SlideShare a Scribd company logo
1 of 46
DEMOLITION OF STRUCTURES
A Seminar on
INDEX
I. Introduction
II. History
III. Objectives
IV. Steps before Demolition
V. Demolition sequence
VI. Methods of Demolition
I. INTRODUCTION
 Demolition is bringing down the building and other
structures safely.
 The demolition of structure with the help of
explosives is called as implosion.
 The main objective for demolition may be the age of
the structure.
 Methods of demolition depends upon the type of
structure, height and surrounding structures.
Demolition of a building
II. HISTORY
 Historians generally agree that the first true "explosive" was
black powder, which was developed around the 13th century.
 The first recorded use of black powder for demolition purposes
appears to have occurred in the early 1600s, when quarries in
Hungary began using it for rock blasting.
 Black powder was put to use in the tin mines of England, and
Switzerland adopted blasting technology for road construction.
 Throughout the 1930s, structural explosive demolition was
overseen by engineers working directly for large dynamite
manufacturers.
III. OBJECTIVES
 Prevention damaging the neighbourhood environment.
 Repair of damaged structures.
 Construction of other structure at that previously constructed
site.
 Provides safety for the occupants in the building.
IV. STEPS BEFORE DEMOLITION
1. Surveying
2. Removal of hazardous
materials
3. Preparation of plan
4. Safety measures
1. Surveying:
The building survey should cover following:
 The construction materials.
 The existing use and, if possible, the past uses of the building prior
to demolition.
 Adjoining pedestrian and vehicular traffic conditions.
 The sensitivity of neighbourhood with respect to noise, dust, vibration
and traffic impact.
 Available site area to allow on-site sorting of building debris.
2. Removal of hazardous
materials:
Asbestos Containing Material
 In the case when asbestos
containing material are
discovered, specialist contractor
shall be employed to remove such
asbestos containing material. The
asbestos waste should be
handled, stored and disposed of
as chemical waste in accordance
with the Waste Disposal
Regulation.
Soil Contamination Material
 In the case when possible soil
contamination material is present,
specialist shall be employed to
prepare soil contamination test
proposal and submit such
proposal to the Environmental
Protection Department for
comment.
Asbestos Material
Soil Contamination
3. Preparation of plan:
 A plan showing location of the building to be demolished, sections
of the slopes with ground level contours and detailed topography,
ground removal and backfilling, distances of adjacent structures
from the building to be demolished.
 A layout plan of all floors of the building to be demolished, with
adequate sections.
 A plan showing the procedure for the demolition of the building.
 A plan showing the proposed shoring and temporary support to be
provided to the building to be demolished.
 In the case when powered mechanical plants and equipment are
used, a plan showing the route of movement of powered
mechanical plants and equipment.
4. Safety measures:
Training and Communication:
 Demolition workers, including
plant or equipment operators,
shall go through proper job safety
training and be informed of the
potential hazards by attending
training sessions as well as on-
the-job training.
Equipment Maintenance:
 All equipment shall be tested and
examined before use. They shall
be properly stored and
maintained. The equipment shall
be inspected daily and results of
the inspection shall be recorded
accordingly.
Electrical Safety
 A properly connected power source from a local electric utility
supplier or a mobile electricity generator shall be utilized in
demolition sites.
Fire
 All flammable goods shall be removed from site unless they are
necessary for the works involved. Any remaining flammable goods
shall be stored in proper storage facilities. All furniture, timber,
doors, etc. shall be removed before any welding work is performed.
Fire fighting appliances shall be provided and maintained in working
conditions.
Safety Management
V. DEMOLITION SEQUENCE
 All cantilevered structures, verandas and features attached to
the external walls shall first be demolished prior to demolition
of main building.
 When demolishing the roof structure, all lift machine rooms
and water tanks at high level shall be demolished in “top
down” sequence to the main roof level.
 Floor beams shall be demolished in the order of cantilevered
beams, secondary beams and then main beams.
 Columns and load bearing walls shall be demolished after
removal of beams on top.
 If site conditions permit, the first floor slab directly above the
ground floor may be demolished by machine standing on
ground.
 Demolition of the floor slabs shall begin at mid span and
work towards the supporting beams.
 Floor beams shall be demolished in the order of cantilevered
beams, secondary beams and then main beams.
 Wire and winch shall be used to secure the cross beam to other
structural members.
 The concrete is first broken away at both ends near its column
supports to expose the reinforcement.
