SlideShare a Scribd company logo
1 of 155
Download to read offline
FOR INTERNAL CIRCULATION ONLY



            user’s manual
                  of
             Construction
                  (part one)




        Transmission Lines
                   Volume-4
              Tower Erection




             Construction Management
Power Grid Corporation of India Limited
           (A Government of India Enterprise)
DOCUMENT CODE NO. : CM/TL/TOWER ERECTION/96   JUNE,
1996
FROM THE DESK
                               OF
                      DIRECTOR (PERSONNEL)




Four “M’s” viz. men, material, machine & money are vital to run an organization.
However the key to success of the organization lies the way our employees
structure and manage the construction, operation and maintenance activities of
transmission system. Construction activitiy in transmission system is an important
aspect and time, quality and cost are it’s critical parameters.


Experience, no doubt, is a great teacher and a valuable asset. However, the
knowledge of underlined principles of sound working is also equally important.
Preparation of these user’s manuals is the work of our experienced senior field staff
and I find these to be very useful to our site personnel.


These manuals for transmission lines (Vol. 1 2 & 4) alongwith SFQP (Vol. 1) will be
of immense help to our line staff to manage their resources in a more efficient and
systematic way to achieve high quality and reduced time.


I find sincere efforts have gone into preparation of these manuals for which I
congratulate Construction Management team and I am sure the authors will
continue their efforts to bring out more and more such manuals.




                                                                       (R.P. SINGH)
CONTENTS

                          CHAPTER-I

                TOWER CONFIGURATION

1.1    PURPOSE OF TRANSMISSION TOWER

1.2    FACTORS GOVERNING TOWER CONFIGURATION

1.3    TOWER HEIGHT

1.4    ROLE OF WIND PRESSURE

1.5    MAXIMUM & MI8NIMUM TEMPERATURE

1.6    LOADING OF TOWER




                          CHAPTER-2

                  TYPES OF TOWERS
2.1     CLASSIFICATION ACCORDING TO NUMBER OF CIRCUITS

2.2     CLASSIFICATION ACCORDING TO USE

2.3     400KV SINGLE CIRCUIT TOWERS

2.4     400KV DOUBLE CIRCUIT TOWERS

2.5     RIVER CROSSING TOWERS

2.6     RAILWAY CROSSING TOWERS

2.7     HIGH WAY CROSSING TOWERS

2.8     TRANSPOSITION TOWERS

2.9     MULTI CIRCUIT TOWERS

2.10    TOWER EXTENSIONS

2.11    LEG EXTENSIONS
2.12   TRUNCATED TOWERS

2.13   WEIGHT OF DIFFERENT TYPES OF TOWERS


                       CHAPTER-3

                 TOWER FABRICATION


3.1    GENERAL

3.2    BOLTING

3.3    WASHERS

3.4    LAP AND BUTT JOINTS

3.5    GUSSET PLATES

3.6    BRACING TO LEG CONNECTIONS

3.7    CONNECTION TO REDUNDANT MEMBERS

3.8    CROSS-ARM CONNECTIONS

3.9    STEP-BOLTS AND LADDERS

3.10   ANTI-CLIMBING DEVICES

3.11   DANGER AND NUMBER PLATES

3.12   PHASE AND CIRCUIT PLATES

3.13   BIRD GUARD

3.14   AVIATION REQUIREMENT

3.15   PACKING, TRANSPORTATION AND STORAGE OF TOWER PARTS




                       CHAPTER-4

                 METHODS OF ERECTION
4.1    GENERAL
4.1.1    BUILT UP METHOD

4.1.2    SECTION METHOD

4.1.3    GROUND ASSEMBLY

4.1.4    HELICOPTER METHOD

4.2      EARTHING

4.3      TRACK WELDING

4.4      PERMISSIBLE TOLERANCES IN TOWER ERECTION



         ANNEXURE-E/1        -     TOOLS & PLANTS REQUIRED FOR TOWER

                                   ERECTION GANG



         ANNEXURE-E/2        -     MANPOWER REQUIREMENT FOR TOWER

                                   ERECTION GANG




                           CHAPTER-5

         GUIDE LINES FOR SUPERVISION
GL-1     PRE-ERECTION CHECKS

GL-2     CHECKS DURING TOWER ERECTION

GL-3     TIGHTENING AND PUNCHING

GL-4     FIXING OF TOWER ACCESSORIES

GL-5     EARTHING

GL-6     PRE-STRINGING TOWER CHECKS


                           CHAPTER-6

        STANDARDISATION OF TOWER DESIGN
6.1     INTRODUCTION

6.2     STANDARDISATION IN POWERGRID


                       CHAPTER-7

      FORMAT OF TOWER ERECTION CHECKING
Chapter-1
Tower Configuration
___________________________________________________________________________

                                                                          CHAPTER
                                                      ONE
 _________________________________________________________



                                                         TOWER CONFIGURATION



1.1     Purpose of transmission tower

                                                             Back to contents page

           The structures of overhead transmission lines, comprising essentially the
           supports and foundations, have the role of keeping the conductors at the
           necessary distance form one another and form earth, with the specified
           factor of safety to facilitate the flow of power through conductor form one
           point to another with reliability, security and safety.

1.2       Factors governing tower configuration

                                                                Back to contents page

1.2.1     Depending upon the requirements of transmission system, various line
          configurations have to be considered ranging from single circuit
          horizontal to double circuit vertical structures with single or V-strings in
          all phase, as well as any combination of these.

1.2.2     The configuration of a transmission line tower depends on:

          (a)      The length of the insulator assembly.

          (b)      The minimum clearances to be maintained between conductors
                   and between conductor and tower.

          (c)      The location of ground wire or wires with respect to the
                   outermost conductor.

          (d)      The mid span clearance required from considerations of the
                   dynamic behavior of conductors and lightning protection of the
                   line.

          (e)      The minimum clearance of the lower conductor above ground
                   level.

1.3       Tower height
Back to contents page

        The factors governing the height of a tower are:

        (a)     Minimum permissible ground clearance (H1)

        (b)     Maximum sag (H2).

        (c)     Vertical spacing between conductors (H3).

        (d)     Vertical clearance between ground wire and top conductor (H4).

        Thus the total height of the tower is given by

        H = H1 + H2 + H3 + H4

        in the case of a double circuit tower with vertical configuration of
        conductors as shown in Fig. 1.1.

1.3.1   Minimum permissible ground clearance

        From safety considerations, power conductors along the route of the
        transmission line should maintain clearances to ground in open country,
        national highway, rivers, railway tracks, tele-communication lines, other
        power lines etc. as laid down in the Indian Electricity Rule or standards
        or code of practice in vogue.

1.3.2   Maximum sag of Lowermost Conductor

        The size and type of conductor, wind and climatic Conditions of the
        region and span length determine the conductor sag and tensions. Span
        length is fixed from economic considerations. The maximum sag for
        conductor span occurs at the maximum temperature and still wind
        conditions. This maximum value of sag is taken into consideration in
        fixing the overall height of the steel structures. In snow regions, the
        maximum sag may occur even at 0OC with conductors loaded with ice in
        still wind conditions. While working out tension in arriving at the
        maximum sag, the following stipulations laid down, in I.E. Rules (1956)
        are to be satisfied.

        (i)     The minimum factor of safety for conductors shall be based on
                their ultimate tensile strength.

        (ii)    The conductor tension at 32OC (90OF) without external load shall
                not exceed the following percentages of the ultimate tensile
                strength of the conductor.

                Initial unloaded tension                                .   .   35
                percent

                Final Unloaded tension                                  .   .   25
                Percent
In accordance with this stipulation, the maximum working tension under
stringent loading conditions shall not exceed 50 percent of the ultimate
tensile strength or conductor. Sag-Tension computations made for final
stringing of the conductors, therefore, must ensure that factor of safety
of 2 and 4 are obtainable under maximum loading condition and every
day loading condition, respectively.
1.3.3     Spacing of conductors

          The spacing of conductors is determined by considerations which are
          partly electrical and partly mechanical. The material and diameter of the
          conductors should also be considered when deciding the spacing,
          because a smaller conductor especially if made of aluminum, having a
          small weight in relation to the area presented to a cross wind, will swing
          synchronously (in phase) with the wind, but with long spans and small
          wires, there is always the possibility of the conductor swinging non-
          synchronously, and the size of the conductor and the maximum sag at
          the centre of span are factors which should be taken into account in
          determining distance apart at which they should be strung.

1.3.4     Vertical clearance between ground wire and top conductor.

          This is governed by the angle of shielding i.e. the angle which the line
          joining the ground wire and the outermost conductor makes with the
          vertical, required for the interruption of direct lightning strokes at the
          ground and the minimum mid span clearance between the ground wire
          and the top power conductor. The shield angle varies from about 20
          degrees 30 degrees, depending on the configuration of conductors and
          the number of ground wires (one or two) provided.

1.4 Role of wind pressure

                                                              Back to contents page

          The wind load constitutes an important and major component of the total
          loading on towers and so a basic understanding of the computation of
          wind pressures is useful.

          In choosing the appropriate wind velocity for the purpose of determining
          the basic wind pressure, due consideration should be given to the
          degree of exposure appropriate to the location and also to the local
          meteorological data.

          The country has been divided inot six wind zones of different wind
          speeds. The basic wind speeds for the six wind zones are:

          Wind Zone                    Basic wind speed-m/s

               1                       33

               2                       39

               3                       44

               4                       47

               5                       50

               6                       55
Fig. 1.2 shows basic wind speed map of India as applicable at 10m
        height above mean ground level for the six wind zones.

        In case the line traverses on the border of different wind zones, the
        higher wind speed may be considered.



1.4.1   Variation of wind speed with height

        At ground level, the wind intensity is lower and air flow is turbulent
        because of friction with the rough surfaces of the ground. After a certain
        height, the frictional influence of the ground becomes negligible and
        wind velocity increases with height.

1.4.2   Wind force on structure

        The overall load exerted by wind pressure, on structures can be
        expressed by the resultant vector of all aerodynamic forces acting on the
        exposed surfaces. The direction of this resultant can be different from
        the direction of wind. The resultant force acting on the structure is
        divided into three components as shown in Figure 1.3.

        These are :

        (a)     A horizontal component in the direction of wind called drag force
                FD.

        (b)     A horizontal component normal to the direction of wind called
                horizontal lift force FL H.

        (c)     A vertical component normal to the direction of wind called the
                vertical lift force FLV.
1.5 Maximum & minimum temperature :-

                                                           Back to contents page

         A knowledge of the maximum and the minimum temperature of the area
         traversed by transmission line is necessary for calculating sag and
         tensions of conductors and ground wires, thereby deciding the
         appropriate tower design. The maximum and minimum temperature
         normally vary for different localities under different diurnal and seasonal
         conditions.

         The absolute maximum and minimum temperature which may be
         expected in different localities in the country are indicated in the map of
         India in Fig.1.4 and 1.5 respectively. The temperature indicated n these
         maps are the air temperatures in shade.

         The absolute maximum temperature values are increased suitably to
         allow for the sun’s radiation, heating effect of current, etc. in the
         conductor. The tower may be designed to suit the conductor
         temperature of 75 degree C (max) for ACSR and 85 degree C (max) for
         aluminum alloy conductor. The maximum temperature of ground wore
         exposed to sun may be taken as 53 degree C.
1.6     Loading of transmission line towers

                                                             Back to contents page

1.6.1   As per revision o IS;802 regarding materials, loads and permissible
        stresses in transmission line owes, concept o reliability, security and
        safety have been introduced.

        (a)     Reliability

                The Reliability that a transmission system performs a given task,
                under a set of conditions, during a specified time. Reliability is
                thus a measure of the success of a system in accomplishing
                task. The complement to reliability is the probability of failure or
                unreliability. In simple terms, the reliability may be defined as
                the probability that a given item will indeed survive a given
                service environment and loading for a prescribed period of item.

        (b)     Security:-

                The ability of a system to be protected from a major collapse
                such as cascading effect, if a failure is triggered in a given
                component. Security is a deterministic concept as opposed to
                reliability which is a probabilistic concept.

        (c)     Safety:-

                The ability of a system not to cause human injuries or loss of
                lives. It relates mainly to protection of workers during
                construction and maintenance operation. The safety of public
                and environment in general is covered by National regulations.

1.6.2   Nature of loads on Transmission Tower

        Transmission lines are subjected to various loads during their life time.
        These are classified into three distinct categories, namely:

        (a)     Climatic loads:-

                Which relates to reliability requirements.

        (b)     Failure containment loads:-

                Which relates to security requirements.

        (c)     Construction & maintenance loads:-

                Which relates to safety requirements.

1.6.3   Computation of various loads on towers
The loads on of various loads on towers consist of three mutually
perpendicular systems of loads acting vertical, normal to the direction of
the line, and parallel to the direction of the line.

It has been found convenient in practice to standardise the method of
listing and dealing with loads as under:

Transverse load

Longitudinal load

Vertical load

Torsional shear

Weight of structure

Each of the above loads is dealt with separately below:

(a)     Transverse load due to wind on conductors and ground
        wire

        The conductor and ground wire support point loads are made up
        of the following components:

        (i)     Wind on the bare (or ice-covered) conductor / ground
                wire over the wind span and wind on insulator string.

        (ii)    Angular component of line tension due to an angle in the
                line (Figure 1.7).

                The wind span is the sum of the two half spans adjacent
                to the support under consideration. The governing
                direction of wind on conductors for an angle conditions is
                assumed to be parallel to the longitudinal axis of the
                cross-arms (Fig.1.8). Since the wind is blowing on
                reduced front, it could be argued that this reduced span
                should be used for the wind span. In practice, however,
                since the reduction in load would be relatively small, it is
                usual to employ the full span.
(b)    Transverse load due to line deviation

                 The load due to an angle of deviation in the line is computed by
                 finding the resultant force produced by the conductor tensions
                 (Fig. 1.7) in the two adjacent spans. It is clear from the figure
                 that the total transverse load = 2T Sin Ø/2 where Ø is the angle
                 of deviation and T is the conductor tension.

          (c)    Wind load on tower

                 In order to determine the wind load on tower, the tower is
                 divided into different panels having a height ‘h’. These panels
                 should normally be taken between the intersections of the legs
                 and bracings.

1.6.3.2   Longitudinal load

          (a)    Longitudinal load acts on the tower in a direction parallel to the
                 line (Fig. 1.6B) and is caused by unequal conductor tensions
                 acting on the tower. This unequal tension in the conductors may
                 be due to deadending of the tower, broken conductors, unequal
                 spans, etc. and its effect on the tower is to subject the tower to
                 an overturning moment, torsion, or a combination of both. In the
                 case of dead-end tower or a tower with tension strings with a
broken wire, the full tension in the conductor will act as a
                  longitudinal load, whereas in the case of a tower with
                  suspensions strings, the tension in the conductor is reduced to a
                  certain extent under broken-wire conditions as the string swings
                  away from the broken span and this results in a reduced tension
                  in the conductor and correspondingly a reduced longitudinal
                  load on the tower.

          (b)     Torsional load:

                  The longitudinal pull caused by the broken wire condition
                  imposes a torsional movement, T, on the tower which is equal to
                  the product of unbalanced horizontal pull, P and its distance,
                  from the centre of tower in addition to the direct pull being
                  transferred as equivalent longitudinal shear, P as shown in
                  Fig.1.9. The shear P and the torsional movement T = Pe gets
                  transferred to tower members in the plane ABCD.

1.6.3.3   Vertical Load

          Vertical load is applied to the ends of the cross-arms and on the found
          wire peak (Fig.1.6C) and consists of the following vertical downward
          components:

          (i)     Weight of bare or ice-covered conductor, as specified, over the
                  governing weight span.

          (ii)    Weight of insulators, hardware etc., covered with ice, if
                  applicable.

          (iii)   Arbitrary load to provide for the weight of a man with tools.
1.6.3.4   Weight of structure

           The weight of the structure like the wind on the structure, is an unknown
           quantity until the actual design is complete. However in the design of
           towers, an assumption has to be made regarding the dead weight of
           towers. The weight will no doubt depend on the bracing arrangement to
           be adopted, the strut formula used and the quality or qualities of steel
           used, whether the design is a composite one comprising both mild steel
           and high tensile steel or make use of mild steel only. However, as a
           rough approximation, it is possible to estimate the probable tower weight
           from knowledge of the positions of conductors and ground wire above
           ground level and the overturning moment.

           Having arrived at an estimate of the total weight of the tower, the
           estimated tower weight is approximately distributed between the panels.
           Upon completion of the design and estimation of the tower weight, the
           assumed weight used in the load calculation should be reviewed
           Particular attention should be paid to the footing reactions, since an
           estimated weight which is too high will make the uplift footing reaction
           too low.

1.6.3.5    Various loads as mentioned above shall be computed for required
           reliability, security and safety.
Chapter-2
Types of Towers
--------------------------------------------------------------------------
                                                                               CHAPTER
                                                                             TWO
--------------------------------------------------------------------------

                                                                 TYPES OF TOWERS



2.1   Classification according to number of circuits

                                                            Back to contents page

             The    majority      of    high    voltage     double       circuit

       transmission       lines        employ    a    vertical      or     nearly

       vertical configuration              of conductors and single

       circuit transmission lines a triangular arrangement

       of     conductor, single circuit lines, particularly

       at 400 KV and above, generally employ horizontal

       arrangement        of    conductors.          The    arrangement        of

       conductor and ground wires in                  these configurations

       is given at Figure No. 2.1 to Figure No. 2.5.

       The number of ground wires used on the line depends

       on the isoceraunic level (number of thunderstorm

       days/hours        per    year) of the area, importance                 of

       the    line,      and   the      angle    of     coverage      desired.

