HIRARC OF SOIL INVESTIGATION AT GADANG 
CONSTRUCTION SITE 
MOHAMAD ARIFFIN BIN SAMSURI 
DOSHM0713001247 
SEMESTA 3 
BATCH 26G2 
SIR MOHD FARIS BIN MOHD ZAWAWI
introduction 
• Gadang Holdings Berhad (Gadang) was incorporated in Malaysia on 6 October 
1993 as a public limited company under the name of Lai Sing Holdings Berhad 
and was subsequently changed to its present name on 7 November 1997 
• Gadang is an investment holding company while its subsidiaries' core businesses 
are in civil engineering and building construction, property development, water 
concession, mechanical and electrical engineering services and general trading.
COMPANY VISION AND MISION 
VISION 
- to build a reputable Gadang 
- deliver quality products 
- derive positive return. 
MISION 
- to adopt a hands on approach. 
- to be result oriented. 
- to achieve continual growth.
PROJECT LOCATION
WORK PROCESS 
site cleaning 
soil 
investigation 
earth work 
demolition 
work 
bored pile 
concrete 
work 
road work 
drainage 
work
ACTIVITY OF SOIL INVESTIGATION 
Traffic management 
Setup & 
maintenance of the 
drilling & grouting 
machine 
Position the drilling 
machine 
Nights works 
Grouting works 
Drilling works
OBJECTIVE 
• To identify three (3) Safety Hazards and two (2) Health Hazards at the workplace and 
discuss in detail the techniques used to identify all types of hazards. 
• To identify the risk at the workplace 
• To reduce the hazard from happen again 
• To discuss and give appropriate suggestions for control measures in order to eliminate, 
reduce, and minimize the risk of the most critical hazards 
• To explain the implications of the most critical hazards (safety & health hazard) that has 
been identified and their preventive measure
METHODOLOGY 
WORKPLACE HAZARD 
OBSERVATION: 
• To observe the soil investigation 
activities involved and the hazard 
encountered during performing the 
activities. 
• Observe any unsafe act, hazard, 
dangerous at the construction site 
INTERVIEW WITH WORKERS 
• Interview with safety officer Abdul Razak 
Example of question being asking during the interview 
as below; 
How long you work at this company? 
What are the work activities taken until the task is 
completed? 
Did you notify any hazards occur during each job work 
activity? 
What are you concern of during the work activity? 
REVIEW OF AVAILABLE 
INFORMATION 
• Information were collected from the 
company 
• Reviewing the record of workplace for 
example document
LIKELIHOOD TABLE 
EXAMPLE: 
Likelihood 
(L) 
Example Rating 
Most likely The most likely result of the hazard / event being realized 5 
Possible Has a good chance of occurring and is not unusual 4 
Conceivable Might be occur at some time in future 3 
Remote Has not been known to occur after many years 2 
Inconceivable Is practically impossible and has never occurred 1 
SEVERITY TABLE: 
Severity Example Rating 
Catastrophic Numerous fatalities, irrecoverable property damage and 
productivity 
5 
Fatal Approximately one single fatality major property damage if hazard 
is realized 
4 
Serious Non- fatal injury, permanent disability 3 
Minor Disabling but not permanent injury 2 
Negligible Minor abrasions, bruises, cuts, first aid type injury 1
RISK MATRIX TABLE: 
Severity (S) 
Likelihood 
(L) 
1 2 3 4 5 
5 5 10 15 20 25 
4 4 8 12 16 20 
3 3 6 9 12 15 
2 2 4 6 8 10 
1 1 2 3 4 5
HIRARC RESULT 
Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI 
Hazard identification Risk analysis Risk control 
No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 
1 Temporary 
traffic control 
Accident due to 
mobilization of 
machineries 
(crash by heavy 
machinery) 
(safety) 
Serious or 
minor Injury, 
bone 
fracture, 
traffic 
congestion 
Toolbox meeting, 
daily workplace 
inspection, provide 
complete set of ppe 
3 3 9 
medium 
ELIMINATION: N/A 
SUBSTITUTION: N/A 
ISOLATION: N/A 
ENGINEERING CONTROL: N/A 
ADMINISTRATIVE CONTROL: provide 
general workers to direct traffic, competent 
operator and driver with valid driving license, 
implement traffic management as per approved 
by management, Provide clear & working space 
and access with enough flagmen to control the 
traffic. 
PERSONAL PROTECTIVE EQUIPMENT: 
provide hazard warning blinker light 
FMA1987 
(building 
operation and 
works of 
engineering 
construction) 
(runways and 
ramps) 
FMA 1987 
(person in 
charge)(machiner 
y required to be 
in charge of 
persons holding 
certificates of 
competency)(sect 
ion 13, 
assessment of 
drivers)
Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI 
Hazard identification Risk analysis Risk control 
No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 
2 Night work Struck by 
vehicles 
(public transport 
and heavy 
machinery at 
workstation) 
(safety) 
Bone 
fracture 
Toolbox meeting, 
daily workplace 
inspection, provide 
complete set of 
ppe 
5 2 10 
medium 
ELIMINATION: N/A 
SUBSTITUTION: N/A 
ISOLATION: N/A 
ENGINEERING CONTROL: N/A 
ADMINISTRATIVE CONTROL: briefing before 
work, job rotation (arranging work shift to 
workers). provide enough lighting to works, 
provide warning sings 
PERSONAL PROTECTIVE EQUIPMENT: provide 
lighting helmet, reflected light jacket 
OSHA 
1994(general 
duties of 
employers and 
self-employers 
persons)(section 
15)
Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI 
Hazard identification Risk analysis Risk control 
No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 
3 Drilling works Prolonged 
Extremely 
vibration 
(health) 
White finger 
(also known 
as "dead 
finger" ) - 
damage to 
hands 
causing 
whiteness 
and pain in 
the fingers 
Toolbox meeting, 
daily workplace 
inspection, provide 
complete set of ppe 
3 2 6 
medium 
ELIMINATION: N/A 
SUBSTITUTION: N/A 
ISOLATION: N/A 
ENGINEERING CONTROL: 
N/A 
ADMINISTRATIVE CONTROL: Job rotation 
every one hour, frequent short break, 
