Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13 Harmal RMS-2 Construction & 16" DSS Pipeline to KGP Phase 1 & Phase 2 - FinalHarmal FD-10-Oct13 Harmal RMS-2 Construction & 16" D... 776 09-Dec-12 28-Jan-15 0
Harmal FD-10-Oct13.3 Harmal Field Development - Phase-1Harmal FD-10-Oct13.3 Harmal Field Development - Phase-1 625 09-Dec-12 30-Aug-14 36
Harmal FD-10-Oct13.3.1.11 ENGINEERING Phase 1Harmal FD-10-Oct13.3.1.11 ENGINEERING Phase 1 625 09-Dec-12 30-Aug-14 36
Harmal FD-10-Oct13.3.1.11.1.1.2 AFC PackageHarmal FD-10-Oct13.3.1.11.1.1.2 AFC Package 286 09-Dec-12 25-Sep-13 140
D100 Electrical 200 05-Jan-13 10-Sep-13 28
D100A Electrical-OHL 238 05-Jan-13 31-Aug-13 165
D110 Control and automation 215 01-Jan-13 25-Sep-13 28
D120 Pipeline 237 06-Jan-13 31-Aug-13 71
D70 Civil 145 27-Jan-13 27-Jul-13 53
D80 Mechanical and Piping 142 24-Dec-12 18-Jun-13 28
D90 Process 225 09-Dec-12 14-Sep-13 0
Harmal FD-10-Oct13.3.1.11.1 Bulk MTOHarmal FD-10-Oct13.3.1.11.1 Bulk MTO 172 30-Jan-13 21-Jul-13 50
A3110 Mechanical and Piping 170 30-Jan-13 19-Jul-13 37
A3120 Civil and Structural 165 01-Feb-13 16-Jul-13 50
A3130 Electrical 165 06-Feb-13 21-Jul-13 50
A3140 Control and Automation 162 06-Feb-13 18-Jul-13 50
Harmal FD-10-Oct13.3.1.11.2 Project Management and Support DocumentsHarmal FD-10-Oct13.3.1.11.2 Project Management and Support Documents 625 09-Dec-12 30-Aug-14 36
A3150 Project Management 600 09-Dec-12 05-Aug-14 41
A3160 Project Support & As Built Completion 339 25-Sep-13 30-Aug-14 36
A3270 SAP Management 319 25-Sep-13 10-Aug-14 36
A3280 CCMS 319 25-Sep-13 10-Aug-14 36
Harmal FD-10-Oct13.3.1.2 PROCUREMENT Phase 1Harmal FD-10-Oct13.3.1.2 PROCUREMENT Phase 1 487 13-Jan-13 15-May-14 66
Harmal FD-10-Oct13.3.1.2.1 16" DSS Pipeline & RMS-2 ConstructionHarmal FD-10-Oct13.3.1.2.1 16" DSS Pipeline & RMS-2 Construction 487 13-Jan-13 15-May-14 66
Harmal FD-10-Oct13.3.1.2.1.2 MechanicalHarmal FD-10-Oct13.3.1.2.1.2 Mechanical 474 13-Jan-13 02-May-14 67
Harmal FD-10-Oct13.3.1.2.1.2.1.2.1 Delivery of 16" DSS PipesHarmal FD-10-Oct13.3.1.2.1.2.1.2.1 Delivery of 16" DSS Pipes 367 13-Jan-13 15-Jan-14 47
357 PR Issue 1 13-Jan-13 14-Jan-13 47
358 Enquiry Floating 7 14-Jan-13 21-Jan-13 47
359 Receive quotes from Vendors 7 22-Jan-13 29-Jan-13 47
360 Technical Bid Evaluation 14 30-Jan-13 13-Feb-13 47
361 Vendor Data and complete commercial 10 14-Feb-13 24-Feb-13 47
362 Issue of PO 2 25-Feb-13 27-Feb-13 47
363 Manufacturing of Pipes & Coating 286 28-Feb-13 11-Dec-13 47
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
364 Inspection, Rlease & Shipment 150 29-Jul-13 26-Dec-13 47
365 Pipe Receipt at Site 125 12-Sep-13 15-Jan-14 47
Harmal FD-10-Oct13.3.1.2.1.2.1.2.3 FlangesHarmal FD-10-Oct13.3.1.2.1.2.1.2.3 Flanges 283 30-Mar-13 07-Jan-14 67
375 PR Issue 2 30-Mar-13 01-Apr-13 67
376 Enquiry Floating 7 02-Apr-13 09-Apr-13 67
377 Receive quotes from Vendors 21 09-Apr-13 30-Apr-13 67
378 Technical Bid Evaluation 15 30-Apr-13 15-May-13 67
379 Vendor Data and complete commercial 5 15-May-13 20-May-13 67
380 Issue of PO 7 21-May-13 28-May-13 67
381 Manufacturing process at Vendor Yard 145 28-May-13 20-Oct-13 67
382 Shipping Delivery 34 20-Oct-13 23-Nov-13 67
383 Flange Receipt at site 45 23-Nov-13 07-Jan-14 67
Harmal FD-10-Oct13.3.1.2.1.2.1.2.6 IJ SpoolsHarmal FD-10-Oct13.3.1.2.1.2.1.2.6 IJ Spools 322 31-Mar-13 16-Feb-14 76
402 PR Issue 2 31-Mar-13 02-Apr-13 76
403 Enquiry Floating 11 03-Apr-13 14-Apr-13 76
404 Receive quotes from Vendors 14 15-Apr-13 29-Apr-13 76
405 Technical Bid Evaluation 30 30-Apr-13 30-May-13 76
406 Vendor Data and complete commercial 10 31-May-13 10-Jun-13 76
407 Issue of PO 6 11-Jun-13 17-Jun-13 76
408 Manufacturing of Items 185 18-Jun-13 20-Dec-13 76
409 Shipping Delivery 40 21-Dec-13 30-Jan-14 76
410 IJ Spool Receipt at Site 10 06-Feb-14 16-Feb-14 76
Harmal FD-10-Oct13.3.1.2.1.2.1.2.7 Barred TeeHarmal FD-10-Oct13.3.1.2.1.2.1.2.7 Barred Tee 316 01-Apr-13 11-Feb-14 138
411 PR Issue 2 01-Apr-13 03-Apr-13 138
412 Enquiry Floating 7 03-Apr-13 10-Apr-13 138
413 Receive quotes from Vendors 14 10-Apr-13 24-Apr-13 138
414 Technical Bid Evaluation 30 24-Apr-13 24-May-13 138
415 Vendor Data and complete commercial 14 24-May-13 07-Jun-13 138
416 Issue of PO 2 07-Jun-13 09-Jun-13 138
417 Manufacturing of Items 190 09-Jun-13 16-Dec-13 138
418 Shipping Delivery 20 16-Dec-13 05-Jan-14 138
419 Barred TEE Receipt at Site 30 12-Jan-14 11-Feb-14 138
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13.3.1.2.1.2.1.2.8 Shrink sleeveHarmal FD-10-Oct13.3.1.2.1.2.1.2.8 Shrink sleeve 210 15-Apr-13 11-Nov-13 85
420 PR Issue 2 15-Apr-13 17-Apr-13 85
421 Enquiry Floating 11 17-Apr-13 28-Apr-13 85
422 Receive quotes from Vendors 14 28-Apr-13 12-May-13 85
423 TBE & Vendor Finilize 30 12-May-13 11-Jun-13 85
424 Issue of PO 2 11-Jun-13 13-Jun-13 85
425 Manufacturing of Items 100 13-Jun-13 21-Sep-13 85
426 Inspection & Release 4 21-Sep-13 25-Sep-13 85
427 Material Delivery 20 25-Sep-13 15-Oct-13 85
428 Shrink Sleeve Receipt at Site 20 22-Oct-13 11-Nov-13 85
Harmal FD-10-Oct13.3.1.2.1.2.2 Vent StackHarmal FD-10-Oct13.3.1.2.1.2.2 Vent Stack 383 14-Apr-13 02-May-14 67
A1360 PR Issue 6 14-Apr-13 20-Apr-13 67
A1370 Enquiry Floating 14 20-Apr-13 04-May-13 67
A1380 Receive quotes from Vendors 145 04-May-13 26-Sep-13 67
A1390 TBE & Vendor Finilize 140 19-May-13 06-Oct-13 67
A1400 Issue of PO 2 06-Oct-13 08-Oct-13 67
A1410 Manufacturing of Items 120 08-Oct-13 05-Feb-14 67
A1420 FAT, Final Inspection & Release 30 05-Feb-14 07-Mar-14 67
A1430 Material Delivery 20 07-Mar-14 27-Mar-14 67
A1431 Vent Stack Receipt at Site 26 06-Apr-14 02-May-14 67
Harmal FD-10-Oct13.3.1.2.1.2.1 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.2.1 Bulk Materials 298 30-Apr-13 22-Feb-14 37
1529 PR Issue 30 30-Apr-13 30-May-13 37
1539 Enquiry Floating 90 30-May-13 28-Aug-13 37
1549 Receive quotes from Vendors 100 04-Jun-13 12-Sep-13 37
1569 Vendor Data and complete commercial 75 09-Jul-13 22-Sep-13 37
1579 Issue of PO 30 23-Sep-13 23-Oct-13 37
1589 Manufacturing of Materials 110 13-Oct-13 31-Jan-14 37
1599 Shipping Delivery 110 02-Nov-13 20-Feb-14 37
1609 Fittings Receipt at site( 106 08-Nov-13 22-Feb-14 37
Harmal FD-10-Oct13.3.1.2.1.2.4 Internal ClampsHarmal FD-10-Oct13.3.1.2.1.2.4 Internal Clamps 151 27-Apr-13 25-Sep-13 79
A2330 PR Issue 6 27-Apr-13 03-May-13 79
A2340 Enquiry Floating 14 03-May-13 17-May-13 79
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
A2350 Recieve quotes from Vendors 21 17-May-13 07-Jun-13 79
A2360 Vendor Data and complete commercial 7 07-Jun-13 14-Jun-13 79
A2370 Issue of PO 2 15-Jun-13 17-Jun-13 79
A2380 Maufacturing of mateirals 70 18-Jun-13 27-Aug-13 79
A2390 Shipping Delivery 10 28-Aug-13 17-Sep-13 79
A2400 Reciept at site 7 18-Sep-13 25-Sep-13 79
Harmal FD-10-Oct13.3.1.2.1.3 ElectricalHarmal FD-10-Oct13.3.1.2.1.3 Electrical 361 08-May-13 04-May-14 63
Harmal FD-10-Oct13.3.1.2.1.3.1 415 V LVSBHarmal FD-10-Oct13.3.1.2.1.3.1 415 V LVSB 224 26-Jun-13 05-Feb-14 136
A1200 PR Issue 2 26-Jun-13 28-Jun-13 136
A1210 Enquiry Floating 14 28-Jun-13 12-Jul-13 136
A1220 Receive quotes from Vendor 7 12-Jul-13 19-Jul-13 136
A1230 TBE & Vendor Finilze 62 19-Jul-13 19-Sep-13 136
A1240 Issue of PO 2 19-Sep-13 21-Sep-13 136
A1250 Manufacturing of Material 90 21-Sep-13 20-Dec-13 136
A1260 Inspection & Release 20 20-Dec-13 09-Jan-14 136
A1270 Material Delivery 20 16-Jan-14 05-Feb-14 136
Harmal FD-10-Oct13.3.1.2.1.3.1.2.11 Electrical TransformerHarmal FD-10-Oct13.3.1.2.1.3.1.2.11 Electrical Transformer 345 08-May-13 18-Apr-14 61
448 PR Issue 2 08-May-13 10-May-13 61
449 Enquiry Floating 14 10-May-13 24-May-13 61
450 Receive quotes from Vendors 120 20-May-13 17-Sep-13 61
451 Technical Bid Evaluation & Vendor Finalize 120 30-May-13 27-Sep-13 61
452 Vendor Data and complete commercial 12 27-Sep-13 09-Oct-13 61
453 Issue of PO 9 09-Oct-13 18-Oct-13 61
454 Manufacturing of Items 125 18-Oct-13 20-Feb-14 61
455 FAT, Final Inspection & Release 30 20-Feb-14 22-Mar-14 61
456 Delivery at Site 20 29-Mar-14 18-Apr-14 61
Harmal FD-10-Oct13.3.1.2.1.3.1.2.12 Electrical DBHarmal FD-10-Oct13.3.1.2.1.3.1.2.12 Electrical DB 259 25-Jun-13 11-Mar-14 117
458 PR Issue 6 25-Jun-13 01-Jul-13 117
459 Enquiry Floating 21 01-Jul-13 22-Jul-13 117
460 Receive quotes from Vendors 15 22-Jul-13 06-Aug-13 117
461 Vendor Finilize 55 06-Aug-13 30-Sep-13 117
462 Issue of PO 10 30-Sep-13 10-Oct-13 117
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
463 Manufacturing of Items 100 10-Oct-13 18-Jan-14 117
464 FAT, Final Inspection & Release 15 18-Jan-14 02-Feb-14 117
465 Material Delivery 30 09-Feb-14 11-Mar-14 117
Harmal FD-10-Oct13.3.1.2.1.3.1.2.14 OHL materialsHarmal FD-10-Oct13.3.1.2.1.3.1.2.14 OHL materials 213 25-Jun-13 24-Jan-14 137
477 PR Issue 6 25-Jun-13 01-Jul-13 137
478 Enquiry Floating 6 01-Jul-13 07-Jul-13 137
479 Receive quotes from Vendors 12 07-Jul-13 19-Jul-13 137
480 Vendor Finilize 15 19-Jul-13 03-Aug-13 137
481 Issue of PO 4 03-Aug-13 07-Aug-13 137
482 Manufacturing of Items 140 07-Aug-13 25-Dec-13 137
483 Material Delivery 20 04-Jan-14 24-Jan-14 137
Harmal FD-10-Oct13.3.1.2.1.3.2 Containerized SubstationHarmal FD-10-Oct13.3.1.2.1.3.2 Containerized Substation 313 25-Jun-13 04-May-14 50
A1520 PR Issue 2 25-Jun-13 27-Jun-13 50
A1530 Enquiry Floating 7 27-Jun-13 04-Jul-13 50
A1540 Receive quotes from Vendors 90 04-Jul-13 02-Oct-13 50
A1550 Technical Bid Evaluation 15 02-Oct-13 17-Oct-13 50
A1560 Vendor Data and complete commercial 10 17-Oct-13 27-Oct-13 50
A1570 Issue of PO 6 27-Oct-13 02-Nov-13 50
A1580 Manufacturing of Items 150 02-Nov-13 01-Apr-14 50
A1590 FAT, Final Inspection & Release 15 01-Apr-14 16-Apr-14 50
A1600 Material Delivery 15 19-Apr-14 04-May-14 50
Harmal FD-10-Oct13.3.1.2.1.3.1.2.13 AC UPS & UPS DBHarmal FD-10-Oct13.3.1.2.1.3.1.2.13 AC UPS & UPS DB 296 25-Jun-13 17-Apr-14 75
467 PR Issue 7 25-Jun-13 02-Jul-13 75
468 Enquiry Floating 21 02-Jul-13 23-Jul-13 75
469 Receive quotes from Vendors 60 23-Jul-13 21-Sep-13 75
470 Technical Bid Evaluation 15 21-Sep-13 06-Oct-13 75
471 Vendor Data and complete commercial 15 06-Oct-13 21-Oct-13 75
472 Issue of PO 6 21-Oct-13 27-Oct-13 75
473 Manufacturing of Items 130 27-Oct-13 06-Mar-14 75
474 FAT, Final Inspection & Release 15 06-Mar-14 21-Mar-14 75
475 Material Delivery 20 28-Mar-14 17-Apr-14 75
Harmal FD-10-Oct13.3.1.2.1.3.3 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.3.3 Bulk Materials 193 24-Aug-13 05-Mar-14 112
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
1709 PR Issue 6 24-Aug-13 30-Aug-13 112
1719 Enquiry Floating 6 30-Aug-13 05-Sep-13 112
1729 Receive quotes from Vendors 25 05-Sep-13 30-Sep-13 112
1739 Vendor Finilize 30 30-Sep-13 30-Oct-13 112
1749 Issue of PO 6 30-Oct-13 05-Nov-13 112
1759 Manufacturing of Items 90 05-Nov-13 03-Feb-14 112
1769 Material Delivery 20 13-Feb-14 05-Mar-14 112
Harmal FD-10-Oct13.3.1.2.1.4 InstrumentationHarmal FD-10-Oct13.3.1.2.1.4 Instrumentation 396 14-Apr-13 15-May-14 66
Harmal FD-10-Oct13.3.1.2.1.4.1.2.10 FCS systemHarmal FD-10-Oct13.3.1.2.1.4.1.2.10 FCS system 329 16-Jun-13 11-May-14 51
438 PR Issue 2 16-Jun-13 18-Jun-13 51
439 Enquiry Floating 7 18-Jun-13 25-Jun-13 51
440 Receive quotes from Vendors 130 25-Jun-13 02-Nov-13 51
441 Technical Bid Evaluation 10 02-Nov-13 12-Nov-13 51
442 Vendor Data and complete commercial 10 12-Nov-13 22-Nov-13 51
443 Issue of PO 10 22-Nov-13 02-Dec-13 51
444 Manufacturing of Items 120 02-Dec-13 01-Apr-14 51
445 FAT, Final Inspection & Release 15 01-Apr-14 16-Apr-14 51
446 Material Delivery 20 21-Apr-14 11-May-14 51
Harmal FD-10-Oct13.3.1.2.1.4.4 GaugeHarmal FD-10-Oct13.3.1.2.1.4.4 Gauge 369 14-Apr-13 18-Apr-14 81
889 PR Issue 2 14-Apr-13 16-Apr-13 81
899 Enquiry Floating 14 17-Apr-13 01-May-13 81
909 Receive quotes from Vendors 160 02-May-13 09-Oct-13 81
919 Technical Bid Evaluation 20 11-Oct-13 31-Oct-13 81
929 Vendor Data and complete commercial 20 01-Nov-13 21-Nov-13 81
939 Issue of PO 2 22-Nov-13 24-Nov-13 81
949 Manufacturing of Items 120 04-Dec-13 03-Apr-14 81
959 Material Delivery 10 08-Apr-14 18-Apr-14 81
Harmal FD-10-Oct13.3.1.2.1.4.7 TransmittersHarmal FD-10-Oct13.3.1.2.1.4.7 Transmitters 315 21-May-13 01-Apr-14 98
1129 PR Issue 30 21-May-13 20-Jun-13 98
1139 Enquiry Floating 140 20-Jun-13 07-Nov-13 98
