      Managing Temporary
            Works
              Andrea Robbins
      HM Inspector of Health and Safety
What are temporary works?

BS 5975:2008+A1:2011 defines temporary
 works as:


 “those parts of the works that allow or
 enable construction of, protect, support or
 provide access to the permanent works
 and which might or might not remain in
 place at the completion of the works”
Temporary Works Examples -
    Earthworks
•   Piling Platforms, Underpinning and Cofferdams
    etc.




    Construction of a Piling Platform
                                        Completed Piling Platform   Underpinning
Temporary Works Examples

• Earthworks – (Supports) for Trenches, Excavations



                                                                 Waler Frames –
                                                            For Medium Sized Trenches
                                          Close Boarded
                                          Trench Support




                 Design of trench box -
                  access ladder and
                    edge protection
  Trench Boxes      attached to box                         Hydraulic / Mechanical Struts
                                          Strutting Frame
Temporary Works Examples

•   Structures – Formwork & Falsework




      Formwork (Shuttering)        Falsework (Supports)
Temporary Works Examples

•   Structures – Scaffold, Propping & Façade Retention




                                        Propping


         Façade Retention
Temporary Works Examples

•   Structures – Edge Protection, Loading Bays,
    Temporary Bridges, Hoarding, and Signage etc




                                                    Signage
      Edge Protection
                        Temporary Bridges




                            Hoarding        Signage On Scaffolds etc
       Loading Bays
Temporary Works Examples

•   Plant - Mobile Crane Outrigger Design, Hoists /
    Mast Climbers, Tower Crane Bases etc.




                                       Hoists / Mast Climbers




         Tower Crane
            Base
                                   Mobile Crane Outrigger Design
Legal obligations – CDM Regulations
2007

•   Reg 4 – competence required of all those with a role to discharge
    in planning, design and execution of TW;
•   Regs 5 & 6 - co-operation and co-ordination of activities, including
    TW, incumbent on all involved;
•   Reg 10 – client’s duty to provide pre-construction information, e.g.
    ground conditions, structural drawings;
•   Reg 11 – duties of designers: avoidance of foreseeable risk
    arising from preparing or modifying designs;
•   Reg 18 – additional duties of designers: provision of information to
    assist the CDM Co-ordinator;
•   Regs 13 & 22 – duties of contractors and the principal contractor:
    planning, management and monitoring of construction work;
Legal obligations – CDM Regulations
2007
•   Reg 20 – duties of CDM(Cs) – all reasonable steps to
    ensure designers comply with their duties and to ensure
    co-operation between designers and principal contractors
    in relation to any design or design change;
•   Reg 26 – safe place of work – scaffolding, flooring, stairs
    etc;
•   Reg 28 – stability of structures: any support or temporary
    structure must be designed, installed and maintained so as
    to withstand foreseeable loads;
•   Reg 29 – demolition or dismantling: planning and recording
    of arrangements;
•   Reg 31 – excavations: planning and execution;
•   Reg 32 – cofferdams and caissons: design, planning and
    execution;
Temporary Works Procedure

•   Appointment of a Temporary Works Co-ordinator (TWC)
•   Completion and maintenance of a Temporary Works Register
•   Preparation of design briefs for elements identified in the register
•   Production of temporary works designs
•   Temporary works design check
•   Preparation of risk assessments/method statements
•   Pre-erection inspection of the TW materials and components
•   Supervision of erection of temporary works
•   Check that the TW have been erected in accordance with the design
•   Issue a formal “permit to load” where necessary
•   Confirm that the TW have attained adequate strength to allow TW to
    be dismantled
•   Issue a formal “permit to dismantle” where necessary
Temporary Works Co-ordinator

•   Formal appointment in writing
•   Must be competent = experience + a formal
    qualification, e.g.
    [1] Degree/HND qualified as a minimum
    [2] Chartered Civil/Structural Engineer
    [3] Has completed formal temporary works
    training
Temporary Works Co-ordinator

Typical duties:
•   To determine the TW for a project, compile a TW register
    and keep all TW records;
•   To ensure the procedures for the control of TW are
    implemented on site;
•   To determine the type and risk class of TW on a project;
•   To ensure that all TW are designed and checked
    appropriately;
•   To issue the permit to load and permit to dismantle; and
•   To ensure that all TW activities are adequately planned
    and supervised.
Temporary Works Supervisor

•   Assists the TW Co-ordinator
•   Carries out checks on the implementation
    process of the TW.
•   May issue the permit to load and permit to
    dismantle when specifically authorised for
    a defined scope and range of work.
CDM Co-ordinator

