Nick Foster, Tian Tian, Yulin Lu, Zhengda Wang
Project Management in the Information Age
MASY1-GC1250.100
Team Project Business Case
June 27, 2017
Contents
Executive Summary
(Nick).....................................................................................
........................ 2
Current Situation (Tian)
...............................................................................................
.................. 2
Recommendation (Zhengda)
...............................................................................................
............ 2
Options Considered (Zhengda)
...............................................................................................
....... 3
Goals & Objectives (Tian)
...............................................................................................
............... 3
Assumptions (Nick)
...............................................................................................
......................... 4
Constraints (Nick)
...............................................................................................
............................ 4
Critical Success Factors (Zhengda)
...............................................................................................
. 4
Costs & Benefits (Yulin)
...............................................................................................
................. 5
Project Delivery Schedule Summary (Yulin)
................................................................................. 5
Conclusion & Next Steps (Yulin)
...............................................................................................
.... 6
2
Executive Summary
The purpose of this project is enhance California’s economy by
way of a high-speed rail line between
Los Angeles and San Francisco, in keeping with RapidTrak’s
mission to expand high-speed rail service
across the country. Our project will catalyze environmental and
economic benefits in the state and
greatly reduce the time necessary to travel between its two
biggest cities. Total costs for the entire
endeavor are projected at $50 billion, for an estimated
completion by the end of 2029.
Current Situation
Compared to systems in Japan, China and Europe, inter-city rail
service in the United States is
undeveloped. The main national carrier, Amtrak, is only
profitable in its Northeast Corridor line (serving
Boston to Washington, D.C.), and even the “high-speed” Acela
trains that operate on this line are very
slow compared to state-of-the-art high-speed rail abroad.
However, American public interest in high-
speed rail is markedly on the rise, especially in the wealthier ,
more densely-populated coastal states.
This comes at a time when interest in revitalizing America’s
transportation infrastructure to be more
environmentally friendly is also reaching a peak.
The domestic railway industry is generally stagnant or in
decline, with a lack of appropriate investment
in new technology and expert personnel leaving the workforce.
Throughout the country, Amtrak
operates slow, outdated trains, mostly on tracks that are actually
owned by major freight rail lines,
meaning that passenger traffic must yield to freight at all times.
Domestic expertise in high-speed rail is
limited, so any attempt to implement a high-speed system here
will have to import and adapt
technologies pertaining to the design and control of the trains
themselves, techniques in track
construction and more.
Recommendation
Given these challenges, our attention turns to California, which
has made it a priority to improve its
environment and transportation in tandem. The state’s roadways
are among the most-used (and most-
congested) in the nation, with drivers wasting over $18 billion
annually in lost productivity and wasted
fuel. Moreover, the air travel routes between Los Angeles and
San Francisco serve over five million
passengers annually but regular delays significantly erode the
time saved by flying. As passenger
volumes increase and climate and pollution become more of a
concern, it becomes clear that the state is
in serious need of additional transportation options.
Therefore, California is a perfect candidate for RapidTrak’s
inaugural high-speed project. Our
recommendation is to construct and operate a high-speed rail
line between Los Angeles and San
Francisco, in the style of Japan’s “Shinkansen” railroad,
connecting the cities of Bakersfield, Fresno and
San Jose along the way. Planning and executing the project
within a single state exposes us to fewer
political and regulatory challenges. Plus, California’s
government is receptive to the idea of high-speed
rail, so we expect it to be a cooperative partner.
We expect such a rail line to achieve a range of economic and
environmental effects for the state,
summarized here and further elaborated throughout this
document:
.
• Reduced travel times
• Job creation
3
• Statewide economic growth
• Greenhouse gas reductions
• Eased traffic congestion and fewer automobile accidents
Options Considered
Because RapidTrack has a nation-wide mission, we chose
between three potential routes for a new high-
speed line:
• Boston to Washington, D.C.: This route would accelerate
transit along the profitable and
densely populated Northeast Corridor.
• New York to Chicago: Satisfies an under-served East-West
route and improves economic
access to/from Midwest cities like Indianapolis, Columbus and
Pittsburgh.
• Los Angeles to San Francisco: Operates in a single state,
serves two of the nation’s highest-
value cities, and solves known, critical problems about traffic
and pollution.
Within this scope, however, and because domestic expertise in
high-speed rail is limited, we have to
choose whether to model RapidTraks’ line on Chinese, Japanese
or European technology. Ultimately we
are attracted to Japan’s “Shinkansen” system for its excellent
safety ratings and overall high quality.
Goals & Objectives
RapidTrack’s goal is to improve California’s transportation
infrastructure, ease environmental pressure,
and create economic opportunity in the region. To that end, the
objective of this project is to build a
high-speed rail line connecting Los Angeles and San Francisco,
the state’s two most important cities.
Providing a reliable rail network can help serve the needs of
national and regional area by offering
convenient access to economic centers. We hope to achieve the
following objectives by way of our high-
speed line.
• Reduction in travel time. Covering a little over 400 miles at
speeds approaching 200 miles per
hour, the total length of a journey between Los Angeles and San
Francisco should be little more
than two hours. Currently, flying between each city takes at
least two and a half hours,
accounting for time spent getting to or from each airport in
California’s bad traffic.
• Reduction in carbon emissions. The rail line could eliminate
up to 300,000 metric tons of
carbon dioxide (CO2) emissions in the first year of operation,
equivalent to 53,000 personal
vehicles taken off the road. By 2040, the system is estimated to
reduce vehicles miles of travel in
the state by almost 10 million miles of travel every day.
• Reduction in auto accidents. By providing a safe, efficient
alternative, we hope to reduce auto
accidents in line with a general reduction in auto traffic
between both termini.
• Economic growth. The rail line will provide faster and more
convenient access to major city
centers, extending the geographic range in which they can spend
money and work. We expect
the project to add at least 100,000 jobs to the California
economy, accounting for temporary
work attached to the project itself and permanent job growth
resulting from the train’s presence
in the region.
4
Assumptions
The project makes a set of assumptions about the logistics and
nature of the proposed high-speed line:
• What RapidTrak provides to California aligns with its
expressed goals and values, so therefore
we assume that state and local governments will be cooperative,
at least enough as to not impede
the project.
• We will make a conservative assumption that we will not be
able to acquire all the land
necessary for tracks and stations along our idealized route. We
assume that it will sometimes be
necessary to deviate from the planned route in order to avoid
insurmountable costs or
inconvenience, even though doing so will require changes to
scheduling and budget.
• The extent of the economic benefit to California can only be
drawn in assumptions at this point.
Past rail projects in other countries do point to promising
results, however.
• The most basic assumption made by this project is that
Californians would be interested enough
in high-speed rail to use our line in such high numbers as to
achieve the desired economic benefit
for the region.
Constraints
We also have to acknowledge the challenges and constraints
that will likely affect our work.
• As mentioned in the proposal, one of the biggest sets of
constraints will be where exactly
RapidTrak can secure land for building the tracks.
• Because of RapidTrak’s ownership by the federal government,
we expect conflict over budget
constraints to arise every year, especially during times of
turnover in political leadership as the
government re-calibrates its priorities for infrastructure
spending.
• Constructing the rail line will require a massive amount of
labor, over a long period of time and
spread across a wide geographical area. It could be challenge to
have as many appropriately
skilled workers as are needed at all active job sites at all times.
Critical Success Factors
In order for this project to be successful, we see five factors
that deserve our close attention moving
forward.
• A highly detailed but flexible WBS. This will be a massive,
long-term infrastructure project,
vulnerable to complication and delay at a micro level. Our work
breakdown structure must be
able to account for the possibility of contingency spending,
crashing, re-scheduling and more
whenever necessary.