       Single         circuit           lines         using         horizontal

       configuration generally employ                   two ground wires,

       due to the comparative             width of the configuration;

       whereas        lines       using         vertical        and        offset

       arrangements more often utilise one ground                           wire

       except       on    higher voltage lines of 400 KV                      and

       above, where        it is usually found advantageous to

       string      two   ground    wires,       as    the   phase     to    phase
spacing of conductors would require an excessively

high positioning of ground       wire to give adequate

coverage.   Details   of   different   types   of   400   KV

single circuit and 400 KV double circuit towers are

given at Clause No. 2.3 and 2.4.
2.2. Classification according to use

                                                          Back to contents page

          Towers   are      classified      according       to    their   use

     independent       of     the     number       of    conductors       they

     support.

     A tower has to withstand the loadings ranging from

     straight runs up to varying angles and dead ends.

     To   simplify      the    designs       and    ensure       an   overall

     economy     in    first        cost    and     maintenance,        tower

     designs are generally confined to a few standard

     types as follows.

2.2.1 Tangent suspension tower

      Suspension towers are used primarily on tangents

     but often        are designed to withstand angles in the

     line    up to two degrees or higher in addition to

     the wind,     ice, and         broken-conductor loads. If the

     transmission        line        traverses          relatively      flat,

     featureless terrain, 90 percent of the line may be

     composed of this type of tower. Thus the design of

     tangent    tower       provides       the    greatest       opportunity

     for the structural         engineer          to minimise the total

     weight of steel required.




2.2.2 Angle towers

     Angle towers, sometimes called semi-anchor towers,

     are used where the lines makes a horizontal angle
greater than two degrees (Figure 2.6). As they must

resist a transverse load from the components of the

line tension induced by this angle, in addition to

the    usual   wind,    ice    and   broken     conductor       loads,

they     are   necessarily         heavier      than     suspension

towers. Unless restricted by site conditions, or

influenced      by   conductor       tensions,     angle        towers

should be located so that the axis of the cross-

arms bisects the angle formed by the conductors.

       Theoretically,        different   line    angles        require

different      towers,       but   for   economy       there     is   a

limiting number of different towers which should be

used. This number is a function of all the factors

which make the total erected cost of a tower line.

However, experience has shown that the following

angle towers are generally suitable for most of the

lines :

1. Light angle              - 2 to 150 line deviation

2. Medium angle             - 15 to 300 line deviation

3. Heavy angle              - 30 to 600 line deviation

                              (and dead end)

  While the angles of line deviation are for the

normal span, the span may be increased up to an

optimum     limit      by    reducing    the     angle    of      line

deviation and vice versa. IS:802 (Part I) - 1977

also recommends the above            classification.
The loadings on a tower in the case of a 60 degree

angle condition and dead-end condition are almost

the same. As the number of locations at which 60

degree   angle    towers     and     dead-end    towers      are

required are comparatively few, it is economical to

design   the   heavy   angle   towers    both    for   the   60

degree   angle   condition     and    dead-end    condition,
whichever is more       stringent    for each individual

      structural member.

        For each type of tower, the upper limit of the

      angle range     is designed for the same basic span as

      the tangent tower, so that a decreased angle can be

      accommodated with an increased span or vice versa.

       It would be uneconomical to use 30 degree angle

      towers in locations where angles higher than                2

      degree and smaller than 30 degree are encountered.

      There are limitations to the use of 2 degree angle

      towers at higher angles with reduced spans and the

      use of 30 degree angle towers with smaller angles

      and    increased   spans.   The   introduction   of    a   15

      degree tower would bring about sizable economics.

      Pilot suspension insulator string

      - This shall be used if found necessary to restrict

      the jumper swings to design value at both middle

      and outer phases.

      Unequal cross arms

       -      Another method to get over the difficulty of

      higher swing of Jumper is to have unequal cross

      arms.

2.3   400 kv single circuit towers

                                               Back to contents page

            The bundled conductors are kept in horizontal

      configuration      with a minimum clearance of 11 mtrs.

      phase    to phase.
The     latticed        parts    are     fully    galvanised.

Galvanised hexagonal round head bolts and nuts are

used for fastening with necessary spring or plate

washers.

Normally 4 types of single circuit towers are used

as detailed below :-

a) "A" type towers :

      These     towers    are    used    as     tangent    towers    for

straight run of the transmission line. These are

called suspension or tangent towers. These towers

can carry only vertical loads and are designed for

carrying the weight of the conductor, insulators

and     other     accessories.          These    towers     are     also

designed for a deviation upto                 2 degrees.

b)" B" type towers :

 These towers can be used as sectionalising towers

without angle and angle towers from 2 degrees up to

15 degrees deviation.

c) " C" type towers

 These towers can be used for deviations ranging

from 15 degrees up to 30 degrees. They are also

being    used     as     transposition         towers     without    any

angle.

d) "D" type towers :

  These towers can be used as Dead End or anchor

towers without any angle on the tower.                     Also these

towers can be used for deviations ranging from 30
degree   -   60 degree.

            These towers are usually provided as terminal

       towers near gantry with slack span on one side or

       as   anchoring     tower      before     major    river     crossing,

       power line crossing, railway crossings etc.

       Fig. 2.8 shows two types of tower configuration for

       400 KV single circuit towers.

       A section of 400 kv single circuit towers is shown

       in Fig.2.9.




2.4   400 KV Double circuit towers

                                                         Back to contents page

        These towers are designed to carry two circuits

       consisting    of        3    phases      each,     having      bundled

       conductors.      Here,       the    circuits     are   placed        in   a

       vertical configuration. A minimum phase to phase

       clearance    of    8     mtrs.      is   maintained.      A    minimum

       clearance    of    11       mtrs.   is     maintained         from    one

       circuit to another. Two earthwires are placed above

       each circuit in such a way to provide the required

       shielding angle.
Like single circuit towers, these towers are also

galvanised, lattice steel type structures designed

to carry the tension and weight of the conductor

alongwith       the     insulators,      earthwire         and    its

accessories.

      Normally these towers are identified as P (D/C

 suspension towers), Q, R & S (D/C tension towers)

 or as       DA, DB, DC and DD respectively.

  As in the single circuit towers, DA/P towers are

 used as suspension towers from O degrees-2                  degrees

 deviations. DB/Q,DC/R and DD/S towers are used as

 tension      towers    with    angle   of     deviation     from   2

 degrees-15 degrees, 15 degrees-30 degrees and 30

 degrees - 60 degrees respectively.

  DB towers are also used as sectionalising towers

 without angle.

      DC tower is also used as transposition tower

 without any angle.

  The Double Circuit towers are used while crossing

 reserved       forest,      major   river     crossings,     narrow

 corridors      near    switchyards     etc.     so   as    to   make

 provision for future transmission lines since the

 approval from various           authorities can be obtained

 at    one    time    (for   example,   from    forest,     aviation

 authorities etc.) and to minimise expenditure in

 laying foundations in rivers.

 Fig.2.8 shows two types of tower configuration for
400 kv double circuit towers.

2.5   River-crossing tower

                                                               Back to contents page

              The    height       and     weight    of        the   towers       vary

       considerably          depending        on        the     span,       minimum

       clearance above            water, ice       and wind loads, number

       of     `unbroken'          conductors,           etc.        Usually      the

       governing          specification          requires           that     towers

       employed for crossing of navigable water ways be

       designed for heavy loading conditions and utilise

       larger minimum size members than the remainder of

       the     line.        In     addition        to     these       structural

       requirements, it is often necessary to limit the

       height       of    tall    crossing       towers        because      of   the

       hazard they present to aircraft.

            Fig.2.10 shows a view of 400 kv double circuit

       River crossing tower.

2.6   Railway crossing tower

                                                               Back to contents page

            Angle or dead end towers (Type B,C or D) with

       suitable          extensions       and      with        double      tension

       insulator strings are employed for railway crossing

       in conformity with the relevant specification of

       Railway Authorities.

2.7   High way crossing tower

                                                               Back to contents page

             Angle       towers   (Type    B,C     or    D)    with        suitable
extension    and    with       double     tension    strings    are

employed    for    high    way    crossing.angle      towers    are

used for National High way crossing to make the

crossing    span    as     a     single    section    so   as    to

facilitate independent and prompt striginig.
2.8   Transposition tower

                                                        Back to contents page

 2.8.1 Power transmission lines are transposed primarily

        to   eliminate       or       reduce     disturbances      in    the

        neighboring communication circuits produced by the

        geometric imbalance of power lines. An incidental

        effect of transposing power line section is the

        geometric     balancing        of    such    circuits      between

        terminals which assumes                balanced conditions at

        every point of the             power     transmission system.

        Improvements       and       developments        in     both     the

        communications       and     power     fields   have,     however,

        greatly reduced the need for transposition of high

        voltage lines at close               intervals. In fact, in

        India,     the    central           standing     committee       for

        coordination of power and telecommunication system

        has ruled that "the           power supply authorities need

        not provide       transposition         on power      lines      for

        coordination      with       telecommunication lines".

 2.8.2 However, when transposition are eliminated, there

       are   the   effects      of    geometric      imbalance     of    the

       conductor arrangements on the power system itself,

       and the residual         current        to be considered.         The

       imbalance    of    the     three      phase   voltages      due    to

       asymmetry     of      conductor         arrangement       is      not

       considered serious in view of the equalizing effect
of      the     three     phase        transformer          bank     and

      synchronous         machinery at various           points     on    the

      system. The remaining consideration viz. residual

      currents due to the elimination of transposition,

      might be important from the point of view of relay

      settings to         prevent      causing undesirable          tripping

      of ground current relays. Operating experience has

      shown that many disturbance on high voltage line

      occur     on    transposition          towers   and        statistical

      records       indicate    that    at   least    one    of    the    four

      outages        is     physically         associated          with     a

      transposition.

 2.8.3 A good practice would be to adopt about 200 KM as

      the permissible length of the line without taking

      recourse       to     special      transposition           structures,

      transposition being confined                to substation           and

      switching station only, provided they are located

      at suitable intervals.

 2.8.4 Tower type C under O degree deviation limit and

      with     suitable       modification       shall      be    used     for

      transposition for line maintaining all the required

      clearances          and       shielding.        Arrangement           of

      transposition is shown at Figure 2.7. A view of 400

      kv single circuit transposition tower is also shown

      in Fig.2.11.

2.9   Multi circuit towers.

                                                         Back to contents page
To transmit bulk power at a economical rate, Multi

circuit towers are used. It may be mentioned here

that   a   double   circuit   line   is    cheaper    than   two

independent single circuit lines and four circuit

line    cheaper     than    two   double     circuit      lines.

However, the capital outlays involved become heavy

and it is not easy to visualise the manner in which

the loads build up and the powerflow takes place in

the    longterm     prospective.     Further,      reliability

considerations become very important at extra                high

voltages.    A    balance   has   therefore   to     be   struck

between    the two somewhat opposing        considerations.
2.10   Tower extensions

                                                    Back to contents page

         All towers are designed in such a way that they

         can be provided with standard tower extensions.

         Extensions are designed as +3, +6 +9 and + 25 in

         Mtrs.    These    extensions    can   be   used    alongwith

         standard towers to provide sufficient clearance

         over ground or while crossing power lines, Railway

         lines, highways, undulated, uneven ground etc.

         A view of 400 kv single circuit towers crossing

         anoth er 400 kv single circuit line is shown at

         Fig. 2.12

2.11     Leg extensions

                                                    Back to contents page

         Leg extensions are designed to provide extension

         to   tower       legs   which   are   located     at   uneven

         ground    where different legs of the tower are at

         different levels.
Standard designs can be made for 1.5, 2.5 and 3.5 M

     leg extensions.

      These leg extensions can be utilised where towers

     are located on hill slopes, undulated ground etc.

     By    providing       leg     extensions,         specially     in   hilly

     areas,    heavy        cost    of     benching/revetment          can    be

     avoided       completely or reduced substantially.

2.12 Truncated towers             (Tower reductions)

                                                           Back to contents page

      Similar to extension towers, truncated towers can

     also be used for getting the sufficient electrical

     clearance while crossing below the existing                          Extra

     High     Voltage      lines.       For   instance,a       DD-6.9     Mtrs.

     truncated tower has been used in 220 KV RSEB S/Stn.

     at Heerapura (Jaipur). In this particular case 2

     nos. of 400 KV S/C lines are already crossing over

     the 220 KV D/C Kota-Jaipur RSEB feeders with A+25

     Mtrs. extension type of towers. While constructing

     another D/C 220 KV line from Anta to Jaipur which

     was    also     to    be     terminated      in    the   same   sub-stn.

     either to under cross these 400 KV S/C lines by

     using gantry system or to make use of                      the existing

     A+25 Mtrs. extension towers. But with the existing

     A+25     Mtrs        extension       tower,       required      clearance

     between the earth wire of the 220 KV line and hot

     Conductor       of     400    KV     lines    were   not     within     the

     permissible          limit.     So    for    getting     the     required
electrical clearance either to remove the earthwire

       of 220 KV line or to use truncated tower. So to

       avoid     the    removal    of     earth    wire     a     `DD'    type

       truncated tower (-6.9 Mtrs.) has been used in order

       to cross these lines safely and with the required

       permissible electrical clearances.

            The truncated tower is similar to normal tower

       except 6.9       Mtrs    of bottom section of normal tower

       has     been removed, the other section of the tower

       parts    remain un-changed.

       This is a ideal crossing in an area where one line

       has already crossed over the existing lines                        with

       Special extension tower and we have to accommodate

       another line in the existing crossing span.

2.13         Weight of different types of towers

                                                      Back to contents page

            The weight of various types of towers used on

       transmission lines, 66 KV to 400 KV, together with

       the     spans and       sizes of conductor and ground wire

       used in lines are given in Table 2.1. Assuming that

       80    percent     are    tangent    towers,    15        percent    300

       towers     and    5     percent    600   towers      and     dead-end

       towers,     and       allowing      15     percent       extra      for

       extensions and stubs, the weights of towers for a

       10 kms. line are also given in the Table 2.1.

        Table 2.1 Weights of towers used on various

                   voltage categories in India
(Metric tones)
                        400 kV       220 kV      220 kV     132 kV        132 kV        66 kV        66 kV

                        Single       Double      Single     Double        Single       Double       Single

                        Circuit      Circuit     Circuit    Circuit       Circuit      circuit      Circuit
Span (m)                  400          320         320        320           320          245          245
Conductor                Moose        Zebra       Zebra     Panther       Panther     Dog 6/4.72   Dog 6/4.72

                       54/3.53 mm   54/3.18 mm   54/3.18    30/3 mm       30/3 mm     mm Al. +       Al. +

                       al. + 3.53     Al +       mm Al. +    Al. +        Al.+7/3     7/1.57 mm    7/1.57 mm

                       mm Steel     7/3.18 mm    7/3.18     7/3 mm        mm Steel      Steel        Steel

                                      Steel      mm Steel    Steel
Groundwire             7/4 mm 110   7/3.15 mm     7/3.15    7/3.15        7/3.15      7/2.5 mm     7/2.5 110

                        Kgf/mm2        110       mm 110     mm 110        mm 110         110        Kgf/mm2

                        quality      Kgf/mm2     Kgf/mm2    Kgf/mm2       Kgf/mm2      Kgf/mm2      quality

                                     quality     quality    quality       quality      quality
Tangent Tower              7.7          4.5        3.0        2.8           1.7          1.2          0.8
30 Deg. Tower             15.8          9.3        6.2        5.9           3.5          2.3          1.5
60 Deg. And Dead-end     23.16         13.4        9.2        8.3           4.9          3.2          2.0

Tower
Weight of towers for      279          202         135       126            76            2           48

a 10-km line




      Note:     Recent      designs       have    shown     10       to    20%       reduction      in

      weights.
--------------------------------------------------------------------------
                                                                           CHAPTER
                                                                       THREE
                                Chapter-3
--------------------------------------------------------------------------

                                                            TOWER FABRICATION
                        Tower Fabrication
3.1   General

                                                              Back to contents page

        After     completing       the     tower     design,       a   structural

        assembly    drawing       is     prepared.     This    gives     complete

        details    of    joints,       member   sizes,      bolt   gauge       lines,

        sizes and lengths of bolts, washers, first and                         second

        slope    dimensions,       etc.     From     this    drawing,      a    more

        detailed drawing is prepared for all the individual

        members. This is called a shop drawing or fabrication

        drawing. Since all parts of the tower are fabricated

        in accordance with the shop drawing, the latter should

        be drawn to a suitable scale, clearly indicating all

        the details required to facilitate correct and smooth

        fabrication.

        Towers used are of bolted lattice type. In no case

        welding    is     allowed.       All    members,     bolts,     nuts     and

        fittings are          galvanised. Spring       washers are         electro

        galvanised.

        Fabrication of towers are done in accordance with IS

        codes which is ensured by visit to the fabrication

        workshops       and    undertaking      specified       tests,     in    the

        presence of POWERGRID quality engineers. The following

        may be ensured during fabrication of the towers.
i)      Butts, splices should be used and thickness of

                inside   cleat     should     not   be   less    than    that    of

                heavier member connected. Lap splices are used to

                connect unequal sizes.

        ii)     While designing, joints are to be made so that

                eccentricity is avoided.

        iii) Filler should be avoided as far as practicable.

        iv)     The dia of hole = dia of bolt            + 1.5 mm

        v)      Drain holes are to be provided where pockets of

                depression are likely to hold water.

        vi)     All similar      parts should       be interchangeable           to

                facilitate repairs.

        vii) There should be no rough edges.

        viii) Punched holes should be square with plates and

                must have their walls parallel.

        ix)     It   should   be     checked    that     all    burrs    left    by

                drilling      or      punching       should        be     removed

                completely.        Drilling    or      reaming      to    enlarge

                defective holes is not allowed.