1149 Receive quotes from Vendors 140 30-Jun-13 17-Nov-13 98
1159 Technical Bid Evaluation 140 10-Jul-13 27-Nov-13 98
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
1169 Vendor Data and complete commercial 140 20-Jul-13 07-Dec-13 98
1179 Issue of PO 6 09-Aug-13 08-Oct-13 98
1189 Manufacturing of Items 150 08-Oct-13 07-Mar-14 98
1199 Material Delivery 20 12-Mar-14 01-Apr-14 98
Harmal FD-10-Oct13.3.1.2.1.4.10 F&G SystemsHarmal FD-10-Oct13.3.1.2.1.4.10 F&G Systems 321 05-May-13 22-Mar-14 108
1289 PR Issue 2 05-May-13 07-May-13 108
1299 Enquiry Floating 7 07-May-13 14-May-13 108
1309 Receive quotes from Vendors 150 22-May-13 19-Oct-13 108
1319 Technical Bid Evaluation 146 06-Jun-13 30-Oct-13 108
1329 Vendor Data and complete commercial 25 10-Oct-13 04-Nov-13 108
1339 Issue of PO 3 04-Nov-13 07-Nov-13 108
1349 Manufacturing of Items 110 07-Nov-13 25-Feb-14 108
1359 Material Delivery 20 02-Mar-14 22-Mar-14 108
Harmal FD-10-Oct13.3.1.2.1.4.13 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.4.13 Bulk Materials 360 20-May-13 15-May-14 66
1619 PR Issue 2 28-May-13 30-May-13 66
1629 Enquiry Floating 140 30-May-13 17-Oct-13 66
1639 Receive quotes from Vendors 160 20-May-13 27-Oct-13 66
1659 Vendor Data and complete commercial 15 22-Oct-13 06-Nov-13 66
1669 Issue of PO 140 16-Nov-13 05-Apr-14 66
1679 Manufacturing of Items 150 26-Nov-13 25-Apr-14 66
1699 Material Delivery 20 25-Apr-14 15-May-14 66
Harmal FD-10-Oct13.3.4 CONSTRUCTION Phase 1Harmal FD-10-Oct13.3.4 CONSTRUCTION Phase 1 605 09-Dec-12 10-Aug-14 45
Harmal FD-10-Oct13.3.4.1.3.1 Bulk Header Line 16" DSS (16 km)Harmal FD-10-Oct13.3.4.1.3.1 Bulk Header Line 16" DSS (16 km) 349 26-Aug-13 10-Aug-14 44
Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.1 Civil WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.1 Civil Works 349 26-Aug-13 10-Aug-14 44
PL C1000 Route Survey and Peg Marking 30 26-Aug-13 25-Sep-13 35
PL C1010 Right of Way Preparation 30 31-Aug-13 30-Sep-13 35
PL C1020 Excavation of Trench 80 24-Nov-13 12-Feb-14 44
PL C1030 Prepadding of sand for Pipeline 70 27-Nov-13 05-Feb-14 44
PL C1040 Post Padding after Laying of Pipeline 45 17-Apr-14 01-Jun-14 44
PL C1050 Back filling of Trench 80 18-Mar-14 06-Jun-14 44
PL C1060 Construction of Windrow 31 08-Jul-14 08-Aug-14 44
PL C1070 Final Grading for the ROW & Marker plate 30 11-Jul-14 10-Aug-14 44
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.2 Mechanical WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.2 Mechanical Works 287 24-Sep-13 08-Jul-14 44
PL M1000 Stringing of Pipes 120 24-Sep-13 22-Jan-14 47
PL M1020 Straight Welding 180 20-Oct-13 18-Apr-14 47
PL M1030 NDT and repair if any 170 04-Nov-13 23-Apr-14 47
PL M1040 Sleeve Installation 150 29-Nov-13 28-Apr-14 47
PL M1050 Lowering of Pipes 150 09-Dec-13 08-May-14 44
PL M1060 Tie-in Welding 150 16-Dec-13 15-May-14 44
PL M1070 Barred Tee Welding 4 26-Apr-14 30-Apr-14 64
PL M1080 IJ Spool Installation 8 27-Apr-14 05-May-14 56
PL M1090 NDT and Repair if any 80 01-Mar-14 20-May-14 44
PL M1100 Sleeve Installation 75 13-Mar-14 27-May-14 44
PL M1110 Line Completion and Clearence 5 03-Jun-14 08-Jun-14 44
PL M1120 Hydrotesting 30 08-Jun-14 08-Jul-14 44
Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.3 FOC WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.3 FOC Works 103 09-Apr-14 21-Jul-14 54
PL FOC1000 HDPE Duct Laying 60 09-Apr-14 08-Jun-14 67
PL FOC1010 Post Padding & Backfilling 50 22-Apr-14 11-Jun-14 80
PL FOC1020 FO Cable Blowing 7 08-Jul-14 15-Jul-14 54
PL FOC1030 FO Jointing & Splicing 5 16-Jul-14 21-Jul-14 54
Harmal FD-10-Oct13.3.4.2 Cathodic Protection WorksHarmal FD-10-Oct13.3.4.2 Cathodic Protection Works 597 09-Dec-12 02-Aug-14 44
Harmal FD-10-Oct13.3.4.2.1 Design WorksHarmal FD-10-Oct13.3.4.2.1 Design Works 45 09-Dec-12 27-Jan-13 192
PL CP1000 Design Preparation, Submission & Approval 45 09-Dec-12 27-Jan-13 192
Harmal FD-10-Oct13.3.4.2.4 ProcurementHarmal FD-10-Oct13.3.4.2.4 Procurement 365 29-Jan-13 29-Jan-14 192
A2280 CP Transformer Manufacturing 250 29-Jan-13 06-Oct-13 192
A2290 FAT & Documentation and Release 100 07-Oct-13 21-Dec-13 192
A2300 CP Transformer Receipt 31 29-Dec-13 29-Jan-14 192
Harmal FD-10-Oct13.3.4.2.2 Temporary CP InstallationHarmal FD-10-Oct13.3.4.2.2 Temporary CP Installation 75 09-Mar-14 23-May-14 58
PL CP1010 Temp.CP Installation for Pipeline 75 09-Mar-14 23-May-14 58
Harmal FD-10-Oct13.3.4.2.3 Permanent CP InstallationHarmal FD-10-Oct13.3.4.2.3 Permanent CP Installation 57 06-Jun-14 02-Aug-14 44
PL CP1020 Ground Bed Installation 15 06-Jun-14 21-Jun-14 44
PL CP1030 Anode JB Installation 3 19-Jun-14 22-Jun-14 46
PL CP1040 NDB Installation 2 22-Jun-14 24-Jun-14 46
PL CP1080 CP Tranformer Installation 1 26-Jun-14 27-Jun-14 44
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
PL CP1100 Trenching, Cable laying, Backfilling 7 26-Jun-14 03-Jul-14 44
PL CP1110 CP Cable Termination 5 03-Jul-14 08-Jul-14 44
PL CP1120 DCVG Survey 10 11-Jun-14 21-Jun-14 60
PL CP1140 Pre-Commissioning activity 10 08-Jul-14 18-Jul-14 44
PL CP1150 Final Commissioning 15 18-Jul-14 02-Aug-14 44
PL CP1160 CP System CIPS Survey 10 18-Jul-14 28-Jul-14 49
Harmal FD-10-Oct13.3.4.1.3.2 Harmal RMS-2 Manifold Construction workHarmal FD-10-Oct13.3.4.1.3.2 Harmal RMS-2 Manifold Construction work 339 05-Sep-13 10-Aug-14 45
Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.1 Civil WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.1 Civil Works 339 05-Sep-13 10-Aug-14 45
RMS C101 Plot Survey and set out 50 05-Sep-13 25-Oct-13 35
RMS C102 Land Filling and Access Road Preparation 45 09-Nov-13 24-Dec-13 35
RMS C103 Precasting for Foundation 45 25-Oct-13 09-Dec-13 50
RMS C104 Fencing and Gate Instalaltion 25 19-Nov-13 14-Dec-13 35
RMS C105 Marking and Excavation of the Foundation 20 24-Nov-13 14-Dec-13 36
RMS C106 PCC for Foundation 20 01-Dec-13 21-Dec-13 36
RMS C107 Foundation Installation 30 08-Dec-13 07-Jan-14 36
RMS C108 Foundation Backfilling & Compacting 35 12-May-14 16-Jun-14 36
RMS C109 Cable Trench Excavation 15 16-Jun-14 01-Jul-14 39
RMS C110 Cable Trench Backfilling 10 12-Jul-14 22-Jul-14 45
RMS C111 Grouting, Final Grading & House Keeping 19 22-Jul-14 10-Aug-14 45
Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.2 Mechanical WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.2 Mechanical Works 211 22-Nov-13 21-Jun-14 67
RMS M101 Prefabrication of Spools 105 22-Nov-13 07-Mar-14 37
RMS M102 NDT and Repair if any 90 22-Dec-13 22-Mar-14 52
RMS M103 Structure Support Fabrication & Coating 105 22-Nov-13 07-Mar-14 37
RMS M104 Suppot Erection 80 07-Jan-14 28-Mar-14 36
RMS M105 Piping Erection, Welding & Tie In 75 14-Jan-14 30-Mar-14 36
RMS M106 NDT and Repair if any 20 20-Mar-14 09-Apr-14 36
RMS M107 Box Up 25 01-Apr-14 26-Apr-14 36
RMS M108 Hydrotesting 35 05-Apr-14 10-May-14 36
RMS M109 Vent Stack Installation 50 02-May-14 21-Jun-14 67
Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.3 Instrument WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.3 Instrument Works 66 11-May-14 16-Jul-14 36
RMS I101 Panel Installation 10 14-Jun-14 24-Jun-14 36
RMS I102 Cable laying 25 17-Jun-14 12-Jul-14 39
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
RMS I103 Field Instrument Installation 15 11-May-14 26-May-14 58
RMS I104 Junction Box & Support Installation 20 13-May-14 02-Jun-14 58
RMS I105 Glanding, Tremination & Tubing 22 24-Jun-14 16-Jul-14 36
RMS I106 Actuated Valve Installation 20 17-May-14 06-Jun-14 62
RMS I107 Name Plate Installation 5 24-May-14 29-May-14 62
Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.4 Electrical WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.4 Electrical Works 92 25-Apr-14 26-Jul-14 39
RMS E101 Transformer installation (3 nos) 15 25-Apr-14 10-May-14 61
RMS E102 Instrument Air Compressor 5 10-May-14 15-May-14 61
RMS E103 Cable Laying 15 17-Jun-14 02-Jul-14 39
RMS E104 Glanding & Termination 7 04-Jul-14 11-Jul-14 39
RMS E105 Fence Earthing 15 25-Apr-14 10-May-14 66
RMS E106 Equipment Earthing 35 25-May-14 29-Jun-14 51
RMS E107 Panel Energization 15 11-Jul-14 26-Jul-14 39
Harmal FD-10-Oct13.3.4.1.3.2.1 Containerized Substation Building- Civil worksHarmal FD-10-Oct13.3.4.1.3.2.1 Containerized Substation Building- Civil wo... 227 17-Nov-13 02-Jul-14 50
SS C1001 Earth Work for Containerized Building Foundation 25 17-Nov-13 12-Dec-13 83
SS C1002 Laying of Polythene sheet 3 13-Dec-13 16-Dec-13 83
SS C1003 PCC for the foundation 2 13-Dec-13 15-Dec-13 83
SS C1004 Reinforce work for Foundation 7 15-Dec-13 22-Dec-13 83
SS C1005 Shuttering for Foundation 4 23-Dec-13 27-Dec-13 83
SS C1006 Concreting work for Foundation 3 28-Dec-13 31-Dec-13 83
SS C1007 Deshuttering for Foundation 4 01-Jan-14 05-Jan-14 83
SS C1008 Reinforcement work for Coloumn 4 07-Jan-14 11-Jan-14 83
SS C1009 Shuttering of column 6 12-Jan-14 18-Jan-14 83
SS C1010 Column Concreting 7 18-Jan-14 25-Jan-14 83
SS C1011 Deshuttering for Column 4 26-Jan-14 30-Jan-14 83
SS C1012 Shuttering work for floor beam 20 31-Jan-14 20-Feb-14 83
SS C1013 Reinforcement work for floor beam 20 05-Feb-14 25-Feb-14 83
SS C1014 Concreting for floor beam 3 26-Feb-14 01-Mar-14 83
SS C1015 Deshuttering of floor beam 7 08-Mar-14 15-Mar-14 83
SS C1016 Applying Protective coating 7 16-Mar-14 23-Mar-14 83
SS C1017 Backfilling the foundation 9 23-Mar-14 01-Apr-14 83
SS C1018 Containerized Substation Installation 8 04-May-14 12-May-14 50
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13.3.4.1.3.2.1.2 Equipment Installation WorksHarmal FD-10-Oct13.3.4.1.3.2.1.2 Equipment Installation Works 52 11-May-14 02-Jul-14 50
SS I1000 Installation of Panels 4 11-May-14 15-May-14 51
SS I1010 Installation of Battery Bank 10 15-May-14 25-May-14 52
SS I1020 Installation of DC-DB 7 25-May-14 01-Jun-14 52
SS I1030 Installation of Lighting DB 7 12-May-14 19-May-14 50
SS I1040 Installation of 415 v Switch Board 15 12-May-14 27-May-14 50
SS I1050 Installation of emergency Lighting DB 7 27-May-14 03-Jun-14 50
SS I1060 Installation of HVAC system 29 03-Jun-14 02-Jul-14 50
Harmal FD-10-Oct13.3.4.1.3.4 OHL Construction (7 Km RMS-1 to RMS-2)Harmal FD-10-Oct13.3.4.1.3.4 OHL Construction (7 Km RMS-1 to RMS-2) 190 25-Oct-13 03-May-14 110
OHL 1000 Survey & ROW grading 50 25-Oct-13 14-Dec-13 110
OHL 1020 Pole hole drilling 50 14-Dec-13 02-Feb-14 110
OHL 1030 Pole distribution 50 22-Dec-13 10-Feb-14 110
OHL 1040 Dressing 35 15-Feb-14 22-Mar-14 110
OHL 1050 Errectioning 25 20-Feb-14 17-Mar-14 110
OHL 1060 Conductor Stringing 20 24-Feb-14 16-Mar-14 110
OHL 1070 Jumpering 15 16-Mar-14 31-Mar-14 110
OHL 1080 Installation of Field Isolator 14 31-Mar-14 14-Apr-14 110
OHL 1090 Installation of Auto recloser 14 02-Apr-14 16-Apr-14 110
OHL 1100 33 KV Spur Lines from OHL to RMS 14 17-Apr-14 01-May-14 110
OHL 1110 33 KV Underground cabling and Termination 10 23-Apr-14 03-May-14 110
Harmal FD-10-Oct13.3.4.6 Shut Down ActivitiesHarmal FD-10-Oct13.3.4.6 Shut Down Activities 183 25-Sep-13 27-Mar-14 153
Harmal FD-10-Oct13.3.4.6.1.3.3.1 Civil WorksHarmal FD-10-Oct13.3.4.6.1.3.3.1 Civil Works 183 25-Sep-13 27-Mar-14 152
SD C10 Plot Survey and set out 15 25-Sep-13 10-Oct-13 270
SD C20 Precasting for Foundation 15 25-Sep-13 10-Oct-13 287
SD C30 Marking and Excavation of the Foundation 20 11-Oct-13 31-Oct-13 270
SD C40 PCC for Foundation 15 20-Oct-13 04-Nov-13 270
SD C50 Foundation Installation 10 27-Oct-13 06-Nov-13 270
SD C60 Foundation Backfilling & Compacting 15 09-Nov-13 24-Nov-13 270
SD C70 Cable Trench Excavation 20 22-Jan-14 11-Feb-14 156
SD C80 Cable Trench Backfilling 10 08-Mar-14 18-Mar-14 156
SD C90 Grouting, Final Grading & House Keeping 5 22-Mar-14 27-Mar-14 152
Harmal FD-10-Oct13.3.4.6.1.3.3.2 Mechanical WorksHarmal FD-10-Oct13.3.4.6.1.3.3.2 Mechanical Works 99 28-Nov-13 07-Mar-14 152
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
SD M10 Prefabrication of Spools 55 28-Nov-13 22-Jan-14 152
SD M20 NDT and Repair if any 10 17-Jan-14 27-Jan-14 159
SD M30 Structure Support Fabrication & Coating 30 08-Dec-13 07-Jan-14 152
SD M40 Suppot Erection 30 12-Jan-14 11-Feb-14 152
SD M50 Piping Erection, Welding 15 03-Feb-14 18-Feb-14 152
SD M60 NDT and Repair if any 20 05-Feb-14 25-Feb-14 152