• Effective control of the project budget. The demands of the
WBS also mean that at a high-
level, the management of our project budget must be of utmost
quality.
• Diligent earned value management. Because this will be such a
large, expensive project with
so many moving parts, we must play close attention to how we
are spending our funds, which
aspects of the project are making the most efficient use of time
and money, and be ready to re-
plan or re-allocate those resources within the project portfolio
as becomes necessary.
• Satisfaction of state and local government stakeholders. It will
be crucial to keep these
stakeholders informed, engaged and satisfied with and about our
work. If RapidTrak should wear
out its welcome in the state, our project will be doomed.
5
• Excellence in procurement and labor management. The rail
line will run for hundreds of
miles, in a years-long construction effort. It will be of utmost
importance to ensure that the
project has enough labor hired and in action in the right place at
the right time, all the time.
Building materials and other vital components, such as the
rolling stock itself, will need to
sourced and delivered to budget, on time, and without
complication.
To measure the ultimate success of the project, reference the
economic benefits cited in our
Recommendation, Goals & Objectives and Costs & Benefits.
Costs & Benefits
This project will be a major undertaking, costing billions of
dollars over more than a decade. We
estimate that RapidTrak will need to acquire approximately
9,000 acres of land in order to construct the
track, calculated at 500 miles (building a buffer into the net
lengths, as per our assumptions) by 150 feet
(needed for the width of the track and relevant infrastructure. At
an average cost of $12,000 per acre of
irrigated cropland in California (comprising most of the land
between our target cities), this comes to a
net estimated cost of $108 million for land acquisition.
Add this figure to the expected combined costs of construction
labor, rolling stock (Japan’s Shinkansen
trains are very expensive), information technology, facilities
and stations, and contingency funds, and
we anticipate the total cost of the project to be $35 billion. With
a 30% buffer, the total budget rises to
$50 billion.
As 10,000 passengers per day, it would take 137 years of
passengers paying $100 for a ticket to break
even with the current $50 billion cost estimate. However, it
provides an immediate tangible benefit to
the state by reducing travel time between Los Angeles and San
Francisco to just two hours. Compare
this with a five hour drive or a two-to-three hour flight
experience.
Project Delivery Schedule Summary
In keeping with this project’s sheer size, we plan for the entire
setup, construction and testing process to
take approximately 11 years, running from the beginning of
2019 to the very end of 2029. The delivery
milestones are outlined below.
Milestones Completion
Project Start Jan. 1, 2019
Route Planning Dec. 31, 2020
Zoning Approval Dec. 31, 2023
Fundraising Jul. 31, 2025
Land Acquisition Dec. 31, 2025
Infrastructure & Construction Jul. 31, 2029
Operational Testing and Service Training Dec. 31, 2029
6
Conclusion & Next Steps
RapidTrak’s proposed railway will provide efficient and safe
mass transit between two major cities,
promote energy efficiency and environmental quality in
California, and benefit regional and statewide
economic growth. We expect to complete the project by the end
of 2029, for a total cost of $50 billion.
The approval of the proposed project outlined in this business
case will enable the organization to
charter the project for next steps:
• Authorize developing a formal project plan
• Initial geographical mapping for optimize route
• Secure funding from stakeholder
• Engage relevant government officials and seek regulatory
approval
It would be wise to get the Governor of California involved in
the process relatively soon, since the
project is of material concern to the state. Also, given that we
plan on replicating Japanese rail
technologies and techniques, we would like to connect with
Japan’s Central Railway Company for
consulting advice.
Approvals
• Prepared by Nick Foster, Co-Project Manager
• Approved by Zhengda Wang, Co-Project Manager
• Certified by Tian Tian, Co-Project Manager
• Verified by Yulin Lu, Co-Project Manager
MASY1-GC1250 – Project Management in the Information Age
– Sp2022
Team Simulation Project – Project Business Case
For the second phase of the team simulation project, your team
will be expected to create and submit a business case for your
proposed project. This exercise builds from the project proposal
created in the first phase and should address any feedback
requested by your instructor in his comme nts regarding your
team’s project proposal.
A template has been provided for the business case. It is
included along with the assignment content in the designated
assignment page in NYU Classes, as well as in the Templates
folder in the Resources area. For your convenience, an example
of a business case created by a team from a former course will
also be provided.
The business case template incorporates aspects of your project
proposal and specifically addresses the reasons why the project
is being proposed. Most importantly, it includes details about
the cost and benefits of the project and lists key factors
affecting its success. Your business case should include each of
the sections listed below. Detailed explanations of each section
are included in the business case template. Please contact your
instructor if any additional explanations or clarifications are
needed:
· Executive Summary
· Current Situation
· Recommendation
· Options Considered
· Goals and Objectives
· Assumptions
· Constraints
· Critical Success Factors
· Costs and Benefits
· Project Delivery Schedule Summary
· Conclusion and Next Steps
Nowadays, smartphones are a necessity in people's lives, but the
problem with using them too often is that you can't guarantee
that they will always be fully charged when you're out. So in
order to allow cell phone users to charge their phones at any
time, this project is to promote a mobile power source in New
York called Pikachu Power Bank (PPB), which can be used to
charge phones anytime and anywhere using a USB cable,
eliminating the need to connect to an outlet. We will start with
a trial run in New York, and eventually we hope to roll it out
across the US. The power bank will have a certain lifespan, so
the company will need to replace the power bank regularly to
ensure the availability of the rechargeable battery.
Pikachu Power Bank (PPB) is the organization that takes charge
of the operation of a shared power bank in the NYC area. PPB’s
mission statement is to provide an easy lifestyle at the era of
technology. Shared power banks can be deployed in a variety of
application scenarios, such as restaurants, cinemas, shopping
malls and cafes. PPB operates a franchise model, where people
with no experience can rent or purchase our equipment (power
bank and charging pile) and set it in the partner area. We also
provide loans at a low interest rate for expanding the market.
7/24 Customer service provides dedicated remote support. PBB
also comes with a 3-year hardware warranty and software
technology upgrades for free. For customers, they can verify
their identities on the PPB app and rent the power banks at a
constant price per hour without deposit. If customers forget to
return and the cost is high because of long holding time, they
can choose to buy the power bank for personal use.
The first problem with the Pikachu power bank project that may
arise is funding needs, how to make power banks of different
specifications with the least capital. The second point is that we
need to determine the user group through market research. Like
what kind of people use the power bank most efficiently?
Thereby to determine where to place it.
Third, after the investigation, we need to cooperate with
merchants in different geographical locations, including a series
of cooperation needs such as advertising.
Electricity is always a big problem since people do not always
carry their charger wires and adapters. Considering this case,
the mission of Pikachu Power Bank (PPB) is to help people
power up their phones more conveniently, especially when they
are in emergencies. In order to achieve the strategic goal, a
contract between PPB and business partners is supposed to be
signed. Then, a good publicity is needed as well, the products
can be promoted with images such as reasonable pricing,
environmentally friendly, or swifty.
We will have stand-alone storefronts or premises in regional
markets with suitable PPB to operate. Next, we will seek
cooperation with local shops, placing our PPB in prominent
positions such as cashier counters or store entrances. There are
three main profit models: 1. Power bank rental 2. Cabinet
advertising 3. Data cable sales. As the name suggests, power
bank rental makes a profit by renting our power bank, which can
be adjusted from the price of $1 per hour according to the
market. Cabinet advertising is to place advertisements of
cooperative advertisers on our charging piles. This income
might be our main profit in popular areas, etc. Finally,
individual cabinets can provide data cables for sale, such as
vending machines.
In terms of product production, there are some points which will
directly affect the reputation of the product. As we all know, the
charging bank is a mobile energy station. In the process of
production, we must pay attention to the safety of the charging
bank. The capacity of the charging bank must strictly comply
with the national regulations. For products of raw materials,
after ensuring the safety of strength of materials, we will choose
recycled ABS resin, after use to a certain number of times,
charging bank charging efficiency will be greatly reduced. At
that time, we will offer customers who use our brand charger
bank a trade-in activity.