maintenance the machines 
PERSONAL PROTECTIVE EQUIPMENT: 
Provide glove reduce vibration (leather) 
OSHA 1994 
(safety and health 
officer)(duties of 
safety and health 
officers) 
OSHA 
1994(USECHH 
2000) (use of 
approved 
personal 
protective 
equipment)
Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI 
Hazard identification Risk analysis Risk control 
No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 
4 Drilling work Exposed to sand 
dust inhalation 
(health) 
Respiratory 
problem, eye 
irritation 
Toolbox meeting, 
daily workplace 
inspection, provide 
complete set of ppe 
4 3 12 
medium 
ELIMINATION: N/A 
SUBSTITUTION: N/A 
ISOLATION: isolate the worker(was related to 
drilling work) 
ENGINEERING CONTROL: provide the 
barrier around the work station and install the 
ventilation 
ADMINISTRATIVE CONTROL: job rotation, 
and frequent short break, Provide shift work for 
the worker to reduce the duration of workers 
exposed to the soil sand dust. 
PERSONAL PROTECTIVE EQUIPMENT: 
Provide respirator, (filter mask) goggle, face 
shield 
FMA 1987 
REGULATIONS 
1984 
(RESPIRATORY 
PREOTECTION)
Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI 
Hazard identification Risk analysis Risk control 
No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 
5 Drilling work Excessive extreme 
heat 
Heat 
stress(sweati 
ng)/skin 
redness/fainti 
ng 
Toolbox meeting, 
daily workplace 
inspection, provide 
complete set of ppe 
5 2 10 
medium 
ELIMINATION: N/A 
SUBSTITUTION: N/A 
ISOLATION: N/A 
ENGINEERING CONTROL:N/A 
ADMINISTRATIVE CONTROL: provide 
water fan, provide canopy to protect worker from 
heat. 
PERSONAL PROTECTIVE EQUIPMENT: 
provide cotton clothes or clothes absorb 
sweating. 
OSHA 
1994(general 
duties of 
employers and 
self-employers 
persons)(section 
15)
DISCUSSION 
MOST CRITICAL HAZARD (SAFETY HAZARD) 
No Work activity Hazard Effect Existing control L S Risk 
2 Night works Struck by 
vehicles (public 
transport and 
heavy machinery 
at workstation) 
(safety) 
Bone fracture Toolbox meeting, daily 
workplace inspection, 
provide complete set of ppe 
5 2 10 
The worker also has been supplied by complete all ppe . Workers who work at nights are not aware of the hazard 
related to the work activity. The effect of the hazard is workers will minor injury, bone fracture, or more badly. 
The implication of workers towards nights, the worker might be exposed to accident.
MOST CRITICAL HAZARD (HEALTH HAZARD 
No Work activity Hazard Effect Existing control L S Risk 
4 
drilling work Expose to sand 
dust inhalation 
Respiratory 
problem 
Toolbox meeting, daily 
workplace inspection, 
provide complete set of ppe, 
4 3 12 
This hazard is the most significant critical health hazards because the worker also has been inducted by safety personnel and 
provide complete set of PPE. Workers who work with drilling work are not aware of the hazard related to the work activity. 
The effect of the hazard workers will get respiratory problem due to drilling sand dust inhalation. The implication of workers 
towards drilling sand dust inhalation.
RECOMMENDATION FOR MOST CRITICAL SAFETY HAZARD 
No Hierarchy of control Control Measure 
1. 
Elimination 
Not applicable 
Description: 
a) There are nothing can be eliminate in this process 
2. 
Substitution 
Not applicable 
Description: 
a) There are nothing can be substitute in the process 
3. Isolation 
Not applicable 
Description: 
a) There are nothing can be substitute in the process 
4. Engineering control 
Not applicable 
Description 
a) There are nothing can be substitute in the process 
5 
Administration control 
a) briefing before work 
b) job rotation (arranging work shift to workers) 
c) provide enough lighting to works 
Description 
a) Increase awareness about the hazard among workers during the toolbox meeting before work is 
carried out 
b) light is important for employees who work at night to avoid from accident happen at the workplace 
6. Personal Protective Equipment (PPE) a) provide lighting helmet 
b) reflected light jacket 
Description: 
a) lighting helmet and reflect light jacket is important because as one way to facilitate the work at night 
or as a signalman to vehicles
RECOMMENDATION FOR MOST CRITICAL HEALTH HAZARD 
No Hierarchy of control Control Measure 
1. Elimination 
Not applicable 
Description: 
a) There are nothing can be eliminate in this process 
2. Substitution 
Not applicable 
Description: 
a) There are nothing can be substitute in the process 
3. Isolation 
a) isolate other worker 
Description: 
a) Only the person who are involved in drilling works is needed in the area 
4. Engineering control 
a) install the barrier around the work station 
Description: 
a) To reduce dust from directly exposed to our respirator system 
5. Administration control 
a) Job rotation and frequent short break or provide the work shift for the worker 
Description: 
a) Job rotation at once in 2 hours, 
b) Work shift to workers is necessary 
6. Personal Protective Equipment 
(PPE) 
a) Provide respirator (filter mask) goggle, face shield 
Description: 
a) respirator is needed while drilling the sand for protection of the worker from inhaled the dust
CONCLUSION 
 In order to reduce the hazard or most critical hazard rate, the employer should show commitment 
towards safety and health practices and therefore give full priority to promote and enforce the 
safety and health rules in workplace. 
 Hierarchy of control were use in order to minimize and control the most critical hazard that exist at 
the workplace. 
 To ensure the safety culture can be implemented in an organization. 
 the management and workers have to take part in any safety and health program and give a full 
cooperation when comes to safety and health issues.
APPENDIX 
Thanks for listening 
Soil investigation

