SlideShare a Scribd company logo
1 of 12
Waller Creek Citizen
 Advisory Committee
Tunnel Project Update

     January 2011
Overview
      Project Management Activities
         Project-wide Issues
         Schedule
         Budget


      Sub-Projects
         Lady Bird Lake Trail Bridge
         PARD Boat Facility
         Tunnel/ 4th Street Inlet
         Inlet Sub-Project
         Outlet Sub-Project
         8th Street Inlet
         Restoration Projects
Legend:   Design
Schedule Status                                  Bid & Award
                                                 Construction
Project                  2009 2010 2011 2012 2013 2014
Bridge Rehabilitation
                                                          Tunnel
Boathouse                                                 Connect

Tunnel
Inlet
Outlet
8th Street Inlet
Waterloo Restoration
Outlet Restoration
4th Street Restoration
8th Street Restoration
                               Today
Lady Bird Lake Trail Bridge
In Construction

Construction Schedule:
  Pier construction in January
  Bridge construction in February

Current Status:
  Construction entrance complete
  Environmental pre-con complete
  Pier site preparation complete
  Steel submittals approved
  Steel being fabricated
PARD Boat Facility
In Construction

Current Status:
 Construction entrance complete
 Environmental pre-con complete
 Temp Boat Storage being constructed
 Utility work ongoing
 Landscape screening complete
Tunnel / 4th Street Sub-Project
In Award

Schedule:
  RCA to Council February 17, 2011
  Anticipated construction start
  February 28, 2011

Current Status:
  Property access acquired
  Site power being installed
  Parking leases set for closure
  Field offices being set up
Inlet Sub-Project
Design is 90% complete.

Current Activities:
      Permit application under review
      Bid documents being developed



Next Steps:
Advertised date is:
March 28, 2011
Tree Preventative Maintenance
Austin Tree Experts awarded contract
http://www.austintreeexperts.com/waterloo.cfm

Current Activities:
      Tree pruning and mulching
      Web site developed and linked
      Outlet Heritage trees inspected

Next Steps:
This process will continue
until inlet contractor starts.
Outlet Sub-Project
Design is 60% complete.

Current Activities:
      Performing design reviews

Next Steps:
90% due in February
8th Street Inlet
Design is 90% complete.

Current Activities:
      Review comments being addressed
      Utility relocation being coordinated

Next Steps:
Pre-final due in March
Restoration Projects
(Outlet Restoration - Waterloo Restoration – 4th & 8th St. restoration)

Design is 25- 30% complete.
Design is linked to site development but will be constructed in 2013.

Current Activities:
     Design is part of related area project for permitting.
     Once approved, restoration will be bid as separate packages.
     Additional detail and coordination:
           Trellis
           Solar elements
           Benches
           Trails
           Trees, etc
Next Steps:
Define scope for construction packages – Late 2011
Public Outreach
Recent activities:
  Transitioning to Construction Phase outreach
  KVUE interview
  KLBJ interview

Upcoming activities:
• Flyers adjacent to boathouse construction site
• Signage adjacent to boathouse construction site
• Flood Awareness Campaign
• Winter newsletter
• Planning the tunnel groundbreaking

More Related Content

What's hot

Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Crosstown TO
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restorationFairfax County
 
Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15VDOT Northern Virginia
 
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingSpringfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingFairfax County
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Fairfax County
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016VDOT Northern Virginia
 
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Fairfax County
 
CPAC Meeting 9-22-03
CPAC Meeting 9-22-03CPAC Meeting 9-22-03
CPAC Meeting 9-22-03HartTWI
 
Lakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community MeetingLakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community MeetingFairfax County
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairFairfax County
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestFairfax County
 
Fort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer ProjectFort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer ProjectFairfax County
 
Waynewood II Force Main Replacement
Waynewood II Force Main ReplacementWaynewood II Force Main Replacement
Waynewood II Force Main ReplacementFairfax County
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationFairfax County
 
Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23Darren Shaw, SIOR
 
Pike Branch Tributary Ridgeview Park - May 19, 2016
Pike Branch Tributary Ridgeview Park - May 19, 2016Pike Branch Tributary Ridgeview Park - May 19, 2016
Pike Branch Tributary Ridgeview Park - May 19, 2016Fairfax County
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairFairfax County
 

What's hot (20)

Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
Brentcliffe - Victoria Park Construction Liaison Committee Meeting - June 2017
 
Substantial completion flatlick branch iii stream restoration
Substantial completion   flatlick branch iii stream restorationSubstantial completion   flatlick branch iii stream restoration
Substantial completion flatlick branch iii stream restoration
 
Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15Diverging Diamond Interchange: I-66 and Route 15
Diverging Diamond Interchange: I-66 and Route 15
 
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community MeetingSpringfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
Springfield Estates Pump Station Gravity Sewer Replacement - Community Meeting
 
euclid creek tunnel ppt may 2013
euclid creek tunnel ppt may 2013euclid creek tunnel ppt may 2013
euclid creek tunnel ppt may 2013
 
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
Celedon Lane Virtual Community Meeting Slipline Replacement August 19, 2020
 
Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016Pardon Our Dust meeting, March 9, 2016
Pardon Our Dust meeting, March 9, 2016
 
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
Little Pimmit Run at Chesterbrook Stream Restoration Project and Little Pimmi...
 
