SlideShare a Scribd company logo
1 of 24
INTEGRATED PROJECT DELIVERY
ACE Mentorship Program: Team 2, January 20th, 2015
Design-Bid-Build: traditional approach – owner contracts separately with all
parties. Occasionally referred to as Design-Bid-ReDesign-ReBid-Build.
Design-Build: One entity performs both architecturalengineering design and
construction under one contract. Either an architect-led or contractor-led
approach.
CM-at Risk, or GMP: Construction Manager is a consultant to the owner during
design phases, and acts as general contractor during construction with a
commitment to deliver the project within a guaranteed maximum price.
Turnkey Project Delivery: frequently used in power plants, manufacturing
facilities, a method to provide an owner with a complete facility, ready to operate
and turn out product.
Traditional processes
Design- Bid- Build Most common form of Project
Delivery
•Three phases, three prime
players
•Independent contracts
between architect/owner and
contractor/owner
•Linear sequence of work
•Common with public owners
with requirements to select
low bid
•One entity hired by
Owner to complete
design and
construction
•May all be
Contractor's in-house
design expertise or
Contractor may
engage outside
Architect
•Early cost
commitment is made
(GMP) by Contractor
based upon
preliminary design
OWNER
DESIGN -
BUILDER
S
F
Design- Build
E
E
Everyone Signs the Same Agreement
Full IPD
Owner
Sub.ContractorCons. Architect
Sub.Cons.
AIA C195
ConsensusDocs 300
1/14/2016
6
Traditional (Today) Integrated Project Delivery (Tomorrow)
Fragmented, assembled on “just-
as-needed” or “minimum
necessary” basis, strongly
hierarchical, controlled
TEAMS An integrated team entity
composed of all project lifecycle
stakeholders, assembled early in
the process, open, collaborative
Linear, distinct, segregated;
knowledge gathered “just-as-
needed”; information hoarded
PROCESS Concurrent, multi-level,
integrated; early contributions of
knowledge and expertise;
information openly shared
Individually managed, transferred
to the greatest extent possible
RISK Collectively managed,
appropriately shared
Individually pursued; minimum
effort for maximum
return;(usually) first-cost based
COMPENSATION
REWARD
Team success tied to project
success; value-based
Paper-based, 2 dimensional;
analog
COMMUNICATION
S
TECHNOLOGY
Digitally based, virtual, 4
dimensional; BIM
Minimum effort for maximum
return; minimize or transfer risk;
don’t share
AGREEMENTS Encourage, foster, promote and
support open sharing and
collaboration, full integration
Individually focused, emphasis on
composition
EDUCATION Team-based, integrated,
collaborative; technologically
inclusive; materials and methods
focus in addition to compositionAIA California Council IPD FAQ - 2006
1/14/2016
7
PD SD CD PR CA OPDD
Time
Effort/Effect
PD: Pre-design
SD: Schematic design
DD: Design development
CD: Construction documentation
PR: Procurement
CA: Construction Administration
OP: Operation
Graphic originated by Patrick McLeay, AIA / HOK
Ability to impact cost and
functional capabilities1
1
Cost of design changes
2
2
Traditional design process3 3
Preferred design process
4
4
• Owner Leadership
• Integrated Project Structure
• Open Information Sharing
• Virtual Building Models
It’s about Productivity
Agency
Owner
Architect
Engineers
GC
Subs
Predesign Schematic
Design
Design
Development
Construction
Documents
Agency
Permit /
Bidding
Construction Closeout
WHO
REALIZE
HOW
WHAT
Traditional
WHAT
WHO
HOW
Agency
Owner
Architect
Engineers
GC
Subs
Conceptual-
ization
Criteria
Design
Detailed
Design
Implementation
Documents
Agency Coord /
Final Buyout
Construction Closeout
REALIZE
Integrated
•Define the processes, structure and metrics up front!
Source: AIA Convention 2009 – Jim Bedrick
 Competitive Schematic Design. The winner was ($655,000)
under 2nd place.
 Competitive approach to 3 systems, saving ($132,000) in
supplemental support steel.
 LEAN approach to have contract documents designed to 1
curtain wall system manufacturer
Integrated approach with all stakeholders collaborating to
achieve the best solution
 Used pre-engineered
curtain wall system.
 Architect spent less time
designing. Project relied
heavily on Trade Partner
shop drawings and Revit
model for final construction
drawings.
 Saved time & money!
Hand Drawing 2D CAD 3D CAD
EVOLUTION From Hand Drawing to Smart Models
BIM
Electrical Detailer
Structural Steel Detailer
Mechanical Piping Detailer
MEP Manager
BIM Engineer
Model & CAD Drawings
Architect
Smartboard & Projector
3D MEP Coordination
ANY QUESTIONS?