More Related Content

What's hot

Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay versionHazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay versionNorrazman Zaiha Zainol
 
Topik 4 pengurusan kselamatan & kesihatan pkerjaan
Topik 4 pengurusan kselamatan & kesihatan pkerjaanTopik 4 pengurusan kselamatan & kesihatan pkerjaan
Topik 4 pengurusan kselamatan & kesihatan pkerjaanWan Nurhidayati Wan Johari
 
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...PECB
 
BINAPURI OSH Management System Awareness Training
BINAPURI OSH Management System Awareness TrainingBINAPURI OSH Management System Awareness Training
BINAPURI OSH Management System Awareness Trainingmuss
 
Keselamatan Semasa Mengendalikan Bahan Kimia Berbahaya
Keselamatan Semasa Mengendalikan Bahan Kimia BerbahayaKeselamatan Semasa Mengendalikan Bahan Kimia Berbahaya
Keselamatan Semasa Mengendalikan Bahan Kimia BerbahayaAhmad Aidil Nasir
 
Factories and machinery act 1967 (fma 1967
Factories and machinery act 1967 (fma 1967Factories and machinery act 1967 (fma 1967
Factories and machinery act 1967 (fma 1967siti hamidah
 
ICOP For Safe Working in A Confined Space 2010 by Mr Husdin Che Mat
ICOP For Safe Working in A Confined Space 2010 by Mr Husdin Che MatICOP For Safe Working in A Confined Space 2010 by Mr Husdin Che Mat
ICOP For Safe Working in A Confined Space 2010 by Mr Husdin Che MatMoon Girl
 
Akta 514 Keselamatan dan Kesihatan Pekerja
Akta 514 Keselamatan dan Kesihatan PekerjaAkta 514 Keselamatan dan Kesihatan Pekerja
Akta 514 Keselamatan dan Kesihatan PekerjaAhmad Nazib
 
PERANAN ERT / OKK & PERSEDIAAN LATIHAN FIRE DRILL
PERANAN ERT / OKK & PERSEDIAAN LATIHAN FIRE DRILLPERANAN ERT / OKK & PERSEDIAAN LATIHAN FIRE DRILL
PERANAN ERT / OKK & PERSEDIAAN LATIHAN FIRE DRILLMuhd Athir
 
Chapter 1 occupational,safety and health
Chapter 1 occupational,safety and healthChapter 1 occupational,safety and health
Chapter 1 occupational,safety and healthFarizan Azahri
 

What's hot (20)

Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay versionHazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
Hazard Identification, Risk Assessment and Risk Control (HIRARC) Malay version
 
Hirarc
HirarcHirarc
Hirarc
 
Topik 4 pengurusan kselamatan & kesihatan pkerjaan
Topik 4 pengurusan kselamatan & kesihatan pkerjaanTopik 4 pengurusan kselamatan & kesihatan pkerjaan
Topik 4 pengurusan kselamatan & kesihatan pkerjaan
 
HIRARC
HIRARCHIRARC
HIRARC
 
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
PECB Webinar: Occupational Hazard Identification Risk Assessment and Risk Con...
 
BINAPURI OSH Management System Awareness Training
BINAPURI OSH Management System Awareness TrainingBINAPURI OSH Management System Awareness Training
BINAPURI OSH Management System Awareness Training
 
HIRADC
HIRADCHIRADC
HIRADC
 
Topik 3 punca kmalangan&pcegahan
Topik 3 punca kmalangan&pcegahanTopik 3 punca kmalangan&pcegahan
Topik 3 punca kmalangan&pcegahan
 
Chapter 01 -Introduction of OSHA
Chapter 01 -Introduction of OSHAChapter 01 -Introduction of OSHA
Chapter 01 -Introduction of OSHA
 
Keselamatan Semasa Mengendalikan Bahan Kimia Berbahaya
Keselamatan Semasa Mengendalikan Bahan Kimia BerbahayaKeselamatan Semasa Mengendalikan Bahan Kimia Berbahaya
Keselamatan Semasa Mengendalikan Bahan Kimia Berbahaya
 
Factories and machinery act 1967 (fma 1967
Factories and machinery act 1967 (fma 1967Factories and machinery act 1967 (fma 1967
Factories and machinery act 1967 (fma 1967
 
HIRARC
HIRARCHIRARC
HIRARC
 
Chapter 3 - OSHA Management
Chapter 3 - OSHA ManagementChapter 3 - OSHA Management
Chapter 3 - OSHA Management
 
ICOP For Safe Working in A Confined Space 2010 by Mr Husdin Che Mat
ICOP For Safe Working in A Confined Space 2010 by Mr Husdin Che MatICOP For Safe Working in A Confined Space 2010 by Mr Husdin Che Mat
ICOP For Safe Working in A Confined Space 2010 by Mr Husdin Che Mat
 
Akta 514 Keselamatan dan Kesihatan Pekerja
Akta 514 Keselamatan dan Kesihatan PekerjaAkta 514 Keselamatan dan Kesihatan Pekerja
Akta 514 Keselamatan dan Kesihatan Pekerja
 
Hirarc
HirarcHirarc
Hirarc
 
PERANAN ERT / OKK & PERSEDIAAN LATIHAN FIRE DRILL
PERANAN ERT / OKK & PERSEDIAAN LATIHAN FIRE DRILLPERANAN ERT / OKK & PERSEDIAAN LATIHAN FIRE DRILL
PERANAN ERT / OKK & PERSEDIAAN LATIHAN FIRE DRILL
 
Jkk di tempat kerja
Jkk di tempat kerjaJkk di tempat kerja
Jkk di tempat kerja
 
Occupational safety and health act 1994 (act 514)
Occupational safety and health act 1994 (act 514)Occupational safety and health act 1994 (act 514)
Occupational safety and health act 1994 (act 514)
 
Chapter 1 occupational,safety and health
Chapter 1 occupational,safety and healthChapter 1 occupational,safety and health
Chapter 1 occupational,safety and health
 

Similar to Presentation HIRARC Sem 3

Boom Lift - working from_2.docx
Boom Lift - working from_2.docxBoom Lift - working from_2.docx
Boom Lift - working from_2.docxolorunyomi wale
 
Safety equipments
Safety equipments Safety equipments
Safety equipments Dip Kadia
 
EDEAGHE ONOSABUNA GABRIEL CV (1)
EDEAGHE ONOSABUNA GABRIEL CV (1)EDEAGHE ONOSABUNA GABRIEL CV (1)
EDEAGHE ONOSABUNA GABRIEL CV (1)Gabriel Edeaghe
 
