SlideShare a Scribd company logo
1 of 8
Download to read offline
Progress Update (Nr. 3)
Week ending 23rd October
Programme Update - ITS
For Period : Mon 10th October – Friday 23rd October
- Commence excavations to the new basement area of the extension and muck away
- Begin excavations of new perimeter retaining walls
- Fully set out new building footprint and excavate necessary pad foundations
- Installation of associated insulation, reinforcement and temporary formwork in
preparation for concrete pours
- Completed new internal flooring infills where redundant staircases removed
- Commence first fix mechanical and electrical works within existing building
Progress Photos – Internal
First fix mechanical and
electrical works
commenced within the
existing buidling
Progress Photos – Internal
Damp proof membrane
applied to walls within
basement
Progress Photos – Internal
Further internal damp-
proofing works to basement
walls commenced including
re-plaster (to 1.5m) where
required
Progress Photos – External
Reduced level dig complete
to basement area with
damp proofing and
reinforcement installation
begun.
Progress Photos – External
Below ground drainage
‘pop ups’ for sinks and
toilets etc installed prior to
concrete pours
Next Few Weeks………..
A look ahead to works commencing within the next 2 weeks :
- Complete excavations to new ground floor slab and perimeter retaining walls
- Complete installation of reinforcement to basement slab and concrete pour
- Excavate pad foundations to proposed ground floor and install associated holding
down bolts in preparation for steelwork
- Complete internal damp-proofing works to basement walls
- Commence internal builders work and remove remaining load bearing walls:
including installing required lintels and steelwork
- Continue first fix mechanical and electrical works within existing building to all floors

More Related Content

Viewers also liked

Air safety attitudes: preliminary insights post MH370
Air safety attitudes: preliminary insights post MH370Air safety attitudes: preliminary insights post MH370
Air safety attitudes: preliminary insights post MH370
Institute for Transport Studies (ITS)
 
Would predicting peoples’ choices get any easier if we understood behaviour?
Would predicting peoples’ choices get any easier if we understood behaviour?Would predicting peoples’ choices get any easier if we understood behaviour?
Would predicting peoples’ choices get any easier if we understood behaviour?
Institute for Transport Studies (ITS)
 

Viewers also liked (20)

Public Opinion of Low Carbon Innovation Policy
Public Opinion of Low Carbon Innovation Policy Public Opinion of Low Carbon Innovation Policy
Public Opinion of Low Carbon Innovation Policy
 
Air safety attitudes: preliminary insights post MH370
Air safety attitudes: preliminary insights post MH370Air safety attitudes: preliminary insights post MH370
Air safety attitudes: preliminary insights post MH370
 
Is the equity value of time really fair
Is the equity value of time really fairIs the equity value of time really fair
Is the equity value of time really fair
 
International comparisons of transport appraisal practice.
International comparisons of transport appraisal practice.  International comparisons of transport appraisal practice.
International comparisons of transport appraisal practice.
 
MSc Transport Planning & MSc Sustainability (Transport)
MSc Transport Planning & MSc Sustainability (Transport) MSc Transport Planning & MSc Sustainability (Transport)
MSc Transport Planning & MSc Sustainability (Transport)
 
Vehicle emissions measurement: micro-trip analysis of non-stationary time-series
Vehicle emissions measurement: micro-trip analysis of non-stationary time-seriesVehicle emissions measurement: micro-trip analysis of non-stationary time-series
Vehicle emissions measurement: micro-trip analysis of non-stationary time-series
 
Buses and the_economy_ii_main_report_july2014
Buses and the_economy_ii_main_report_july2014Buses and the_economy_ii_main_report_july2014
Buses and the_economy_ii_main_report_july2014
 
Freight transport models with logistics in data-rich and not so rich environ...
Freight transport models with logistics in data-rich and not so rich environ...Freight transport models with logistics in data-rich and not so rich environ...
Freight transport models with logistics in data-rich and not so rich environ...
 
Would predicting peoples’ choices get any easier if we understood behaviour?
Would predicting peoples’ choices get any easier if we understood behaviour?Would predicting peoples’ choices get any easier if we understood behaviour?
Would predicting peoples’ choices get any easier if we understood behaviour?
 