More Related Content

What's hot

BIM Uses In Design
BIM Uses In DesignBIM Uses In Design
BIM Uses In Design
nevena_psu
 

What's hot (20)

IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
IRJET- Application of Revit as Building Information Modeling (BIM) for Integr...
 
Bim for construction safety design
Bim for construction safety designBim for construction safety design
Bim for construction safety design
 
Human resource management for const management
Human resource management for const managementHuman resource management for const management
Human resource management for const management
 
iBIM and Knowledge Management
iBIM and Knowledge ManagementiBIM and Knowledge Management
iBIM and Knowledge Management
 
Digital construction for DfMA
Digital construction for DfMADigital construction for DfMA
Digital construction for DfMA
 
Building Information Modeling (BIM)
Building Information Modeling (BIM)Building Information Modeling (BIM)
Building Information Modeling (BIM)
 
The Information Challenge Managing Construction with BIM
The Information ChallengeManaging Construction with BIMThe Information ChallengeManaging Construction with BIM
The Information Challenge Managing Construction with BIM
 
BIM at Salford - Professor Arto Kiviniemi
BIM at Salford - Professor Arto KiviniemiBIM at Salford - Professor Arto Kiviniemi
BIM at Salford - Professor Arto Kiviniemi
 
BIM Implementation in a Lean Operating System
BIM Implementation in a Lean Operating SystemBIM Implementation in a Lean Operating System
BIM Implementation in a Lean Operating System
 
BIM project execution
BIM project executionBIM project execution
BIM project execution
 
081204 Virtual Design & Construction
081204 Virtual Design & Construction081204 Virtual Design & Construction
081204 Virtual Design & Construction
 
Building information modeling & value to the AEC industry Part 2
Building information modeling &  value to the AEC industry   Part 2Building information modeling &  value to the AEC industry   Part 2
Building information modeling & value to the AEC industry Part 2
 
BIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project DeliveryBIM: The Promise of an Integrated Approach to Project Delivery
BIM: The Promise of an Integrated Approach to Project Delivery
 
Bim presentation km 21-10-2011
Bim presentation km 21-10-2011Bim presentation km 21-10-2011
Bim presentation km 21-10-2011
 
Global_BIM_Management_catalog
Global_BIM_Management_catalogGlobal_BIM_Management_catalog
Global_BIM_Management_catalog
 
BIM Uses In Design
BIM Uses In DesignBIM Uses In Design
BIM Uses In Design
 
Ashrae denver business project development and ipd_ springer
Ashrae denver business project development and ipd_ springerAshrae denver business project development and ipd_ springer
Ashrae denver business project development and ipd_ springer
 
Mci sr 2011report_summary_lit
Mci sr 2011report_summary_litMci sr 2011report_summary_lit
Mci sr 2011report_summary_lit
 
Integrating decision support systems (dss)and bim
Integrating decision support systems (dss)and bimIntegrating decision support systems (dss)and bim
Integrating decision support systems (dss)and bim
 
bim and project controls
 bim and project controls bim and project controls
bim and project controls
 

Similar to ACE Team 2 - WK6 - IPD Presentation

15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper
Todd Sullivan
 
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
ChassyTesoro1
 
Whats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docxWhats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docx
cooperapleh
 
Whats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docxWhats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docx
eubanksnefen
 
Whats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docxWhats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docx
helzerpatrina
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
AYM1979
 