Core Risk Assessment for Office work.docx
Core  Risk Assessment for Office work.docxCore  Risk Assessment for Office work.docx
Core Risk Assessment for Office work.docxIbrahimEsmat
 
HSE Management Plan
HSE Management PlanHSE Management Plan
HSE Management PlanPhilip Hà
 
Construction Site Health & Safety
Construction Site Health & SafetyConstruction Site Health & Safety
Construction Site Health & SafetySAURABH SINGH
 
02._SGW-_Risk_Assessment__Management.pptx
02._SGW-_Risk_Assessment__Management.pptx02._SGW-_Risk_Assessment__Management.pptx
02._SGW-_Risk_Assessment__Management.pptxsafetygoodwe
 
Safe work procedure1
Safe work procedure1Safe work procedure1
Safe work procedure1Jahanzeb Khan
 
VJ Presentation 3 Oct 2022.pptx
VJ Presentation 3 Oct 2022.pptxVJ Presentation 3 Oct 2022.pptx
VJ Presentation 3 Oct 2022.pptxViejayBalachandar
 
SAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITESAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITEHasnizam Md Saad
 
SAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITESAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITEHasnizam Md Saad
 

Similar to Presentation HIRARC Sem 3 (20)

Boom Lift - working from_2.docx
Boom Lift - working from_2.docxBoom Lift - working from_2.docx
Boom Lift - working from_2.docx
 
Safety equipments
Safety equipments Safety equipments
Safety equipments
 
EDEAGHE ONOSABUNA GABRIEL CV (1)
EDEAGHE ONOSABUNA GABRIEL CV (1)EDEAGHE ONOSABUNA GABRIEL CV (1)
EDEAGHE ONOSABUNA GABRIEL CV (1)
 
Core Risk Assessment for Office work.docx
Core  Risk Assessment for Office work.docxCore  Risk Assessment for Office work.docx
Core Risk Assessment for Office work.docx
 
Safety plan
Safety planSafety plan
Safety plan
 
HSE Management Plan
HSE Management PlanHSE Management Plan
HSE Management Plan
 
MUSADDIQ UPDATED CV
MUSADDIQ UPDATED CVMUSADDIQ UPDATED CV
MUSADDIQ UPDATED CV
 
Construction Site Health & Safety
Construction Site Health & SafetyConstruction Site Health & Safety
Construction Site Health & Safety
 
Safety in manufacturing
Safety in manufacturingSafety in manufacturing
Safety in manufacturing
 
Summer training report
Summer training reportSummer training report
Summer training report
 
resume updated
resume updatedresume updated
resume updated
 
RESUME
RESUMERESUME
RESUME
 
1. Resume
1. Resume1. Resume
1. Resume
 
02._SGW-_Risk_Assessment__Management.pptx
02._SGW-_Risk_Assessment__Management.pptx02._SGW-_Risk_Assessment__Management.pptx
02._SGW-_Risk_Assessment__Management.pptx
 
Safe work procedure1
Safe work procedure1Safe work procedure1
Safe work procedure1
 
Safety cycle
Safety cycleSafety cycle
Safety cycle
 
Introduction 1
Introduction 1Introduction 1
Introduction 1
 
VJ Presentation 3 Oct 2022.pptx
VJ Presentation 3 Oct 2022.pptxVJ Presentation 3 Oct 2022.pptx
VJ Presentation 3 Oct 2022.pptx
 
SAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITESAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITE
 
SAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITESAFETY REQUIREMENTS & GUIDELINES AT SITE
SAFETY REQUIREMENTS & GUIDELINES AT SITE
 

Recently uploaded

❤️Call Girl Service In Chandigarh☎️9814379184☎️ Call Girl in Chandigarh☎️ Cha...
❤️Call Girl Service In Chandigarh☎️9814379184☎️ Call Girl in Chandigarh☎️ Cha...❤️Call Girl Service In Chandigarh☎️9814379184☎️ Call Girl in Chandigarh☎️ Cha...
❤️Call Girl Service In Chandigarh☎️9814379184☎️ Call Girl in Chandigarh☎️ Cha...Sheetaleventcompany
 
Bandra East [ best call girls in Mumbai Get 50% Off On VIP Escorts Service 90...
Bandra East [ best call girls in Mumbai Get 50% Off On VIP Escorts Service 90...Bandra East [ best call girls in Mumbai Get 50% Off On VIP Escorts Service 90...
Bandra East [ best call girls in Mumbai Get 50% Off On VIP Escorts Service 90...Angel
 
Control of Local Blood Flow: acute and chronic
Control of Local Blood Flow: acute and chronicControl of Local Blood Flow: acute and chronic
Control of Local Blood Flow: acute and chronicMedicoseAcademics
 
Race Course Road } Book Call Girls in Bangalore | Whatsapp No 6378878445 VIP ...
Race Course Road } Book Call Girls in Bangalore | Whatsapp No 6378878445 VIP ...Race Course Road } Book Call Girls in Bangalore | Whatsapp No 6378878445 VIP ...
Race Course Road } Book Call Girls in Bangalore | Whatsapp No 6378878445 VIP ...dishamehta3332
 
Gastric Cancer: Сlinical Implementation of Artificial Intelligence, Synergeti...
Gastric Cancer: Сlinical Implementation of Artificial Intelligence, Synergeti...Gastric Cancer: Сlinical Implementation of Artificial Intelligence, Synergeti...
Gastric Cancer: Сlinical Implementation of Artificial Intelligence, Synergeti...Oleg Kshivets
 
Cara Menggugurkan Kandungan Dengan Cepat Selesai Dalam 24 Jam Secara Alami Bu...
Cara Menggugurkan Kandungan Dengan Cepat Selesai Dalam 24 Jam Secara Alami Bu...Cara Menggugurkan Kandungan Dengan Cepat Selesai Dalam 24 Jam Secara Alami Bu...
Cara Menggugurkan Kandungan Dengan Cepat Selesai Dalam 24 Jam Secara Alami Bu...Cara Menggugurkan Kandungan 087776558899
 
