Does Better Scheduling Drive Execution Success?
                         Dr. Dan Patterson PMP// CEO Acumen
                                                  May 9 2012
  //
// Acumen                                           Realistic Scheduling

     Proven Project Analytics                       // S1      The Base


                                                    // S2      Critiqued


◦    Project Management Software                    // S3    Risk-Adjusted


◦    Oracle Primavera partner                       // S4     Optimized

◦    Insight into challenges & use of               // S5    Team-Aligned

     analytics to overcome them
                                                     Product Offerings
◦    Core Concepts:
      1.    Project success requires a sound plan       Acumen Fuse®


      2.    Forecast accuracy requires risk             Risk Workshops
            consideration
                                                       Software Training


 May 10, 2012   //   2
// Presentation Overview
   A Case Study


      S1//S5 Schedule Maturity Model

           Developing sound schedules

           Schedule Index™

           Baseline Compliance™

           Acumen Fuse analysis


      Case Study/software demo

      Questions & Answers


 May 10, 2012   //   3
// Schedule Maturity Framework
                                 Acumen S1//S5


                             6	
  
                                                                                                                                        •  Schedule	
  Basis	
  
                                                                                                                           	
  S1	
     •  Owner/contractor	
  schedule	
  
                             5	
  
                                                                                                                                        •  Cri/qued	
  Schedule	
  
                                                                                                                           S2	
         •  Ensure	
  structural	
  integrity	
  
                             4	
  
Chance	
  of	
  Sucess	
  




                                                                                                                                        •  Risk-­‐Adjusted	
  Schedule	
  
                             3	
  
                                                                                                                           S3	
         •  Account	
  for	
  risk/uncertainty	
  

                             2	
  
                                                                                                                                        •  Op/mized	
  Target	
  Scenarios	
  
                                                                                                                           S4	
         •  Schedule	
  accelera>on	
  
                             1	
  


                                                                                                                                        •  Team	
  Validated	
  Scenario	
  
                             0	
  
                                     0	
          1	
              2	
              3	
            4	
     5	
     6	
     S5	
         •  Buy-­‐in	
  on	
  op>miza>on	
  
                                                                           Maturity	
  Level	
  

                                             Measure quality through the Fuse Schedule Index™
            May 10, 2012                                  //   4
// Schedule Quality Measurement
   Metric Analysis


   ◦    Legacy
         ◦    duration, constraints, excessive lags,
              negative float
   ◦    Industry Standards
                ◦  DCMA 14 Point Assessment
                ◦  NDIA GASP/ GAO

   ◦    Acumen Metrics
         ◦  Logic Density™
         ◦  Insufficient Detail™
 May 10, 2012   //   5
// Acumen Schedule Metrics
 Advanced Project Insight




    Finish	
              Insufficient	
               Logic	
                   Logic	
  
    Compliance™	
         Detail™	
                  Density™	
                Hotspot™	
  
    • Accurate	
          • Ac>vity	
  V	
           • Measure	
  of	
         • Timely	
  start?	
  
      measure	
  of	
       project	
  dura>on	
       complexity/
      performance	
                                    completeness	
  


    Milestone	
           Broad	
  Risk	
            Float	
  Ra>o™	
          Redundancy	
  
    Ra>o™	
               Range	
                    • Degree	
  of	
          Index™	
  
    • Detail	
  V	
       • Check	
  for	
             flexibility	
  per	
     • Non-­‐needed	
  
      repor>ng	
            erroneous	
  risk	
        day	
  of	
  work	
       logic	
  
                            input	
  




              //
// Logic Density™
  Planning Consistency


 ◦    Determine Logic Hotspots™ in schedule
 ◦    Indication of sufficient logic
 ◦    Excellent means of trending detail level



                                             More	
  defini>on	
  
                                                needed	
  




        May 10, 2012
         // 7
// Advanced Logic Analysis
  Sound Basis of Schedule


  ◦    Use of FS, FF, SS, FS links
  ◦    Lags & Leads
        ◦    Lags hide schedule detail            redundant

