SlideShare a Scribd company logo
1 of 11
Evaluation of a Report published by NASA on the
Loss of Mars Polar Lander and Deep Space 2
Missions
Om Shukla
1001171582
1
CSE 5325- Software Engineering-II
Class Project:
Evaluation of the Report Published by NASA on the Loss of the Mars Polar Lander
and Deep Space 2 Missions.
Name: Shukla, Om
Student ID: 1001171582.
Date: 11/24/2015
2
Contents
1. Introduction………………………………….………………….3
2. Summary of Report………………………….………………….4
3. Conclusion…………………………………….…………………7
4. Appendix…………………………………….…………………..9
5. Reference List………………………………………………….10
3
Introduction:
Through history, people have wondered whether there is life beyond Earth. And from the
last two decades we have been continuously advancing our ability to pursue this question. Mars
is a nearest planet feasible enough for the human exploration. The Mars Pathfinder landing on
July 4th, 1997, demonstrated extraordinary public interest in Mars, setting a record of the number
of visits to a Web site. Hence the Mars Program Independent Assessment Team found no reason
not to continue the Mars exploration. While the challenges were tough, the deep space success
demonstrated that the high risk were manageable and acceptable. In 1998, NASA conducted a
review of multi-year Mars program, calling in the outside experts help evaluate and refine the
architecture for the direction of the effort. The review resulted in the series of sample-return
missions, in the early next decade. The initial plan was to launch the missions almost every year
from 1999 continuing next decade till 2013.
Thus, Mars Polar Lander was launched on January 3, 1999 at 3:21 p.m. Eastern Standard
Time, on Delta II rocket from Space Launch Complex at Cape Canaveral Air Station, Florida.
The Mars Polar Lander was the part of Jet Propulsion Laboratory’s (JPL) Mars’ 98 Development
Project. Mars Polar Lander was with two Deep Space 2 Probes, designed by NASA’s New
Millennium Program, whose purpose is to flight test new technologies and demonstrate
innovative approaches for future Missions. Deep Space 2 probe were as the size of basketball, its
challenge was that a miniature components could be sent to other planet to conduct the science
experiments. The Mars Polar Lander approached the Mars on 3 December 1999, until then the
communications were up, then there was a small trajectory-correction maneuver, this made the
Mars Polar Lander onto entry trajectory and thus the antenna pointed off from Earth, and signal
was lost as expected. After twelve minutes the communications were supposed to have
established and data should have transferred to Earth, 24 hours later. Therefore it was expected
that the first data would be received on 4th December at 7:25 p.m. PST, about seven hours after
the touchdown. However no communications were established and none data received.
Attempts to communicate with Mars Polar Lander continued till mid-January without any
success. On 17 January 2000, the flight team announced that effort to recover the Mars Polar
Lander has concluded. The JPL Special Review Board and its consultants identified number of
failure scenarios, which for convenience were organized by mission phase. The Board divided
and organized itself into the each of the Mars Polar Lander’s development areas. Each Review
Team provided an assessment in their respective areas related design and test practices relevant
to the hypothesized failure. The Review team conducted their investigations through meetings
with Mars Surveyor 98’s personnel from Lockheed Martin Aeronautics (LMA) and JPL and
Deep Space 2 project personnel.
4
Summary of Report:
In 1992, Daniel S. Goldin became the NASA administrator, after two months he
introduced a new way of working to the employees of JPL, he challenged the employees of JPL
to revolutionize the future NASA space missions to provide American people more cost-
effective space science programs. (Daniel Goldin, 1992) “How can we do everything better,
faster and cheaper, without compromising the safety?” And thus began the revolution of space
missions, the Faster Better Cheaper (FBC) strategy introduced concept of smaller spacecraft and
thus more frequent missions. The FBC strategy also distributes the risks over larger number of
small missions oppose to one large mission. Utilization of new technology was integral to the
FBC success.
REVIEW AND ANALYZE RECENT MARS AND DEEP SPACE MISSIONS
Missions Successes Failures
1. Mars Global Surveyor. x
2. Pathfinder. x
3. DeepSpace 1. x
4. Mars Climate Orbiter. x
5. Mars Polar Lander. x
6. Deep Space 2. x
Table: 1- Caparisons of Mars Missions.
However, NASA, JPL and LMA have not completely made the transition to FBC. They
had not documented the policies and procedure that made up their FBC approach. Rather project
managers had their own different interpretation. Under this environment the Mars missions
started. These different interpretation caused management to miss few steps resulting in the
failure to effectively implement FBC. Like all major changes, converting to FBC was a serious
management and leadership problem. This caused high failure rates in Mars Missions as shown
in Table 1 above. For the Mars Polar Lander, the JPL and LMA committed to the overly
challenging problematic goals during bidding for this project. The JPL management perception
was that, no cost increase is permissible. On the other hand the aggressive pricing strategy of
LMA exacerbated this problematic situation. This massive pressure of meeting the cost and
schedule goals resulted in environment of increasing risk in which too many corners were cut,
even in applying the proven engineering practices and applying the necessary checks and
balances. The Mars Program Independent Assessment Team (MPIAT) in its “Report on the Loss
of the Mars Polar Lander and Deep Space 2 Missions” dated 3/22/2000, provided the examples
such as: incomplete systems testing, lack of critical event telemetry and requirements creep.
5
According to MPIAT, the organizations JPL and LMA also failed to ensure adequate
independent reviews and adherence to the established policies and procedures.
Fig-1
The Figure above illustrates the overly constraint conditions of Mars’ 98 project. The
cost, schedule and technical requirements and launch vehicles margins were inadequate. And as
shown in figure the only remaining variable was Risk. However even in high cost constraint
environment great care should be taken for cost-risk tradeoff. Accordingly for this mission the
management was facing excessive risks, mostly which were accompanied by integrating the new
technologies. As the matter of fact management did not manage the risk quite well as it should
have been. The MPIAT in its report mentioned that there was lack of adequate risk identification,
communication, management and mitigations, and which compromised the mission’s success.
The JPL Special Review Space Board in its report “Mars Polar Lander/Deep space 2 Loss – JPL
Special Review Board Report” found few choices that were further resulted in unanticipated
design complexity and consequences. One of those decision to use the four smaller off-the-shelf
engines for stability and control for which the Lander only required at least two canted engines in
each of three locations. Another decision was to use the pulse-mode control for the descent
engines to avoid the cost and cos-risk of developing and qualifying the throttle valve and
somewhat more difficult terminal descent guidance system algorithms. This introduced other
risks in the propulsion, mechanical and control areas.
From the beginning the Mars Polar Lander project was under considerable funding and
schedule pressure. In order to meet this challenges, the Laboratory decided to manage the project
with small JPL team and to rely heavily on LMA’s management and engineering structure.
Consequently, there was no JPL line management involved into the project. The LMA first- and
6
second-level technical managers provided day to day technical oversight of the project. The JPL
team of approximately 10 technical and management people provided higher level technical
oversight. The result was minimal involvement by the JPL technical experts. On the other hand
the LMA used excessive overtime in order to complete the work on schedule within available
workforce. According to the JPL Special Review Board Report the record shows that
development staff worked 60 hours per week, and in which some of them were working almost
80 hours per week. Another consequence of the tight funding constraint was that many key
technical areas were staffed by a single individual. It is the Board’s assessment that this staffing
