SlideShare a Scribd company logo
1 of 30
CONSTRUCTION AND
DESIGN OF EARTHEN
DAMS
-by Anand M Hulagabali
CONTENT :
 Site Identification
 Site Preparation
 Construction steps
 Design criteria
 Design of Components of dam
 Material and Machinery used
 Measures to be taken
SITE IDENTIFICATION
 Foundations : all types of foundation are suitable. rock type,
nature and extend of fault zones is investigated.
 Engineering surveys –topographic survey is done and various
contour plans are prepared
 Hydrological investigation- Water resources available ,
maximum flood discharge, fixation of storage capacity.
 Site for spillway – spillway is provided separately from dam
body and located in the flank.
 Quantity &quality of material available for dam construction.
considering above factors, best site is selected.
SITE PREPARATION
 Clearing:
It is the removal of tress, boulders, fences, buildings, and other
structures from the area. This is for the borrow pits and the area to
be occupied by the dam
 Grubbing:
It is the removal of roots, stumps and organic matter. Grubbing is
done only in the actual borrow pits and within the outline of
embankments
 Stripping:
It is the removal of all topsoil, organic materials and soft pockets
which are unsuitable for the borrow in the borrow pit areas or
unsuitable for supporting structure within the embankment outlines.
STEPS OF CONSTRUCTION
DIVERSION OF STREAM
 dewatering of place where construction is to be done.
 Firstly, temporary dam or cofferdam is constructed
which walls off and protects the site area.
 Secondly, diversion of stream is done either by
following two methods -:
 placing large pipes- if flow volume is less.
 tunnel or diversion ditch- if flow volume is large.
 diversion is done usually in summer season.
FOUNDATION PREPARATION
 Dewatering by pumping from sumps is done.
 For greatest economy an open excavation is used.
 Water table is be lowered so that there is never an
upward flow of water in to the excavation
 All loose materials and porous materials are
removed.
 Pits and crevices are cleaned out as deep as
possible.
 Clay or cement grouting is done if required.
Contd…
 Cutoff trench
A cutoff trench is excavated below the base of the fill
upstream of the centerline of the fill.
The cutoff trench is incorporated in the design for two
reasons:
 to anchor the dam to the base material.
 to prevent piping (seepage under the fill).
BORROW PIT EXCAVATION
 Excavation of the embankment materials,
processing them, and hauling them to the job are
important from considerations of both cost and the
quality of the materials delivered to the
embankment.
 Excavation is done either by hands or power driven
equipments.
FILL PLACEMENT
All objectionable materials are removed during and
immediately after the spreading operation.
• These include roots, clumps of grass and the other
organic matter, and large stones which would interfere
with compaction
• Mixing of various material is done as per design
&availability.
Moisture addition is done by sprinkling water several
hours before compaction.
SOIL COMPACTION
 Compaction is the process by which the required
density is obtained in an embankment. Compaction
is done to:
1) increase stiffness,
2) minimize settlements during and after
construction,
3) increase strength,
4) prevent sliding shear failure of embankment,
and
5) water tight, to obtain required imperviousness
of the core zone
 Contd…
 Compaction is done in stages.
 Compaction is done by following equipments :
1. Tampers
2. vibrating rollers
3. Sheep foot rollers
4. Heavy pneumatic-tired roller, etc.
Chimney drains, filters etc. are mounted in stages as dam
construction progress.
DESIGN CRITERIA
1. Safe against overtopping during design flood by
providing adequate spillway and outlet capacity.
2. Sufficient free board so that it is not overtopped by
wave action.
3. Seepage line should be well within d/s face so that
no sloughing of slope takes place.
4. Side slopes stable during construction and under all
condition of reservoir operation.
5.Upstream slope is safe against rapid drawdown.
6.Side slopes u/s and d/s are flat enough so that the
shear stress induced in the foundation is less then
the shear strength of material.
7.D/S slope is safe during steady seepage under full
reservoir condition.
8. d/s of the impervious core is provided by suitable
drainage system.
9.There is no possibility of free flow of water from
u/s through either the dam body or foundation.
10. Dam as a whole should be earthquake resistant.
DESIGN OF COMPONENTS OF
DAM
 Before the construction, preliminary design of
some of the components of dam is done. Following
are some of them :
 Top width
 Free board
 outer shell
 central impervious core
 D/s drainage system
TOP WIDTH :
 Top width is between 20-40ft.
 No dam should have top width less then 10ft (This is
minimum needed for an access road to permit
maintenance)
FREE BOARD :
 Sufficient freeboard must be provided so that there is no
danger of overtopping.
 The seepage line is well within the downstream face of
the dam.
 For any height of dam, minimum 2mtr and maximum
3mtr freeboard is provided over maximum flood level.
OUTER SHELL :
 Function : impart stability and protect core.
 Material : relatively pervious materials are
used which are not subjected to
cracking like SW, GW, SP, GP,
GC, etc
 Slope :
U/s slope : range – 2:1 to 4:1
D/s slope : range – 2:1 to 2.5:1
CORE :
 Function : core checks the seepage of water
through dam body.
 Material : material used should not have
high compressibility ,low liquid limit
& less or no organic content.
Materials like highly plastic tough
clay, silt or combination of above
can be used.
 Width of core at the crest should be minimum of 3mtr.
 Sloping cores can also be provided.
D/S DRAINAGE SYSTEM
 Function : reduce pore pressure in d/s portion
and checks the migration of the
particles.
 Material : sufficiently fine material to prevent
base material from clogging the
filter and coarser enough to
remove the water as early as
possible.
 3 types of drains are provided :
Toe drain.
Horizontal blanket drain.
Chimney drains.
MATERIALS USED
material for constructing dam is usually derived by
digging of nearby areas. Different type of materials are
used for different zones.
1. Outer shell – well graded or uniformly graded
gravel, sand, silty sand, etc...
2. Inner core – high to medium plastic clay, silt, silty
sand, etc…
3. Cut-off trench – concrete, same material as that used
in inner core (to maintain homogeneity)
4. Filter – sand and gravel placed in form of layers.
MACHINERY
Following are some the most widely used
machinery in construction of dam :
 Excavation - power shovel, dragline, scraper and
elevating grader
 hauling – trucks, wagons.
 Compaction –pneumatic tampers, sheep foot
roller, vibrating roller, heavy pneumatic-tired roller,
smooth steel drum roller.
MEASURES TO BE TAKEN
 Drainage is necessary for pits below ground water. This
should be done far enough in advance of the construction so
that the soil is not water logged.
 The operation of the borrow pit must be carefully
controlled for better quality
 Moisture should be controlled while placing the soil.
 Compaction must be done in layers and each layer should
be compacted to achieve about 95% of standard proctor
maximum.
 A testing laboratory is set up at the borrow pit where the
moisture content, gradation, and even plasticity can be
determined in minimum time.
Contd…
 Thickness of soil to be compacted in layer is
important to keep good quality of fill.
 Small compactors are effective near abutment
foundation.
THANK YOU…

