SlideShare a Scribd company logo
1 of 11
Overall Equipment Efficiency
By Abdelfatah Hussein
0201010366654
What Is the OEE System?
• A System That used to measure and understand performance & effectiveness
for the Equipment and Processes.
It,
- Helps us to understand the current status of Machines
- Support production planning and facilitate improvement plans
- Supports investment decisions when we need to know the forecasting capex.
What Is the OEE System?
- Measure the down time
- Measure the planned maintenance time
- Unplanned cleaning
- Quality rate per machine
- Maximum theoretical ,ideal capacity per machine
- Defects time per machine
- Operator delay
- Material/ Spare parts shortages
- Startups/shutdown time even if short mins
Key factors of OEE
• Availability
• Performance
• Quality
And the equation is
Overall equipment efficiency = Availability x Performance x Quality
How to Calculating OEE ?
1. Availability
• Availability is calculated as Run Time to Planned Production Time:
• Availability = Run Time / Planned Production Time
• Run Time is simply Planned Production Time less Stop Time, where Stop Time is defined
as all time where the manufacturing process was intended to be running but was not due
to Unplanned Stops
• Run Time = Planned Production Time − Stop Time
2. Performance
• Performance count anything that causes the manufacturing process to run at less
than the maximum possible speed when it is running (including both Slow
Cycles and Small Stops).
• Performance = (Total Count / Run Time) / Ideal Run Rate
• Performance should never be greater than 100%. If it is, that usually indicates that
Ideal Cycle Time is set incorrectly as our case for fiber machine.
• Quality
• Quality takes into account manufactured parts that do not meet quality standards,
including parts that need rework.
• quality is similar to FPY, in that it define Good Parts as parts that successfully pass first
time without needing any rework.
• Quality is calculated as:
• Quality = Good Count / Total Count
Example for OEE Fiber Machine No1 Old factory “ day “
Production Data
Shift Length 22 Hours = 1320 Minutes
Short Breaks 0 Breaks @ 0 Minutes Each = 0 Minutes Total
Meal Break 0 Breaks @ 30 Minutes Each = 0 Minutes Total
Down Time 120 Minutes
Ideal Run Rate 0.300926 PPM (Pieces Per Minute)
Total Pieces 300 Pieces
Reject Pieces 10 Pieces
Support Variable Calculation Result
Planned
Production Time Shift Length - Breaks 1,320 Minutes
Operating Time Planned Production Time - Down Time 1,200 Minutes
Good Pieces Total Pieces - Reject Pieces 290 Pieces
OEE Factor Calculation My OEE%
Availability Operating Time / Planned Production Time 90.91%
Performance (Total Pieces / Operation Time) / Ideal Run Rate 83.08%
Quality Good Pieces / Total Pieces 96.67%
Overall OEE Availability x Performance x Quality 73.01%
OEE Factor
World
Class
My OEE%
Availability 90.00% 90.91%
Performance 95.00% 83.08%
Quality 99.90% 96.67%
Overall OEE 85.00% 73.01%
90.91%
83.08%
96.67%
73.01%
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
Availability Performance Quality Overall OEE
Chart Title
• All of the above for calculating The current status of our
machines
• Next step is how to improve the current state by reducing the
wastes
Thank You

More Related Content

What's hot (20)

The Six Big Losses of OEE
The Six Big Losses of OEEThe Six Big Losses of OEE
The Six Big Losses of OEE
 
Line balancing
Line balancing Line balancing
Line balancing
 
Batch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous FlowBatch & Queue vs Lean Continuous Flow
Batch & Queue vs Lean Continuous Flow
 
Takt Time, Cycle Time & Line Balancing
Takt Time, Cycle Time & Line BalancingTakt Time, Cycle Time & Line Balancing
Takt Time, Cycle Time & Line Balancing
 
Ch17 scheduling
Ch17 schedulingCh17 scheduling
Ch17 scheduling
 
Line balancing and heuristics
Line balancing and heuristicsLine balancing and heuristics
Line balancing and heuristics
 
JAMES WRIGHT Resume
JAMES WRIGHT ResumeJAMES WRIGHT Resume
JAMES WRIGHT Resume
 
TPM Training HON Torrance
TPM Training HON TorranceTPM Training HON Torrance
TPM Training HON Torrance
 
Resume
ResumeResume
Resume
 
Scooter india,sip presentation
Scooter india,sip presentationScooter india,sip presentation
Scooter india,sip presentation
 