        ◦    Leads cause reverse dates        A
  ◦    Circular logic between projects
  ◦    Out-of-Sequence updates                       B
  ◦    Open ends/missing logic                                C
  ◦    Open start/finish (hidden open ends)
  ◦    Logic Density
  ◦    Logic Hotspot
  ◦    Redundancy Index
              //
// Measuring Schedule Quality
   Fuse Schedule Index™




 May 10, 2012   //   9
// Baseline Compliance Index™




     Examines	
  how	
  
     many	
  ac>vi>es	
  
     fell	
  within	
  the	
  
        expected	
  
    repor>ng	
  period	
  




          //
// Baseline Compliance™
            Performance Analysis


            ◦    More than date comparison
            ◦    Measures period-compliance
            ◦    Included in Fuse® library
100%	
  

  50%	
  
    0%	
  




      May 10, 2012   //   11
// Acumen Fuse Platform
 Enterprise Project Analysis
                                            Metric	
  
                                           Analyzer	
  
 ◦    Fuse: analytics platform
                                            Logic	
  
      ◦    Improves schedule quality       Analyzer	
  

      ◦    Insight into performance        Forensic	
  
                                           Analyzer	
  

 ◦    Fuse 360: goal-based acceleration    Schedule	
  
                                           Cleanser	
  
      ◦    Schedule Acceleration
                                           Schedule	
  
      ◦    Decision-support               Accelerator	
  


            // May 10, 2012
// Metric Analysis
      Slice & Dice


    Benefit:
"     Pinpoint shortcomings
"     Project characteristics
"     Slice and dice


     Schedule	
                 Cost	
         Performance	
      Characteris>cs	
               Earned	
  Value	
             Risk	
  

• Logic	
              • Overrun	
           • Status	
          • Level	
  of	
  detail	
     • CPI/SPI	
             • Exposure	
  
• Float	
              • Capacity	
          • Completed	
       • Constrained	
               • Trending	
            • Hot	
  spots	
  
• Dura>on	
            • Burn	
  rates	
     • Delayed	
         • Riding	
  Data	
            • Earned	
              • Hidden	
  paths	
  
                                                                   Date	
                        schedule	
  



                    // May 10, 2012
// Metrics to fit: Criteria, Thresholds
  Fuse Metric Editor




         //
// Fuse Schedule Cleanser™
 Actionable Insight




        //
// Project Forensics
  Insight into Schedule Cleanse




         // May 10, 2012
// Claims Analysis
     Insight into project variances


◦    Advanced forensics
◦    Fuse gives meaning to the
     impact of changes
◦    Pinpoints changes to critical/
     driving path
◦    Every single project attribute
     can be checked
◦    Calendar definition changes


             // May 10, 2012
Case Study
// Acumen Fuse® Software Demonstration




        //
// Case Study
 Owner/contractor Alignment


 •    Houston-based oil/gas owner
 •    Objective:
      •    More on-time completion for projects over $250MM
      •    Encourage more mature contractor schedules
      •    Overcome “brain drain” in scheduling
 •    How achieved:
      •    Mandated contractor Fuse Schedule Index of 75+
      •    Gave contractor opportunity to self-assess

            //
// Quality Planning Truly Drives Success
                                     100%	
  
 Probability of On-Time Completion




                                      90%	
  

                                      80%	
  

                                      70%	
  

                                      60%	
  

                                      50%	
  

                                      40%	
  

                                      30%	
  

                                      20%	
  

                                      10%	
  

                                        0%	
  
                                                 0%	
          10%	
     20%	
     30%	
       40%	
     50%	
     60%	
     70%	
     80%	
     90%	
     100%	
  

                                                                                             Fuse Schedule Index™

 May 10, 2012                                             //    20
// Q&A




     //
More information:
     White papers: www.projectacumen.com
     Software Trial: www.projectacumen.com/trial
//   Twitter: @projectacumen
     Email: info@projectacumen.com




           //

More Related Content

What's hot

Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevonNASAPMC
 
Richard.grammier
Richard.grammierRichard.grammier
Richard.grammierNASAPMC
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vinceNASAPMC
 
Hazen michael
Hazen michaelHazen michael
Hazen michaelNASAPMC
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.jamesNASAPMC
 