conditions led to a breakdown in inter-group communications, and there was insufficient time to
reflect on what may be the unintended consequence of day-to-day decision would be. In short
there was insufficient time and workforce available then normally found in the JPL projects.
The project did not have documented review plan but did hold many reviews, both formal
and informal. Subsystems Preliminary Design Reviews (PDRs) and Critical design Reviews
(CDRs) were conducted in a manner that they have reduced the level of formality but still
covering the appropriate depth and breadth of the Technical oversight. Most of the PDRs and
CDRs were included in-depth penetration by technical experts but some did not. According to
the JPL’s Special Review Boards report, in case of Propulsion subsystem, the thermal control
design interfaces were not mature enough to evaluate at CDR’s. A delta review should have been
held, but was not. Such a review could have been discovered the problems faced during the
flight. This limitation on technical penetration of action item and their closures were not typical
of JPL’s projects and was probably the unintended consequence of Project funding limitations.
The subsystems PDRs and CDRs were adequate in identifying most of technical issues.
Although all actions and recommendations were closed out formally prior to launch, these
closures were usually approved by the projects based on the LMA closures without any
independent technical support. The JPL’s Special Review Board reviewed these closure of some
action items that related to the potential failures, and found that while appropriate concerns were
raised at the reviews, the actions taken by the project did not adequately addresses these concerns
in all the cases. Why was such concerns remained unaddressed? Did they ignored such concerns,
under the pressure of schedule and budget limitations, this might be considered as unethical,
wrapping up the review process just to complete a formality!
7
Conclusion:
Figure-2: Development Cost comparison Between Pathfinder & MCO & MPL.
The most probable cause of the Mars Polar Lander failure was: premature shutdown of
lander engines due to spurious signal generated at the lander leg deployment during the descent.
The spurious signals would be a false indication that the lander has landed. This in turn will
result in the crash of Lander due to the over speed during descent. Because of the absence of
flight data there is no way to know that whether Lander reached the terminal propulsion descent
phase of the mission. If it did, the extensive test results show that it would almost certainly have
been lost due premature engine shutdown. In short the most probable cause of the Mars Polar
Lander resulted from inadequate checks and balances that permitted an incomplete systems test
and allowed a significant software design flaw to go undetected.
As we have discussed, the attributes which led to the failure:
 Inadequate JPL management Oversight.
 Inadequate margin from the beginning:
o Only variable was risk
o Overly aggressive LMA’s cost proposals
o Excessively optimistic project implementation
o Inadequate staffing: single individuals implementing many
important activities.
 Requirements Creep, inadequate Requirements management
 No Entry, Descent and Landing Telemetry (EDL)
o Impedes failure analysis, and limits ability the corrective actions.
8
When it comes to the Risk Management, it starts from the systems architectural design
phase. It is the role of the systems architect or a team of architects to evaluate the risks and
prepare risks assessments, later starts the plan for the risk identification, managements and then
avoidance or contingencies, which depends on the probability and the risk-cost. The LMA’s
Management was unable to go through all such process due to constraints we discussed, as the
project was understaffed, many key technical decisions and activities were carried out by the
single individuals. Peers working together is the best line of defense against errors. The LMA’s
negligence to such procedures and proper risk management activities attributed to the failure of
Mars Polar Lander Project.
As we can observe from the statistics of the Development cost comparison between the
Pathfinder project, which was the success with the Mars Polar Lander and Mars Climate Orbiter
project, both were failures. There is a considerable cost difference in Project management and
the Mission Engineering and Operations Development. The cost for Project Management was
less than half of that of a Pathfinder’s Project management cost. On the other hand they spend
almost same amount in science and instruments development. It could have been better if they
had found a proper balance between these spending. The technology which was being developed
should have been developed and planned such that it would be enough funding and time to carry
out reviews and testing, to make sure that the technology is ready for the mission. Which was
clearly not the case for the Deep Space 2 probes, the JPL Special Review Board found out that
the Deep Space 2 probes had not been tested enough and were not ready for the launch.
The Communication between the organizations were ineffective, which should have.
They should have conducted the high level technical and current status review with the technical
experts and senior management personnel from each organization, NASA, JPL and LMA. The
alternatives should have been explored, which would address the cost and schedule constraints of
the project. As explained by senior lecturer at University of Texas at Arlington, Dr. John Robb in
his Software Testing class (Robb, 2015) that “almost 90 % of the defects can be found by
Technical reviews”. He also explained that to find significant amount of defects in these
technical reviews, it is important to plan the review and give appropriate time for preparation to
the review members. These Technical reviews should have been carried out more frequently by
the JPL and LMA’s development team. They also should have revised the organizational
procedures for these reviews to make sure that the issues raised in these technical reviews should
be addressed by appropriate actions and notified to the issuer about these actions.
The decisions that were taken at the early phase of development should have been
documented properly, this document would have helped understanding the reasons behind those
decisions. For example the decisions of not implementing the EDL telemetry. Because the EDL
telemetry was not implemented there was no proper way to test the system, which in this case
would have helped significantly, and even could have prevented the mishap. One of the most
probable reasons that the Mars Polar Lander crashed was because, the software that should have
been designed to ignore the spurious signals was not designed to do so after all.
9
References:
1. JPL Special Review Board, “Report of the Loss of the Mars Polar Lander and Deep
Space 2 Missions” Parts [1] [2] [3] [4] [5].
2. Mars Program Independent Assessment Team (MPIAT) “Report on the Loss of the Mars
Polar Lander and Deep Space 2 Missions” date: 03/22/2000.
3. NASA Press Release.
4. Hans van Vliet (2008), Software Engineering: Principles and Practice, John Wiley &
Sons.
5. Dr. John Robb (2015), Lecture Slides on Software Testing:
https://elearn.uta.edu/webapps/blackboard/content/listContent.jsp?course_id=_268351_1
6. Paul C. Jorgensen (2013), Software Testing: A Craftsman’s Approach, Fourth Edition,
CRC Press.
10
Appendix:
1. NASA: The National Aeronautics and Space Administration (NASA) is the United States
Government agency responsible for the civilian space program as well as aeronautics and
aerospace research.
2. JPL: The Jet Propulsion Laboratory, is a federally funded research and development
center and NASA field center located in Pasadena, California, United States.
3. LMA: Lockheed Martin Aeronautics is an American global aerospace, defense, security
and advanced technologies company with worldwide interests.
4. Mars Pathfinder: Mars Pathfinder is an American robotic spacecraft that landed a base
station with a roving probe on Mars in 1997.
5. MPL: The Mars Polar Lander, was a 290-kilogram robotic spacecraft lander launched by
NASA.
6. DS2: Deep Space 2 was a NASA probe part of the New Millennium Program.
7. MCO: Mars Climate Orbiter was a 338 kilogram robotic space probe launched by
NASA.
8. EDL: Entry, Descent, and Landing.
9. MPIAT: Mars Program Independent Assessment Team.
10. PDR: Preliminary Design Review.
11. CDR: Critical Design Review.