OEE
OEEOEE
OEE
 
Line balancing and its formulation
Line balancing and its formulationLine balancing and its formulation
Line balancing and its formulation
 
Schneider Case Study Challenge
Schneider Case Study ChallengeSchneider Case Study Challenge
Schneider Case Study Challenge
 
Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)Single Minute Exchange of Dies (SMED)
Single Minute Exchange of Dies (SMED)
 
BQ-RTPT 2012
BQ-RTPT 2012BQ-RTPT 2012
BQ-RTPT 2012
 
Types of loading, production & operations management
Types of loading, production & operations managementTypes of loading, production & operations management
Types of loading, production & operations management
 
How to implement Single minute exchange of die
How to implement Single minute exchange of die How to implement Single minute exchange of die
How to implement Single minute exchange of die
 
Balancing exercise for garment industry
Balancing exercise for garment industryBalancing exercise for garment industry
Balancing exercise for garment industry
 
Process Improvements[1]
Process Improvements[1]Process Improvements[1]
Process Improvements[1]
 
Case 2 AIC Netbooks
Case 2 AIC NetbooksCase 2 AIC Netbooks
Case 2 AIC Netbooks
 

Viewers also liked

KULIAH PENGANTAR HISTORY TAKING DAN PHYSICAL ASSESSMENT
KULIAH PENGANTAR HISTORY TAKING  DAN PHYSICAL  ASSESSMENT KULIAH PENGANTAR HISTORY TAKING  DAN PHYSICAL  ASSESSMENT
KULIAH PENGANTAR HISTORY TAKING DAN PHYSICAL ASSESSMENT yohanes meor
 
Sudah jadi tugas b.i
Sudah jadi tugas b.iSudah jadi tugas b.i
Sudah jadi tugas b.iAli Ahmadi
 
HubSpot Presentation Q1 Meeting
HubSpot Presentation Q1 MeetingHubSpot Presentation Q1 Meeting
HubSpot Presentation Q1 MeetingKnoxville HUG
 
FRICollegePresents 2014i copy
FRICollegePresents 2014i copyFRICollegePresents 2014i copy
FRICollegePresents 2014i copyLarry Kushner
 
Project Management Overview for Aerospace and Defense Industry
Project Management Overview for Aerospace and Defense Industry Project Management Overview for Aerospace and Defense Industry
Project Management Overview for Aerospace and Defense Industry Fujitsu Glovia, Inc.
 
Curriculum Vitae, Addendum -Theatre
Curriculum Vitae, Addendum -TheatreCurriculum Vitae, Addendum -Theatre
Curriculum Vitae, Addendum -TheatreB. R. FLEMING
 
Materi Tentang Parasomnia_wajib dipelajari bagi mahasiswa yang kulia di keseh...
Materi Tentang Parasomnia_wajib dipelajari bagi mahasiswa yang kulia di keseh...Materi Tentang Parasomnia_wajib dipelajari bagi mahasiswa yang kulia di keseh...
Materi Tentang Parasomnia_wajib dipelajari bagi mahasiswa yang kulia di keseh...yohanes meor
 

Viewers also liked (11)

KULIAH PENGANTAR HISTORY TAKING DAN PHYSICAL ASSESSMENT
KULIAH PENGANTAR HISTORY TAKING  DAN PHYSICAL  ASSESSMENT KULIAH PENGANTAR HISTORY TAKING  DAN PHYSICAL  ASSESSMENT
KULIAH PENGANTAR HISTORY TAKING DAN PHYSICAL ASSESSMENT
 
Hydrolic
HydrolicHydrolic
Hydrolic
 
Pochii & Denise
Pochii & DenisePochii & Denise
Pochii & Denise
 
Sudah jadi tugas b.i
Sudah jadi tugas b.iSudah jadi tugas b.i
Sudah jadi tugas b.i
 
HubSpot Presentation Q1 Meeting
HubSpot Presentation Q1 MeetingHubSpot Presentation Q1 Meeting
HubSpot Presentation Q1 Meeting
 
FRICollegePresents 2014i copy
FRICollegePresents 2014i copyFRICollegePresents 2014i copy
FRICollegePresents 2014i copy
 
Project Management Overview for Aerospace and Defense Industry
Project Management Overview for Aerospace and Defense Industry Project Management Overview for Aerospace and Defense Industry
Project Management Overview for Aerospace and Defense Industry
 