Charles.leising
Charles.leisingCharles.leising
Charles.leisingNASAPMC
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseNASAPMC
 
Jim.cassidy
Jim.cassidyJim.cassidy
Jim.cassidyNASAPMC
 
Jenks.ken
Jenks.kenJenks.ken
Jenks.kenNASAPMC
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.johnNASAPMC
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardoNASAPMC
 
Healy edward
Healy edwardHealy edward
Healy edwardNASAPMC
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrongNASAPMC
 
Accounting cycle powerpoint presentation templates
Accounting cycle powerpoint presentation templatesAccounting cycle powerpoint presentation templates
Accounting cycle powerpoint presentation templatesSlideTeam.net
 
Dusterwald
DusterwaldDusterwald
DusterwaldNASAPMC
 
Gavin.tom
Gavin.tomGavin.tom
Gavin.tomNASAPMC
 

What's hot (19)

Lau.cheevon
Lau.cheevonLau.cheevon
Lau.cheevon
 
Richard.grammier
Richard.grammierRichard.grammier
Richard.grammier
 
Bilardo.vince
Bilardo.vinceBilardo.vince
Bilardo.vince
 
Hazen michael
Hazen michaelHazen michael
Hazen michael
 
Ortiz.james
Ortiz.jamesOrtiz.james
Ortiz.james
 
Charles.leising
Charles.leisingCharles.leising
Charles.leising
 
Mullane stanley-hamilton-wise
Mullane stanley-hamilton-wiseMullane stanley-hamilton-wise
Mullane stanley-hamilton-wise
 
Jim.cassidy
Jim.cassidyJim.cassidy
Jim.cassidy
 
Risk Management
Risk ManagementRisk Management
Risk Management
 
Jenks.ken
Jenks.kenJenks.ken
Jenks.ken
 
Saltzman.john
Saltzman.johnSaltzman.john
Saltzman.john
 
Vince.bilardo
Vince.bilardoVince.bilardo
Vince.bilardo
 
Healy edward
Healy edwardHealy edward
Healy edward
 
Charles.armstrong
Charles.armstrongCharles.armstrong
Charles.armstrong
 
Kickoffsample
KickoffsampleKickoffsample
Kickoffsample
 
Accounting cycle powerpoint presentation templates
Accounting cycle powerpoint presentation templatesAccounting cycle powerpoint presentation templates
Accounting cycle powerpoint presentation templates
 
Integrated Operations io-PMO
Integrated Operations io-PMOIntegrated Operations io-PMO
Integrated Operations io-PMO
 
Dusterwald
DusterwaldDusterwald
Dusterwald
 
Gavin.tom
Gavin.tomGavin.tom
Gavin.tom
 

Similar to Does Better Scheduling Drive Execution Success?

Fuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceFuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceAcumen
 
Does better scheduling drive execution success ppt
Does better scheduling drive execution success pptDoes better scheduling drive execution success ppt
Does better scheduling drive execution success pptp6academy
 
Opticon - Construction ERP Overview presentation
Opticon - Construction ERP Overview presentationOpticon - Construction ERP Overview presentation
Opticon - Construction ERP Overview presentationSoftTech Engineers
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Acumen
 
Agile NCR 2013 - Archana Joshi - maintaining agile equilibrium v4
Agile NCR 2013 - Archana Joshi -  maintaining agile equilibrium v4Agile NCR 2013 - Archana Joshi -  maintaining agile equilibrium v4
Agile NCR 2013 - Archana Joshi - maintaining agile equilibrium v4AgileNCR2013
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAcumen
 
Process implementation at Droisys
Process implementation at DroisysProcess implementation at Droisys
Process implementation at DroisysDroisys Inc
 
Process implementation v_1.1
Process implementation v_1.1Process implementation v_1.1
Process implementation v_1.1Droisys Inc
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueAcumen
 
LKG Project Level Presentation FEL in New Energies 2023.ppsx
LKG Project Level Presentation FEL in  New Energies 2023.ppsxLKG Project Level Presentation FEL in  New Energies 2023.ppsx
LKG Project Level Presentation FEL in New Energies 2023.ppsxAngusMacleod18
 
