SlideShare a Scribd company logo
1 of 103
Course no.: CE 416
Course title: Pre-stressed
concrete lab
Course Teacher: Munshi Galib
Muktadir
Group-02
10.01.03.123 Raktim Barua
10.01.03.124 Sabrina Shahrin
10.01.03.125 Toufiq Rifath
10.01.03.126 Touhiduzzaman Bizoy
10.01.03.127 Tameem Samdanee
10.01.03.128 Kaji Riyadh Al Saif Ahmed
10.01.03.129 Tanni Sarker
10.01.03.130 Juwairiyah Ishrat Jahan
Loss of pre-
stress
• Notations(symbols)
• Introduction to the losses(names and
classifications);
• Brief description of losses;
• Calculations;
• Diagrams.
•Geometric properties
•Load variables
The commonly used geometric properties of a prestressed member are defined as
follows.
Ac = Area of concrete section
= Net cross-sectional area of concrete excluding the area of prestressing steel.
Ap = Area of prestressing steel
Total cross-sectional area of the tendons
A = Area of prestressed member
= Gross cross-sectional area of prestressed member
= Ac + Ap
At = Transformed area of prestressed member
= Area of the member when steel is substituted by an equivalent area of
concrete.
= Ac + mAp
= A + (m – 1)Ap
Here,
m = the modular ratio = Ep/Ec
Ec = short-term elastic modulus of concrete
Ep = elastic modulus of steel.
The following figure shows the commonly used areas of the prestressed
members.
Figure 2-1.1 Areas for prestressed members
CGC = Centroid of concrete
= Centroid of the gross section. The CGC may lie outside the
concrete
CGS = Centroid of prestressing steel
= Centroid of the tendons. The CGS may lie outside the tendons or
the concrete
I = Moment of inertia of prestressed member
= Second moment of area of the gross section about the CGC.
It = Moment of inertia of transformed section
= Second moment of area of the transformed section about the
centroid of the transformed section.
e = Eccentricity of CGS with respect to CGC
= Vertical distance between CGC and CGS. If CGS lies below CGC,
e will be considered positive and vice versa
Figure: CGC, CGS and eccentricity of typical prestressed
members
Pi = Initial prestressing force
= The force which is applied to the tendons by the jack.
P0 = Prestressing force after immediate losses
= The reduced value of prestressing force after elastic
shortening, anchorage slip and loss due to friction.
Pe = Effective prestressing force after time-dependent losses
= The final value of prestressing force after the occurrence of
creep, shrinkage and relaxation.
Introduction
• In pre-stressed concrete applications, most important
variable is the pre-stressing force. In the earlier days, it
was observed that the pre-stressing force does not stay
constant.
• Even during pre-stressing of the tendons and the transfer
of pre-stress to the concrete members, there is a drop of
the pre-stressing force from the recorded value in the jack
gauge. The various reductions of the pre-stressing force
are termed as the losses in pre-stress.
 In pre – tensioning system, the high- strength steel
tendons are pulled between two end abutments (also
called bulkheads) prior to the casting of concrete. The
abutments are fixed at the end pre stressing bed.
 Once the concrete attains the desires strength for
prestressing, the tendon are cut loose from the
abutments. The pre stress is transferred to the concrete
from the tendons, due the bond between them.
 During the transfer of pre stress, the member undergoes
elastic shortening. If the tendons are located
eccentrically, the member is likely to bend and deflect
(camber).
 Post-tensioning is a method of reinforcing
(strengthening) concrete or other materials with
high-strength steel strands or bars, typically
referred to as tendons
 Post-tensioning applications include office and
apartment buildings, parking structures, slabs-on-
ground, bridges, sports stadiums, rock and soil
anchors, and water-tanks
Type of Loss
Pre-
tensioning
Post-tensioning
1. Elastic
Shortening
Yes
i. No, if all the cables are
simultaneously
tensioned.
ii. If the wires are
tensioned in stages
loss will exist.
2. Anchorage Slip No Yes
3. Friction Loss No Yes
4.Creep and
Shrinkage of
Concrete
Yes Yes
5. Relaxation of
Steel
Yes Yes
• Pre-tensioned axial members
• Pre-tensioned bending
members
• Post-tensioned axial members
• Post-tensioned bending
members.
• When the members are cut and the pre-stressing force is
transferred to the member, the concrete undergoes
immediate shortening due to the pre-stress. The tendon
also shortens by the same amount, which leads to the
loss of pre-stress.
Pre-tensioned Members:
The following figure will explain the operation of pre-
tensioning through various stages by animation
Fig: Pre-tensioning of a member
Prestressing bed
• If there is only one tendon, there is no loss because the
applied pre-stress is recorded after the elastic shortening
of the member. For more than one tendon, if the tendons
are stretched sequentially, there is loss in a tendon during
subsequent stretching of the other tendons.
Casting bed
Duct
jackAnchorage
Fig: Post-tensioning of a member
Post-tensioned Members:
The following figure will explain the complete
operation of post-tensioning through various stages
by animation.
Elastic Shortening:
• Loss due to elastic shortening is quantified by the drop in
prestress (∆fp) in a tendon due to change in strain in tendon
(∆εp).
• It is assumed that the change in strain in tendon is equal to
strain in concrete (εc) at the level of tendon due to prestressing
force, which is called strain compatibility between concrete and
steel.
• Strain in concrete at the level of tendon is calculated from the
stress in concrete (fc) at the same level due to the prestressing