SD M70 Hydrotesting 10 25-Feb-14 07-Mar-14 152
Harmal FD-10-Oct13.3.4.6.1.3.3.4 Electrical WorksHarmal FD-10-Oct13.3.4.6.1.3.3.4 Electrical Works 25 11-Feb-14 08-Mar-14 156
SD E10 Cable Laying 15 11-Feb-14 26-Feb-14 156
SD E20 Glanding & Termination 10 26-Feb-14 08-Mar-14 156
Harmal FD-10-Oct13.3.4.6.1.3.3.3 Instrument WorksHarmal FD-10-Oct13.3.4.6.1.3.3.3 Instrument Works 41 14-Feb-14 27-Mar-14 153
SD I10 Cable laying 15 14-Feb-14 01-Mar-14 163
SD I20 Field Instrument Installation 10 25-Feb-14 07-Mar-14 152
SD I30 Junction Box & Support Installation 10 27-Feb-14 09-Mar-14 152
SD I40 Glanding, Tremination & Tubing 15 12-Mar-14 27-Mar-14 152
SD I50 ESD Valve Installation 7 01-Mar-14 08-Mar-14 171
SD I60 Name Plate Installation 5 04-Mar-14 09-Mar-14 171
Harmal FD-10-Oct13.3.4.1.3.3 TIE-IN Works at KautherHarmal FD-10-Oct13.3.4.1.3.3 TIE-IN Works at Kauther 11 17-Mar-14 28-Mar-14 171
Harmal FD-10-Oct13.3.4.1.3.3.1 Shut Down Tie-In Date confirmation by PDOHarmal FD-10-Oct13.3.4.1.3.3.1 Shut Down Tie-In Date confirmation by PDO 11 17-Mar-14 28-Mar-14 171
SD 1000 Final Shut Down Date from PDO 11 17-Mar-14 28-Mar-14 171
Harmal FD-10-Oct13.3.1 Pre-Commisioning Activities Phase 1Harmal FD-10-Oct13.3.1 Pre-Commisioning Activities Phase 1 124 18-Apr-14 20-Aug-14 36
A3170 Punch List Clearance 30 21-Jul-14 20-Aug-14 36
A3180 CP-Testing and Commmision 7 26-Jul-14 02-Aug-14 44
A3190 HVAC system 15 02-Jul-14 17-Jul-14 50
A3200 FOC ODTR Testing 2 21-Jul-14 23-Jul-14 54
A3210 RMS-2 Loop checking works 25 16-Jul-14 10-Aug-14 36
A3220 RMS-2 Electrical Testing 12 26-Jul-14 07-Aug-14 39
A3230 RMS-2 Panel Enegization 10 22-Jul-14 01-Aug-14 45
A3240 Transformer Energization 10 11-Jul-14 21-Jul-14 46
A3250 OHL Relay Setting and Testing 20 18-Apr-14 08-May-14 110
A3260 Pre-Commisioning Completion 10 10-Aug-14 20-Aug-14 36
Harmal FD-10-Oct13.1 Harmal Field Development - Phase-2Harmal FD-10-Oct13.1 Harmal Field Development - Phase-2 686 09-Dec-12 30-Oct-14 90
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
Harmal FD-10-Oct13.1.1.1 ENGINEERING Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.1.1 ENGINEERING Phase 2- Well Test Installation 682 09-Dec-12 26-Oct-14 23
Harmal FD-10-Oct13.1.1.1.1.1.2 AFC PackageHarmal FD-10-Oct13.1.1.1.1.1.2 AFC Package 210 09-Dec-12 29-Oct-13 55
D0010 Process 320 09-Dec-12 29-Oct-13 0
D0020 Civil 287 14-Jan-13 28-Oct-13 56
D0030 Mechanical and Piping 310 22-Dec-12 29-Oct-13 0
D0040 Electrical 297 31-Dec-12 24-Oct-13 0
D0050 Control and automation 300 29-Dec-12 25-Oct-13 0
Harmal FD-10-Oct13.1.1.1.1 Bulk MTOHarmal FD-10-Oct13.1.1.1.1 Bulk MTO 254 18-Jan-13 29-Sep-13 85
A3620 Civil & Structural 205 19-Feb-13 12-Sep-13 45
A3630 Electrical 235 20-Jan-13 12-Sep-13 45
A3640 Mechanical and Piping 249 23-Jan-13 29-Sep-13 85
A3650 Control and Automation 240 18-Jan-13 15-Sep-13 44
Harmal FD-10-Oct13.1.1.1.2 Project Management and Supporting DocumentsHarmal FD-10-Oct13.1.1.1.2 Project Management and Supporting Documents 642 22-Jan-13 26-Oct-14 23
A3660 Project Management 580 22-Jan-13 25-Aug-14 85
A3670 As Built Packages 35 21-Sep-14 26-Oct-14 4
A3790 SAP 45 22-Aug-14 06-Oct-14 0
A3800 CCMS 45 22-Aug-14 06-Oct-14 0
Harmal FD-10-Oct13.1.1.21 PROCUREMENT Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.1.21 PROCUREMENT Phase 2- Well Test Installation 533 03-Mar-13 18-Aug-14 31
Harmal FD-10-Oct13.1.1.21.5 Test Seperator Installation MaterialsHarmal FD-10-Oct13.1.1.21.5 Test Seperator Installation Materials 533 03-Mar-13 18-Aug-14 31
Harmal FD-10-Oct13.1.1.21.5.1.2.4 ESD ValveHarmal FD-10-Oct13.1.1.21.5.1.2.4 ESD Valve 494 24-Mar-13 31-Jul-14 49
1939 PR Issue 2 24-Mar-13 26-Mar-13 31
1949 Enquiry Floating 14 27-Mar-13 10-Apr-13 49
1959 Receive quotes from Vendors 180 10-Apr-13 07-Oct-13 49
1969 Technical Bid Evaluation 30 07-Oct-13 06-Nov-13 49
1979 Vendor Data and complete commercial 15 06-Nov-13 21-Nov-13 49
1989 Issue of PO 5 21-Nov-13 26-Nov-13 49
1999 Manufacturing of Items 200 27-Nov-13 15-Jun-14 49
2009 Shipping Delivery 30 16-Jun-14 16-Jul-14 49
3189 ESD Valve Receipt at site 10 21-Jul-14 31-Jul-14 49
Harmal FD-10-Oct13.1.1.21.5.1.2.5 Relief ValveHarmal FD-10-Oct13.1.1.21.5.1.2.5 Relief Valve 493 27-Mar-13 02-Aug-14 23
2019 PR Issue 2 27-Mar-13 29-Mar-13 23
2029 Enquiry Floating 14 29-Mar-13 12-Apr-13 23
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
2039 Receive quotes from Vendors 200 13-Apr-13 19-Oct-13 23
2049 Technical Bid Evaluation 16 20-Oct-13 04-Nov-13 23
2059 Vendor Data and complete commercial 16 05-Nov-13 20-Nov-13 23
2069 Issue of PO 7 21-Nov-13 28-Nov-13 23
2079 Manufacturing of Items 200 28-Nov-13 16-Jun-14 23
2089 Shipping Delivery 30 16-Jun-14 16-Jul-14 23
3199 Relief Valve Receipt at Site 10 23-Jul-14 02-Aug-14 23
Harmal FD-10-Oct13.1.1.21.5.1.2.9 Control ValvesHarmal FD-10-Oct13.1.1.21.5.1.2.9 Control Valves 465 16-Mar-13 24-Jun-14 62
2339 PR Issue 2 16-Mar-13 18-Mar-13 62
2349 Enquiry Floating 14 18-Mar-13 01-Apr-13 62
2359 Receive quotes from Vendors 190 01-Apr-13 08-Oct-13 62
2369 Technical Bid Evaluation 16 08-Oct-13 24-Oct-13 62
2379 Vendor Data and complete commercial 12 17-Oct-13 29-Oct-13 62
2389 Issue of PO 7 29-Oct-13 05-Nov-13 62
2399 Manufacturing of Items 184 05-Nov-13 08-May-14 62
2409 Shipping Delivery 30 08-May-14 07-Jun-14 62
3209 Control Valve Receipt at Site 10 14-Jun-14 24-Jun-14 62
Harmal FD-10-Oct13.1.1.21.5.1 Test SeparatorHarmal FD-10-Oct13.1.1.21.5.1 Test Separator 517 03-Mar-13 02-Aug-14 0
A2490 PR Issue 2 03-Mar-13 05-Mar-13 0
A2500 Enquiry Floating 14 05-Mar-13 19-Mar-13 0
A2510 Receive Quotes from Vendor 21 19-Mar-13 09-Apr-13 0
A2520 TBE & Vendor Finilize 195 09-Apr-13 21-Oct-13 0
A2530 Issue of PO 4 21-Oct-13 25-Oct-13 0
A2540 Manufacturing of Items 236 29-Oct-13 22-Jun-14 0
A2550 Inspection & Release 20 22-Jun-14 12-Jul-14 0
A2560 Material Delivery 12 13-Jul-14 25-Jul-14 0
A2820 Test Separator Receipt at Site 7 26-Jul-14 02-Aug-14 0
Harmal FD-10-Oct13.1.1.21.5.2 Piping Materials & FittingsHarmal FD-10-Oct13.1.1.21.5.2 Piping Materials & Fittings 403 26-Mar-13 03-May-14 73
A2850 PR Issue 2 26-Mar-13 28-Mar-13 73
A2860 Enquiry Floating 48 28-Mar-13 15-May-13 73
A2870 Receive Quotes from Vendor 140 15-May-13 02-Oct-13 73
A2880 TBE & Vendor Finilize 88 30-Jul-13 26-Oct-13 73
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
A2890 Issue of PO 28 26-Oct-13 23-Nov-13 73
A2900 Manufacturing of Items 136 23-Nov-13 08-Apr-14 73
A2910 Inspection & Release 112 23-Dec-13 14-Apr-14 73
A2920 Material Delivery 112 28-Dec-13 19-Apr-14 73
A2930 Material Receipt at Site 112 11-Jan-14 03-May-14 73
Harmal FD-10-Oct13.1.1.21.5.3 Bulk MaterialsHarmal FD-10-Oct13.1.1.21.5.3 Bulk Materials 413 26-Mar-13 13-May-14 56
A2940 PR Issue 2 26-Mar-13 28-Mar-13 56
A2950 Enquiry Floating 7 29-Mar-13 05-Apr-13 56
A2960 Receive Quotes from Vendor 128 06-Apr-13 12-Aug-13 56
A2970 Vendor Finilize 128 30-Apr-13 05-Sep-13 56
A2980 Issue of PO 48 05-Sep-13 23-Oct-13 56
A2990 Manufacturing of Items 200 12-Sep-13 31-Mar-14 56
A3000 Inspection & Release 200 10-Oct-13 28-Apr-14 56
A3010 Material Receipt at Site 150 14-Dec-13 13-May-14 56
Harmal FD-10-Oct13.1.1.21.5.4 Instrument Air CompressorHarmal FD-10-Oct13.1.1.21.5.4 Instrument Air Compressor 429 28-Mar-13 31-May-14 85
A3020 PR Issue 6 28-Mar-13 03-Apr-13 85
A3030 Enquiry Floating 152 03-Apr-13 02-Sep-13 85
A3040 Receive quotes from Vendors 144 23-Apr-13 14-Sep-13 85
A3050 TBE & Vendor Finilize 136 13-May-13 26-Sep-13 85
A3060 Issue of PO 7 26-Sep-13 03-Oct-13 85
A3070 Manufacturing of Items 160 03-Oct-13 12-Mar-14 85
A3080 Inspection & Release 20 12-Mar-14 01-Apr-14 85
A3090 Material Delivery 20 01-Apr-14 21-Apr-14 85
A3100 Air Compressor Receipt at Site 30 01-May-14 31-May-14 85
Harmal FD-10-Oct13.1.1.21.5.5 Flow MeterHarmal FD-10-Oct13.1.1.21.5.5 Flow Meter 445 24-Mar-13 12-Jun-14 98
A3680 PR Issue 6 24-Mar-13 30-Mar-13 31
A3690 Enquiry Floating 152 30-Mar-13 29-Aug-13 31
A3700 Receive quotes from Vendors 136 23-Apr-13 06-Sep-13 31
A3710 TBE & Vendor Finilize 12 06-Sep-13 18-Sep-13 31
A3720 Issue of PO 7 18-Sep-13 25-Sep-13 31
A3730 Manufacturing of Items 180 25-Sep-13 24-Mar-14 98
A3740 Inspection & Release 20 24-Mar-14 13-Apr-14 98
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
A3750 Material Delivery 20 13-Apr-14 03-May-14 98
A3760 Material Receipt at Site 30 13-May-14 12-Jun-14 98
Harmal FD-10-Oct13.1.1.21.5.6 F & G SystemHarmal FD-10-Oct13.1.1.21.5.6 F & G System 334 18-Sep-13 18-Aug-14 31
A3810 PR Issue 25 18-Sep-13 13-Oct-13 31
A3820 Enquiry Floating 60 13-Oct-13 12-Dec-13 31
A3830 Receive quotes from Vendors 60 21-Oct-13 20-Dec-13 31
A3840 TBE & Vendor Finilize 12 20-Dec-13 01-Jan-14 31
A3850 Issue of PO 7 01-Jan-14 08-Jan-14 31
A3860 Manufacturing of Items 150 08-Jan-14 07-Jun-14 31
A3870 Inspection & Release 20 07-Jun-14 27-Jun-14 31
A3880 Material Delivery 20 27-Jun-14 17-Jul-14 31
A3890 Material Receipt at Site 22 27-Jul-14 18-Aug-14 31
Harmal FD-10-Oct13.1.2 CONSTRUCTION Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.2 CONSTRUCTION Phase 2- Well Test Installation 197 29-Mar-14 12-Oct-14 107
Harmal FD-10-Oct13.1.2.2 Well Test Seperator InstallationHarmal FD-10-Oct13.1.2.2 Well Test Seperator Installation 197 29-Mar-14 12-Oct-14 107
Harmal FD-10-Oct13.1.2.2.1 Civil WorksHarmal FD-10-Oct13.1.2.2.1 Civil Works 197 29-Mar-14 12-Oct-14 107
WTS C18 Excavation for Foundations 30 29-Apr-14 29-May-14 35
WTS C28 PCC for Foundation 45 01-May-14 15-Jun-14 35
WTS C38 Foundation Installation 45 08-May-14 22-Jun-14 35
WTS C48 Foundation Backfilling & Compaction 30 15-Aug-14 14-Sep-14 136
WTS C58 Excavation for Cable Trench 7 29-May-14 05-Jun-14 96
WTS C68 Cable trench backfilling 7 14-Sep-14 21-Sep-14 2
WTS C78 Grouting, Final Grading and Housekeeping 22 21-Sep-14 12-Oct-14 2
WTS C8 Plot Survey and set out 30 29-Mar-14 28-Apr-14 35
Harmal FD-10-Oct13.1.2.2.2 Mechanical WorksHarmal FD-10-Oct13.1.2.2.2 Mechanical Works 172 11-Apr-14 30-Sep-14 0
WTS M19 Prefabrication of Piping spools 40 11-Apr-14 21-May-14 56
WTS M29 NDT 36 25-Apr-14 31-May-14 56
WTS M39 Spool Hydrotest 32 09-May-14 10-Jun-14 56
WTS M49 Structural support Fabrication & Coating 32 11-Apr-14 13-May-14 82
WTS M59 Structual Support installation 24 22-Jun-14 16-Jul-14 35
WTS M69 Piping Erection 35 05-Aug-14 09-Sep-14 0
WTS M79 Final Hydrotest 7 09-Sep-14 16-Sep-14 0
WTS M89 Valve installation / Nitrogen Purging 14 16-Sep-14 30-Sep-14 0
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 
Activity ID Activity Name Original
Duration
Start Finish Total Float
WTS M9 Test Separator errection and alignment 3 02-Aug-14 05-Aug-14 0
Harmal FD-10-Oct13.1.2.2.3 Electrical WorksHarmal FD-10-Oct13.1.2.2.3 Electrical Works 27 09-Sep-14 06-Oct-14 0
WTS E13 Cable Glanding & Termination 12 15-Sep-14 27-Sep-14 0
WTS E23 Earthing works for Equipment & Instruments 9 27-Sep-14 06-Oct-14 0
WTS E3 Cable laying 5 09-Sep-14 14-Sep-14 0
Harmal FD-10-Oct13.1.2.2.4 Instrumentation worksHarmal FD-10-Oct13.1.2.2.4 Instrumentation works 65 02-Aug-14 06-Oct-14 0
WTS I14 ESD Valve /Flow meter /F & G system Installation 12 18-Sep-14 30-Sep-14 0
WTS I24 Instrument cable laying & Termination 12 21-Sep-14 03-Oct-14 0
WTS I34 Instrument Tubing works 19 17-Sep-14 06-Oct-14 0
WTS I4 Instruments Calibration 24 02-Aug-14 26-Aug-14 23
Harmal FD-10-Oct13.1.7 Pre-Commissioning Activities Phase 2Harmal FD-10-Oct13.1.7 Pre-Commissioning Activities Phase 2 175 08-May-14 30-Oct-14 0
Pre 072 Substation Readiness 15 08-May-14 23-May-14 115
Pre 092 WTS Precommissioning activities 24 06-Oct-14 30-Oct-14 0
Pre 102 Ex- Inspection works 10 10-Oct-14 20-Oct-14 0
Pre 112 Pie - Configuration by PDO 14 06-Oct-14 20-Oct-14 0
Pre 122 Loop Checking 10 20-Oct-14 30-Oct-14 0
Harmal FD-10-Oct13.Comm Support Commissioning SupportHarmal FD-10-Oct13.Comm Support Commissioning Support 161 20-Aug-14 28-Jan-15 0
A3770 Commissioning Support Assistance for Testing Facilities 90 30-Oct-14 28-Jan-15 0
A3780 Commisioning Support Assistance for Production Facilities 90 20-Aug-14 18-Nov-14 36
D J F M A M J J A S O N D J F A J J A S N D J
2013 2014 2015
Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32
Primary Baseline
Actual Work
Remaining Work
Critical Remaining Work
Baseline Milestone
Milestone
 