David Weir And Graham Fisher - Scaling Agility Across the Enterprise
David Weir And Graham Fisher - Scaling Agility Across the EnterpriseDavid Weir And Graham Fisher - Scaling Agility Across the Enterprise
David Weir And Graham Fisher - Scaling Agility Across the EnterpriseAgile Lietuva
 
Key Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning ImplementationKey Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning ImplementationAlithya
 
Tool Box Talk - World Class Maintenance Edited
Tool Box Talk - World Class Maintenance   EditedTool Box Talk - World Class Maintenance   Edited
Tool Box Talk - World Class Maintenance EditedRicky Smith CMRP, CMRT
 
Fuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCFuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCAcumen
 
Project management - kickoff - opensource erp
Project management - kickoff - opensource erpProject management - kickoff - opensource erp
Project management - kickoff - opensource erpThanh Nguyen
 
Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llNASAPMC
 
Run Your Oracle BI QA Cycles More Effectively
Run Your Oracle BI QA Cycles More EffectivelyRun Your Oracle BI QA Cycles More Effectively
Run Your Oracle BI QA Cycles More EffectivelyKPI Partners
 
Introduction To Agile
Introduction To AgileIntroduction To Agile
Introduction To AgileTony Deng
 
Flevy.com - Pricing a Consulting Project
Flevy.com - Pricing a Consulting ProjectFlevy.com - Pricing a Consulting Project
Flevy.com - Pricing a Consulting ProjectDavid Tracy
 

Similar to Does Better Scheduling Drive Execution Success? (20)

Fuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project ComplianceFuse Customer Perspectives Webinar: Project Compliance
Fuse Customer Perspectives Webinar: Project Compliance
 
Does better scheduling drive execution success ppt
Does better scheduling drive execution success pptDoes better scheduling drive execution success ppt
Does better scheduling drive execution success ppt
 
Opticon - Construction ERP Overview presentation
Opticon - Construction ERP Overview presentationOpticon - Construction ERP Overview presentation
Opticon - Construction ERP Overview presentation
 
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
Advanced Project Analysis and Project Benchmarking with Acumen Cloud™
 
Agile NCR 2013 - Archana Joshi - maintaining agile equilibrium v4
Agile NCR 2013 - Archana Joshi -  maintaining agile equilibrium v4Agile NCR 2013 - Archana Joshi -  maintaining agile equilibrium v4
Agile NCR 2013 - Archana Joshi - maintaining agile equilibrium v4
 
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder ExpectationsAchieving the Unachievable: Aligning a Project with Stakeholder Expectations
Achieving the Unachievable: Aligning a Project with Stakeholder Expectations
 
Forensic schedule analysis acesss
Forensic schedule analysis acesssForensic schedule analysis acesss
Forensic schedule analysis acesss
 
Process implementation at Droisys
Process implementation at DroisysProcess implementation at Droisys
Process implementation at Droisys
 
Process implementation v_1.1
Process implementation v_1.1Process implementation v_1.1
Process implementation v_1.1
 
Benchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned ValueBenchmarking Execution Performance and Earned Value
Benchmarking Execution Performance and Earned Value
 
LKG Project Level Presentation FEL in New Energies 2023.ppsx
LKG Project Level Presentation FEL in  New Energies 2023.ppsxLKG Project Level Presentation FEL in  New Energies 2023.ppsx
LKG Project Level Presentation FEL in New Energies 2023.ppsx
 
David Weir And Graham Fisher - Scaling Agility Across the Enterprise
David Weir And Graham Fisher - Scaling Agility Across the EnterpriseDavid Weir And Graham Fisher - Scaling Agility Across the Enterprise
David Weir And Graham Fisher - Scaling Agility Across the Enterprise
 
Key Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning ImplementationKey Considerations for a Successful Hyperion Planning Implementation
Key Considerations for a Successful Hyperion Planning Implementation
 
Tool Box Talk - World Class Maintenance Edited
Tool Box Talk - World Class Maintenance   EditedTool Box Talk - World Class Maintenance   Edited
Tool Box Talk - World Class Maintenance Edited
 
Fuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPCFuse Customer Perspectives Webinar: EPC
Fuse Customer Perspectives Webinar: EPC
 
Project management - kickoff - opensource erp
Project management - kickoff - opensource erpProject management - kickoff - opensource erp
Project management - kickoff - opensource erp
 
Ipao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis llIpao great houseetc-programmatic analysis ll
Ipao great houseetc-programmatic analysis ll
 
Run Your Oracle BI QA Cycles More Effectively
Run Your Oracle BI QA Cycles More EffectivelyRun Your Oracle BI QA Cycles More Effectively
Run Your Oracle BI QA Cycles More Effectively
 
Introduction To Agile
Introduction To AgileIntroduction To Agile
Introduction To Agile
 
Flevy.com - Pricing a Consulting Project
Flevy.com - Pricing a Consulting ProjectFlevy.com - Pricing a Consulting Project
Flevy.com - Pricing a Consulting Project
 

More from Acumen

How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownAcumen
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityAcumen
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Acumen
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentAcumen
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceAcumen
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsAcumen
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit KeynoteAcumen
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessAcumen
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Acumen
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Acumen
 
Acumen Risk Workshops Overview
Acumen Risk Workshops OverviewAcumen Risk Workshops Overview
Acumen Risk Workshops OverviewAcumen
 
Acumen Fuse Independent Review
Acumen Fuse Independent ReviewAcumen Fuse Independent Review
Acumen Fuse Independent ReviewAcumen
 
Fuse Information Sheet
Fuse Information SheetFuse Information Sheet
Fuse Information SheetAcumen
 
Improved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric AssessmentImproved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric AssessmentAcumen
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceAcumen
 
Project Simplification through Metric Analysis
Project Simplification through Metric AnalysisProject Simplification through Metric Analysis
Project Simplification through Metric AnalysisAcumen
 
Measuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyMeasuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyAcumen
 
The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsAcumen
 

More from Acumen (18)

How Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us DownHow Traditional Risk Reporting Has Let Us Down
How Traditional Risk Reporting Has Let Us Down
 
Developing Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule QualityDeveloping Standards for Enterprise Schedule Quality
Developing Standards for Enterprise Schedule Quality
 
Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360Dr. McNatty Webinar: An Introduction to Acumen 360
Dr. McNatty Webinar: An Introduction to Acumen 360
 
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise EnvironmentPMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
PMICOS Webinar: Building a Sound Schedule in an Enterprise Environment
 
Smarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project PerformanceSmarter Project Analysis and Improved Project Performance
Smarter Project Analysis and Improved Project Performance
 
Meeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance StandardsMeeting Project Schedule Compliance Standards
Meeting Project Schedule Compliance Standards
 
2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote2011 Acumen Annual Summit Keynote
2011 Acumen Annual Summit Keynote
 
Calgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project SuccessCalgary Breakfast Seminar: Predict and Influence Project Success
Calgary Breakfast Seminar: Predict and Influence Project Success
 
Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360Intelligent Project Acceleration: An Introduction to Acumen 360
Intelligent Project Acceleration: An Introduction to Acumen 360
 
Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0Advanced Project Analysis: An Introduction to Fuse 3.0
Advanced Project Analysis: An Introduction to Fuse 3.0
 
Acumen Risk Workshops Overview
Acumen Risk Workshops OverviewAcumen Risk Workshops Overview
Acumen Risk Workshops Overview
 
Acumen Fuse Independent Review
Acumen Fuse Independent ReviewAcumen Fuse Independent Review
Acumen Fuse Independent Review
 
Fuse Information Sheet
Fuse Information SheetFuse Information Sheet
Fuse Information Sheet
 
Improved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric AssessmentImproved Schedule Risk Analysis through Metric Assessment
Improved Schedule Risk Analysis through Metric Assessment
 
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct ScienceWhy Scheduling Mustn't Be Allowed to Become an Extinct Science
Why Scheduling Mustn't Be Allowed to Become an Extinct Science
 