force.
• A linear elastic relationship is used to calculate the strain from
the stress.
The quantification of the losses is explained below:
∆fp = Ep ∆εp
= Ep εc
=Ep (fc / Ec )
• For simplicity, the loss in all the tendons can be
calculated based on the stress in concrete at the level of
CGS.
• This simplification cannot be used when tendons are
stretched sequentially in a post-tensioned member.
∆fp = m fc
Pre-tensioned Axial Members
Original length of member at transfer of prestress
Length after elastic shortening
Pi
P0
Fig:Elastic shortening of a pre-tensioned axial member
Pre-tensioned Axial Members:
∆fp = m fc
=m(P0/Ac)
∆fp =m(Pi/At) ≈ m(Pi/A)
 The stress in concrete (P0/Ac) can be equated to the
stress in the transformed section due to the initial pre-
stress (Pi/At) .
 The transformed area At of the pre-stressed member can
be approximated to the gross area A.
Pre-tensioned Axial Members
Pi
P0
Length of tendon before stretching
εpi
εp0 εc
Fig: Elastic shortening of a pre-tensioned axial
member
• The strain in concrete due to elastic shortening (εc) is the
difference between the initial strain in steel (εpi) and the
residual strain in steel (εpo).
εc= εpi – εpo
 The strains can be expressed in terms of the pre-stressing
forces as follows:
εc =(P0/AcEc)
εpi =(Pi/ApEp)
εpo=(Po/ApEp)
Thus, the stress in concrete due to the prestressing
force after immediate losses (Po/Ac) can be equated to
the stress in the transformed section due to the initial
prestress (P /A ).
• A prestressed concrete sleeper produced by pre-
tensioning method has a rectangular cross-section of
300mm × 250 mm (b × h). It is prestressed with 9
numbers of straight 7mm diameter wires at 0.8 times
the ultimate strength of 1570 N/mm2. Estimate the
percentage loss of stress due to elastic shortening of
concrete. Consider m = 6.
Pre-tensioned Bending Members:
Fig: Elastic shortening of a pre-tensioned bending
member
Due to the effect of self-weight, the stress in concrete
varies along length (previous figure). The loss can be
calculated by Eqn. (∆fp = m fc ) with a suitable
evaluation of the stress in concrete. To have a
conservative estimate of the loss, the maximum stress
at the level of CGS at the mid-span is considered.
M=moment at mid-span due to self weight.
Precise result of A & I is not computationally
warranted. In the above expression the eccentricity of
C.G.S (e) was assumed to be constant.
• Post-tensioned Axial Members:
For more than one tendon, if the tendons are stretched
sequentially, there is loss in a tendon during subsequent
stretching of the other tendons. The loss in each tendon can be
calculated in progressive sequence. Else,an approximation can
be used to calculate the losses.
The loss in the first tendon is evaluated precisely and half of that
value is used as an average loss for all the tendons.
• Post-tensioned Bending Members :
The calculation of loss for tendons stretched sequentially, is
similar to post-tensioned axial members. For curved profiles, the
eccentricity of the CGS and hence, the stress in concrete at the
level of CGS vary along the length. An average stress in
concrete can be considered.
For a parabolic tendon, the average stress (fc,avg) is given by the
following equation.
fc1 = stress in concrete at the end of the member
fc2 = stress in concrete at the mid-span of the member.
• The friction generated at the interface of concrete and
steel during the stretching of a curved tendon in a post-
tensioned member, leads to a drop in the pre-stress
along the member from the stretching end.
• The loss due to friction does not occur in pre-tensioned
members because there is no concrete during the
stretching of the tendons.
Friction
• In addition to friction, the stretching has to
overcome the wobble of the tendon. The wobble
refers to the change in position of the tendon
along the duct. The losses due to friction and
wobble are grouped together under friction.
Friction
Figure :Force acting in a tendon of infinitesimal length
• The derivation of the expression of P is based on a circular
profile. Although a cable profile is parabolic based on the
bending moment diagram, the error induced is
insignificant.
• The friction is proportional to the following variables.
(a) Coefficient of friction (μ) between concrete and
steel.
(b)The resultant of the vertical reaction from the
concrete on the tendon (N) generated due to curvature.
From the equilibrium of forces in the force triangle, N is
given as follows.
The friction over the length dx is equal to μN = μPdα.
• The wobble in the tendon is effected by the following variables.
• Rigidity of sheathing
• Diameter of sheathing
• Spacing of sheath supports
• Type of tendon
• Type of construction
• For a tendon of length dx, the friction due to wobble is
expressed as kPdx, where k is the wobble coefficient or
coefficient for wave effect.
• Based on the equilibrium of forces in the tendon for the
horizontal direction, the following equation can be written.
P = P + dP + (μPdα + kPdx)
or, dP = – (μPdα + kPdx)
Thus, the total drop in pre-stress (dP) over length dx is equal to
–(μPdα + kPdx). The above differential equation can be solved
to express P in terms of x.
• Here,
Po = the pre-stress at the stretching end after any loss due
to elastic shortening.
For small values of μα + kx, the above expression can be
simplified by the Taylor series expansion.
Px = Po (1– μα – kx)
Thus, for a tendon with single curvature, the variation of the
pre-stressing force is linear with the distance from the
stretching end.
• The following figure shows the variation of pre-stressing force
