SlideShare a Scribd company logo
1 of 20
 During the construction of the spectacular
Oresund bridge and tunnel, which connects
Sweden to Denmark, risk analysis showed that
the project was unlikely to meet its planned
opening date upon which its financial viability
was calculated. Mitigating actions and
alternative scenarios were considered leading
to significant changes in approach. After the
mitigating actions were applied, the risk
analysis showed high confidence that Oresund
could be opened three months early - which it
was. Early opening easily paid for the specialist
risk management work.
 A European retail and wholesale bank
replaced its core operational systems
following their "Rapid Implementation
Plan" (RIP). Their previous systems were
obsolete and inadequate. As they
needed the space for the new hardware
when it was ready, they physically
removed and scrapped the old
hardware to switch over immediately to
the new system.
 Very soon, major problems were found
with the new system. It did not correctly
calculate interest and consequently was
misstating customers' balances. Very
large amounts of money were vanishing
in the accounts. There was no possibility
of reverting to the previous system.
 Our review identified the problems and
external teams were brought in to fix the
system and to correct the accounts. The
one thing we could not fix was their
reputation. The bank was no longer a
viable profit-making entity, but, thanks to
our work, it was able to cease retail
trading in an orderly fashion.
 A global telecoms service provider had
built new customer and billing systems.
To save time and cost, no one had
bothered to document the system. Some
time later they realized that this was
causing operational difficulties in running
the system.
 Our work was to retro-document the
systems. As no one knew any of the
detail we did this by examining the code
and deciphering what it did. One
element of the billing algorithm was
particularly strange. When we explained
it to the Finance Director he said "no it
can't work like that - if it did we'd be
bankrupt". It did, they were.
Identify Risk
Analyze
Probability
and Impact
Apply avoidance or
Reduction
Define
Contingency Plans
Monitor
and
Manage
Realistic risks should be identified.
Capture the information electronically in a risk register.
Following things should be noted:
 Description of the risk.
 Probability of the risk occurrence.
 Description of the potential impact of the risk
 Likely cost to the project or organization if that risk
occurs
 What actions should be taken now and by Whom
 What contingency plans should be formulated now
so that the organization is ready to act if the risk
occurs.
Team members should be motivated to
list the potential risk items .
List of the potential risk items should be
compile into single list with duplicates
removed .
Break the master list in small parts and
each part of list should be used to
identify the triggers (warning signs) for
project risks.
Calculate the probability and the
impact of each item on the master
list.
Identify possible preventive actions for
the threats.
Create a contingency plan for all project
risks a plan that includes the actions one
would take if a trigger or a risk were to
occur.
Determine the owner of each risk on the
list.
 The owner is the person who is
responsible for watching out for triggers
and then for responding appropriately if
the triggers do in fact occur by
implementing the pre-approved and
now established contingency plan.
For quick implementation and any
clarification please contact : -
Vishvas Yadav
Senior Manager/ Business Analyst
Codoca Mtvcola Marketing Advertising
And Outsourcing Pvt. Ltd.
Mail id : info@codocamtvcola.co.in
Mobile: 08884782639

More Related Content

Viewers also liked

Project Implementation Process
Project Implementation ProcessProject Implementation Process
Project Implementation Process
eklaksh
 
Strategy implementation
Strategy implementationStrategy implementation
Strategy implementation
bwire sedrick
 
2013 yaz modasi
2013 yaz modasi2013 yaz modasi
2013 yaz modasi
gizem13
 
Sustainable development, human dignity and family
Sustainable development, human dignity and familySustainable development, human dignity and family
Sustainable development, human dignity and family
Almudena Divi
 

Viewers also liked (19)

Friday roundtable oresund_bridge
Friday roundtable oresund_bridgeFriday roundtable oresund_bridge
Friday roundtable oresund_bridge
 
The øresund bridge
The øresund bridge  The øresund bridge
The øresund bridge
 
Pont oresund
Pont oresundPont oresund
Pont oresund
 
The amazing bridge
The amazing bridgeThe amazing bridge
The amazing bridge
 
Project Implementation Process
Project Implementation ProcessProject Implementation Process
Project Implementation Process
 
Project Implementation
Project ImplementationProject Implementation
Project Implementation
 
Strategy implementation
Strategy implementationStrategy implementation
Strategy implementation
 