 Reinforcement shall be then cut to partially drop the beam and
the brought down with wire.
 Secure the column by wire and
winch to existing structure.
 Pre-weakening at the bottom of
column:
1) Break away the concrete to
expose the reinforcing bars.
2) Cut the reinforcing bars at the
exterior half of the column.
Cutting shall be performed
immediately prior to pulling.
 Pulling down the column in a
controlled motion.
VI. METHODS OF DEMOLITION:
A. Ball and crane
B. Dismantling
C. Pneumatic and hydraulic breaker
D. Pressure bursting
E. Explosives
A. Ball and crane
 This is one of the oldest and
most commonly used methods
for building demolition. A crane
uses a wrecking ball, weighing
up to 6120 kg, which is either
dropped onto or swung into the
element to be demolished.
 The ball is made
from forged steel, which means
the steel is not cast into a
mould in a molten state. It is
formed under very high
pressure while the steel is red
hot (soft but not molten) to
compress and to strengthen it.
 Concrete members can be
broken into small pieces, but
secondary cutting of reinforcing
may be necessary.
Wrecking ball at rest
Swinging the wrecking ball
 Advantages:
1) To demolish roofs and other horizontal spans.
2) The wrecking balls are still used when demolition may not
be possible due to local environmental issues or
asbestos/lead building content.
1) It demands a great deal of skill from the crane operator.
2) The height of a building that can be demolished is limited
by crane size and working room; however, buildings as high
as 20 stories have been demolished.
3) The breakup process can cause considerable dust,
vibration and noise which may be objectionable.
 Advantages and Disadvantages of Ball and
Crane method:
Advantages
Disadvantages
B. Dismantling
 Selective or complete demolition of
concrete structures is possible by
cutting elements and then
removing them with a crane.
 The cutting process may be by
sawing, water jetting or thermal
lance.
 Because the surface of the cut
concrete is smooth and relatively
regular, these methods have
particular application when the
objective is partial demolition, for
instance in the creation of
openings in walls and slabs.
Dismantling a beam
 Cutting with a water jet
minimizes dust and eliminates
vibration and fire hazards. An
abrasive and water-catching
system is required to clean up
during the jetting process.
 Hydro demolition uses a high
pressure supersonic water jet,
that penetrates the pores and
cracks of the concrete
and builds up an internal
pressure. When this pressure
exceeds the tensile strength of
the concrete, the concrete
breaks.
 The water jet can be used not
only for cutting straight lines
but also contours, a useful
feature for cutting access
manholes.
Water Jet cutting
 A thermal lance is created by packing a seamless mild steel
tube with low carbon rods and passing oxygen through the tube.
 While this method eliminates vibration and dust problems, it
creates other hazards associated with smoke and fire danger.
 Whether sawing, jetting or lancing is used to dismantle the
structure or its components, each element must be safely
lowered to the ground.
Thermal Lance Sawing method
1) Dismantlement of building components, specifically for re-
use, recycling, and waste management.
2) Reducing disposal costs where waste collection, hauling or
disposal is supported by the tax base.
3) Building components that are dismantled will need to be stored
in a secure, dry location. This will protect them from water
damage and theft.
1) The amount of time and cost of labor are the main drawbacks.
2) Harvesting materials from a structure can take weeks, whereas
demolition may be completed in roughly a day.
3) Toxic waste such as asbestos sheets and lead paint have no
resale value so they are discarded.
 Advantages and Disadvantages of Dismantling
method:
Advantages
Disadvantages
C. Pneumatic and hydraulic breaker
 A common piece of equipment used for demolishing bridge
decks, foundations and pavements is a hydraulically or
pneumatically operated, boom-mounted breaker.
 The advantages of a machine mounted breaker may include a
telescoping boom for easy reach and, remote control
operation and underwater demolition capabilities
 Some of the smaller remote- controlled machines can be lifted
through window openings and used inside a building to
demolish floors and walls.
 Productivity can vary greatly depending on hammer size, type
of concrete, amount of reinforcing and working conditions.
Pneumatic hammer
 A jackhammer is
a pneumatic or electro-
mechanical tool that combines
a hammer directly with
a chisel.
 Hand-held jackhammers are
typically powered
by compressed air, but some
use electric motors.
Electric powered tools come
in a variety of sizes from about
12 lbs - 65 lbs.
They require an external
power source, but do not
require a compressor.
Hydraulic breaker
 A hydraulic jackhammer, typically much larger than portable ones, may be
fitted to mechanical excavators or backhoes and is widely used for
roadwork, quarrying and general demolition or construction groundwork.
 They are used
in mines where there is an
explosion risk since they lack
any high-power electrical
circuitry that might cause a