Project Simplification through Metric Analysis
Project Simplification through Metric AnalysisProject Simplification through Metric Analysis
Project Simplification through Metric Analysis
 
Measuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range CertaintyMeasuring Risk Exposure through Risk Range Certainty
Measuring Risk Exposure through Risk Range Certainty
 
The Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk WorkshopsThe Art and Science Behind Successful Risk Workshops
The Art and Science Behind Successful Risk Workshops
 

Recently uploaded

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Servicegiselly40
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure servicePooja Nehwal
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024Scott Keck-Warren
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonAnna Loughnan Colquhoun
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxMalak Abu Hammad
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhisoniya singh
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Alan Dix
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Drew Madelung
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024Results
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slidevu2urc
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 3652toLead Limited
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 

Recently uploaded (20)

CNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of ServiceCNv6 Instructor Chapter 6 Quality of Service
CNv6 Instructor Chapter 6 Quality of Service
 
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure serviceWhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
WhatsApp 9892124323 ✓Call Girls In Kalyan ( Mumbai ) secure service
 
SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024SQL Database Design For Developers at php[tek] 2024
SQL Database Design For Developers at php[tek] 2024
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Data Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt RobisonData Cloud, More than a CDP by Matt Robison
Data Cloud, More than a CDP by Matt Robison
 
The Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptxThe Codex of Business Writing Software for Real-World Solutions 2.pptx
The Codex of Business Writing Software for Real-World Solutions 2.pptx
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | DelhiFULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
FULL ENJOY 🔝 8264348440 🔝 Call Girls in Diplomatic Enclave | Delhi
 
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...Swan(sea) Song – personal research during my six years at Swansea ... and bey...
Swan(sea) Song – personal research during my six years at Swansea ... and bey...
 
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
Strategies for Unlocking Knowledge Management in Microsoft 365 in the Copilot...
 
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
Transcript: #StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024A Call to Action for Generative AI in 2024
A Call to Action for Generative AI in 2024
 
Histor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slideHistor y of HAM Radio presentation slide
Histor y of HAM Radio presentation slide
 
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
Tech-Forward - Achieving Business Readiness For Copilot in Microsoft 365
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 

Does Better Scheduling Drive Execution Success?