Bahasa indonesia
Bahasa indonesiaBahasa indonesia
Bahasa indonesia
 
2013 yaz modasi
2013 yaz modasi2013 yaz modasi
2013 yaz modasi
 
Иван Кучеренко, SPN Ogilvy
Иван Кучеренко, SPN Ogilvy Иван Кучеренко, SPN Ogilvy
Иван Кучеренко, SPN Ogilvy
 
Sustainable development, human dignity and family
Sustainable development, human dignity and familySustainable development, human dignity and family
Sustainable development, human dignity and family
 
May 2011 highlights slideshow
May 2011 highlights slideshowMay 2011 highlights slideshow
May 2011 highlights slideshow
 
Economy Matters
Economy MattersEconomy Matters
Economy Matters
 
Экологический контроль в Волгоградской области
Экологический контроль в Волгоградской областиЭкологический контроль в Волгоградской области
Экологический контроль в Волгоградской области
 
Onafhankelijk advies pensioen, hypotheek
Onafhankelijk advies pensioen, hypotheekOnafhankelijk advies pensioen, hypotheek
Onafhankelijk advies pensioen, hypotheek
 
Prism, November 2013
Prism, November 2013Prism, November 2013
Prism, November 2013
 
PCIC Data Portal 2.0
PCIC Data Portal 2.0PCIC Data Portal 2.0
PCIC Data Portal 2.0
 
Zinavo technologies services
Zinavo technologies servicesZinavo technologies services
Zinavo technologies services
 
Алексей Геращенко, Freud House; Евгений Сафонов, Владимир Медушивский, Promodo
Алексей Геращенко, Freud House; Евгений Сафонов, Владимир Медушивский, PromodoАлексей Геращенко, Freud House; Евгений Сафонов, Владимир Медушивский, Promodo
Алексей Геращенко, Freud House; Евгений Сафонов, Владимир Медушивский, Promodo
 

Similar to Process implementation for project risk management

1Risk ReportingRisk ReportingRique Gidde.docx
1Risk ReportingRisk ReportingRique Gidde.docx1Risk ReportingRisk ReportingRique Gidde.docx
1Risk ReportingRisk ReportingRique Gidde.docx
felicidaddinwoodie
 
Contingency Plan WAK BANKS ATM
Contingency Plan WAK BANKS ATMContingency Plan WAK BANKS ATM
Contingency Plan WAK BANKS ATM
Wajahat Ali Khan
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.ppt
BetshaTizazu2
 
Project Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docxProject Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docx
AASTHA76
 
Project Risk Management Plan © 2015 by Jones & Bartl.docx
 Project Risk Management Plan © 2015 by Jones & Bartl.docx Project Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docx
gertrudebellgrove
 
Project Risk Management Plan © 2015 by Jones & Bartl.docx
 Project Risk Management Plan © 2015 by Jones & Bartl.docx Project Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docx
aryan532920
 

Similar to Process implementation for project risk management (20)

1Risk ReportingRisk ReportingRique Gidde.docx
1Risk ReportingRisk ReportingRique Gidde.docx1Risk ReportingRisk ReportingRique Gidde.docx
1Risk ReportingRisk ReportingRique Gidde.docx
 
Bt8901 objective oriented systems2
Bt8901 objective oriented systems2Bt8901 objective oriented systems2
Bt8901 objective oriented systems2
 
Contingency Plan WAK BANKS ATM
Contingency Plan WAK BANKS ATMContingency Plan WAK BANKS ATM
Contingency Plan WAK BANKS ATM
 
Detailed Programme Case Study
Detailed Programme Case StudyDetailed Programme Case Study
Detailed Programme Case Study
 
اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222اهم برزنتيشن لجنك2222
اهم برزنتيشن لجنك2222
 
project_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.pptproject_risk_mgmt_final 1.ppt
project_risk_mgmt_final 1.ppt
 
PMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.pptPMI project_risk_management_final_2022.ppt
PMI project_risk_management_final_2022.ppt
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.ppt
 
project_risk_mgmt_final.ppt
project_risk_mgmt_final.pptproject_risk_mgmt_final.ppt
project_risk_mgmt_final.ppt
 
Project risk management
Project risk managementProject risk management
Project risk management
 
Storytelling, el poder de las historias como elemento de gestión del conocimi...
Storytelling, el poder de las historias como elemento de gestión del conocimi...Storytelling, el poder de las historias como elemento de gestión del conocimi...
Storytelling, el poder de las historias como elemento de gestión del conocimi...
 