More Related Content

Similar to 1 Nick Foster, Tian Tian,

Rapid Ride Corridor Planning
Rapid Ride Corridor PlanningRapid Ride Corridor Planning
Rapid Ride Corridor PlanningZach Shaner
 
HSR in the US 9-2009.pdf how it works in usa
HSR in the US 9-2009.pdf how it works in usaHSR in the US 9-2009.pdf how it works in usa
HSR in the US 9-2009.pdf how it works in usarhyoju
 
Smith_Cody_Economics_Thesis_2015
Smith_Cody_Economics_Thesis_2015Smith_Cody_Economics_Thesis_2015
Smith_Cody_Economics_Thesis_2015Cody Smith
 
Moving-About-Paradise
Moving-About-ParadiseMoving-About-Paradise
Moving-About-ParadiseAlan Hoffman
 
Managing California HSPR Programs-Caltrain, Bazeley
Managing California HSPR Programs-Caltrain, Bazeley Managing California HSPR Programs-Caltrain, Bazeley
Managing California HSPR Programs-Caltrain, Bazeley Roger Bazeley, USA
 
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010Barrington Institute
 
Southwest Chief Maintenance Application
Southwest Chief Maintenance ApplicationSouthwest Chief Maintenance Application
Southwest Chief Maintenance ApplicationJoshua Sharf
 
Draft Feasibility report of the railway system in Karachi
Draft Feasibility report of the railway system in KarachiDraft Feasibility report of the railway system in Karachi
Draft Feasibility report of the railway system in KarachiUmer Mover
 
Vision plan spur 11.30 presentation - hires
Vision plan   spur 11.30 presentation - hiresVision plan   spur 11.30 presentation - hires
Vision plan spur 11.30 presentation - hiresAdina Levin
 
City Systems- Full Report
City Systems- Full ReportCity Systems- Full Report
City Systems- Full ReportGordon Best
 
121808 - FINAL Report on the Potential Impact of Regional Transit on Metropol...
121808 - FINAL Report on the Potential Impact of Regional Transit on Metropol...121808 - FINAL Report on the Potential Impact of Regional Transit on Metropol...
121808 - FINAL Report on the Potential Impact of Regional Transit on Metropol...John Crocker
 
Caltrans: Overview of Public Private Partnerships (P3)
Caltrans: Overview of Public Private Partnerships (P3)Caltrans: Overview of Public Private Partnerships (P3)
Caltrans: Overview of Public Private Partnerships (P3)AGC of California
 
P3s for Puerto Rico - 17 May 2023 - Updated.pptx
P3s for Puerto Rico  - 17 May 2023 - Updated.pptxP3s for Puerto Rico  - 17 May 2023 - Updated.pptx
P3s for Puerto Rico - 17 May 2023 - Updated.pptxMarc Joffe
 
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...Jonathan Granda
 
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 PresentationPublic Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 PresentationAGC of California
 
Economics of Crossrail (Microeconomics)
Economics of Crossrail (Microeconomics)Economics of Crossrail (Microeconomics)
Economics of Crossrail (Microeconomics)Eton College
 

Similar to 1 Nick Foster, Tian Tian, (20)

Rapid Ride Corridor Planning
Rapid Ride Corridor PlanningRapid Ride Corridor Planning
Rapid Ride Corridor Planning
 
SmartTrack & Regional Express Rail Display Boards
SmartTrack & Regional Express Rail Display BoardsSmartTrack & Regional Express Rail Display Boards
SmartTrack & Regional Express Rail Display Boards
 