Ipd Convention 2009 Lessons Learned Presentation Final
Ipd Convention 2009 Lessons Learned Presentation FinalIpd Convention 2009 Lessons Learned Presentation Final
Ipd Convention 2009 Lessons Learned Presentation Final
Andrew Huseman
 
Construction process
Construction processConstruction process
Construction process
Mazen Al-Qadi
 

Similar to ACE Team 2 - WK6 - IPD Presentation (20)

ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)
 
ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)ACH 231 Lecture 06 (Project Delivery)
ACH 231 Lecture 06 (Project Delivery)
 
Design-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful OutcomesDesign-Build: The Owner’s Role in Successful Outcomes
Design-Build: The Owner’s Role in Successful Outcomes
 
integrated-project-delivery-constru
integrated-project-delivery-construintegrated-project-delivery-constru
integrated-project-delivery-constru
 
15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper15-MOR-101_IPDWhitepaper
15-MOR-101_IPDWhitepaper
 
Bridging Gt Apr09
Bridging Gt Apr09Bridging Gt Apr09
Bridging Gt Apr09
 
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdfCCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
CCDC-Boise-Parking-Structure-Design-Guidelines_2016-Final-Draft-08-04-2016.pdf
 
Whats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docxWhats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docx
 
Whats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docxWhats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docx
 
Whats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docxWhats the BIM IdeaWhy does this happenProjec.docx
Whats the BIM IdeaWhy does this happenProjec.docx
 
Architect-Led Design-Build: a PRACTICAL business plan
Architect-Led Design-Build:  a PRACTICAL business planArchitect-Led Design-Build:  a PRACTICAL business plan
Architect-Led Design-Build: a PRACTICAL business plan
 
Residential Design Build Whitepaper
Residential Design Build WhitepaperResidential Design Build Whitepaper
Residential Design Build Whitepaper
 
Early contractor involvement (eci) procurement approach spm talk 2016
Early contractor involvement (eci) procurement approach   spm talk 2016Early contractor involvement (eci) procurement approach   spm talk 2016
Early contractor involvement (eci) procurement approach spm talk 2016
 
Construction contracts docuements_08092008
Construction contracts docuements_08092008Construction contracts docuements_08092008
Construction contracts docuements_08092008
 
6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods6 Alternative Construction Project Delivery Methods
6 Alternative Construction Project Delivery Methods
 
Exploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project deliveryExploration of risks and risk management in construction project delivery
Exploration of risks and risk management in construction project delivery
 
Lecture 1.pptx
Lecture 1.pptxLecture 1.pptx
Lecture 1.pptx
 
Integrated project delivery case studies
Integrated project delivery   case studiesIntegrated project delivery   case studies
Integrated project delivery case studies
 
Ipd Convention 2009 Lessons Learned Presentation Final
Ipd Convention 2009 Lessons Learned Presentation FinalIpd Convention 2009 Lessons Learned Presentation Final
Ipd Convention 2009 Lessons Learned Presentation Final
 
Construction process
Construction processConstruction process
Construction process
 

More from Ausrine Rakauskaite

State Farm Center: Renovation and Addition Project
State Farm Center: Renovation and Addition ProjectState Farm Center: Renovation and Addition Project
State Farm Center: Renovation and Addition Project
Ausrine Rakauskaite
 

More from Ausrine Rakauskaite (13)

Kaplan Institute Constuction - Illinois Tech
Kaplan Institute Constuction - Illinois TechKaplan Institute Constuction - Illinois Tech
Kaplan Institute Constuction - Illinois Tech
 
Project Delivery and Best Practices
Project Delivery and Best PracticesProject Delivery and Best Practices
Project Delivery and Best Practices
 
Capital Programs - O'Hare 21
Capital Programs - O'Hare 21 Capital Programs - O'Hare 21
Capital Programs - O'Hare 21
 
UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...UL Understanding the Importance of Air and Water Field Testing of Installed F...
UL Understanding the Importance of Air and Water Field Testing of Installed F...
 