What it managers need to know about working capital it-toolkits.org
What it managers need to know about working capital   it-toolkits.orgWhat it managers need to know about working capital   it-toolkits.org
What it managers need to know about working capital it-toolkits.org
 
8. project risk management
8. project risk management8. project risk management
8. project risk management
 
Project Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docxProject Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docx
 
Risk analysis
Risk analysisRisk analysis
Risk analysis
 
IRJET-Financial Distress Prediction of a Company using Data Mining
IRJET-Financial Distress Prediction of a Company using Data MiningIRJET-Financial Distress Prediction of a Company using Data Mining
IRJET-Financial Distress Prediction of a Company using Data Mining
 
Joe Graziano – Challenge 2 Design Solution (Part 2)
Joe Graziano – Challenge 2 Design Solution (Part 2)Joe Graziano – Challenge 2 Design Solution (Part 2)
Joe Graziano – Challenge 2 Design Solution (Part 2)
 
Project Risk Management Plan © 2015 by Jones & Bartl.docx
 Project Risk Management Plan © 2015 by Jones & Bartl.docx Project Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docx
 
Project Risk Management Plan © 2015 by Jones & Bartl.docx
 Project Risk Management Plan © 2015 by Jones & Bartl.docx Project Risk Management Plan © 2015 by Jones & Bartl.docx
Project Risk Management Plan © 2015 by Jones & Bartl.docx
 
Cap markets news sep2002
Cap markets news sep2002Cap markets news sep2002
Cap markets news sep2002
 

More from vishvasyadav45

Cmmaao pmi-resume template-18-cmmaao-pmi
Cmmaao pmi-resume template-18-cmmaao-pmiCmmaao pmi-resume template-18-cmmaao-pmi
Cmmaao pmi-resume template-18-cmmaao-pmi
vishvasyadav45
 
Cmmaao pmi-resume template-15
Cmmaao pmi-resume template-15Cmmaao pmi-resume template-15
Cmmaao pmi-resume template-15
vishvasyadav45
 
Cmmaao pmi-resume template-16
Cmmaao pmi-resume template-16Cmmaao pmi-resume template-16
Cmmaao pmi-resume template-16
vishvasyadav45
 
Cmmaao pmi-resume template-17
Cmmaao pmi-resume template-17Cmmaao pmi-resume template-17
Cmmaao pmi-resume template-17
vishvasyadav45
 
Cmmaao pmi-resume template-17
Cmmaao pmi-resume template-17Cmmaao pmi-resume template-17
Cmmaao pmi-resume template-17
vishvasyadav45
 
Cmmaao pmi-resume template-18
Cmmaao pmi-resume template-18Cmmaao pmi-resume template-18
Cmmaao pmi-resume template-18
vishvasyadav45
 
Cmmaao pmi-resume template-19
Cmmaao pmi-resume template-19Cmmaao pmi-resume template-19
Cmmaao pmi-resume template-19
vishvasyadav45
 
Cmmaao pmi-resume template-13
Cmmaao pmi-resume template-13Cmmaao pmi-resume template-13
Cmmaao pmi-resume template-13
vishvasyadav45
 
Cmmaao pmi-resume template-12
Cmmaao pmi-resume template-12Cmmaao pmi-resume template-12
Cmmaao pmi-resume template-12
vishvasyadav45
 
Cmmaao pmi-resume template-11
Cmmaao pmi-resume template-11Cmmaao pmi-resume template-11
Cmmaao pmi-resume template-11
vishvasyadav45
 
Cmmaao pmi-resume template-10
Cmmaao pmi-resume template-10Cmmaao pmi-resume template-10
Cmmaao pmi-resume template-10
vishvasyadav45
 
Cmmaao pmi-resume template-9
Cmmaao pmi-resume template-9Cmmaao pmi-resume template-9
Cmmaao pmi-resume template-9
vishvasyadav45
 
Cmmaao pmi-resume template-8
Cmmaao pmi-resume template-8Cmmaao pmi-resume template-8
Cmmaao pmi-resume template-8
vishvasyadav45
 
Cmmaao pmi-resume template-7
Cmmaao pmi-resume template-7Cmmaao pmi-resume template-7
Cmmaao pmi-resume template-7
vishvasyadav45
 
Cmmaao pmi-resume template-6
Cmmaao pmi-resume template-6Cmmaao pmi-resume template-6
Cmmaao pmi-resume template-6
vishvasyadav45
 