👉 Amritsar Call Girls 👉📞 8725944379 👉📞 Just📲 Call Ruhi Call Girl Near Me Amri...
👉 Amritsar Call Girls 👉📞 8725944379 👉📞 Just📲 Call Ruhi Call Girl Near Me Amri...👉 Amritsar Call Girls 👉📞 8725944379 👉📞 Just📲 Call Ruhi Call Girl Near Me Amri...
👉 Amritsar Call Girls 👉📞 8725944379 👉📞 Just📲 Call Ruhi Call Girl Near Me Amri...Sheetaleventcompany
 
Cardiac Output, Venous Return, and Their Regulation
Cardiac Output, Venous Return, and Their RegulationCardiac Output, Venous Return, and Their Regulation
Cardiac Output, Venous Return, and Their RegulationMedicoseAcademics
 
Circulatory Shock, types and stages, compensatory mechanisms
Circulatory Shock, types and stages, compensatory mechanismsCirculatory Shock, types and stages, compensatory mechanisms
Circulatory Shock, types and stages, compensatory mechanismsMedicoseAcademics
 
Intramuscular & Intravenous Injection.pptx
Intramuscular & Intravenous Injection.pptxIntramuscular & Intravenous Injection.pptx
Intramuscular & Intravenous Injection.pptxsaranpratha12
 
Dehradun Call Girl Service ❤️🍑 8854095900 👄🫦Independent Escort Service Dehradun
Dehradun Call Girl Service ❤️🍑 8854095900 👄🫦Independent Escort Service DehradunDehradun Call Girl Service ❤️🍑 8854095900 👄🫦Independent Escort Service Dehradun
Dehradun Call Girl Service ❤️🍑 8854095900 👄🫦Independent Escort Service DehradunSheetaleventcompany
 
🚺LEELA JOSHI WhatsApp Number +91-9930245274 ✔ Unsatisfied Bhabhi Call Girls T...
🚺LEELA JOSHI WhatsApp Number +91-9930245274 ✔ Unsatisfied Bhabhi Call Girls T...🚺LEELA JOSHI WhatsApp Number +91-9930245274 ✔ Unsatisfied Bhabhi Call Girls T...
🚺LEELA JOSHI WhatsApp Number +91-9930245274 ✔ Unsatisfied Bhabhi Call Girls T...soniya pandit
 
💚Chandigarh Call Girls 💯Riya 📲🔝8868886958🔝Call Girls In Chandigarh No💰Advance...
💚Chandigarh Call Girls 💯Riya 📲🔝8868886958🔝Call Girls In Chandigarh No💰Advance...💚Chandigarh Call Girls 💯Riya 📲🔝8868886958🔝Call Girls In Chandigarh No💰Advance...
💚Chandigarh Call Girls 💯Riya 📲🔝8868886958🔝Call Girls In Chandigarh No💰Advance...Sheetaleventcompany
 
tongue disease lecture Dr Assadawy legacy
tongue disease lecture Dr Assadawy legacytongue disease lecture Dr Assadawy legacy
tongue disease lecture Dr Assadawy legacyDrMohamed Assadawy
 
Call 8250092165 Patna Call Girls ₹4.5k Cash Payment With Room Delivery
Call 8250092165 Patna Call Girls ₹4.5k Cash Payment With Room DeliveryCall 8250092165 Patna Call Girls ₹4.5k Cash Payment With Room Delivery
Call 8250092165 Patna Call Girls ₹4.5k Cash Payment With Room DeliveryJyoti singh
 
Electrocardiogram (ECG) physiological basis .pdf
Electrocardiogram (ECG) physiological basis .pdfElectrocardiogram (ECG) physiological basis .pdf
Electrocardiogram (ECG) physiological basis .pdfMedicoseAcademics
 
Whitefield { Call Girl in Bangalore ₹7.5k Pick Up & Drop With Cash Payment 63...
Whitefield { Call Girl in Bangalore ₹7.5k Pick Up & Drop With Cash Payment 63...Whitefield { Call Girl in Bangalore ₹7.5k Pick Up & Drop With Cash Payment 63...
Whitefield { Call Girl in Bangalore ₹7.5k Pick Up & Drop With Cash Payment 63...dishamehta3332
 
Pune Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Pune No💰Adva...
Pune Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Pune No💰Adva...Pune Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Pune No💰Adva...
Pune Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Pune No💰Adva...Sheetaleventcompany
 
Genuine Call Girls Hyderabad 9630942363 Book High Profile Call Girl in Hydera...
Genuine Call Girls Hyderabad 9630942363 Book High Profile Call Girl in Hydera...Genuine Call Girls Hyderabad 9630942363 Book High Profile Call Girl in Hydera...
Genuine Call Girls Hyderabad 9630942363 Book High Profile Call Girl in Hydera...GENUINE ESCORT AGENCY
 
Nagpur Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Nagpur No💰...
Nagpur Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Nagpur No💰...Nagpur Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Nagpur No💰...
Nagpur Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Nagpur No💰...Sheetaleventcompany
 

Recently uploaded (20)

❤️Call Girl Service In Chandigarh☎️9814379184☎️ Call Girl in Chandigarh☎️ Cha...
❤️Call Girl Service In Chandigarh☎️9814379184☎️ Call Girl in Chandigarh☎️ Cha...❤️Call Girl Service In Chandigarh☎️9814379184☎️ Call Girl in Chandigarh☎️ Cha...
❤️Call Girl Service In Chandigarh☎️9814379184☎️ Call Girl in Chandigarh☎️ Cha...
 
Bandra East [ best call girls in Mumbai Get 50% Off On VIP Escorts Service 90...
Bandra East [ best call girls in Mumbai Get 50% Off On VIP Escorts Service 90...Bandra East [ best call girls in Mumbai Get 50% Off On VIP Escorts Service 90...
Bandra East [ best call girls in Mumbai Get 50% Off On VIP Escorts Service 90...
 