More Related Content

What's hot (9)

Standard detailed drawings
Standard detailed drawingsStandard detailed drawings
Standard detailed drawings
 
Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011Monthly Progress Report No.13 - September 2011
Monthly Progress Report No.13 - September 2011
 
Update Data of APR2014 in SPICEPARK
Update Data of APR2014 in SPICEPARK Update Data of APR2014 in SPICEPARK
Update Data of APR2014 in SPICEPARK
 
Cetpro san pedro
Cetpro san pedroCetpro san pedro
Cetpro san pedro
 
Slide3 phasing ofp_rdelgrpswork
Slide3 phasing ofp_rdelgrpsworkSlide3 phasing ofp_rdelgrpswork
Slide3 phasing ofp_rdelgrpswork
 
Rice Co-Op Presentation
Rice Co-Op PresentationRice Co-Op Presentation
Rice Co-Op Presentation
 
Equivalent grades of steel
Equivalent grades of steelEquivalent grades of steel
Equivalent grades of steel
 
1) Photo report Hook up Pipe spool#6
1) Photo report Hook up Pipe spool#61) Photo report Hook up Pipe spool#6
1) Photo report Hook up Pipe spool#6
 
PIPING DESIGNER
PIPING DESIGNERPIPING DESIGNER
PIPING DESIGNER
 

Similar to Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2

HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
Roumik Mukherjee
 
020-IRC-CS Pipes-the Bengal mill
020-IRC-CS Pipes-the Bengal mill020-IRC-CS Pipes-the Bengal mill
020-IRC-CS Pipes-the Bengal mill
Ramesh Menariai
 
26071 v46 a-d-160-01-00012-051_detail drawing of ladder & platform for ca...
26071 v46 a-d-160-01-00012-051_detail drawing of ladder & platform for ca...26071 v46 a-d-160-01-00012-051_detail drawing of ladder & platform for ca...
26071 v46 a-d-160-01-00012-051_detail drawing of ladder & platform for ca...
musslih yulianto
 

Similar to Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2 (20)

HSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activityHSM 2nd July Schedule -All activity
HSM 2nd July Schedule -All activity
 
10. Overall Implementation Programme
10. Overall Implementation Programme10. Overall Implementation Programme
10. Overall Implementation Programme
 
Update Data of SEP2014 in SPICEPARK
Update Data of SEP2014 in SPICEPARKUpdate Data of SEP2014 in SPICEPARK
Update Data of SEP2014 in SPICEPARK
 
2014年11月度のアップデート(スパイス・パーク)
2014年11月度のアップデート(スパイス・パーク)2014年11月度のアップデート(スパイス・パーク)
2014年11月度のアップデート(スパイス・パーク)
 
Update Data MAY2015 (22 Models) in SPICE PARK
Update Data MAY2015 (22 Models) in SPICE PARKUpdate Data MAY2015 (22 Models) in SPICE PARK
Update Data MAY2015 (22 Models) in SPICE PARK
 
Spice park May2015 22pcs (update)
Spice park May2015 22pcs (update)Spice park May2015 22pcs (update)
Spice park May2015 22pcs (update)
 
Update Data of AUG2014 in SPICEPARK
Update Data of AUG2014 in SPICEPARKUpdate Data of AUG2014 in SPICEPARK
Update Data of AUG2014 in SPICEPARK
 
Weekly report no 19
Weekly report no 19Weekly report no 19
Weekly report no 19
 
Term schedule for 201308.htm the data you see here may
Term schedule for 201308.htm the data you see here may Term schedule for 201308.htm the data you see here may
Term schedule for 201308.htm the data you see here may
 
Machinery schedule
Machinery scheduleMachinery schedule
Machinery schedule
 
Machinery schedule
Machinery scheduleMachinery schedule
Machinery schedule
 
020-IRC-CS Pipes-the Bengal mill
020-IRC-CS Pipes-the Bengal mill020-IRC-CS Pipes-the Bengal mill
020-IRC-CS Pipes-the Bengal mill
 
26071 v46 a-d-160-01-00012-051_detail drawing of ladder & platform for ca...
26071 v46 a-d-160-01-00012-051_detail drawing of ladder & platform for ca...26071 v46 a-d-160-01-00012-051_detail drawing of ladder & platform for ca...
26071 v46 a-d-160-01-00012-051_detail drawing of ladder & platform for ca...
 