triggering spark.
The jackhammer is
connected with hydraulic
hoses to a portable hydraulic
power pack: either a petrol or
diesel engine driving a
hydraulic pump
1) The hydraulic breakers have tremendous power output
also means they are the most power efficient, getting the
most work out of the available energy.
2) A properly used and maintained hydraulic machine can last
for a long time.
3) Pneumatic breakers are simpler tools with fewer moving
parts, requiring less maintenance.
1) They require power, fuel or battery for their work.
2) They tend to be the most expensive types.
3) They require an external power source.
 Advantages and Disadvantages of Pressure
Bursting method:
Advantages
Disadvantages
D. Pressure bursting
 Pressure bursting can be used in
cases where relatively quiet, dust-
free, controlled demolition is
preferred.
 Both mechanical and chemical
pressure bursting split the concrete,
either with a splitting machine
operating on hydraulic pressure
provided by a motor in the case of
mechanical bursting, or through the
insertion of an expansive slurry into
a pre-determined pattern of
boreholes in the case of chemical
bursting.
 The split concrete is then easily
removed, either by hand or by crane.
 Both methods work by applying
lateral forces against the inside of
holes drilled into the concrete.
Pressure bursting
E. Explosives
 Introduction
 In the controlled
demolition industry, building
implosion is the strategic placing
of explosive material and timing of its
detonation so that a structure collapses
on itself in a matter of seconds,
minimizing the physical damage to its
immediate surroundings.
 Despite its terminology, building
implosion also includes the controlled
demolition of other structures, such
as bridges, smokestacks, towers,
and tunnels.
 Numerous small explosives,
strategically placed within the structure,
are used to catalyze the collapse. Nitro-
glycerine, dynamite, or other explosives
are used to shatter reinforced concrete
supports.
RDX-based explosive
compounds expand at a very
high rate of
speed, up to 27,000 feet per
second (8,230 meters per
second)
Building Implosion
 Blasting methods employ rapidly
expanding gases confined within
a series of boreholes to produce
controlled fractures which provide
for easy concrete removal.
 For the demolition of concrete
structures it is usual to drill holes
at a predetermined angle into the
concrete to be removed.
 Implosion is the strategic placing
of explosive material and timing
of its detonation so that a
structure collapses on itself in a
matter of seconds, minimizing the
physical damage to its immediate
surroundings.
 The technique weakens or
removes critical supports so that
the building can no longer
withstand the force of gravity and
falls under its own weight.
Strategic implosion
 Pre-blast Considerations
 The design may include pre-weakening of the structure, the
strategy in placement of the explosives and time delay so that
the building will collapse in a safe manner.
 Pre-weakening of the structure may include cutting out a
portion of the shear walls and other structural elements.
 A test blast may be conducted to verify the strength of the
structural member and to fine tune the explosive design.
 Protection of the adjacent properties and habitats is also an
important consideration.
 Pre-weakening of the structure may include cutting out a
portion of the shear walls and other structural elements.
 A test blast may be conducted to verify the strength of the
structural member and to fine tune the explosive design.
 Protection of the adjacent properties and habitats is also an
important consideration.
Process of Implosion
Post-Demolition
Test Blast:
Before carrying out the actual blasting, a test blast, in ordered
to ascertain the efficiency of explosive & detonators.
Wrapping of holes:
The wrapping of holes is done to ensure that due to explosion
of charges the debris does not fly in air. For this purpose, the
holes were covered with gunny bags and iron net after
placement of explosive and detonators.
Ballasting:
Ballasting of Charges / Explosives work are carried out in a
controlled manner such that there will be a time gap of 1/100
second between two successive blasts. The trigger of charges
is done in such a control manner so that the noise pollution
and air pollution should be minimum.
Falling of structure:
Once central support/column will be destroyed and adjoining
columns will be weakened, due to its gravity the entire mass
will come down on its footprints
CONCLUSION
 It can be concluded that demolishing/imploding the
building structure will prove very useful, economical
and quickest for reconstruction.
 Leads to a safe and controlled demolition for the
occupants and neighbourhood.
 Development in techniques allows rapid demolition
with no harm to the environment.
REFERENCES
 http://www.implosionworld.com/history.html
 www.wikipedia.com
 http://archsd.gov.hk/media/11640/demolition_e2004
.pdf
 http://wiki.iricen.gov.in/doku/lib/exe/fetch.php?medi
a=m%E0%A4%BEr%E0%A5%8Dc_march_2013:a
chuta_rao.pdf
 http://www.concreteconstruction.net/Images/Demoli
tion%20of%20Concrete%20Structures_tcm45-
341335.pdf
THANK YOU