Control of Local Blood Flow: acute and chronic
Control of Local Blood Flow: acute and chronicControl of Local Blood Flow: acute and chronic
Control of Local Blood Flow: acute and chronic
 
Race Course Road } Book Call Girls in Bangalore | Whatsapp No 6378878445 VIP ...
Race Course Road } Book Call Girls in Bangalore | Whatsapp No 6378878445 VIP ...Race Course Road } Book Call Girls in Bangalore | Whatsapp No 6378878445 VIP ...
Race Course Road } Book Call Girls in Bangalore | Whatsapp No 6378878445 VIP ...
 
Gastric Cancer: Сlinical Implementation of Artificial Intelligence, Synergeti...
Gastric Cancer: Сlinical Implementation of Artificial Intelligence, Synergeti...Gastric Cancer: Сlinical Implementation of Artificial Intelligence, Synergeti...
Gastric Cancer: Сlinical Implementation of Artificial Intelligence, Synergeti...
 
Cara Menggugurkan Kandungan Dengan Cepat Selesai Dalam 24 Jam Secara Alami Bu...
Cara Menggugurkan Kandungan Dengan Cepat Selesai Dalam 24 Jam Secara Alami Bu...Cara Menggugurkan Kandungan Dengan Cepat Selesai Dalam 24 Jam Secara Alami Bu...
Cara Menggugurkan Kandungan Dengan Cepat Selesai Dalam 24 Jam Secara Alami Bu...
 
👉 Amritsar Call Girls 👉📞 8725944379 👉📞 Just📲 Call Ruhi Call Girl Near Me Amri...
👉 Amritsar Call Girls 👉📞 8725944379 👉📞 Just📲 Call Ruhi Call Girl Near Me Amri...👉 Amritsar Call Girls 👉📞 8725944379 👉📞 Just📲 Call Ruhi Call Girl Near Me Amri...
👉 Amritsar Call Girls 👉📞 8725944379 👉📞 Just📲 Call Ruhi Call Girl Near Me Amri...
 
Cardiac Output, Venous Return, and Their Regulation
Cardiac Output, Venous Return, and Their RegulationCardiac Output, Venous Return, and Their Regulation
Cardiac Output, Venous Return, and Their Regulation
 
Circulatory Shock, types and stages, compensatory mechanisms
Circulatory Shock, types and stages, compensatory mechanismsCirculatory Shock, types and stages, compensatory mechanisms
Circulatory Shock, types and stages, compensatory mechanisms
 
Intramuscular & Intravenous Injection.pptx
Intramuscular & Intravenous Injection.pptxIntramuscular & Intravenous Injection.pptx
Intramuscular & Intravenous Injection.pptx
 
Dehradun Call Girl Service ❤️🍑 8854095900 👄🫦Independent Escort Service Dehradun
Dehradun Call Girl Service ❤️🍑 8854095900 👄🫦Independent Escort Service DehradunDehradun Call Girl Service ❤️🍑 8854095900 👄🫦Independent Escort Service Dehradun
Dehradun Call Girl Service ❤️🍑 8854095900 👄🫦Independent Escort Service Dehradun
 
🚺LEELA JOSHI WhatsApp Number +91-9930245274 ✔ Unsatisfied Bhabhi Call Girls T...
🚺LEELA JOSHI WhatsApp Number +91-9930245274 ✔ Unsatisfied Bhabhi Call Girls T...🚺LEELA JOSHI WhatsApp Number +91-9930245274 ✔ Unsatisfied Bhabhi Call Girls T...
🚺LEELA JOSHI WhatsApp Number +91-9930245274 ✔ Unsatisfied Bhabhi Call Girls T...
 
💚Chandigarh Call Girls 💯Riya 📲🔝8868886958🔝Call Girls In Chandigarh No💰Advance...
💚Chandigarh Call Girls 💯Riya 📲🔝8868886958🔝Call Girls In Chandigarh No💰Advance...💚Chandigarh Call Girls 💯Riya 📲🔝8868886958🔝Call Girls In Chandigarh No💰Advance...
💚Chandigarh Call Girls 💯Riya 📲🔝8868886958🔝Call Girls In Chandigarh No💰Advance...
 
tongue disease lecture Dr Assadawy legacy
tongue disease lecture Dr Assadawy legacytongue disease lecture Dr Assadawy legacy
tongue disease lecture Dr Assadawy legacy
 
Call 8250092165 Patna Call Girls ₹4.5k Cash Payment With Room Delivery
Call 8250092165 Patna Call Girls ₹4.5k Cash Payment With Room DeliveryCall 8250092165 Patna Call Girls ₹4.5k Cash Payment With Room Delivery
Call 8250092165 Patna Call Girls ₹4.5k Cash Payment With Room Delivery
 
Electrocardiogram (ECG) physiological basis .pdf
Electrocardiogram (ECG) physiological basis .pdfElectrocardiogram (ECG) physiological basis .pdf
Electrocardiogram (ECG) physiological basis .pdf
 
Whitefield { Call Girl in Bangalore ₹7.5k Pick Up & Drop With Cash Payment 63...
Whitefield { Call Girl in Bangalore ₹7.5k Pick Up & Drop With Cash Payment 63...Whitefield { Call Girl in Bangalore ₹7.5k Pick Up & Drop With Cash Payment 63...
Whitefield { Call Girl in Bangalore ₹7.5k Pick Up & Drop With Cash Payment 63...
 
Pune Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Pune No💰Adva...
Pune Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Pune No💰Adva...Pune Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Pune No💰Adva...
Pune Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Pune No💰Adva...
 
Genuine Call Girls Hyderabad 9630942363 Book High Profile Call Girl in Hydera...
Genuine Call Girls Hyderabad 9630942363 Book High Profile Call Girl in Hydera...Genuine Call Girls Hyderabad 9630942363 Book High Profile Call Girl in Hydera...
Genuine Call Girls Hyderabad 9630942363 Book High Profile Call Girl in Hydera...
 
Nagpur Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Nagpur No💰...
Nagpur Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Nagpur No💰...Nagpur Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Nagpur No💰...
Nagpur Call Girl Service 📞9xx000xx09📞Just Call Divya📲 Call Girl In Nagpur No💰...
 