Curriculum Vitae, Addendum -Theatre
Curriculum Vitae, Addendum -TheatreCurriculum Vitae, Addendum -Theatre
Curriculum Vitae, Addendum -Theatre
 
sb arakeri.pdf cv
sb arakeri.pdf cvsb arakeri.pdf cv
sb arakeri.pdf cv
 
Materi Tentang Parasomnia_wajib dipelajari bagi mahasiswa yang kulia di keseh...
Materi Tentang Parasomnia_wajib dipelajari bagi mahasiswa yang kulia di keseh...Materi Tentang Parasomnia_wajib dipelajari bagi mahasiswa yang kulia di keseh...
Materi Tentang Parasomnia_wajib dipelajari bagi mahasiswa yang kulia di keseh...
 
apsingh resume
apsingh resume apsingh resume
apsingh resume
 

Similar to Overall Equipment Efficiency

Overall equipment effectiveness
Overall equipment effectivenessOverall equipment effectiveness
Overall equipment effectivenessRachit Laharia
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Pramod A
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)MohammedLahssaini1
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Brian Thomas
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.pptSandipanMaji3
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1Matthew Clemens
 
SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineParth Patel
 
Smed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineSmed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineDhruvShah202
 
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryOverall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryInfoStream Solutions
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxMukhtarMohamedAbdila
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systemsAyman Aljahdali
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysisvideoaakash15
 

Similar to Overall Equipment Efficiency (20)

Overall equipment effectiveness
Overall equipment effectivenessOverall equipment effectiveness
Overall equipment effectiveness
 
OEE CALCULATION PPT
OEE CALCULATION PPTOEE CALCULATION PPT
OEE CALCULATION PPT
 
Autonomous Maintenance (AM)
Autonomous Maintenance (AM)Autonomous Maintenance (AM)
Autonomous Maintenance (AM)
 
Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)Implémentation Méthode Single Minute Exchange of Dies(SMED)
Implémentation Méthode Single Minute Exchange of Dies(SMED)
 
OEE.pptx
OEE.pptxOEE.pptx
OEE.pptx
 
Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)Production Line OEE (Overall Equipment Effectiveness)
Production Line OEE (Overall Equipment Effectiveness)
 
lean & agile
lean & agilelean & agile
lean & agile
 
Process Selection and Facility layout.ppt
Process Selection and Facility layout.pptProcess Selection and Facility layout.ppt
Process Selection and Facility layout.ppt
 
Equipment reliability l1
Equipment reliability l1Equipment reliability l1
Equipment reliability l1
 
TPM Loss Analysis
TPM  Loss AnalysisTPM  Loss Analysis
TPM Loss Analysis
 
SMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping LineSMED implementation on Automated Stamping Line
SMED implementation on Automated Stamping Line
 
Smed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping lineSmed implementation on manufacturing stamping line
Smed implementation on manufacturing stamping line
 
[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)[Partial Preview:] Overall Equipment Effectiveness (OEE)
[Partial Preview:] Overall Equipment Effectiveness (OEE)
 
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing IndustryOverall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
Overall Equipment Efficiency - A Next-Gen KPI for the Manufacturing Industry
 
Ofs whitepaper
Ofs whitepaperOfs whitepaper
Ofs whitepaper
 
Oee part 2
Oee part  2 Oee part  2
Oee part 2
 
ch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptxch5-processanalysis-131122013048-phpapp02 (1).pptx
ch5-processanalysis-131122013048-phpapp02 (1).pptx
 
Quick Smed Sample
Quick Smed SampleQuick Smed Sample
Quick Smed Sample
 
Just in time and Lean systems
Just in time and Lean systemsJust in time and Lean systems
Just in time and Lean systems
 
Ch5 process analysis
Ch5 process analysisCh5 process analysis
Ch5 process analysis
 

Recently uploaded

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfAsst.prof M.Gokilavani
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxJoão Esperancinha
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...asadnawaz62
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxKartikeyaDwivedi3
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girlsssuser7cb4ff
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxwendy cai
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...srsj9000
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidNikhilNagaraju
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024hassan khalil
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)dollysharma2066
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfme23b1001
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and usesDevarapalliHaritha
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 

Recently uploaded (20)

Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdfCCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
CCS355 Neural Network & Deep Learning Unit II Notes with Question bank .pdf
 