More Related Content

Viewers also liked

Fady Samy -Quantity Surveyor
Fady Samy -Quantity SurveyorFady Samy -Quantity Surveyor
Fady Samy -Quantity Surveyor
fady qezman
 
How to Get What You Want - Data led reserach management
How to Get What You Want - Data led reserach managementHow to Get What You Want - Data led reserach management
How to Get What You Want - Data led reserach management
Jason Briggs, MInstF (Dip)
 

Viewers also liked (20)

Colegio nacional nicolas esguherra 2
Colegio nacional nicolas esguherra 2Colegio nacional nicolas esguherra 2
Colegio nacional nicolas esguherra 2
 
Colegio nacional nicolas esguerraghgf
Colegio nacional nicolas esguerraghgfColegio nacional nicolas esguerraghgf
Colegio nacional nicolas esguerraghgf
 
Fady Samy -Quantity Surveyor
Fady Samy -Quantity SurveyorFady Samy -Quantity Surveyor
Fady Samy -Quantity Surveyor
 
Finalaya featured result_25jan2013
Finalaya featured result_25jan2013Finalaya featured result_25jan2013
Finalaya featured result_25jan2013
 
The Financial Crisis of 2015: An Avoidable History
The Financial Crisis of 2015: An Avoidable HistoryThe Financial Crisis of 2015: An Avoidable History
The Financial Crisis of 2015: An Avoidable History
 