More Related Content

What's hot

What's hot (20)

Demolition of a building
Demolition of a buildingDemolition of a building
Demolition of a building
 
Ila's ppt on demolition
Ila's ppt on demolitionIla's ppt on demolition
Ila's ppt on demolition
 
Demolition of building
Demolition of building Demolition of building
Demolition of building
 
Building demolition techniques and methods
Building demolition techniques and methodsBuilding demolition techniques and methods
Building demolition techniques and methods
 
DEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUESDEMOLITION AND DISMANTLING TECHNIQUES
DEMOLITION AND DISMANTLING TECHNIQUES
 
Demolition of buildings
Demolition of buildingsDemolition of buildings
Demolition of buildings
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
DEMOLITION OF BUILDING
DEMOLITION OF BUILDINGDEMOLITION OF BUILDING
DEMOLITION OF BUILDING
 
Techniques for Demolition of Structure
Techniques for Demolition of StructureTechniques for Demolition of Structure
Techniques for Demolition of Structure
 
Demolition pptx
Demolition pptxDemolition pptx
Demolition pptx
 
DEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORKDEMOLITION & DISMANTLING OF WORK
DEMOLITION & DISMANTLING OF WORK
 
Introduction to demolition
Introduction to demolitionIntroduction to demolition
Introduction to demolition
 
Demolition of Structure ppt.pptx
Demolition of Structure ppt.pptxDemolition of Structure ppt.pptx
Demolition of Structure ppt.pptx
 
Demolition work of existing building
Demolition work of existing buildingDemolition work of existing building
Demolition work of existing building
 
BCT Mod 4 demolition of structure
BCT Mod 4 demolition of structureBCT Mod 4 demolition of structure
BCT Mod 4 demolition of structure
 
Building Construction 1: project 1
Building Construction 1: project 1Building Construction 1: project 1
Building Construction 1: project 1
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Prestressed concrete
Prestressed concretePrestressed concrete
Prestressed concrete
 
Pile and pile driving equipments
Pile and pile driving equipmentsPile and pile driving equipments
Pile and pile driving equipments
 
Pre-stressed Concrete
Pre-stressed ConcretePre-stressed Concrete
Pre-stressed Concrete
 

Similar to DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

Tata blue scope roof maintenance procedure
Tata blue scope roof maintenance procedureTata blue scope roof maintenance procedure
Tata blue scope roof maintenance procedure
Prudhvi raj
 

Similar to DEMOLITION OF STRUCTURE BY ABHINAV RAWAT (20)

Syed Naireen.
Syed Naireen.Syed Naireen.
Syed Naireen.
 
BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)BCT Mod 4 demolition of structure (Updated)
BCT Mod 4 demolition of structure (Updated)
 
Rehabilitation of structures,Method of Demolition of Structures
Rehabilitation of  structures,Method of Demolition of  StructuresRehabilitation of  structures,Method of Demolition of  Structures
Rehabilitation of structures,Method of Demolition of Structures
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structures
 
Techniques behind demolition of structures
Techniques behind demolition of structuresTechniques behind demolition of structures
Techniques behind demolition of structures
 
Demolition of BUILDING.pptx
Demolition of BUILDING.pptxDemolition of BUILDING.pptx
Demolition of BUILDING.pptx
 
Study of Safety in Demolition of Buildings
Study of Safety in Demolition of BuildingsStudy of Safety in Demolition of Buildings
Study of Safety in Demolition of Buildings
 