CPAC Meeting 9-22-03
CPAC Meeting 9-22-03CPAC Meeting 9-22-03
CPAC Meeting 9-22-03
 
Lakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community MeetingLakevale Estates Collection Improvements Community Meeting
Lakevale Estates Collection Improvements Community Meeting
 
Graham Port Plaza Emergency Repair
Graham Port Plaza Emergency RepairGraham Port Plaza Emergency Repair
Graham Port Plaza Emergency Repair
 
Accotink Tributary at Danbury Forest
Accotink Tributary at Danbury ForestAccotink Tributary at Danbury Forest
Accotink Tributary at Danbury Forest
 
Fort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer ProjectFort Hunt Road Emergency Gravity Sewer Project
Fort Hunt Road Emergency Gravity Sewer Project
 
Waynewood II Force Main Replacement
Waynewood II Force Main ReplacementWaynewood II Force Main Replacement
Waynewood II Force Main Replacement
 
Little Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station RehabilitationLittle Hunting Creek Pump Station Rehabilitation
Little Hunting Creek Pump Station Rehabilitation
 
Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23Wlrt com-grand linq-technical-briefing-2015-02-23
Wlrt com-grand linq-technical-briefing-2015-02-23
 
Pike Branch Tributary Ridgeview Park - May 19, 2016
Pike Branch Tributary Ridgeview Park - May 19, 2016Pike Branch Tributary Ridgeview Park - May 19, 2016
Pike Branch Tributary Ridgeview Park - May 19, 2016
 
Fitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement ProjectFitchburg Commuter Rail Line Improvement Project
Fitchburg Commuter Rail Line Improvement Project
 
Fairfax Community Leaders Conference
Fairfax Community Leaders ConferenceFairfax Community Leaders Conference
Fairfax Community Leaders Conference
 
Green Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer RepairGreen Hill Estates Emergency Sewer Repair
Green Hill Estates Emergency Sewer Repair
 

Similar to Wccac Update Jan 11

Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road RealignmentFairfax County
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Fairfax County
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IVFairfax County
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration ProjectFairfax County
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectFairfax County
 
Oak Harbor Design Open House
Oak Harbor Design Open HouseOak Harbor Design Open House
Oak Harbor Design Open Housepublicinvolvement
 
Peyton Run POD Presentation_5_12_21
 Peyton Run POD Presentation_5_12_21 Peyton Run POD Presentation_5_12_21
Peyton Run POD Presentation_5_12_21Fairfax County
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)Crosstown TO
 
Waynewood l Force Main Rehabilitation Project Jan 8, 2021
Waynewood l Force Main Rehabilitation Project Jan 8, 2021Waynewood l Force Main Rehabilitation Project Jan 8, 2021
Waynewood l Force Main Rehabilitation Project Jan 8, 2021Fairfax County
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectFairfax County
 
Oakton Community Park Phase 2A
Oakton Community Park Phase 2AOakton Community Park Phase 2A
Oakton Community Park Phase 2AFairfax County
 
Exposition Light Rail Transit Project 1
Exposition Light Rail Transit Project 1Exposition Light Rail Transit Project 1
Exposition Light Rail Transit Project 1Daryl Kellner
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingCrosstown TO
 
Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014Fairfax County
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectFairfax County
 
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Fairfax County
 
Accotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration ProjectAccotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration ProjectFairfax County
 

Similar to Wccac Update Jan 11 (20)

Exec Team Update 6 6 11
Exec Team Update 6 6 11Exec Team Update 6 6 11
Exec Team Update 6 6 11
 
Cinder Bed Road Realignment
Cinder Bed Road RealignmentCinder Bed Road Realignment
Cinder Bed Road Realignment
 
Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2Flatlick Sewer Rehabilitation Project Phase 1 and 2
Flatlick Sewer Rehabilitation Project Phase 1 and 2
 
Burke VRE Connector Phase IV
Burke VRE Connector Phase IVBurke VRE Connector Phase IV
Burke VRE Connector Phase IV
 
Indian Run Restoration Project
Indian Run Restoration ProjectIndian Run Restoration Project
Indian Run Restoration Project
 
Oak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction ProjectOak Marr Pump Station Rehabilitation – Construction Project
Oak Marr Pump Station Rehabilitation – Construction Project
 
Canal City - Poster-
Canal City - Poster-Canal City - Poster-
Canal City - Poster-
 
