Your SlideShare is downloading. ×
0
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Wccac Update Jan 11
Upcoming SlideShare
Loading in...5
×

Thanks for flagging this SlideShare!

Oops! An error has occurred.

×
Saving this for later? Get the SlideShare app to save on your phone or tablet. Read anywhere, anytime – even offline.
Text the download link to your phone
Standard text messaging rates apply

Wccac Update Jan 11

113

Published on

Waller Creek Tunnel Project Status briefing to Advisory Committee - Meeting cancelled due to snow :)

Waller Creek Tunnel Project Status briefing to Advisory Committee - Meeting cancelled due to snow :)

0 Comments
0 Likes
Statistics
Notes
  • Be the first to comment

  • Be the first to like this

No Downloads
Views
Total Views
113
On Slideshare
0
From Embeds
0
Number of Embeds
0
Actions
Shares
0
Downloads
0
Comments
0
Likes
0
Embeds 0
No embeds

Report content
Flagged as inappropriate Flag as inappropriate
Flag as inappropriate

Select your reason for flagging this presentation as inappropriate.

Cancel
No notes for slide

Transcript

  • 1. Waller Creek Citizen Advisory CommitteeTunnel Project Update January 2011
  • 2. Overview Project Management Activities Project-wide Issues Schedule Budget Sub-Projects Lady Bird Lake Trail Bridge PARD Boat Facility Tunnel/ 4th Street Inlet Inlet Sub-Project Outlet Sub-Project 8th Street Inlet Restoration Projects
  • 3. Legend: DesignSchedule Status Bid & Award ConstructionProject 2009 2010 2011 2012 2013 2014Bridge Rehabilitation TunnelBoathouse ConnectTunnelInletOutlet8th Street InletWaterloo RestorationOutlet Restoration4th Street Restoration8th Street Restoration Today
  • 4. Lady Bird Lake Trail BridgeIn ConstructionConstruction Schedule: Pier construction in January Bridge construction in FebruaryCurrent Status: Construction entrance complete Environmental pre-con complete Pier site preparation complete Steel submittals approved Steel being fabricated
  • 5. PARD Boat FacilityIn ConstructionCurrent Status: Construction entrance complete Environmental pre-con complete Temp Boat Storage being constructed Utility work ongoing Landscape screening complete
  • 6. Tunnel / 4th Street Sub-ProjectIn AwardSchedule: RCA to Council February 17, 2011 Anticipated construction start February 28, 2011Current Status: Property access acquired Site power being installed Parking leases set for closure Field offices being set up
  • 7. Inlet Sub-ProjectDesign is 90% complete.Current Activities: Permit application under review Bid documents being developedNext Steps:Advertised date is:March 28, 2011
  • 8. Tree Preventative MaintenanceAustin Tree Experts awarded contracthttp://www.austintreeexperts.com/waterloo.cfmCurrent Activities: Tree pruning and mulching Web site developed and linked Outlet Heritage trees inspectedNext Steps:This process will continueuntil inlet contractor starts.
  • 9. Outlet Sub-ProjectDesign is 60% complete.Current Activities: Performing design reviewsNext Steps:90% due in February
  • 10. 8th Street InletDesign is 90% complete.Current Activities: Review comments being addressed Utility relocation being coordinatedNext Steps:Pre-final due in March
  • 11. Restoration Projects(Outlet Restoration - Waterloo Restoration – 4th & 8th St. restoration)Design is 25- 30% complete.Design is linked to site development but will be constructed in 2013.Current Activities: Design is part of related area project for permitting. Once approved, restoration will be bid as separate packages. Additional detail and coordination: Trellis Solar elements Benches Trails Trees, etcNext Steps:Define scope for construction packages – Late 2011
  • 12. Public OutreachRecent activities: Transitioning to Construction Phase outreach KVUE interview KLBJ interviewUpcoming activities:• Flyers adjacent to boathouse construction site• Signage adjacent to boathouse construction site• Flood Awareness Campaign• Winter newsletter• Planning the tunnel groundbreaking

×