after stretching. The left side is the stretching end and the right
side is the anchored end.
Figure: Variation of pre-stressing force after
stretching
Table: Friction co-efficient for post-tensioning tendons
*Reference from: Design of pre-stressed concrete structures by
T.Y.LIN,NED H. Burns
Example
• In a post-tensioned member, when the pre-stress is
transferred to the concrete, the wedges slip through a
little distance before they get properly seated in the
conical space.
• The anchorage block also moves before it settles on the
concrete. There is loss of pre-stress due to the
consequent reduction in the length of the tendon.
• The total anchorage slip depends on the type of
anchorage system. In absence of manufacturer’s data, the
following typical values for some systems can be used.
Anchorage System Anchorage Slip
(Δs)
Freyssinet system
12 - 5mm Φ strands
12 - 8mm Φ strands
4 mm
6 mm
Magnel system 8 mm
Dywidag system 1 mm
Anchorage Slip
• Due to the setting of the anchorage block, as the tendon shortens,
there is a reverse friction. Hence, the effect of anchorage slip is
present up to a certain length (figure below)). Beyond this setting
length, the effect is absent. This length is denoted as lset.
Figure :Variation of pre-stressing force after anchorage slip.
Anchorage Slip
• The magnitude of the prestressing force varies along the length of a post-
tensioned member due to friction losses and setting of the anchorage block.
The diagram representing the variation of prestressing force is called the
force variation diagram.
Considering the effect of friction, the magnitude of the pre-stressing force at a
distance x from the stretching end is given as follows.
Px = Poe-nx
Here, ηx = μα + kx denotes the total effect of friction and wobble. The plot of
Px gives the force variation diagram.
The initial part of the force variation diagram, up to length lset is influenced by
the setting of the anchorage block. Let the drop in the pre-stressing force at
the stretching end be ΔP. The determination of ΔP and lset are necessary to
plot the force variation diagram including the effect of the setting of the
anchorage block.
Force Variation
Diagram
• Considering the drop in the prestressing force and the effect of
reverse friction, the magnitude of the prestressing force at a
distance x from the stretching end is given as follows.
P’
x=(Po- ΔP) en’x
Here, η’ for reverse friction is analogous to η for friction and
wobble.
Force Variation
Diagram
Figure :Force variation diagrams for stretching in
stages
The force variation diagrams for the various stages are
explained:
• a) The initial tension at the right end is high to compensate
for the anchorage slip. It corresponds to about 0.8 fpk initial
prestress. The force variation diagram (FVD) is linear.
• b) After the anchorage slip, the FVD drops near the right
end till the length lset.
• c) The initial tension at the left end also corresponds to
about 0.8 fpk initial prestress. The FVD is linear up to the
centre line of the beam.
• d) After the anchorage slip, the FVD drops near the left
end till the length lset.
• It is observed that after two stages, the variation of the
prestressing force over the length of the beam is less than
after the first stage
• For stress in concrete less than one-third of the
characteristic strength, the ultimate creep strain (εcr,ult) is
found to be proportional to the elastic strain (εel). The
ratio of the ultimate creep strain to the elastic strain is
defined as the ultimate creep coefficient or simply creep
coefficient θ. The ultimate creep strain is then given as
follows.
εcr,ult = θ εel
• IS:1343 - 1980 gives guidelines to estimate
the ultimate creep strain in Section 5.2.5. It
is a simplified estimate where only one
factor has been considered. The factor is
age of loading of the prestressed concrete
structure. The creep coefficient θ is
provided for three values of age of loading.
• The loss in prestress (Δfp ) due to creep is given as
follows.
Here, Ep is the modulus of the prestressing steel.
Δfp = Ep
εcr,ult
The following considerations are applicable for calculating
the loss of pre-stress due to creep:
• The creep is due to sustained load only.
• Since the pre-stress may vary along the length of the
member, an average value of the pre-stress may be
considered.
• The pre-stress changes due to creep and the creep is
related to the instantaneous pre-stress. To consider the
interaction, the calculation of creep can be iterated over
small time steps.
The shrinkage of concrete is defined as
the contraction due to loss of moisture.
Due to the shrinkage of concrete, the
prestress in the tendon is reduced with
time.
Relaxation of
Steel
• Relaxation of steel is defined as the decrease in
stress with time under constant strain. Due to the
relaxation of steel, the prestress in the tendon is
reduced with time.
• The relaxation depends on the type of steel,
initial prestress (fpi) and the temperature.
• The losses of prestress due to creep and shrinkage of
concrete and the relaxation of the steel are all time-
dependent and inter-related to each other. If the losses are
calculated separately and added, the calculated total time-
dependent loss is over-estimated. To consider the inter-
relationship of the cause and effect, the calculation can be
done for discrete time steps. The results at the end of each
time step are used for the next time step.
• This step-by-step procedure was suggested by the Precast
/ Prestressed Concrete Institute (PCI) committee and is
called the General method
Losses in prestress
Losses in prestress
Losses in prestress

