheater  protectionBoiler Reheater  protection
Boiler Reheater protection
 
Unit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdownUnit lightup synchronisation &amp; shutdown
Unit lightup synchronisation &amp; shutdown
 
Handling of turbine during emergencies
Handling of turbine during emergenciesHandling of turbine during emergencies
Handling of turbine during emergencies
 
Super critical boiler
Super critical boilerSuper critical boiler
Super critical boiler
 
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam TurbineThermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
Thermal Power Plant Simulator, Cold, warm and Hot rolling of Steam Turbine
 
Condensate system
Condensate systemCondensate system
Condensate system
 
Boiler Introduction
Boiler IntroductionBoiler Introduction
Boiler Introduction
 
Thermal Power Plant - Emergency situations
Thermal Power Plant   -   Emergency situations Thermal Power Plant   -   Emergency situations
Thermal Power Plant - Emergency situations
 
AFBC BOILERS PERFORMANCE IMPROVEMENT
AFBC BOILERS PERFORMANCE IMPROVEMENTAFBC BOILERS PERFORMANCE IMPROVEMENT
AFBC BOILERS PERFORMANCE IMPROVEMENT
 
Feed water and condensate heaters
Feed water and condensate heatersFeed water and condensate heaters
Feed water and condensate heaters
 
Feedwater heaters in thermal power plants
Feedwater heaters in thermal power plantsFeedwater heaters in thermal power plants
Feedwater heaters in thermal power plants
 
Case studies in boiler vibration and BFP cavitation by k.k.parthiban
Case studies in boiler vibration and BFP cavitation by k.k.parthibanCase studies in boiler vibration and BFP cavitation by k.k.parthiban
Case studies in boiler vibration and BFP cavitation by k.k.parthiban
 
Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation Circulating fluidizing bed combustion Boiler presentation
Circulating fluidizing bed combustion Boiler presentation
 
Improve plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater controlImprove plant heat rate with feedwater heater control
Improve plant heat rate with feedwater heater control
 
Cfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenanceCfb boiler basic design, operation and maintenance
Cfb boiler basic design, operation and maintenance
 

Similar to CFBC Boiler Operation

Boilers ps mrng sessn
Boilers ps mrng sessnBoilers ps mrng sessn
Boilers ps mrng sessnInes Kkumar
 
Boilers ps mrng sessn
Boilers ps mrng sessnBoilers ps mrng sessn
Boilers ps mrng sessnInes Kkumar
 
Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01arvind singh rathore
 
Kota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTUKota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTUManohar Nagar
 
Coal fired electric power plants23
Coal fired electric power plants23Coal fired electric power plants23
Coal fired electric power plants23Munna Sagar
 
Tpp summer pro rep
Tpp summer pro repTpp summer pro rep
Tpp summer pro repRohit Anand
 
MET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsMET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsIbrahim AboKhalil
 
UNIT-1-Steam Power Plant.pptx
UNIT-1-Steam Power Plant.pptxUNIT-1-Steam Power Plant.pptx
UNIT-1-Steam Power Plant.pptxprakash0712
 
2013edusat lecture on steam plant(2)
2013edusat lecture on steam  plant(2)2013edusat lecture on steam  plant(2)
2013edusat lecture on steam plant(2)iimt college meerut
 
Steam-Power-Plant-updated.pdf engineering students
Steam-Power-Plant-updated.pdf engineering studentsSteam-Power-Plant-updated.pdf engineering students
Steam-Power-Plant-updated.pdf engineering studentsashokpradhan23
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)sometech
 
Steam boilers
Steam boilersSteam boilers
Steam boilerssing367
 
STEAM GENERATORS.pptx
STEAM GENERATORS.pptxSTEAM GENERATORS.pptx
STEAM GENERATORS.pptxssusere6313f
 
Overview of Thermal Power Plants
Overview of Thermal Power PlantsOverview of Thermal Power Plants
Overview of Thermal Power PlantsDebajyoti Bose
 
Ipe301 e steam generation unit
Ipe301 e steam generation unitIpe301 e steam generation unit
Ipe301 e steam generation unitK. M.
 
