SlideShare a Scribd company logo
1 of 10
USING RISK ANALYSIS TO MODEL
CONSTRUCTION SCHEDULE DELAYS : A
BAYESIAN BELIEF NETWORKS APPROACH

Presented by- Group-B3
Asian School Of Business Management
PGDM/13-15
Sec-B
Objectives
 To find out the Schedule delay from the Delay analysis of

the Ash handling plant construction project.
 To identify the risk factors responsible for the schedule

delay.
 To rank the risk factors and to find a method for

evaluating the probability of construction schedule delay.
Key Literature Survey
Sl

Author

Description

1.

Chapman (1990)

This paper outlines an approach to the management of project risk
which was initially developed for offshore North Sea projects and was
subsequently adapted for a range of projects in the USA, Canada and
elsewhere.

2

Ward et. al (1991)

The willingness of contracting parties to take on risks is an important
consideration in the allocation of project risks. A number of factors
contribute to willingness to bear risks, but not all motivate
conscientious, effective project risk management.

3

Shen et. al (2001)

established a risk significance index to show the relative significance
among the risks associated with the joint ventures in the Chinese
construction procurement practice.

4

Luu et. al (2009)

This paper describes how Bayesian belief network (BBN) is applied
to quantify the probability of construction project delays in a
developing country.

5

Jha et. al (2011)

This research presents the international construction risk factors from
the Indian construction professionals’ viewpoint, in a comprehensive
format to enable practitioners to prioritize the efforts to manage the
risk factors.
Bayesian belief network
Bayesian belief networks are directed graphical methods

developed
at Stanford University in the 1970s.
BBNs can be very useful for modelling situations where historical
data is utilized and input data is malfunctioned or is partially
unavailable.
The basic nature of BBN consists of node,arc,and variables with
properties.
A node can be parent or child and the cause-effect relationship
between them is by connecting parent node to child nodes.
BBNs use Bayes’ theorem of conditional probability.
Model development:
Provides accurate solutions even if input data is incomplete

or malfunctioning.
It is user friendly,i.e;additions or modifications in the
knowledge database are easy.
It is flexible is accepting inputs and providing outputs.
Analytical calculations can be corrected efficiently with latest
updates on data.
Input to the network need not be historical data or may be a
set of expert opinions.
Data collection
A web based survey was designed to collect data on experts.
Perceptions of risk factor and their significance in causing

schedule delays for a specific construction project.
The survey was used to collect historical data on each project
and its schedule on each project and its schedule
performance results.
The reliability of the collected data was tested using
CHRONBACH’S ALPHA coefficient between the frequency
of factors and the schedule impact was 0.892 and 0.925
respectively.
BNN model for estimating the probability of
schedule Delay
The collected data was converted into quantitative output based on

the numerical scale adapted from Shen(2001).
The probabilty of occurrence of each factor in a certain project was
set to 50% due to the discrete nature of potential risk delays.
For the parent nodes, representing six groups of collected data,the
relative frequency of each individual group was calculated based on
the summation of the frequency index of each child node.
Conclusion:
As scheduled delays continue to be one of the biggest

problems in construction.
This paper developed a model that will help project
managers to estimate the likelihood of a project’s schedule
delay resulting from different risk factors.
This model will allow project managers to make sufficient
arrangement to mitigate these causes in order to avoid
schedule growth.
This paper also demonstrates the benefits of using BBN as a
modeling tool for schedule delays.
References
Abdelgawas,M.,Hybrid Decision support System for Risk Critically

Assessment
Al-bahar, Risk management in construction project : A systematic
analytical approach for contractors,Ph.D., Universitynof
California,Berkeley,1988.
Assaf S.& Al-Hejji,”causes of delay in large construction
projects”,international journal of projects management,Vol-2,No-4,
Al-Momani”reasons for delays in public projects in Turkey”,construct
management economics,vol-3
Bordoli et.al,”causes of delays in large builiding construction
proojects”,ASCE Journal of Mnagement in Engineering, Vol-11