More Related Content

What's hot

Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
Ankit Singh
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing Method
Md Tanvir Alam
 
Advantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concreteAdvantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concrete
Baruti Balinda Jonathan
 

What's hot (20)

Design of columns biaxial bending as per IS 456-2000
Design of columns  biaxial bending as per IS 456-2000Design of columns  biaxial bending as per IS 456-2000
Design of columns biaxial bending as per IS 456-2000
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Lec.3 working stress 1
Lec.3   working stress 1Lec.3   working stress 1
Lec.3 working stress 1
 
Singly reinforced beam design
Singly reinforced beam   designSingly reinforced beam   design
Singly reinforced beam design
 
Structural analysis 1
Structural analysis   1Structural analysis   1
Structural analysis 1
 
Static Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic IndeterminacyStatic Indeterminacy and Kinematic Indeterminacy
Static Indeterminacy and Kinematic Indeterminacy
 
Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete Loss of pre stress in pre-stressed concrete
Loss of pre stress in pre-stressed concrete
 
Design of slender columns as per IS 456-2000
Design of slender columns as per IS 456-2000Design of slender columns as per IS 456-2000
Design of slender columns as per IS 456-2000
 
Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)
Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)
Design Procedure of Singly,Doubly & T-Beam(As Per ACI code)
 
7 losses in prestress
7 losses in prestress7 losses in prestress
7 losses in prestress
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
 
Cable Layout, Continuous Beam & Load Balancing Method
 Cable Layout, Continuous Beam & Load Balancing Method Cable Layout, Continuous Beam & Load Balancing Method
Cable Layout, Continuous Beam & Load Balancing Method
 
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
Lec06 Analysis and Design of T Beams (Reinforced Concrete Design I & Prof. Ab...
 
Fundamentals of structural analysis
Fundamentals of structural analysisFundamentals of structural analysis
Fundamentals of structural analysis
 
consistent deformation
consistent deformationconsistent deformation
consistent deformation
 
crack control and crack width estimation
crack control and crack width estimationcrack control and crack width estimation
crack control and crack width estimation
 
Advantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concreteAdvantages and disadvantages of Prestressed concrete
Advantages and disadvantages of Prestressed concrete
 
Design of torsion reinforcement
 Design of torsion reinforcement Design of torsion reinforcement
Design of torsion reinforcement
 
IS 456 2000 summary
IS 456 2000 summary IS 456 2000 summary
IS 456 2000 summary
 
Prestressed concrete continuous beam
Prestressed concrete continuous beamPrestressed concrete continuous beam
Prestressed concrete continuous beam
 

Viewers also liked

Prestressed concrete baru
Prestressed concrete baruPrestressed concrete baru
Prestressed concrete baru
Kartina Sazali
 
A comparative study of static and response spectrum analysis of a rc building
A comparative study of static and response spectrum analysis of a rc buildingA comparative study of static and response spectrum analysis of a rc building
A comparative study of static and response spectrum analysis of a rc building
Tameem Samdanee
 
Elastic response spectra
Elastic response spectra Elastic response spectra
Elastic response spectra
Alban KURIQI
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
9833356555
 
W.h.mosley, j.h.bungey. reinforced concrete design book
W.h.mosley, j.h.bungey. reinforced concrete design bookW.h.mosley, j.h.bungey. reinforced concrete design book
W.h.mosley, j.h.bungey. reinforced concrete design book
Reyam AL Mousawi
 

Viewers also liked (20)

Prestress loss
Prestress lossPrestress loss
Prestress loss
 
Prestress loss due to friction & anchorage take up
Prestress loss due to friction & anchorage take upPrestress loss due to friction & anchorage take up
Prestress loss due to friction & anchorage take up
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
prestressed concrete
prestressed concreteprestressed concrete
prestressed concrete
 
Prestressed concrete baru
Prestressed concrete baruPrestressed concrete baru
Prestressed concrete baru
 
A comparative study of static and response spectrum analysis of a rc building
A comparative study of static and response spectrum analysis of a rc buildingA comparative study of static and response spectrum analysis of a rc building
A comparative study of static and response spectrum analysis of a rc building
 
It project
It projectIt project
It project
 
02 chapter: Earthquake: Strong Motion and Estimation of Seismic Hazard
02 chapter: Earthquake: Strong Motion and Estimation of Seismic Hazard02 chapter: Earthquake: Strong Motion and Estimation of Seismic Hazard
02 chapter: Earthquake: Strong Motion and Estimation of Seismic Hazard
 
Post-Tensioning Developments in Texas
Post-Tensioning Developments in TexasPost-Tensioning Developments in Texas
Post-Tensioning Developments in Texas
 
55013585 structural
55013585 structural55013585 structural
55013585 structural
 
Response spectrum
Response spectrumResponse spectrum
Response spectrum
 
Response spectrum method
Response spectrum methodResponse spectrum method
Response spectrum method
 
PT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGSPT STRUCTURES IN BUILDINGS
PT STRUCTURES IN BUILDINGS
 
Post-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for ContractorsPost-Tension Concrete - Info session for Contractors
Post-Tension Concrete - Info session for Contractors
 
Elastic response spectra
Elastic response spectra Elastic response spectra
Elastic response spectra
 
post tensioning slabs
post tensioning slabspost tensioning slabs
post tensioning slabs
 
Response Spectrum
Response SpectrumResponse Spectrum
Response Spectrum
 
Introduction to prestressed concrete
Introduction to prestressed concreteIntroduction to prestressed concrete
Introduction to prestressed concrete
 
W.h.mosley, j.h.bungey. reinforced concrete design book
W.h.mosley, j.h.bungey. reinforced concrete design bookW.h.mosley, j.h.bungey. reinforced concrete design book
W.h.mosley, j.h.bungey. reinforced concrete design book
 