10 hours ss6
10 hours ss610 hours ss6
10 hours ss6
 
AyushUnni
AyushUnniAyushUnni
AyushUnni
 
Ppt
PptPpt
Ppt
 
EGWT
EGWTEGWT
EGWT
 
Pop up English Zone Prospectus
Pop up English Zone ProspectusPop up English Zone Prospectus
Pop up English Zone Prospectus
 
Bab iii dan iv
Bab iii dan ivBab iii dan iv
Bab iii dan iv
 
O Coelliño Branco
O Coelliño Branco O Coelliño Branco
O Coelliño Branco
 
How to Get What You Want - Data led reserach management
How to Get What You Want - Data led reserach managementHow to Get What You Want - Data led reserach management
How to Get What You Want - Data led reserach management
 
Internationalization and Localization of User Interfaces
Internationalization and Localization of User InterfacesInternationalization and Localization of User Interfaces
Internationalization and Localization of User Interfaces
 
12 startup learnings and advice
12 startup learnings and advice12 startup learnings and advice
12 startup learnings and advice
 
Insights de Emprendimiento: No se trata de lo que vendes sino Por qué lo vendes
Insights de Emprendimiento: No se trata de lo que vendes sino Por qué lo vendesInsights de Emprendimiento: No se trata de lo que vendes sino Por qué lo vendes
Insights de Emprendimiento: No se trata de lo que vendes sino Por qué lo vendes
 
Bank of England Resilience of the UK Financial System
Bank of England Resilience of the UK Financial SystemBank of England Resilience of the UK Financial System
Bank of England Resilience of the UK Financial System
 
#CommunityPower: El verdadero marketing está en la gente.
#CommunityPower: El verdadero marketing está en la gente. #CommunityPower: El verdadero marketing está en la gente.
#CommunityPower: El verdadero marketing está en la gente.
 
Cumbre Mundial de Naciones Unidas sobre el desarrollo sostenible 2015
Cumbre Mundial de Naciones Unidas sobre el desarrollo sostenible 2015Cumbre Mundial de Naciones Unidas sobre el desarrollo sostenible 2015
Cumbre Mundial de Naciones Unidas sobre el desarrollo sostenible 2015
 
Cumbre de johannesburgo
Cumbre de johannesburgoCumbre de johannesburgo
Cumbre de johannesburgo
 

Similar to Evaluation of the Report Published by NASA on the Loss of the Mars Polar Lander and Deep Space 2 Missions.

Lunar-Underground-Mining-and-Construction-A-Terrestrial-Vision-Enabling-Space...
Lunar-Underground-Mining-and-Construction-A-Terrestrial-Vision-Enabling-Space...Lunar-Underground-Mining-and-Construction-A-Terrestrial-Vision-Enabling-Space...
Lunar-Underground-Mining-and-Construction-A-Terrestrial-Vision-Enabling-Space...
Louis Grenier
 
NorthDakotaSYSTEMS
NorthDakotaSYSTEMSNorthDakotaSYSTEMS
NorthDakotaSYSTEMS
Austin Cote
 
Climate architecture final
Climate architecture finalClimate architecture final
Climate architecture final
Jaume Satorra
 
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
Art Charo
 
KGrothe Capstone Project Final Presentation
KGrothe Capstone Project Final PresentationKGrothe Capstone Project Final Presentation
KGrothe Capstone Project Final Presentation
Karen Grothe
 
713725main 2012 niac_fall_sym_day2
713725main 2012 niac_fall_sym_day2713725main 2012 niac_fall_sym_day2
713725main 2012 niac_fall_sym_day2
Clifford Stone
 
Challenger final release
Challenger final releaseChallenger final release
Challenger final release
mickmonte
 
52352main contour
52352main contour52352main contour
52352main contour
Pedro León
 
Master's Independent Study Final Report.doc
Master's Independent Study Final Report.docMaster's Independent Study Final Report.doc
Master's Independent Study Final Report.doc
butest
 
Message understanding conference 6 a brief history
Message understanding conference  6  a brief historyMessage understanding conference  6  a brief history
Message understanding conference 6 a brief history
sugeladi
 

Similar to Evaluation of the Report Published by NASA on the Loss of the Mars Polar Lander and Deep Space 2 Missions. (20)

Lunar-Underground-Mining-and-Construction-A-Terrestrial-Vision-Enabling-Space...
Lunar-Underground-Mining-and-Construction-A-Terrestrial-Vision-Enabling-Space...Lunar-Underground-Mining-and-Construction-A-Terrestrial-Vision-Enabling-Space...
Lunar-Underground-Mining-and-Construction-A-Terrestrial-Vision-Enabling-Space...
 
2583
25832583
2583
 
NorthDakotaSYSTEMS
NorthDakotaSYSTEMSNorthDakotaSYSTEMS
NorthDakotaSYSTEMS
 
The Future of Solar System Exploration
The Future of Solar System ExplorationThe Future of Solar System Exploration
The Future of Solar System Exploration
 
Final PDR; Team 15
Final PDR; Team 15Final PDR; Team 15
Final PDR; Team 15
 
Leo final report
Leo final reportLeo final report
Leo final report
 
Climate architecture final
Climate architecture finalClimate architecture final
Climate architecture final
 
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
The 2013 NRC Decadal Survey in Solar and Space Physics (Heliophysics)
 
KGrothe Capstone Project Final Presentation
KGrothe Capstone Project Final PresentationKGrothe Capstone Project Final Presentation
KGrothe Capstone Project Final Presentation
 