3.2   Bolting

                                                               Back to contents page

3.2.1 The minimum diameter of bolts used for the erection of

       transmission line towers is 12 mm. Other sizes commonly

       used are 16 mm and 20 mm.

3.2.2 The length of the bolt should be such that the threaded

      portion does not lie in the plane of contact of members.
Figure 3.1 shows the wrong uses and the correct uses of

      bolt threads.

3.2.3 Table 3.1 gives the minimum cover to free edge and bolt

      spacing as per IS:802 (Part II)-1978 Code of Practice

      for Use of Structural Steel in Overhead Transmission

      line Towers. The bolts used with minimum angle sizes

      restrict the edge distances as given in Table 3.2 for

      the bolt sizes of 12 mm, 16 mm and 20 mm used on 40 x6

      mm, 45x6 mm and 60x 8 mm angle sizes respectively.


        Table 3.1 Spacing of bolts and edge distances
                                                           (mm)
 -------------------------------------------------------------
 Bolt     Hole      Bolt spacing      Edge distance(min)
 Dia      dia       min.              Hole         Hole
                                      centre       centre
                                      to rolled    to
                                      edge         sheared
                                                   edge
 -------------------------------------------------------------
 12       13.5      32                16           20
 16       17.5      40                20           23
 20       21.5      48                25           28
 -------------------------------------------------------------
                                           (See next page)
Table 3.2 Maximum edge distance possible
                with minimum angle size      (mm)

---------------------------------------------------------
                   Size of bolted          Maximum edge
 Bolt dia.         leg of angle            distance that
                   section and its         can be
                   thickness               actually
                                           obtained
 --------------------------------------------------------
         12                  40x6            17
         16                  45x6            18
         20                  60x8            25
 --------------------------------------------------------



 3.2.4 The bolts may be specified to have Whitworth or

      other approved standard threads to take the full

      depth    of     the       nut,    with     the   threading     done    far

      enough to permit             firm gripping of the members but

      no farther, and with the threaded portion of each

      bolt projecting through the nut by at least one

      thread.    It    may       also       be   specified   that    the     nuts

      should fit hand-tight to the bolts, and that there

      should be no appreciable fillet at the point where

      the     shank    of       the     bolt     connects     to    the    head.

      Emphasis        should           be     laid     on    achieving        and

      maintaining proper clamp load control in threaded

      fastners.       If    a    threaded        fastener    is    torqued   too

      high, there is a danger of failure on installation

      by stripping the threads or breaking the bolt or

      making the fasteners yield excessively. If the bolt

      is torqued too low, a low preload will be induced

      in the fastener assembly, possibly inviting fatigue

      or vibration failure. For every bolt system, there
is an optimum preload objective which is obtained

    by proper torquing of the bolt and nut combination.

      The three techniques for obtaining the required

    pretension are the calibration wrench method, the

    turn-of-the-nut            method        and        the    direct     tension

    indication method.

      The calibrated wrench method includes the use of

    manual torque wrenches and power wrenches adjusted

    to stall at a specified torque value. Variations in

    bolt tension, produced by a given torque, have been

    found to be plus minus 10 percent.

    The turn-of-the-nut method has been developed where

    the pretensioning force in the bolt is obtained by

    specified       rotation       of   the        nut    from    an    initially

    snug tight position by an impact wrench or the full

    effort   of      a   man    using        an    ordinary       wrench.       This

    method     is    found      to      be    reliable,          cheapest        and

    preferred.

         The      third      and     the      most       recent      method      for

    establishing         bolt      tension         is    by    direct     tension

    indicator.        There      are       patented           load     indicating

    washers,        where      correct        bolt        tension       could     be

    assessed        by      observing         the        deformation.           Upon

    tightening the bolt, the washers are flattened and

    the gap is reduced. The bolt tension is determined

    by measuring the remaining gap.

3.2.5 Most of the transmission line specifications do
not specify the maximum permissible group length of

      bolts. It is a good practice to ensure that no bolt

      connects aggregate thickness more than three times

      the    diameter of the bolt. Further more, the grip

      strength developed by a bolt depends not only upon

      the thickness of the members but also on the number

      of members to be connected. This is due to the fact

      that      the   surface   of   the    members    may    not     be

      perfectly smooth and plain and, therefore, if the

      number of members to be connected is too many, the

      full grip strength would not be developed. In the

      tower construction, the need for connecting more

      than three members by a single bolt rarely arises,

      it would be reasonable to limit            the number of the

      members to be connected by a single             bolt to three.

      The    limitation      regarding     the   thickness    of     the

      members and the number of members to be connected

      is necessary not only from the point of view of

      developing maximum grip strength but also from the

      point of view of reducing the bending stresses on

      the bolt to a minimum.

 3.2.6 The threaded portion of the bolt should protrude

      not less        than   3 mm and not more than 8 mm            over

      the    nut after it is fully tightened.

3.3   Washers

                                                   Back to contents page

       At present, both flat and spring steel washers are
being     used      in    the     construction           of    transmission

      line     towers      in    India.          The    advantage       of    spring

      washers over flat washers is that the former, in

      addition to developing the full bearing area of the

      bolt,        also        serve        to     lock        the     nuts.     The

      disadvantages, however, are that it is extremely

      difficult to get the correct quality of steel for

      spring washers, and also that they are too brittle

      and     consequently        break          when    the    nuts    are    fully

      tightened. Furthermore, the spring washers, unlike

      flat     washers     tend        to    cut       into    and   destroy    the

      galvanising.

      When spring washers are used, their thicknesses

      should be as recommended in IS:802 (Part II)-1978

      and given in Table. 3.3

               Table 3.3: Thicknesses of spring washers

                                                      (mm)
------------------------------------------------------------
           Bolt dia.          Thickness of spring washer
------------------------------------------------------------
             12                        2.5
             16                        3.5
             20                        4.0
------------------------------------------------------------


            With    regard       to    the       locking       arrangement,     the

      general      practice       is    to       lock    the    nuts    by    centre

      punching of the bolts or punching the threads. In

      special cases such as tall river-crossing towers

      which    are     subjected            to    unusual      vibrations,       the

      bolts are secured from slacking back by the use of
lock nuts, by spring washers, or by cross-cutting

      of the thread.

             A    minimum     thickness           of    3mm    for    washers       is

      generally specified.

            In our transmission lines, we are using spring

      washers        under    all    nuts         of    tower.    These      spring

      washers        are electro-galvanised.

3.4   Lap and butt joint

      (figure 3.2 and 3.3)

                                                               Back to contents page

       Lap splices are normally preferred for leg members

      as     these      joints    are    generally         simpler      and      more

      economical         compared       to    the       heavier      butt    joints

      which are employed only if structural requirements

      warrant their use.

       In lap splices, the back(heel) of the inside                              angle

      should       be    ground     to       clear      the    fillet       of     the

      outside angle.

3.5   Gusset plates

                                                               Back to contents page

       In the case of suspension towers, the stresses in

       the web system are usually small enough to keep the

       use       of gusset plates to the minimum. On heavier

       structures, however, the web stresses may be very

       large and it          may not         be    possible to accommodate

       the number of bolts required for the leg connection

       in    the     space       available         on    the     members,        thus
necessitating the use of gusset plates. Plates may

also be required to reduce the secondary stresses

introduced due to eccentricity to a minimum.

 The bracing members should preferably meet at a

common point     within   the width of the tower leg in

order to limit the bending stresses induced in the

main members due to eccentricity in the joints. To

satisfy   this   condition,   it   may   sometimes   become

necessary to use gusset plates.
3.6   Bracing to leg connections

                                                      Back to contents page

        Typical connections of diagonals and struts to a

      leg member are shown in Figure 3.4.

           The number of bolts required in these simple

      connections     is    derived   directly       from    the    member

      load and    the capacity per bolt either in shear or

      bearing.   Diagonal        members    which    are     clipped       or

      coped for clearance purposes must be checked for

      capacity   of   the       reduced    net    section.       Note    that

      gusset plates are not used at leg connections, but

      eccentricity is kept to a minimum by maintaining a

      clearance of 9.5mm to 16mm between members.

       If the leg does not provide enough gauge lines to

      accommodate     the       required    bolts     in     a    diagonal

      connection, a gusset plate as shown in Figure                      3.5

      may be employed. The thickness of gusset plate must

      be   sufficient      to    develop    the    required       load    per

      bolt.

        Typical gusset plate connection at waist lines on

      the normal face for a wasp-waist tower is shown in

      Figure 3.6.



3.7   Connection of redundant members

                                                      Back to contents page

           Redundant sub-members usually require only one
bolt connection to transfer their nominal loads.

       Thus,        gusset    plates    can    easily    be       avoided   if

       clipping        and     coping    are     used        to     advantage.

       Typical connections, shown in Figures 3.7, 3.8 and

       3.9 indicate the methods of clipping or turning

       members in or out to keep the number of bolts to a

       minimum. Figure 3.7 illustrates the use of a small

       plate rather than connecting five members on one

       bolt, as it has been found that erection of more

       than    four     thicknesses      per    bolt     is       particularly

       awkward.

3.8   Cross-arm connections

                                                         Back to contents page

       The cross-arm to leg connection (Figure 3.10) must

       be considered as one of the most important joints

       on     a tower         since all loads originating from the

       conductors are          transferred      through the cross-arms

       to     the     tower    shaft    by    means     of    these    bolts.

       Because of its importance, a minimum of two bolts

       is often specified for this connection.
An example of a hanger-to-arm-angle connection on `Vee'

       cross-arm is shown in Figure 3.11, Both vertical

       and horizontal eccentricities may become excessive

       if the detail of this joint is not carefully worked

       out. Suspension towers are provided with holes at

       the    ends    of   the        cross-arms,     as     shown    in   Figure

       3.10,    for    U-Bolts         which    receive        the    insulator

       string    clamps.         Strain      towers,       however,       must    be

       supplied with strain plates (Figure 3.12) which are

       not    only    capable          of      resisting      the    full       line

       tension, but also shock and fatigue                      loads as well

       as wear.

3.9   step bolts and ladders

                                                             Back to contents page

       The step bolts usually adopted are of 16mm diameter

       and 175mm length. They are spaced 450mm apart and

       extend from about 3.5 metres above the ground level

       to the top of the tower. The bolts are provided

       with    two    nuts       on    one   end     to    fasten    the    bolts

       securely      to    the    tower,       and   button     heads      at    the

       other end to prevent the foot from slipping away.

       The step bolts should be capable of withstanding a

       vertical load of not less than 1.5 KN. Step bolts

       are provided from 3.5 m to 30 m height of the

       superstructure. For special structures, where the

       height    of    the   superstructure               exceeds    50    metres,

       ladders along with protection rings are provided
(in     continuation              of      the     step    bolts        on     the

        longitudinal          face      of     the      tower)    from    30    metres

        above    ground           level      to    the    top     of    the    special

        structure. A platform, using 6mm thick chequered

        plates,     along with a suitable                   railing       for access

        from     step        bolts to the ladder                  and     from        the

        ladder         to    each       cross-arm,        and    the    ground      wire

        support is also provided.

3.10   Anti-climbing devices

                                                                  Back to contents page

        All towers are provided with anti-climbing devices

        at     about        3.5     metres        above     ground       level.       The

        details     of       anti-climbing              devices    are     shown       in

        Figure 3.13.

3.11   Danger and number plates

                                                                  Back to contents page

         Provision is made on the transverse face of the

       tower for fixing the danger and number plates while

       developing             the         fabrication            drawing.           These

       accessories           are       generally        fixed     at    about       4.5mm

       above the ground level. Fig. 3.18 and Fig.3.16 show

       the      details            of      danger         and     number        plates

       respectively.

          The letters, figures and the conventional skull

       and bones of the danger plates should conform to

       IS:2551-1982 Specification for Danger Notice Plates

       and      they are          to     be painted in signal red on the
front   of   the plate.
3.12   Phase and circuit plates

                                                       Back to contents page

        Each tension tower shall be provided with a set of

       phase plates. The transposition towers should have

       the provisions of fixing phase plates on both the

       transverse faces. The details of phase plate are

       given in Fig. 3.15.

         All the double circuit towers shall be provided

       with   circuit       plate    fixed     near    the    legs.    The

       details      of     circuit    plates     are     indicated       in

       Fig.3.17.

          These plates shall also be fixed at about 4.5m

       above ground level.

3.13   Bird guard

                                                       Back to contents page

         Perching of Birds on tower cross arms results in

       spoiling of insulator discs of suspension strings

       which leads to tripping of line. To overcome this

       problem,     bird    guards    are    fixed     over   suspension

       insulator string. The details are given at Figure

       No. 3.14.

       Bird guards shall be used for type-I string only.



3.14   Aviation requirements :-

                                                       Back to contents page

 3.14.1 The river crossing towers and any other towers in
the vicinity of an airport shall be painted and the

     crossing    span   shall   be    provided   with   markers   to

     caution    the low flying air craft.

3.14.2 The full length of the towers shall be painted

       over    the   galvanised surface in contrasting bands

       of   orange or    red    and   white. The bands shall be

       horizontal. Fig.2.10 shows the river crossing

       tower with aviation paints.
3.15    Packing, transportation and storage of tower parts.

                                                           Back to contents page

 3.15.1     Packing :

            a)     Angle section shall be wire bundled. Cleat

                   angles,    gusset        plates,    brackets,        fillet

                   plates,        hangers    and similar loose pieces

                   shall be bolted together to multiples or

                   securely wired together through holes.

            b)     Bolts, nuts, washers and other attachments

                   shall     be     packed    in     double     gunny     bags

                   accurately tagged in accordance with the

                   contents.

            c)     The   packing      shall     be    properly        done   to

                   avoid losses/damages during transit.                   Each

                   bundle or package shall be appropriately

                   marked.

3.15.2      Transportation.

            The transport of steel towers from the works to

            the nearest railway station presents no special

            difficulty. The towers are delivered in trucks

            having one or two towers per truck according to

            the weight involved. A station having a loading

            bay    is    highly      desirable,       as      this    greatly

            facilitates handling. The lorries can be backed

            against the bay and the ease of                 handling      will

            then   offset     any     slight       increase      in   haulage
costs from a station less well equipped. The

parts of each tower should be kept separate so

that they can be delivered from the bay direct

to the tower site. Tower sets are made up in

sections,     since     it    is     impracticable       for    the

corner angles to be in one length. Each section

is    carefully      marked     at    the       works.   In    each

section      there are generally one or more panels

and these are marked to facilitate erection.

The tower sets should be carefully checked when

unloaded      from     the trucks and then placed in a

suitable position on the bay where they can be

picked up easily as             a    complete unit. If the

steelwork is delivered in bundles, the checking

is even more important and there are two meth-

ods    of    doing     this.        Some    Engineers       prefer

laying      the     steelwork       out    in    members      while

others prefer it laid out in towers and in our

opinion       the      latter        method          has       many

advantages.         Shortages        are        easily     spotted

and scheduled and the tower can be loaded and

taken to its particular position. All bolts,

washers, nuts and small parts should be in bags

and labelled with the number of the tower they

are intended for. A word of warning                  re-garding

the handling of the long corner angles                      should

be    clearly displayed. These must be carefully
transported or they may get bent and it is a

         very difficult job to straighten them without

         damaging         the         galvanising.            All         material

         transport     shall          be     undertaken            in     vehicles

         suitable    for        the    purpose         and    free       from    the

         effects     of     any        chemical         substances.            Tower

         members shall be loaded and transported in such

         a manner that these are not bent in transit and

         sharp-bent        members          are      not     opened        up     or

         damaged.

3.15.3   Storage.

         A.   The         selection            of       location           of      a

              construction             store      is    important          as    the

              movement of construction materials is time

              consuming process and it requires detailed

              planning          and     Managerial           attention.          The

              selection of location is generally based

              on the following criteria.

         a.   Close       proximity         to      rail     heads,       National

              Highways.

         b.   Proximity to urbanisation and towns.

         c.   Availability             of      water         and        electrical

              power.

         d.   Distance          from        the      proposed           line     and

              approach.

         e.   Type    of    land.          (The     store     should       not    be

              located on marshy or wet lands. Also, the
low lying and water stagnant areas)

f.   Availability of land in sufficient area.

g.   Communication facilities.

h.   Availability of labour for the work in the

     stores.

B.   Once    land      is    selected,      it    is    better    to

     identify the space for towers, insulators,

     conductors,            hardware     and     the     tools    &

     plants       of         erection       contractor.          The

     selection         of     place     for      each    type     of

     material should be very judicious and in

     such     a     way       that      inward     or     outward

     movement       of       one     item      should     not     be

     through      the stacking           of the materials of

     other     item.        Proper      board     markings       and

     pointers may be kept for each                      item     for

     easy identification.

C.   Tower parts should not be kept directly

     on     the ground             and it should be placed

     above stones of               proper size or sleepers

     to avoid contact with mud.