Lista solin pintado todo
Lista solin pintado todoLista solin pintado todo
Lista solin pintado todo
 
SeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule finalSeconTowers MEP Time Schedule final
SeconTowers MEP Time Schedule final
 
ARB JANADREA 25.01.16 UPDATE PM
ARB JANADREA 25.01.16 UPDATE  PMARB JANADREA 25.01.16 UPDATE  PM
ARB JANADREA 25.01.16 UPDATE PM
 
Project Schedule - Level IV Schedule
Project Schedule - Level IV ScheduleProject Schedule - Level IV Schedule
Project Schedule - Level IV Schedule
 
IC3D example dwgs
IC3D example dwgsIC3D example dwgs
IC3D example dwgs
 
ERUP WBS
ERUP WBSERUP WBS
ERUP WBS
 
ADWEA_APPROVED_VENDORS_LIST.pdf
ADWEA_APPROVED_VENDORS_LIST.pdfADWEA_APPROVED_VENDORS_LIST.pdf
ADWEA_APPROVED_VENDORS_LIST.pdf
 

Harmal Field Development Phase 1 and Phase 2 Final-10.10.2013-R2

  • 1. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13 Harmal RMS-2 Construction & 16" DSS Pipeline to KGP Phase 1 & Phase 2 - FinalHarmal FD-10-Oct13 Harmal RMS-2 Construction & 16" D... 776 09-Dec-12 28-Jan-15 0 Harmal FD-10-Oct13.3 Harmal Field Development - Phase-1Harmal FD-10-Oct13.3 Harmal Field Development - Phase-1 625 09-Dec-12 30-Aug-14 36 Harmal FD-10-Oct13.3.1.11 ENGINEERING Phase 1Harmal FD-10-Oct13.3.1.11 ENGINEERING Phase 1 625 09-Dec-12 30-Aug-14 36 Harmal FD-10-Oct13.3.1.11.1.1.2 AFC PackageHarmal FD-10-Oct13.3.1.11.1.1.2 AFC Package 286 09-Dec-12 25-Sep-13 140 D100 Electrical 200 05-Jan-13 10-Sep-13 28 D100A Electrical-OHL 238 05-Jan-13 31-Aug-13 165 D110 Control and automation 215 01-Jan-13 25-Sep-13 28 D120 Pipeline 237 06-Jan-13 31-Aug-13 71 D70 Civil 145 27-Jan-13 27-Jul-13 53 D80 Mechanical and Piping 142 24-Dec-12 18-Jun-13 28 D90 Process 225 09-Dec-12 14-Sep-13 0 Harmal FD-10-Oct13.3.1.11.1 Bulk MTOHarmal FD-10-Oct13.3.1.11.1 Bulk MTO 172 30-Jan-13 21-Jul-13 50 A3110 Mechanical and Piping 170 30-Jan-13 19-Jul-13 37 A3120 Civil and Structural 165 01-Feb-13 16-Jul-13 50 A3130 Electrical 165 06-Feb-13 21-Jul-13 50 A3140 Control and Automation 162 06-Feb-13 18-Jul-13 50 Harmal FD-10-Oct13.3.1.11.2 Project Management and Support DocumentsHarmal FD-10-Oct13.3.1.11.2 Project Management and Support Documents 625 09-Dec-12 30-Aug-14 36 A3150 Project Management 600 09-Dec-12 05-Aug-14 41 A3160 Project Support & As Built Completion 339 25-Sep-13 30-Aug-14 36 A3270 SAP Management 319 25-Sep-13 10-Aug-14 36 A3280 CCMS 319 25-Sep-13 10-Aug-14 36 Harmal FD-10-Oct13.3.1.2 PROCUREMENT Phase 1Harmal FD-10-Oct13.3.1.2 PROCUREMENT Phase 1 487 13-Jan-13 15-May-14 66 Harmal FD-10-Oct13.3.1.2.1 16" DSS Pipeline & RMS-2 ConstructionHarmal FD-10-Oct13.3.1.2.1 16" DSS Pipeline & RMS-2 Construction 487 13-Jan-13 15-May-14 66 Harmal FD-10-Oct13.3.1.2.1.2 MechanicalHarmal FD-10-Oct13.3.1.2.1.2 Mechanical 474 13-Jan-13 02-May-14 67 Harmal FD-10-Oct13.3.1.2.1.2.1.2.1 Delivery of 16" DSS PipesHarmal FD-10-Oct13.3.1.2.1.2.1.2.1 Delivery of 16" DSS Pipes 367 13-Jan-13 15-Jan-14 47 357 PR Issue 1 13-Jan-13 14-Jan-13 47 358 Enquiry Floating 7 14-Jan-13 21-Jan-13 47 359 Receive quotes from Vendors 7 22-Jan-13 29-Jan-13 47 360 Technical Bid Evaluation 14 30-Jan-13 13-Feb-13 47 361 Vendor Data and complete commercial 10 14-Feb-13 24-Feb-13 47 362 Issue of PO 2 25-Feb-13 27-Feb-13 47 363 Manufacturing of Pipes & Coating 286 28-Feb-13 11-Dec-13 47 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 2. Activity ID Activity Name Original Duration Start Finish Total Float 364 Inspection, Rlease & Shipment 150 29-Jul-13 26-Dec-13 47 365 Pipe Receipt at Site 125 12-Sep-13 15-Jan-14 47 Harmal FD-10-Oct13.3.1.2.1.2.1.2.3 FlangesHarmal FD-10-Oct13.3.1.2.1.2.1.2.3 Flanges 283 30-Mar-13 07-Jan-14 67 375 PR Issue 2 30-Mar-13 01-Apr-13 67 376 Enquiry Floating 7 02-Apr-13 09-Apr-13 67 377 Receive quotes from Vendors 21 09-Apr-13 30-Apr-13 67 378 Technical Bid Evaluation 15 30-Apr-13 15-May-13 67 379 Vendor Data and complete commercial 5 15-May-13 20-May-13 67 380 Issue of PO 7 21-May-13 28-May-13 67 381 Manufacturing process at Vendor Yard 145 28-May-13 20-Oct-13 67 382 Shipping Delivery 34 20-Oct-13 23-Nov-13 67 383 Flange Receipt at site 45 23-Nov-13 07-Jan-14 67 Harmal FD-10-Oct13.3.1.2.1.2.1.2.6 IJ SpoolsHarmal FD-10-Oct13.3.1.2.1.2.1.2.6 IJ Spools 322 31-Mar-13 16-Feb-14 76 402 PR Issue 2 31-Mar-13 02-Apr-13 76 403 Enquiry Floating 11 03-Apr-13 14-Apr-13 76 404 Receive quotes from Vendors 14 15-Apr-13 29-Apr-13 76 405 Technical Bid Evaluation 30 30-Apr-13 30-May-13 76 406 Vendor Data and complete commercial 10 31-May-13 10-Jun-13 76 407 Issue of PO 6 11-Jun-13 17-Jun-13 76 408 Manufacturing of Items 185 18-Jun-13 20-Dec-13 76 409 Shipping Delivery 40 21-Dec-13 30-Jan-14 76 410 IJ Spool Receipt at Site 10 06-Feb-14 16-Feb-14 76 Harmal FD-10-Oct13.3.1.2.1.2.1.2.7 Barred TeeHarmal FD-10-Oct13.3.1.2.1.2.1.2.7 Barred Tee 316 01-Apr-13 11-Feb-14 138 411 PR Issue 2 01-Apr-13 03-Apr-13 138 412 Enquiry Floating 7 03-Apr-13 10-Apr-13 138 413 Receive quotes from Vendors 14 10-Apr-13 24-Apr-13 138 414 Technical Bid Evaluation 30 24-Apr-13 24-May-13 138 415 Vendor Data and complete commercial 14 24-May-13 07-Jun-13 138 416 Issue of PO 2 07-Jun-13 09-Jun-13 138 417 Manufacturing of Items 190 09-Jun-13 16-Dec-13 138 418 Shipping Delivery 20 16-Dec-13 05-Jan-14 138 419 Barred TEE Receipt at Site 30 12-Jan-14 11-Feb-14 138 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 3. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13.3.1.2.1.2.1.2.8 Shrink sleeveHarmal FD-10-Oct13.3.1.2.1.2.1.2.8 Shrink sleeve 210 15-Apr-13 11-Nov-13 85 420 PR Issue 2 15-Apr-13 17-Apr-13 85 421 Enquiry Floating 11 17-Apr-13 28-Apr-13 85 422 Receive quotes from Vendors 14 28-Apr-13 12-May-13 85 423 TBE & Vendor Finilize 30 12-May-13 11-Jun-13 85 424 Issue of PO 2 11-Jun-13 13-Jun-13 85 425 Manufacturing of Items 100 13-Jun-13 21-Sep-13 85 426 Inspection & Release 4 21-Sep-13 25-Sep-13 85 427 Material Delivery 20 25-Sep-13 15-Oct-13 85 428 Shrink Sleeve Receipt at Site 20 22-Oct-13 11-Nov-13 85 Harmal FD-10-Oct13.3.1.2.1.2.2 Vent StackHarmal FD-10-Oct13.3.1.2.1.2.2 Vent Stack 383 14-Apr-13 02-May-14 67 A1360 PR Issue 6 14-Apr-13 20-Apr-13 67 A1370 Enquiry Floating 14 20-Apr-13 04-May-13 67 A1380 Receive quotes from Vendors 145 04-May-13 26-Sep-13 67 A1390 TBE & Vendor Finilize 140 19-May-13 06-Oct-13 67 A1400 Issue of PO 2 06-Oct-13 08-Oct-13 67 A1410 Manufacturing of Items 120 08-Oct-13 05-Feb-14 67 A1420 FAT, Final Inspection & Release 30 05-Feb-14 07-Mar-14 67 A1430 Material Delivery 20 07-Mar-14 27-Mar-14 67 A1431 Vent Stack Receipt at Site 26 06-Apr-14 02-May-14 67 Harmal FD-10-Oct13.3.1.2.1.2.1 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.2.1 Bulk Materials 298 30-Apr-13 22-Feb-14 37 1529 PR Issue 30 30-Apr-13 30-May-13 37 1539 Enquiry Floating 90 30-May-13 28-Aug-13 37 1549 Receive quotes from Vendors 100 04-Jun-13 12-Sep-13 37 1569 Vendor Data and complete commercial 75 09-Jul-13 22-Sep-13 37 1579 Issue of PO 30 23-Sep-13 23-Oct-13 37 1589 Manufacturing of Materials 110 13-Oct-13 31-Jan-14 37 1599 Shipping Delivery 110 02-Nov-13 20-Feb-14 37 1609 Fittings Receipt at site( 106 08-Nov-13 22-Feb-14 37 Harmal FD-10-Oct13.3.1.2.1.2.4 Internal ClampsHarmal FD-10-Oct13.3.1.2.1.2.4 Internal Clamps 151 27-Apr-13 25-Sep-13 79 A2330 PR Issue 6 27-Apr-13 03-May-13 79 A2340 Enquiry Floating 14 03-May-13 17-May-13 79 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 4. Activity ID Activity Name Original Duration Start Finish Total Float A2350 Recieve quotes from Vendors 21 17-May-13 07-Jun-13 79 A2360 Vendor Data and complete commercial 7 07-Jun-13 14-Jun-13 79 A2370 Issue of PO 2 15-Jun-13 17-Jun-13 79 A2380 Maufacturing of mateirals 70 18-Jun-13 27-Aug-13 79 A2390 Shipping Delivery 10 28-Aug-13 17-Sep-13 79 A2400 Reciept at site 7 18-Sep-13 25-Sep-13 79 Harmal FD-10-Oct13.3.1.2.1.3 ElectricalHarmal FD-10-Oct13.3.1.2.1.3 Electrical 361 08-May-13 04-May-14 63 Harmal FD-10-Oct13.3.1.2.1.3.1 415 V LVSBHarmal FD-10-Oct13.3.1.2.1.3.1 415 V LVSB 224 26-Jun-13 05-Feb-14 136 A1200 PR Issue 2 26-Jun-13 28-Jun-13 136 A1210 Enquiry Floating 14 28-Jun-13 12-Jul-13 136 A1220 Receive quotes from Vendor 7 12-Jul-13 19-Jul-13 136 A1230 TBE & Vendor Finilze 62 19-Jul-13 19-Sep-13 136 A1240 Issue of PO 2 19-Sep-13 21-Sep-13 136 A1250 Manufacturing of Material 90 21-Sep-13 20-Dec-13 136 A1260 Inspection & Release 20 20-Dec-13 09-Jan-14 136 A1270 Material Delivery 20 16-Jan-14 05-Feb-14 136 Harmal FD-10-Oct13.3.1.2.1.3.1.2.11 Electrical TransformerHarmal FD-10-Oct13.3.1.2.1.3.1.2.11 Electrical Transformer 345 08-May-13 18-Apr-14 61 448 PR Issue 2 08-May-13 10-May-13 61 449 Enquiry Floating 14 10-May-13 24-May-13 61 450 Receive quotes from Vendors 120 20-May-13 17-Sep-13 61 451 Technical Bid Evaluation & Vendor Finalize 120 30-May-13 27-Sep-13 61 452 Vendor Data and complete commercial 12 27-Sep-13 09-Oct-13 61 453 Issue of PO 9 09-Oct-13 18-Oct-13 61 454 Manufacturing of Items 125 18-Oct-13 20-Feb-14 61 455 FAT, Final Inspection & Release 30 20-Feb-14 22-Mar-14 61 456 Delivery at Site 20 29-Mar-14 18-Apr-14 61 Harmal FD-10-Oct13.3.1.2.1.3.1.2.12 Electrical DBHarmal FD-10-Oct13.3.1.2.1.3.1.2.12 Electrical DB 259 25-Jun-13 11-Mar-14 117 458 PR Issue 6 25-Jun-13 01-Jul-13 117 459 Enquiry Floating 21 01-Jul-13 22-Jul-13 117 460 Receive quotes from Vendors 15 22-Jul-13 06-Aug-13 117 461 Vendor Finilize 55 06-Aug-13 30-Sep-13 117 462 Issue of PO 10 30-Sep-13 10-Oct-13 117 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 5. Activity ID Activity Name Original Duration Start Finish Total Float 463 Manufacturing of Items 100 10-Oct-13 18-Jan-14 117 464 FAT, Final Inspection & Release 