Cmmaao pmi-resume template-5
Cmmaao pmi-resume template-5Cmmaao pmi-resume template-5
Cmmaao pmi-resume template-5
vishvasyadav45
 
Cmmaao pmi-resume template-4
Cmmaao pmi-resume template-4Cmmaao pmi-resume template-4
Cmmaao pmi-resume template-4
vishvasyadav45
 
Cmmaao pmi-resume template-3
Cmmaao pmi-resume template-3Cmmaao pmi-resume template-3
Cmmaao pmi-resume template-3
vishvasyadav45
 
Cmmaao pmi-resume template-2
Cmmaao pmi-resume template-2Cmmaao pmi-resume template-2
Cmmaao pmi-resume template-2
vishvasyadav45
 
Vishvas resume template-18-cmmaao-pmi
Vishvas resume template-18-cmmaao-pmiVishvas resume template-18-cmmaao-pmi
Vishvas resume template-18-cmmaao-pmi
vishvasyadav45
 

More from vishvasyadav45 (20)

Cmmaao pmi-resume template-18-cmmaao-pmi
Cmmaao pmi-resume template-18-cmmaao-pmiCmmaao pmi-resume template-18-cmmaao-pmi
Cmmaao pmi-resume template-18-cmmaao-pmi
 
Cmmaao pmi-resume template-15
Cmmaao pmi-resume template-15Cmmaao pmi-resume template-15
Cmmaao pmi-resume template-15
 
Cmmaao pmi-resume template-16
Cmmaao pmi-resume template-16Cmmaao pmi-resume template-16
Cmmaao pmi-resume template-16
 
Cmmaao pmi-resume template-17
Cmmaao pmi-resume template-17Cmmaao pmi-resume template-17
Cmmaao pmi-resume template-17
 
Cmmaao pmi-resume template-17
Cmmaao pmi-resume template-17Cmmaao pmi-resume template-17
Cmmaao pmi-resume template-17
 
Cmmaao pmi-resume template-18
Cmmaao pmi-resume template-18Cmmaao pmi-resume template-18
Cmmaao pmi-resume template-18
 
Cmmaao pmi-resume template-19
Cmmaao pmi-resume template-19Cmmaao pmi-resume template-19
Cmmaao pmi-resume template-19
 
Cmmaao pmi-resume template-13
Cmmaao pmi-resume template-13Cmmaao pmi-resume template-13
Cmmaao pmi-resume template-13
 
Cmmaao pmi-resume template-12
Cmmaao pmi-resume template-12Cmmaao pmi-resume template-12
Cmmaao pmi-resume template-12
 
Cmmaao pmi-resume template-11
Cmmaao pmi-resume template-11Cmmaao pmi-resume template-11
Cmmaao pmi-resume template-11
 
Cmmaao pmi-resume template-10
Cmmaao pmi-resume template-10Cmmaao pmi-resume template-10
Cmmaao pmi-resume template-10
 
Cmmaao pmi-resume template-9
Cmmaao pmi-resume template-9Cmmaao pmi-resume template-9
Cmmaao pmi-resume template-9
 
Cmmaao pmi-resume template-8
Cmmaao pmi-resume template-8Cmmaao pmi-resume template-8
Cmmaao pmi-resume template-8
 
Cmmaao pmi-resume template-7
Cmmaao pmi-resume template-7Cmmaao pmi-resume template-7
Cmmaao pmi-resume template-7
 
Cmmaao pmi-resume template-6
Cmmaao pmi-resume template-6Cmmaao pmi-resume template-6
Cmmaao pmi-resume template-6
 
Cmmaao pmi-resume template-5
Cmmaao pmi-resume template-5Cmmaao pmi-resume template-5
Cmmaao pmi-resume template-5
 
Cmmaao pmi-resume template-4
Cmmaao pmi-resume template-4Cmmaao pmi-resume template-4
Cmmaao pmi-resume template-4
 
Cmmaao pmi-resume template-3
Cmmaao pmi-resume template-3Cmmaao pmi-resume template-3
Cmmaao pmi-resume template-3
 
Cmmaao pmi-resume template-2
Cmmaao pmi-resume template-2Cmmaao pmi-resume template-2
Cmmaao pmi-resume template-2
 
Vishvas resume template-18-cmmaao-pmi
Vishvas resume template-18-cmmaao-pmiVishvas resume template-18-cmmaao-pmi
Vishvas resume template-18-cmmaao-pmi
 