More Related Content

What's hot

Design of stilling basin and roughness devices
Design of stilling basin and roughness devices Design of stilling basin and roughness devices
Design of stilling basin and roughness devices Bilal Mirani
 
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 10
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 10Class lecture on Hydrology by Rabindra Ranjan saha Lecture 10
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 10World University of Bangladesh
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipatorSAGAR RAUT
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksGAURAV. H .TANDON
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and typesRajkumar G
 
Dam - Classification based on structure
Dam - Classification based on structureDam - Classification based on structure
Dam - Classification based on structureAbhijit Pal
 
Design of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion HeadworkDesign of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion HeadworkRamanuj Jaldhari
 
weir & barrage
weir & barrageweir & barrage
weir & barrageRaj Daxini
 
Lacey Regime Theory - Irrigation Engineering
Lacey Regime Theory - Irrigation EngineeringLacey Regime Theory - Irrigation Engineering
Lacey Regime Theory - Irrigation EngineeringLatif Hyder Wadho
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworksJimit Shah
 

What's hot (20)

Design of stilling basin and roughness devices
Design of stilling basin and roughness devices Design of stilling basin and roughness devices
Design of stilling basin and roughness devices
 
Reservior planning
Reservior    planningReservior    planning
Reservior planning
 
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 10
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 10Class lecture on Hydrology by Rabindra Ranjan saha Lecture 10
Class lecture on Hydrology by Rabindra Ranjan saha Lecture 10
 