D.   It is always preferable to stack the tower

     parts in       a neat and systematic fashion in

     tower wise order. On request of erection

     gang,     store-keeper            should     be     able    to

     provide him one full set of tower without

     any difficulty and delay.
E.   The following points may be ensured in the

     stores.

     a.   Complete fencing of the store yard.

     b.   24 hours vigilant security.

     c.   Proper lighting.

     d.   Fire protection equipments.
Chapter-4
Methods of Erection
--------------------------------------------------------------------------
                                                                     CHAPTER
                                                                    FOUR
--------------------------------------------------------------------------


                                             METHODS OF ERECTION



4.1       GENERAL

                                                         Back to contents page

           There are four main methods of erection of steel

           transmission towers which are described as below

           i.    Built-up method or Piecemeal method.

           ii.   Section method

           iii. Ground assembly method.

           iv.   Helicopter method

4.1.1     Built up method

                                                         Back to contents page

           This method is most commonly used in this country

           for the erection of 66 KV, 132 KV, 220 KV and 400 KV

           Transmission      Line   Towers    due   to    the      following

           advantages.

           i.    Tower    materials    can   be   supplied    to    site   in

                 knocked down condition which facilitate             easier

                 and   cheaper transportation.

           ii.    It does not require any heavy machinery such

                 as cranes etc.

           iii. Tower erection activity can be done in any kind

                 of terrain and mostly through out the year.
iv. Availability of workmen at cheap rates.

     This method consists of erecting the towers,

     member by member. The tower members are kept on

     ground serially according to erection sequence

     to    avoid    search       or    time   loss.      The    erection

     progresses from the bottom upwards, the four

     main corner leg members of the first section of

     the    tower    are     first      erected     and    guyed         off.

     Sometimes more than continuous leg sections of

     each    corner       leg    are    bolted     together         at   the

     ground and erected.

     The cross braces of the first section which are

     already assembled on the ground are raised one

     by one as a unit and bolted to the already

     erected corner leg angles. First section of the

     tower    thus    built      and     horizontal       struts         (bet

     members) if any, are bolted in position. For

     assembling the second section of the towers,

     two gin poles are placed one each on the top of

     the     diagonally opposite corner legs. These two

     poles    are    used       for    raising     parts       of   second

     section. The leg members and braces of this

     section are then hoisted and assembled. The gin

     poles    are     then      shifted       to   the     corner         leg

     members on the top of second section to raise

     the    parts    of    third       section     of   the     tower     in

     position for assembly. The gin pole is thus
moved up as the tower grows. This process is

continued till the complete tower is erected.

Cross-arm members are assembled on the ground

and raised up and fixed to the main body of the

tower.    For     heavier    towers,      a   small     boom   is

rigged on one of the tower legs for hoisting

purposes.       The    members/sections         Are       hoisted

either manually or by winch machines operated

from      the         ground.       For       smaller        base

towers/vertical configuration towers, one gin

pole is used instead of two gin poles. In order

to     maintain    speed     and    efficiency,       a     small

assembly party goes ahead of the main erection

gang and its purpose is to sort out the tower

members,     keeping        the     members      in       correct

position     on    the     ground    and      assembling       the

panels on the ground which can be erected as a

complete unit.

Sketches indicating different steps of erection

by built up method are shown at Figure 4.1 to

Figure 4.7.

List of Tools and Plants and Manpower for Tower

Erection is given at Annexure E/1 and E/2.

Guying arrangement - Guying arrangements are to

be done at waiste level/bottom cross-arm level

as well as in the girder level/top cross-arm

level depending on SC/DC towers and it is to be
installed at 450 from vertical. The deadments

              for     guying    arrangements    is    to    be    properly

              made. A sample of deadments drawing is enclosed

              at Figure 4.8 for reference. Guying should be

              steel     wire    or    polypropylene    rope      depending

              upon    requirements.      Nominal   tension       is   to    be

              given in guying wire/rope for holding the tower

              in position.

4.1.2   Section method

                                                      Back to contents page

         In the section method, major sections of the tower

         are assembled on the ground and the same are erected

         as units. Either a mobile crane or a gin pole is

         used. The gin pole used is approximately 10 m long

         and is held in place by means of guys by the side of

         the tower to be erected. The two opposite sides of

         the lower section of the tower are assembled on the

         ground. Each assembled side is then lifted clear of

         the ground with the gin or derrick and is lowered

         into position on bolts          to stubs or anchor bolts.

         One side is held in place with props while the other

         side is being erected.

         The two opposite sides are then laced together with

         cross members diagonals; and the assembled section

         is   lined    up,     made   square   with   the     line,        and

         levelled. After completing the first section, gin

         pole is set on the top of the first section. The gin
rests on a strut of the tower immediately below the

leg joint. The gin pole then has to be properly

guyed into position.

The first face of the section is raised. To raise

the second face of this section it is necessary to

slide    the   foot   of   the    gin    on    the   strut   to    the

opposite of the tower. After the two opposite faces

are raised, the lacing on the other two sides is

bolted   up.   The    last    lift     raises    the   top   of    the

towers. After the tower top is placed and all side

of the lacings have been bolted up, all the guys are

thrown off except one which is used to lower the gin

pole.    Sometimes    whole      one    face    of   the   tower   is

assembled on the ground, hoisted and supported in

position. The opposite face is similarly assembled

and hoisted and then bracing angles connecting these

two faces are fitted.
4.1.3   Ground assembly method

                                                                  Back to contents page

         This    method     consists      of      assembling          the     tower      on

         ground,     and    erecting         as      a     complete          unit.      The

         complete tower is assembled in a horizontal position

         on even ground, at some distance from tower footing.

         The tower is assembled in a linewise position to

         allow     the    cross-arms         to     be        fitted.    On       sloping

         ground, however elaborate packing of the low side is

         essential       before      assembly            commences.          After      the

         assembly is complete the tower is picked up from the

         ground with the help of a crane and carried to its

         location and set on its foundation. For this method

         of erection, a level piece of ground close to the

         footing    is     chosen      for     the       tower     assembly.            This

         method is not useful when the towers are large and

         heavy    and    the     foundations         are       located       in    arable

         land    where     building     and       erecting        complete         towers

         would    cause     damage      to     large          areas     or    in       hilly

         terrain    where      the     assembly          of    complete       tower      on

         slopping ground may not be possible and it may be

         difficult to get crane into position to raise the

         complete tower.

         In   India,      this    method       is    not        generally         adopted

         because of prohibitive cost of mobile crane, and

         non-availability         of    good        approach          roads       to    the
location.

4.1.4   Helicopter method

                                                                 Back to contents page

         n the helicopter method, the transmission tower is

         erected in sections. For example bottom section is

         first lifted on to the stubs and then upper section

         is lifted and bolted to the first section and the

         process    is    repeated         till       the    complete     tower       is

         erected.      Sometimes      a    complete          assembled       tower    is

         raised with the help of a helicopter. Helicopters

         are also used forlifting completely assembled towers

         with guys from the marshalling yards, where these

         are fabricated and then transported one by one to

         line location. The helicopter hovers over the line

         location      while    the    tower      is        securely    guyed.       The

         ground crew men connect and tighten                     the tower guyed

         and as soon as the tie lines are bolted                         tight, the

         helicopter disengages and return to the marshalling

         yards   for     another      tower.      This        method    is    adopted

         particularly          when       the     approach         is     extremely

         difficult.

4.2     Earthing

                                                                 Back to contents page

         Once    the     geometry         of    the     tower     and    the     line

         insulation level are fixed, the one factor which

         affects the lightning performance of a line that can

         be controlled during the construction phase of the
line,       is      the       Tower-footing         resistance.

        Consequently, this should be measured during this

        phase of the work and, if necessary, extra earthing

        provided. The measured resistance alters if the soil

        conditions change due to seasonal variations.

        When the footing resistance exceeds a desired value

        from the lightning protection point of view, the

        towers are earthed generally with pipe type and, in

        special cases, with counterpoise type earthing.                 In

        the former case, a 25mm diameter galvanised iron

        pipe,   3,050mm     long,    is    used   with   6.5mm   diameter

        holes drilled at 150mm            apart to facilitate ingress

        of moisture, and is surrounded by a layer of finely

        broken coke of 25mm granular size and salt.

        The earthing should be done in accordance with the

        stipulations made in IS:3043-1972 and IS:5613 (Part

        II/Section 1)-1976.

        The general earthing arrangement is shown in Figures

        4.9   and   4.10.    Where    the    tower   stands      on   rock,

        efforts should be made to obtain a good ground by

        carrying a length of galvanised steel tape from the

        tower leg to the      pipe driven in soil, at as short a

        distance from the tower as possible. The connecting

        tape is burried in a groove cut in the rock surface

        and   adequately protected from damage.

4.2.1   Measurement of Tower Footing Resistance

        The megger can be used in two ways to measure the
resistivity of the soil, namely, the three point

method    and       the   four-point         method.       The    four-point

method is simpler and more accurate and                          is    briefly

described below.

a)      Soil Resistivity

        Four    similar        electrodes          are    burried      in   the

        earth to a depth B at equal distances A from

        one    another     in     a    straight          line.   The    megger

        connections are shown in Figure 4.11. If the

        crank of the instrument is then rotated at the

        stipulated         speed       (usually           100    rpm),      the

        resistance        R,    as    read    on    the     scale,     is   the

        resistance        of     the       earth     between          the   two

        equipotential surfaces with which P1 and P2                         are

        in contact.

        If the depth of the electrode in soil B (in

        cm)    is     small      in        comparison       with       A,   the

        resistivity        of        the    soil     is     given      by   the

        following expression.

      2x22 x AxR
P =   -----------
          7

Where

P = earth resistivity in ohms/cm3

A = spacing between the electrodes in cm, and

R = resistance in ohms as read on the megger.

For all practical purposes, A should be at least

twenty times that of B.
b)   Tower Footing Resistance

     For     measuring     tower      footing       resistance,

     Terminal C-1 of megger shall be connected with

     tower leg instead of electrode C-1. The value

     of    resistance    read   on   the   megger    multiplied

     with multiplying factor gives the tower footing

     resistance in ohms.
4.3     Tack welding :-

                                                        Back to contents page

         All bolts/nuts below waist level in single circuit

         tower or bottom cross arm in Double circuit tower,

         shall   be    tackwelded       to   prevent    theft   of     tower

         members.

         Two 10mm thick welding tacks should be done on each

         bolt & nut in the diagonally opposite direction by

         suitably selecting welding electrods of size 1.6mm

         to 2.5mm equivalent to over cord-S, code AWS-E6013

         (Advani-Oerlikon).        After     removing   slag    over    tack

         welding,     zinc    rich       (90%    zinc    content)       cold

         galvanising paint equivalent to epilux-4 of Berger

         Paint shall be applied on the welding.

4.4     Permissible tolerances in tower erection

                                                        Back to contents page

         As per IS;5613 (Part 3/Sec.2) :1989, the following

         tolerances in tower erection are permitted:

4.4.1    No member of a tower shall be out of straightness

         by   more    than   one   in    1000.   Members    failing      the

         requirements shall be straightened before erection

         in a manner that shall not damage their properties

         or the protective finish.

4.4.2    The tower shall not be out of vertical by more than

         1 in 360 before stringing is carried out.
Annexure - E/1

                                                Back to contents page

            POWER GRID CORPORATION OF INDIA LIMITED

                    (CONSTRUCTION MANAGEMENT)

                        LINE CONSTRUCTION

                        ERECTION ACTIVITY

Tools & plants reqd. for Tower erection gang



1.   Ginpole/Derric Pole 75/100mm

     dia. and of length 8.5-9m.             2nos.

2.   Polypropylene rope                     25mm dia. 700 m.

                                            19mm dia.1000 m.

3.   Single sheave pulley                   Closed type    8 nos.

4.   Crow Bars(25mm dia and

     1.8m length)                           16 nos.

5.   Spanners,(both Ring and Flat)

     Hammers,Slings,(16mm dia.and

     1m length), hooks (12mm dia)

     D shackle,Tommy Bars.                  As per reqt.

6.   Tents,Buckets,Water drums, camping,

     cots, tables, chairs, and petromax

     etc.                                   As per reqt.

7.   D Shackle 7.6 cm (3 in.)               6 nos.



8.   Hexagonal box spanner with fixed

     liver and end of the liver

     pointed to use                         Reqd. sizes
hole bar.                            Each size 6 nos.

9.   Safety equipments :

     i.     Safety helmets                40 nos.

     ii.   Safety belts                   10 nos.

     iii. Safety shoes                    50 nos.

     iv.   Welding Goggles                2 nos.

     v.    First Aid Box                  1 no.

Note :     The quantity of safety equipments may be changed as

per manpower engaged.
Annexure - E/2

                                                      Back to contents page

              POWER GRID CORPORATION OF INDIA LIMITED

                       (CONSTRUCTION MANAGEMENT)

                         CONSTRUCTION ACTIVITY

                         MANPOWER REQUIREMENT

                                  FOR

                          TOWER ERECTION GANG



One Engineer shall be earmarked exclusively for the work of

Tower Erection being carried out by different gangs.

Following manpower is required for each Tower Erection gang.

1)   Supervisor                              1 No.

2)   Fitter                                  8 Nos.

3)   Skilled workers                         12 Nos.

4)   Unskilled workers                       20 Nos.

Note: Average output per gang per month will be approximately

80   MT.   The   man   power   may   be   regulated    depending     upon

requirements
Chapter-5
Guide Lines
--------------------------------------------------------------------------
                                                                                  CHAPTER
                                                                                  FIVE
--------------------------------------------------------------------------

                                                                           GUIDELINES

                     GL-1 PRE-ERECTION CHECKS

                                                          Back to contents page

NAME OF LINE___________________                   LOCATION NO. _____________

NAME OF CONTRACTOR_____________                   TYPE OF TOWER ____________

Before taking up tower erection works, following preparations

need to be made.

1.1        Foundation checks

1.1.1      Tower erection work shall be taken up only after

           concreting      is   cured     and     set    for    14        days    as    per

           technical specifications. This is essential so that

           concrete    gains      sufficient        strength         to      withstand

           various     forces       acting        during       and        after     tower

           erection.

1.1.2      The   stubs     shall     be     set    such    that       the        distance

           between the stubs and their alignment and slop is in

           accordance      with     the     approved       drawings         so     as    to

           permit assembling of superstructures without undue

           strain or       distortion in any part of the structure.

           To    ensure     above    following          checks       are     necessary

           before tower erection.

           (a)   Level of all the four stubs shall be on one

                 horizontal         plane    in order to ensure                   correct

                 and      smooth tower erection. The level of top of
the stubs shall be checked to ensure that these

               are on one horizontal plane.

        (b)    Distance       between    the    stubs    shall    be    as   per

               approved       drawing    so    that    correct    and    smooth

               tower     erection       is    achieved.    Hence       distance

               (diagonals) between the stubs are measured and

               verified for its correctness.

1.1.3   Revetment/Benching           wherever         required     shall     be

        completed so that there is no danger to foundation

        during and after tower erection. However, if it is

        felt    that, non-completion            of Revetment/Benching is

        not going to harm foundation during and after tower

        erection, the same may be programmed and executed on

        later date.

1.2     Tower materials

1.2.1   It     shall     be    ensured        that    approved     structural

        drawings and Bill of Material with latest revision

        are available at           site to facilitate tower erection.

        Preferably one set of structural drawings properly

        laminated and Bill of Material in Bound Book shall

        be available at site with each gang.



1.2.2   All tower Members shall be available at site as per

        approved       Bill   of    Material     and    shall    be    serially

        placed on ground in order of erection requirement.

1.2.3   It shall be checked that no tower Member, Nut/Bolt,

        accessories are rusted, bent or damaged.
1.2.4   All    required       sizes    of    Bolts/Nuts,        spring/packing

        washers in required quantity are available at site.

1.2.5   If    any    defects    in    protective       surface        finish    are

        found in case of hot dip galvanised members, the

        damage shall be repaired by applying two coats of

        zinc-rich      paint    having       atleast      90%   zinc    contents

        conforming to I.S. code.

1.2.6   Members bent in transit shall be straightened such

        that the protective surface finish is not damaged.

1.3     Tools & plants

1.3.1   All    the    tools    and    plants       required     for    safe    and

        efficient      tower     erection       shall      be     available      at

        site.A list of necessary tools                 and plants is given

        at    Annexure-E/1.

1.3.2   All the tools and plants shall be tested as per

        approved        safety        norms         and      relevant          test

        certificates shall            be     available.         In addition to

        above,       periodic testing         of tools and plants shall

        be carried       out    and its safe working capacity shall

        be worked out.

1.4     Personal protective equipments

1.4.1   All the persons working on tower shall wear safety

        helmet, safety belt and safety shoes,.Similarly all

        the    persons    working      on    ground       shall      wear   safety

        helmet and safety shoes. List of personal protective

        equipments is given at Annexure-E/1.

1.4.2   Safety      equipments       shall    be    tested      as    per   safety
norms      and    necessary        test    certificate     shall     be

        available. Also, a periodic check shall be carried

        out to ensure requisite strength.

1.5     Manpower

1.5.1   Manpower engaged for the purpose of tower erection

        shall      be    skilled   and     competent    enough     to    ensure

        safe, smooth and efficient tower erection activity.

1.5.2   A   list    of    necessary      manpower    required      for   tower

        erection is given at Annexure-E/2.

1.6     Miscellaneous

1.6.1   If there is any LT/HT power line near the vicinity

        of tower        erection, necessary shutdown of the               power

        line shall be obtained in writing from the concerned

        Agency in order to avoid electrical hazards caused

        by accidental touching of stay/Guy ropes with power

        line.