Demolition of building
Demolition of buildingDemolition of building
Demolition of building
 
Demolishing of concrete structures
Demolishing of concrete structuresDemolishing of concrete structures
Demolishing of concrete structures
 
DEMOLITION OF BUILDING 2.pptx
DEMOLITION OF BUILDING 2.pptxDEMOLITION OF BUILDING 2.pptx
DEMOLITION OF BUILDING 2.pptx
 
Demolition of building and blasting equipment
Demolition of building and blasting equipmentDemolition of building and blasting equipment
Demolition of building and blasting equipment
 
DOC pramod .pptx
DOC pramod .pptxDOC pramod .pptx
DOC pramod .pptx
 
Demolition.pptx
Demolition.pptxDemolition.pptx
Demolition.pptx
 
Lecture_all.pdf
Lecture_all.pdfLecture_all.pdf
Lecture_all.pdf
 
advanced constructiion technologies
advanced constructiion technologiesadvanced constructiion technologies
advanced constructiion technologies
 
Innovation in construction industry
Innovation in construction industryInnovation in construction industry
Innovation in construction industry
 
Building Service Chapter 4
Building Service Chapter 4Building Service Chapter 4
Building Service Chapter 4
 
Tata blue scope roof maintenance procedure
Tata blue scope roof maintenance procedureTata blue scope roof maintenance procedure
Tata blue scope roof maintenance procedure
 
Special structure
Special structureSpecial structure
Special structure
 
BLAST RESISTANT STRUCTURES
BLAST RESISTANT STRUCTURESBLAST RESISTANT STRUCTURES
BLAST RESISTANT STRUCTURES
 

Recently uploaded

XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
ssuser89054b
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
Epec Engineered Technologies
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
9953056974 Low Rate Call Girls In Saket, Delhi NCR
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
HenryBriggs2
 

Recently uploaded (20)

Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
Navigating Complexity: The Role of Trusted Partners and VIAS3D in Dassault Sy...
 
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced LoadsFEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
FEA Based Level 3 Assessment of Deformed Tanks with Fluid Induced Loads
 
School management system project Report.pdf
School management system project Report.pdfSchool management system project Report.pdf
School management system project Report.pdf
 
Introduction to Serverless with AWS Lambda
Introduction to Serverless with AWS LambdaIntroduction to Serverless with AWS Lambda
Introduction to Serverless with AWS Lambda
 
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
XXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXXX
 
Standard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power PlayStandard vs Custom Battery Packs - Decoding the Power Play
Standard vs Custom Battery Packs - Decoding the Power Play
 
Bridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptxBridge Jacking Design Sample Calculation.pptx
Bridge Jacking Design Sample Calculation.pptx
 
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKARHAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
HAND TOOLS USED AT ELECTRONICS WORK PRESENTED BY KOUSTAV SARKAR
 
Air Compressor reciprocating single stage
Air Compressor reciprocating single stageAir Compressor reciprocating single stage
Air Compressor reciprocating single stage
 
A Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna MunicipalityA Study of Urban Area Plan for Pabna Municipality
A Study of Urban Area Plan for Pabna Municipality
 
Computer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to ComputersComputer Lecture 01.pptxIntroduction to Computers
Computer Lecture 01.pptxIntroduction to Computers
 
Thermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.pptThermal Engineering -unit - III & IV.ppt
Thermal Engineering -unit - III & IV.ppt
 
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best ServiceTamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
Tamil Call Girls Bhayandar WhatsApp +91-9930687706, Best Service
 
Generative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPTGenerative AI or GenAI technology based PPT
Generative AI or GenAI technology based PPT
 
Unleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leapUnleashing the Power of the SORA AI lastest leap
Unleashing the Power of the SORA AI lastest leap
 
Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086Minimum and Maximum Modes of microprocessor 8086
Minimum and Maximum Modes of microprocessor 8086
 
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
Call Girls in South Ex (delhi) call me [🔝9953056974🔝] escort service 24X7
 
Engineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planesEngineering Drawing focus on projection of planes
Engineering Drawing focus on projection of planes
 
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
scipt v1.pptxcxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxxx...
 