•   Ensures co-operation between
    permanent and temporary design;
•   Check suitability of construction phase
    plan – stability of structures – have they
    been addressed;
•   Advises client of the suitability of the
    construction phase plan.
Temporary works register

Should include:
•   Design brief number;
•   Short description of temporary works;
•   Date required for design solution;
•   Risk category of temporary works;
•   Designer and design checker;
•   Date design complete;
•   Date design checked/approved; and
•   Erection complete and checked or “permit to
    load” then “permit to dismantle”.
Risk classes of temporary works

High risk (class 1 or class A)
•   Falsework and formwork over 3m high
•   Hoarding and fencing over 3m high
•   Façade retention schemes
•   Complex designed scaffold
•   Complex propping schemes – multiple props and multiple levels
•   Needling of structures greater than 2 storeys high
•   Working platforms for cranes and piling rigs; tower crane bases
•   Ground support schemes greater than 3m deep
•   Trenchless construction including headings, thrust bores, mini
    tunnels
•   Cofferdams
•   Complex structural steelwork and pre-cast concrete erection
    schemes
Risk classes of temporary works

Medium risk (class 2 or class B)
•   Hoardings & fencing up to 3m high
•   Simple designed scaffolds
•   Falsework up to 3m high
•   Formwork for concrete columns and walls up to 3m high
•   More complex propping schemes – multiple props at single
    level
•   Needling of structures up to 2 storeys high
•   Foundation underpinning not using piles
•   Excavations up to 3m deep in good ground
•   Safety net systems fixed to robust primary members
•   Temporary roofs
Risk classes of temporary works

Low risk (class 3 or class C)
•   Internal hoarding systems and temporary partitions not
    subject to wind or differential air pressure or crowd loading
•   Fencing and hoarding up to 1.2m high
•   Standard scaffold
•   Formwork less than 1.2m high
•   Shallow excavations less than 1.2m deep in good ground
•   Simple propping schemes – 1 or 2 props
•   Small MEWPs operating on a pavement designed for
    HGV’s or on internal ground bearing slabs and working
    within the level of tolerances set by the manufacturer
Temporary works design brief

•   Purpose of TW – include drawings of permanent
    works and any specifications;
•   Required dimensions and any known
    constraints;
•   Particular loads including impact loads;
•   Ground conditions – i.e. soils, groundwater etc;
•   Site conditions including services, adjacent
    structures and access;
•   Available materials and equipment; and
•   Construction sequence and loading stages.
Categories of Design Checks
Table 1 BS5975:2008+A1:2011
Category               Scope                                Comment                          Independence
                                                                                               of checker
           Restricted to standard solutions only,      This applies to the use of standard   Because this is a site issue, the
   0       to ensure the site conditions do not
           conflict with the scope or limitations of
                                                       solutions and Not the original
                                                       design, which will require both
                                                                                             check may be carried out by
                                                                                             another member of site or design
           the chosen standard solution.               structural calculation and checking   team.
                                                       to category 1, 2 or 3 as
                                                       appropriate.
           For simple designs. These may               Such designs would be                 The check may be carried out by
   1       include: formwork: false work (where
           top restraint is not assumed): needling
                                                       undertaken using simple methods
                                                       of analysis and be in accordance
                                                                                             another member of the design
                                                                                             team.
           and propping to brickwork openings in       with the relevant standards,
           single storey construction.                 supplier’s technical literature or
                                                       other reference publications.
           On more complex or involved designs.        Category 2 checks would include       The check should be carried out
   2       Designs for excavations, for
           foundations, for structural steelwork
                                                       designs where a considerable
                                                       degree of interpretation of loading
                                                                                             by an individual not involved in the
                                                                                             design and not consulted by the
           connections, for reinforced concrete.       or soils’ information is required     designer.
                                                       before the design of the
                                                       foundations or excavation support
                                                       or slope
           For complex or innovative designs,          These designs include unusual         The check should be carried out
   3       which result in complex sequences of
           moving and/or construction of either
                                                       designs or where significant
                                                       departures from standards, novel
                                                                                             by another organization.

           the temporary works or permanent            methods of analysis or
           works.                                      considerable exercise of
                                                       engineering judgement are
                                                       involved.
Temporary works design checks

•   For high risk TW there must be an
    independent check made on the design.
•   For medium risk TW the check can be
    undertaken by the same organisation as
    long as there is documentary proof of the
    independence of the checkers.
•   For low risk TW the checks can be
    undertaken by someone in the site team
    or the design team.
Temporary works design checks

In all cases the design check should provide
  an independent check on:


  1) Design concept;
  2) Strength and structural adequacy
  (including lateral stability and overturning
  etc); and
  3) Compliance with the design brief.
Why are temporary works important?