1.6.2   In order to develop and maintain cordial relations

        with    field      owners,    it    is    desired   that   crop/tree

        compensation of foundation is paid to the owners

        before taking up tower erection works.
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower
design of tower

More Related Content

What's hot

transmission line tower design
transmission line tower designtransmission line tower design
transmission line tower designkunalbhattgecd
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Designmaylene san luis
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)ahsanrabbani
 
Steel Structural Design Manual for Engineers
Steel Structural Design Manual for EngineersSteel Structural Design Manual for Engineers
Steel Structural Design Manual for EngineersPrem Chand Sharma
 
Indian standard specification for high strength structural bolts
Indian standard specification for high strength structural boltsIndian standard specification for high strength structural bolts
Indian standard specification for high strength structural boltsJisha John
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Ankit Singh
 
Reinforced concrete deck girder bridge
Reinforced concrete deck girder bridgeReinforced concrete deck girder bridge
Reinforced concrete deck girder bridgeMarian Joyce Macadine
 
Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920INTEZAAR ALAM
 
Microwave Tower Presentation.ppt
Microwave Tower Presentation.pptMicrowave Tower Presentation.ppt
Microwave Tower Presentation.pptRuturajJadhav25
 
Design of steel structures Introduction
Design of steel structures IntroductionDesign of steel structures Introduction
Design of steel structures IntroductionPrakash Kumar Sekar
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Shekh Muhsen Uddin Ahmed
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C BeamAr. Aakansha
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteMAHFUZUR RAHMAN
 
Design of tension members
Design of tension membersDesign of tension members
Design of tension membersSabna Thilakan
 
Design and Analysis of Transmission Tower at Allahabad
Design and Analysis of Transmission Tower at AllahabadDesign and Analysis of Transmission Tower at Allahabad
Design and Analysis of Transmission Tower at AllahabadAbhijit Kumar
 

What's hot (20)

transmission line tower design
transmission line tower designtransmission line tower design
transmission line tower design
 
Introduction of Reinforced Concrete Design
Introduction of Reinforced Concrete DesignIntroduction of Reinforced Concrete Design
Introduction of Reinforced Concrete Design
 
Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)Design of steel structure as per is 800(2007)
Design of steel structure as per is 800(2007)
 
Steel Structural Design Manual for Engineers
Steel Structural Design Manual for EngineersSteel Structural Design Manual for Engineers
Steel Structural Design Manual for Engineers
 
Indian standard specification for high strength structural bolts
Indian standard specification for high strength structural boltsIndian standard specification for high strength structural bolts
Indian standard specification for high strength structural bolts
 
Is 1893-part2-2014
Is 1893-part2-2014Is 1893-part2-2014
Is 1893-part2-2014
 
Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)Design of t beam bridge using wsm(2)
Design of t beam bridge using wsm(2)
 
Monopole
MonopoleMonopole
Monopole
 
Reinforced concrete deck girder bridge
Reinforced concrete deck girder bridgeReinforced concrete deck girder bridge
Reinforced concrete deck girder bridge
 
Swing angle
Swing angleSwing angle
Swing angle
 
Ductile detailing IS 13920
Ductile detailing IS 13920Ductile detailing IS 13920
Ductile detailing IS 13920
 
Microwave Tower Presentation.ppt
Microwave Tower Presentation.pptMicrowave Tower Presentation.ppt
Microwave Tower Presentation.ppt
 
Design of beams
Design of beamsDesign of beams
Design of beams
 
Wind load
Wind  loadWind  load
Wind load
 
Design of steel structures Introduction
Design of steel structures IntroductionDesign of steel structures Introduction
Design of steel structures Introduction
 
Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)Reinforced slab bridge design(AASHTO allowable stress design method)
Reinforced slab bridge design(AASHTO allowable stress design method)
 
Design of R.C.C Beam
Design of R.C.C BeamDesign of R.C.C Beam
Design of R.C.C Beam
 
Shear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concreteShear, bond bearing,camber & deflection in prestressed concrete
Shear, bond bearing,camber & deflection in prestressed concrete
 
Design of tension members
Design of tension membersDesign of tension members
Design of tension members
 
Design and Analysis of Transmission Tower at Allahabad
Design and Analysis of Transmission Tower at AllahabadDesign and Analysis of Transmission Tower at Allahabad
Design and Analysis of Transmission Tower at Allahabad
 

Similar to design of tower

OH_constandard_Internet.pdf
OH_constandard_Internet.pdfOH_constandard_Internet.pdf
OH_constandard_Internet.pdfRaufAhmed29
 
Tes p-122.05-pi-r0
Tes p-122.05-pi-r0Tes p-122.05-pi-r0
Tes p-122.05-pi-r0Ibrahim Ali
 
IRJET- Comparative Study of Dynamic Analysis of Transmission Towers
IRJET- Comparative Study of Dynamic Analysis of Transmission TowersIRJET- Comparative Study of Dynamic Analysis of Transmission Towers
IRJET- Comparative Study of Dynamic Analysis of Transmission TowersIRJET Journal
 
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Deepak Saxena
 
HV tower design 3
HV tower design 3HV tower design 3
HV tower design 3Thy Khy
 
Dynamic Response of Offshore Articulated Tower-Under Airy and Stokes Theories
Dynamic Response of Offshore Articulated Tower-Under Airy and Stokes TheoriesDynamic Response of Offshore Articulated Tower-Under Airy and Stokes Theories
Dynamic Response of Offshore Articulated Tower-Under Airy and Stokes TheoriesIRJET Journal
 
Analysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docxAnalysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docxAdnan Lazem
 
Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Pratap Bhunia
 
instructionss.docxjust to make sure againi need u to ext.docx
instructionss.docxjust to make sure againi need u to ext.docxinstructionss.docxjust to make sure againi need u to ext.docx
instructionss.docxjust to make sure againi need u to ext.docxdirkrplav
 
IRJET- Design, Modeling and Analysis of a Vacuum Chamber for High Speed T...
IRJET-  	  Design, Modeling and Analysis of a Vacuum Chamber for High Speed T...IRJET-  	  Design, Modeling and Analysis of a Vacuum Chamber for High Speed T...
IRJET- Design, Modeling and Analysis of a Vacuum Chamber for High Speed T...IRJET Journal
 
Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)Ibrahim Ali
 
Tes p-122.05-pii-r0 (1)
Tes p-122.05-pii-r0 (1)Tes p-122.05-pii-r0 (1)
Tes p-122.05-pii-r0 (1)Ibrahim Ali
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation Tejveer Choudhary
 
IRJET- Review Paper on Comparative Study of Dynamic Analysis of Transmission ...
IRJET- Review Paper on Comparative Study of Dynamic Analysis of Transmission ...IRJET- Review Paper on Comparative Study of Dynamic Analysis of Transmission ...
IRJET- Review Paper on Comparative Study of Dynamic Analysis of Transmission ...IRJET Journal
 
Design of PVC Bladed Horizontal Axis Wind Turbine for Low Wind Speed Region
Design of PVC Bladed Horizontal Axis Wind Turbine for Low Wind Speed RegionDesign of PVC Bladed Horizontal Axis Wind Turbine for Low Wind Speed Region
Design of PVC Bladed Horizontal Axis Wind Turbine for Low Wind Speed RegionIJERA Editor
 
Experimental Study on Tuned Liquid Damper and Column Tuned Liquid Damper on a...
Experimental Study on Tuned Liquid Damper and Column Tuned Liquid Damper on a...Experimental Study on Tuned Liquid Damper and Column Tuned Liquid Damper on a...
Experimental Study on Tuned Liquid Damper and Column Tuned Liquid Damper on a...IRJET Journal
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission linesfiraoltemesgen1
 
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...IJCSIS Research Publications
 
Cableway guidance note 1 design
Cableway guidance note 1   designCableway guidance note 1   design
Cableway guidance note 1 designhydrologyproject0
 

Similar to design of tower (20)

OH_constandard_Internet.pdf
OH_constandard_Internet.pdfOH_constandard_Internet.pdf
OH_constandard_Internet.pdf
 
Tes p-122.05-pi-r0
Tes p-122.05-pi-r0Tes p-122.05-pi-r0
Tes p-122.05-pi-r0
 
IRJET- Comparative Study of Dynamic Analysis of Transmission Towers
IRJET- Comparative Study of Dynamic Analysis of Transmission TowersIRJET- Comparative Study of Dynamic Analysis of Transmission Towers
IRJET- Comparative Study of Dynamic Analysis of Transmission Towers
 
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
Analysis-And-Design-Of-220kv-Transmission-Line-Tower-In-Different-Zones-I-&-V...
 
HV tower design 3
HV tower design 3HV tower design 3
HV tower design 3
 
Dynamic Response of Offshore Articulated Tower-Under Airy and Stokes Theories
Dynamic Response of Offshore Articulated Tower-Under Airy and Stokes TheoriesDynamic Response of Offshore Articulated Tower-Under Airy and Stokes Theories
Dynamic Response of Offshore Articulated Tower-Under Airy and Stokes Theories
 
Analysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docxAnalysis and Design of Power Transmission Lines Steel Towers.docx
Analysis and Design of Power Transmission Lines Steel Towers.docx
 
Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...Engineering Final Year Project Report on "Electrical Safety and Protection of...
Engineering Final Year Project Report on "Electrical Safety and Protection of...
 
instructionss.docxjust to make sure againi need u to ext.docx
instructionss.docxjust to make sure againi need u to ext.docxinstructionss.docxjust to make sure againi need u to ext.docx
instructionss.docxjust to make sure againi need u to ext.docx
 
IRJET- Design, Modeling and Analysis of a Vacuum Chamber for High Speed T...
IRJET-  	  Design, Modeling and Analysis of a Vacuum Chamber for High Speed T...IRJET-  	  Design, Modeling and Analysis of a Vacuum Chamber for High Speed T...
IRJET- Design, Modeling and Analysis of a Vacuum Chamber for High Speed T...
 
Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)Tes p-122.10-r0 (1)
Tes p-122.10-r0 (1)
 
Tes p-122.05-pii-r0 (1)
Tes p-122.05-pii-r0 (1)Tes p-122.05-pii-r0 (1)
Tes p-122.05-pii-r0 (1)
 
Training at 132 kv substation
Training at 132 kv substation Training at 132 kv substation
Training at 132 kv substation
 
IRJET- Review Paper on Comparative Study of Dynamic Analysis of Transmission ...
IRJET- Review Paper on Comparative Study of Dynamic Analysis of Transmission ...IRJET- Review Paper on Comparative Study of Dynamic Analysis of Transmission ...
IRJET- Review Paper on Comparative Study of Dynamic Analysis of Transmission ...
 
Design of PVC Bladed Horizontal Axis Wind Turbine for Low Wind Speed Region
Design of PVC Bladed Horizontal Axis Wind Turbine for Low Wind Speed RegionDesign of PVC Bladed Horizontal Axis Wind Turbine for Low Wind Speed Region
Design of PVC Bladed Horizontal Axis Wind Turbine for Low Wind Speed Region
 
Experimental Study on Tuned Liquid Damper and Column Tuned Liquid Damper on a...
Experimental Study on Tuned Liquid Damper and Column Tuned Liquid Damper on a...Experimental Study on Tuned Liquid Damper and Column Tuned Liquid Damper on a...
Experimental Study on Tuned Liquid Damper and Column Tuned Liquid Damper on a...
 
tower spotting
tower spottingtower spotting
tower spotting
 
Chapter 4 mechanical design of transmission lines
Chapter 4  mechanical design of transmission linesChapter 4  mechanical design of transmission lines
Chapter 4 mechanical design of transmission lines
 
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
ACSR Overhead Transmission lines Modeling Considering Sag-Tension Estimation ...
 
Cableway guidance note 1 design
Cableway guidance note 1   designCableway guidance note 1   design
Cableway guidance note 1 design
 