Spillways & energy dissipator
Spillways & energy dissipatorSpillways & energy dissipator
Spillways & energy dissipator
 
Spillway
Spillway Spillway
Spillway
 
Canal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage WorksCanal Regulation & Cross Drainage Works
Canal Regulation & Cross Drainage Works
 
Gravity dam
Gravity damGravity dam
Gravity dam
 
Design of barrages
Design of barragesDesign of barrages
Design of barrages
 
Spillways
SpillwaysSpillways
Spillways
 
Spillways components and types
Spillways components and typesSpillways components and types
Spillways components and types
 
design of weirs
design of weirsdesign of weirs
design of weirs
 
Dam - Classification based on structure
Dam - Classification based on structureDam - Classification based on structure
Dam - Classification based on structure
 
Design of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion HeadworkDesign of Canal (Kennedy & Lacey Theory) & Diversion Headwork
Design of Canal (Kennedy & Lacey Theory) & Diversion Headwork
 
weir & barrage
weir & barrageweir & barrage
weir & barrage
 
Diversion head works
Diversion head worksDiversion head works
Diversion head works
 
Chapter 4 embankment dams
Chapter 4 embankment damsChapter 4 embankment dams
Chapter 4 embankment dams
 
Lacey Regime Theory - Irrigation Engineering
Lacey Regime Theory - Irrigation EngineeringLacey Regime Theory - Irrigation Engineering
Lacey Regime Theory - Irrigation Engineering
 
Spillway gates
Spillway gatesSpillway gates
Spillway gates
 
Diversion headworks
Diversion headworksDiversion headworks
Diversion headworks
 
Weir and barrage lecture
Weir and barrage lectureWeir and barrage lecture
Weir and barrage lecture
 

Similar to 4. Construction and design criteria Earthen Dams.pptx

Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling explorationjamali husain
 
Unit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringUnit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringSahl Buhary
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptxJackRider12
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructionsVinay Vb
 
Construction considerations of Earthen Dams
Construction considerations of Earthen DamsConstruction considerations of Earthen Dams
Construction considerations of Earthen DamsUday kumar Devalla
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptxKhawarSakhani
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERINGVATSAL PATEL
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)Adib Ramli
 
CH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethiCH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethimulugetakassa1988
 
Well completion.
Well completion.Well completion.
Well completion.Mawa James
 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxHirenThakkar31
 

Similar to 4. Construction and design criteria Earthen Dams.pptx (20)

Tunnel Engineering.pptx
Tunnel Engineering.pptxTunnel Engineering.pptx
Tunnel Engineering.pptx
 
Tunneling exploration
Tunneling explorationTunneling exploration
Tunneling exploration
 
NATM ppt sumit
NATM ppt sumitNATM ppt sumit
NATM ppt sumit
 
Unit 37: Advanced Civil Engineering
Unit 37: Advanced Civil EngineeringUnit 37: Advanced Civil Engineering
Unit 37: Advanced Civil Engineering
 
UNIT-2.pptx
UNIT-2.pptxUNIT-2.pptx
UNIT-2.pptx
 
Cofferdam_ppt.pptx
Cofferdam_ppt.pptxCofferdam_ppt.pptx
Cofferdam_ppt.pptx
 
Tunnel constructions
Tunnel constructionsTunnel constructions
Tunnel constructions
 
Construction considerations of Earthen Dams
Construction considerations of Earthen DamsConstruction considerations of Earthen Dams
Construction considerations of Earthen Dams
 
Construction of Dams.pptx
Construction of Dams.pptxConstruction of Dams.pptx
Construction of Dams.pptx
 
LECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdfLECT 2 - EARTHWORK.pdf
LECT 2 - EARTHWORK.pdf
 
Earthen dam
Earthen damEarthen dam
Earthen dam
 
Ppt of design of dams
Ppt of design of damsPpt of design of dams
Ppt of design of dams
 
7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING7. TUNNEL ENGINEERING
7. TUNNEL ENGINEERING
 
EARTHERN DAM
EARTHERN DAMEARTHERN DAM
EARTHERN DAM
 
sample.pptx
sample.pptxsample.pptx
sample.pptx
 
Earthen Dams
Earthen DamsEarthen Dams
Earthen Dams
 
The construction method for surface drainage (housing)
The construction method for surface drainage (housing)The construction method for surface drainage (housing)
The construction method for surface drainage (housing)
 
CH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethiCH7.2.ppt,ground water hydrology in ethi
CH7.2.ppt,ground water hydrology in ethi
 
Well completion.
Well completion.Well completion.
Well completion.
 
GOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptxGOOD CONSTRUCTION PRACTICE.pptx
GOOD CONSTRUCTION PRACTICE.pptx
 

Recently uploaded

VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130Suhani Kapoor
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsCall Girls in Nagpur High Profile
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCall Girls in Nagpur High Profile
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝soniya singh
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort servicejennyeacort
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxPoojaBan
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVRajaP95
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 

Recently uploaded (20)

Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
VIP Call Girls Service Kondapur Hyderabad Call +91-8250192130
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur EscortsHigh Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
High Profile Call Girls Nagpur Meera Call 7001035870 Meet With Nagpur Escorts
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service NashikCollege Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
College Call Girls Nashik Nehal 7001305949 Independent Escort Service Nashik
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
Model Call Girl in Narela Delhi reach out to us at 🔝8264348440🔝
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort serviceGurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
Gurgaon ✡️9711147426✨Call In girls Gurgaon Sector 51 escort service
 
Heart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptxHeart Disease Prediction using machine learning.pptx
Heart Disease Prediction using machine learning.pptx
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCRCall Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
Call Us -/9953056974- Call Girls In Vikaspuri-/- Delhi NCR
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IVHARMONY IN THE NATURE AND EXISTENCE - Unit-IV
HARMONY IN THE NATURE AND EXISTENCE - Unit-IV
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 