Hostel management system project report..pdf
Hostel management system project report..pdfHostel management system project report..pdf
Hostel management system project report..pdf
 

DEMOLITION OF STRUCTURE BY ABHINAV RAWAT

  • 2. INDEX I. Introduction II. History III. Objectives IV. Steps before Demolition V. Demolition sequence VI. Methods of Demolition
  • 3. I. INTRODUCTION  Demolition is bringing down the building and other structures safely.  The demolition of structure with the help of explosives is called as implosion.  The main objective for demolition may be the age of the structure.  Methods of demolition depends upon the type of structure, height and surrounding structures.
  • 4. Demolition of a building
  • 5. II. HISTORY  Historians generally agree that the first true "explosive" was black powder, which was developed around the 13th century.  The first recorded use of black powder for demolition purposes appears to have occurred in the early 1600s, when quarries in Hungary began using it for rock blasting.  Black powder was put to use in the tin mines of England, and Switzerland adopted blasting technology for road construction.  Throughout the 1930s, structural explosive demolition was overseen by engineers working directly for large dynamite manufacturers.
  • 6. III. OBJECTIVES  Prevention damaging the neighbourhood environment.  Repair of damaged structures.  Construction of other structure at that previously constructed site.  Provides safety for the occupants in the building.
  • 7. IV. STEPS BEFORE DEMOLITION 1. Surveying 2. Removal of hazardous materials 3. Preparation of plan 4. Safety measures
  • 8. 1. Surveying: The building survey should cover following:  The construction materials.  The existing use and, if possible, the past uses of the building prior to demolition.  Adjoining pedestrian and vehicular traffic conditions.  The sensitivity of neighbourhood with respect to noise, dust, vibration and traffic impact.  Available site area to allow on-site sorting of building debris.
  • 9. 2. Removal of hazardous materials: Asbestos Containing Material  In the case when asbestos containing material are discovered, specialist contractor shall be employed to remove such asbestos containing material. The asbestos waste should be handled, stored and disposed of as chemical waste in accordance with the Waste Disposal Regulation. Soil Contamination Material  In the case when possible soil contamination material is present, specialist shall be employed to prepare soil contamination test proposal and submit such proposal to the Environmental Protection Department for comment. Asbestos Material Soil Contamination
  • 10. 3. Preparation of plan:  A plan showing location of the building to be demolished, sections of the slopes with ground level contours and detailed topography, ground removal and backfilling, distances of adjacent structures from the building to be demolished.  A layout plan of all floors of the building to be demolished, with adequate sections.  A plan showing the procedure for the demolition of the building.  A plan showing the proposed shoring and temporary support to be provided to the building to be demolished.  In the case when powered mechanical plants and equipment are used, a plan showing the route of movement of powered mechanical plants and equipment.
  • 11.
  • 12.
  • 13. 4. Safety measures: Training and Communication:  Demolition workers, including plant or equipment operators, shall go through proper job safety training and be informed of the potential hazards by attending training sessions as well as on- the-job training. Equipment Maintenance:  All equipment shall be tested and examined before use. They shall be properly stored and maintained. The equipment shall be inspected daily and results of the inspection shall be recorded accordingly.
  • 14. Electrical Safety  A properly connected power source from a local electric utility supplier or a mobile electricity generator shall be utilized in demolition sites. Fire  All flammable goods shall be removed from site unless they are necessary for the works involved. Any remaining flammable goods shall be stored in proper storage facilities. All furniture, timber, doors, etc. shall be removed before any welding work is performed. Fire fighting appliances shall be provided and maintained in working conditions.
  • 16. V. DEMOLITION SEQUENCE  All cantilevered structures, verandas and features attached to the external walls shall first be demolished prior to demolition of main building.  When demolishing the roof structure, all lift machine rooms and water tanks at high level shall be demolished in “top down” sequence to the main roof level.  Floor beams shall be demolished in the order of cantilevered beams, secondary beams and then main beams.  Columns and load bearing walls shall be demolished after removal of beams on top.  If site conditions permit, the first floor slab directly above the ground floor may be demolished by machine standing on ground.
  • 17.  Demolition of the floor slabs shall begin at mid span and work towards the supporting beams.