Thermal Power Station
Thermal Power StationThermal Power Station
Thermal Power StationDinesh Sharma
 

Similar to CFBC Boiler Operation (20)

Boilers ps mrng sessn
Boilers ps mrng sessnBoilers ps mrng sessn
Boilers ps mrng sessn
 
Boilers ps mrng sessn
Boilers ps mrng sessnBoilers ps mrng sessn
Boilers ps mrng sessn
 
Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01Coalfiredelectricpowerplants23 131208122612-phpapp01
Coalfiredelectricpowerplants23 131208122612-phpapp01
 
Kota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTUKota super thermal power plant,kstps ppt,RTU
Kota super thermal power plant,kstps ppt,RTU
 
Coal fired electric power plants23
Coal fired electric power plants23Coal fired electric power plants23
Coal fired electric power plants23
 
Tpp summer pro rep
Tpp summer pro repTpp summer pro rep
Tpp summer pro rep
 
THERMAL
THERMALTHERMAL
THERMAL
 
MET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generatorsMET 401 Chapter 4 boilers_and_steam_generators
MET 401 Chapter 4 boilers_and_steam_generators
 
UNIT-1-Steam Power Plant.pptx
UNIT-1-Steam Power Plant.pptxUNIT-1-Steam Power Plant.pptx
UNIT-1-Steam Power Plant.pptx
 
lecture on steam plant
 lecture on steam  plant lecture on steam  plant
lecture on steam plant
 
2013edusat lecture on steam plant(2)
2013edusat lecture on steam  plant(2)2013edusat lecture on steam  plant(2)
2013edusat lecture on steam plant(2)
 
Steam-Power-Plant-updated.pdf engineering students
Steam-Power-Plant-updated.pdf engineering studentsSteam-Power-Plant-updated.pdf engineering students
Steam-Power-Plant-updated.pdf engineering students
 
Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)Thermal Plant report (Mechanical)
Thermal Plant report (Mechanical)
 
Steam boilers
Steam boilersSteam boilers
Steam boilers
 
STEAM GENERATORS.pptx
STEAM GENERATORS.pptxSTEAM GENERATORS.pptx
STEAM GENERATORS.pptx
 
Overview of Thermal Power Plants
Overview of Thermal Power PlantsOverview of Thermal Power Plants
Overview of Thermal Power Plants
 
Ipe301 e steam generation unit
Ipe301 e steam generation unitIpe301 e steam generation unit
Ipe301 e steam generation unit
 
Thermal Power Station
Thermal Power StationThermal Power Station
Thermal Power Station
 
boilers
boilersboilers
boilers
 
Steam Power Plant and Components
Steam Power Plant and ComponentsSteam Power Plant and Components
Steam Power Plant and Components
 

Recently uploaded

Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii SoldatenkoFwdays
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsRizwan Syed
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationSlibray Presentation
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfAddepto
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brandgvaughan
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024Lorenzo Miniero
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationRidwan Fadjar
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...shyamraj55
 
Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfjimielynbastida
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitecturePixlogix Infotech
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebUiPathCommunity
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfAlex Barbosa Coqueiro
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 

Recently uploaded (20)

Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko"Debugging python applications inside k8s environment", Andrii Soldatenko
"Debugging python applications inside k8s environment", Andrii Soldatenko
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
Scanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL CertsScanning the Internet for External Cloud Exposures via SSL Certs
Scanning the Internet for External Cloud Exposures via SSL Certs
 
Connect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck PresentationConnect Wave/ connectwave Pitch Deck Presentation
Connect Wave/ connectwave Pitch Deck Presentation
 
Gen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdfGen AI in Business - Global Trends Report 2024.pdf
Gen AI in Business - Global Trends Report 2024.pdf
 
WordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your BrandWordPress Websites for Engineers: Elevate Your Brand
WordPress Websites for Engineers: Elevate Your Brand
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024SIP trunking in Janus @ Kamailio World 2024
SIP trunking in Janus @ Kamailio World 2024
 
My Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 PresentationMy Hashitalk Indonesia April 2024 Presentation
My Hashitalk Indonesia April 2024 Presentation
 
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
Automating Business Process via MuleSoft Composer | Bangalore MuleSoft Meetup...
 
Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdf
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Understanding the Laravel MVC Architecture
Understanding the Laravel MVC ArchitectureUnderstanding the Laravel MVC Architecture
Understanding the Laravel MVC Architecture
 
Dev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio WebDev Dives: Streamline document processing with UiPath Studio Web
Dev Dives: Streamline document processing with UiPath Studio Web
 
Unraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdfUnraveling Multimodality with Large Language Models.pdf
Unraveling Multimodality with Large Language Models.pdf
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 

CFBC Boiler Operation

  • 1. Bajaj Energy Pvt. Ltd. 2×45 MW IPP Unit: Barkhera WELCOME BEPL Barkhera “CFBC Boiler Operation” Present by Subodh kandwal
  • 2.
  • 3. BOILER DEFINITION A Boiler is a device used for generating steam for Power generation , process use or heating purposes. According to IBR Act 1923,a boiler is a closed pressure vessel with capacity exceeding 22.75 Liters used for generating steam under pressure.
  • 4. BOILER CONFIGURATION • Natural Circulation, Single Drum, Top Supported, Balanced Draft, Tower Type, Membrane Panel Constructed, Outdoor Unit Equipped with Two Cyclones, having Economizer and Tubular Airpreheater as back end heat traps and 2x 60% Draught Plant (Primary Air fan, Secondary Air Fan and Induced Draught Fan).
  • 5. Water & Steam Circuit (Schematic Diagram)
  • 6. In general the heat absorbing parts subject to internal pressure in a boiler will be called as pressure parts. The main pressure parts in a boiler are as follows :- – Drums – Water walls – Super heaters – Economizers – Evaporators – Screen Tubes • First pass:-The Drum, Down comers, evaporators, economizer, water wall headers and water walls will form the circulation system and cover the furnace zone, in which the water is converted into steam-water mixture at the same temperature, by absorbing the radiant heat in the furnace zone. The furnace walls form the enclosure to the first pass. • Second pass:-The second pass enclosures, in which the temperature of the water is raised to the required level by a combination of radiation & convection process. Economiser coils are located in the second pass. Along with Tubular type Air Pre Heater. Copyright © 2014 Bajaj Energy Pvt. Ltd. 6
  • 7. • The down comers carry the water from the drum to the bottom ring headers. The water at high temperature flows through the furnace walls from the headers. Heat transfer takes place through the water wall tubes and the fluid raises to the top headers from where the steam-water mixture is transmitted to the drum. • The drum provides the necessary space for locating the steam separating equipments for separation of steam from mixture of steam and water. It also serves as a reservoir for the supply of water to circulation system to avoid possible starvation during operation. • Super heaters are used to raise the steam temperature above the saturation temperature by absorbing heat from flue gas to increase the cycle efficiency. For utility boilers which are meant for power generation, the super heater outlet temperature is limited to 535 ̊C due to metallurgical considerations. • Economizers are used to absorb heat from the flue gases and add this as sensible heat to the feed water before water enters the evaporation circuit of the boiler. Copyright © 2014 Bajaj Energy Pvt. Ltd. 7
  • 8. Types of water circulation in boiler The water circulation in the boiler may be natural circulation due to density difference or by force circulation with the help of pumps. • Natural circulation • Forced circulation
  • 9. Natural Circulation type Steam Generator (Basic Circuit Diagram)
  • 11. Types of Fluidised Bed Combustion Boilers There are three basic types of fluidised bed combustion boilers: 1. Atmospheric classic Fluidised Bed Combustion System (AFBC) 2. Pressurised Fluidised Bed Combustion System (PFBC). 3. Circulating (fast) Fluidised Bed Combustion system(CFBC) Deepak Rana, Bajaj Energy Ltd - Barkhera