713725main 2012 niac_fall_sym_day2
713725main 2012 niac_fall_sym_day2713725main 2012 niac_fall_sym_day2
713725main 2012 niac_fall_sym_day2
 
Robotic Refueling Mission
Robotic Refueling MissionRobotic Refueling Mission
Robotic Refueling Mission
 
Astronauts and Robots 2015: John Grunsfeld, NASA
Astronauts and Robots 2015: John Grunsfeld, NASAAstronauts and Robots 2015: John Grunsfeld, NASA
Astronauts and Robots 2015: John Grunsfeld, NASA
 
Challenger final release
Challenger final releaseChallenger final release
Challenger final release
 
52352main contour
52352main contour52352main contour
52352main contour
 
Embry Riddle Final
Embry Riddle FinalEmbry Riddle Final
Embry Riddle Final
 
AJ_Article
AJ_ArticleAJ_Article
AJ_Article
 
Master's Independent Study Final Report.doc
Master's Independent Study Final Report.docMaster's Independent Study Final Report.doc
Master's Independent Study Final Report.doc
 
The challenger disaster Case Study
The challenger disaster Case StudyThe challenger disaster Case Study
The challenger disaster Case Study
 
Message understanding conference 6 a brief history
Message understanding conference  6  a brief historyMessage understanding conference  6  a brief history
Message understanding conference 6 a brief history
 
Risk management paper
Risk management paperRisk management paper
Risk management paper
 

Recently uploaded

Low Atmospheric Pressure Stunning is not a humane alternative to Carbon Dioxi...
Low Atmospheric Pressure Stunning is not a humane alternative to Carbon Dioxi...Low Atmospheric Pressure Stunning is not a humane alternative to Carbon Dioxi...
Low Atmospheric Pressure Stunning is not a humane alternative to Carbon Dioxi...
Harm Kiezebrink
 
Dawson City Rolling Ads for May 15 2024 Yukon
Dawson City Rolling Ads for May 15 2024 YukonDawson City Rolling Ads for May 15 2024 Yukon
Dawson City Rolling Ads for May 15 2024 Yukon
pmenzies
 
Program Kickoff- Cohort 4______ (2).pptx
Program Kickoff- Cohort 4______ (2).pptxProgram Kickoff- Cohort 4______ (2).pptx
Program Kickoff- Cohort 4______ (2).pptx
ScottMeyers35
 

Recently uploaded (20)

Help set up SERUDS Orphanage virtual classroom
Help set up SERUDS Orphanage virtual classroomHelp set up SERUDS Orphanage virtual classroom
Help set up SERUDS Orphanage virtual classroom
 
Building a better Britain: How cities like Bradford can help to end economic ...
Building a better Britain: How cities like Bradford can help to end economic ...Building a better Britain: How cities like Bradford can help to end economic ...
Building a better Britain: How cities like Bradford can help to end economic ...
 
Low Atmospheric Pressure Stunning is not a humane alternative to Carbon Dioxi...
Low Atmospheric Pressure Stunning is not a humane alternative to Carbon Dioxi...Low Atmospheric Pressure Stunning is not a humane alternative to Carbon Dioxi...
Low Atmospheric Pressure Stunning is not a humane alternative to Carbon Dioxi...
 
Mothers Without Children Yale Historical Review
Mothers Without Children Yale Historical ReviewMothers Without Children Yale Historical Review
Mothers Without Children Yale Historical Review
 
07/03/2024 Publiekdomeindag - namiddag
07/03/2024 Publiekdomeindag - namiddag07/03/2024 Publiekdomeindag - namiddag
07/03/2024 Publiekdomeindag - namiddag
 
OilChange: Big Oil Reality Check May 2024
OilChange: Big Oil Reality Check May 2024OilChange: Big Oil Reality Check May 2024
OilChange: Big Oil Reality Check May 2024
 
Finland's mental health policy and its implementation: a CSO perspective
Finland's mental health policy and its implementation: a CSO perspectiveFinland's mental health policy and its implementation: a CSO perspective
Finland's mental health policy and its implementation: a CSO perspective
 
RPO America Peer Exchange: Rural Transportation Planning Programs
RPO America Peer Exchange: Rural Transportation Planning ProgramsRPO America Peer Exchange: Rural Transportation Planning Programs
RPO America Peer Exchange: Rural Transportation Planning Programs
 
Families and Climate Change - iyf30 - IDF.2024 AGENDA PROGRAMME.
Families and Climate Change - iyf30 - IDF.2024 AGENDA PROGRAMME.Families and Climate Change - iyf30 - IDF.2024 AGENDA PROGRAMME.
Families and Climate Change - iyf30 - IDF.2024 AGENDA PROGRAMME.
 
Dawson City Rolling Ads for May 15 2024 Yukon
Dawson City Rolling Ads for May 15 2024 YukonDawson City Rolling Ads for May 15 2024 Yukon
Dawson City Rolling Ads for May 15 2024 Yukon
 
Program Kickoff- Cohort 4______ (2).pptx
Program Kickoff- Cohort 4______ (2).pptxProgram Kickoff- Cohort 4______ (2).pptx
Program Kickoff- Cohort 4______ (2).pptx
 
2024_End_of_Session_Report_Final_With_Vetoes.pdf
2024_End_of_Session_Report_Final_With_Vetoes.pdf2024_End_of_Session_Report_Final_With_Vetoes.pdf
2024_End_of_Session_Report_Final_With_Vetoes.pdf
 
Happy International Day of light - SPIE.
Happy International Day of light - SPIE.Happy International Day of light - SPIE.
Happy International Day of light - SPIE.
 