4. Construction and design criteria Earthen Dams.pptx

  • 1. CONSTRUCTION AND DESIGN OF EARTHEN DAMS -by Anand M Hulagabali
  • 2. CONTENT :  Site Identification  Site Preparation  Construction steps  Design criteria  Design of Components of dam  Material and Machinery used  Measures to be taken
  • 3. SITE IDENTIFICATION  Foundations : all types of foundation are suitable. rock type, nature and extend of fault zones is investigated.  Engineering surveys –topographic survey is done and various contour plans are prepared  Hydrological investigation- Water resources available , maximum flood discharge, fixation of storage capacity.  Site for spillway – spillway is provided separately from dam body and located in the flank.  Quantity &quality of material available for dam construction. considering above factors, best site is selected.
  • 4. SITE PREPARATION  Clearing: It is the removal of tress, boulders, fences, buildings, and other structures from the area. This is for the borrow pits and the area to be occupied by the dam  Grubbing: It is the removal of roots, stumps and organic matter. Grubbing is done only in the actual borrow pits and within the outline of embankments  Stripping: It is the removal of all topsoil, organic materials and soft pockets which are unsuitable for the borrow in the borrow pit areas or unsuitable for supporting structure within the embankment outlines.
  • 6. DIVERSION OF STREAM  dewatering of place where construction is to be done.  Firstly, temporary dam or cofferdam is constructed which walls off and protects the site area.  Secondly, diversion of stream is done either by following two methods -:  placing large pipes- if flow volume is less.  tunnel or diversion ditch- if flow volume is large.  diversion is done usually in summer season.
  • 7. FOUNDATION PREPARATION  Dewatering by pumping from sumps is done.  For greatest economy an open excavation is used.  Water table is be lowered so that there is never an upward flow of water in to the excavation  All loose materials and porous materials are removed.  Pits and crevices are cleaned out as deep as possible.  Clay or cement grouting is done if required.
  • 8. Contd…  Cutoff trench A cutoff trench is excavated below the base of the fill upstream of the centerline of the fill. The cutoff trench is incorporated in the design for two reasons:  to anchor the dam to the base material.  to prevent piping (seepage under the fill).
  • 9.
  • 10. BORROW PIT EXCAVATION  Excavation of the embankment materials, processing them, and hauling them to the job are important from considerations of both cost and the quality of the materials delivered to the embankment.  Excavation is done either by hands or power driven equipments.
  • 11. FILL PLACEMENT All objectionable materials are removed during and immediately after the spreading operation. • These include roots, clumps of grass and the other organic matter, and large stones which would interfere with compaction • Mixing of various material is done as per design &availability. Moisture addition is done by sprinkling water several hours before compaction.
  • 12. SOIL COMPACTION  Compaction is the process by which the required density is obtained in an embankment. Compaction is done to: 1) increase stiffness, 2) minimize settlements during and after construction, 3) increase strength, 4) prevent sliding shear failure of embankment, and 5) water tight, to obtain required imperviousness of the core zone
  • 13.  Contd…  Compaction is done in stages.  Compaction is done by following equipments : 1. Tampers 2. vibrating rollers 3. Sheep foot rollers 4. Heavy pneumatic-tired roller, etc. Chimney drains, filters etc. are mounted in stages as dam construction progress.
  • 14. DESIGN CRITERIA 1. Safe against overtopping during design flood by providing adequate spillway and outlet capacity. 2. Sufficient free board so that it is not overtopped by wave action. 3. Seepage line should be well within d/s face so that no sloughing of slope takes place. 4. Side slopes stable during construction and under all condition of reservoir operation.
  • 15. 5.Upstream slope is safe against rapid drawdown. 6.Side slopes u/s and d/s are flat enough so that the shear stress induced in the foundation is less then the shear strength of material. 7.D/S slope is safe during steady seepage under full reservoir condition. 8. d/s of the impervious core is provided by suitable drainage system.
  • 16. 9.There is no possibility of free flow of water from u/s through either the dam body or foundation. 10. Dam as a whole should be earthquake resistant.
  • 17. DESIGN OF COMPONENTS OF DAM  Before the construction, preliminary design of some of the components of dam is done. Following are some of them :  Top width  Free board  outer shell  central impervious core  D/s drainage system
  • 18. TOP WIDTH :  Top width is between 20-40ft.  No dam should have top width less then 10ft (This is minimum needed for an access road to permit maintenance) FREE BOARD :  Sufficient freeboard must be provided so that there is no danger of overtopping.  The seepage line is well within the downstream face of the dam.  For any height of dam, minimum 2mtr and maximum 3mtr freeboard is provided over maximum flood level.
  • 19. OUTER SHELL :  Function : impart stability and protect core.  Material : relatively pervious materials are used which are not subjected to cracking like SW, GW, SP, GP, GC, etc  Slope : U/s slope : range – 2:1 to 4:1 D/s slope : range – 2:1 to 2.5:1
  • 20. CORE :  Function : core checks the seepage of water through dam body.  Material : material used should not have high compressibility ,low liquid limit & less or no organic content. Materials like highly plastic tough clay, silt or combination of above can be used.  Width of core at the crest should be minimum of 3mtr.  Sloping cores can also be provided.
  • 21. D/S DRAINAGE SYSTEM  Function : reduce pore pressure in d/s portion and checks the migration of the particles.  Material : sufficiently fine material to prevent base material from clogging the filter and coarser enough to remove the water as early as possible.  3 types of drains are provided : Toe drain. Horizontal blanket drain. Chimney drains.
  • 22.
  • 23.
  • 24. MATERIALS USED material for constructing dam is usually derived by digging of nearby areas. Different type of materials are used for different zones. 1. Outer shell – well graded or uniformly graded gravel, sand, silty sand, etc... 2. Inner core – high to medium plastic clay, silt, silty sand, etc… 3. Cut-off trench – concrete, same material as that used in inner core (to maintain homogeneity) 4. Filter – sand and gravel placed in form of layers.
  • 25.
  • 27. Following are some the most widely used machinery in construction of dam :  Excavation - power shovel, dragline, scraper and elevating grader  hauling – trucks, wagons.  Compaction –pneumatic tampers, sheep foot roller, vibrating roller, heavy pneumatic-tired roller, smooth steel drum roller.
  • 28. MEASURES TO BE TAKEN  Drainage is necessary for pits below ground water. This should be done far enough in advance of the construction so that the soil is not water logged.  The operation of the borrow pit must be carefully controlled for better quality  Moisture should be controlled while placing the soil.  Compaction must be done in layers and each layer should be compacted to achieve about 95% of standard proctor maximum.  A testing laboratory is set up at the borrow pit where the moisture content, gradation, and even plasticity can be determined in minimum time.
  • 29. Contd…  Thickness of soil to be compacted in layer is important to keep good quality of fill.  Small compactors are effective near abutment foundation.