  • 12. Circulating (fast) Fluidised Bed Combustion system(CFBC) This CFBC technology utilizes the fluidized bed principle in which crushed (6 – 12 mm size) fuel and limestone are injected into the furnace or combustor. The particles are suspended in a stream of upwardly flowing air (60-70% of the total air), which enters the bottom of the furnace through air distribution nozzles. The fluidising velocity in circulating beds ranges from 3.7 to 9 m/sec. The balance of combustion air is admitted above the bottom of the furnace as secondary air. Since limestone is used as particle bed, control of sulfur dioxide and nitrogen oxide emissions in the combustion chamber is achieved without any additional control equipment. This is one of the major advantages over conventional boilers. Deepak Rana, Bajaj Energy Ltd - Barkhera
  • 13. Circulating Fluidized Bed At the bottom of the boiler furnace there is a bed of inert material. Bed is where the coal or fuel spreads. Air supply is from under the bed at high pressure. This lifts the bed material and the coal particles and keeps it in suspension. The coal combustion takes place in this suspended condition. This is the Fluidized bed. Special design of the air nozzles at the bottom of the bed allows air flow without clogging. Primary air fans provide the preheated Fluidizing air. Secondary air fans provide pre-heated Combustion air. Nozzles in the furnace walls at various levels distribute the Combustion air in the furnace Deepak Rana, Bajaj Energy Ltd - Barkhera Circulating Fluidized Bed At the bottom of the boiler furnace there is a bed of inert material. Bed is where the coal or fuel spreads. Air supply is from under the bed at high pressure. This lifts the bed material and the coal particles and keeps it in suspension. The coal combustion takes place in this suspended condition. This is the Fluidized bed. Special design of the air nozzles at the bottom of the bed allows air flow without clogging. Primary air fans provide the preheated Fluidizing air. Secondary air fans provide pre-heated Combustion air. Nozzles in the furnace walls at various levels distribute the Combustion air in the furnace
  • 14. Circulation Fine particles of partly burned coal, ash and bed material are carried along with the flue gases to the upper areas of the furnace and then into a cyclone. In the cyclone the heavier particles separate from the gas and falls to the hopper of the cyclone. This returns to the furnace for recirculation. Hence the name Circulating Fluidized Bed combustion. The hot gases from the cyclone pass to the heat transfer surfaces and go out of the boiler. Bed Material To start with the bed material is sand. Some portion is lost in the ash during the operation and this has to be made-up. In coal fired boilers the ash from the coal itself will be the makeup material. When firing bio fuels with very low ash content sand will be the makeup bed material. For high Sulphur coals Limestone addition to the bed material reduces SO2 emissions. CFBC uses crushed coal of 3 to 6 mm size. This requires only a crusher not a pulverizer. From storage hoppers Conveyer and feeders transport the coal to feed chutes in the furnace. Start up is by oil burners in the furnace. Ash spouts in the furnace remove the ash from the bottom of the furnace. Deepak Rana, Bajaj Energy Ltd - Barkhera
  • 15. Deepak Rana, Bajaj Energy Ltd - Barkhera
  • 16. • Type of Cyclone:- • 1. Hot cyclone ( Temp around 800-850 degree) • 2. cold cyclone (Temp around 400-450 degree) • 3. U Beam cyclone (Temp around similar to bed temp.) • Hot Cyclone:- Hot cyclone generally use for low volatile matter and high ash content coal. It helps during low reactivity as heat absorbed by hot cyclone helps to burn this type of fuel. • Cold Cyclone:- Cold Cyclone generally use for high volatile matter and low ash content coal. • U Beam Cyclone:- This type of cyclone is generally used for High volatile matter and low ash content coal. Deepak Rana, Bajaj Energy Ltd - Barkhera