Recently uploaded

QATAR Pills for Abortion -+971*55*85*39*980-in Dubai. Abu Dhabi.
QATAR Pills for Abortion -+971*55*85*39*980-in Dubai. Abu Dhabi.QATAR Pills for Abortion -+971*55*85*39*980-in Dubai. Abu Dhabi.
QATAR Pills for Abortion -+971*55*85*39*980-in Dubai. Abu Dhabi.
hyt3577
 
+97470301568>>buy weed in qatar,buy thc oil in qatar doha>>buy cannabis oil i...
+97470301568>>buy weed in qatar,buy thc oil in qatar doha>>buy cannabis oil i...+97470301568>>buy weed in qatar,buy thc oil in qatar doha>>buy cannabis oil i...
+97470301568>>buy weed in qatar,buy thc oil in qatar doha>>buy cannabis oil i...
Health
 
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnLaw of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
TintoTom3
 

Recently uploaded (20)

QATAR Pills for Abortion -+971*55*85*39*980-in Dubai. Abu Dhabi.
QATAR Pills for Abortion -+971*55*85*39*980-in Dubai. Abu Dhabi.QATAR Pills for Abortion -+971*55*85*39*980-in Dubai. Abu Dhabi.
QATAR Pills for Abortion -+971*55*85*39*980-in Dubai. Abu Dhabi.
 
Lion One Corporate Presentation May 2024
Lion One Corporate Presentation May 2024Lion One Corporate Presentation May 2024
Lion One Corporate Presentation May 2024
 
Toronto dominion bank investor presentation.pdf
Toronto dominion bank investor presentation.pdfToronto dominion bank investor presentation.pdf
Toronto dominion bank investor presentation.pdf
 
7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator Options7 tips trading Deriv Accumulator Options
7 tips trading Deriv Accumulator Options
 
cost-volume-profit analysis.ppt(managerial accounting).pptx
cost-volume-profit analysis.ppt(managerial accounting).pptxcost-volume-profit analysis.ppt(managerial accounting).pptx
cost-volume-profit analysis.ppt(managerial accounting).pptx
 
+97470301568>>buy weed in qatar,buy thc oil in qatar doha>>buy cannabis oil i...
+97470301568>>buy weed in qatar,buy thc oil in qatar doha>>buy cannabis oil i...+97470301568>>buy weed in qatar,buy thc oil in qatar doha>>buy cannabis oil i...
+97470301568>>buy weed in qatar,buy thc oil in qatar doha>>buy cannabis oil i...
 
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
20240419-SMC-submission-Annual-Superannuation-Performance-Test-–-design-optio...
 
Female Escorts Service in Hyderabad Starting with 5000/- for Savita Escorts S...
Female Escorts Service in Hyderabad Starting with 5000/- for Savita Escorts S...Female Escorts Service in Hyderabad Starting with 5000/- for Savita Escorts S...
Female Escorts Service in Hyderabad Starting with 5000/- for Savita Escorts S...
 
NO1 Verified Online Love Vashikaran Specialist Kala Jadu Expert Specialist In...
NO1 Verified Online Love Vashikaran Specialist Kala Jadu Expert Specialist In...NO1 Verified Online Love Vashikaran Specialist Kala Jadu Expert Specialist In...
NO1 Verified Online Love Vashikaran Specialist Kala Jadu Expert Specialist In...
 
Bhubaneswar🌹Ravi Tailkes ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswar ...
Bhubaneswar🌹Ravi Tailkes  ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswar ...Bhubaneswar🌹Ravi Tailkes  ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswar ...
Bhubaneswar🌹Ravi Tailkes ❤CALL GIRLS 9777949614 💟 CALL GIRLS IN bhubaneswar ...
 
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & RequirementsExplore Dual Citizenship in Africa | Citizenship Benefits & Requirements
Explore Dual Citizenship in Africa | Citizenship Benefits & Requirements
 
Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...
Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...
Certified Kala Jadu, Black magic specialist in Rawalpindi and Bangali Amil ba...
 
Black magic specialist in Canada (Kala ilam specialist in UK) Bangali Amil ba...
Black magic specialist in Canada (Kala ilam specialist in UK) Bangali Amil ba...Black magic specialist in Canada (Kala ilam specialist in UK) Bangali Amil ba...
Black magic specialist in Canada (Kala ilam specialist in UK) Bangali Amil ba...
 
