WELCOME!
Thank you for attending the first of two public open houses for the Disco Road Biogas
Utilization Project.
Today we are here to:
• Introduce the Disco Road Biogas Utilization Project
• Provide an overview of the approval process and potential
environmental impacts
• Answer your questions
• Ask for your feedback on the project
Please :
• Sign in to stay updated on the project
• Take hand out materials
• Fill out a Comment Sheet
• Review the Display Boards
• Speak directly with staff
Note: There is no formal presentation
1
Key Project Elements
Project Overview
• designed to produce electricity to operate the Disco Road Organics Processing
Facility (120 Disco Road), rather than purchase energy from the grid
• designed to capture waste heat that will be used to heat the digester tanks and
buildings
• the City is in the planning and early design stages of the Project and a Draft
Project Description Report (PDR) is available
Major components of the biogas utilization facility include:
• biogas pre-treatment facilities to ensure the system runs smoothly
• 2 generating engines that will produce up to 2.8 megawatts (MW) of power
• heat recovery and supply equipment
• electrical power connections to City facilities at 120 Disco Road (and
potential electrical power connections with 150 Disco Road)
The City is soliciting feedback from the public and Aboriginal communities, and
will respond to all concerns and questions.
Copies of the Draft Project Description Report are available:
• in print at today’s meeting
• In print at local libraries – Northern Elms, Humberwood, Rexdale, Albion, City Hall
• online at www.toronto.ca/discogreen
2
Project Location
Location: 150 Disco Road in Etobicoke, near Highways 427 and 409
Land Use: Industrial land owned by the City of Toronto, on a 5.4 hectare property
3
How Biogas Facilities Work
Start
here
Residual Waste, such as
plastic bags, sent to Green
Lane Landfill
Water added to material
Clean Organic Pulp
Tipping Floor
Green Bin materials collected and
sent to transfer stations.
Suspension
Buffer Tank
Anaerobic Digester
Tanks
Water
Removed
Effluent
Digester Solids
Compost
Biogas
Biogas
Utilization
system
Flare
Electricity generation for
facility (to remove/reduce
reliance on power grid)
Key Words
Anaerobic Digestion
• A process by which naturally occurring
anaerobic bacteria partially break down
biodegradable material in the absence of
oxygen
• A by-product of anaerobic digestion is biogas
Biogas
• A mixture of approximately 60% methane
and 40% carbon dioxide
• Contains minor amounts of other trace gases
and compounds
• Biogas is a renewable energy source
4
Hydropulper
processing area
The Approval Process: Renewable Energy Approval (REA)
This project involves the generation of electricity from a renewable energy source
(biogas from Green Bin waste), for which the City must apply and be granted a
Renewable Energy Approval (REA) from the Ministry of the Environment and Climate
Change.
The REA process is:
• governed by Ontario Regulation 359/09
• a strict approval process that requires extensive studies on the project’s potential
effects on the following :
• Natural heritage: plants, water,
animals
• Cultural heritage: archaeology
and built heritage
• Noise, air emissions and odours
The REA process sets out minimum
consultation requirements with the
public, municipalities and Aboriginal
communities.
Note: See Slide 7 for further detail on project timeline
Source: www.energy.gov.on.ca/images/content/en/fitguide/REA%20Timelines.JPG
5
Renewable Energy Approval: Potential Environmental Impacts and Required Studies
Natural Heritage Cultural Heritage Noise, Air Emissions and Odour
• The goal of the natural heritage
assessment is to protect natural
heritage features, such as wetlands,
woodlands, areas of natural and
scientific interest. This involves:
1. A detailed review of available
natural heritage information about
the area, including online and
published sources.
2. Site investigations during which
biologists will examine all air, land
and water within a minimum of 120