Nauru Government Gazette G.N.No. 620/2018.pdf
Nauru Government Gazette G.N.No. 620/2018.pdfNauru Government Gazette G.N.No. 620/2018.pdf
Nauru Government Gazette G.N.No. 620/2018.pdf
 
Effective Financial Reporting - May 2024
Effective Financial Reporting - May 2024Effective Financial Reporting - May 2024
Effective Financial Reporting - May 2024
 
International Day of Families - 15 May 2024 - UNDESA.
International Day of Families - 15 May 2024 - UNDESA.International Day of Families - 15 May 2024 - UNDESA.
International Day of Families - 15 May 2024 - UNDESA.
 
2024: The FAR - Federal Acquisition Regulations, Part 35
2024: The FAR - Federal Acquisition Regulations, Part 352024: The FAR - Federal Acquisition Regulations, Part 35
2024: The FAR - Federal Acquisition Regulations, Part 35
 
IEA Global Critical Minerals Outlook2024
IEA Global Critical Minerals Outlook2024IEA Global Critical Minerals Outlook2024
IEA Global Critical Minerals Outlook2024
 
Who are the Sherden Yale Historical Review
Who are the Sherden Yale Historical ReviewWho are the Sherden Yale Historical Review
Who are the Sherden Yale Historical Review
 
Dreamwater Portable Filter- Footsteps Bangladesh
Dreamwater Portable Filter- Footsteps BangladeshDreamwater Portable Filter- Footsteps Bangladesh
Dreamwater Portable Filter- Footsteps Bangladesh
 

Evaluation of the Report Published by NASA on the Loss of the Mars Polar Lander and Deep Space 2 Missions.