  • 18.  Floor beams shall be demolished in the order of cantilevered beams, secondary beams and then main beams.  Wire and winch shall be used to secure the cross beam to other structural members.  The concrete is first broken away at both ends near its column supports to expose the reinforcement.  Reinforcement shall be then cut to partially drop the beam and the brought down with wire.
  • 19.  Secure the column by wire and winch to existing structure.  Pre-weakening at the bottom of column: 1) Break away the concrete to expose the reinforcing bars. 2) Cut the reinforcing bars at the exterior half of the column. Cutting shall be performed immediately prior to pulling.  Pulling down the column in a controlled motion.
  • 20. VI. METHODS OF DEMOLITION: A. Ball and crane B. Dismantling C. Pneumatic and hydraulic breaker D. Pressure bursting E. Explosives
  • 21. A. Ball and crane  This is one of the oldest and most commonly used methods for building demolition. A crane uses a wrecking ball, weighing up to 6120 kg, which is either dropped onto or swung into the element to be demolished.  The ball is made from forged steel, which means the steel is not cast into a mould in a molten state. It is formed under very high pressure while the steel is red hot (soft but not molten) to compress and to strengthen it.  Concrete members can be broken into small pieces, but secondary cutting of reinforcing may be necessary. Wrecking ball at rest Swinging the wrecking ball
  • 22.
  • 23.
  • 24.  Advantages: 1) To demolish roofs and other horizontal spans. 2) The wrecking balls are still used when demolition may not be possible due to local environmental issues or asbestos/lead building content. 1) It demands a great deal of skill from the crane operator. 2) The height of a building that can be demolished is limited by crane size and working room; however, buildings as high as 20 stories have been demolished. 3) The breakup process can cause considerable dust, vibration and noise which may be objectionable.  Advantages and Disadvantages of Ball and Crane method: Advantages Disadvantages
  • 25. B. Dismantling  Selective or complete demolition of concrete structures is possible by cutting elements and then removing them with a crane.  The cutting process may be by sawing, water jetting or thermal lance.  Because the surface of the cut concrete is smooth and relatively regular, these methods have particular application when the objective is partial demolition, for instance in the creation of openings in walls and slabs. Dismantling a beam
  • 26.  Cutting with a water jet minimizes dust and eliminates vibration and fire hazards. An abrasive and water-catching system is required to clean up during the jetting process.  Hydro demolition uses a high pressure supersonic water jet, that penetrates the pores and cracks of the concrete and builds up an internal pressure. When this pressure exceeds the tensile strength of the concrete, the concrete breaks.  The water jet can be used not only for cutting straight lines but also contours, a useful feature for cutting access manholes. Water Jet cutting
  • 27.  A thermal lance is created by packing a seamless mild steel tube with low carbon rods and passing oxygen through the tube.  While this method eliminates vibration and dust problems, it creates other hazards associated with smoke and fire danger.  Whether sawing, jetting or lancing is used to dismantle the structure or its components, each element must be safely lowered to the ground. Thermal Lance Sawing method
  • 28. 1) Dismantlement of building components, specifically for re- use, recycling, and waste management. 2) Reducing disposal costs where waste collection, hauling or disposal is supported by the tax base. 3) Building components that are dismantled will need to be stored in a secure, dry location. This will protect them from water damage and theft. 1) The amount of time and cost of labor are the main drawbacks. 2) Harvesting materials from a structure can take weeks, whereas demolition may be completed in roughly a day. 3) Toxic waste such as asbestos sheets and lead paint have no resale value so they are discarded.  Advantages and Disadvantages of Dismantling method: Advantages Disadvantages
  • 29. C. Pneumatic and hydraulic breaker  A common piece of equipment used for demolishing bridge decks, foundations and pavements is a hydraulically or pneumatically operated, boom-mounted breaker.  The advantages of a machine mounted breaker may include a telescoping boom for easy reach and, remote control operation and underwater demolition capabilities  Some of the smaller remote- controlled machines can be lifted through window openings and used inside a building to demolish floors and walls.  Productivity can vary greatly depending on hammer size, type of concrete, amount of reinforcing and working conditions.
  • 30. Pneumatic hammer  A jackhammer is a pneumatic or electro- mechanical tool that combines a hammer directly with a chisel.  Hand-held jackhammers are typically powered by compressed air, but some use electric motors. Electric powered tools come in a variety of sizes from about 12 lbs - 65 lbs. They require an external power source, but do not require a compressor.