design of tower

  • 1. FOR INTERNAL CIRCULATION ONLY user’s manual of Construction (part one) Transmission Lines Volume-4 Tower Erection Construction Management Power Grid Corporation of India Limited (A Government of India Enterprise)
  • 2. DOCUMENT CODE NO. : CM/TL/TOWER ERECTION/96 JUNE, 1996
  • 3. FROM THE DESK OF DIRECTOR (PERSONNEL) Four “M’s” viz. men, material, machine & money are vital to run an organization. However the key to success of the organization lies the way our employees structure and manage the construction, operation and maintenance activities of transmission system. Construction activitiy in transmission system is an important aspect and time, quality and cost are it’s critical parameters. Experience, no doubt, is a great teacher and a valuable asset. However, the knowledge of underlined principles of sound working is also equally important. Preparation of these user’s manuals is the work of our experienced senior field staff and I find these to be very useful to our site personnel. These manuals for transmission lines (Vol. 1 2 & 4) alongwith SFQP (Vol. 1) will be of immense help to our line staff to manage their resources in a more efficient and systematic way to achieve high quality and reduced time. I find sincere efforts have gone into preparation of these manuals for which I congratulate Construction Management team and I am sure the authors will continue their efforts to bring out more and more such manuals. (R.P. SINGH)
  • 4. CONTENTS CHAPTER-I TOWER CONFIGURATION 1.1 PURPOSE OF TRANSMISSION TOWER 1.2 FACTORS GOVERNING TOWER CONFIGURATION 1.3 TOWER HEIGHT 1.4 ROLE OF WIND PRESSURE 1.5 MAXIMUM & MI8NIMUM TEMPERATURE 1.6 LOADING OF TOWER CHAPTER-2 TYPES OF TOWERS 2.1 CLASSIFICATION ACCORDING TO NUMBER OF CIRCUITS 2.2 CLASSIFICATION ACCORDING TO USE 2.3 400KV SINGLE CIRCUIT TOWERS 2.4 400KV DOUBLE CIRCUIT TOWERS 2.5 RIVER CROSSING TOWERS 2.6 RAILWAY CROSSING TOWERS 2.7 HIGH WAY CROSSING TOWERS 2.8 TRANSPOSITION TOWERS 2.9 MULTI CIRCUIT TOWERS 2.10 TOWER EXTENSIONS 2.11 LEG EXTENSIONS
  • 5. 2.12 TRUNCATED TOWERS 2.13 WEIGHT OF DIFFERENT TYPES OF TOWERS CHAPTER-3 TOWER FABRICATION 3.1 GENERAL 3.2 BOLTING 3.3 WASHERS 3.4 LAP AND BUTT JOINTS 3.5 GUSSET PLATES 3.6 BRACING TO LEG CONNECTIONS 3.7 CONNECTION TO REDUNDANT MEMBERS 3.8 CROSS-ARM CONNECTIONS 3.9 STEP-BOLTS AND LADDERS 3.10 ANTI-CLIMBING DEVICES 3.11 DANGER AND NUMBER PLATES 3.12 PHASE AND CIRCUIT PLATES 3.13 BIRD GUARD 3.14 AVIATION REQUIREMENT 3.15 PACKING, TRANSPORTATION AND STORAGE OF TOWER PARTS CHAPTER-4 METHODS OF ERECTION 4.1 GENERAL
  • 6. 4.1.1 BUILT UP METHOD 4.1.2 SECTION METHOD 4.1.3 GROUND ASSEMBLY 4.1.4 HELICOPTER METHOD 4.2 EARTHING 4.3 TRACK WELDING 4.4 PERMISSIBLE TOLERANCES IN TOWER ERECTION ANNEXURE-E/1 - TOOLS & PLANTS REQUIRED FOR TOWER ERECTION GANG ANNEXURE-E/2 - MANPOWER REQUIREMENT FOR TOWER ERECTION GANG CHAPTER-5 GUIDE LINES FOR SUPERVISION GL-1 PRE-ERECTION CHECKS GL-2 CHECKS DURING TOWER ERECTION GL-3 TIGHTENING AND PUNCHING GL-4 FIXING OF TOWER ACCESSORIES GL-5 EARTHING GL-6 PRE-STRINGING TOWER CHECKS CHAPTER-6 STANDARDISATION OF TOWER DESIGN
  • 7. 6.1 INTRODUCTION 6.2 STANDARDISATION IN POWERGRID CHAPTER-7 FORMAT OF TOWER ERECTION CHECKING
  • 9. ___________________________________________________________________________ CHAPTER ONE _________________________________________________________ TOWER CONFIGURATION 1.1 Purpose of transmission tower Back to contents page The structures of overhead transmission lines, comprising essentially the supports and foundations, have the role of keeping the conductors at the necessary distance form one another and form earth, with the specified factor of safety to facilitate the flow of power through conductor form one point to another with reliability, security and safety. 1.2 Factors governing tower configuration Back to contents page 1.2.1 Depending upon the requirements of transmission system, various line configurations have to be considered ranging from single circuit horizontal to double circuit vertical structures with single or V-strings in all phase, as well as any combination of these. 1.2.2 The configuration of a transmission line tower depends on: (a) The length of the insulator assembly. (b) The minimum clearances to be maintained between conductors and between conductor and tower. (c) The location of ground wire or wires with respect to the outermost conductor. (d) The mid span clearance required from considerations of the dynamic behavior of conductors and lightning protection of the line. (e) The minimum clearance of the lower conductor above ground level. 1.3 Tower height
  • 10. Back to contents page The factors governing the height of a tower are: (a) Minimum permissible ground clearance (H1) (b) Maximum sag (H2). (c) Vertical spacing between conductors (H3). (d) Vertical clearance between ground wire and top conductor (H4). Thus the total height of the tower is given by H = H1 + H2 + H3 + H4 in the case of a double circuit tower with vertical configuration of conductors as shown in Fig. 1.1. 1.3.1 Minimum permissible ground clearance From safety considerations, power conductors along the route of the transmission line should maintain clearances to ground in open country, national highway, rivers, railway tracks, tele-communication lines, other power lines etc. as laid down in the Indian Electricity Rule or standards or code of practice in vogue. 1.3.2 Maximum sag of Lowermost Conductor The size and type of conductor, wind and climatic Conditions of the region and span length determine the conductor sag and tensions. Span length is fixed from economic considerations. The maximum sag for conductor span occurs at the maximum temperature and still wind conditions. This maximum value of sag is taken into consideration in fixing the overall height of the steel structures. In snow regions, the maximum sag may occur even at 0OC with conductors loaded with ice in still wind conditions. While working out tension in arriving at the maximum sag, the following stipulations laid down, in I.E. Rules (1956) are to be satisfied. (i) The minimum factor of safety for conductors shall be based on their ultimate tensile strength. (ii) The conductor tension at 32OC (90OF) without external load shall not exceed the following percentages of the ultimate tensile strength of the conductor. Initial unloaded tension . . 35 percent Final Unloaded tension . . 25 Percent
  • 11. In accordance with this stipulation, the maximum working tension under stringent loading conditions shall not exceed 50 percent of the ultimate tensile strength or conductor. Sag-Tension computations made for final stringing of the conductors, therefore, must ensure that factor of safety of 2 and 4 are obtainable under maximum loading condition and every day loading condition, respectively.
  • 12.
  • 13. 1.3.3 Spacing of conductors The spacing of conductors is determined by considerations which are partly electrical and partly mechanical. The material and diameter of the conductors should also be considered when deciding the spacing, because a smaller conductor especially if made of aluminum, having a small weight in relation to the area presented to a cross wind, will swing synchronously (in phase) with the wind, but with long spans and small wires, there is always the possibility of the conductor swinging non- synchronously, and the size of the conductor and the maximum sag at the centre of span are factors which should be taken into account in determining distance apart at which they should be strung. 1.3.4 Vertical clearance between ground wire and top conductor. This is governed by the angle of shielding i.e. the angle which the line joining the ground wire and the outermost conductor makes with the vertical, required for the interruption of direct lightning strokes at the ground and the minimum mid span clearance between the ground wire and the top power conductor. The shield angle varies from about 20 degrees 30 degrees, depending on the configuration of conductors and the number of ground wires (one or two) provided. 1.4 Role of wind pressure Back to contents page The wind load constitutes an important and major component of the total loading on towers and so a basic understanding of the computation of wind pressures is useful. In choosing the appropriate wind velocity for the purpose of determining the basic wind pressure, due consideration should be given to the degree of exposure appropriate to the location and also to the local meteorological data. The country has been divided inot six wind zones of different wind speeds. The basic wind speeds for the six wind zones are: Wind Zone Basic wind speed-m/s 1 33 2 39 3 44 4 47 5 50 6 55
  • 14. Fig. 1.2 shows basic wind speed map of India as applicable at 10m height above mean ground level for the six wind zones. In case the line traverses on the border of different wind zones, the higher wind speed may be considered. 1.4.1 Variation of wind speed with height At ground level, the wind intensity is lower and air flow is turbulent because of friction with the rough surfaces of the ground. After a certain height, the frictional influence of the ground becomes negligible and wind velocity increases with height. 1.4.2 Wind force on structure The overall load exerted by wind pressure, on structures can be expressed by the resultant vector of all aerodynamic forces acting on the exposed surfaces. The direction of this resultant can be different from the direction of wind. The resultant force acting on the structure is divided into three components as shown in Figure 1.3. These are : (a) A horizontal component in the direction of wind called drag force FD. (b) A horizontal component normal to the direction of wind called horizontal lift force FL H. (c) A vertical component normal to the direction of wind called the vertical lift force FLV.
  • 15.
  • 16.
  • 17. 1.5 Maximum & minimum temperature :- Back to contents page A knowledge of the maximum and the minimum temperature of the area traversed by transmission line is necessary for calculating sag and tensions of conductors and ground wires, thereby deciding the appropriate tower design. The maximum and minimum temperature normally vary for different localities under different diurnal and seasonal conditions. The absolute maximum and minimum temperature which may be expected in different localities in the country are indicated in the map of India in Fig.1.4 and 1.5 respectively. The temperature indicated n these maps are the air temperatures in shade. The absolute maximum temperature values are increased suitably to allow for the sun’s radiation, heating effect of current, etc. in the conductor. The tower may be designed to suit the conductor temperature of 75 degree C (max) for ACSR and 85 degree C (max) for aluminum alloy conductor. The maximum temperature of ground wore exposed to sun may be taken as 53 degree C.
  • 18.
  • 19.
  • 20. 1.6 Loading of transmission line towers Back to contents page 1.6.1 As per revision o IS;802 regarding materials, loads and permissible stresses in transmission line owes, concept o reliability, security and safety have been introduced. (a) Reliability The Reliability that a transmission system performs a given task, under a set of conditions, during a specified time. Reliability is thus a measure of the success of a system in accomplishing task. The complement to reliability is the probability of failure or unreliability. In simple terms, the reliability may be defined as the probability that a given item will indeed survive a given service environment and loading for a prescribed period of item. (b) Security:- The ability of a system to be protected from a major collapse such as cascading effect, if a failure is triggered in a given component. Security is a deterministic concept as opposed to reliability which is a probabilistic concept. (c) Safety:- The ability of a system not to cause human injuries or loss of lives. It relates mainly to protection of workers during construction and maintenance operation. The safety of public and environment in general is covered by National regulations. 1.6.2 Nature of loads on Transmission Tower Transmission lines are subjected to various loads during their life time. These are classified into three distinct categories, namely: (a) Climatic loads:- Which relates to reliability requirements. (b) Failure containment loads:- Which relates to security requirements. (c) Construction & maintenance loads:- Which relates to safety requirements. 1.6.3 Computation of various loads on towers
  • 21. The loads on of various loads on towers consist of three mutually perpendicular systems of loads acting vertical, normal to the direction of the line, and parallel to the direction of the line. It has been found convenient in practice to standardise the method of listing and dealing with loads as under: Transverse load Longitudinal load Vertical load Torsional shear Weight of structure Each of the above loads is dealt with separately below: (a) Transverse load due to wind on conductors and ground wire The conductor and ground wire support point loads are made up of the following components: (i) Wind on the bare (or ice-covered) conductor / ground wire over the wind span and wind on insulator string. (ii) Angular component of line tension due to an angle in the line (Figure 1.7). The wind span is the sum of the two half spans adjacent to the support under consideration. The governing direction of wind on conductors for an angle conditions is assumed to be parallel to the longitudinal axis of the cross-arms (Fig.1.8). Since the wind is blowing on reduced front, it could be argued that this reduced span should be used for the wind span. In practice, however, since the reduction in load would be relatively small, it is usual to employ the full span.
  • 22.
  • 23.
  • 24. (b) Transverse load due to line deviation The load due to an angle of deviation in the line is computed by finding the resultant force produced by the conductor tensions (Fig. 1.7) in the two adjacent spans. It is clear from the figure that the total transverse load = 2T Sin Ø/2 where Ø is the angle of deviation and T is the conductor tension. (c) Wind load on tower In order to determine the wind load on tower, the tower is divided into different panels having a height ‘h’. These panels should normally be taken between the intersections of the legs and bracings. 1.6.3.2 Longitudinal load (a) Longitudinal load acts on the tower in a direction parallel to the line (Fig. 1.6B) and is caused by unequal conductor tensions acting on the tower. This unequal tension in the conductors may be due to deadending of the tower, broken conductors, unequal spans, etc. and its effect on the tower is to subject the tower to an overturning moment, torsion, or a combination of both. In the case of dead-end tower or a tower with tension strings with a
  • 25. broken wire, the full tension in the conductor will act as a longitudinal load, whereas in the case of a tower with suspensions strings, the tension in the conductor is reduced to a certain extent under broken-wire conditions as the string swings away from the broken span and this results in a reduced tension in the conductor and correspondingly a reduced longitudinal load on the tower. (b) Torsional load: The longitudinal pull caused by the broken wire condition imposes a torsional movement, T, on the tower which is equal to the product of unbalanced horizontal pull, P and its distance, from the centre of tower in addition to the direct pull being transferred as equivalent longitudinal shear, P as shown in Fig.1.9. The shear P and the torsional movement T = Pe gets transferred to tower members in the plane ABCD. 1.6.3.3 Vertical Load Vertical load is applied to the ends of the cross-arms and on the found wire peak (Fig.1.6C) and consists of the following vertical downward components: (i) Weight of bare or ice-covered conductor, as specified, over the governing weight span. (ii) Weight of insulators, hardware etc., covered with ice, if applicable. (iii) Arbitrary load to provide for the weight of a man with tools.
  • 26.
  • 27. 1.6.3.4 Weight of structure The weight of the structure like the wind on the structure, is an unknown quantity until the actual design is complete. However in the design of towers, an assumption has to be made regarding the dead weight of towers. The weight will no doubt depend on the bracing arrangement to be adopted, the strut formula used and the quality or qualities of steel used, whether the design is a composite one comprising both mild steel and high tensile steel or make use of mild steel only. However, as a rough approximation, it is possible to estimate the probable tower weight from knowledge of the positions of conductors and ground wire above ground level and the overturning moment. Having arrived at an estimate of the total weight of the tower, the estimated tower weight is approximately distributed between the panels. Upon completion of the design and estimation of the tower weight, the assumed weight used in the load calculation should be reviewed Particular attention should be paid to the footing reactions, since an estimated weight which is too high will make the uplift footing reaction too low. 1.6.3.5 Various loads as mentioned above shall be computed for required reliability, security and safety.
  • 29. -------------------------------------------------------------------------- CHAPTER TWO -------------------------------------------------------------------------- TYPES OF TOWERS 2.1 Classification according to number of circuits Back to contents page The majority of high voltage double circuit transmission lines employ a vertical or nearly vertical configuration of conductors and single circuit transmission lines a triangular arrangement of conductor, single circuit lines, particularly at 400 KV and above, generally employ horizontal arrangement of conductors. The arrangement of conductor and ground wires in these configurations is given at Figure No. 2.1 to Figure No. 2.5. The number of ground wires used on the line depends on the isoceraunic level (number of thunderstorm days/hours per year) of the area, importance of the line, and the angle of coverage desired. Single circuit lines using horizontal configuration generally employ two ground wires, due to the comparative width of the configuration; whereas lines using vertical and offset arrangements more often utilise one ground wire except on higher voltage lines of 400 KV and above, where it is usually found advantageous to string two ground wires, as the phase to phase
  • 30. spacing of conductors would require an excessively high positioning of ground wire to give adequate coverage. Details of different types of 400 KV single circuit and 400 KV double circuit towers are given at Clause No. 2.3 and 2.4.
  • 31.
  • 32.
  • 33.
  • 34.
  • 35. 2.2. Classification according to use Back to contents page Towers are classified according to their use independent of the number of conductors they support. A tower has to withstand the loadings ranging from straight runs up to varying angles and dead ends. To simplify the designs and ensure an overall economy in first cost and maintenance, tower designs are generally confined to a few standard types as follows. 2.2.1 Tangent suspension tower Suspension towers are used primarily on tangents but often are designed to withstand angles in the line up to two degrees or higher in addition to the wind, ice, and broken-conductor loads. If the transmission line traverses relatively flat, featureless terrain, 90 percent of the line may be composed of this type of tower. Thus the design of tangent tower provides the greatest opportunity for the structural engineer to minimise the total weight of steel required. 2.2.2 Angle towers Angle towers, sometimes called semi-anchor towers, are used where the lines makes a horizontal angle
  • 36. greater than two degrees (Figure 2.6). As they must resist a transverse load from the components of the line tension induced by this angle, in addition to the usual wind, ice and broken conductor loads, they are necessarily heavier than suspension towers. Unless restricted by site conditions, or influenced by conductor tensions, angle towers should be located so that the axis of the cross- arms bisects the angle formed by the conductors. Theoretically, different line angles require different towers, but for economy there is a limiting number of different towers which should be used. This number is a function of all the factors which make the total erected cost of a tower line. However, experience has shown that the following angle towers are generally suitable for most of the lines : 1. Light angle - 2 to 150 line deviation 2. Medium angle - 15 to 300 line deviation 3. Heavy angle - 30 to 600 line deviation (and dead end) While the angles of line deviation are for the normal span, the span may be increased up to an optimum limit by reducing the angle of line deviation and vice versa. IS:802 (Part I) - 1977 also recommends the above classification.
  • 37. The loadings on a tower in the case of a 60 degree angle condition and dead-end condition are almost the same. As the number of locations at which 60 degree angle towers and dead-end towers are required are comparatively few, it is economical to design the heavy angle towers both for the 60 degree angle condition and dead-end condition,
  • 38. whichever is more stringent for each individual structural member. For each type of tower, the upper limit of the angle range is designed for the same basic span as the tangent tower, so that a decreased angle can be accommodated with an increased span or vice versa. It would be uneconomical to use 30 degree angle towers in locations where angles higher than 2 degree and smaller than 30 degree are encountered. There are limitations to the use of 2 degree angle towers at higher angles with reduced spans and the use of 30 degree angle towers with smaller angles and increased spans. The introduction of a 15 degree tower would bring about sizable economics. Pilot suspension insulator string - This shall be used if found necessary to restrict the jumper swings to design value at both middle and outer phases. Unequal cross arms - Another method to get over the difficulty of higher swing of Jumper is to have unequal cross arms. 2.3 400 kv single circuit towers Back to contents page The bundled conductors are kept in horizontal configuration with a minimum clearance of 11 mtrs. phase to phase.
  • 39. The latticed parts are fully galvanised. Galvanised hexagonal round head bolts and nuts are used for fastening with necessary spring or plate washers. Normally 4 types of single circuit towers are used as detailed below :- a) "A" type towers : These towers are used as tangent towers for straight run of the transmission line. These are called suspension or tangent towers. These towers can carry only vertical loads and are designed for carrying the weight of the conductor, insulators and other accessories. These towers are also designed for a deviation upto 2 degrees. b)" B" type towers : These towers can be used as sectionalising towers without angle and angle towers from 2 degrees up to 15 degrees deviation. c) " C" type towers These towers can be used for deviations ranging from 15 degrees up to 30 degrees. They are also being used as transposition towers without any angle. d) "D" type towers : These towers can be used as Dead End or anchor towers without any angle on the tower. Also these towers can be used for deviations ranging from 30