Presentation HIRARC Sem 3

  • 1. HIRARC OF SOIL INVESTIGATION AT GADANG CONSTRUCTION SITE MOHAMAD ARIFFIN BIN SAMSURI DOSHM0713001247 SEMESTA 3 BATCH 26G2 SIR MOHD FARIS BIN MOHD ZAWAWI
  • 2. introduction • Gadang Holdings Berhad (Gadang) was incorporated in Malaysia on 6 October 1993 as a public limited company under the name of Lai Sing Holdings Berhad and was subsequently changed to its present name on 7 November 1997 • Gadang is an investment holding company while its subsidiaries' core businesses are in civil engineering and building construction, property development, water concession, mechanical and electrical engineering services and general trading.
  • 3. COMPANY VISION AND MISION VISION - to build a reputable Gadang - deliver quality products - derive positive return. MISION - to adopt a hands on approach. - to be result oriented. - to achieve continual growth.
  • 5. WORK PROCESS site cleaning soil investigation earth work demolition work bored pile concrete work road work drainage work
  • 6. ACTIVITY OF SOIL INVESTIGATION Traffic management Setup & maintenance of the drilling & grouting machine Position the drilling machine Nights works Grouting works Drilling works
  • 7. OBJECTIVE • To identify three (3) Safety Hazards and two (2) Health Hazards at the workplace and discuss in detail the techniques used to identify all types of hazards. • To identify the risk at the workplace • To reduce the hazard from happen again • To discuss and give appropriate suggestions for control measures in order to eliminate, reduce, and minimize the risk of the most critical hazards • To explain the implications of the most critical hazards (safety & health hazard) that has been identified and their preventive measure
  • 8. METHODOLOGY WORKPLACE HAZARD OBSERVATION: • To observe the soil investigation activities involved and the hazard encountered during performing the activities. • Observe any unsafe act, hazard, dangerous at the construction site INTERVIEW WITH WORKERS • Interview with safety officer Abdul Razak Example of question being asking during the interview as below; How long you work at this company? What are the work activities taken until the task is completed? Did you notify any hazards occur during each job work activity? What are you concern of during the work activity? REVIEW OF AVAILABLE INFORMATION • Information were collected from the company • Reviewing the record of workplace for example document
  • 9. LIKELIHOOD TABLE EXAMPLE: Likelihood (L) Example Rating Most likely The most likely result of the hazard / event being realized 5 Possible Has a good chance of occurring and is not unusual 4 Conceivable Might be occur at some time in future 3 Remote Has not been known to occur after many years 2 Inconceivable Is practically impossible and has never occurred 1 SEVERITY TABLE: Severity Example Rating Catastrophic Numerous fatalities, irrecoverable property damage and productivity 5 Fatal Approximately one single fatality major property damage if hazard is realized 4 Serious Non- fatal injury, permanent disability 3 Minor Disabling but not permanent injury 2 Negligible Minor abrasions, bruises, cuts, first aid type injury 1
  • 10. RISK MATRIX TABLE: Severity (S) Likelihood (L) 1 2 3 4 5 5 5 10 15 20 25 4 4 8 12 16 20 3 3 6 9 12 15 2 2 4 6 8 10 1 1 2 3 4 5
  • 11. HIRARC RESULT Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI Hazard identification Risk analysis Risk control No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 1 Temporary traffic control Accident due to mobilization of machineries (crash by heavy machinery) (safety) Serious or minor Injury, bone fracture, traffic congestion Toolbox meeting, daily workplace inspection, provide complete set of ppe 3 3 9 medium ELIMINATION: N/A SUBSTITUTION: N/A ISOLATION: N/A ENGINEERING CONTROL: N/A ADMINISTRATIVE CONTROL: provide general workers to direct traffic, competent operator and driver with valid driving license, implement traffic management as per approved by management, Provide clear & working space and access with enough flagmen to control the traffic. PERSONAL PROTECTIVE EQUIPMENT: provide hazard warning blinker light FMA1987 (building operation and works of engineering construction) (runways and ramps) FMA 1987 (person in charge)(machiner y required to be in charge of persons holding certificates of competency)(sect ion 13, assessment of drivers)
  • 12. Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI Hazard identification Risk analysis Risk control No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 2 Night work Struck by vehicles (public transport and heavy machinery at workstation) (safety) Bone fracture Toolbox meeting, daily workplace inspection, provide complete set of ppe 5 2 10 medium ELIMINATION: N/A SUBSTITUTION: N/A ISOLATION: N/A ENGINEERING CONTROL: N/A ADMINISTRATIVE CONTROL: briefing before work, job rotation (arranging work shift to workers). provide enough lighting to works, provide warning sings PERSONAL PROTECTIVE EQUIPMENT: provide lighting helmet, reflected light jacket OSHA 1994(general duties of employers and self-employers persons)(section 15)
  • 13. Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI Hazard identification Risk analysis Risk control No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 3 Drilling works Prolonged Extremely vibration (health) White finger (also known as "dead finger" ) - damage to hands causing whiteness and pain in the fingers Toolbox meeting, daily workplace inspection, provide complete set of ppe 3 2 6 medium ELIMINATION: N/A SUBSTITUTION: N/A ISOLATION: N/A ENGINEERING CONTROL: N/A ADMINISTRATIVE CONTROL: Job rotation every one hour, frequent short break, maintenance the machines PERSONAL PROTECTIVE EQUIPMENT: Provide glove reduce vibration (leather) OSHA 1994 (safety and health officer)(duties of safety and health officers) OSHA 1994(USECHH 2000) (use of approved personal protective equipment)
  • 14. Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI Hazard identification Risk analysis Risk control No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 4 Drilling work Exposed to sand dust inhalation (health) Respiratory problem, eye irritation Toolbox meeting, daily workplace inspection, provide complete set of ppe 4 3 12 medium ELIMINATION: N/A SUBSTITUTION: N/A ISOLATION: isolate the worker(was related to drilling work) ENGINEERING CONTROL: provide the barrier around the work station and install the ventilation ADMINISTRATIVE CONTROL: job rotation, and frequent short break, Provide shift work for the worker to reduce the duration of workers exposed to the soil sand dust. PERSONAL PROTECTIVE EQUIPMENT: Provide respirator, (filter mask) goggle, face shield FMA 1987 REGULATIONS 1984 (RESPIRATORY PREOTECTION)
  • 15. Work process: CONSTRUCTION OF SOIL INVESTIGATION Conducted by: MOHAMAD ARIFFIN BIN SAMSURI Hazard identification Risk analysis Risk control No Work activity Hazard Effect Existing control L S Risk recommendation Legal requirement 5 Drilling work Excessive extreme heat Heat stress(sweati ng)/skin redness/fainti ng Toolbox meeting, daily workplace inspection, provide complete set of ppe 5 2 10 medium ELIMINATION: N/A SUBSTITUTION: N/A ISOLATION: N/A ENGINEERING CONTROL:N/A ADMINISTRATIVE CONTROL: provide water fan, provide canopy to protect worker from heat. PERSONAL PROTECTIVE EQUIPMENT: provide cotton clothes or clothes absorb sweating. OSHA 1994(general duties of employers and self-employers persons)(section 15)
  • 16. DISCUSSION MOST CRITICAL HAZARD (SAFETY HAZARD) No Work activity Hazard Effect Existing control L S Risk 2 Night works Struck by vehicles (public transport and heavy machinery at workstation) (safety) Bone fracture Toolbox meeting, daily workplace inspection, provide complete set of ppe 5 2 10 The worker also has been supplied by complete all ppe . Workers who work at nights are not aware of the hazard related to the work activity. The effect of the hazard is workers will minor injury, bone fracture, or more badly. The implication of workers towards nights, the worker might be exposed to accident.
  • 17. MOST CRITICAL HAZARD (HEALTH HAZARD No Work activity Hazard Effect Existing control L S Risk 4 drilling work Expose to sand dust inhalation Respiratory problem Toolbox meeting, daily workplace inspection, provide complete set of ppe, 4 3 12 This hazard is the most significant critical health hazards because the worker also has been inducted by safety personnel and provide complete set of PPE. Workers who work with drilling work are not aware of the hazard related to the work activity. The effect of the hazard workers will get respiratory problem due to drilling sand dust inhalation. The implication of workers towards drilling sand dust inhalation.
  • 18. RECOMMENDATION FOR MOST CRITICAL SAFETY HAZARD No Hierarchy of control Control Measure 1. Elimination Not applicable Description: a) There are nothing can be eliminate in this process 2. Substitution Not applicable Description: a) There are nothing can be substitute in the process 3. Isolation Not applicable Description: a) There are nothing can be substitute in the process 4. Engineering control Not applicable Description a) There are nothing can be substitute in the process 5 Administration control a) briefing before work b) job rotation (arranging work shift to workers) c) provide enough lighting to works Description a) Increase awareness about the hazard among workers during the toolbox meeting before work is carried out b) light is important for employees who work at night to avoid from accident happen at the workplace 6. Personal Protective Equipment (PPE) a) provide lighting helmet b) reflected light jacket Description: a) lighting helmet and reflect light jacket is important because as one way to facilitate the work at night or as a signalman to vehicles
  • 19. RECOMMENDATION FOR MOST CRITICAL HEALTH HAZARD No Hierarchy of control Control Measure 1. Elimination Not applicable Description: a) There are nothing can be eliminate in this process 2. Substitution Not applicable Description: a) There are nothing can be substitute in the process 3. Isolation a) isolate other worker Description: a) Only the person who are involved in drilling works is needed in the area 4. Engineering control a) install the barrier around the work station Description: a) To reduce dust from directly exposed to our respirator system 5. Administration control a) Job rotation and frequent short break or provide the work shift for the worker Description: a) Job rotation at once in 2 hours, b) Work shift to workers is necessary 6. Personal Protective Equipment (PPE) a) Provide respirator (filter mask) goggle, face shield Description: a) respirator is needed while drilling the sand for protection of the worker from inhaled the dust
  • 20. CONCLUSION  In order to reduce the hazard or most critical hazard rate, the employer should show commitment towards safety and health practices and therefore give full priority to promote and enforce the safety and health rules in workplace.  Hierarchy of control were use in order to minimize and control the most critical hazard that exist at the workplace.  To ensure the safety culture can be implemented in an organization.  the management and workers have to take part in any safety and health program and give a full cooperation when comes to safety and health issues.
  • 21. APPENDIX Thanks for listening Soil investigation