GOOD temporary works can bring:
•   Better safety;
•   Enhanced efficiency, quality, productivity;
    and
•   More certainty on completion times and
    cost.
What happens when TW go wrong?
Causes:

 •   No (or inadequate) TW procedure
 •   No (or inadequate) TWC appointed
 •   Lack of competent contractor/developer/ builder
 •   No (or inadequate) TW design
 •   Inadequate design brief or failure to carry out
     proper investigation of ground conditions,
     underground services or structural condition of
     existing buildings
 •   Unauthorised changes to an approved TW
     design
 •   Lack of competent TW designer and/or erectors
What happens when TW go wrong?
Causes:

•   Incorrect estimation of loads to be supported
    (overloading)
•   Lack of adequate lateral stability: inadequate
    horizontal and/or diagonal bracing to resist
    lateral (wind) loads
•   Inadequate foundations
•   No temporary works equipment available
•   Inappropriate use of TW equipment or other non
    TW equipment being used for the purpose of TW
•   TW poorly constructed
What happens when TW go wrong?
Consequences:

•   Collapse or failure of the TW;
•   Structural failure and/or collapse of the
    permanent works;
•   Uncontrolled ingress or egress of materials,
    spoils or water;
•   Collapse of adjacent structures;
•   Risk of fatalities and injuries to workers and
    members of the public;
•   Delays and increased costs; and
•   Financial & commercial risks to contractors, sub-
    contractors, designers, suppliers & clients.
Basement construction, London E17
Basement construction, London E17
When it goes wrong

                     •   Was the contractor
                         competent ?


                     •   Was the initial
                         construction phase
                         plan suitable?
CASE STUDIES
AA Fanum House, Cardiff
Scaffold collapse, 13 December 2000
White Hart Lane, London
Shanghai June 2009
Shanghai June 2009
Shanghai June 2009
Shanghai June 2009
Shanghai June 2009
Shanghai June 2009
Shanghai June 2009
Shanghai June 2009
Shanghai June 2009
Shanghai June 2009
What is HSE doing?

Work Plan 2011/12 – Aims for Temporary
 Works
•   Promote awareness & knowledge of the importance
    of managing TW effectively;
•   Improve contractors’ management arrangements
    for TW;
•   Increase the competence of those involved in TW
    management & design; and
•   Reduce accidents arising from TW failures
What is HSE doing?

How will this be achieved?
•   HSE Construction inspectors to target TW
    activities during routine site inspections;
•   A programme of targeted visits by HSE
    Civil/Structural Engineers
•   Initial engagement with principal
    contractors
•   May involve some “tracking back” from
    site to the CDM-C and the TW designer
Sources of information

•   HSE website - http://www.hse.gov.uk


•   SIM 02/2010/04 – The Management of
    Temporary Works in Construction
•   BS5975:2008+A1:2011 – Code of
    practice for temporary works procedures
    and the permissible stress design of
    falsework
Any questions?

More Related Content

What's hot

Lec10 finite element_beam_structures 2
Lec10 finite element_beam_structures 2Lec10 finite element_beam_structures 2
Lec10 finite element_beam_structures 2Mahdi Damghani
 
presentation on mobile cranes
presentation on mobile cranespresentation on mobile cranes
presentation on mobile cranesvipin balan
 
Ladders module1
Ladders module1Ladders module1
Ladders module1Zbut.Eu
 
Crane maintenance services
Crane maintenance servicesCrane maintenance services
Crane maintenance servicesJulia Heart
 
Overhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IOverhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IAtlantic Training, LLC.
 
Handbook for rigger signalman hasnizam
Handbook for rigger signalman hasnizamHandbook for rigger signalman hasnizam
Handbook for rigger signalman hasnizamHASNIZAM BIN MD SAAD
 
Etabs tutorial-tall-building-design (1)
Etabs tutorial-tall-building-design (1)Etabs tutorial-tall-building-design (1)
Etabs tutorial-tall-building-design (1)Nitesh Singh
 
Cause of accident and prevention in construction industry
Cause of accident and prevention in construction industryCause of accident and prevention in construction industry
Cause of accident and prevention in construction industryYASMINE HASLAN
 
Safety management for construction machines & equipments
 Safety management for construction machines & equipments Safety management for construction machines & equipments
Safety management for construction machines & equipmentsSelva Prakash
 
working at height
working at heightworking at height
working at heightJYOTHISHKT
 

What's hot (20)