Concrete
ConcreteConcrete
Concrete
 

Similar to Losses in prestress

Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
vijayvijay327286
 
10.01.03.043
10.01.03.04310.01.03.043
10.01.03.043
Muurad
 

Similar to Losses in prestress (20)

Losses in prestress [autosaved]
Losses in prestress [autosaved]Losses in prestress [autosaved]
Losses in prestress [autosaved]
 
PSC Design and construction.ppt
PSC Design and construction.pptPSC Design and construction.ppt
PSC Design and construction.ppt
 
Chapter 1
Chapter 1Chapter 1
Chapter 1
 
L01_Unit Info & Design Revision(2).pdf
L01_Unit Info & Design Revision(2).pdfL01_Unit Info & Design Revision(2).pdf
L01_Unit Info & Design Revision(2).pdf
 
1presetrssed_concrete.ppt
1presetrssed_concrete.ppt1presetrssed_concrete.ppt
1presetrssed_concrete.ppt
 
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdfDeflections in PT elements pt structure for all pt slabs in civil industry.pdf
Deflections in PT elements pt structure for all pt slabs in civil industry.pdf
 
2-Flexural Analysis and Design of Beams.pdf
2-Flexural Analysis and Design of Beams.pdf2-Flexural Analysis and Design of Beams.pdf
2-Flexural Analysis and Design of Beams.pdf
 
3-Flexural Analysis prestress concrete ppt
3-Flexural Analysis prestress concrete ppt3-Flexural Analysis prestress concrete ppt
3-Flexural Analysis prestress concrete ppt
 
PreStress.pptx
PreStress.pptxPreStress.pptx
PreStress.pptx
 
10.01.03.043
10.01.03.04310.01.03.043
10.01.03.043
 
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
Lec03 Flexural Behavior of RC Beams (Reinforced Concrete Design I & Prof. Abd...
 
Conceps of RCC-PCC.pptx
Conceps of RCC-PCC.pptxConceps of RCC-PCC.pptx
Conceps of RCC-PCC.pptx
 
Lec 5-flexural analysis and design of beamns
Lec 5-flexural analysis and design of beamnsLec 5-flexural analysis and design of beamns
Lec 5-flexural analysis and design of beamns
 
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONSANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
ANALYSIS & DESIGN ASPECTS OF PRE-STRESSED MEMBERS USING F.R.P. TENDONS
 
Lec 5-flexural analysis and design of beamns
Lec 5-flexural analysis and design of beamnsLec 5-flexural analysis and design of beamns
Lec 5-flexural analysis and design of beamns
 
Lec 5
Lec 5Lec 5
Lec 5
 
LOSSES OF PRESTRESS (Immediate and Time dependant)-DCS-II.ppt
LOSSES OF PRESTRESS (Immediate and Time dependant)-DCS-II.pptLOSSES OF PRESTRESS (Immediate and Time dependant)-DCS-II.ppt
LOSSES OF PRESTRESS (Immediate and Time dependant)-DCS-II.ppt
 
module3-Design-of-Tension-Members.pdf
module3-Design-of-Tension-Members.pdfmodule3-Design-of-Tension-Members.pdf
module3-Design-of-Tension-Members.pdf
 
Compression member
Compression memberCompression member
Compression member
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concrete
 

Recently uploaded

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
dollysharma2066
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
ankushspencer015
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
dharasingh5698
 

Recently uploaded (20)

Design For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the startDesign For Accessibility: Getting it right from the start
Design For Accessibility: Getting it right from the start
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
FULL ENJOY Call Girls In Mahipalpur Delhi Contact Us 8377877756
 
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
(INDIRA) Call Girl Aurangabad Call Now 8617697112 Aurangabad Escorts 24x7
 
AKTU Computer Networks notes --- Unit 3.pdf
AKTU Computer Networks notes ---  Unit 3.pdfAKTU Computer Networks notes ---  Unit 3.pdf
AKTU Computer Networks notes --- Unit 3.pdf
 
Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01Double rodded leveling 1 pdf activity 01
Double rodded leveling 1 pdf activity 01
 
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...Booking open Available Pune Call Girls Pargaon  6297143586 Call Hot Indian Gi...
Booking open Available Pune Call Girls Pargaon 6297143586 Call Hot Indian Gi...
 
Intro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdfIntro To Electric Vehicles PDF Notes.pdf
Intro To Electric Vehicles PDF Notes.pdf
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 BookingVIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
VIP Call Girls Palanpur 7001035870 Whatsapp Number, 24/07 Booking
 
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete RecordCCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
CCS335 _ Neural Networks and Deep Learning Laboratory_Lab Complete Record
 
Thermal Engineering Unit - I & II . ppt
Thermal Engineering  Unit - I & II . pptThermal Engineering  Unit - I & II . ppt
Thermal Engineering Unit - I & II . ppt
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
(INDIRA) Call Girl Meerut Call Now 8617697112 Meerut Escorts 24x7
 
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank  Design by Working Stress - IS Method.pdfIntze Overhead Water Tank  Design by Working Stress - IS Method.pdf
Intze Overhead Water Tank Design by Working Stress - IS Method.pdf
 
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
VIP Model Call Girls Kothrud ( Pune ) Call ON 8005736733 Starting From 5K to ...
 