Editor's Notes

  1. Project is located in new development area that interaction with public traffic, education institution, commercial / industrial area, residential area, hospital and religious building. The proposed PMRTLK – Jajaran Sungai Buloh – Kajang (approximately 51 km) which involve the construction of both elevated guideway (41.5 km) and underground tunnel (9.5 km) from Sungai Buloh to Kajang. Package V2 starts from Taman Industri Sg. Buloh Station and will end at Dataran Sunway Station, approximately 5.1 km in length. Construction period for Package V2 starts from July 2012 and expected to be completed by February 2016. The PMRTLK dicadangkan - Jajaran Sungai Buloh - Kajang (sekitar 51 km) yang melibatkan pembinaan guideway kedua meningkat (41.5 km) dan terowong bawah tanah (9.5 km) dari Sungai Buloh ke Kajang. Pakej V2 bermula dari Taman Industri Sg. Stesen Buloh dan akan berakhir di Stesen Sunway Dataran, kira-kira 5.1 km panjang. Tempoh pembinaan bagi Pakej V2 bermula dari bulan Julai 2012 dan dijangka siap pada bulan Februari 2016
  2. Review of avaible information the record of workplace inspection, accident and incident statistic, audit, exposure monitoring reports and job safety analysis (JSA) of the project provide by the company.  
  3. Provide clear & working space and access with enough flagmen to control the traffic. -Menyediakan ruang yang jelas & kerja dan akses dengan pemegang bendera yang cukup untuk mengawal lalu lintas. provide general workers to direct traffic, competent operator and driver with valid driving license, implement traffic management as per approved by -menyediakan pekerja am untuk mengarahkan lalu lintas, operator yang kompeten dan pemandu yang mempunyai lesen memandu yang sah, melaksanakan pengurusan trafik seperti yang diluluskan oleh pihak pengurusan