metres of the Project Location to
verify the results of the records
review, identify additional natural
features, and classify features.
• Assessment of cultural heritage
resources will be carried out in keeping
with the Ministry of Tourism, Culture
and Sport’s guidance for the REA
process.
• While archaeological resources are not
expected near the Project Location due
to use as a landfill, an assessment of
archaeological potential will be carried
out by a licensed consultant
archaeologist.
• Since buildings over 40 years of age
are situated near the Project Location,
an assessment of the Project’s impacts
to built heritage resources will be
conducted by a qualified heritage
consultant.
• Noise from the generators will be
assessed to ensure compliance with
Ministry of the Environment and
Climate Change noise level limits.
• Emissions of nitrogen oxides, sulphur
dioxide, particulate matter and other
parameters into the air will be assessed
to demonstrate compliance with
Ministry of the Environment and
Climate Change standards under
Ontario Regulation 419/05.
• Sources of odour, mitigation measures
and the potential for odour to cause
negative effects will be identified.
6
Key Project Dates and Activities
• Biogas
Utilization Study
• PIC #1 (tonight)
• Draft Project
Description
Report
• Additional
Reports
• PIC #2 (Nov.)
• Submit REA
application
Note: All timelines subject to change
Planning Design Construction Operation
De-
Commission
Summer 2013 to
Winter 2015
Winter to
Summer 2015
Fall 2015 to
Winter 2016
Spring 2016
To be
Determined
• Receive REA
approval
• Issue Design/
Build/ Operate
(DBO) Request
for Proposal
• Award DBO
Contract
• Start
Construction
• Prepare Site
• Construct
facility
• Rehabilitate
Site
• Commission
and start
operation of
Biogas
Utilization
Facility
• Operate facility
for 20 years
(expected)
• Remove and
salvage facility
components
• Restore land to
acceptable
condition for
future use
7
Next Steps:
• Summarize and respond to
comments received at this
Open House
• Prepare and complete
reports for the required
environmental studies, taking
your feedback into account
• Hold a final Public Open
House event (estimate Fall,
2014)
Contact Us:
www.toronto.ca/discogreen
Kate Kusiak, Public Consultation
416-392-2962
kkusiak@toronto.ca
or
Silvio Abate, Project Engineer
416-392-7088
sabate@toronto.ca
8
We value your feedback and
want to hear what you think
about this project.
Please complete a comment sheet
before you go so that we can take
your feedback into consideration.
9
9
City of Toronto: Future Biogas Opportunities
Additional opportunities for Biogas
Beyond Disco Road Organics Processing Facility, Solid Waste Management Services
(SWMS) has the following additional opportunities to develop biogas at 2 other
existing facilities:
1. Dufferin Organics Processing Facility – 35 Vanley Crescent, Toronto
2. Green Lane Landfill (landfill gas) - Southwold, ON
These two facilities (along with the Disco Road facility) currently collect biogas and
safely flare it on-site. Dufferin Organics Processing Facility is currently closed for
expansion and is scheduled to re-open in 2017 (estimated).
The City of Toronto’s Solid Waste Management Services is finalizing a Biogas and
Landfill Gas Utilization Strategy Study to review and assess options to further use
biogas at these two sites, including:
• Production of renewable natural gas
• Production of methanol
• Conversion to heat
• Electricity generation
10
About the City of Toronto Solid Waste Management Services Division
Mission Statement
To be a leader in providing innovative management services to residents, businesses
and visitors within the City of Toronto in an efficient, effective and courteous manner,
creating environmental sustainability, promoting diversion and maintaining a clean city.
The Division oversees and manages:
• 13 maintenance and operating yards
• Two organics processing facilities
• Seven transfer stations and
household hazardous waste depots
• Two materials recovery facilities
• The Green Lane Landfill
www.toronto.ca/garbage
11