HSR in the US 9-2009.pdf how it works in usa
HSR in the US 9-2009.pdf how it works in usaHSR in the US 9-2009.pdf how it works in usa
HSR in the US 9-2009.pdf how it works in usa
 
Smith_Cody_Economics_Thesis_2015
Smith_Cody_Economics_Thesis_2015Smith_Cody_Economics_Thesis_2015
Smith_Cody_Economics_Thesis_2015
 
Moving-About-Paradise
Moving-About-ParadiseMoving-About-Paradise
Moving-About-Paradise
 
Managing California HSPR Programs-Caltrain, Bazeley
Managing California HSPR Programs-Caltrain, Bazeley Managing California HSPR Programs-Caltrain, Bazeley
Managing California HSPR Programs-Caltrain, Bazeley
 
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
Economic benefits-of-hrrc-passenger-service stephan sheppard 2010
 
Info about ST3
Info about ST3Info about ST3
Info about ST3
 
Southwest Chief Maintenance Application
Southwest Chief Maintenance ApplicationSouthwest Chief Maintenance Application
Southwest Chief Maintenance Application
 
Draft Feasibility report of the railway system in Karachi
Draft Feasibility report of the railway system in KarachiDraft Feasibility report of the railway system in Karachi
Draft Feasibility report of the railway system in Karachi
 
Vision plan spur 11.30 presentation - hires
Vision plan   spur 11.30 presentation - hiresVision plan   spur 11.30 presentation - hires
Vision plan spur 11.30 presentation - hires
 
City Systems- Full Report
City Systems- Full ReportCity Systems- Full Report
City Systems- Full Report
 
DTPW's Rapid Transit Corridors Conceptual Financial Plan Proposal
DTPW's Rapid Transit Corridors Conceptual Financial Plan ProposalDTPW's Rapid Transit Corridors Conceptual Financial Plan Proposal
DTPW's Rapid Transit Corridors Conceptual Financial Plan Proposal
 
121808 - FINAL Report on the Potential Impact of Regional Transit on Metropol...
121808 - FINAL Report on the Potential Impact of Regional Transit on Metropol...121808 - FINAL Report on the Potential Impact of Regional Transit on Metropol...
121808 - FINAL Report on the Potential Impact of Regional Transit on Metropol...
 
Caltrans: Overview of Public Private Partnerships (P3)
Caltrans: Overview of Public Private Partnerships (P3)Caltrans: Overview of Public Private Partnerships (P3)
Caltrans: Overview of Public Private Partnerships (P3)
 
P3s for Puerto Rico - 17 May 2023 - Updated.pptx
P3s for Puerto Rico  - 17 May 2023 - Updated.pptxP3s for Puerto Rico  - 17 May 2023 - Updated.pptx
P3s for Puerto Rico - 17 May 2023 - Updated.pptx
 
NCDOT Rail Update
NCDOT Rail UpdateNCDOT Rail Update
NCDOT Rail Update
 
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
Archived - Metrolinx to modernize signalling system in Toronto's Union Statio...
 
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 PresentationPublic Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
Public Private Partnerships (P3) - Kome Ajese AGC 01.2011 Presentation
 
Economics of Crossrail (Microeconomics)
Economics of Crossrail (Microeconomics)Economics of Crossrail (Microeconomics)
Economics of Crossrail (Microeconomics)
 

More from AbbyWhyte974

1. Use Postman” to test API at  httpspostman-echo.coma. Use
1. Use Postman” to test API at  httpspostman-echo.coma. Use1. Use Postman” to test API at  httpspostman-echo.coma. Use
1. Use Postman” to test API at  httpspostman-echo.coma. UseAbbyWhyte974
 
1. Use the rubric to complete the assignment and pay attention t
1. Use the rubric to complete the assignment and pay attention t1. Use the rubric to complete the assignment and pay attention t
1. Use the rubric to complete the assignment and pay attention tAbbyWhyte974
 
1. True or false. Unlike a merchandising business, a manufacturing
1. True or false. Unlike a merchandising business, a manufacturing1. True or false. Unlike a merchandising business, a manufacturing
1. True or false. Unlike a merchandising business, a manufacturingAbbyWhyte974
 
1. Top hedge fund manager Sally Buffit believes that a stock with
1. Top hedge fund manager Sally Buffit believes that a stock with 1. Top hedge fund manager Sally Buffit believes that a stock with
1. Top hedge fund manager Sally Buffit believes that a stock with AbbyWhyte974
 
1. This question is on the application of the Binomial option
1. This question is on the application of the Binomial option1. This question is on the application of the Binomial option
1. This question is on the application of the Binomial optionAbbyWhyte974
 
1. Tiktaalik httpswww.palaeocast.comtiktaalikW
1. Tiktaalik        httpswww.palaeocast.comtiktaalikW1. Tiktaalik        httpswww.palaeocast.comtiktaalikW
1. Tiktaalik httpswww.palaeocast.comtiktaalikWAbbyWhyte974
 
1. This week, we learned about the balanced scorecard and dashboar
1. This week, we learned about the balanced scorecard and dashboar1. This week, we learned about the balanced scorecard and dashboar
1. This week, we learned about the balanced scorecard and dashboarAbbyWhyte974
 
1. The company I chose was Amazon2.3.4.1) Keep i
1. The company I chose was Amazon2.3.4.1) Keep i1. The company I chose was Amazon2.3.4.1) Keep i
1. The company I chose was Amazon2.3.4.1) Keep iAbbyWhyte974
 
1. Think about a persuasive speech that you would like to present
1. Think about a persuasive speech that you would like to present 1. Think about a persuasive speech that you would like to present
1. Think about a persuasive speech that you would like to present AbbyWhyte974
 
1. The two properties about a set of measurements of a dependent v
1. The two properties about a set of measurements of a dependent v1. The two properties about a set of measurements of a dependent v
1. The two properties about a set of measurements of a dependent vAbbyWhyte974
 
1. The Danube River flows through 10 countries. Name them in the s
1. The Danube River flows through 10 countries. Name them in the s1. The Danube River flows through 10 countries. Name them in the s
1. The Danube River flows through 10 countries. Name them in the sAbbyWhyte974
 
1. The 3 genes that you will compare at listed below. Take a look.
1. The 3 genes that you will compare at listed below. Take a look.1. The 3 genes that you will compare at listed below. Take a look.
1. The 3 genes that you will compare at listed below. Take a look.AbbyWhyte974
 