Lec10 finite element_beam_structures 2
Lec10 finite element_beam_structures 2Lec10 finite element_beam_structures 2
Lec10 finite element_beam_structures 2
 
presentation on mobile cranes
presentation on mobile cranespresentation on mobile cranes
presentation on mobile cranes
 
Ladders module1
Ladders module1Ladders module1
Ladders module1
 
Crane maintenance services
Crane maintenance servicesCrane maintenance services
Crane maintenance services
 
Rigging and lifting
Rigging and liftingRigging and lifting
Rigging and lifting
 
HSE Temporary works management plan
HSE Temporary works management planHSE Temporary works management plan
HSE Temporary works management plan
 
Rigging Presentation
Rigging PresentationRigging Presentation
Rigging Presentation
 
Overhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&IOverhead Crane Safety by Pennslyvania L&I
Overhead Crane Safety by Pennslyvania L&I
 
Bridge defects
Bridge defectsBridge defects
Bridge defects
 
Handbook for rigger signalman hasnizam
Handbook for rigger signalman hasnizamHandbook for rigger signalman hasnizam
Handbook for rigger signalman hasnizam
 
Scaffolding by UTK
Scaffolding by UTKScaffolding by UTK
Scaffolding by UTK
 
Operating practices
Operating practicesOperating practices
Operating practices
 
Axis symmetric
Axis symmetricAxis symmetric
Axis symmetric
 
Etabs tutorial-tall-building-design (1)
Etabs tutorial-tall-building-design (1)Etabs tutorial-tall-building-design (1)
Etabs tutorial-tall-building-design (1)
 
Scaffolding
ScaffoldingScaffolding
Scaffolding
 
LSM
LSMLSM
LSM
 
Cause of accident and prevention in construction industry
Cause of accident and prevention in construction industryCause of accident and prevention in construction industry
Cause of accident and prevention in construction industry
 
Documents scaffolding
 Documents scaffolding Documents scaffolding
Documents scaffolding
 
Safety management for construction machines & equipments
 Safety management for construction machines & equipments Safety management for construction machines & equipments
Safety management for construction machines & equipments
 
working at height
working at heightworking at height
working at height
 

Similar to Managing Temporary Works - Andrea Robbins(HSE)

iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdfXiMdhk
 
Mouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxMouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxZakaria156221
 
CE 72.32 (January 2016 Semester) Lecture 2 - Design Philosophy
CE 72.32 (January 2016 Semester) Lecture 2 - Design PhilosophyCE 72.32 (January 2016 Semester) Lecture 2 - Design Philosophy
CE 72.32 (January 2016 Semester) Lecture 2 - Design PhilosophyFawad Najam
 
Final -jan-apr_2013
Final  -jan-apr_2013Final  -jan-apr_2013
Final -jan-apr_2013Sporsho
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTRiyaVerma238431
 
Modified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMModified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMnadeemovic
 
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)Shubham Arora
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projectsmtingle
 
Wheelchair Tennis: Clubhouses And Pavillions
Wheelchair Tennis: Clubhouses And PavillionsWheelchair Tennis: Clubhouses And Pavillions
Wheelchair Tennis: Clubhouses And PavillionsScott Rains
 
Ici and itd prensentation new
Ici and itd prensentation newIci and itd prensentation new
Ici and itd prensentation newWadeLim
 
CE72.52 - Lecture1 - Introduction
CE72.52 - Lecture1 - IntroductionCE72.52 - Lecture1 - Introduction
CE72.52 - Lecture1 - IntroductionFawad Najam
 
Pressure vessels
Pressure vessels  Pressure vessels
Pressure vessels GPTraining
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Processd_mackay
 
Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9Michael Shellshear
 
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed AnwarCost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed AnwarAIT Solutions
 

Similar to Managing Temporary Works - Andrea Robbins(HSE) (20)

iosh-temporary-works.pdf
iosh-temporary-works.pdfiosh-temporary-works.pdf
iosh-temporary-works.pdf
 
Mouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptxMouyadin moumin abdillahi.pptx
Mouyadin moumin abdillahi.pptx
 
CE 72.32 (January 2016 Semester) Lecture 2 - Design Philosophy
CE 72.32 (January 2016 Semester) Lecture 2 - Design PhilosophyCE 72.32 (January 2016 Semester) Lecture 2 - Design Philosophy
CE 72.32 (January 2016 Semester) Lecture 2 - Design Philosophy
 
Final -jan-apr_2013
Final  -jan-apr_2013Final  -jan-apr_2013
Final -jan-apr_2013
 
building economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENTbuilding economics.PPT LAESE, BUDGET MANAGEMENT
building economics.PPT LAESE, BUDGET MANAGEMENT
 