More Related Content

What's hot

Biomass Power Plants
Biomass Power PlantsBiomass Power Plants
Biomass Power Plants
Daniel Campos
 
Biomass energy for rural india
Biomass energy for rural indiaBiomass energy for rural india
Biomass energy for rural india
Ashish Verma
 
9 biogas as_vehicle_fuel__098192800_1209_19042007
9 biogas as_vehicle_fuel__098192800_1209_190420079 biogas as_vehicle_fuel__098192800_1209_19042007
9 biogas as_vehicle_fuel__098192800_1209_19042007
Asveen Sahota
 
Waste to energy
Waste to energyWaste to energy
Waste to energy
Yuebo Yu
 

What's hot (20)

Electricity Production By Waste Materials
Electricity Production By Waste MaterialsElectricity Production By Waste Materials
Electricity Production By Waste Materials
 
Power-to-Gas - Dr. Benoit Boulinguiez
Power-to-Gas - Dr. Benoit BoulinguiezPower-to-Gas - Dr. Benoit Boulinguiez
Power-to-Gas - Dr. Benoit Boulinguiez
 
Biogas as a vehicle fuel
Biogas as a vehicle fuelBiogas as a vehicle fuel
Biogas as a vehicle fuel
 
Biomethane in the Netherlands - current state and future outlook - Michael Sa...
Biomethane in the Netherlands - current state and future outlook - Michael Sa...Biomethane in the Netherlands - current state and future outlook - Michael Sa...
Biomethane in the Netherlands - current state and future outlook - Michael Sa...
 
Analysis of producer gas carburetor for different air fuel ratios using cfd
Analysis of producer gas carburetor for different air fuel ratios using cfdAnalysis of producer gas carburetor for different air fuel ratios using cfd
Analysis of producer gas carburetor for different air fuel ratios using cfd
 
Energy from bio mass
Energy from bio massEnergy from bio mass
Energy from bio mass
 
Digestates utlilization in agriculture - a holistic analysis - Prof. Eberhard...
Digestates utlilization in agriculture - a holistic analysis - Prof. Eberhard...Digestates utlilization in agriculture - a holistic analysis - Prof. Eberhard...
Digestates utlilization in agriculture - a holistic analysis - Prof. Eberhard...
 
Biomass Power Plants
Biomass Power PlantsBiomass Power Plants
Biomass Power Plants
 
poster
posterposter
poster
 
Biomass energy for rural india
Biomass energy for rural indiaBiomass energy for rural india
Biomass energy for rural india
 
Waste to energy projects with reference to MSW, Sourabh Manuja, TERI, India
Waste to energy projects with reference to MSW, Sourabh Manuja, TERI, IndiaWaste to energy projects with reference to MSW, Sourabh Manuja, TERI, India
Waste to energy projects with reference to MSW, Sourabh Manuja, TERI, India
 
Biomass Gasification Overview - Ilkka Hannula
Biomass Gasification Overview - Ilkka HannulaBiomass Gasification Overview - Ilkka Hannula
Biomass Gasification Overview - Ilkka Hannula
 
Best practice projects and future challenges in biogas production - Frank Stumpf
Best practice projects and future challenges in biogas production - Frank StumpfBest practice projects and future challenges in biogas production - Frank Stumpf
Best practice projects and future challenges in biogas production - Frank Stumpf
 
9 biogas as_vehicle_fuel__098192800_1209_19042007
9 biogas as_vehicle_fuel__098192800_1209_190420079 biogas as_vehicle_fuel__098192800_1209_19042007
9 biogas as_vehicle_fuel__098192800_1209_19042007
 
Waste to Energy Complex Briefing
Waste to Energy Complex Briefing Waste to Energy Complex Briefing
Waste to Energy Complex Briefing
 
Biomas- Importance of Biomass and classification of Energy conversion
Biomas- Importance of Biomass and classification of Energy conversionBiomas- Importance of Biomass and classification of Energy conversion
Biomas- Importance of Biomass and classification of Energy conversion
 
Production of-renewable-energy-from-biological-sources
Production of-renewable-energy-from-biological-sourcesProduction of-renewable-energy-from-biological-sources
Production of-renewable-energy-from-biological-sources
 
Waste to energy
Waste to energyWaste to energy
Waste to energy
 
NRRI Presentation on Biomass and Deployable Housing
NRRI Presentation on Biomass and Deployable HousingNRRI Presentation on Biomass and Deployable Housing
NRRI Presentation on Biomass and Deployable Housing
 