1. Student and trainer detailsStudent details Full nameStu
1. Student and trainer detailsStudent details  Full nameStu1. Student and trainer detailsStudent details  Full nameStu
1. Student and trainer detailsStudent details Full nameStuAbbyWhyte974
 
1. Student uses MS Excel to calculate income tax expense or refund
1. Student uses MS Excel to calculate income tax expense or refund1. Student uses MS Excel to calculate income tax expense or refund
1. Student uses MS Excel to calculate income tax expense or refundAbbyWhyte974
 
1. Socrates - In your view, what was it about Socrates’ teachings
1. Socrates - In your view, what was it about Socrates’ teachings 1. Socrates - In your view, what was it about Socrates’ teachings
1. Socrates - In your view, what was it about Socrates’ teachings AbbyWhyte974
 
1. Select a patient” (friend or family member) on whom to perform
1. Select a patient” (friend or family member) on whom to perform1. Select a patient” (friend or family member) on whom to perform
1. Select a patient” (friend or family member) on whom to performAbbyWhyte974
 
1. Respond to your classmates’ question and post. Submission to y
1. Respond to your classmates’ question and post.  Submission to y1. Respond to your classmates’ question and post.  Submission to y
1. Respond to your classmates’ question and post. Submission to yAbbyWhyte974
 
1. Review the HCAPHS survey document, by clicking on the hyperlink
1. Review the HCAPHS survey document, by clicking on the hyperlink1. Review the HCAPHS survey document, by clicking on the hyperlink
1. Review the HCAPHS survey document, by clicking on the hyperlinkAbbyWhyte974
 
1. Saint Leo Portal loginUser ID[email protected]
1. Saint Leo Portal loginUser ID[email protected]          1. Saint Leo Portal loginUser ID[email protected]
1. Saint Leo Portal loginUser ID[email protected] AbbyWhyte974
 
1. Reference is ch. 5 in the e-text, or ch. 2 in paper text...plea
1. Reference is ch. 5 in the e-text, or ch. 2 in paper text...plea1. Reference is ch. 5 in the e-text, or ch. 2 in paper text...plea
1. Reference is ch. 5 in the e-text, or ch. 2 in paper text...pleaAbbyWhyte974
 

More from AbbyWhyte974 (20)

1. Use Postman” to test API at  httpspostman-echo.coma. Use
1. Use Postman” to test API at  httpspostman-echo.coma. Use1. Use Postman” to test API at  httpspostman-echo.coma. Use
1. Use Postman” to test API at  httpspostman-echo.coma. Use
 
1. Use the rubric to complete the assignment and pay attention t
1. Use the rubric to complete the assignment and pay attention t1. Use the rubric to complete the assignment and pay attention t
1. Use the rubric to complete the assignment and pay attention t
 
1. True or false. Unlike a merchandising business, a manufacturing
1. True or false. Unlike a merchandising business, a manufacturing1. True or false. Unlike a merchandising business, a manufacturing
1. True or false. Unlike a merchandising business, a manufacturing
 
1. Top hedge fund manager Sally Buffit believes that a stock with
1. Top hedge fund manager Sally Buffit believes that a stock with 1. Top hedge fund manager Sally Buffit believes that a stock with
1. Top hedge fund manager Sally Buffit believes that a stock with
 
1. This question is on the application of the Binomial option
1. This question is on the application of the Binomial option1. This question is on the application of the Binomial option
1. This question is on the application of the Binomial option
 
1. Tiktaalik httpswww.palaeocast.comtiktaalikW
1. Tiktaalik        httpswww.palaeocast.comtiktaalikW1. Tiktaalik        httpswww.palaeocast.comtiktaalikW
1. Tiktaalik httpswww.palaeocast.comtiktaalikW
 
1. This week, we learned about the balanced scorecard and dashboar
1. This week, we learned about the balanced scorecard and dashboar1. This week, we learned about the balanced scorecard and dashboar
1. This week, we learned about the balanced scorecard and dashboar
 
1. The company I chose was Amazon2.3.4.1) Keep i
1. The company I chose was Amazon2.3.4.1) Keep i1. The company I chose was Amazon2.3.4.1) Keep i
1. The company I chose was Amazon2.3.4.1) Keep i
 
1. Think about a persuasive speech that you would like to present
1. Think about a persuasive speech that you would like to present 1. Think about a persuasive speech that you would like to present
1. Think about a persuasive speech that you would like to present
 
1. The two properties about a set of measurements of a dependent v
1. The two properties about a set of measurements of a dependent v1. The two properties about a set of measurements of a dependent v
1. The two properties about a set of measurements of a dependent v
 
1. The Danube River flows through 10 countries. Name them in the s
1. The Danube River flows through 10 countries. Name them in the s1. The Danube River flows through 10 countries. Name them in the s
1. The Danube River flows through 10 countries. Name them in the s
 
1. The 3 genes that you will compare at listed below. Take a look.
1. The 3 genes that you will compare at listed below. Take a look.1. The 3 genes that you will compare at listed below. Take a look.
1. The 3 genes that you will compare at listed below. Take a look.
 
1. Student and trainer detailsStudent details Full nameStu
1. Student and trainer detailsStudent details  Full nameStu1. Student and trainer detailsStudent details  Full nameStu
1. Student and trainer detailsStudent details Full nameStu
 
1. Student uses MS Excel to calculate income tax expense or refund
1. Student uses MS Excel to calculate income tax expense or refund1. Student uses MS Excel to calculate income tax expense or refund
1. Student uses MS Excel to calculate income tax expense or refund
 
1. Socrates - In your view, what was it about Socrates’ teachings
1. Socrates - In your view, what was it about Socrates’ teachings 1. Socrates - In your view, what was it about Socrates’ teachings
1. Socrates - In your view, what was it about Socrates’ teachings
 
1. Select a patient” (friend or family member) on whom to perform
1. Select a patient” (friend or family member) on whom to perform1. Select a patient” (friend or family member) on whom to perform
1. Select a patient” (friend or family member) on whom to perform
 
1. Respond to your classmates’ question and post. Submission to y
1. Respond to your classmates’ question and post.  Submission to y1. Respond to your classmates’ question and post.  Submission to y
1. Respond to your classmates’ question and post. Submission to y
 
1. Review the HCAPHS survey document, by clicking on the hyperlink
1. Review the HCAPHS survey document, by clicking on the hyperlink1. Review the HCAPHS survey document, by clicking on the hyperlink
1. Review the HCAPHS survey document, by clicking on the hyperlink
 
