12. Building Information Modeling (BIM) data & communication technology tool for object-oriented development using purpose-driven exchange to design & construct a project
13. Integrated Project Delivery (IPD) collaborative method guided by transparency and shared risk & reward to achieve the Owner’s desired outcome
14. Project Information Management (PIM) organized purpose-driven exchange approach toenable project team collaboration using BIM
15. Architect Architect Structural Engineer Civil Engineer Structural Engineer Civil Engineer Building Information Model (BIM) Building Owner Building Owner HVAC Engineer HVAC Engineer City City Facilities Manager Facilities Manager Constr. Manager Constr. Manager Early BIM
16. Author 3DS Max Rhino Maya ADT Research Gravity Affinity Ecotect Sketch Up Tekla Create BIM Navisworks Hold Wind CadDuct 5D 4D Construction Information Model TriRiga (IWMS) Mature BIM Purpose – built models Purpose – driven exchange
22. Owners do projects because they must not because they want to Owners want to create wealth Outcome
23. Cost value for money Velocity increased speed to market Quality decreased tolerance for error Complexity increased systems integration Risk decreased tolerance for uncertainty FEAR Challenges Owners Face RISK
24. Owner Scope Contractor $Does Not Easily Flow$ Architect Labor & Materials DPE DPE Profit Fee ? General Conditions Overhead
25. O O C A A C T A Design Build A Design Bid Build Design Assist + O O O O A C C A BIM GMP A C T Novation A IPD Project Delivery Methods C BIM T
26. O O C A A C T A Design Build A Design Bid Build O Design Assist + O O O O A C P3 PFI A C C Client Interaction C A BIM Design Assist T GMP A C BIM T Novation IPD A T Design / Construct Integration
27. O High Design / Construct Integration O C A A C T A Design Build A Design Bid Build O Design Assist + O High Client Interaction O O O A C P3 PFI A C C Client Interaction C A BIM Design Assist T GMP A C BIM T Novation IPD A Design / Construct Integration T
28. Tools Form of Agreement Model Progression Specification Essential Features of IPD
30. ROLE INTEGRITY Relational Outcome RECIPROCITY FLEXIBILITY CREATION OF RESTRAINT ON POWER IMPLEMENTATION OF PLANNING CONTRACTUAL SOLIDARITY Discrete Service PROPRIETY OF MEANS HARMONIZATION WITH SOCIAL MATRIX EFFECTUATION OF CONSENT RESTITUTION, RELIANCE, EXPECTATIONS - David Campbell,“Ian Macneil and the Relational Theory of Contract” Relational Contract Theory
37. Essential Features of IPD Shared Objective Joint Project Management Early Participation Shared Risk & Reward Source - Howard W. Ashcraft, Jr.; Hanson Bridgett LLP
38. Shared Objective Validated Target Program qualitative & quantitative goals setting the Owner’s project requirements Validated Target Cost (with ICL) single sum for all Direct Costs to design & build the project (also sets the ICL) Validated Target Schedule key task timelines, milestones, target date for Substantial Completion
39. Project Management Team Executive Committee Direction, approval & decisions Project Implementation Team Design and Build the Project Key Participants, early as possible Joint Project Management
52. Early Participation WHAT WHO REALIZE HOW Agency Owner Architect Engineers GC Subs Implementation Documents Agency Coord / Final Buyout Construction Conceptualization Criteria Design Closeout Detailed Design Agency Owner Architect Engineers Collaborate GC Subs HOW WHO WHAT REALIZE Construction Documents Agency Permit / Bidding Construction Predesign Schematic Design Closeout Design Development Key Participants Traditional - AIA,“Integrated Project Delivery: A Guide”
53. Safeguard against fast & cheap Project Quality Adjustment PQA Shared Risk & Reward Project Schedule Adjustment PSA Construction Efficiency Adjustment CEA Incentive Compensation Layer (ICL) ICL Owner Participation
54. PQA C A Owner Cost Reimbursable… C A Owner PSA Cost Reimbursable… C A Owner CEA Cost Reimbursable… Contractor Architect ICL Cost Reimbursable Consultants & Contractors
55. +$8,000 -$3,200 -$3,200 20% of ICL, Maximum PQA -$1,600 +$1,500/day -$200/day -$200/day Late Penalty @ 1/3 of Early Bonus PSA -$100/day $2,000 $2,000 $5,000 $10,000 savings CEA $1,000 $16,000 $16,000 $40,000 ICL $8,000 Hypothetical $1,000,000 VTC
57. What is it all about? What is the idea? What do you really need? Recognize conditions; state directions. What do you want to do? Why? Problem Statement Goals Facts Concepts Needs Function Form Cost Time Discovery Analysis Findings Courtesy of HOK: Problem-Seeking ™ Information Index
58. What is Direct Cost? Profit-at-Risk (ICL) Profit-Not-at-Risk Within VTC Overhead Breakeven ‘Guaranteed’ Beyond VTC DPE Reimbursables
59. Shared Pain & Gain Owner pays direct costs Scheduled Completion ICL ICL pays direct costs 4% VTC Actual Completion Owner pays direct costs Cost Time
60. Design Costs Architect Cost Reimbursable Consultants Fixed-Price Consultants Reimbursable Expenses Construction Costs General Contractor Cost Reimbursable Sub-Contractors Fixed-Price Sub-Contractors General Conditions Other Direct Costs PMT Facilitator FF&E Design and Construct to Objective
62. How to Recognize IPD Multi-Party Agreement Shared Risk & Reward Relational Contract Shared Project Objective ‘Zero’ Change Orders Shared Unitary Fund BIM-Optional (in theory)
63. 1 Multi-Party Agreement Single, signed agreement Owner, Designer, Constructor More parties, counterproductive Joint project management Achieve the project objective as the Project Management Team (PMT) Limited / Waived liability Among PMT
64. 2 Shared Risk & Reward Shared pain & gain based on project outcome Team performance trumps individual Early involvement of key participants Cost Reimbursable consultants & contractors
65. 3 Relational Contract Agreement defines the working relationship of: Owner, Designer, Constructor Roles retain integrity Deliver a project outcome, not a service
68. 6 Shared Unitary Fund VTC is the single source funding all design & construction direct costs Funds ‘flow’ to maximize Owner value If spending more on design saves much more on construction, then money moves that way, & vice-versa
69. 7 BIM-Optional (in theory) BIM is a tool, IPD a method IPD without BIM is possible, but so difficult as to be impractical BIM technology enables IPD
70. Is it good for you? Ask, do we… use a transparent & immediate decision-making process? have knowledge regarding design & construction? not delegate our project participation & responsibility? know our building type? enjoy a reputation for reliability?