Growing and understanding passenger rail demand
Growing and understanding passenger rail demandGrowing and understanding passenger rail demand
Growing and understanding passenger rail demand
 
Congestion pricing in Gothenburg
Congestion pricing in GothenburgCongestion pricing in Gothenburg
Congestion pricing in Gothenburg
 
Annual Research Report 2014 - Institute for Transport Studies
Annual Research Report 2014 - Institute for Transport StudiesAnnual Research Report 2014 - Institute for Transport Studies
Annual Research Report 2014 - Institute for Transport Studies
 
Designing a new train
Designing a new trainDesigning a new train
Designing a new train
 
Déclaration sur la gouvernance démocratique politique-economique entreprises
 Déclaration sur la gouvernance démocratique politique-economique entreprises Déclaration sur la gouvernance démocratique politique-economique entreprises
Déclaration sur la gouvernance démocratique politique-economique entreprises
 
Le japon une puissance déclinante - quelles conséquences géopolitiques
Le japon   une puissance déclinante - quelles conséquences géopolitiquesLe japon   une puissance déclinante - quelles conséquences géopolitiques
Le japon une puissance déclinante - quelles conséquences géopolitiques
 
La réorganisation géostratégique mondiale
La réorganisation géostratégique mondialeLa réorganisation géostratégique mondiale
La réorganisation géostratégique mondiale
 
Le système éducatif djiboutien Diagnostic sectoriel et perspectives pour la p...
Le système éducatif djiboutien Diagnostic sectoriel et perspectives pour la p...Le système éducatif djiboutien Diagnostic sectoriel et perspectives pour la p...
Le système éducatif djiboutien Diagnostic sectoriel et perspectives pour la p...
 
Pedestrian planning and modelling
Pedestrian planning and modellingPedestrian planning and modelling
Pedestrian planning and modelling
 
Crossrail 2 - Planning for the Future
Crossrail 2 - Planning for the FutureCrossrail 2 - Planning for the Future
Crossrail 2 - Planning for the Future
 
AUDIT ENVIRONNEMENTAL DU DÉPÔT D’HYDROCARBURES DE LA SOCIETE « HORIZON TERMIN...
AUDIT ENVIRONNEMENTAL DU DÉPÔT D’HYDROCARBURES DE LA SOCIETE « HORIZON TERMIN...AUDIT ENVIRONNEMENTAL DU DÉPÔT D’HYDROCARBURES DE LA SOCIETE « HORIZON TERMIN...
AUDIT ENVIRONNEMENTAL DU DÉPÔT D’HYDROCARBURES DE LA SOCIETE « HORIZON TERMIN...
 

Similar to ITS building project progress update 3

SCTE Solar Story
SCTE Solar StorySCTE Solar Story
SCTE Solar Story
SCTE
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Crosstown TO
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Crosstown TO
 

Similar to ITS building project progress update 3 (12)

ITS building project progress update 1+2
ITS building project progress update 1+2ITS building project progress update 1+2
ITS building project progress update 1+2
 
ITS Building Project - progress update 8
ITS Building Project - progress update 8ITS Building Project - progress update 8
ITS Building Project - progress update 8
 
ITS Building Project - progress update 5
ITS Building Project - progress update 5ITS Building Project - progress update 5
ITS Building Project - progress update 5
 
ITS Bulding Project - progress update April 2016
ITS Bulding Project  - progress update April 2016 ITS Bulding Project  - progress update April 2016
ITS Bulding Project - progress update April 2016
 
SCTE Solar Story
SCTE Solar StorySCTE Solar Story
SCTE Solar Story
 
Roosevelt High School Renovation Project SIT Meeting (January 15, 2015)
Roosevelt High School Renovation Project SIT Meeting (January 15, 2015)Roosevelt High School Renovation Project SIT Meeting (January 15, 2015)
Roosevelt High School Renovation Project SIT Meeting (January 15, 2015)
 
Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation Please click here to view the Cranmer Court Presentation
Please click here to view the Cranmer Court Presentation
 
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
Chaplin & Avenue Construction Liaison Committee Meeting - July 2017
 
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
Chaplin-Avenue Construction Liaison Committee Meeting - October 2017
 
Retrofitting case study of RCC structure
Retrofitting case study of RCC structureRetrofitting case study of RCC structure
Retrofitting case study of RCC structure
 