Presentation-Demolition-Yıkım
Presentation-Demolition-YıkımPresentation-Demolition-Yıkım
Presentation-Demolition-Yıkım
 
Modified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAMModified Risk Analysis Model APRAM
Modified Risk Analysis Model APRAM
 
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
Industrial Internship at Shapoorji Pallonji & Co. Pvt. Ltd. (HBCH & RC Site)
 
Ddg architecture
Ddg architectureDdg architecture
Ddg architecture
 
Managing The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy ProjectsManaging The Risk Of Financing Renewable Energy Projects
Managing The Risk Of Financing Renewable Energy Projects
 
Wheelchair Tennis: Clubhouses And Pavillions
Wheelchair Tennis: Clubhouses And PavillionsWheelchair Tennis: Clubhouses And Pavillions
Wheelchair Tennis: Clubhouses And Pavillions
 
Site report
Site reportSite report
Site report
 
Ici and itd prensentation new
Ici and itd prensentation newIci and itd prensentation new
Ici and itd prensentation new
 
CE72.52 - Lecture1 - Introduction
CE72.52 - Lecture1 - IntroductionCE72.52 - Lecture1 - Introduction
CE72.52 - Lecture1 - Introduction
 
Presentation_PBD.pptx
Presentation_PBD.pptxPresentation_PBD.pptx
Presentation_PBD.pptx
 
Pressure vessels
Pressure vessels  Pressure vessels
Pressure vessels
 
The Commissioning Process
The Commissioning ProcessThe Commissioning Process
The Commissioning Process
 
Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9Contractor management sections 5 topics 8& 9
Contractor management sections 5 topics 8& 9
 
The Merits of Structural Steelwork
The Merits of Structural SteelworkThe Merits of Structural Steelwork
The Merits of Structural Steelwork
 
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed AnwarCost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
Cost Effective Structural Configurations For Tall Buildings by Dr. Naveed Anwar
 

More from Alan Bassett

TOOLBOX TALK | noise and vibration
TOOLBOX TALK | noise and vibrationTOOLBOX TALK | noise and vibration
TOOLBOX TALK | noise and vibrationAlan Bassett
 
SAFETY ALERT | crane incident
SAFETY ALERT | crane incidentSAFETY ALERT | crane incident
SAFETY ALERT | crane incidentAlan Bassett
 
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2Alan Bassett
 
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalitiesSAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalitiesAlan Bassett
 
TOOLBOX TALK | dust and air quality
TOOLBOX TALK | dust and air qualityTOOLBOX TALK | dust and air quality
TOOLBOX TALK | dust and air qualityAlan Bassett
 
TOOLBOX TALK | Oxygen Enrichment
TOOLBOX TALK | Oxygen EnrichmentTOOLBOX TALK | Oxygen Enrichment
TOOLBOX TALK | Oxygen EnrichmentAlan Bassett
 
Safety alert 112 first aid
Safety alert 112 first aidSafety alert 112 first aid
Safety alert 112 first aidAlan Bassett
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsAlan Bassett
 
TOOLBOX TALK | safe use of lift trucks and telehandlers
TOOLBOX TALK | safe use of lift trucks and telehandlersTOOLBOX TALK | safe use of lift trucks and telehandlers
TOOLBOX TALK | safe use of lift trucks and telehandlersAlan Bassett
 
TOOLBOX TALK | Working at Height
TOOLBOX TALK | Working at HeightTOOLBOX TALK | Working at Height
TOOLBOX TALK | Working at HeightAlan Bassett
 
Ju t lifting bulletin
Ju t lifting bulletinJu t lifting bulletin
Ju t lifting bulletinAlan Bassett
 
02. point of work risk assessments
02. point of work risk assessments02. point of work risk assessments
02. point of work risk assessmentsAlan Bassett
 
45. 12 tips to a safe christmas
45. 12 tips to a safe christmas45. 12 tips to a safe christmas
45. 12 tips to a safe christmasAlan Bassett
 
Processed like-any-other-criminal
Processed like-any-other-criminalProcessed like-any-other-criminal
Processed like-any-other-criminalAlan Bassett
 
Toolbox talk alcohol substance_driving_2016
Toolbox talk alcohol substance_driving_2016Toolbox talk alcohol substance_driving_2016
Toolbox talk alcohol substance_driving_2016Alan Bassett
 
Safety bulletin 031 ring finger injuries
Safety bulletin 031 ring finger injuriesSafety bulletin 031 ring finger injuries
Safety bulletin 031 ring finger injuriesAlan Bassett
 
Toolbox talk jewellery
Toolbox talk jewelleryToolbox talk jewellery
Toolbox talk jewelleryAlan Bassett
 