Energy recovery from municipal solid waste (WASTE-TO-ENERGY)
Energy recovery from municipal solid waste (WASTE-TO-ENERGY)Energy recovery from municipal solid waste (WASTE-TO-ENERGY)
Energy recovery from municipal solid waste (WASTE-TO-ENERGY)
 

Similar to Disco Road Biogas Utilization Project

OLADE-Slide-Deck-compressed para ver.pdf
OLADE-Slide-Deck-compressed para ver.pdfOLADE-Slide-Deck-compressed para ver.pdf
OLADE-Slide-Deck-compressed para ver.pdf
HenryApaza12
 
BULLITT CENTER, SEATTLE, WASHINGTON.pptx
BULLITT CENTER, SEATTLE, WASHINGTON.pptxBULLITT CENTER, SEATTLE, WASHINGTON.pptx
BULLITT CENTER, SEATTLE, WASHINGTON.pptx
PushpaHarshitha05
 
Southern_Peacehaven_2014
Southern_Peacehaven_2014Southern_Peacehaven_2014
Southern_Peacehaven_2014
Iain McGregor
 
Solid wast mangement
Solid wast mangementSolid wast mangement
Solid wast mangement
Vijay Krishna
 
Marketing Presentation - June 2016
Marketing Presentation - June 2016 Marketing Presentation - June 2016
Marketing Presentation - June 2016
Mark Knippa
 

Similar to Disco Road Biogas Utilization Project (20)

EIA Case study on Fertilizer industry
EIA Case study on Fertilizer industryEIA Case study on Fertilizer industry
EIA Case study on Fertilizer industry
 
Emerging Technologies in Onsite Wastewater Treatment
Emerging Technologies in Onsite Wastewater TreatmentEmerging Technologies in Onsite Wastewater Treatment
Emerging Technologies in Onsite Wastewater Treatment
 
ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016ADBA Spring Regulatory Forum - May 2016
ADBA Spring Regulatory Forum - May 2016
 
OLADE-Slide-Deck-compressed para ver.pdf
OLADE-Slide-Deck-compressed para ver.pdfOLADE-Slide-Deck-compressed para ver.pdf
OLADE-Slide-Deck-compressed para ver.pdf
 
Solid and liquid waste management in smart cities
Solid and liquid waste management in smart citiesSolid and liquid waste management in smart cities
Solid and liquid waste management in smart cities
 
KEJORA_EIA_TRC_-_May_2021_Rev3.pptx
KEJORA_EIA_TRC_-_May_2021_Rev3.pptxKEJORA_EIA_TRC_-_May_2021_Rev3.pptx
KEJORA_EIA_TRC_-_May_2021_Rev3.pptx
 
One stopsolution
One stopsolutionOne stopsolution
One stopsolution
 
Demonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERCDemonstration project design, Ed Steadman, EERC
Demonstration project design, Ed Steadman, EERC
 
BULLITT CENTER, SEATTLE, WASHINGTON.pptx
BULLITT CENTER, SEATTLE, WASHINGTON.pptxBULLITT CENTER, SEATTLE, WASHINGTON.pptx
BULLITT CENTER, SEATTLE, WASHINGTON.pptx
 
Role of chemical engineer in environment
Role of chemical engineer in environmentRole of chemical engineer in environment
Role of chemical engineer in environment
 
ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx
 ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx
ENVIRONMENTAL IMPACT ASSESSMENT OF CEMENT PLANT___ A.pptx
 
swm.ppt
swm.pptswm.ppt
swm.ppt
 
Southern_Peacehaven_2014
Southern_Peacehaven_2014Southern_Peacehaven_2014
Southern_Peacehaven_2014
 
Solid wast mangement
Solid wast mangementSolid wast mangement
Solid wast mangement
 
Stormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste FacilityStormwater Monitoring - Newington Solid Waste Facility
Stormwater Monitoring - Newington Solid Waste Facility
 
CCUS_Fracking
CCUS_FrackingCCUS_Fracking
CCUS_Fracking
 
Solid wast management
Solid wast management Solid wast management
Solid wast management
 
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
SECARB Plant Barry CCS Project: Sharing Knowledge & Learning - Presentation b...
 