  • 1. Evaluation of a Report published by NASA on the Loss of Mars Polar Lander and Deep Space 2 Missions Om Shukla 1001171582
  • 2. 1 CSE 5325- Software Engineering-II Class Project: Evaluation of the Report Published by NASA on the Loss of the Mars Polar Lander and Deep Space 2 Missions. Name: Shukla, Om Student ID: 1001171582. Date: 11/24/2015
  • 3. 2 Contents 1. Introduction………………………………….………………….3 2. Summary of Report………………………….………………….4 3. Conclusion…………………………………….…………………7 4. Appendix…………………………………….…………………..9 5. Reference List………………………………………………….10
  • 4. 3 Introduction: Through history, people have wondered whether there is life beyond Earth. And from the last two decades we have been continuously advancing our ability to pursue this question. Mars is a nearest planet feasible enough for the human exploration. The Mars Pathfinder landing on July 4th, 1997, demonstrated extraordinary public interest in Mars, setting a record of the number of visits to a Web site. Hence the Mars Program Independent Assessment Team found no reason not to continue the Mars exploration. While the challenges were tough, the deep space success demonstrated that the high risk were manageable and acceptable. In 1998, NASA conducted a review of multi-year Mars program, calling in the outside experts help evaluate and refine the architecture for the direction of the effort. The review resulted in the series of sample-return missions, in the early next decade. The initial plan was to launch the missions almost every year from 1999 continuing next decade till 2013. Thus, Mars Polar Lander was launched on January 3, 1999 at 3:21 p.m. Eastern Standard Time, on Delta II rocket from Space Launch Complex at Cape Canaveral Air Station, Florida. The Mars Polar Lander was the part of Jet Propulsion Laboratory’s (JPL) Mars’ 98 Development Project. Mars Polar Lander was with two Deep Space 2 Probes, designed by NASA’s New Millennium Program, whose purpose is to flight test new technologies and demonstrate innovative approaches for future Missions. Deep Space 2 probe were as the size of basketball, its challenge was that a miniature components could be sent to other planet to conduct the science experiments. The Mars Polar Lander approached the Mars on 3 December 1999, until then the communications were up, then there was a small trajectory-correction maneuver, this made the Mars Polar Lander onto entry trajectory and thus the antenna pointed off from Earth, and signal was lost as expected. After twelve minutes the communications were supposed to have established and data should have transferred to Earth, 24 hours later. Therefore it was expected that the first data would be received on 4th December at 7:25 p.m. PST, about seven hours after the touchdown. However no communications were established and none data received. Attempts to communicate with Mars Polar Lander continued till mid-January without any success. On 17 January 2000, the flight team announced that effort to recover the Mars Polar Lander has concluded. The JPL Special Review Board and its consultants identified number of failure scenarios, which for convenience were organized by mission phase. The Board divided and organized itself into the each of the Mars Polar Lander’s development areas. Each Review Team provided an assessment in their respective areas related design and test practices relevant to the hypothesized failure. The Review team conducted their investigations through meetings with Mars Surveyor 98’s personnel from Lockheed Martin Aeronautics (LMA) and JPL and Deep Space 2 project personnel.
  • 5. 4 Summary of Report: In 1992, Daniel S. Goldin became the NASA administrator, after two months he introduced a new way of working to the employees of JPL, he challenged the employees of JPL to revolutionize the future NASA space missions to provide American people more cost- effective space science programs. (Daniel Goldin, 1992) “How can we do everything better, faster and cheaper, without compromising the safety?” And thus began the revolution of space missions, the Faster Better Cheaper (FBC) strategy introduced concept of smaller spacecraft and thus more frequent missions. The FBC strategy also distributes the risks over larger number of small missions oppose to one large mission. Utilization of new technology was integral to the FBC success. REVIEW AND ANALYZE RECENT MARS AND DEEP SPACE MISSIONS Missions Successes Failures 1. Mars Global Surveyor. x 2. Pathfinder. x 3. DeepSpace 1. x 4. Mars Climate Orbiter. x 5. Mars Polar Lander. x 6. Deep Space 2. x Table: 1- Caparisons of Mars Missions. However, NASA, JPL and LMA have not completely made the transition to FBC. They had not documented the policies and procedure that made up their FBC approach. Rather project managers had their own different interpretation. Under this environment the Mars missions started. These different interpretation caused management to miss few steps resulting in the failure to effectively implement FBC. Like all major changes, converting to FBC was a serious management and leadership problem. This caused high failure rates in Mars Missions as shown in Table 1 above. For the Mars Polar Lander, the JPL and LMA committed to the overly challenging problematic goals during bidding for this project. The JPL management perception was that, no cost increase is permissible. On the other hand the aggressive pricing strategy of LMA exacerbated this problematic situation. This massive pressure of meeting the cost and schedule goals resulted in environment of increasing risk in which too many corners were cut, even in applying the proven engineering practices and applying the necessary checks and balances. The Mars Program Independent Assessment Team (MPIAT) in its “Report on the Loss of the Mars Polar Lander and Deep Space 2 Missions” dated 3/22/2000, provided the examples such as: incomplete systems testing, lack of critical event telemetry and requirements creep.
  • 6. 5 According to MPIAT, the organizations JPL and LMA also failed to ensure adequate independent reviews and adherence to the established policies and procedures. Fig-1 The Figure above illustrates the overly constraint conditions of Mars’ 98 project. The cost, schedule and technical requirements and launch vehicles margins were inadequate. And as shown in figure the only remaining variable was Risk. However even in high cost constraint environment great care should be taken for cost-risk tradeoff. Accordingly for this mission the management was facing excessive risks, mostly which were accompanied by integrating the new technologies. As the matter of fact management did not manage the risk quite well as it should have been. The MPIAT in its report mentioned that there was lack of adequate risk identification, communication, management and mitigations, and which compromised the mission’s success. The JPL Special Review Space Board in its report “Mars Polar Lander/Deep space 2 Loss – JPL Special Review Board Report” found few choices that were further resulted in unanticipated design complexity and consequences. One of those decision to use the four smaller off-the-shelf engines for stability and control for which the Lander only required at least two canted engines in each of three locations. Another decision was to use the pulse-mode control for the descent engines to avoid the cost and cos-risk of developing and qualifying the throttle valve and somewhat more difficult terminal descent guidance system algorithms. This introduced other risks in the propulsion, mechanical and control areas. From the beginning the Mars Polar Lander project was under considerable funding and schedule pressure. In order to meet this challenges, the Laboratory decided to manage the project with small JPL team and to rely heavily on LMA’s management and engineering structure. Consequently, there was no JPL line management involved into the project. The LMA first- and