More Related Content

Viewers also liked

Adventure holiday companies
Adventure holiday companiesAdventure holiday companies
Adventure holiday companiesourservice
 
The Transformation of Indian Two Wheeler Market
The Transformation of Indian Two Wheeler MarketThe Transformation of Indian Two Wheeler Market
The Transformation of Indian Two Wheeler MarketShaswati Mohapatra
 
MAHINDRA N MAHINDRA CASE STUDY ANALYSIS
MAHINDRA N MAHINDRA  CASE STUDY ANALYSISMAHINDRA N MAHINDRA  CASE STUDY ANALYSIS
MAHINDRA N MAHINDRA CASE STUDY ANALYSISShaswati Mohapatra
 
construction risk factor analysis: BBN Network
construction risk factor analysis: BBN Networkconstruction risk factor analysis: BBN Network
construction risk factor analysis: BBN NetworkShaswati Mohapatra
 
What is Emotional Obesity?
What is Emotional Obesity?What is Emotional Obesity?
What is Emotional Obesity?Laura Coe
 

Viewers also liked (8)

Adventure holiday companies
Adventure holiday companiesAdventure holiday companies
Adventure holiday companies
 
The Transformation of Indian Two Wheeler Market
The Transformation of Indian Two Wheeler MarketThe Transformation of Indian Two Wheeler Market
The Transformation of Indian Two Wheeler Market
 
Coca cola
Coca colaCoca cola
Coca cola
 
MAHINDRA N MAHINDRA CASE STUDY ANALYSIS
MAHINDRA N MAHINDRA  CASE STUDY ANALYSISMAHINDRA N MAHINDRA  CASE STUDY ANALYSIS
MAHINDRA N MAHINDRA CASE STUDY ANALYSIS
 
COMMUNICATION..
COMMUNICATION..COMMUNICATION..
COMMUNICATION..
 
construction risk factor analysis: BBN Network
construction risk factor analysis: BBN Networkconstruction risk factor analysis: BBN Network
construction risk factor analysis: BBN Network
 
Coca cola Market analysis....
Coca cola Market analysis....Coca cola Market analysis....
Coca cola Market analysis....
 
What is Emotional Obesity?
What is Emotional Obesity?What is Emotional Obesity?
What is Emotional Obesity?
 

Similar to CON

Risk Prediction for Production of an Enterprise
Risk Prediction for Production of an EnterpriseRisk Prediction for Production of an Enterprise
Risk Prediction for Production of an EnterpriseEditor IJCATR
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - PaperDaniel Ackermann
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
Ppt of final thesis
Ppt of final thesisPpt of final thesis
Ppt of final thesisWU
 
Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6Loren Schwappach
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET Journal
 
IRJET- Development of a Neural Network based Model for Construction Proje...
IRJET-  	  Development of a Neural Network based Model for Construction Proje...IRJET-  	  Development of a Neural Network based Model for Construction Proje...
IRJET- Development of a Neural Network based Model for Construction Proje...IRJET Journal
 
Cost Estimation Predictive Modeling: Regression versus Neural Network
Cost Estimation Predictive Modeling: Regression versus Neural NetworkCost Estimation Predictive Modeling: Regression versus Neural Network
Cost Estimation Predictive Modeling: Regression versus Neural Networkmustafa sarac
 
A defect prediction model based on the relationships between developers and c...
A defect prediction model based on the relationships between developers and c...A defect prediction model based on the relationships between developers and c...
A defect prediction model based on the relationships between developers and c...Vrije Universiteit Brussel
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET Journal
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisInSync Conference
 
IRJET- Projects in Constructions due to Inadequate Risk Management
IRJET-  	  Projects in Constructions due to Inadequate Risk ManagementIRJET-  	  Projects in Constructions due to Inadequate Risk Management
IRJET- Projects in Constructions due to Inadequate Risk ManagementIRJET Journal
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramIJAEMSJORNAL
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthGlen Alleman
 