Marketing Presentation - June 2016
Marketing Presentation - June 2016 Marketing Presentation - June 2016
Marketing Presentation - June 2016
 
New Union South Sustainability 6.1.2009
New Union South Sustainability 6.1.2009New Union South Sustainability 6.1.2009
New Union South Sustainability 6.1.2009
 

More from Toronto Public Consultation Unit

More from Toronto Public Consultation Unit (20)

Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE). Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
Waterfront Sanitary Servicing Master Plan Update (Oct. 30 PIE).
 
SmartTrack Public Meeting Presentation
SmartTrack Public Meeting PresentationSmartTrack Public Meeting Presentation
SmartTrack Public Meeting Presentation
 
Waterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display PanelsWaterfront Transit Reset Phase 2 Display Panels
Waterfront Transit Reset Phase 2 Display Panels
 
Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation Waterfront Transit Reset Public Meeting Presentation
Waterfront Transit Reset Public Meeting Presentation
 
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
King-Liberty Pedestrian / Cycling Bridge Project Update - Slides
 
Sewer Outfall Project
Sewer Outfall ProjectSewer Outfall Project
Sewer Outfall Project
 
General information
General informationGeneral information
General information
 
Disinfection System
Disinfection SystemDisinfection System
Disinfection System
 
2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information 2017 Sediment Basin construction updated information
2017 Sediment Basin construction updated information
 
Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards Scarborough Subway TPAP Boards
Scarborough Subway TPAP Boards
 
2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final2017 05-18 Etobicoke Creek Nort Trail panels final
2017 05-18 Etobicoke Creek Nort Trail panels final
 
King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck King Street Phase 2 Slide Deck
King Street Phase 2 Slide Deck
 
Scarborough Subway TPAP PIC
Scarborough Subway TPAP PICScarborough Subway TPAP PIC
Scarborough Subway TPAP PIC
 
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017Six Points Interchange Reconfiguration public event display panels, May 11, 2017
Six Points Interchange Reconfiguration public event display panels, May 11, 2017
 
Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing Downsview Area Long Term Water Servicing
Downsview Area Long Term Water Servicing
 
FG Gardiner New Simcoe Ramp - display boards
FG Gardiner   New Simcoe Ramp - display boardsFG Gardiner   New Simcoe Ramp - display boards
FG Gardiner New Simcoe Ramp - display boards
 
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28  finalCollege Street Promenade BIA Streetscaping Update Public Meeting Feb 28  final
College Street Promenade BIA Streetscaping Update Public Meeting Feb 28 final
 
Swc public consultation_pres_170307_final
Swc public consultation_pres_170307_finalSwc public consultation_pres_170307_final
Swc public consultation_pres_170307_final
 
King Street Pilot Public Meeting
King Street Pilot Public MeetingKing Street Pilot Public Meeting
King Street Pilot Public Meeting
 
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
King-Liberty Pedestrian / Cycling Bridge (Dec. 8 2016 Information Panels)
 

Recently uploaded

Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
Kamal Acharya
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
mphochane1998
 

Recently uploaded (20)

Online food ordering system project report.pdf
Online food ordering system project report.pdfOnline food ordering system project report.pdf
Online food ordering system project report.pdf
 
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptxA CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
A CASE STUDY ON CERAMIC INDUSTRY OF BANGLADESH.pptx
 
Block diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.pptBlock diagram reduction techniques in control systems.ppt
Block diagram reduction techniques in control systems.ppt
 
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLEGEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
GEAR TRAIN- BASIC CONCEPTS AND WORKING PRINCIPLE
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Wadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptxWadi Rum luxhotel lodge Analysis case study.pptx
Wadi Rum luxhotel lodge Analysis case study.pptx
 
Hospital management system project report.pdf
Hospital management system project report.pdfHospital management system project report.pdf
Hospital management system project report.pdf
 
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
Work-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptxWork-Permit-Receiver-in-Saudi-Aramco.pptx
Work-Permit-Receiver-in-Saudi-Aramco.pptx
 