Lower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 ConstructionLower Don Valley Trail 2015 Construction
Lower Don Valley Trail 2015 Construction
 
Oak Harbor Design Open House
Oak Harbor Design Open HouseOak Harbor Design Open House
Oak Harbor Design Open House
 
Peyton Run POD Presentation_5_12_21
 Peyton Run POD Presentation_5_12_21 Peyton Run POD Presentation_5_12_21
Peyton Run POD Presentation_5_12_21
 
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
CLC presentation deck Brentcliffe to Victoria Park (July 9 2020)
 
Waynewood l Force Main Rehabilitation Project Jan 8, 2021
Waynewood l Force Main Rehabilitation Project Jan 8, 2021Waynewood l Force Main Rehabilitation Project Jan 8, 2021
Waynewood l Force Main Rehabilitation Project Jan 8, 2021
 
Pike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization ProjectPike Branch at Wilton Road Stream Stabilization Project
Pike Branch at Wilton Road Stream Stabilization Project
 
Oakton Community Park Phase 2A
Oakton Community Park Phase 2AOakton Community Park Phase 2A
Oakton Community Park Phase 2A
 
Exposition Light Rail Transit Project 1
Exposition Light Rail Transit Project 1Exposition Light Rail Transit Project 1
Exposition Light Rail Transit Project 1
 
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) MeetingBrentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
Brentcliffe - Victoria Park Construction Liaison Committee (CLC) Meeting
 
Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014Miller Heights Outfall Rehabilitation Project 2014
Miller Heights Outfall Rehabilitation Project 2014
 
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction ProjectCommunity Meeting - Indian Run Gravity Sewer Replacement Construction Project
Community Meeting - Indian Run Gravity Sewer Replacement Construction Project
 
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
Stream & Water Quality Improvements Dulles Maintenance Facility (DMF) Salt St...
 
Accotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration ProjectAccotink Creek at Wakefield Park Stream Restoration Project
Accotink Creek at Wakefield Park Stream Restoration Project
 

Wccac Update Jan 11

  • 1. Waller Creek Citizen Advisory Committee Tunnel Project Update January 2011
  • 2. Overview Project Management Activities Project-wide Issues Schedule Budget Sub-Projects Lady Bird Lake Trail Bridge PARD Boat Facility Tunnel/ 4th Street Inlet Inlet Sub-Project Outlet Sub-Project 8th Street Inlet Restoration Projects
  • 3. Legend: Design Schedule Status Bid & Award Construction Project 2009 2010 2011 2012 2013 2014 Bridge Rehabilitation Tunnel Boathouse Connect Tunnel Inlet Outlet 8th Street Inlet Waterloo Restoration Outlet Restoration 4th Street Restoration 8th Street Restoration Today
  • 4. Lady Bird Lake Trail Bridge In Construction Construction Schedule: Pier construction in January Bridge construction in February Current Status: Construction entrance complete Environmental pre-con complete Pier site preparation complete Steel submittals approved Steel being fabricated
  • 5. PARD Boat Facility In Construction Current Status: Construction entrance complete Environmental pre-con complete Temp Boat Storage being constructed Utility work ongoing Landscape screening complete
  • 6. Tunnel / 4th Street Sub-Project In Award Schedule: RCA to Council February 17, 2011 Anticipated construction start February 28, 2011 Current Status: Property access acquired Site power being installed Parking leases set for closure Field offices being set up
  • 7. Inlet Sub-Project Design is 90% complete. Current Activities: Permit application under review Bid documents being developed Next Steps: Advertised date is: March 28, 2011
  • 8. Tree Preventative Maintenance Austin Tree Experts awarded contract http://www.austintreeexperts.com/waterloo.cfm Current Activities: Tree pruning and mulching Web site developed and linked Outlet Heritage trees inspected Next Steps: This process will continue until inlet contractor starts.
  • 9. Outlet Sub-Project Design is 60% complete. Current Activities: Performing design reviews Next Steps: 90% due in February
  • 10. 8th Street Inlet Design is 90% complete. Current Activities: Review comments being addressed Utility relocation being coordinated Next Steps: Pre-final due in March
  • 11. Restoration Projects (Outlet Restoration - Waterloo Restoration – 4th & 8th St. restoration) Design is 25- 30% complete. Design is linked to site development but will be constructed in 2013. Current Activities: Design is part of related area project for permitting. Once approved, restoration will be bid as separate packages. Additional detail and coordination: Trellis Solar elements Benches Trails Trees, etc Next Steps: Define scope for construction packages – Late 2011
  • 12. Public Outreach Recent activities: Transitioning to Construction Phase outreach KVUE interview KLBJ interview Upcoming activities: • Flyers adjacent to boathouse construction site • Signage adjacent to boathouse construction site • Flood Awareness Campaign • Winter newsletter • Planning the tunnel groundbreaking