40. work at height scaffold
40. work at height scaffold40. work at height scaffold
40. work at height scaffoldAlan Bassett
 
Grinder injury bos 17 10 16
Grinder injury bos 17 10 16Grinder injury bos 17 10 16
Grinder injury bos 17 10 16Alan Bassett
 

More from Alan Bassett (20)

TOOLBOX TALK | noise and vibration
TOOLBOX TALK | noise and vibrationTOOLBOX TALK | noise and vibration
TOOLBOX TALK | noise and vibration
 
SAFETY ALERT | crane incident
SAFETY ALERT | crane incidentSAFETY ALERT | crane incident
SAFETY ALERT | crane incident
 
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
SAFETY ALERT | serious event silo explosion_11 5 2018 rv2
 
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalitiesSAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
SAFETY ALERT | Ig safety bulletin 3350 178 machine controller fatalities
 
TOOLBOX TALK | dust and air quality
TOOLBOX TALK | dust and air qualityTOOLBOX TALK | dust and air quality
TOOLBOX TALK | dust and air quality
 
TOOLBOX TALK | Oxygen Enrichment
TOOLBOX TALK | Oxygen EnrichmentTOOLBOX TALK | Oxygen Enrichment
TOOLBOX TALK | Oxygen Enrichment
 
Safety alert 112 first aid
Safety alert 112 first aidSafety alert 112 first aid
Safety alert 112 first aid
 
TOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operationsTOOLBOX TALK | lifting & rigging operations
TOOLBOX TALK | lifting & rigging operations
 
TOOLBOX TALK | safe use of lift trucks and telehandlers
TOOLBOX TALK | safe use of lift trucks and telehandlersTOOLBOX TALK | safe use of lift trucks and telehandlers
TOOLBOX TALK | safe use of lift trucks and telehandlers
 
TOOLBOX TALK | Working at Height
TOOLBOX TALK | Working at HeightTOOLBOX TALK | Working at Height
TOOLBOX TALK | Working at Height
 
Ju t lifting bulletin
Ju t lifting bulletinJu t lifting bulletin
Ju t lifting bulletin
 
02. point of work risk assessments
02. point of work risk assessments02. point of work risk assessments
02. point of work risk assessments
 
45. 12 tips to a safe christmas
45. 12 tips to a safe christmas45. 12 tips to a safe christmas
45. 12 tips to a safe christmas
 
Processed like-any-other-criminal
Processed like-any-other-criminalProcessed like-any-other-criminal
Processed like-any-other-criminal
 
Toolbox talk alcohol substance_driving_2016
Toolbox talk alcohol substance_driving_2016Toolbox talk alcohol substance_driving_2016
Toolbox talk alcohol substance_driving_2016
 
41. line of fire
41. line of fire41. line of fire
41. line of fire
 
Safety bulletin 031 ring finger injuries
Safety bulletin 031 ring finger injuriesSafety bulletin 031 ring finger injuries
Safety bulletin 031 ring finger injuries
 
Toolbox talk jewellery
Toolbox talk jewelleryToolbox talk jewellery
Toolbox talk jewellery
 
40. work at height scaffold
40. work at height scaffold40. work at height scaffold
40. work at height scaffold
 
Grinder injury bos 17 10 16
Grinder injury bos 17 10 16Grinder injury bos 17 10 16
Grinder injury bos 17 10 16
 

Managing Temporary Works - Andrea Robbins(HSE)