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
Call Girls Pimpri Chinchwad Call Me 7737669865 Budget Friendly No Advance Boo...
 
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdfONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
ONLINE FOOD ORDER SYSTEM PROJECT REPORT.pdf
 

Losses in prestress

  • 1. Course no.: CE 416 Course title: Pre-stressed concrete lab Course Teacher: Munshi Galib Muktadir
  • 2. Group-02 10.01.03.123 Raktim Barua 10.01.03.124 Sabrina Shahrin 10.01.03.125 Toufiq Rifath 10.01.03.126 Touhiduzzaman Bizoy 10.01.03.127 Tameem Samdanee 10.01.03.128 Kaji Riyadh Al Saif Ahmed 10.01.03.129 Tanni Sarker 10.01.03.130 Juwairiyah Ishrat Jahan
  • 4. • Notations(symbols) • Introduction to the losses(names and classifications); • Brief description of losses; • Calculations; • Diagrams.
  • 6. The commonly used geometric properties of a prestressed member are defined as follows. Ac = Area of concrete section = Net cross-sectional area of concrete excluding the area of prestressing steel. Ap = Area of prestressing steel Total cross-sectional area of the tendons A = Area of prestressed member = Gross cross-sectional area of prestressed member = Ac + Ap At = Transformed area of prestressed member = Area of the member when steel is substituted by an equivalent area of concrete. = Ac + mAp = A + (m – 1)Ap Here, m = the modular ratio = Ep/Ec Ec = short-term elastic modulus of concrete Ep = elastic modulus of steel.
  • 7. The following figure shows the commonly used areas of the prestressed members. Figure 2-1.1 Areas for prestressed members CGC = Centroid of concrete = Centroid of the gross section. The CGC may lie outside the concrete CGS = Centroid of prestressing steel = Centroid of the tendons. The CGS may lie outside the tendons or the concrete
  • 8. I = Moment of inertia of prestressed member = Second moment of area of the gross section about the CGC. It = Moment of inertia of transformed section = Second moment of area of the transformed section about the centroid of the transformed section. e = Eccentricity of CGS with respect to CGC = Vertical distance between CGC and CGS. If CGS lies below CGC, e will be considered positive and vice versa Figure: CGC, CGS and eccentricity of typical prestressed members
  • 9. Pi = Initial prestressing force = The force which is applied to the tendons by the jack. P0 = Prestressing force after immediate losses = The reduced value of prestressing force after elastic shortening, anchorage slip and loss due to friction. Pe = Effective prestressing force after time-dependent losses = The final value of prestressing force after the occurrence of creep, shrinkage and relaxation.
  • 10.
  • 11. Introduction • In pre-stressed concrete applications, most important variable is the pre-stressing force. In the earlier days, it was observed that the pre-stressing force does not stay constant. • Even during pre-stressing of the tendons and the transfer of pre-stress to the concrete members, there is a drop of the pre-stressing force from the recorded value in the jack gauge. The various reductions of the pre-stressing force are termed as the losses in pre-stress.
  • 12.
  • 13.  In pre – tensioning system, the high- strength steel tendons are pulled between two end abutments (also called bulkheads) prior to the casting of concrete. The abutments are fixed at the end pre stressing bed.  Once the concrete attains the desires strength for prestressing, the tendon are cut loose from the abutments. The pre stress is transferred to the concrete from the tendons, due the bond between them.  During the transfer of pre stress, the member undergoes elastic shortening. If the tendons are located eccentrically, the member is likely to bend and deflect (camber).
  • 14.  Post-tensioning is a method of reinforcing (strengthening) concrete or other materials with high-strength steel strands or bars, typically referred to as tendons  Post-tensioning applications include office and apartment buildings, parking structures, slabs-on- ground, bridges, sports stadiums, rock and soil anchors, and water-tanks
  • 15. Type of Loss Pre- tensioning Post-tensioning 1. Elastic Shortening Yes i. No, if all the cables are simultaneously tensioned. ii. If the wires are tensioned in stages loss will exist. 2. Anchorage Slip No Yes 3. Friction Loss No Yes 4.Creep and Shrinkage of Concrete Yes Yes 5. Relaxation of Steel Yes Yes
  • 16.
  • 17. • Pre-tensioned axial members • Pre-tensioned bending members • Post-tensioned axial members • Post-tensioned bending members.
  • 18. • When the members are cut and the pre-stressing force is transferred to the member, the concrete undergoes immediate shortening due to the pre-stress. The tendon also shortens by the same amount, which leads to the loss of pre-stress.
  • 19. Pre-tensioned Members: The following figure will explain the operation of pre- tensioning through various stages by animation Fig: Pre-tensioning of a member Prestressing bed
  • 20. • If there is only one tendon, there is no loss because the applied pre-stress is recorded after the elastic shortening of the member. For more than one tendon, if the tendons are stretched sequentially, there is loss in a tendon during subsequent stretching of the other tendons.
  • 21. Casting bed Duct jackAnchorage Fig: Post-tensioning of a member Post-tensioned Members: The following figure will explain the complete operation of post-tensioning through various stages by animation.
  • 22. Elastic Shortening: • Loss due to elastic shortening is quantified by the drop in prestress (∆fp) in a tendon due to change in strain in tendon (∆εp). • It is assumed that the change in strain in tendon is equal to strain in concrete (εc) at the level of tendon due to prestressing force, which is called strain compatibility between concrete and steel. • Strain in concrete at the level of tendon is calculated from the stress in concrete (fc) at the same level due to the prestressing force. • A linear elastic relationship is used to calculate the strain from the stress.