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptxDecoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
Decoding Kotlin - Your guide to solving the mysterious in Kotlin.pptx
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...complete construction, environmental and economics information of biomass com...
complete construction, environmental and economics information of biomass com...
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Concrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptxConcrete Mix Design - IS 10262-2019 - .pptx
Concrete Mix Design - IS 10262-2019 - .pptx
 
Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Call Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call GirlsCall Girls Narol 7397865700 Independent Call Girls
Call Girls Narol 7397865700 Independent Call Girls
 
What are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptxWhat are the advantages and disadvantages of membrane structures.pptx
What are the advantages and disadvantages of membrane structures.pptx
 
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
Gfe Mayur Vihar Call Girls Service WhatsApp -> 9999965857 Available 24x7 ^ De...
 
main PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfidmain PPT.pptx of girls hostel security using rfid
main PPT.pptx of girls hostel security using rfid
 
Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024Architect Hassan Khalil Portfolio for 2024
Architect Hassan Khalil Portfolio for 2024
 
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
Call Us ≽ 8377877756 ≼ Call Girls In Shastri Nagar (Delhi)
 
Electronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdfElectronically Controlled suspensions system .pdf
Electronically Controlled suspensions system .pdf
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
power system scada applications and uses
power system scada applications and usespower system scada applications and uses
power system scada applications and uses
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 

Overall Equipment Efficiency

  • 1. Overall Equipment Efficiency By Abdelfatah Hussein 0201010366654
  • 2. What Is the OEE System? • A System That used to measure and understand performance & effectiveness for the Equipment and Processes. It, - Helps us to understand the current status of Machines - Support production planning and facilitate improvement plans - Supports investment decisions when we need to know the forecasting capex.
  • 3. What Is the OEE System? - Measure the down time - Measure the planned maintenance time - Unplanned cleaning - Quality rate per machine - Maximum theoretical ,ideal capacity per machine - Defects time per machine - Operator delay - Material/ Spare parts shortages - Startups/shutdown time even if short mins
  • 4. Key factors of OEE • Availability • Performance • Quality And the equation is Overall equipment efficiency = Availability x Performance x Quality
  • 5. How to Calculating OEE ? 1. Availability • Availability is calculated as Run Time to Planned Production Time: • Availability = Run Time / Planned Production Time • Run Time is simply Planned Production Time less Stop Time, where Stop Time is defined as all time where the manufacturing process was intended to be running but was not due to Unplanned Stops • Run Time = Planned Production Time − Stop Time
  • 6. 2. Performance • Performance count anything that causes the manufacturing process to run at less than the maximum possible speed when it is running (including both Slow Cycles and Small Stops). • Performance = (Total Count / Run Time) / Ideal Run Rate • Performance should never be greater than 100%. If it is, that usually indicates that Ideal Cycle Time is set incorrectly as our case for fiber machine.
  • 7. • Quality • Quality takes into account manufactured parts that do not meet quality standards, including parts that need rework. • quality is similar to FPY, in that it define Good Parts as parts that successfully pass first time without needing any rework. • Quality is calculated as: • Quality = Good Count / Total Count
  • 8. Example for OEE Fiber Machine No1 Old factory “ day “ Production Data Shift Length 22 Hours = 1320 Minutes Short Breaks 0 Breaks @ 0 Minutes Each = 0 Minutes Total Meal Break 0 Breaks @ 30 Minutes Each = 0 Minutes Total Down Time 120 Minutes Ideal Run Rate 0.300926 PPM (Pieces Per Minute) Total Pieces 300 Pieces Reject Pieces 10 Pieces Support Variable Calculation Result Planned Production Time Shift Length - Breaks 1,320 Minutes Operating Time Planned Production Time - Down Time 1,200 Minutes Good Pieces Total Pieces - Reject Pieces 290 Pieces OEE Factor Calculation My OEE% Availability Operating Time / Planned Production Time 90.91% Performance (Total Pieces / Operation Time) / Ideal Run Rate 83.08% Quality Good Pieces / Total Pieces 96.67% Overall OEE Availability x Performance x Quality 73.01% OEE Factor World Class My OEE% Availability 90.00% 90.91% Performance 95.00% 83.08% Quality 99.90% 96.67% Overall OEE 85.00% 73.01%
  • 10. • All of the above for calculating The current status of our machines • Next step is how to improve the current state by reducing the wastes