1. Saint Leo Portal loginUser ID[email protected]
1. Saint Leo Portal loginUser ID[email protected]          1. Saint Leo Portal loginUser ID[email protected]
1. Saint Leo Portal loginUser ID[email protected]
 
1. Reference is ch. 5 in the e-text, or ch. 2 in paper text...plea
1. Reference is ch. 5 in the e-text, or ch. 2 in paper text...plea1. Reference is ch. 5 in the e-text, or ch. 2 in paper text...plea
1. Reference is ch. 5 in the e-text, or ch. 2 in paper text...plea
 

Recently uploaded

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Educationpboyjonauth
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17Celine George
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...JhezDiaz1
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...Nguyen Thanh Tu Collection
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentInMediaRes1
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxEyham Joco
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementmkooblal
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxpboyjonauth
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxOH TEIK BIN
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon AUnboundStockton
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for BeginnersSabitha Banu
 
Quarter 4 Peace-education.pptx Catch Up Friday
Quarter 4 Peace-education.pptx Catch Up FridayQuarter 4 Peace-education.pptx Catch Up Friday
Quarter 4 Peace-education.pptx Catch Up FridayMakMakNepo
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfphamnguyenenglishnb
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfMr Bounab Samir
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPCeline George
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPCeline George
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........LeaCamillePacle
 

Recently uploaded (20)

Introduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher EducationIntroduction to ArtificiaI Intelligence in Higher Education
Introduction to ArtificiaI Intelligence in Higher Education
 
How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17How to Configure Email Server in Odoo 17
How to Configure Email Server in Odoo 17
 
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
ENGLISH 7_Q4_LESSON 2_ Employing a Variety of Strategies for Effective Interp...
 
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
HỌC TỐT TIẾNG ANH 11 THEO CHƯƠNG TRÌNH GLOBAL SUCCESS ĐÁP ÁN CHI TIẾT - CẢ NĂ...
 
Alper Gobel In Media Res Media Component
Alper Gobel In Media Res Media ComponentAlper Gobel In Media Res Media Component
Alper Gobel In Media Res Media Component
 
Types of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptxTypes of Journalistic Writing Grade 8.pptx
Types of Journalistic Writing Grade 8.pptx
 
Hierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of managementHierarchy of management that covers different levels of management
Hierarchy of management that covers different levels of management
 
Introduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptxIntroduction to AI in Higher Education_draft.pptx
Introduction to AI in Higher Education_draft.pptx
 
Solving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptxSolving Puzzles Benefits Everyone (English).pptx
Solving Puzzles Benefits Everyone (English).pptx
 
Crayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon ACrayon Activity Handout For the Crayon A
Crayon Activity Handout For the Crayon A
 
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdfTataKelola dan KamSiber Kecerdasan Buatan v022.pdf
TataKelola dan KamSiber Kecerdasan Buatan v022.pdf
 
Full Stack Web Development Course for Beginners
Full Stack Web Development Course  for BeginnersFull Stack Web Development Course  for Beginners
Full Stack Web Development Course for Beginners
 
9953330565 Low Rate Call Girls In Rohini Delhi NCR
9953330565 Low Rate Call Girls In Rohini  Delhi NCR9953330565 Low Rate Call Girls In Rohini  Delhi NCR
9953330565 Low Rate Call Girls In Rohini Delhi NCR
 
Quarter 4 Peace-education.pptx Catch Up Friday
Quarter 4 Peace-education.pptx Catch Up FridayQuarter 4 Peace-education.pptx Catch Up Friday
Quarter 4 Peace-education.pptx Catch Up Friday
 
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdfAMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
AMERICAN LANGUAGE HUB_Level2_Student'sBook_Answerkey.pdf
 
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdfLike-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
Like-prefer-love -hate+verb+ing & silent letters & citizenship text.pdf
 
How to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERPHow to do quick user assign in kanban in Odoo 17 ERP
How to do quick user assign in kanban in Odoo 17 ERP
 
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
Model Call Girl in Tilak Nagar Delhi reach out to us at 🔝9953056974🔝
 
What is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERPWhat is Model Inheritance in Odoo 17 ERP
What is Model Inheritance in Odoo 17 ERP
 
Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........Atmosphere science 7 quarter 4 .........
Atmosphere science 7 quarter 4 .........
 