  • 1. Health and Safety Health and Safety Executive Executive Managing Temporary Works Andrea Robbins HM Inspector of Health and Safety
  • 2. What are temporary works? BS 5975:2008+A1:2011 defines temporary works as: “those parts of the works that allow or enable construction of, protect, support or provide access to the permanent works and which might or might not remain in place at the completion of the works”
  • 3. Temporary Works Examples - Earthworks • Piling Platforms, Underpinning and Cofferdams etc. Construction of a Piling Platform Completed Piling Platform Underpinning
  • 4. Temporary Works Examples • Earthworks – (Supports) for Trenches, Excavations Waler Frames – For Medium Sized Trenches Close Boarded Trench Support Design of trench box - access ladder and edge protection Trench Boxes attached to box Hydraulic / Mechanical Struts Strutting Frame
  • 5. Temporary Works Examples • Structures – Formwork & Falsework Formwork (Shuttering) Falsework (Supports)
  • 6. Temporary Works Examples • Structures – Scaffold, Propping & Façade Retention Propping Façade Retention
  • 7. Temporary Works Examples • Structures – Edge Protection, Loading Bays, Temporary Bridges, Hoarding, and Signage etc Signage Edge Protection Temporary Bridges Hoarding Signage On Scaffolds etc Loading Bays
  • 8. Temporary Works Examples • Plant - Mobile Crane Outrigger Design, Hoists / Mast Climbers, Tower Crane Bases etc. Hoists / Mast Climbers Tower Crane Base Mobile Crane Outrigger Design
  • 9. Legal obligations – CDM Regulations 2007 • Reg 4 – competence required of all those with a role to discharge in planning, design and execution of TW; • Regs 5 & 6 - co-operation and co-ordination of activities, including TW, incumbent on all involved; • Reg 10 – client’s duty to provide pre-construction information, e.g. ground conditions, structural drawings; • Reg 11 – duties of designers: avoidance of foreseeable risk arising from preparing or modifying designs; • Reg 18 – additional duties of designers: provision of information to assist the CDM Co-ordinator; • Regs 13 & 22 – duties of contractors and the principal contractor: planning, management and monitoring of construction work;
  • 10. Legal obligations – CDM Regulations 2007 • Reg 20 – duties of CDM(Cs) – all reasonable steps to ensure designers comply with their duties and to ensure co-operation between designers and principal contractors in relation to any design or design change; • Reg 26 – safe place of work – scaffolding, flooring, stairs etc; • Reg 28 – stability of structures: any support or temporary structure must be designed, installed and maintained so as to withstand foreseeable loads; • Reg 29 – demolition or dismantling: planning and recording of arrangements; • Reg 31 – excavations: planning and execution; • Reg 32 – cofferdams and caissons: design, planning and execution;
  • 11. Temporary Works Procedure • Appointment of a Temporary Works Co-ordinator (TWC) • Completion and maintenance of a Temporary Works Register • Preparation of design briefs for elements identified in the register • Production of temporary works designs • Temporary works design check • Preparation of risk assessments/method statements • Pre-erection inspection of the TW materials and components • Supervision of erection of temporary works • Check that the TW have been erected in accordance with the design • Issue a formal “permit to load” where necessary • Confirm that the TW have attained adequate strength to allow TW to be dismantled • Issue a formal “permit to dismantle” where necessary
  • 12. Temporary Works Co-ordinator • Formal appointment in writing • Must be competent = experience + a formal qualification, e.g. [1] Degree/HND qualified as a minimum [2] Chartered Civil/Structural Engineer [3] Has completed formal temporary works training
  • 13. Temporary Works Co-ordinator Typical duties: • To determine the TW for a project, compile a TW register and keep all TW records; • To ensure the procedures for the control of TW are implemented on site; • To determine the type and risk class of TW on a project; • To ensure that all TW are designed and checked appropriately; • To issue the permit to load and permit to dismantle; and • To ensure that all TW activities are adequately planned and supervised.
  • 14. Temporary Works Supervisor • Assists the TW Co-ordinator • Carries out checks on the implementation process of the TW. • May issue the permit to load and permit to dismantle when specifically authorised for a defined scope and range of work.
  • 15. CDM Co-ordinator • Ensures co-operation between permanent and temporary design; • Check suitability of construction phase plan – stability of structures – have they been addressed; • Advises client of the suitability of the construction phase plan.
  • 16. Temporary works register Should include: • Design brief number; • Short description of temporary works; • Date required for design solution; • Risk category of temporary works; • Designer and design checker; • Date design complete; • Date design checked/approved; and • Erection complete and checked or “permit to load” then “permit to dismantle”.
  • 17. Risk classes of temporary works High risk (class 1 or class A) • Falsework and formwork over 3m high • Hoarding and fencing over 3m high • Façade retention schemes • Complex designed scaffold • Complex propping schemes – multiple props and multiple levels • Needling of structures greater than 2 storeys high • Working platforms for cranes and piling rigs; tower crane bases • Ground support schemes greater than 3m deep • Trenchless construction including headings, thrust bores, mini tunnels • Cofferdams • Complex structural steelwork and pre-cast concrete erection schemes
  • 18. Risk classes of temporary works Medium risk (class 2 or class B) • Hoardings & fencing up to 3m high • Simple designed scaffolds • Falsework up to 3m high • Formwork for concrete columns and walls up to 3m high • More complex propping schemes – multiple props at single level • Needling of structures up to 2 storeys high • Foundation underpinning not using piles • Excavations up to 3m deep in good ground • Safety net systems fixed to robust primary members • Temporary roofs