15 18-Jan-14 02-Feb-14 117 465 Material Delivery 30 09-Feb-14 11-Mar-14 117 Harmal FD-10-Oct13.3.1.2.1.3.1.2.14 OHL materialsHarmal FD-10-Oct13.3.1.2.1.3.1.2.14 OHL materials 213 25-Jun-13 24-Jan-14 137 477 PR Issue 6 25-Jun-13 01-Jul-13 137 478 Enquiry Floating 6 01-Jul-13 07-Jul-13 137 479 Receive quotes from Vendors 12 07-Jul-13 19-Jul-13 137 480 Vendor Finilize 15 19-Jul-13 03-Aug-13 137 481 Issue of PO 4 03-Aug-13 07-Aug-13 137 482 Manufacturing of Items 140 07-Aug-13 25-Dec-13 137 483 Material Delivery 20 04-Jan-14 24-Jan-14 137 Harmal FD-10-Oct13.3.1.2.1.3.2 Containerized SubstationHarmal FD-10-Oct13.3.1.2.1.3.2 Containerized Substation 313 25-Jun-13 04-May-14 50 A1520 PR Issue 2 25-Jun-13 27-Jun-13 50 A1530 Enquiry Floating 7 27-Jun-13 04-Jul-13 50 A1540 Receive quotes from Vendors 90 04-Jul-13 02-Oct-13 50 A1550 Technical Bid Evaluation 15 02-Oct-13 17-Oct-13 50 A1560 Vendor Data and complete commercial 10 17-Oct-13 27-Oct-13 50 A1570 Issue of PO 6 27-Oct-13 02-Nov-13 50 A1580 Manufacturing of Items 150 02-Nov-13 01-Apr-14 50 A1590 FAT, Final Inspection & Release 15 01-Apr-14 16-Apr-14 50 A1600 Material Delivery 15 19-Apr-14 04-May-14 50 Harmal FD-10-Oct13.3.1.2.1.3.1.2.13 AC UPS & UPS DBHarmal FD-10-Oct13.3.1.2.1.3.1.2.13 AC UPS & UPS DB 296 25-Jun-13 17-Apr-14 75 467 PR Issue 7 25-Jun-13 02-Jul-13 75 468 Enquiry Floating 21 02-Jul-13 23-Jul-13 75 469 Receive quotes from Vendors 60 23-Jul-13 21-Sep-13 75 470 Technical Bid Evaluation 15 21-Sep-13 06-Oct-13 75 471 Vendor Data and complete commercial 15 06-Oct-13 21-Oct-13 75 472 Issue of PO 6 21-Oct-13 27-Oct-13 75 473 Manufacturing of Items 130 27-Oct-13 06-Mar-14 75 474 FAT, Final Inspection & Release 15 06-Mar-14 21-Mar-14 75 475 Material Delivery 20 28-Mar-14 17-Apr-14 75 Harmal FD-10-Oct13.3.1.2.1.3.3 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.3.3 Bulk Materials 193 24-Aug-13 05-Mar-14 112 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 6. Activity ID Activity Name Original Duration Start Finish Total Float 1709 PR Issue 6 24-Aug-13 30-Aug-13 112 1719 Enquiry Floating 6 30-Aug-13 05-Sep-13 112 1729 Receive quotes from Vendors 25 05-Sep-13 30-Sep-13 112 1739 Vendor Finilize 30 30-Sep-13 30-Oct-13 112 1749 Issue of PO 6 30-Oct-13 05-Nov-13 112 1759 Manufacturing of Items 90 05-Nov-13 03-Feb-14 112 1769 Material Delivery 20 13-Feb-14 05-Mar-14 112 Harmal FD-10-Oct13.3.1.2.1.4 InstrumentationHarmal FD-10-Oct13.3.1.2.1.4 Instrumentation 396 14-Apr-13 15-May-14 66 Harmal FD-10-Oct13.3.1.2.1.4.1.2.10 FCS systemHarmal FD-10-Oct13.3.1.2.1.4.1.2.10 FCS system 329 16-Jun-13 11-May-14 51 438 PR Issue 2 16-Jun-13 18-Jun-13 51 439 Enquiry Floating 7 18-Jun-13 25-Jun-13 51 440 Receive quotes from Vendors 130 25-Jun-13 02-Nov-13 51 441 Technical Bid Evaluation 10 02-Nov-13 12-Nov-13 51 442 Vendor Data and complete commercial 10 12-Nov-13 22-Nov-13 51 443 Issue of PO 10 22-Nov-13 02-Dec-13 51 444 Manufacturing of Items 120 02-Dec-13 01-Apr-14 51 445 FAT, Final Inspection & Release 15 01-Apr-14 16-Apr-14 51 446 Material Delivery 20 21-Apr-14 11-May-14 51 Harmal FD-10-Oct13.3.1.2.1.4.4 GaugeHarmal FD-10-Oct13.3.1.2.1.4.4 Gauge 369 14-Apr-13 18-Apr-14 81 889 PR Issue 2 14-Apr-13 16-Apr-13 81 899 Enquiry Floating 14 17-Apr-13 01-May-13 81 909 Receive quotes from Vendors 160 02-May-13 09-Oct-13 81 919 Technical Bid Evaluation 20 11-Oct-13 31-Oct-13 81 929 Vendor Data and complete commercial 20 01-Nov-13 21-Nov-13 81 939 Issue of PO 2 22-Nov-13 24-Nov-13 81 949 Manufacturing of Items 120 04-Dec-13 03-Apr-14 81 959 Material Delivery 10 08-Apr-14 18-Apr-14 81 Harmal FD-10-Oct13.3.1.2.1.4.7 TransmittersHarmal FD-10-Oct13.3.1.2.1.4.7 Transmitters 315 21-May-13 01-Apr-14 98 1129 PR Issue 30 21-May-13 20-Jun-13 98 1139 Enquiry Floating 140 20-Jun-13 07-Nov-13 98 1149 Receive quotes from Vendors 140 30-Jun-13 17-Nov-13 98 1159 Technical Bid Evaluation 140 10-Jul-13 27-Nov-13 98 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 7. Activity ID Activity Name Original Duration Start Finish Total Float 1169 Vendor Data and complete commercial 140 20-Jul-13 07-Dec-13 98 1179 Issue of PO 6 09-Aug-13 08-Oct-13 98 1189 Manufacturing of Items 150 08-Oct-13 07-Mar-14 98 1199 Material Delivery 20 12-Mar-14 01-Apr-14 98 Harmal FD-10-Oct13.3.1.2.1.4.10 F&G SystemsHarmal FD-10-Oct13.3.1.2.1.4.10 F&G Systems 321 05-May-13 22-Mar-14 108 1289 PR Issue 2 05-May-13 07-May-13 108 1299 Enquiry Floating 7 07-May-13 14-May-13 108 1309 Receive quotes from Vendors 150 22-May-13 19-Oct-13 108 1319 Technical Bid Evaluation 146 06-Jun-13 30-Oct-13 108 1329 Vendor Data and complete commercial 25 10-Oct-13 04-Nov-13 108 1339 Issue of PO 3 04-Nov-13 07-Nov-13 108 1349 Manufacturing of Items 110 07-Nov-13 25-Feb-14 108 1359 Material Delivery 20 02-Mar-14 22-Mar-14 108 Harmal FD-10-Oct13.3.1.2.1.4.13 Bulk MaterialsHarmal FD-10-Oct13.3.1.2.1.4.13 Bulk Materials 360 20-May-13 15-May-14 66 1619 PR Issue 2 28-May-13 30-May-13 66 1629 Enquiry Floating 140 30-May-13 17-Oct-13 66 1639 Receive quotes from Vendors 160 20-May-13 27-Oct-13 66 1659 Vendor Data and complete commercial 15 22-Oct-13 06-Nov-13 66 1669 Issue of PO 140 16-Nov-13 05-Apr-14 66 1679 Manufacturing of Items 150 26-Nov-13 25-Apr-14 66 1699 Material Delivery 20 25-Apr-14 15-May-14 66 Harmal FD-10-Oct13.3.4 CONSTRUCTION Phase 1Harmal FD-10-Oct13.3.4 CONSTRUCTION Phase 1 605 09-Dec-12 10-Aug-14 45 Harmal FD-10-Oct13.3.4.1.3.1 Bulk Header Line 16" DSS (16 km)Harmal FD-10-Oct13.3.4.1.3.1 Bulk Header Line 16" DSS (16 km) 349 26-Aug-13 10-Aug-14 44 Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.1 Civil WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.1 Civil Works 349 26-Aug-13 10-Aug-14 44 PL C1000 Route Survey and Peg Marking 30 26-Aug-13 25-Sep-13 35 PL C1010 Right of Way Preparation 30 31-Aug-13 30-Sep-13 35 PL C1020 Excavation of Trench 80 24-Nov-13 12-Feb-14 44 PL C1030 Prepadding of sand for Pipeline 70 27-Nov-13 05-Feb-14 44 PL C1040 Post Padding after Laying of Pipeline 45 17-Apr-14 01-Jun-14 44 PL C1050 Back filling of Trench 80 18-Mar-14 06-Jun-14 44 PL C1060 Construction of Windrow 31 08-Jul-14 08-Aug-14 44 PL C1070 Final Grading for the ROW & Marker plate 30 11-Jul-14 10-Aug-14 44 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 8. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.2 Mechanical WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.2 Mechanical Works 287 24-Sep-13 08-Jul-14 44 PL M1000 Stringing of Pipes 120 24-Sep-13 22-Jan-14 47 PL M1020 Straight Welding 180 20-Oct-13 18-Apr-14 47 PL M1030 NDT and repair if any 170 04-Nov-13 23-Apr-14 47 PL M1040 Sleeve Installation 150 29-Nov-13 28-Apr-14 47 PL M1050 Lowering of Pipes 150 09-Dec-13 08-May-14 44 PL M1060 Tie-in Welding 150 16-Dec-13 15-May-14 44 PL M1070 Barred Tee Welding 4 26-Apr-14 30-Apr-14 64 PL M1080 IJ Spool Installation 8 27-Apr-14 05-May-14 56 PL M1090 NDT and Repair if any 80 01-Mar-14 20-May-14 44 PL M1100 Sleeve Installation 75 13-Mar-14 27-May-14 44 PL M1110 Line Completion and Clearence 5 03-Jun-14 08-Jun-14 44 PL M1120 Hydrotesting 30 08-Jun-14 08-Jul-14 44 Harmal FD-10-Oct13.3.4.1.3.1.1.3.1.3 FOC WorksHarmal FD-10-Oct13.3.4.1.3.1.1.3.1.3 FOC Works 103 09-Apr-14 21-Jul-14 54 PL FOC1000 HDPE Duct Laying 60 09-Apr-14 08-Jun-14 67 PL FOC1010 Post Padding & Backfilling 50 22-Apr-14 11-Jun-14 80 PL FOC1020 FO Cable Blowing 7 08-Jul-14 15-Jul-14 54 PL FOC1030 FO Jointing & Splicing 5 16-Jul-14 21-Jul-14 54 Harmal FD-10-Oct13.3.4.2 Cathodic Protection WorksHarmal FD-10-Oct13.3.4.2 Cathodic Protection Works 597 09-Dec-12 02-Aug-14 44 Harmal FD-10-Oct13.3.4.2.1 Design WorksHarmal FD-10-Oct13.3.4.2.1 Design Works 45 09-Dec-12 27-Jan-13 192 PL CP1000 Design Preparation, Submission & Approval 45 09-Dec-12 27-Jan-13 192 Harmal FD-10-Oct13.3.4.2.4 ProcurementHarmal FD-10-Oct13.3.4.2.4 Procurement 365 29-Jan-13 29-Jan-14 192 A2280 CP Transformer Manufacturing 250 29-Jan-13 06-Oct-13 192 A2290 FAT & Documentation and Release 100 07-Oct-13 21-Dec-13 192 A2300 CP Transformer Receipt 31 29-Dec-13 29-Jan-14 192 Harmal FD-10-Oct13.3.4.2.2 Temporary CP InstallationHarmal FD-10-Oct13.3.4.2.2 Temporary CP Installation 75 09-Mar-14 23-May-14 58 PL CP1010 Temp.CP Installation for Pipeline 75 09-Mar-14 23-May-14 58 Harmal FD-10-Oct13.3.4.2.3 Permanent CP InstallationHarmal FD-10-Oct13.3.4.2.3 Permanent CP Installation 57 06-Jun-14 02-Aug-14 44 PL CP1020 Ground Bed Installation 15 06-Jun-14 21-Jun-14 44 PL CP1030 Anode JB Installation 3 19-Jun-14 22-Jun-14 46 PL CP1040 NDB Installation 2 22-Jun-14 24-Jun-14 46 PL CP1080 CP Tranformer Installation 1 26-Jun-14 27-Jun-14 44 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 9. Activity ID Activity Name Original Duration Start Finish Total Float PL CP1100 Trenching, Cable laying, Backfilling 7 26-Jun-14 03-Jul-14 44 PL CP1110 CP Cable Termination 5 03-Jul-14 08-Jul-14 44 PL CP1120 DCVG Survey 10 11-Jun-14 21-Jun-14 60 PL CP1140 Pre-Commissioning activity 10 08-Jul-14 18-Jul-14 44 PL CP1150 Final Commissioning 15 18-Jul-14 02-Aug-14 44 PL CP1160 CP System CIPS Survey 10 18-Jul-14 28-Jul-14 49 Harmal FD-10-Oct13.3.4.1.3.2 Harmal RMS-2 Manifold Construction workHarmal FD-10-Oct13.3.4.1.3.2 Harmal RMS-2 Manifold Construction work 339 05-Sep-13 10-Aug-14 45 Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.1 Civil WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.1 Civil Works 339 05-Sep-13 10-Aug-14 45 RMS C101 Plot Survey and set out 50 05-Sep-13 25-Oct-13 35 RMS C102 Land Filling and Access Road Preparation 45 09-Nov-13 24-Dec-13 35 RMS C103 Precasting for Foundation 45 25-Oct-13 09-Dec-13 50 RMS