  • 40. degree - 60 degree. These towers are usually provided as terminal towers near gantry with slack span on one side or as anchoring tower before major river crossing, power line crossing, railway crossings etc. Fig. 2.8 shows two types of tower configuration for 400 KV single circuit towers. A section of 400 kv single circuit towers is shown in Fig.2.9. 2.4 400 KV Double circuit towers Back to contents page These towers are designed to carry two circuits consisting of 3 phases each, having bundled conductors. Here, the circuits are placed in a vertical configuration. A minimum phase to phase clearance of 8 mtrs. is maintained. A minimum clearance of 11 mtrs. is maintained from one circuit to another. Two earthwires are placed above each circuit in such a way to provide the required shielding angle.
  • 41.
  • 42.
  • 43. Like single circuit towers, these towers are also galvanised, lattice steel type structures designed to carry the tension and weight of the conductor alongwith the insulators, earthwire and its accessories. Normally these towers are identified as P (D/C suspension towers), Q, R & S (D/C tension towers) or as DA, DB, DC and DD respectively. As in the single circuit towers, DA/P towers are used as suspension towers from O degrees-2 degrees deviations. DB/Q,DC/R and DD/S towers are used as tension towers with angle of deviation from 2 degrees-15 degrees, 15 degrees-30 degrees and 30 degrees - 60 degrees respectively. DB towers are also used as sectionalising towers without angle. DC tower is also used as transposition tower without any angle. The Double Circuit towers are used while crossing reserved forest, major river crossings, narrow corridors near switchyards etc. so as to make provision for future transmission lines since the approval from various authorities can be obtained at one time (for example, from forest, aviation authorities etc.) and to minimise expenditure in laying foundations in rivers. Fig.2.8 shows two types of tower configuration for
  • 44. 400 kv double circuit towers. 2.5 River-crossing tower Back to contents page The height and weight of the towers vary considerably depending on the span, minimum clearance above water, ice and wind loads, number of `unbroken' conductors, etc. Usually the governing specification requires that towers employed for crossing of navigable water ways be designed for heavy loading conditions and utilise larger minimum size members than the remainder of the line. In addition to these structural requirements, it is often necessary to limit the height of tall crossing towers because of the hazard they present to aircraft. Fig.2.10 shows a view of 400 kv double circuit River crossing tower. 2.6 Railway crossing tower Back to contents page Angle or dead end towers (Type B,C or D) with suitable extensions and with double tension insulator strings are employed for railway crossing in conformity with the relevant specification of Railway Authorities. 2.7 High way crossing tower Back to contents page Angle towers (Type B,C or D) with suitable
  • 45. extension and with double tension strings are employed for high way crossing.angle towers are used for National High way crossing to make the crossing span as a single section so as to facilitate independent and prompt striginig.
  • 46. 2.8 Transposition tower Back to contents page 2.8.1 Power transmission lines are transposed primarily to eliminate or reduce disturbances in the neighboring communication circuits produced by the geometric imbalance of power lines. An incidental effect of transposing power line section is the geometric balancing of such circuits between terminals which assumes balanced conditions at every point of the power transmission system. Improvements and developments in both the communications and power fields have, however, greatly reduced the need for transposition of high voltage lines at close intervals. In fact, in India, the central standing committee for coordination of power and telecommunication system has ruled that "the power supply authorities need not provide transposition on power lines for coordination with telecommunication lines". 2.8.2 However, when transposition are eliminated, there are the effects of geometric imbalance of the conductor arrangements on the power system itself, and the residual current to be considered. The imbalance of the three phase voltages due to asymmetry of conductor arrangement is not considered serious in view of the equalizing effect
  • 47. of the three phase transformer bank and synchronous machinery at various points on the system. The remaining consideration viz. residual currents due to the elimination of transposition, might be important from the point of view of relay settings to prevent causing undesirable tripping of ground current relays. Operating experience has shown that many disturbance on high voltage line occur on transposition towers and statistical records indicate that at least one of the four outages is physically associated with a transposition. 2.8.3 A good practice would be to adopt about 200 KM as the permissible length of the line without taking recourse to special transposition structures, transposition being confined to substation and switching station only, provided they are located at suitable intervals. 2.8.4 Tower type C under O degree deviation limit and with suitable modification shall be used for transposition for line maintaining all the required clearances and shielding. Arrangement of transposition is shown at Figure 2.7. A view of 400 kv single circuit transposition tower is also shown in Fig.2.11. 2.9 Multi circuit towers. Back to contents page
  • 48. To transmit bulk power at a economical rate, Multi circuit towers are used. It may be mentioned here that a double circuit line is cheaper than two independent single circuit lines and four circuit line cheaper than two double circuit lines. However, the capital outlays involved become heavy and it is not easy to visualise the manner in which the loads build up and the powerflow takes place in the longterm prospective. Further, reliability considerations become very important at extra high voltages. A balance has therefore to be struck between the two somewhat opposing considerations.
  • 49.
  • 50.
  • 51.
  • 52. 2.10 Tower extensions Back to contents page All towers are designed in such a way that they can be provided with standard tower extensions. Extensions are designed as +3, +6 +9 and + 25 in Mtrs. These extensions can be used alongwith standard towers to provide sufficient clearance over ground or while crossing power lines, Railway lines, highways, undulated, uneven ground etc. A view of 400 kv single circuit towers crossing anoth er 400 kv single circuit line is shown at Fig. 2.12 2.11 Leg extensions Back to contents page Leg extensions are designed to provide extension to tower legs which are located at uneven ground where different legs of the tower are at different levels.
  • 53.
  • 54. Standard designs can be made for 1.5, 2.5 and 3.5 M leg extensions. These leg extensions can be utilised where towers are located on hill slopes, undulated ground etc. By providing leg extensions, specially in hilly areas, heavy cost of benching/revetment can be avoided completely or reduced substantially. 2.12 Truncated towers (Tower reductions) Back to contents page Similar to extension towers, truncated towers can also be used for getting the sufficient electrical clearance while crossing below the existing Extra High Voltage lines. For instance,a DD-6.9 Mtrs. truncated tower has been used in 220 KV RSEB S/Stn. at Heerapura (Jaipur). In this particular case 2 nos. of 400 KV S/C lines are already crossing over the 220 KV D/C Kota-Jaipur RSEB feeders with A+25 Mtrs. extension type of towers. While constructing another D/C 220 KV line from Anta to Jaipur which was also to be terminated in the same sub-stn. either to under cross these 400 KV S/C lines by using gantry system or to make use of the existing A+25 Mtrs. extension towers. But with the existing A+25 Mtrs extension tower, required clearance between the earth wire of the 220 KV line and hot Conductor of 400 KV lines were not within the permissible limit. So for getting the required
  • 55. electrical clearance either to remove the earthwire of 220 KV line or to use truncated tower. So to avoid the removal of earth wire a `DD' type truncated tower (-6.9 Mtrs.) has been used in order to cross these lines safely and with the required permissible electrical clearances. The truncated tower is similar to normal tower except 6.9 Mtrs of bottom section of normal tower has been removed, the other section of the tower parts remain un-changed. This is a ideal crossing in an area where one line has already crossed over the existing lines with Special extension tower and we have to accommodate another line in the existing crossing span. 2.13 Weight of different types of towers Back to contents page The weight of various types of towers used on transmission lines, 66 KV to 400 KV, together with the spans and sizes of conductor and ground wire used in lines are given in Table 2.1. Assuming that 80 percent are tangent towers, 15 percent 300 towers and 5 percent 600 towers and dead-end towers, and allowing 15 percent extra for extensions and stubs, the weights of towers for a 10 kms. line are also given in the Table 2.1. Table 2.1 Weights of towers used on various voltage categories in India
  • 56. (Metric tones) 400 kV 220 kV 220 kV 132 kV 132 kV 66 kV 66 kV Single Double Single Double Single Double Single Circuit Circuit Circuit Circuit Circuit circuit Circuit Span (m) 400 320 320 320 320 245 245 Conductor Moose Zebra Zebra Panther Panther Dog 6/4.72 Dog 6/4.72 54/3.53 mm 54/3.18 mm 54/3.18 30/3 mm 30/3 mm mm Al. + Al. + al. + 3.53 Al + mm Al. + Al. + Al.+7/3 7/1.57 mm 7/1.57 mm mm Steel 7/3.18 mm 7/3.18 7/3 mm mm Steel Steel Steel Steel mm Steel Steel Groundwire 7/4 mm 110 7/3.15 mm 7/3.15 7/3.15 7/3.15 7/2.5 mm 7/2.5 110 Kgf/mm2 110 mm 110 mm 110 mm 110 110 Kgf/mm2 quality Kgf/mm2 Kgf/mm2 Kgf/mm2 Kgf/mm2 Kgf/mm2 quality quality quality quality quality quality Tangent Tower 7.7 4.5 3.0 2.8 1.7 1.2 0.8 30 Deg. Tower 15.8 9.3 6.2 5.9 3.5 2.3 1.5 60 Deg. And Dead-end 23.16 13.4 9.2 8.3 4.9 3.2 2.0 Tower Weight of towers for 279 202 135 126 76 2 48 a 10-km line Note: Recent designs have shown 10 to 20% reduction in weights.
  • 57. -------------------------------------------------------------------------- CHAPTER THREE Chapter-3 -------------------------------------------------------------------------- TOWER FABRICATION Tower Fabrication 3.1 General Back to contents page After completing the tower design, a structural assembly drawing is prepared. This gives complete details of joints, member sizes, bolt gauge lines, sizes and lengths of bolts, washers, first and second slope dimensions, etc. From this drawing, a more detailed drawing is prepared for all the individual members. This is called a shop drawing or fabrication drawing. Since all parts of the tower are fabricated in accordance with the shop drawing, the latter should be drawn to a suitable scale, clearly indicating all the details required to facilitate correct and smooth fabrication. Towers used are of bolted lattice type. In no case welding is allowed. All members, bolts, nuts and fittings are galvanised. Spring washers are electro galvanised. Fabrication of towers are done in accordance with IS codes which is ensured by visit to the fabrication workshops and undertaking specified tests, in the presence of POWERGRID quality engineers. The following may be ensured during fabrication of the towers.
  • 58. i) Butts, splices should be used and thickness of inside cleat should not be less than that of heavier member connected. Lap splices are used to connect unequal sizes. ii) While designing, joints are to be made so that eccentricity is avoided. iii) Filler should be avoided as far as practicable. iv) The dia of hole = dia of bolt + 1.5 mm v) Drain holes are to be provided where pockets of depression are likely to hold water. vi) All similar parts should be interchangeable to facilitate repairs. vii) There should be no rough edges. viii) Punched holes should be square with plates and must have their walls parallel. ix) It should be checked that all burrs left by drilling or punching should be removed completely. Drilling or reaming to enlarge defective holes is not allowed. 3.2 Bolting Back to contents page 3.2.1 The minimum diameter of bolts used for the erection of transmission line towers is 12 mm. Other sizes commonly used are 16 mm and 20 mm. 3.2.2 The length of the bolt should be such that the threaded portion does not lie in the plane of contact of members.
  • 59. Figure 3.1 shows the wrong uses and the correct uses of bolt threads. 3.2.3 Table 3.1 gives the minimum cover to free edge and bolt spacing as per IS:802 (Part II)-1978 Code of Practice for Use of Structural Steel in Overhead Transmission line Towers. The bolts used with minimum angle sizes restrict the edge distances as given in Table 3.2 for the bolt sizes of 12 mm, 16 mm and 20 mm used on 40 x6 mm, 45x6 mm and 60x 8 mm angle sizes respectively. Table 3.1 Spacing of bolts and edge distances (mm) ------------------------------------------------------------- Bolt Hole Bolt spacing Edge distance(min) Dia dia min. Hole Hole centre centre to rolled to edge sheared edge ------------------------------------------------------------- 12 13.5 32 16 20 16 17.5 40 20 23 20 21.5 48 25 28 ------------------------------------------------------------- (See next page)
  • 60.
  • 61. Table 3.2 Maximum edge distance possible with minimum angle size (mm) --------------------------------------------------------- Size of bolted Maximum edge Bolt dia. leg of angle distance that section and its can be thickness actually obtained -------------------------------------------------------- 12 40x6 17 16 45x6 18 20 60x8 25 -------------------------------------------------------- 3.2.4 The bolts may be specified to have Whitworth or other approved standard threads to take the full depth of the nut, with the threading done far enough to permit firm gripping of the members but no farther, and with the threaded portion of each bolt projecting through the nut by at least one thread. It may also be specified that the nuts should fit hand-tight to the bolts, and that there should be no appreciable fillet at the point where the shank of the bolt connects to the head. Emphasis should be laid on achieving and maintaining proper clamp load control in threaded fastners. If a threaded fastener is torqued too high, there is a danger of failure on installation by stripping the threads or breaking the bolt or making the fasteners yield excessively. If the bolt is torqued too low, a low preload will be induced in the fastener assembly, possibly inviting fatigue or vibration failure. For every bolt system, there
  • 62. is an optimum preload objective which is obtained by proper torquing of the bolt and nut combination. The three techniques for obtaining the required pretension are the calibration wrench method, the turn-of-the-nut method and the direct tension indication method. The calibrated wrench method includes the use of manual torque wrenches and power wrenches adjusted to stall at a specified torque value. Variations in bolt tension, produced by a given torque, have been found to be plus minus 10 percent. The turn-of-the-nut method has been developed where the pretensioning force in the bolt is obtained by specified rotation of the nut from an initially snug tight position by an impact wrench or the full effort of a man using an ordinary wrench. This method is found to be reliable, cheapest and preferred. The third and the most recent method for establishing bolt tension is by direct tension indicator. There are patented load indicating washers, where correct bolt tension could be assessed by observing the deformation. Upon tightening the bolt, the washers are flattened and the gap is reduced. The bolt tension is determined by measuring the remaining gap. 3.2.5 Most of the transmission line specifications do
  • 63. not specify the maximum permissible group length of bolts. It is a good practice to ensure that no bolt connects aggregate thickness more than three times the diameter of the bolt. Further more, the grip strength developed by a bolt depends not only upon the thickness of the members but also on the number of members to be connected. This is due to the fact that the surface of the members may not be perfectly smooth and plain and, therefore, if the number of members to be connected is too many, the full grip strength would not be developed. In the tower construction, the need for connecting more than three members by a single bolt rarely arises, it would be reasonable to limit the number of the members to be connected by a single bolt to three. The limitation regarding the thickness of the members and the number of members to be connected is necessary not only from the point of view of developing maximum grip strength but also from the point of view of reducing the bending stresses on the bolt to a minimum. 3.2.6 The threaded portion of the bolt should protrude not less than 3 mm and not more than 8 mm over the nut after it is fully tightened. 3.3 Washers Back to contents page At present, both flat and spring steel washers are
  • 64. being used in the construction of transmission line towers in India. The advantage of spring washers over flat washers is that the former, in addition to developing the full bearing area of the bolt, also serve to lock the nuts. The disadvantages, however, are that it is extremely difficult to get the correct quality of steel for spring washers, and also that they are too brittle and consequently break when the nuts are fully tightened. Furthermore, the spring washers, unlike flat washers tend to cut into and destroy the galvanising. When spring washers are used, their thicknesses should be as recommended in IS:802 (Part II)-1978 and given in Table. 3.3 Table 3.3: Thicknesses of spring washers (mm) ------------------------------------------------------------ Bolt dia. Thickness of spring washer ------------------------------------------------------------ 12 2.5 16 3.5 20 4.0 ------------------------------------------------------------ With regard to the locking arrangement, the general practice is to lock the nuts by centre punching of the bolts or punching the threads. In special cases such as tall river-crossing towers which are subjected to unusual vibrations, the bolts are secured from slacking back by the use of
  • 65. lock nuts, by spring washers, or by cross-cutting of the thread. A minimum thickness of 3mm for washers is generally specified. In our transmission lines, we are using spring washers under all nuts of tower. These spring washers are electro-galvanised. 3.4 Lap and butt joint (figure 3.2 and 3.3) Back to contents page Lap splices are normally preferred for leg members as these joints are generally simpler and more economical compared to the heavier butt joints which are employed only if structural requirements warrant their use. In lap splices, the back(heel) of the inside angle should be ground to clear the fillet of the outside angle. 3.5 Gusset plates Back to contents page In the case of suspension towers, the stresses in the web system are usually small enough to keep the use of gusset plates to the minimum. On heavier structures, however, the web stresses may be very large and it may not be possible to accommodate the number of bolts required for the leg connection in the space available on the members, thus
  • 66. necessitating the use of gusset plates. Plates may also be required to reduce the secondary stresses introduced due to eccentricity to a minimum. The bracing members should preferably meet at a common point within the width of the tower leg in order to limit the bending stresses induced in the main members due to eccentricity in the joints. To satisfy this condition, it may sometimes become necessary to use gusset plates.
  • 67.
  • 68. 3.6 Bracing to leg connections Back to contents page Typical connections of diagonals and struts to a leg member are shown in Figure 3.4. The number of bolts required in these simple connections is derived directly from the member load and the capacity per bolt either in shear or bearing. Diagonal members which are clipped or coped for clearance purposes must be checked for capacity of the reduced net section. Note that gusset plates are not used at leg connections, but eccentricity is kept to a minimum by maintaining a clearance of 9.5mm to 16mm between members. If the leg does not provide enough gauge lines to accommodate the required bolts in a diagonal connection, a gusset plate as shown in Figure 3.5 may be employed. The thickness of gusset plate must be sufficient to develop the required load per bolt. Typical gusset plate connection at waist lines on the normal face for a wasp-waist tower is shown in Figure 3.6. 3.7 Connection of redundant members Back to contents page Redundant sub-members usually require only one
  • 69. bolt connection to transfer their nominal loads. Thus, gusset plates can easily be avoided if clipping and coping are used to advantage. Typical connections, shown in Figures 3.7, 3.8 and 3.9 indicate the methods of clipping or turning members in or out to keep the number of bolts to a minimum. Figure 3.7 illustrates the use of a small plate rather than connecting five members on one bolt, as it has been found that erection of more than four thicknesses per bolt is particularly awkward. 3.8 Cross-arm connections Back to contents page The cross-arm to leg connection (Figure 3.10) must be considered as one of the most important joints on a tower since all loads originating from the conductors are transferred through the cross-arms to the tower shaft by means of these bolts. Because of its importance, a minimum of two bolts is often specified for this connection.
  • 70.
  • 71.
  • 72. An example of a hanger-to-arm-angle connection on `Vee' cross-arm is shown in Figure 3.11, Both vertical and horizontal eccentricities may become excessive if the detail of this joint is not carefully worked out. Suspension towers are provided with holes at the ends of the cross-arms, as shown in Figure 3.10, for U-Bolts which receive the insulator string clamps. Strain towers, however, must be supplied with strain plates (Figure 3.12) which are not only capable of resisting the full line tension, but also shock and fatigue loads as well as wear. 3.9 step bolts and ladders Back to contents page The step bolts usually adopted are of 16mm diameter and 175mm length. They are spaced 450mm apart and extend from about 3.5 metres above the ground level to the top of the tower. The bolts are provided with two nuts on one end to fasten the bolts securely to the tower, and button heads at the other end to prevent the foot from slipping away. The step bolts should be capable of withstanding a vertical load of not less than 1.5 KN. Step bolts are provided from 3.5 m to 30 m height of the superstructure. For special structures, where the height of the superstructure exceeds 50 metres, ladders along with protection rings are provided