  • 1. // Does Better Scheduling Drive Execution Success? Dr. Dan Patterson PMP// CEO Acumen May 9 2012 //
  • 2. // Acumen Realistic Scheduling Proven Project Analytics // S1 The Base // S2 Critiqued ◦  Project Management Software // S3 Risk-Adjusted ◦  Oracle Primavera partner // S4 Optimized ◦  Insight into challenges & use of // S5 Team-Aligned analytics to overcome them Product Offerings ◦  Core Concepts: 1.  Project success requires a sound plan Acumen Fuse® 2.  Forecast accuracy requires risk Risk Workshops consideration Software Training May 10, 2012 // 2
  • 3. // Presentation Overview A Case Study S1//S5 Schedule Maturity Model Developing sound schedules Schedule Index™ Baseline Compliance™ Acumen Fuse analysis Case Study/software demo Questions & Answers May 10, 2012 // 3
  • 4. // Schedule Maturity Framework Acumen S1//S5 6   •  Schedule  Basis    S1   •  Owner/contractor  schedule   5   •  Cri/qued  Schedule   S2   •  Ensure  structural  integrity   4   Chance  of  Sucess   •  Risk-­‐Adjusted  Schedule   3   S3   •  Account  for  risk/uncertainty   2   •  Op/mized  Target  Scenarios   S4   •  Schedule  accelera>on   1   •  Team  Validated  Scenario   0   0   1   2   3   4   5   6   S5   •  Buy-­‐in  on  op>miza>on   Maturity  Level   Measure quality through the Fuse Schedule Index™ May 10, 2012 // 4
  • 5. // Schedule Quality Measurement Metric Analysis ◦  Legacy ◦  duration, constraints, excessive lags, negative float ◦  Industry Standards ◦  DCMA 14 Point Assessment ◦  NDIA GASP/ GAO ◦  Acumen Metrics ◦  Logic Density™ ◦  Insufficient Detail™ May 10, 2012 // 5
  • 6. // Acumen Schedule Metrics Advanced Project Insight Finish   Insufficient   Logic   Logic   Compliance™   Detail™   Density™   Hotspot™   • Accurate   • Ac>vity  V   • Measure  of   • Timely  start?   measure  of   project  dura>on   complexity/ performance   completeness   Milestone   Broad  Risk   Float  Ra>o™   Redundancy   Ra>o™   Range   • Degree  of   Index™   • Detail  V   • Check  for   flexibility  per   • Non-­‐needed   repor>ng   erroneous  risk   day  of  work   logic   input   //
  • 7. // Logic Density™ Planning Consistency ◦  Determine Logic Hotspots™ in schedule ◦  Indication of sufficient logic ◦  Excellent means of trending detail level More  defini>on   needed   May 10, 2012 // 7
  • 8. // Advanced Logic Analysis Sound Basis of Schedule ◦  Use of FS, FF, SS, FS links ◦  Lags & Leads ◦  Lags hide schedule detail redundant ◦  Leads cause reverse dates A ◦  Circular logic between projects ◦  Out-of-Sequence updates B ◦  Open ends/missing logic C ◦  Open start/finish (hidden open ends) ◦  Logic Density ◦  Logic Hotspot ◦  Redundancy Index //
  • 9. // Measuring Schedule Quality Fuse Schedule Index™ May 10, 2012 // 9
  • 10. // Baseline Compliance Index™ Examines  how   many  ac>vi>es   fell  within  the   expected   repor>ng  period   //
  • 11. // Baseline Compliance™ Performance Analysis ◦  More than date comparison ◦  Measures period-compliance ◦  Included in Fuse® library 100%   50%   0%   May 10, 2012 // 11
  • 12. // Acumen Fuse Platform Enterprise Project Analysis Metric   Analyzer   ◦  Fuse: analytics platform Logic   ◦  Improves schedule quality Analyzer   ◦  Insight into performance Forensic   Analyzer   ◦  Fuse 360: goal-based acceleration Schedule   Cleanser   ◦  Schedule Acceleration Schedule   ◦  Decision-support Accelerator   // May 10, 2012
  • 13. // Metric Analysis Slice & Dice Benefit: " Pinpoint shortcomings " Project characteristics " Slice and dice Schedule   Cost   Performance   Characteris>cs   Earned  Value   Risk   • Logic   • Overrun   • Status   • Level  of  detail   • CPI/SPI   • Exposure   • Float   • Capacity   • Completed   • Constrained   • Trending   • Hot  spots   • Dura>on   • Burn  rates   • Delayed   • Riding  Data   • Earned   • Hidden  paths   Date   schedule   // May 10, 2012
  • 14. // Metrics to fit: Criteria, Thresholds Fuse Metric Editor //
  • 15. // Fuse Schedule Cleanser™ Actionable Insight //
  • 16. // Project Forensics Insight into Schedule Cleanse // May 10, 2012
  • 17. // Claims Analysis Insight into project variances ◦  Advanced forensics ◦  Fuse gives meaning to the impact of changes ◦  Pinpoints changes to critical/ driving path ◦  Every single project attribute can be checked ◦  Calendar definition changes // May 10, 2012
  • 18. Case Study // Acumen Fuse® Software Demonstration //
  • 19. // Case Study Owner/contractor Alignment •  Houston-based oil/gas owner •  Objective: •  More on-time completion for projects over $250MM •  Encourage more mature contractor schedules •  Overcome “brain drain” in scheduling •  How achieved: •  Mandated contractor Fuse Schedule Index of 75+ •  Gave contractor opportunity to self-assess //
  • 20. // Quality Planning Truly Drives Success 100%   Probability of On-Time Completion 90%   80%   70%   60%   50%   40%   30%   20%   10%   0%   0%   10%   20%   30%   40%   50%   60%   70%   80%   90%   100%   Fuse Schedule Index™ May 10, 2012 // 20
  • 21. // Q&A //
  • 22. More information: White papers: www.projectacumen.com Software Trial: www.projectacumen.com/trial // Twitter: @projectacumen Email: info@projectacumen.com //