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
Unit 4_Part 1 CSE2001 Exception Handling and Function Template and Class Temp...
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments""Lesotho Leaps Forward: A Chronicle of Transformative Developments"
"Lesotho Leaps Forward: A Chronicle of Transformative Developments"
 
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
Bhubaneswar🌹Call Girls Bhubaneswar ❤Komal 9777949614 💟 Full Trusted CALL GIRL...
 
data_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdfdata_management_and _data_science_cheat_sheet.pdf
data_management_and _data_science_cheat_sheet.pdf
 
AIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech studentsAIRCANVAS[1].pdf mini project for btech students
AIRCANVAS[1].pdf mini project for btech students
 
Moment Distribution Method For Btech Civil
Moment Distribution Method For Btech CivilMoment Distribution Method For Btech Civil
Moment Distribution Method For Btech Civil
 
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
COST-EFFETIVE  and Energy Efficient BUILDINGS ptxCOST-EFFETIVE  and Energy Efficient BUILDINGS ptx
COST-EFFETIVE and Energy Efficient BUILDINGS ptx
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 

Disco Road Biogas Utilization Project

  • 1. WELCOME! Thank you for attending the first of two public open houses for the Disco Road Biogas Utilization Project. Today we are here to: • Introduce the Disco Road Biogas Utilization Project • Provide an overview of the approval process and potential environmental impacts • Answer your questions • Ask for your feedback on the project Please : • Sign in to stay updated on the project • Take hand out materials • Fill out a Comment Sheet • Review the Display Boards • Speak directly with staff Note: There is no formal presentation 1
  • 2. Key Project Elements Project Overview • designed to produce electricity to operate the Disco Road Organics Processing Facility (120 Disco Road), rather than purchase energy from the grid • designed to capture waste heat that will be used to heat the digester tanks and buildings • the City is in the planning and early design stages of the Project and a Draft Project Description Report (PDR) is available Major components of the biogas utilization facility include: • biogas pre-treatment facilities to ensure the system runs smoothly • 2 generating engines that will produce up to 2.8 megawatts (MW) of power • heat recovery and supply equipment • electrical power connections to City facilities at 120 Disco Road (and potential electrical power connections with 150 Disco Road) The City is soliciting feedback from the public and Aboriginal communities, and will respond to all concerns and questions. Copies of the Draft Project Description Report are available: • in print at today’s meeting • In print at local libraries – Northern Elms, Humberwood, Rexdale, Albion, City Hall • online at www.toronto.ca/discogreen 2
  • 3. Project Location Location: 150 Disco Road in Etobicoke, near Highways 427 and 409 Land Use: Industrial land owned by the City of Toronto, on a 5.4 hectare property 3
  • 4. How Biogas Facilities Work Start here Residual Waste, such as plastic bags, sent to Green Lane Landfill Water added to material Clean Organic Pulp Tipping Floor Green Bin materials collected and sent to transfer stations. Suspension Buffer Tank Anaerobic Digester Tanks Water Removed Effluent Digester Solids Compost Biogas Biogas Utilization system Flare Electricity generation for facility (to remove/reduce reliance on power grid) Key Words Anaerobic Digestion • A process by which naturally occurring anaerobic bacteria partially break down biodegradable material in the absence of oxygen • A by-product of anaerobic digestion is biogas Biogas • A mixture of approximately 60% methane and 40% carbon dioxide • Contains minor amounts of other trace gases and compounds • Biogas is a renewable energy source 4 Hydropulper processing area
  • 5. The Approval Process: Renewable Energy Approval (REA) This project involves the generation of electricity from a renewable energy source (biogas from Green Bin waste), for which the City must apply and be granted a Renewable Energy Approval (REA) from the Ministry of the Environment and Climate Change. The REA process is: • governed by Ontario Regulation 359/09 • a strict approval process that requires extensive studies on the project’s potential effects on the following : • Natural heritage: plants, water, animals • Cultural heritage: archaeology and built heritage • Noise, air emissions and odours The REA process sets out minimum consultation requirements with the public, municipalities and Aboriginal communities. Note: See Slide 7 for further detail on project timeline Source: www.energy.gov.on.ca/images/content/en/fitguide/REA%20Timelines.JPG 5