C104 Fencing and Gate Instalaltion 25 19-Nov-13 14-Dec-13 35 RMS C105 Marking and Excavation of the Foundation 20 24-Nov-13 14-Dec-13 36 RMS C106 PCC for Foundation 20 01-Dec-13 21-Dec-13 36 RMS C107 Foundation Installation 30 08-Dec-13 07-Jan-14 36 RMS C108 Foundation Backfilling & Compacting 35 12-May-14 16-Jun-14 36 RMS C109 Cable Trench Excavation 15 16-Jun-14 01-Jul-14 39 RMS C110 Cable Trench Backfilling 10 12-Jul-14 22-Jul-14 45 RMS C111 Grouting, Final Grading & House Keeping 19 22-Jul-14 10-Aug-14 45 Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.2 Mechanical WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.2 Mechanical Works 211 22-Nov-13 21-Jun-14 67 RMS M101 Prefabrication of Spools 105 22-Nov-13 07-Mar-14 37 RMS M102 NDT and Repair if any 90 22-Dec-13 22-Mar-14 52 RMS M103 Structure Support Fabrication & Coating 105 22-Nov-13 07-Mar-14 37 RMS M104 Suppot Erection 80 07-Jan-14 28-Mar-14 36 RMS M105 Piping Erection, Welding & Tie In 75 14-Jan-14 30-Mar-14 36 RMS M106 NDT and Repair if any 20 20-Mar-14 09-Apr-14 36 RMS M107 Box Up 25 01-Apr-14 26-Apr-14 36 RMS M108 Hydrotesting 35 05-Apr-14 10-May-14 36 RMS M109 Vent Stack Installation 50 02-May-14 21-Jun-14 67 Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.3 Instrument WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.3 Instrument Works 66 11-May-14 16-Jul-14 36 RMS I101 Panel Installation 10 14-Jun-14 24-Jun-14 36 RMS I102 Cable laying 25 17-Jun-14 12-Jul-14 39 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 10. Activity ID Activity Name Original Duration Start Finish Total Float RMS I103 Field Instrument Installation 15 11-May-14 26-May-14 58 RMS I104 Junction Box & Support Installation 20 13-May-14 02-Jun-14 58 RMS I105 Glanding, Tremination & Tubing 22 24-Jun-14 16-Jul-14 36 RMS I106 Actuated Valve Installation 20 17-May-14 06-Jun-14 62 RMS I107 Name Plate Installation 5 24-May-14 29-May-14 62 Harmal FD-10-Oct13.3.4.1.3.2.1.3.2.4 Electrical WorksHarmal FD-10-Oct13.3.4.1.3.2.1.3.2.4 Electrical Works 92 25-Apr-14 26-Jul-14 39 RMS E101 Transformer installation (3 nos) 15 25-Apr-14 10-May-14 61 RMS E102 Instrument Air Compressor 5 10-May-14 15-May-14 61 RMS E103 Cable Laying 15 17-Jun-14 02-Jul-14 39 RMS E104 Glanding & Termination 7 04-Jul-14 11-Jul-14 39 RMS E105 Fence Earthing 15 25-Apr-14 10-May-14 66 RMS E106 Equipment Earthing 35 25-May-14 29-Jun-14 51 RMS E107 Panel Energization 15 11-Jul-14 26-Jul-14 39 Harmal FD-10-Oct13.3.4.1.3.2.1 Containerized Substation Building- Civil worksHarmal FD-10-Oct13.3.4.1.3.2.1 Containerized Substation Building- Civil wo... 227 17-Nov-13 02-Jul-14 50 SS C1001 Earth Work for Containerized Building Foundation 25 17-Nov-13 12-Dec-13 83 SS C1002 Laying of Polythene sheet 3 13-Dec-13 16-Dec-13 83 SS C1003 PCC for the foundation 2 13-Dec-13 15-Dec-13 83 SS C1004 Reinforce work for Foundation 7 15-Dec-13 22-Dec-13 83 SS C1005 Shuttering for Foundation 4 23-Dec-13 27-Dec-13 83 SS C1006 Concreting work for Foundation 3 28-Dec-13 31-Dec-13 83 SS C1007 Deshuttering for Foundation 4 01-Jan-14 05-Jan-14 83 SS C1008 Reinforcement work for Coloumn 4 07-Jan-14 11-Jan-14 83 SS C1009 Shuttering of column 6 12-Jan-14 18-Jan-14 83 SS C1010 Column Concreting 7 18-Jan-14 25-Jan-14 83 SS C1011 Deshuttering for Column 4 26-Jan-14 30-Jan-14 83 SS C1012 Shuttering work for floor beam 20 31-Jan-14 20-Feb-14 83 SS C1013 Reinforcement work for floor beam 20 05-Feb-14 25-Feb-14 83 SS C1014 Concreting for floor beam 3 26-Feb-14 01-Mar-14 83 SS C1015 Deshuttering of floor beam 7 08-Mar-14 15-Mar-14 83 SS C1016 Applying Protective coating 7 16-Mar-14 23-Mar-14 83 SS C1017 Backfilling the foundation 9 23-Mar-14 01-Apr-14 83 SS C1018 Containerized Substation Installation 8 04-May-14 12-May-14 50 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 11. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13.3.4.1.3.2.1.2 Equipment Installation WorksHarmal FD-10-Oct13.3.4.1.3.2.1.2 Equipment Installation Works 52 11-May-14 02-Jul-14 50 SS I1000 Installation of Panels 4 11-May-14 15-May-14 51 SS I1010 Installation of Battery Bank 10 15-May-14 25-May-14 52 SS I1020 Installation of DC-DB 7 25-May-14 01-Jun-14 52 SS I1030 Installation of Lighting DB 7 12-May-14 19-May-14 50 SS I1040 Installation of 415 v Switch Board 15 12-May-14 27-May-14 50 SS I1050 Installation of emergency Lighting DB 7 27-May-14 03-Jun-14 50 SS I1060 Installation of HVAC system 29 03-Jun-14 02-Jul-14 50 Harmal FD-10-Oct13.3.4.1.3.4 OHL Construction (7 Km RMS-1 to RMS-2)Harmal FD-10-Oct13.3.4.1.3.4 OHL Construction (7 Km RMS-1 to RMS-2) 190 25-Oct-13 03-May-14 110 OHL 1000 Survey & ROW grading 50 25-Oct-13 14-Dec-13 110 OHL 1020 Pole hole drilling 50 14-Dec-13 02-Feb-14 110 OHL 1030 Pole distribution 50 22-Dec-13 10-Feb-14 110 OHL 1040 Dressing 35 15-Feb-14 22-Mar-14 110 OHL 1050 Errectioning 25 20-Feb-14 17-Mar-14 110 OHL 1060 Conductor Stringing 20 24-Feb-14 16-Mar-14 110 OHL 1070 Jumpering 15 16-Mar-14 31-Mar-14 110 OHL 1080 Installation of Field Isolator 14 31-Mar-14 14-Apr-14 110 OHL 1090 Installation of Auto recloser 14 02-Apr-14 16-Apr-14 110 OHL 1100 33 KV Spur Lines from OHL to RMS 14 17-Apr-14 01-May-14 110 OHL 1110 33 KV Underground cabling and Termination 10 23-Apr-14 03-May-14 110 Harmal FD-10-Oct13.3.4.6 Shut Down ActivitiesHarmal FD-10-Oct13.3.4.6 Shut Down Activities 183 25-Sep-13 27-Mar-14 153 Harmal FD-10-Oct13.3.4.6.1.3.3.1 Civil WorksHarmal FD-10-Oct13.3.4.6.1.3.3.1 Civil Works 183 25-Sep-13 27-Mar-14 152 SD C10 Plot Survey and set out 15 25-Sep-13 10-Oct-13 270 SD C20 Precasting for Foundation 15 25-Sep-13 10-Oct-13 287 SD C30 Marking and Excavation of the Foundation 20 11-Oct-13 31-Oct-13 270 SD C40 PCC for Foundation 15 20-Oct-13 04-Nov-13 270 SD C50 Foundation Installation 10 27-Oct-13 06-Nov-13 270 SD C60 Foundation Backfilling & Compacting 15 09-Nov-13 24-Nov-13 270 SD C70 Cable Trench Excavation 20 22-Jan-14 11-Feb-14 156 SD C80 Cable Trench Backfilling 10 08-Mar-14 18-Mar-14 156 SD C90 Grouting, Final Grading & House Keeping 5 22-Mar-14 27-Mar-14 152 Harmal FD-10-Oct13.3.4.6.1.3.3.2 Mechanical WorksHarmal FD-10-Oct13.3.4.6.1.3.3.2 Mechanical Works 99 28-Nov-13 07-Mar-14 152 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 12. Activity ID Activity Name Original Duration Start Finish Total Float SD M10 Prefabrication of Spools 55 28-Nov-13 22-Jan-14 152 SD M20 NDT and Repair if any 10 17-Jan-14 27-Jan-14 159 SD M30 Structure Support Fabrication & Coating 30 08-Dec-13 07-Jan-14 152 SD M40 Suppot Erection 30 12-Jan-14 11-Feb-14 152 SD M50 Piping Erection, Welding 15 03-Feb-14 18-Feb-14 152 SD M60 NDT and Repair if any 20 05-Feb-14 25-Feb-14 152 SD M70 Hydrotesting 10 25-Feb-14 07-Mar-14 152 Harmal FD-10-Oct13.3.4.6.1.3.3.4 Electrical WorksHarmal FD-10-Oct13.3.4.6.1.3.3.4 Electrical Works 25 11-Feb-14 08-Mar-14 156 SD E10 Cable Laying 15 11-Feb-14 26-Feb-14 156 SD E20 Glanding & Termination 10 26-Feb-14 08-Mar-14 156 Harmal FD-10-Oct13.3.4.6.1.3.3.3 Instrument WorksHarmal FD-10-Oct13.3.4.6.1.3.3.3 Instrument Works 41 14-Feb-14 27-Mar-14 153 SD I10 Cable laying 15 14-Feb-14 01-Mar-14 163 SD I20 Field Instrument Installation 10 25-Feb-14 07-Mar-14 152 SD I30 Junction Box & Support Installation 10 27-Feb-14 09-Mar-14 152 SD I40 Glanding, Tremination & Tubing 15 12-Mar-14 27-Mar-14 152 SD I50 ESD Valve Installation 7 01-Mar-14 08-Mar-14 171 SD I60 Name Plate Installation 5 04-Mar-14 09-Mar-14 171 Harmal FD-10-Oct13.3.4.1.3.3 TIE-IN Works at KautherHarmal FD-10-Oct13.3.4.1.3.3 TIE-IN Works at Kauther 11 17-Mar-14 28-Mar-14 171 Harmal FD-10-Oct13.3.4.1.3.3.1 Shut Down Tie-In Date confirmation by PDOHarmal FD-10-Oct13.3.4.1.3.3.1 Shut Down Tie-In Date confirmation by PDO 11 17-Mar-14 28-Mar-14 171 SD 1000 Final Shut Down Date from PDO 11 17-Mar-14 28-Mar-14 171 Harmal FD-10-Oct13.3.1 Pre-Commisioning Activities Phase 1Harmal FD-10-Oct13.3.1 Pre-Commisioning Activities Phase 1 124 18-Apr-14 20-Aug-14 36 A3170 Punch List Clearance 30 21-Jul-14 20-Aug-14 36 A3180 CP-Testing and Commmision 7 26-Jul-14 02-Aug-14 44 A3190 HVAC system 15 02-Jul-14 17-Jul-14 50 A3200 FOC ODTR Testing 2 21-Jul-14 23-Jul-14 54 A3210 RMS-2 Loop checking works 25 16-Jul-14 10-Aug-14 36 A3220 RMS-2 Electrical Testing 12 26-Jul-14 07-Aug-14 39 A3230 RMS-2 Panel Enegization 10 22-Jul-14 01-Aug-14 45 A3240 Transformer Energization 10 11-Jul-14 21-Jul-14 46 A3250 OHL Relay Setting and Testing 20 18-Apr-14 08-May-14 110 A3260 Pre-Commisioning Completion 10 10-Aug-14 20-Aug-14 36 Harmal FD-10-Oct13.1 Harmal Field Development - Phase-2Harmal FD-10-Oct13.1 Harmal Field Development - Phase-2 686 09-Dec-12 30-Oct-14 90 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 13. Activity ID Activity Name Original Duration Start Finish Total Float Harmal FD-10-Oct13.1.1.1 ENGINEERING Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.1.1 ENGINEERING Phase 2- Well Test Installation 682 09-Dec-12 26-Oct-14 23 Harmal FD-10-Oct13.1.1.1.1.1.2 AFC PackageHarmal FD-10-Oct13.1.1.1.1.1.2 AFC Package 210 09-Dec-12 29-Oct-13 55 D0010 Process 320 09-Dec-12 29-Oct-13 0 D0020 Civil 287 14-Jan-13 28-Oct-13 56 D0030 Mechanical and Piping 310 22-Dec-12 29-Oct-13 0 D0040 Electrical 297 31-Dec-12 24-Oct-13 0 D0050 Control and automation 300 29-Dec-12 25-Oct-13 0 Harmal FD-10-Oct13.1.1.1.1 Bulk MTOHarmal FD-10-Oct13.1.1.1.1 Bulk MTO 254 18-Jan-13 29-Sep-13 85 A3620 Civil & Structural 205 19-Feb-13 12-Sep-13 45 A3630 Electrical 235 20-Jan-13 12-Sep-13 45 A3640 Mechanical and Piping 249 23-Jan-13 29-Sep-13 85 A3650 Control and Automation 240 18-Jan-13 15-Sep-13 44 Harmal FD-10-Oct13.1.1.1.2 Project