1 Nick Foster, Tian Tian,

  • 1. 1 Nick Foster, Tian Tian, Yulin Lu, Zhengda Wang Project Management in the Information Age MASY1-GC1250.100 Team Project Business Case June 27, 2017
  • 2. Contents Executive Summary (Nick)..................................................................................... ........................ 2 Current Situation (Tian) ............................................................................................... .................. 2 Recommendation (Zhengda) ............................................................................................... ............ 2 Options Considered (Zhengda) ............................................................................................... ....... 3 Goals & Objectives (Tian) ............................................................................................... ............... 3 Assumptions (Nick) ............................................................................................... ......................... 4 Constraints (Nick) ............................................................................................... ............................ 4 Critical Success Factors (Zhengda) ............................................................................................... . 4
  • 3. Costs & Benefits (Yulin) ............................................................................................... ................. 5 Project Delivery Schedule Summary (Yulin) ................................................................................. 5 Conclusion & Next Steps (Yulin) ............................................................................................... .... 6 2 Executive Summary The purpose of this project is enhance California’s economy by way of a high-speed rail line between Los Angeles and San Francisco, in keeping with RapidTrak’s mission to expand high-speed rail service across the country. Our project will catalyze environmental and economic benefits in the state and greatly reduce the time necessary to travel between its two biggest cities. Total costs for the entire endeavor are projected at $50 billion, for an estimated completion by the end of 2029.
  • 4. Current Situation Compared to systems in Japan, China and Europe, inter-city rail service in the United States is undeveloped. The main national carrier, Amtrak, is only profitable in its Northeast Corridor line (serving Boston to Washington, D.C.), and even the “high-speed” Acela trains that operate on this line are very slow compared to state-of-the-art high-speed rail abroad. However, American public interest in high- speed rail is markedly on the rise, especially in the wealthier , more densely-populated coastal states. This comes at a time when interest in revitalizing America’s transportation infrastructure to be more environmentally friendly is also reaching a peak. The domestic railway industry is generally stagnant or in decline, with a lack of appropriate investment in new technology and expert personnel leaving the workforce. Throughout the country, Amtrak operates slow, outdated trains, mostly on tracks that are actually owned by major freight rail lines, meaning that passenger traffic must yield to freight at all times. Domestic expertise in high-speed rail is
  • 5. limited, so any attempt to implement a high-speed system here will have to import and adapt technologies pertaining to the design and control of the trains themselves, techniques in track construction and more. Recommendation Given these challenges, our attention turns to California, which has made it a priority to improve its environment and transportation in tandem. The state’s roadways are among the most-used (and most- congested) in the nation, with drivers wasting over $18 billion annually in lost productivity and wasted fuel. Moreover, the air travel routes between Los Angeles and San Francisco serve over five million passengers annually but regular delays significantly erode the time saved by flying. As passenger volumes increase and climate and pollution become more of a concern, it becomes clear that the state is in serious need of additional transportation options. Therefore, California is a perfect candidate for RapidTrak’s inaugural high-speed project. Our recommendation is to construct and operate a high-speed rail line between Los Angeles and San
  • 6. Francisco, in the style of Japan’s “Shinkansen” railroad, connecting the cities of Bakersfield, Fresno and San Jose along the way. Planning and executing the project within a single state exposes us to fewer political and regulatory challenges. Plus, California’s government is receptive to the idea of high-speed rail, so we expect it to be a cooperative partner. We expect such a rail line to achieve a range of economic and environmental effects for the state, summarized here and further elaborated throughout this document: . • Reduced travel times • Job creation 3 • Statewide economic growth • Greenhouse gas reductions • Eased traffic congestion and fewer automobile accidents
  • 7. Options Considered Because RapidTrack has a nation-wide mission, we chose between three potential routes for a new high- speed line: • Boston to Washington, D.C.: This route would accelerate transit along the profitable and densely populated Northeast Corridor. • New York to Chicago: Satisfies an under-served East-West route and improves economic access to/from Midwest cities like Indianapolis, Columbus and Pittsburgh. • Los Angeles to San Francisco: Operates in a single state, serves two of the nation’s highest- value cities, and solves known, critical problems about traffic and pollution. Within this scope, however, and because domestic expertise in high-speed rail is limited, we have to choose whether to model RapidTraks’ line on Chinese, Japanese or European technology. Ultimately we are attracted to Japan’s “Shinkansen” system for its excellent safety ratings and overall high quality. Goals & Objectives RapidTrack’s goal is to improve California’s transportation infrastructure, ease environmental pressure,
  • 8. and create economic opportunity in the region. To that end, the objective of this project is to build a high-speed rail line connecting Los Angeles and San Francisco, the state’s two most important cities. Providing a reliable rail network can help serve the needs of national and regional area by offering convenient access to economic centers. We hope to achieve the following objectives by way of our high- speed line. • Reduction in travel time. Covering a little over 400 miles at speeds approaching 200 miles per hour, the total length of a journey between Los Angeles and San Francisco should be little more than two hours. Currently, flying between each city takes at least two and a half hours, accounting for time spent getting to or from each airport in California’s bad traffic. • Reduction in carbon emissions. The rail line could eliminate up to 300,000 metric tons of carbon dioxide (CO2) emissions in the first year of operation, equivalent to 53,000 personal vehicles taken off the road. By 2040, the system is estimated to
  • 9. reduce vehicles miles of travel in the state by almost 10 million miles of travel every day. • Reduction in auto accidents. By providing a safe, efficient alternative, we hope to reduce auto accidents in line with a general reduction in auto traffic between both termini. • Economic growth. The rail line will provide faster and more convenient access to major city centers, extending the geographic range in which they can spend money and work. We expect the project to add at least 100,000 jobs to the California economy, accounting for temporary work attached to the project itself and permanent job growth resulting from the train’s presence in the region. 4 Assumptions The project makes a set of assumptions about the logistics and nature of the proposed high-speed line:
  • 10. • What RapidTrak provides to California aligns with its expressed goals and values, so therefore we assume that state and local governments will be cooperative, at least enough as to not impede the project. • We will make a conservative assumption that we will not be able to acquire all the land necessary for tracks and stations along our idealized route. We assume that it will sometimes be necessary to deviate from the planned route in order to avoid insurmountable costs or inconvenience, even though doing so will require changes to scheduling and budget. • The extent of the economic benefit to California can only be drawn in assumptions at this point. Past rail projects in other countries do point to promising results, however. • The most basic assumption made by this project is that Californians would be interested enough in high-speed rail to use our line in such high numbers as to achieve the desired economic benefit for the region. Constraints
  • 11. We also have to acknowledge the challenges and constraints that will likely affect our work. • As mentioned in the proposal, one of the biggest sets of constraints will be where exactly RapidTrak can secure land for building the tracks. • Because of RapidTrak’s ownership by the federal government, we expect conflict over budget constraints to arise every year, especially during times of turnover in political leadership as the government re-calibrates its priorities for infrastructure spending. • Constructing the rail line will require a massive amount of labor, over a long period of time and spread across a wide geographical area. It could be challenge to have as many appropriately skilled workers as are needed at all active job sites at all times. Critical Success Factors In order for this project to be successful, we see five factors that deserve our close attention moving forward. • A highly detailed but flexible WBS. This will be a massive,