Clark Construction/PD3 Presentation - McCormick HQ
Clark Construction/PD3 Presentation - McCormick HQClark Construction/PD3 Presentation - McCormick HQ
Clark Construction/PD3 Presentation - McCormick HQ
 
CMAA Riverwalk Presentation
CMAA Riverwalk PresentationCMAA Riverwalk Presentation
CMAA Riverwalk Presentation
 
CMAA January Luncheon - Illinois Tollway
CMAA January Luncheon - Illinois TollwayCMAA January Luncheon - Illinois Tollway
CMAA January Luncheon - Illinois Tollway
 
State Farm Center: Renovation and Addition Project
State Farm Center: Renovation and Addition ProjectState Farm Center: Renovation and Addition Project
State Farm Center: Renovation and Addition Project
 
CMAA April Luncheon - Focal Point
CMAA April Luncheon - Focal PointCMAA April Luncheon - Focal Point
CMAA April Luncheon - Focal Point
 
CMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement ProgramCMAA OHare and Midway International Airports Capital Improvement Program
CMAA OHare and Midway International Airports Capital Improvement Program
 
CMAA Presentation Final Cook County
CMAA Presentation Final Cook CountyCMAA Presentation Final Cook County
CMAA Presentation Final Cook County
 
November 2014 CCM Newsletter
November 2014 CCM NewsletterNovember 2014 CCM Newsletter
November 2014 CCM Newsletter
 
The State of Rail in Illinois
The State of Rail in IllinoisThe State of Rail in Illinois
The State of Rail in Illinois
 

Recently uploaded

1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
QucHHunhnh
 

Recently uploaded (20)

Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Python Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docxPython Notes for mca i year students osmania university.docx
Python Notes for mca i year students osmania university.docx
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 
Single or Multiple melodic lines structure
Single or Multiple melodic lines structureSingle or Multiple melodic lines structure
Single or Multiple melodic lines structure
 
Towards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptxTowards a code of practice for AI in AT.pptx
Towards a code of practice for AI in AT.pptx
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Holdier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdfHoldier Curriculum Vitae (April 2024).pdf
Holdier Curriculum Vitae (April 2024).pdf
 
ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.ICT role in 21st century education and it's challenges.
ICT role in 21st century education and it's challenges.
 
Introduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The BasicsIntroduction to Nonprofit Accounting: The Basics
Introduction to Nonprofit Accounting: The Basics
 
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptxSKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
SKILL OF INTRODUCING THE LESSON MICRO SKILLS.pptx
 
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptxHMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
HMCS Max Bernays Pre-Deployment Brief (May 2024).pptx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024FSB Advising Checklist - Orientation 2024
FSB Advising Checklist - Orientation 2024
 
1029 - Danh muc Sach Giao Khoa 10 . pdf
1029 -  Danh muc Sach Giao Khoa 10 . pdf1029 -  Danh muc Sach Giao Khoa 10 . pdf
1029 - Danh muc Sach Giao Khoa 10 . pdf
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Graduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - EnglishGraduate Outcomes Presentation Slides - English
Graduate Outcomes Presentation Slides - English
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 