Management and Supporting DocumentsHarmal FD-10-Oct13.1.1.1.2 Project Management and Supporting Documents 642 22-Jan-13 26-Oct-14 23 A3660 Project Management 580 22-Jan-13 25-Aug-14 85 A3670 As Built Packages 35 21-Sep-14 26-Oct-14 4 A3790 SAP 45 22-Aug-14 06-Oct-14 0 A3800 CCMS 45 22-Aug-14 06-Oct-14 0 Harmal FD-10-Oct13.1.1.21 PROCUREMENT Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.1.21 PROCUREMENT Phase 2- Well Test Installation 533 03-Mar-13 18-Aug-14 31 Harmal FD-10-Oct13.1.1.21.5 Test Seperator Installation MaterialsHarmal FD-10-Oct13.1.1.21.5 Test Seperator Installation Materials 533 03-Mar-13 18-Aug-14 31 Harmal FD-10-Oct13.1.1.21.5.1.2.4 ESD ValveHarmal FD-10-Oct13.1.1.21.5.1.2.4 ESD Valve 494 24-Mar-13 31-Jul-14 49 1939 PR Issue 2 24-Mar-13 26-Mar-13 31 1949 Enquiry Floating 14 27-Mar-13 10-Apr-13 49 1959 Receive quotes from Vendors 180 10-Apr-13 07-Oct-13 49 1969 Technical Bid Evaluation 30 07-Oct-13 06-Nov-13 49 1979 Vendor Data and complete commercial 15 06-Nov-13 21-Nov-13 49 1989 Issue of PO 5 21-Nov-13 26-Nov-13 49 1999 Manufacturing of Items 200 27-Nov-13 15-Jun-14 49 2009 Shipping Delivery 30 16-Jun-14 16-Jul-14 49 3189 ESD Valve Receipt at site 10 21-Jul-14 31-Jul-14 49 Harmal FD-10-Oct13.1.1.21.5.1.2.5 Relief ValveHarmal FD-10-Oct13.1.1.21.5.1.2.5 Relief Valve 493 27-Mar-13 02-Aug-14 23 2019 PR Issue 2 27-Mar-13 29-Mar-13 23 2029 Enquiry Floating 14 29-Mar-13 12-Apr-13 23 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 14. Activity ID Activity Name Original Duration Start Finish Total Float 2039 Receive quotes from Vendors 200 13-Apr-13 19-Oct-13 23 2049 Technical Bid Evaluation 16 20-Oct-13 04-Nov-13 23 2059 Vendor Data and complete commercial 16 05-Nov-13 20-Nov-13 23 2069 Issue of PO 7 21-Nov-13 28-Nov-13 23 2079 Manufacturing of Items 200 28-Nov-13 16-Jun-14 23 2089 Shipping Delivery 30 16-Jun-14 16-Jul-14 23 3199 Relief Valve Receipt at Site 10 23-Jul-14 02-Aug-14 23 Harmal FD-10-Oct13.1.1.21.5.1.2.9 Control ValvesHarmal FD-10-Oct13.1.1.21.5.1.2.9 Control Valves 465 16-Mar-13 24-Jun-14 62 2339 PR Issue 2 16-Mar-13 18-Mar-13 62 2349 Enquiry Floating 14 18-Mar-13 01-Apr-13 62 2359 Receive quotes from Vendors 190 01-Apr-13 08-Oct-13 62 2369 Technical Bid Evaluation 16 08-Oct-13 24-Oct-13 62 2379 Vendor Data and complete commercial 12 17-Oct-13 29-Oct-13 62 2389 Issue of PO 7 29-Oct-13 05-Nov-13 62 2399 Manufacturing of Items 184 05-Nov-13 08-May-14 62 2409 Shipping Delivery 30 08-May-14 07-Jun-14 62 3209 Control Valve Receipt at Site 10 14-Jun-14 24-Jun-14 62 Harmal FD-10-Oct13.1.1.21.5.1 Test SeparatorHarmal FD-10-Oct13.1.1.21.5.1 Test Separator 517 03-Mar-13 02-Aug-14 0 A2490 PR Issue 2 03-Mar-13 05-Mar-13 0 A2500 Enquiry Floating 14 05-Mar-13 19-Mar-13 0 A2510 Receive Quotes from Vendor 21 19-Mar-13 09-Apr-13 0 A2520 TBE & Vendor Finilize 195 09-Apr-13 21-Oct-13 0 A2530 Issue of PO 4 21-Oct-13 25-Oct-13 0 A2540 Manufacturing of Items 236 29-Oct-13 22-Jun-14 0 A2550 Inspection & Release 20 22-Jun-14 12-Jul-14 0 A2560 Material Delivery 12 13-Jul-14 25-Jul-14 0 A2820 Test Separator Receipt at Site 7 26-Jul-14 02-Aug-14 0 Harmal FD-10-Oct13.1.1.21.5.2 Piping Materials & FittingsHarmal FD-10-Oct13.1.1.21.5.2 Piping Materials & Fittings 403 26-Mar-13 03-May-14 73 A2850 PR Issue 2 26-Mar-13 28-Mar-13 73 A2860 Enquiry Floating 48 28-Mar-13 15-May-13 73 A2870 Receive Quotes from Vendor 140 15-May-13 02-Oct-13 73 A2880 TBE & Vendor Finilize 88 30-Jul-13 26-Oct-13 73 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 15. Activity ID Activity Name Original Duration Start Finish Total Float A2890 Issue of PO 28 26-Oct-13 23-Nov-13 73 A2900 Manufacturing of Items 136 23-Nov-13 08-Apr-14 73 A2910 Inspection & Release 112 23-Dec-13 14-Apr-14 73 A2920 Material Delivery 112 28-Dec-13 19-Apr-14 73 A2930 Material Receipt at Site 112 11-Jan-14 03-May-14 73 Harmal FD-10-Oct13.1.1.21.5.3 Bulk MaterialsHarmal FD-10-Oct13.1.1.21.5.3 Bulk Materials 413 26-Mar-13 13-May-14 56 A2940 PR Issue 2 26-Mar-13 28-Mar-13 56 A2950 Enquiry Floating 7 29-Mar-13 05-Apr-13 56 A2960 Receive Quotes from Vendor 128 06-Apr-13 12-Aug-13 56 A2970 Vendor Finilize 128 30-Apr-13 05-Sep-13 56 A2980 Issue of PO 48 05-Sep-13 23-Oct-13 56 A2990 Manufacturing of Items 200 12-Sep-13 31-Mar-14 56 A3000 Inspection & Release 200 10-Oct-13 28-Apr-14 56 A3010 Material Receipt at Site 150 14-Dec-13 13-May-14 56 Harmal FD-10-Oct13.1.1.21.5.4 Instrument Air CompressorHarmal FD-10-Oct13.1.1.21.5.4 Instrument Air Compressor 429 28-Mar-13 31-May-14 85 A3020 PR Issue 6 28-Mar-13 03-Apr-13 85 A3030 Enquiry Floating 152 03-Apr-13 02-Sep-13 85 A3040 Receive quotes from Vendors 144 23-Apr-13 14-Sep-13 85 A3050 TBE & Vendor Finilize 136 13-May-13 26-Sep-13 85 A3060 Issue of PO 7 26-Sep-13 03-Oct-13 85 A3070 Manufacturing of Items 160 03-Oct-13 12-Mar-14 85 A3080 Inspection & Release 20 12-Mar-14 01-Apr-14 85 A3090 Material Delivery 20 01-Apr-14 21-Apr-14 85 A3100 Air Compressor Receipt at Site 30 01-May-14 31-May-14 85 Harmal FD-10-Oct13.1.1.21.5.5 Flow MeterHarmal FD-10-Oct13.1.1.21.5.5 Flow Meter 445 24-Mar-13 12-Jun-14 98 A3680 PR Issue 6 24-Mar-13 30-Mar-13 31 A3690 Enquiry Floating 152 30-Mar-13 29-Aug-13 31 A3700 Receive quotes from Vendors 136 23-Apr-13 06-Sep-13 31 A3710 TBE & Vendor Finilize 12 06-Sep-13 18-Sep-13 31 A3720 Issue of PO 7 18-Sep-13 25-Sep-13 31 A3730 Manufacturing of Items 180 25-Sep-13 24-Mar-14 98 A3740 Inspection & Release 20 24-Mar-14 13-Apr-14 98 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 16. Activity ID Activity Name Original Duration Start Finish Total Float A3750 Material Delivery 20 13-Apr-14 03-May-14 98 A3760 Material Receipt at Site 30 13-May-14 12-Jun-14 98 Harmal FD-10-Oct13.1.1.21.5.6 F & G SystemHarmal FD-10-Oct13.1.1.21.5.6 F & G System 334 18-Sep-13 18-Aug-14 31 A3810 PR Issue 25 18-Sep-13 13-Oct-13 31 A3820 Enquiry Floating 60 13-Oct-13 12-Dec-13 31 A3830 Receive quotes from Vendors 60 21-Oct-13 20-Dec-13 31 A3840 TBE & Vendor Finilize 12 20-Dec-13 01-Jan-14 31 A3850 Issue of PO 7 01-Jan-14 08-Jan-14 31 A3860 Manufacturing of Items 150 08-Jan-14 07-Jun-14 31 A3870 Inspection & Release 20 07-Jun-14 27-Jun-14 31 A3880 Material Delivery 20 27-Jun-14 17-Jul-14 31 A3890 Material Receipt at Site 22 27-Jul-14 18-Aug-14 31 Harmal FD-10-Oct13.1.2 CONSTRUCTION Phase 2- Well Test InstallationHarmal FD-10-Oct13.1.2 CONSTRUCTION Phase 2- Well Test Installation 197 29-Mar-14 12-Oct-14 107 Harmal FD-10-Oct13.1.2.2 Well Test Seperator InstallationHarmal FD-10-Oct13.1.2.2 Well Test Seperator Installation 197 29-Mar-14 12-Oct-14 107 Harmal FD-10-Oct13.1.2.2.1 Civil WorksHarmal FD-10-Oct13.1.2.2.1 Civil Works 197 29-Mar-14 12-Oct-14 107 WTS C18 Excavation for Foundations 30 29-Apr-14 29-May-14 35 WTS C28 PCC for Foundation 45 01-May-14 15-Jun-14 35 WTS C38 Foundation Installation 45 08-May-14 22-Jun-14 35 WTS C48 Foundation Backfilling & Compaction 30 15-Aug-14 14-Sep-14 136 WTS C58 Excavation for Cable Trench 7 29-May-14 05-Jun-14 96 WTS C68 Cable trench backfilling 7 14-Sep-14 21-Sep-14 2 WTS C78 Grouting, Final Grading and Housekeeping 22 21-Sep-14 12-Oct-14 2 WTS C8 Plot Survey and set out 30 29-Mar-14 28-Apr-14 35 Harmal FD-10-Oct13.1.2.2.2 Mechanical WorksHarmal FD-10-Oct13.1.2.2.2 Mechanical Works 172 11-Apr-14 30-Sep-14 0 WTS M19 Prefabrication of Piping spools 40 11-Apr-14 21-May-14 56 WTS M29 NDT 36 25-Apr-14 31-May-14 56 WTS M39 Spool Hydrotest 32 09-May-14 10-Jun-14 56 WTS M49 Structural support Fabrication & Coating 32 11-Apr-14 13-May-14 82 WTS M59 Structual Support installation 24 22-Jun-14 16-Jul-14 35 WTS M69 Piping Erection 35 05-Aug-14 09-Sep-14 0 WTS M79 Final Hydrotest 7 09-Sep-14 16-Sep-14 0 WTS M89 Valve installation / Nitrogen Purging 14 16-Sep-14 30-Sep-14 0 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone  
  • 17. Activity ID Activity Name Original Duration Start Finish Total Float WTS M9 Test Separator errection and alignment 3 02-Aug-14 05-Aug-14 0 Harmal FD-10-Oct13.1.2.2.3 Electrical WorksHarmal FD-10-Oct13.1.2.2.3 Electrical Works 27 09-Sep-14 06-Oct-14 0 WTS E13 Cable Glanding & Termination 12 15-Sep-14 27-Sep-14 0 WTS E23 Earthing works for Equipment & Instruments 9 27-Sep-14 06-Oct-14 0 WTS E3 Cable laying 5 09-Sep-14 14-Sep-14 0 Harmal FD-10-Oct13.1.2.2.4 Instrumentation worksHarmal FD-10-Oct13.1.2.2.4 Instrumentation works 65 02-Aug-14 06-Oct-14 0 WTS I14 ESD Valve /Flow meter /F & G system Installation 12 18-Sep-14 30-Sep-14 0 WTS I24 Instrument cable laying & Termination 12 21-Sep-14 03-Oct-14 0 WTS I34 Instrument Tubing works 19 17-Sep-14 06-Oct-14 0 WTS I4 Instruments Calibration 24 02-Aug-14 26-Aug-14 23 Harmal FD-10-Oct13.1.7 Pre-Commissioning Activities Phase 2Harmal FD-10-Oct13.1.7 Pre-Commissioning Activities Phase 2 175 08-May-14 30-Oct-14 0 Pre 072 Substation Readiness 15 08-May-14 23-May-14 115 Pre 092 WTS Precommissioning activities 24 06-Oct-14 30-Oct-14 0 Pre 102 Ex- Inspection works 10 10-Oct-14 20-Oct-14 0 Pre 112 Pie - Configuration by PDO 14 06-Oct-14 20-Oct-14 0 Pre 122 Loop Checking 10 20-Oct-14 30-Oct-14 0 Harmal FD-10-Oct13.Comm Support Commissioning SupportHarmal FD-10-Oct13.Comm Support Commissioning Support 161 20-Aug-14 28-Jan-15 0 A3770 Commissioning Support Assistance for Testing Facilities 90 30-Oct-14 28-Jan-15 0 A3780 Commisioning Support Assistance for Production Facilities 90 20-Aug-14 18-Nov-14 36 D J F M A M J J A S O N D J F A J J A S N D J 2013 2014 2015 Harmal RMS-2 Construction 16" DSS Pipeline to KGP Phase 1 Phase 2 - Final   10-Oct-13 10:32 Primary Baseline Actual Work Remaining Work Critical Remaining Work Baseline Milestone Milestone