  • 12. long-term infrastructure project, vulnerable to complication and delay at a micro level. Our work breakdown structure must be able to account for the possibility of contingency spending, crashing, re-scheduling and more whenever necessary. • Effective control of the project budget. The demands of the WBS also mean that at a high- level, the management of our project budget must be of utmost quality. • Diligent earned value management. Because this will be such a large, expensive project with so many moving parts, we must play close attention to how we are spending our funds, which aspects of the project are making the most efficient use of time and money, and be ready to re- plan or re-allocate those resources within the project portfolio as becomes necessary. • Satisfaction of state and local government stakeholders. It will be crucial to keep these stakeholders informed, engaged and satisfied with and about our work. If RapidTrak should wear out its welcome in the state, our project will be doomed. 5
  • 13. • Excellence in procurement and labor management. The rail line will run for hundreds of miles, in a years-long construction effort. It will be of utmost importance to ensure that the project has enough labor hired and in action in the right place at the right time, all the time. Building materials and other vital components, such as the rolling stock itself, will need to sourced and delivered to budget, on time, and without complication. To measure the ultimate success of the project, reference the economic benefits cited in our Recommendation, Goals & Objectives and Costs & Benefits. Costs & Benefits This project will be a major undertaking, costing billions of dollars over more than a decade. We estimate that RapidTrak will need to acquire approximately 9,000 acres of land in order to construct the track, calculated at 500 miles (building a buffer into the net lengths, as per our assumptions) by 150 feet (needed for the width of the track and relevant infrastructure. At an average cost of $12,000 per acre of irrigated cropland in California (comprising most of the land
  • 14. between our target cities), this comes to a net estimated cost of $108 million for land acquisition. Add this figure to the expected combined costs of construction labor, rolling stock (Japan’s Shinkansen trains are very expensive), information technology, facilities and stations, and contingency funds, and we anticipate the total cost of the project to be $35 billion. With a 30% buffer, the total budget rises to $50 billion. As 10,000 passengers per day, it would take 137 years of passengers paying $100 for a ticket to break even with the current $50 billion cost estimate. However, it provides an immediate tangible benefit to the state by reducing travel time between Los Angeles and San Francisco to just two hours. Compare this with a five hour drive or a two-to-three hour flight experience. Project Delivery Schedule Summary In keeping with this project’s sheer size, we plan for the entire setup, construction and testing process to take approximately 11 years, running from the beginning of 2019 to the very end of 2029. The delivery
  • 15. milestones are outlined below. Milestones Completion Project Start Jan. 1, 2019 Route Planning Dec. 31, 2020 Zoning Approval Dec. 31, 2023 Fundraising Jul. 31, 2025 Land Acquisition Dec. 31, 2025 Infrastructure & Construction Jul. 31, 2029 Operational Testing and Service Training Dec. 31, 2029 6 Conclusion & Next Steps RapidTrak’s proposed railway will provide efficient and safe mass transit between two major cities, promote energy efficiency and environmental quality in California, and benefit regional and statewide economic growth. We expect to complete the project by the end of 2029, for a total cost of $50 billion.
  • 16. The approval of the proposed project outlined in this business case will enable the organization to charter the project for next steps: • Authorize developing a formal project plan • Initial geographical mapping for optimize route • Secure funding from stakeholder • Engage relevant government officials and seek regulatory approval It would be wise to get the Governor of California involved in the process relatively soon, since the project is of material concern to the state. Also, given that we plan on replicating Japanese rail technologies and techniques, we would like to connect with Japan’s Central Railway Company for consulting advice.
  • 17. Approvals • Prepared by Nick Foster, Co-Project Manager • Approved by Zhengda Wang, Co-Project Manager • Certified by Tian Tian, Co-Project Manager • Verified by Yulin Lu, Co-Project Manager MASY1-GC1250 – Project Management in the Information Age – Sp2022 Team Simulation Project – Project Business Case For the second phase of the team simulation project, your team will be expected to create and submit a business case for your proposed project. This exercise builds from the project proposal created in the first phase and should address any feedback requested by your instructor in his comme nts regarding your team’s project proposal. A template has been provided for the business case. It is included along with the assignment content in the designated
  • 18. assignment page in NYU Classes, as well as in the Templates folder in the Resources area. For your convenience, an example of a business case created by a team from a former course will also be provided. The business case template incorporates aspects of your project proposal and specifically addresses the reasons why the project is being proposed. Most importantly, it includes details about the cost and benefits of the project and lists key factors affecting its success. Your business case should include each of the sections listed below. Detailed explanations of each section are included in the business case template. Please contact your instructor if any additional explanations or clarifications are needed: · Executive Summary · Current Situation · Recommendation · Options Considered · Goals and Objectives · Assumptions · Constraints · Critical Success Factors · Costs and Benefits · Project Delivery Schedule Summary · Conclusion and Next Steps Nowadays, smartphones are a necessity in people's lives, but the problem with using them too often is that you can't guarantee that they will always be fully charged when you're out. So in order to allow cell phone users to charge their phones at any time, this project is to promote a mobile power source in New York called Pikachu Power Bank (PPB), which can be used to charge phones anytime and anywhere using a USB cable, eliminating the need to connect to an outlet. We will start with a trial run in New York, and eventually we hope to roll it out across the US. The power bank will have a certain lifespan, so
  • 19. the company will need to replace the power bank regularly to ensure the availability of the rechargeable battery. Pikachu Power Bank (PPB) is the organization that takes charge of the operation of a shared power bank in the NYC area. PPB’s mission statement is to provide an easy lifestyle at the era of technology. Shared power banks can be deployed in a variety of application scenarios, such as restaurants, cinemas, shopping malls and cafes. PPB operates a franchise model, where people with no experience can rent or purchase our equipment (power bank and charging pile) and set it in the partner area. We also provide loans at a low interest rate for expanding the market. 7/24 Customer service provides dedicated remote support. PBB also comes with a 3-year hardware warranty and software technology upgrades for free. For customers, they can verify their identities on the PPB app and rent the power banks at a constant price per hour without deposit. If customers forget to return and the cost is high because of long holding time, they can choose to buy the power bank for personal use. The first problem with the Pikachu power bank project that may arise is funding needs, how to make power banks of different specifications with the least capital. The second point is that we need to determine the user group through market research. Like what kind of people use the power bank most efficiently? Thereby to determine where to place it. Third, after the investigation, we need to cooperate with merchants in different geographical locations, including a series of cooperation needs such as advertising. Electricity is always a big problem since people do not always carry their charger wires and adapters. Considering this case, the mission of Pikachu Power Bank (PPB) is to help people power up their phones more conveniently, especially when they are in emergencies. In order to achieve the strategic goal, a contract between PPB and business partners is supposed to be signed. Then, a good publicity is needed as well, the products can be promoted with images such as reasonable pricing, environmentally friendly, or swifty.
  • 20. We will have stand-alone storefronts or premises in regional markets with suitable PPB to operate. Next, we will seek cooperation with local shops, placing our PPB in prominent positions such as cashier counters or store entrances. There are three main profit models: 1. Power bank rental 2. Cabinet advertising 3. Data cable sales. As the name suggests, power bank rental makes a profit by renting our power bank, which can be adjusted from the price of $1 per hour according to the market. Cabinet advertising is to place advertisements of cooperative advertisers on our charging piles. This income might be our main profit in popular areas, etc. Finally, individual cabinets can provide data cables for sale, such as vending machines. In terms of product production, there are some points which will directly affect the reputation of the product. As we all know, the charging bank is a mobile energy station. In the process of production, we must pay attention to the safety of the charging bank. The capacity of the charging bank must strictly comply with the national regulations. For products of raw materials, after ensuring the safety of strength of materials, we will choose recycled ABS resin, after use to a certain number of times, charging bank charging efficiency will be greatly reduced. At that time, we will offer customers who use our brand charger bank a trade-in activity.