Survey on Software Data Reduction Techniques Accomplishing Bug Triage
Survey on Software Data Reduction Techniques Accomplishing Bug TriageSurvey on Software Data Reduction Techniques Accomplishing Bug Triage
Survey on Software Data Reduction Techniques Accomplishing Bug TriageIRJET Journal
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growthGlen Alleman
 
Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)Glen Alleman
 
Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...Gafel Kareem
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET Journal
 

Similar to CON (20)

Risk Prediction for Production of an Enterprise
Risk Prediction for Production of an EnterpriseRisk Prediction for Production of an Enterprise
Risk Prediction for Production of an Enterprise
 
Repeatable Risk Identification - Paper
Repeatable Risk Identification - PaperRepeatable Risk Identification - Paper
Repeatable Risk Identification - Paper
 
ONE HIDDEN LAYER ANFIS MODEL FOR OOS DEVELOPMENT EFFORT ESTIMATION
ONE HIDDEN LAYER ANFIS MODEL FOR OOS DEVELOPMENT EFFORT ESTIMATIONONE HIDDEN LAYER ANFIS MODEL FOR OOS DEVELOPMENT EFFORT ESTIMATION
ONE HIDDEN LAYER ANFIS MODEL FOR OOS DEVELOPMENT EFFORT ESTIMATION
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
Ppt of final thesis
Ppt of final thesisPpt of final thesis
Ppt of final thesis
 
Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6Pm610 1103 b-02-schwappach-loren-p5-db6
Pm610 1103 b-02-schwappach-loren-p5-db6
 
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
IRJET- A Study on Factors Affecting Estimation of Construction Project : Conc...
 
IRJET- Development of a Neural Network based Model for Construction Proje...
IRJET-  	  Development of a Neural Network based Model for Construction Proje...IRJET-  	  Development of a Neural Network based Model for Construction Proje...
IRJET- Development of a Neural Network based Model for Construction Proje...
 
Cost Estimation Predictive Modeling: Regression versus Neural Network
Cost Estimation Predictive Modeling: Regression versus Neural NetworkCost Estimation Predictive Modeling: Regression versus Neural Network
Cost Estimation Predictive Modeling: Regression versus Neural Network
 
A defect prediction model based on the relationships between developers and c...
A defect prediction model based on the relationships between developers and c...A defect prediction model based on the relationships between developers and c...
A defect prediction model based on the relationships between developers and c...
 
IRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building ProjectIRJET- Developing Cost Prediction Model for Building Project
IRJET- Developing Cost Prediction Model for Building Project
 
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysisC:\documents and settings\ckampschulte\desktop\in sync risk range analysis
C:\documents and settings\ckampschulte\desktop\in sync risk range analysis
 
IRJET- Projects in Constructions due to Inadequate Risk Management
IRJET-  	  Projects in Constructions due to Inadequate Risk ManagementIRJET-  	  Projects in Constructions due to Inadequate Risk Management
IRJET- Projects in Constructions due to Inadequate Risk Management
 
Delay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa DiagramDelay Analysis in EPC Projects using Ishikawa Diagram
Delay Analysis in EPC Projects using Ishikawa Diagram
 
Cure for Cost and Schedule Growth
Cure for Cost and Schedule GrowthCure for Cost and Schedule Growth
Cure for Cost and Schedule Growth
 
Survey on Software Data Reduction Techniques Accomplishing Bug Triage
Survey on Software Data Reduction Techniques Accomplishing Bug TriageSurvey on Software Data Reduction Techniques Accomplishing Bug Triage
Survey on Software Data Reduction Techniques Accomplishing Bug Triage
 
Cure for cost and schedule growth
Cure for cost and schedule growthCure for cost and schedule growth
Cure for cost and schedule growth
 
Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)Cure for cost and schedule growth (submitted)
Cure for cost and schedule growth (submitted)
 
Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...Forecasting the final cost of iraqi public school projects using regression a...
Forecasting the final cost of iraqi public school projects using regression a...
 
IRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction ProjectIRJET- A Study on Factors Affecting Estimation of Construction Project
IRJET- A Study on Factors Affecting Estimation of Construction Project
 

CON

  • 1. USING RISK ANALYSIS TO MODEL CONSTRUCTION SCHEDULE DELAYS : A BAYESIAN BELIEF NETWORKS APPROACH Presented by- Group-B3 Asian School Of Business Management PGDM/13-15 Sec-B
  • 2. Objectives  To find out the Schedule delay from the Delay analysis of the Ash handling plant construction project.  To identify the risk factors responsible for the schedule delay.  To rank the risk factors and to find a method for evaluating the probability of construction schedule delay.
  • 3. Key Literature Survey Sl Author Description 1. Chapman (1990) This paper outlines an approach to the management of project risk which was initially developed for offshore North Sea projects and was subsequently adapted for a range of projects in the USA, Canada and elsewhere. 2 Ward et. al (1991) The willingness of contracting parties to take on risks is an important consideration in the allocation of project risks. A number of factors contribute to willingness to bear risks, but not all motivate conscientious, effective project risk management. 3 Shen et. al (2001) established a risk significance index to show the relative significance among the risks associated with the joint ventures in the Chinese construction procurement practice. 4 Luu et. al (2009) This paper describes how Bayesian belief network (BBN) is applied to quantify the probability of construction project delays in a developing country. 5 Jha et. al (2011) This research presents the international construction risk factors from the Indian construction professionals’ viewpoint, in a comprehensive format to enable practitioners to prioritize the efforts to manage the risk factors.
  • 4. Bayesian belief network Bayesian belief networks are directed graphical methods developed at Stanford University in the 1970s. BBNs can be very useful for modelling situations where historical data is utilized and input data is malfunctioned or is partially unavailable. The basic nature of BBN consists of node,arc,and variables with properties. A node can be parent or child and the cause-effect relationship between them is by connecting parent node to child nodes. BBNs use Bayes’ theorem of conditional probability.
  • 5. Model development: Provides accurate solutions even if input data is incomplete or malfunctioning. It is user friendly,i.e;additions or modifications in the knowledge database are easy. It is flexible is accepting inputs and providing outputs. Analytical calculations can be corrected efficiently with latest updates on data. Input to the network need not be historical data or may be a set of expert opinions.
  • 6. Data collection A web based survey was designed to collect data on experts. Perceptions of risk factor and their significance in causing schedule delays for a specific construction project. The survey was used to collect historical data on each project and its schedule on each project and its schedule performance results. The reliability of the collected data was tested using CHRONBACH’S ALPHA coefficient between the frequency of factors and the schedule impact was 0.892 and 0.925 respectively.
  • 7. BNN model for estimating the probability of schedule Delay The collected data was converted into quantitative output based on the numerical scale adapted from Shen(2001). The probabilty of occurrence of each factor in a certain project was set to 50% due to the discrete nature of potential risk delays. For the parent nodes, representing six groups of collected data,the relative frequency of each individual group was calculated based on the summation of the frequency index of each child node.
  • 8.
  • 9. Conclusion: As scheduled delays continue to be one of the biggest problems in construction. This paper developed a model that will help project managers to estimate the likelihood of a project’s schedule delay resulting from different risk factors. This model will allow project managers to make sufficient arrangement to mitigate these causes in order to avoid schedule growth. This paper also demonstrates the benefits of using BBN as a modeling tool for schedule delays.
  • 10. References Abdelgawas,M.,Hybrid Decision support System for Risk Critically Assessment Al-bahar, Risk management in construction project : A systematic analytical approach for contractors,Ph.D., Universitynof California,Berkeley,1988. Assaf S.& Al-Hejji,”causes of delay in large construction projects”,international journal of projects management,Vol-2,No-4, Al-Momani”reasons for delays in public projects in Turkey”,construct management economics,vol-3 Bordoli et.al,”causes of delays in large builiding construction proojects”,ASCE Journal of Mnagement in Engineering, Vol-11