Protecting PHandENV Dolls place
Protecting PHandENV Dolls placeProtecting PHandENV Dolls place
Protecting PHandENV Dolls place
 
Wellesley High School Project
Wellesley High School ProjectWellesley High School Project
Wellesley High School Project
 

More from Institute for Transport Studies (ITS)

Social networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourSocial networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviour
Institute for Transport Studies (ITS)
 
Rail freight in Japan - track access
Rail freight in Japan - track accessRail freight in Japan - track access
Rail freight in Japan - track access
Institute for Transport Studies (ITS)
 

More from Institute for Transport Studies (ITS) (20)

Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
Transport Projects Aimed at Fostering Economic Growth – experience in the UK ...
 
BA Geography with Transport Studies at the University of Leeds
BA Geography with Transport Studies at the University of LeedsBA Geography with Transport Studies at the University of Leeds
BA Geography with Transport Studies at the University of Leeds
 
Highways Benchmarking - Accelerating Impact
Highways Benchmarking - Accelerating ImpactHighways Benchmarking - Accelerating Impact
Highways Benchmarking - Accelerating Impact
 
Using telematics data to research traffic related air pollution
Using telematics data to research traffic related air pollutionUsing telematics data to research traffic related air pollution
Using telematics data to research traffic related air pollution
 
Masters Dissertation Posters 2017
Masters Dissertation Posters 2017Masters Dissertation Posters 2017
Masters Dissertation Posters 2017
 
Institute for Transport Studies - Masters Open Day 2017
Institute for Transport Studies - Masters Open Day 2017Institute for Transport Studies - Masters Open Day 2017
Institute for Transport Studies - Masters Open Day 2017
 
London's Crossrail Scheme - its evolution, governance, financing and challenges
London's Crossrail Scheme  - its evolution, governance, financing and challengesLondon's Crossrail Scheme  - its evolution, governance, financing and challenges
London's Crossrail Scheme - its evolution, governance, financing and challenges
 
Secretary of State Visit
Secretary of State VisitSecretary of State Visit
Secretary of State Visit
 
Business model innovation for electrical vehicle futures
Business model innovation for electrical vehicle futuresBusiness model innovation for electrical vehicle futures
Business model innovation for electrical vehicle futures
 
A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...A clustering method based on repeated trip behaviour to identify road user cl...
A clustering method based on repeated trip behaviour to identify road user cl...
 
Cars cars everywhere
Cars cars everywhereCars cars everywhere
Cars cars everywhere
 
Annual Review 2015-16 - University of leeds
Annual Review 2015-16 - University of leedsAnnual Review 2015-16 - University of leeds
Annual Review 2015-16 - University of leeds
 
Social networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviourSocial networks, activities, and travel - building links to understand behaviour
Social networks, activities, and travel - building links to understand behaviour
 
Rail freight in Japan - track access
Rail freight in Japan - track accessRail freight in Japan - track access
Rail freight in Japan - track access
 
Real time traffic management - challenges and solutions
Real time traffic management - challenges and solutionsReal time traffic management - challenges and solutions
Real time traffic management - challenges and solutions
 
Proportionally fair scheduling for traffic light networks
Proportionally fair scheduling for traffic light networksProportionally fair scheduling for traffic light networks
Proportionally fair scheduling for traffic light networks
 
Capacity maximising traffic signal control policies
Capacity maximising traffic signal control policiesCapacity maximising traffic signal control policies
Capacity maximising traffic signal control policies
 
Bayesian risk assessment of autonomous vehicles
Bayesian risk assessment of autonomous vehiclesBayesian risk assessment of autonomous vehicles
Bayesian risk assessment of autonomous vehicles
 
Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...Agent based car following model for heterogeneities of platoon driving with v...
Agent based car following model for heterogeneities of platoon driving with v...
 