  • 7. 6 second-level technical managers provided day to day technical oversight of the project. The JPL team of approximately 10 technical and management people provided higher level technical oversight. The result was minimal involvement by the JPL technical experts. On the other hand the LMA used excessive overtime in order to complete the work on schedule within available workforce. According to the JPL Special Review Board Report the record shows that development staff worked 60 hours per week, and in which some of them were working almost 80 hours per week. Another consequence of the tight funding constraint was that many key technical areas were staffed by a single individual. It is the Board’s assessment that this staffing conditions led to a breakdown in inter-group communications, and there was insufficient time to reflect on what may be the unintended consequence of day-to-day decision would be. In short there was insufficient time and workforce available then normally found in the JPL projects. The project did not have documented review plan but did hold many reviews, both formal and informal. Subsystems Preliminary Design Reviews (PDRs) and Critical design Reviews (CDRs) were conducted in a manner that they have reduced the level of formality but still covering the appropriate depth and breadth of the Technical oversight. Most of the PDRs and CDRs were included in-depth penetration by technical experts but some did not. According to the JPL’s Special Review Boards report, in case of Propulsion subsystem, the thermal control design interfaces were not mature enough to evaluate at CDR’s. A delta review should have been held, but was not. Such a review could have been discovered the problems faced during the flight. This limitation on technical penetration of action item and their closures were not typical of JPL’s projects and was probably the unintended consequence of Project funding limitations. The subsystems PDRs and CDRs were adequate in identifying most of technical issues. Although all actions and recommendations were closed out formally prior to launch, these closures were usually approved by the projects based on the LMA closures without any independent technical support. The JPL’s Special Review Board reviewed these closure of some action items that related to the potential failures, and found that while appropriate concerns were raised at the reviews, the actions taken by the project did not adequately addresses these concerns in all the cases. Why was such concerns remained unaddressed? Did they ignored such concerns, under the pressure of schedule and budget limitations, this might be considered as unethical, wrapping up the review process just to complete a formality!
  • 8. 7 Conclusion: Figure-2: Development Cost comparison Between Pathfinder & MCO & MPL. The most probable cause of the Mars Polar Lander failure was: premature shutdown of lander engines due to spurious signal generated at the lander leg deployment during the descent. The spurious signals would be a false indication that the lander has landed. This in turn will result in the crash of Lander due to the over speed during descent. Because of the absence of flight data there is no way to know that whether Lander reached the terminal propulsion descent phase of the mission. If it did, the extensive test results show that it would almost certainly have been lost due premature engine shutdown. In short the most probable cause of the Mars Polar Lander resulted from inadequate checks and balances that permitted an incomplete systems test and allowed a significant software design flaw to go undetected. As we have discussed, the attributes which led to the failure:  Inadequate JPL management Oversight.  Inadequate margin from the beginning: o Only variable was risk o Overly aggressive LMA’s cost proposals o Excessively optimistic project implementation o Inadequate staffing: single individuals implementing many important activities.  Requirements Creep, inadequate Requirements management  No Entry, Descent and Landing Telemetry (EDL) o Impedes failure analysis, and limits ability the corrective actions.
  • 9. 8 When it comes to the Risk Management, it starts from the systems architectural design phase. It is the role of the systems architect or a team of architects to evaluate the risks and prepare risks assessments, later starts the plan for the risk identification, managements and then avoidance or contingencies, which depends on the probability and the risk-cost. The LMA’s Management was unable to go through all such process due to constraints we discussed, as the project was understaffed, many key technical decisions and activities were carried out by the single individuals. Peers working together is the best line of defense against errors. The LMA’s negligence to such procedures and proper risk management activities attributed to the failure of Mars Polar Lander Project. As we can observe from the statistics of the Development cost comparison between the Pathfinder project, which was the success with the Mars Polar Lander and Mars Climate Orbiter project, both were failures. There is a considerable cost difference in Project management and the Mission Engineering and Operations Development. The cost for Project Management was less than half of that of a Pathfinder’s Project management cost. On the other hand they spend almost same amount in science and instruments development. It could have been better if they had found a proper balance between these spending. The technology which was being developed should have been developed and planned such that it would be enough funding and time to carry out reviews and testing, to make sure that the technology is ready for the mission. Which was clearly not the case for the Deep Space 2 probes, the JPL Special Review Board found out that the Deep Space 2 probes had not been tested enough and were not ready for the launch. The Communication between the organizations were ineffective, which should have. They should have conducted the high level technical and current status review with the technical experts and senior management personnel from each organization, NASA, JPL and LMA. The alternatives should have been explored, which would address the cost and schedule constraints of the project. As explained by senior lecturer at University of Texas at Arlington, Dr. John Robb in his Software Testing class (Robb, 2015) that “almost 90 % of the defects can be found by Technical reviews”. He also explained that to find significant amount of defects in these technical reviews, it is important to plan the review and give appropriate time for preparation to the review members. These Technical reviews should have been carried out more frequently by the JPL and LMA’s development team. They also should have revised the organizational procedures for these reviews to make sure that the issues raised in these technical reviews should be addressed by appropriate actions and notified to the issuer about these actions. The decisions that were taken at the early phase of development should have been documented properly, this document would have helped understanding the reasons behind those decisions. For example the decisions of not implementing the EDL telemetry. Because the EDL telemetry was not implemented there was no proper way to test the system, which in this case would have helped significantly, and even could have prevented the mishap. One of the most probable reasons that the Mars Polar Lander crashed was because, the software that should have been designed to ignore the spurious signals was not designed to do so after all.
  • 10. 9 References: 1. JPL Special Review Board, “Report of the Loss of the Mars Polar Lander and Deep Space 2 Missions” Parts [1] [2] [3] [4] [5]. 2. Mars Program Independent Assessment Team (MPIAT) “Report on the Loss of the Mars Polar Lander and Deep Space 2 Missions” date: 03/22/2000. 3. NASA Press Release. 4. Hans van Vliet (2008), Software Engineering: Principles and Practice, John Wiley & Sons. 5. Dr. John Robb (2015), Lecture Slides on Software Testing: https://elearn.uta.edu/webapps/blackboard/content/listContent.jsp?course_id=_268351_1 6. Paul C. Jorgensen (2013), Software Testing: A Craftsman’s Approach, Fourth Edition, CRC Press.
  • 11. 10 Appendix: 1. NASA: The National Aeronautics and Space Administration (NASA) is the United States Government agency responsible for the civilian space program as well as aeronautics and aerospace research. 2. JPL: The Jet Propulsion Laboratory, is a federally funded research and development center and NASA field center located in Pasadena, California, United States. 3. LMA: Lockheed Martin Aeronautics is an American global aerospace, defense, security and advanced technologies company with worldwide interests. 4. Mars Pathfinder: Mars Pathfinder is an American robotic spacecraft that landed a base station with a roving probe on Mars in 1997. 5. MPL: The Mars Polar Lander, was a 290-kilogram robotic spacecraft lander launched by NASA. 6. DS2: Deep Space 2 was a NASA probe part of the New Millennium Program. 7. MCO: Mars Climate Orbiter was a 338 kilogram robotic space probe launched by NASA. 8. EDL: Entry, Descent, and Landing. 9. MPIAT: Mars Program Independent Assessment Team. 10. PDR: Preliminary Design Review. 11. CDR: Critical Design Review.