  • 17. In general the heat absorbing parts subject to internal pressure in a boiler will be called as pressure parts. The main pressure parts in a boiler are as follows :- – Drums – Water walls – Super heaters – Economizers – Evaporators – Screen Tubes • The Drum, Down comers, evaporators, economizer, water wall headers and water walls will form the circulation system and cover the furnace zone, in which the water is converted into steam-water mixture at the same temperature, by absorbing the radiant heat in the furnace zone. The furnace walls form the enclosure to the first pass. • The second pass enclosures, in which the temperature of the water is raised to the required level by a combination of radiation & convection process. Economiser coils are located in the second pass. Along with Tubular type Air Pre Heater. Deepak Rana, Bajaj Energy Ltd - Barkhera
  • 18. • The drum provides the necessary space for locating the steam separating equipments for separation of steam from mixture of steam and water. It also serves as a reservoir for the supply of water to circulation system to avoid possible starvation during operation. • The down comers carry the water from the drum to the bottom ring headers. The water at high temperature flows through the furnace walls from the headers. Heat transfer takes place through the water wall tubes and the fluid raises to the top headers from where the steam-water mixture is transmitted to the drum. • Super heaters are used to raise the steam temperature above the saturation temperature by absorbing heat from flue gas to increase the cycle efficiency. For utility boilers which are meant for power generation, the super heater outlet temperature is limited to 535 ̊C due to metallurgical considerations. • Economizers are used to absorb heat from the flue gases and add this as sensible heat to the feed water before water enters the evaporation circuit of the boiler. Deepak Rana, Bajaj Energy Ltd - Barkhera
  • 19.  Induced Draught (ID) Fan :
  • 20.  Secondary Air (SA) Fan :
  • 21. Starting PA Fans: For starting of the PA Fan, SA fan should be running for the last 5min with SA flow more than 6kg/cm2. • Ensure CO Vent is Open, Before starting PA fan, check the physical condition of the valve in the field also. • Ensure supply and control power is on, all bearings with proper lubrication, free movement of the dampers and cleanness of the area. • Ensure fluidizing air line to siphon are is open condition. • Ensure proper oxygen and CO level at Economiser inlet. Before starting of PA fan CO level at economiser inlet shell be less than 300ppm and oxygen at PA duct should be grater than 18% • Drum level is normal and boiler air protection is ok. • Ensure inlet and outlet dampers of PA Fans are closed condition. • Start one PA fan and instruct site operator to observe any abnormal sound / vibration / abnormal heating / rubbing of the rotating parts. Copyright © 2014 Bajaj Energy Pvt. Ltd. 21
  • 22. • Primary Air (PA) Fan :
  • 23. Operation of HGG Pre- Start-Up Checks For Burner Start-Up • Opening/closing of air slide damper for all the burners are smooth with complete travel. • Verify cooling air to scanners and peep holes are available. • Verify the operation of fuel oil control valve opening and closing. • All instruments for measurement of oil pressure, flow and temperature are in service. • Burner Start Up Procedure: • Starts any one of the oil pump and maintain the rated oil pressure >10 kg/cm2 • Before starting the burner, the pre-interlocks, main interlocks purge interlocks & oil firing permissive are to be satisfied as per BMS logic like as: • LDO pressure > 6kg/cm2 • Atomising air pressure >7kg/cm2 • LPG Pressure >1kg/cm2 • Combustion air flow > 15TPH • Differential across the HGG <25 mmWC Copyright © 2014 Bajaj Energy Pvt. Ltd. 23