A new theory of lane selection on highways
A new theory of lane selection on highwaysA new theory of lane selection on highways
A new theory of lane selection on highways
 

Recently uploaded

Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
negromaestrong
 

Recently uploaded (20)

Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17  How to Extend Models Using Mixin ClassesMixin Classes in Odoo 17  How to Extend Models Using Mixin Classes
Mixin Classes in Odoo 17 How to Extend Models Using Mixin Classes
 
SOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning PresentationSOC 101 Demonstration of Learning Presentation
SOC 101 Demonstration of Learning Presentation
 
Spatium Project Simulation student brief
Spatium Project Simulation student briefSpatium Project Simulation student brief
Spatium Project Simulation student brief
 
Food safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdfFood safety_Challenges food safety laboratories_.pdf
Food safety_Challenges food safety laboratories_.pdf
 
Application orientated numerical on hev.ppt
Application orientated numerical on hev.pptApplication orientated numerical on hev.ppt
Application orientated numerical on hev.ppt
 
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
TỔNG ÔN TẬP THI VÀO LỚP 10 MÔN TIẾNG ANH NĂM HỌC 2023 - 2024 CÓ ĐÁP ÁN (NGỮ Â...
 
Seal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptxSeal of Good Local Governance (SGLG) 2024Final.pptx
Seal of Good Local Governance (SGLG) 2024Final.pptx
 
On National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan FellowsOn National Teacher Day, meet the 2024-25 Kenan Fellows
On National Teacher Day, meet the 2024-25 Kenan Fellows
 
Understanding Accommodations and Modifications
Understanding  Accommodations and ModificationsUnderstanding  Accommodations and Modifications
Understanding Accommodations and Modifications
 
Sociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning ExhibitSociology 101 Demonstration of Learning Exhibit
Sociology 101 Demonstration of Learning Exhibit
 
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...Kodo Millet  PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
Kodo Millet PPT made by Ghanshyam bairwa college of Agriculture kumher bhara...
 
How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17How to Give a Domain for a Field in Odoo 17
How to Give a Domain for a Field in Odoo 17
 
Dyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptxDyslexia AI Workshop for Slideshare.pptx
Dyslexia AI Workshop for Slideshare.pptx
 
How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17How to Create and Manage Wizard in Odoo 17
How to Create and Manage Wizard in Odoo 17
 
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
2024-NATIONAL-LEARNING-CAMP-AND-OTHER.pptx
 
Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024Mehran University Newsletter Vol-X, Issue-I, 2024
Mehran University Newsletter Vol-X, Issue-I, 2024
 
psychiatric nursing HISTORY COLLECTION .docx
psychiatric  nursing HISTORY  COLLECTION  .docxpsychiatric  nursing HISTORY  COLLECTION  .docx
psychiatric nursing HISTORY COLLECTION .docx
 
Unit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptxUnit-V; Pricing (Pharma Marketing Management).pptx
Unit-V; Pricing (Pharma Marketing Management).pptx
 
Magic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptxMagic bus Group work1and 2 (Team 3).pptx
Magic bus Group work1and 2 (Team 3).pptx
 
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
Explore beautiful and ugly buildings. Mathematics helps us create beautiful d...
 

ITS building project progress update 3

  • 1. Progress Update (Nr. 3) Week ending 23rd October
  • 2. Programme Update - ITS For Period : Mon 10th October – Friday 23rd October - Commence excavations to the new basement area of the extension and muck away - Begin excavations of new perimeter retaining walls - Fully set out new building footprint and excavate necessary pad foundations - Installation of associated insulation, reinforcement and temporary formwork in preparation for concrete pours - Completed new internal flooring infills where redundant staircases removed - Commence first fix mechanical and electrical works within existing building
  • 3. Progress Photos – Internal First fix mechanical and electrical works commenced within the existing buidling
  • 4. Progress Photos – Internal Damp proof membrane applied to walls within basement
  • 5. Progress Photos – Internal Further internal damp- proofing works to basement walls commenced including re-plaster (to 1.5m) where required
  • 6. Progress Photos – External Reduced level dig complete to basement area with damp proofing and reinforcement installation begun.
  • 7. Progress Photos – External Below ground drainage ‘pop ups’ for sinks and toilets etc installed prior to concrete pours
  • 8. Next Few Weeks……….. A look ahead to works commencing within the next 2 weeks : - Complete excavations to new ground floor slab and perimeter retaining walls - Complete installation of reinforcement to basement slab and concrete pour - Excavate pad foundations to proposed ground floor and install associated holding down bolts in preparation for steelwork - Complete internal damp-proofing works to basement walls - Commence internal builders work and remove remaining load bearing walls: including installing required lintels and steelwork - Continue first fix mechanical and electrical works within existing building to all floors