  • 19. Risk classes of temporary works Low risk (class 3 or class C) • Internal hoarding systems and temporary partitions not subject to wind or differential air pressure or crowd loading • Fencing and hoarding up to 1.2m high • Standard scaffold • Formwork less than 1.2m high • Shallow excavations less than 1.2m deep in good ground • Simple propping schemes – 1 or 2 props • Small MEWPs operating on a pavement designed for HGV’s or on internal ground bearing slabs and working within the level of tolerances set by the manufacturer
  • 20. Temporary works design brief • Purpose of TW – include drawings of permanent works and any specifications; • Required dimensions and any known constraints; • Particular loads including impact loads; • Ground conditions – i.e. soils, groundwater etc; • Site conditions including services, adjacent structures and access; • Available materials and equipment; and • Construction sequence and loading stages.
  • 21. Categories of Design Checks Table 1 BS5975:2008+A1:2011 Category Scope Comment Independence of checker Restricted to standard solutions only, This applies to the use of standard Because this is a site issue, the 0 to ensure the site conditions do not conflict with the scope or limitations of solutions and Not the original design, which will require both check may be carried out by another member of site or design the chosen standard solution. structural calculation and checking team. to category 1, 2 or 3 as appropriate. For simple designs. These may Such designs would be The check may be carried out by 1 include: formwork: false work (where top restraint is not assumed): needling undertaken using simple methods of analysis and be in accordance another member of the design team. and propping to brickwork openings in with the relevant standards, single storey construction. supplier’s technical literature or other reference publications. On more complex or involved designs. Category 2 checks would include The check should be carried out 2 Designs for excavations, for foundations, for structural steelwork designs where a considerable degree of interpretation of loading by an individual not involved in the design and not consulted by the connections, for reinforced concrete. or soils’ information is required designer. before the design of the foundations or excavation support or slope For complex or innovative designs, These designs include unusual The check should be carried out 3 which result in complex sequences of moving and/or construction of either designs or where significant departures from standards, novel by another organization. the temporary works or permanent methods of analysis or works. considerable exercise of engineering judgement are involved.
  • 22. Temporary works design checks • For high risk TW there must be an independent check made on the design. • For medium risk TW the check can be undertaken by the same organisation as long as there is documentary proof of the independence of the checkers. • For low risk TW the checks can be undertaken by someone in the site team or the design team.
  • 23. Temporary works design checks In all cases the design check should provide an independent check on: 1) Design concept; 2) Strength and structural adequacy (including lateral stability and overturning etc); and 3) Compliance with the design brief.
  • 24. Why are temporary works important? GOOD temporary works can bring: • Better safety; • Enhanced efficiency, quality, productivity; and • More certainty on completion times and cost.
  • 25. What happens when TW go wrong? Causes: • No (or inadequate) TW procedure • No (or inadequate) TWC appointed • Lack of competent contractor/developer/ builder • No (or inadequate) TW design • Inadequate design brief or failure to carry out proper investigation of ground conditions, underground services or structural condition of existing buildings • Unauthorised changes to an approved TW design • Lack of competent TW designer and/or erectors
  • 26. What happens when TW go wrong? Causes: • Incorrect estimation of loads to be supported (overloading) • Lack of adequate lateral stability: inadequate horizontal and/or diagonal bracing to resist lateral (wind) loads • Inadequate foundations • No temporary works equipment available • Inappropriate use of TW equipment or other non TW equipment being used for the purpose of TW • TW poorly constructed
  • 27. What happens when TW go wrong? Consequences: • Collapse or failure of the TW; • Structural failure and/or collapse of the permanent works; • Uncontrolled ingress or egress of materials, spoils or water; • Collapse of adjacent structures; • Risk of fatalities and injuries to workers and members of the public; • Delays and increased costs; and • Financial & commercial risks to contractors, sub- contractors, designers, suppliers & clients.
  • 30. When it goes wrong • Was the contractor competent ? • Was the initial construction phase plan suitable?
  • 32. AA Fanum House, Cardiff Scaffold collapse, 13 December 2000
  • 44. What is HSE doing? Work Plan 2011/12 – Aims for Temporary Works • Promote awareness & knowledge of the importance of managing TW effectively; • Improve contractors’ management arrangements for TW; • Increase the competence of those involved in TW management & design; and • Reduce accidents arising from TW failures
  • 45. What is HSE doing? How will this be achieved? • HSE Construction inspectors to target TW activities during routine site inspections; • A programme of targeted visits by HSE Civil/Structural Engineers • Initial engagement with principal contractors • May involve some “tracking back” from site to the CDM-C and the TW designer
  • 46. Sources of information • HSE website - http://www.hse.gov.uk • SIM 02/2010/04 – The Management of Temporary Works in Construction • BS5975:2008+A1:2011 – Code of practice for temporary works procedures and the permissible stress design of falsework