  • 24. • Burner Start PB Operated • Following Cycle will be initiated: • Step – 1 • LPG Gas valve will open and LPG Timer 35 secs count started Atomizing Air Valve will Open, Igniter Energized and Igniter Timer 15 secs count started. Oil valve will Open 5 secs after Start command And Flame is ON. • Step – 2 • Ignition Timer Over and Igniter De-Energized, LPG Valve closes after 35 sec timer is over. • The Main burner is lighted up keeping oil flow around 150 kg/hr. • In case the Oil does not catch fire during this period the whole sequence is to start again. • The combustion air damper is to be adjusted to the predetermined “air- fuel oil ratio” for efficient combustion and to keep the flame healthy. • Keep dilution air quantity sufficient to maintain HGG outlet gas temperature at around 350 ̊C initially
  • 25.
  • 26. • start raising the oil flow till it reaches around 900 kg/hr. Open dilution air damper such that HGG outlet gas temperature rises gradually and does not exceed 850 ̊C in any case • Both HGGs should not be started together. After approximately 15 minutes of stabilised operation of one HGG, second should be started. • Start Boiler feed pump for maintaining Drum level. • Initially, Superheater drain valves are kept open, along with drum and Superheater vent valves. When drum pressure exceeds 2 kg/cm², drum vent valve and Superheater vent valves should be closed.
  • 27. • Once drum pressure reaches approx. 5 kg/cm², Superheater drain valves are kept partially open for allowing steam flow through the Superheaters. • At approximately 8 to 10 kg/cm² drum pressure, close all S/H drains and partially open start up vent valves such that drum pressure increase is kept within permissible gradient 2 kg/cm² (g) per minute. • This will allow steam flow through the super-heaters and final steam temperature will also increase as per requirement. Copyright © 2014 Bajaj Energy Pvt. Ltd. 27
  • 28. • During pressure raising the water level will normally rise to the top of gauge glasses as steam pressure is increased. This is due to expansion in volume of water due to heat transfer and circulation. • The excess water from system should be removed by blow down. • While giving the blow-down, do not keep the blow-down valves open for more than 20 seconds. The blow-down normally should be given with quick open/close operation
  • 29. • Main fuel (coal) is charged after temperature of bed material exceeds ignition temperature(550 deg. c) of the fuel and all other boiler interlocks are fulfilled. • Due to cold fuel, initially there is slight "dip" in bed temperature. If coal combustion has been established. Take another coal feeder into service adjust PA and SA as per Requirement. after the bed temperature exceeds 700°C, gradually reduce the oil flow to about 250 kg/hr and then smoothly trip the HGGs one after another. Now both coal feeder in service and maintain bed temperature<800deg. And raise main steam pressure. • Once the fuel firing through both the streams is established and HGGs switched off. The HGG Bypass damper should be opened gradually. combustion and dilution damper closed. Deepak Rana, Bajaj Energy Ltd - Barkhera
  • 30. • When main steam pressure came 25kg/cm2. First, open by-pass valve of main steam stop valve. • Allow steam to flow for sufficient time to warm up main steam piping. • Open main steam stop valve and subsequently close by-pass valve. • Now steam charged up to CSDH.
  • 31.
  • 32.
  • 34.
  • 35.
  • 36.
  • 37.
  • 38. Boiler Trip Logics Protection conditions Alarm Value Trip value Remarks 1. Furnace Pr very HI >50 mmwc >100 mmwc PA,SA, CF TRIP, selected ID trip. 2. Furnace Pr very low <-80 mmwc <-150 mmwc Both ID fans trips if both are running 3. Furnace pr. Very low <-80 mmwc <-250 mmwc After selected ID trips and another ID fan running. 4. Drum level Very HI >64% >74% ONLY PA TRIP, selected ID trip. 5. Drum level Very low <30% <10% ONLY PA TRIP, selected ID trip. 6. Total PA flow< minimum <20 Kg/sec <15 Kg/Sec ONLY DCF TRIP 7. Bed height very low <800 mm <500 mm ONLY DCF TRIP 8. Bed height very high >1200 mmwc >1400 mmwc ONLY DCF TRIP 9. Both ID fans tripped 10. MFT operated ONLY DCF TRIP NOT IN GRAPHICS Deepak Rana, Bajaj Energy Ltd - Barkhera Remark if any • Total PA flow once reach above 20 kg/sec then it reduced to below 15 kg/sec then only DCF will trip. •Bed height once reaches above 1000mm then it reduced to below 600mm then only DCF will trip.