  • 23. The quantification of the losses is explained below: ∆fp = Ep ∆εp = Ep εc =Ep (fc / Ec ) • For simplicity, the loss in all the tendons can be calculated based on the stress in concrete at the level of CGS. • This simplification cannot be used when tendons are stretched sequentially in a post-tensioned member. ∆fp = m fc
  • 24. Pre-tensioned Axial Members Original length of member at transfer of prestress Length after elastic shortening Pi P0 Fig:Elastic shortening of a pre-tensioned axial member
  • 25. Pre-tensioned Axial Members: ∆fp = m fc =m(P0/Ac) ∆fp =m(Pi/At) ≈ m(Pi/A)  The stress in concrete (P0/Ac) can be equated to the stress in the transformed section due to the initial pre- stress (Pi/At) .  The transformed area At of the pre-stressed member can be approximated to the gross area A.
  • 26. Pre-tensioned Axial Members Pi P0 Length of tendon before stretching εpi εp0 εc Fig: Elastic shortening of a pre-tensioned axial member
  • 27. • The strain in concrete due to elastic shortening (εc) is the difference between the initial strain in steel (εpi) and the residual strain in steel (εpo). εc= εpi – εpo  The strains can be expressed in terms of the pre-stressing forces as follows: εc =(P0/AcEc) εpi =(Pi/ApEp) εpo=(Po/ApEp)
  • 28. Thus, the stress in concrete due to the prestressing force after immediate losses (Po/Ac) can be equated to the stress in the transformed section due to the initial prestress (P /A ).
  • 29. • A prestressed concrete sleeper produced by pre- tensioning method has a rectangular cross-section of 300mm × 250 mm (b × h). It is prestressed with 9 numbers of straight 7mm diameter wires at 0.8 times the ultimate strength of 1570 N/mm2. Estimate the percentage loss of stress due to elastic shortening of concrete. Consider m = 6.
  • 30.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35. Pre-tensioned Bending Members: Fig: Elastic shortening of a pre-tensioned bending member
  • 36. Due to the effect of self-weight, the stress in concrete varies along length (previous figure). The loss can be calculated by Eqn. (∆fp = m fc ) with a suitable evaluation of the stress in concrete. To have a conservative estimate of the loss, the maximum stress at the level of CGS at the mid-span is considered. M=moment at mid-span due to self weight. Precise result of A & I is not computationally warranted. In the above expression the eccentricity of C.G.S (e) was assumed to be constant.
  • 37. • Post-tensioned Axial Members: For more than one tendon, if the tendons are stretched sequentially, there is loss in a tendon during subsequent stretching of the other tendons. The loss in each tendon can be calculated in progressive sequence. Else,an approximation can be used to calculate the losses. The loss in the first tendon is evaluated precisely and half of that value is used as an average loss for all the tendons.
  • 38. • Post-tensioned Bending Members : The calculation of loss for tendons stretched sequentially, is similar to post-tensioned axial members. For curved profiles, the eccentricity of the CGS and hence, the stress in concrete at the level of CGS vary along the length. An average stress in concrete can be considered. For a parabolic tendon, the average stress (fc,avg) is given by the following equation. fc1 = stress in concrete at the end of the member fc2 = stress in concrete at the mid-span of the member.
  • 39.
  • 40. • The friction generated at the interface of concrete and steel during the stretching of a curved tendon in a post- tensioned member, leads to a drop in the pre-stress along the member from the stretching end. • The loss due to friction does not occur in pre-tensioned members because there is no concrete during the stretching of the tendons.
  • 41.
  • 42. Friction • In addition to friction, the stretching has to overcome the wobble of the tendon. The wobble refers to the change in position of the tendon along the duct. The losses due to friction and wobble are grouped together under friction.
  • 43. Friction Figure :Force acting in a tendon of infinitesimal length
  • 44. • The derivation of the expression of P is based on a circular profile. Although a cable profile is parabolic based on the bending moment diagram, the error induced is insignificant. • The friction is proportional to the following variables. (a) Coefficient of friction (μ) between concrete and steel. (b)The resultant of the vertical reaction from the concrete on the tendon (N) generated due to curvature.
  • 45. From the equilibrium of forces in the force triangle, N is given as follows. The friction over the length dx is equal to μN = μPdα.
  • 46. • The wobble in the tendon is effected by the following variables. • Rigidity of sheathing • Diameter of sheathing • Spacing of sheath supports • Type of tendon • Type of construction • For a tendon of length dx, the friction due to wobble is expressed as kPdx, where k is the wobble coefficient or coefficient for wave effect.
  • 47. • Based on the equilibrium of forces in the tendon for the horizontal direction, the following equation can be written. P = P + dP + (μPdα + kPdx) or, dP = – (μPdα + kPdx) Thus, the total drop in pre-stress (dP) over length dx is equal to –(μPdα + kPdx). The above differential equation can be solved to express P in terms of x.
  • 48. • Here, Po = the pre-stress at the stretching end after any loss due to elastic shortening. For small values of μα + kx, the above expression can be simplified by the Taylor series expansion. Px = Po (1– μα – kx) Thus, for a tendon with single curvature, the variation of the pre-stressing force is linear with the distance from the stretching end.