ACE Team 2 - WK6 - IPD Presentation

  • 1. INTEGRATED PROJECT DELIVERY ACE Mentorship Program: Team 2, January 20th, 2015
  • 2. Design-Bid-Build: traditional approach – owner contracts separately with all parties. Occasionally referred to as Design-Bid-ReDesign-ReBid-Build. Design-Build: One entity performs both architecturalengineering design and construction under one contract. Either an architect-led or contractor-led approach. CM-at Risk, or GMP: Construction Manager is a consultant to the owner during design phases, and acts as general contractor during construction with a commitment to deliver the project within a guaranteed maximum price. Turnkey Project Delivery: frequently used in power plants, manufacturing facilities, a method to provide an owner with a complete facility, ready to operate and turn out product. Traditional processes
  • 3. Design- Bid- Build Most common form of Project Delivery •Three phases, three prime players •Independent contracts between architect/owner and contractor/owner •Linear sequence of work •Common with public owners with requirements to select low bid
  • 4. •One entity hired by Owner to complete design and construction •May all be Contractor's in-house design expertise or Contractor may engage outside Architect •Early cost commitment is made (GMP) by Contractor based upon preliminary design OWNER DESIGN - BUILDER S F Design- Build E E
  • 5. Everyone Signs the Same Agreement Full IPD Owner Sub.ContractorCons. Architect Sub.Cons. AIA C195 ConsensusDocs 300
  • 6. 1/14/2016 6 Traditional (Today) Integrated Project Delivery (Tomorrow) Fragmented, assembled on “just- as-needed” or “minimum necessary” basis, strongly hierarchical, controlled TEAMS An integrated team entity composed of all project lifecycle stakeholders, assembled early in the process, open, collaborative Linear, distinct, segregated; knowledge gathered “just-as- needed”; information hoarded PROCESS Concurrent, multi-level, integrated; early contributions of knowledge and expertise; information openly shared Individually managed, transferred to the greatest extent possible RISK Collectively managed, appropriately shared Individually pursued; minimum effort for maximum return;(usually) first-cost based COMPENSATION REWARD Team success tied to project success; value-based Paper-based, 2 dimensional; analog COMMUNICATION S TECHNOLOGY Digitally based, virtual, 4 dimensional; BIM Minimum effort for maximum return; minimize or transfer risk; don’t share AGREEMENTS Encourage, foster, promote and support open sharing and collaboration, full integration Individually focused, emphasis on composition EDUCATION Team-based, integrated, collaborative; technologically inclusive; materials and methods focus in addition to compositionAIA California Council IPD FAQ - 2006
  • 7. 1/14/2016 7 PD SD CD PR CA OPDD Time Effort/Effect PD: Pre-design SD: Schematic design DD: Design development CD: Construction documentation PR: Procurement CA: Construction Administration OP: Operation Graphic originated by Patrick McLeay, AIA / HOK Ability to impact cost and functional capabilities1 1 Cost of design changes 2 2 Traditional design process3 3 Preferred design process 4 4 • Owner Leadership • Integrated Project Structure • Open Information Sharing • Virtual Building Models It’s about Productivity
  • 8. Agency Owner Architect Engineers GC Subs Predesign Schematic Design Design Development Construction Documents Agency Permit / Bidding Construction Closeout WHO REALIZE HOW WHAT Traditional WHAT WHO HOW Agency Owner Architect Engineers GC Subs Conceptual- ization Criteria Design Detailed Design Implementation Documents Agency Coord / Final Buyout Construction Closeout REALIZE Integrated •Define the processes, structure and metrics up front! Source: AIA Convention 2009 – Jim Bedrick
  • 9.
  • 10.
  • 11.  Competitive Schematic Design. The winner was ($655,000) under 2nd place.  Competitive approach to 3 systems, saving ($132,000) in supplemental support steel.  LEAN approach to have contract documents designed to 1 curtain wall system manufacturer Integrated approach with all stakeholders collaborating to achieve the best solution
  • 12.  Used pre-engineered curtain wall system.  Architect spent less time designing. Project relied heavily on Trade Partner shop drawings and Revit model for final construction drawings.  Saved time & money!
  • 13.
  • 14.
  • 15.
  • 16.
  • 17.
  • 18.
  • 19. Hand Drawing 2D CAD 3D CAD EVOLUTION From Hand Drawing to Smart Models BIM
  • 20. Electrical Detailer Structural Steel Detailer Mechanical Piping Detailer MEP Manager BIM Engineer Model & CAD Drawings Architect Smartboard & Projector 3D MEP Coordination
  • 21.
  • 22.
  • 23.

Editor's Notes

  1. 1
  2. 2
  3. 3
  4. 4
  5. Talk about categories
  6. In the following diagram provided courtesy of Patrick McLeay of HOK, we understand that the ability to impact cost and functional capabilities during a project decreases over life of the project. All the while, the cost of design changes increases as the project cycle progresses. Currently, most of the project design decision-making occurs in the white curve, where the ability to impact cost and functional capabilities crosses with the cost of design changes. A preferred scenario would be to move the design decisions forward in the design process, when the cost of change is low, and the ability to impact cost and functional capabilities is high. A building information modeling approach seeks to accomplish this objective.
  7. IPD Definition Task Group
  8. 19