  • 73. (in continuation of the step bolts on the longitudinal face of the tower) from 30 metres above ground level to the top of the special structure. A platform, using 6mm thick chequered plates, along with a suitable railing for access from step bolts to the ladder and from the ladder to each cross-arm, and the ground wire support is also provided. 3.10 Anti-climbing devices Back to contents page All towers are provided with anti-climbing devices at about 3.5 metres above ground level. The details of anti-climbing devices are shown in Figure 3.13. 3.11 Danger and number plates Back to contents page Provision is made on the transverse face of the tower for fixing the danger and number plates while developing the fabrication drawing. These accessories are generally fixed at about 4.5mm above the ground level. Fig. 3.18 and Fig.3.16 show the details of danger and number plates respectively. The letters, figures and the conventional skull and bones of the danger plates should conform to IS:2551-1982 Specification for Danger Notice Plates and they are to be painted in signal red on the
  • 74. front of the plate.
  • 75. 3.12 Phase and circuit plates Back to contents page Each tension tower shall be provided with a set of phase plates. The transposition towers should have the provisions of fixing phase plates on both the transverse faces. The details of phase plate are given in Fig. 3.15. All the double circuit towers shall be provided with circuit plate fixed near the legs. The details of circuit plates are indicated in Fig.3.17. These plates shall also be fixed at about 4.5m above ground level. 3.13 Bird guard Back to contents page Perching of Birds on tower cross arms results in spoiling of insulator discs of suspension strings which leads to tripping of line. To overcome this problem, bird guards are fixed over suspension insulator string. The details are given at Figure No. 3.14. Bird guards shall be used for type-I string only. 3.14 Aviation requirements :- Back to contents page 3.14.1 The river crossing towers and any other towers in
  • 76. the vicinity of an airport shall be painted and the crossing span shall be provided with markers to caution the low flying air craft. 3.14.2 The full length of the towers shall be painted over the galvanised surface in contrasting bands of orange or red and white. The bands shall be horizontal. Fig.2.10 shows the river crossing tower with aviation paints.
  • 77.
  • 78.
  • 79.
  • 80.
  • 81. 3.15 Packing, transportation and storage of tower parts. Back to contents page 3.15.1 Packing : a) Angle section shall be wire bundled. Cleat angles, gusset plates, brackets, fillet plates, hangers and similar loose pieces shall be bolted together to multiples or securely wired together through holes. b) Bolts, nuts, washers and other attachments shall be packed in double gunny bags accurately tagged in accordance with the contents. c) The packing shall be properly done to avoid losses/damages during transit. Each bundle or package shall be appropriately marked. 3.15.2 Transportation. The transport of steel towers from the works to the nearest railway station presents no special difficulty. The towers are delivered in trucks having one or two towers per truck according to the weight involved. A station having a loading bay is highly desirable, as this greatly facilitates handling. The lorries can be backed against the bay and the ease of handling will then offset any slight increase in haulage
  • 82. costs from a station less well equipped. The parts of each tower should be kept separate so that they can be delivered from the bay direct to the tower site. Tower sets are made up in sections, since it is impracticable for the corner angles to be in one length. Each section is carefully marked at the works. In each section there are generally one or more panels and these are marked to facilitate erection. The tower sets should be carefully checked when unloaded from the trucks and then placed in a suitable position on the bay where they can be picked up easily as a complete unit. If the steelwork is delivered in bundles, the checking is even more important and there are two meth- ods of doing this. Some Engineers prefer laying the steelwork out in members while others prefer it laid out in towers and in our opinion the latter method has many advantages. Shortages are easily spotted and scheduled and the tower can be loaded and taken to its particular position. All bolts, washers, nuts and small parts should be in bags and labelled with the number of the tower they are intended for. A word of warning re-garding the handling of the long corner angles should be clearly displayed. These must be carefully
  • 83. transported or they may get bent and it is a very difficult job to straighten them without damaging the galvanising. All material transport shall be undertaken in vehicles suitable for the purpose and free from the effects of any chemical substances. Tower members shall be loaded and transported in such a manner that these are not bent in transit and sharp-bent members are not opened up or damaged. 3.15.3 Storage. A. The selection of location of a construction store is important as the movement of construction materials is time consuming process and it requires detailed planning and Managerial attention. The selection of location is generally based on the following criteria. a. Close proximity to rail heads, National Highways. b. Proximity to urbanisation and towns. c. Availability of water and electrical power. d. Distance from the proposed line and approach. e. Type of land. (The store should not be located on marshy or wet lands. Also, the
  • 84. low lying and water stagnant areas) f. Availability of land in sufficient area. g. Communication facilities. h. Availability of labour for the work in the stores. B. Once land is selected, it is better to identify the space for towers, insulators, conductors, hardware and the tools & plants of erection contractor. The selection of place for each type of material should be very judicious and in such a way that inward or outward movement of one item should not be through the stacking of the materials of other item. Proper board markings and pointers may be kept for each item for easy identification. C. Tower parts should not be kept directly on the ground and it should be placed above stones of proper size or sleepers to avoid contact with mud. D. It is always preferable to stack the tower parts in a neat and systematic fashion in tower wise order. On request of erection gang, store-keeper should be able to provide him one full set of tower without any difficulty and delay.
  • 85. E. The following points may be ensured in the stores. a. Complete fencing of the store yard. b. 24 hours vigilant security. c. Proper lighting. d. Fire protection equipments.
  • 87. -------------------------------------------------------------------------- CHAPTER FOUR -------------------------------------------------------------------------- METHODS OF ERECTION 4.1 GENERAL Back to contents page There are four main methods of erection of steel transmission towers which are described as below i. Built-up method or Piecemeal method. ii. Section method iii. Ground assembly method. iv. Helicopter method 4.1.1 Built up method Back to contents page This method is most commonly used in this country for the erection of 66 KV, 132 KV, 220 KV and 400 KV Transmission Line Towers due to the following advantages. i. Tower materials can be supplied to site in knocked down condition which facilitate easier and cheaper transportation. ii. It does not require any heavy machinery such as cranes etc. iii. Tower erection activity can be done in any kind of terrain and mostly through out the year.
  • 88. iv. Availability of workmen at cheap rates. This method consists of erecting the towers, member by member. The tower members are kept on ground serially according to erection sequence to avoid search or time loss. The erection progresses from the bottom upwards, the four main corner leg members of the first section of the tower are first erected and guyed off. Sometimes more than continuous leg sections of each corner leg are bolted together at the ground and erected. The cross braces of the first section which are already assembled on the ground are raised one by one as a unit and bolted to the already erected corner leg angles. First section of the tower thus built and horizontal struts (bet members) if any, are bolted in position. For assembling the second section of the towers, two gin poles are placed one each on the top of the diagonally opposite corner legs. These two poles are used for raising parts of second section. The leg members and braces of this section are then hoisted and assembled. The gin poles are then shifted to the corner leg members on the top of second section to raise the parts of third section of the tower in position for assembly. The gin pole is thus
  • 89. moved up as the tower grows. This process is continued till the complete tower is erected. Cross-arm members are assembled on the ground and raised up and fixed to the main body of the tower. For heavier towers, a small boom is rigged on one of the tower legs for hoisting purposes. The members/sections Are hoisted either manually or by winch machines operated from the ground. For smaller base towers/vertical configuration towers, one gin pole is used instead of two gin poles. In order to maintain speed and efficiency, a small assembly party goes ahead of the main erection gang and its purpose is to sort out the tower members, keeping the members in correct position on the ground and assembling the panels on the ground which can be erected as a complete unit. Sketches indicating different steps of erection by built up method are shown at Figure 4.1 to Figure 4.7. List of Tools and Plants and Manpower for Tower Erection is given at Annexure E/1 and E/2. Guying arrangement - Guying arrangements are to be done at waiste level/bottom cross-arm level as well as in the girder level/top cross-arm level depending on SC/DC towers and it is to be
  • 90. installed at 450 from vertical. The deadments for guying arrangements is to be properly made. A sample of deadments drawing is enclosed at Figure 4.8 for reference. Guying should be steel wire or polypropylene rope depending upon requirements. Nominal tension is to be given in guying wire/rope for holding the tower in position. 4.1.2 Section method Back to contents page In the section method, major sections of the tower are assembled on the ground and the same are erected as units. Either a mobile crane or a gin pole is used. The gin pole used is approximately 10 m long and is held in place by means of guys by the side of the tower to be erected. The two opposite sides of the lower section of the tower are assembled on the ground. Each assembled side is then lifted clear of the ground with the gin or derrick and is lowered into position on bolts to stubs or anchor bolts. One side is held in place with props while the other side is being erected. The two opposite sides are then laced together with cross members diagonals; and the assembled section is lined up, made square with the line, and levelled. After completing the first section, gin pole is set on the top of the first section. The gin
  • 91. rests on a strut of the tower immediately below the leg joint. The gin pole then has to be properly guyed into position. The first face of the section is raised. To raise the second face of this section it is necessary to slide the foot of the gin on the strut to the opposite of the tower. After the two opposite faces are raised, the lacing on the other two sides is bolted up. The last lift raises the top of the towers. After the tower top is placed and all side of the lacings have been bolted up, all the guys are thrown off except one which is used to lower the gin pole. Sometimes whole one face of the tower is assembled on the ground, hoisted and supported in position. The opposite face is similarly assembled and hoisted and then bracing angles connecting these two faces are fitted.
  • 92.
  • 93.
  • 94.
  • 95.
  • 96.
  • 97.
  • 98.
  • 99.
  • 100. 4.1.3 Ground assembly method Back to contents page This method consists of assembling the tower on ground, and erecting as a complete unit. The complete tower is assembled in a horizontal position on even ground, at some distance from tower footing. The tower is assembled in a linewise position to allow the cross-arms to be fitted. On sloping ground, however elaborate packing of the low side is essential before assembly commences. After the assembly is complete the tower is picked up from the ground with the help of a crane and carried to its location and set on its foundation. For this method of erection, a level piece of ground close to the footing is chosen for the tower assembly. This method is not useful when the towers are large and heavy and the foundations are located in arable land where building and erecting complete towers would cause damage to large areas or in hilly terrain where the assembly of complete tower on slopping ground may not be possible and it may be difficult to get crane into position to raise the complete tower. In India, this method is not generally adopted because of prohibitive cost of mobile crane, and non-availability of good approach roads to the
  • 101. location. 4.1.4 Helicopter method Back to contents page n the helicopter method, the transmission tower is erected in sections. For example bottom section is first lifted on to the stubs and then upper section is lifted and bolted to the first section and the process is repeated till the complete tower is erected. Sometimes a complete assembled tower is raised with the help of a helicopter. Helicopters are also used forlifting completely assembled towers with guys from the marshalling yards, where these are fabricated and then transported one by one to line location. The helicopter hovers over the line location while the tower is securely guyed. The ground crew men connect and tighten the tower guyed and as soon as the tie lines are bolted tight, the helicopter disengages and return to the marshalling yards for another tower. This method is adopted particularly when the approach is extremely difficult. 4.2 Earthing Back to contents page Once the geometry of the tower and the line insulation level are fixed, the one factor which affects the lightning performance of a line that can be controlled during the construction phase of the
  • 102. line, is the Tower-footing resistance. Consequently, this should be measured during this phase of the work and, if necessary, extra earthing provided. The measured resistance alters if the soil conditions change due to seasonal variations. When the footing resistance exceeds a desired value from the lightning protection point of view, the towers are earthed generally with pipe type and, in special cases, with counterpoise type earthing. In the former case, a 25mm diameter galvanised iron pipe, 3,050mm long, is used with 6.5mm diameter holes drilled at 150mm apart to facilitate ingress of moisture, and is surrounded by a layer of finely broken coke of 25mm granular size and salt. The earthing should be done in accordance with the stipulations made in IS:3043-1972 and IS:5613 (Part II/Section 1)-1976. The general earthing arrangement is shown in Figures 4.9 and 4.10. Where the tower stands on rock, efforts should be made to obtain a good ground by carrying a length of galvanised steel tape from the tower leg to the pipe driven in soil, at as short a distance from the tower as possible. The connecting tape is burried in a groove cut in the rock surface and adequately protected from damage. 4.2.1 Measurement of Tower Footing Resistance The megger can be used in two ways to measure the
  • 103. resistivity of the soil, namely, the three point method and the four-point method. The four-point method is simpler and more accurate and is briefly described below. a) Soil Resistivity Four similar electrodes are burried in the earth to a depth B at equal distances A from one another in a straight line. The megger connections are shown in Figure 4.11. If the crank of the instrument is then rotated at the stipulated speed (usually 100 rpm), the resistance R, as read on the scale, is the resistance of the earth between the two equipotential surfaces with which P1 and P2 are in contact. If the depth of the electrode in soil B (in cm) is small in comparison with A, the resistivity of the soil is given by the following expression. 2x22 x AxR P = ----------- 7 Where P = earth resistivity in ohms/cm3 A = spacing between the electrodes in cm, and R = resistance in ohms as read on the megger. For all practical purposes, A should be at least twenty times that of B.
  • 104. b) Tower Footing Resistance For measuring tower footing resistance, Terminal C-1 of megger shall be connected with tower leg instead of electrode C-1. The value of resistance read on the megger multiplied with multiplying factor gives the tower footing resistance in ohms.
  • 105.
  • 106.
  • 107.
  • 108. 4.3 Tack welding :- Back to contents page All bolts/nuts below waist level in single circuit tower or bottom cross arm in Double circuit tower, shall be tackwelded to prevent theft of tower members. Two 10mm thick welding tacks should be done on each bolt & nut in the diagonally opposite direction by suitably selecting welding electrods of size 1.6mm to 2.5mm equivalent to over cord-S, code AWS-E6013 (Advani-Oerlikon). After removing slag over tack welding, zinc rich (90% zinc content) cold galvanising paint equivalent to epilux-4 of Berger Paint shall be applied on the welding. 4.4 Permissible tolerances in tower erection Back to contents page As per IS;5613 (Part 3/Sec.2) :1989, the following tolerances in tower erection are permitted: 4.4.1 No member of a tower shall be out of straightness by more than one in 1000. Members failing the requirements shall be straightened before erection in a manner that shall not damage their properties or the protective finish. 4.4.2 The tower shall not be out of vertical by more than 1 in 360 before stringing is carried out.
  • 109.
  • 110. Annexure - E/1 Back to contents page POWER GRID CORPORATION OF INDIA LIMITED (CONSTRUCTION MANAGEMENT) LINE CONSTRUCTION ERECTION ACTIVITY Tools & plants reqd. for Tower erection gang 1. Ginpole/Derric Pole 75/100mm dia. and of length 8.5-9m. 2nos. 2. Polypropylene rope 25mm dia. 700 m. 19mm dia.1000 m. 3. Single sheave pulley Closed type 8 nos. 4. Crow Bars(25mm dia and 1.8m length) 16 nos. 5. Spanners,(both Ring and Flat) Hammers,Slings,(16mm dia.and 1m length), hooks (12mm dia) D shackle,Tommy Bars. As per reqt. 6. Tents,Buckets,Water drums, camping, cots, tables, chairs, and petromax etc. As per reqt. 7. D Shackle 7.6 cm (3 in.) 6 nos. 8. Hexagonal box spanner with fixed liver and end of the liver pointed to use Reqd. sizes
  • 111. hole bar. Each size 6 nos. 9. Safety equipments : i. Safety helmets 40 nos. ii. Safety belts 10 nos. iii. Safety shoes 50 nos. iv. Welding Goggles 2 nos. v. First Aid Box 1 no. Note : The quantity of safety equipments may be changed as per manpower engaged.
  • 112. Annexure - E/2 Back to contents page POWER GRID CORPORATION OF INDIA LIMITED (CONSTRUCTION MANAGEMENT) CONSTRUCTION ACTIVITY MANPOWER REQUIREMENT FOR TOWER ERECTION GANG One Engineer shall be earmarked exclusively for the work of Tower Erection being carried out by different gangs. Following manpower is required for each Tower Erection gang. 1) Supervisor 1 No. 2) Fitter 8 Nos. 3) Skilled workers 12 Nos. 4) Unskilled workers 20 Nos. Note: Average output per gang per month will be approximately 80 MT. The man power may be regulated depending upon requirements
  • 114. -------------------------------------------------------------------------- CHAPTER FIVE -------------------------------------------------------------------------- GUIDELINES GL-1 PRE-ERECTION CHECKS Back to contents page NAME OF LINE___________________ LOCATION NO. _____________ NAME OF CONTRACTOR_____________ TYPE OF TOWER ____________ Before taking up tower erection works, following preparations need to be made. 1.1 Foundation checks 1.1.1 Tower erection work shall be taken up only after concreting is cured and set for 14 days as per technical specifications. This is essential so that concrete gains sufficient strength to withstand various forces acting during and after tower erection. 1.1.2 The stubs shall be set such that the distance between the stubs and their alignment and slop is in accordance with the approved drawings so as to permit assembling of superstructures without undue strain or distortion in any part of the structure. To ensure above following checks are necessary before tower erection. (a) Level of all the four stubs shall be on one horizontal plane in order to ensure correct and smooth tower erection. The level of top of
  • 115. the stubs shall be checked to ensure that these are on one horizontal plane. (b) Distance between the stubs shall be as per approved drawing so that correct and smooth tower erection is achieved. Hence distance (diagonals) between the stubs are measured and verified for its correctness. 1.1.3 Revetment/Benching wherever required shall be completed so that there is no danger to foundation during and after tower erection. However, if it is felt that, non-completion of Revetment/Benching is not going to harm foundation during and after tower erection, the same may be programmed and executed on later date. 1.2 Tower materials 1.2.1 It shall be ensured that approved structural drawings and Bill of Material with latest revision are available at site to facilitate tower erection. Preferably one set of structural drawings properly laminated and Bill of Material in Bound Book shall be available at site with each gang. 1.2.2 All tower Members shall be available at site as per approved Bill of Material and shall be serially placed on ground in order of erection requirement. 1.2.3 It shall be checked that no tower Member, Nut/Bolt, accessories are rusted, bent or damaged.
  • 116. 1.2.4 All required sizes of Bolts/Nuts, spring/packing washers in required quantity are available at site. 1.2.5 If any defects in protective surface finish are found in case of hot dip galvanised members, the damage shall be repaired by applying two coats of zinc-rich paint having atleast 90% zinc contents conforming to I.S. code. 1.2.6 Members bent in transit shall be straightened such that the protective surface finish is not damaged. 1.3 Tools & plants 1.3.1 All the tools and plants required for safe and efficient tower erection shall be available at site.A list of necessary tools and plants is given at Annexure-E/1. 1.3.2 All the tools and plants shall be tested as per approved safety norms and relevant test certificates shall be available. In addition to above, periodic testing of tools and plants shall be carried out and its safe working capacity shall be worked out. 1.4 Personal protective equipments 1.4.1 All the persons working on tower shall wear safety helmet, safety belt and safety shoes,.Similarly all the persons working on ground shall wear safety helmet and safety shoes. List of personal protective equipments is given at Annexure-E/1. 1.4.2 Safety equipments shall be tested as per safety
  • 117. norms and necessary test certificate shall be available. Also, a periodic check shall be carried out to ensure requisite strength. 1.5 Manpower 1.5.1 Manpower engaged for the purpose of tower erection shall be skilled and competent enough to ensure safe, smooth and efficient tower erection activity. 1.5.2 A list of necessary manpower required for tower erection is given at Annexure-E/2. 1.6 Miscellaneous 1.6.1 If there is any LT/HT power line near the vicinity of tower erection, necessary shutdown of the power line shall be obtained in writing from the concerned Agency in order to avoid electrical hazards caused by accidental touching of stay/Guy ropes with power line. 1.6.2 In order to develop and maintain cordial relations with field owners, it is desired that crop/tree compensation of foundation is paid to the owners before taking up tower erection works.