  • 49. • The following figure shows the variation of pre-stressing force after stretching. The left side is the stretching end and the right side is the anchored end. Figure: Variation of pre-stressing force after stretching
  • 50. Table: Friction co-efficient for post-tensioning tendons *Reference from: Design of pre-stressed concrete structures by T.Y.LIN,NED H. Burns
  • 52.
  • 53.
  • 54.
  • 55.
  • 56.
  • 57. • In a post-tensioned member, when the pre-stress is transferred to the concrete, the wedges slip through a little distance before they get properly seated in the conical space. • The anchorage block also moves before it settles on the concrete. There is loss of pre-stress due to the consequent reduction in the length of the tendon.
  • 58.
  • 59. • The total anchorage slip depends on the type of anchorage system. In absence of manufacturer’s data, the following typical values for some systems can be used. Anchorage System Anchorage Slip (Δs) Freyssinet system 12 - 5mm Φ strands 12 - 8mm Φ strands 4 mm 6 mm Magnel system 8 mm Dywidag system 1 mm Anchorage Slip
  • 60. • Due to the setting of the anchorage block, as the tendon shortens, there is a reverse friction. Hence, the effect of anchorage slip is present up to a certain length (figure below)). Beyond this setting length, the effect is absent. This length is denoted as lset. Figure :Variation of pre-stressing force after anchorage slip. Anchorage Slip
  • 61. • The magnitude of the prestressing force varies along the length of a post- tensioned member due to friction losses and setting of the anchorage block. The diagram representing the variation of prestressing force is called the force variation diagram. Considering the effect of friction, the magnitude of the pre-stressing force at a distance x from the stretching end is given as follows. Px = Poe-nx Here, ηx = μα + kx denotes the total effect of friction and wobble. The plot of Px gives the force variation diagram. The initial part of the force variation diagram, up to length lset is influenced by the setting of the anchorage block. Let the drop in the pre-stressing force at the stretching end be ΔP. The determination of ΔP and lset are necessary to plot the force variation diagram including the effect of the setting of the anchorage block. Force Variation Diagram
  • 62. • Considering the drop in the prestressing force and the effect of reverse friction, the magnitude of the prestressing force at a distance x from the stretching end is given as follows. P’ x=(Po- ΔP) en’x Here, η’ for reverse friction is analogous to η for friction and wobble. Force Variation Diagram
  • 63.
  • 64. Figure :Force variation diagrams for stretching in stages
  • 65. The force variation diagrams for the various stages are explained: • a) The initial tension at the right end is high to compensate for the anchorage slip. It corresponds to about 0.8 fpk initial prestress. The force variation diagram (FVD) is linear. • b) After the anchorage slip, the FVD drops near the right end till the length lset. • c) The initial tension at the left end also corresponds to about 0.8 fpk initial prestress. The FVD is linear up to the centre line of the beam. • d) After the anchorage slip, the FVD drops near the left end till the length lset. • It is observed that after two stages, the variation of the prestressing force over the length of the beam is less than after the first stage
  • 66.
  • 67.
  • 68.
  • 69.
  • 70.
  • 71.
  • 72.
  • 73.
  • 74. • For stress in concrete less than one-third of the characteristic strength, the ultimate creep strain (εcr,ult) is found to be proportional to the elastic strain (εel). The ratio of the ultimate creep strain to the elastic strain is defined as the ultimate creep coefficient or simply creep coefficient θ. The ultimate creep strain is then given as follows. εcr,ult = θ εel
  • 75.
  • 76.
  • 77. • IS:1343 - 1980 gives guidelines to estimate the ultimate creep strain in Section 5.2.5. It is a simplified estimate where only one factor has been considered. The factor is age of loading of the prestressed concrete structure. The creep coefficient θ is provided for three values of age of loading.
  • 78.
  • 79.
  • 80. • The loss in prestress (Δfp ) due to creep is given as follows. Here, Ep is the modulus of the prestressing steel. Δfp = Ep εcr,ult
  • 81. The following considerations are applicable for calculating the loss of pre-stress due to creep: • The creep is due to sustained load only. • Since the pre-stress may vary along the length of the member, an average value of the pre-stress may be considered. • The pre-stress changes due to creep and the creep is related to the instantaneous pre-stress. To consider the interaction, the calculation of creep can be iterated over small time steps.
  • 82.
  • 83.
  • 84. The shrinkage of concrete is defined as the contraction due to loss of moisture. Due to the shrinkage of concrete, the prestress in the tendon is reduced with time.
  • 85.
  • 86.
  • 87.
  • 88.
  • 89.
  • 90.
  • 92. • Relaxation of steel is defined as the decrease in stress with time under constant strain. Due to the relaxation of steel, the prestress in the tendon is reduced with time. • The relaxation depends on the type of steel, initial prestress (fpi) and the temperature.
  • 93.
  • 94.
  • 95.
  • 96.
  • 97.
  • 98.
  • 99.
  • 100. • The losses of prestress due to creep and shrinkage of concrete and the relaxation of the steel are all time- dependent and inter-related to each other. If the losses are calculated separately and added, the calculated total time- dependent loss is over-estimated. To consider the inter- relationship of the cause and effect, the calculation can be done for discrete time steps. The results at the end of each time step are used for the next time step. • This step-by-step procedure was suggested by the Precast / Prestressed Concrete Institute (PCI) committee and is called the General method