  • 6. Renewable Energy Approval: Potential Environmental Impacts and Required Studies Natural Heritage Cultural Heritage Noise, Air Emissions and Odour • The goal of the natural heritage assessment is to protect natural heritage features, such as wetlands, woodlands, areas of natural and scientific interest. This involves: 1. A detailed review of available natural heritage information about the area, including online and published sources. 2. Site investigations during which biologists will examine all air, land and water within a minimum of 120 metres of the Project Location to verify the results of the records review, identify additional natural features, and classify features. • Assessment of cultural heritage resources will be carried out in keeping with the Ministry of Tourism, Culture and Sport’s guidance for the REA process. • While archaeological resources are not expected near the Project Location due to use as a landfill, an assessment of archaeological potential will be carried out by a licensed consultant archaeologist. • Since buildings over 40 years of age are situated near the Project Location, an assessment of the Project’s impacts to built heritage resources will be conducted by a qualified heritage consultant. • Noise from the generators will be assessed to ensure compliance with Ministry of the Environment and Climate Change noise level limits. • Emissions of nitrogen oxides, sulphur dioxide, particulate matter and other parameters into the air will be assessed to demonstrate compliance with Ministry of the Environment and Climate Change standards under Ontario Regulation 419/05. • Sources of odour, mitigation measures and the potential for odour to cause negative effects will be identified. 6
  • 7. Key Project Dates and Activities • Biogas Utilization Study • PIC #1 (tonight) • Draft Project Description Report • Additional Reports • PIC #2 (Nov.) • Submit REA application Note: All timelines subject to change Planning Design Construction Operation De- Commission Summer 2013 to Winter 2015 Winter to Summer 2015 Fall 2015 to Winter 2016 Spring 2016 To be Determined • Receive REA approval • Issue Design/ Build/ Operate (DBO) Request for Proposal • Award DBO Contract • Start Construction • Prepare Site • Construct facility • Rehabilitate Site • Commission and start operation of Biogas Utilization Facility • Operate facility for 20 years (expected) • Remove and salvage facility components • Restore land to acceptable condition for future use 7
  • 8. Next Steps: • Summarize and respond to comments received at this Open House • Prepare and complete reports for the required environmental studies, taking your feedback into account • Hold a final Public Open House event (estimate Fall, 2014) Contact Us: www.toronto.ca/discogreen Kate Kusiak, Public Consultation 416-392-2962 kkusiak@toronto.ca or Silvio Abate, Project Engineer 416-392-7088 sabate@toronto.ca 8
  • 9. We value your feedback and want to hear what you think about this project. Please complete a comment sheet before you go so that we can take your feedback into consideration. 9 9
  • 10. City of Toronto: Future Biogas Opportunities Additional opportunities for Biogas Beyond Disco Road Organics Processing Facility, Solid Waste Management Services (SWMS) has the following additional opportunities to develop biogas at 2 other existing facilities: 1. Dufferin Organics Processing Facility – 35 Vanley Crescent, Toronto 2. Green Lane Landfill (landfill gas) - Southwold, ON These two facilities (along with the Disco Road facility) currently collect biogas and safely flare it on-site. Dufferin Organics Processing Facility is currently closed for expansion and is scheduled to re-open in 2017 (estimated). The City of Toronto’s Solid Waste Management Services is finalizing a Biogas and Landfill Gas Utilization Strategy Study to review and assess options to further use biogas at these two sites, including: • Production of renewable natural gas • Production of methanol • Conversion to heat • Electricity generation 10
  • 11. About the City of Toronto Solid Waste Management Services Division Mission Statement To be a leader in providing innovative management services to residents, businesses and visitors within the City of Toronto in an efficient, effective and courteous manner, creating environmental sustainability, promoting diversion and maintaining a clean city. The Division oversees and manages: • 13 maintenance and operating yards • Two organics processing facilities • Seven transfer stations and household hazardous waste depots • Two materials recovery facilities • The Green Lane Landfill www.toronto.ca/garbage 11