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnLaw of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
Law of Demand.pptxnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnnn
 
Strategic Resources May 2024 Corporate Presentation
Strategic Resources May 2024 Corporate PresentationStrategic Resources May 2024 Corporate Presentation
Strategic Resources May 2024 Corporate Presentation
 
Collecting banker, Capacity of collecting Banker, conditions under section 13...
Collecting banker, Capacity of collecting Banker, conditions under section 13...Collecting banker, Capacity of collecting Banker, conditions under section 13...
Collecting banker, Capacity of collecting Banker, conditions under section 13...
 
Stock Market Brief Deck (Under Pressure).pdf
Stock Market Brief Deck (Under Pressure).pdfStock Market Brief Deck (Under Pressure).pdf
Stock Market Brief Deck (Under Pressure).pdf
 
Business Principles, Tools, and Techniques in Participating in Various Types...
Business Principles, Tools, and Techniques  in Participating in Various Types...Business Principles, Tools, and Techniques  in Participating in Various Types...
Business Principles, Tools, and Techniques in Participating in Various Types...
 
Group 8 - Goldman Sachs & 1MDB Case Studies
Group 8 - Goldman Sachs & 1MDB Case StudiesGroup 8 - Goldman Sachs & 1MDB Case Studies
Group 8 - Goldman Sachs & 1MDB Case Studies
 
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot GirlsMahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
Mahendragarh Escorts 🥰 8617370543 Call Girls Offer VIP Hot Girls
 

Process implementation for project risk management

  • 1.
  • 2.
  • 3.
  • 4.  During the construction of the spectacular Oresund bridge and tunnel, which connects Sweden to Denmark, risk analysis showed that the project was unlikely to meet its planned opening date upon which its financial viability was calculated. Mitigating actions and alternative scenarios were considered leading to significant changes in approach. After the mitigating actions were applied, the risk analysis showed high confidence that Oresund could be opened three months early - which it was. Early opening easily paid for the specialist risk management work.
  • 5.  A European retail and wholesale bank replaced its core operational systems following their "Rapid Implementation Plan" (RIP). Their previous systems were obsolete and inadequate. As they needed the space for the new hardware when it was ready, they physically removed and scrapped the old hardware to switch over immediately to the new system.
  • 6.  Very soon, major problems were found with the new system. It did not correctly calculate interest and consequently was misstating customers' balances. Very large amounts of money were vanishing in the accounts. There was no possibility of reverting to the previous system.
  • 7.  Our review identified the problems and external teams were brought in to fix the system and to correct the accounts. The one thing we could not fix was their reputation. The bank was no longer a viable profit-making entity, but, thanks to our work, it was able to cease retail trading in an orderly fashion.
  • 8.  A global telecoms service provider had built new customer and billing systems. To save time and cost, no one had bothered to document the system. Some time later they realized that this was causing operational difficulties in running the system.
  • 9.  Our work was to retro-document the systems. As no one knew any of the detail we did this by examining the code and deciphering what it did. One element of the billing algorithm was particularly strange. When we explained it to the Finance Director he said "no it can't work like that - if it did we'd be bankrupt". It did, they were.
  • 10. Identify Risk Analyze Probability and Impact Apply avoidance or Reduction Define Contingency Plans Monitor and Manage
  • 11. Realistic risks should be identified. Capture the information electronically in a risk register. Following things should be noted:  Description of the risk.  Probability of the risk occurrence.  Description of the potential impact of the risk  Likely cost to the project or organization if that risk occurs  What actions should be taken now and by Whom  What contingency plans should be formulated now so that the organization is ready to act if the risk occurs.
  • 12. Team members should be motivated to list the potential risk items .
  • 13. List of the potential risk items should be compile into single list with duplicates removed .
  • 14. Break the master list in small parts and each part of list should be used to identify the triggers (warning signs) for project risks.
  • 15. Calculate the probability and the impact of each item on the master list.
  • 16. Identify possible preventive actions for the threats.
  • 17. Create a contingency plan for all project risks a plan that includes the actions one would take if a trigger or a risk were to occur.
  • 18. Determine the owner of each risk on the list.
  • 19.  The owner is the person who is responsible for watching out for triggers and then for responding appropriately if the triggers do in fact occur by implementing the pre-approved and now established contingency plan.
  • 20. For quick implementation and any clarification please contact : - Vishvas Yadav Senior Manager/ Business Analyst Codoca Mtvcola Marketing Advertising And Outsourcing Pvt. Ltd. Mail id : info@codocamtvcola.co.in Mobile: 08884782639