  • 31. Hydraulic breaker  A hydraulic jackhammer, typically much larger than portable ones, may be fitted to mechanical excavators or backhoes and is widely used for roadwork, quarrying and general demolition or construction groundwork.  They are used in mines where there is an explosion risk since they lack any high-power electrical circuitry that might cause a triggering spark. The jackhammer is connected with hydraulic hoses to a portable hydraulic power pack: either a petrol or diesel engine driving a hydraulic pump
  • 32. 1) The hydraulic breakers have tremendous power output also means they are the most power efficient, getting the most work out of the available energy. 2) A properly used and maintained hydraulic machine can last for a long time. 3) Pneumatic breakers are simpler tools with fewer moving parts, requiring less maintenance. 1) They require power, fuel or battery for their work. 2) They tend to be the most expensive types. 3) They require an external power source.  Advantages and Disadvantages of Pressure Bursting method: Advantages Disadvantages
  • 33. D. Pressure bursting  Pressure bursting can be used in cases where relatively quiet, dust- free, controlled demolition is preferred.  Both mechanical and chemical pressure bursting split the concrete, either with a splitting machine operating on hydraulic pressure provided by a motor in the case of mechanical bursting, or through the insertion of an expansive slurry into a pre-determined pattern of boreholes in the case of chemical bursting.  The split concrete is then easily removed, either by hand or by crane.  Both methods work by applying lateral forces against the inside of holes drilled into the concrete. Pressure bursting
  • 34. E. Explosives  Introduction  In the controlled demolition industry, building implosion is the strategic placing of explosive material and timing of its detonation so that a structure collapses on itself in a matter of seconds, minimizing the physical damage to its immediate surroundings.  Despite its terminology, building implosion also includes the controlled demolition of other structures, such as bridges, smokestacks, towers, and tunnels.  Numerous small explosives, strategically placed within the structure, are used to catalyze the collapse. Nitro- glycerine, dynamite, or other explosives are used to shatter reinforced concrete supports. RDX-based explosive compounds expand at a very high rate of speed, up to 27,000 feet per second (8,230 meters per second)
  • 36.  Blasting methods employ rapidly expanding gases confined within a series of boreholes to produce controlled fractures which provide for easy concrete removal.  For the demolition of concrete structures it is usual to drill holes at a predetermined angle into the concrete to be removed.  Implosion is the strategic placing of explosive material and timing of its detonation so that a structure collapses on itself in a matter of seconds, minimizing the physical damage to its immediate surroundings.  The technique weakens or removes critical supports so that the building can no longer withstand the force of gravity and falls under its own weight. Strategic implosion
  • 37.  Pre-blast Considerations  The design may include pre-weakening of the structure, the strategy in placement of the explosives and time delay so that the building will collapse in a safe manner.  Pre-weakening of the structure may include cutting out a portion of the shear walls and other structural elements.  A test blast may be conducted to verify the strength of the structural member and to fine tune the explosive design.  Protection of the adjacent properties and habitats is also an important consideration.
  • 38.  Pre-weakening of the structure may include cutting out a portion of the shear walls and other structural elements.  A test blast may be conducted to verify the strength of the structural member and to fine tune the explosive design.  Protection of the adjacent properties and habitats is also an important consideration.
  • 41. Test Blast: Before carrying out the actual blasting, a test blast, in ordered to ascertain the efficiency of explosive & detonators.
  • 42. Wrapping of holes: The wrapping of holes is done to ensure that due to explosion of charges the debris does not fly in air. For this purpose, the holes were covered with gunny bags and iron net after placement of explosive and detonators.
  • 43. Ballasting: Ballasting of Charges / Explosives work are carried out in a controlled manner such that there will be a time gap of 1/100 second between two successive blasts. The trigger of charges is done in such a control manner so that the noise pollution and air pollution should be minimum. Falling of structure: Once central support/column will be destroyed and adjoining columns will be weakened, due to its gravity the entire mass will come down on its footprints
  • 44. CONCLUSION  It can be concluded that demolishing/imploding the building structure will prove very useful, economical and quickest for reconstruction.  Leads to a safe and controlled demolition for the occupants and neighbourhood.  Development in techniques allows rapid demolition with no harm to the environment.
  • 45. REFERENCES  http://www.implosionworld.com/history.html  www.wikipedia.com  http://archsd.gov.hk/media/11640/demolition_e2004 .pdf  http://wiki.iricen.gov.in/doku/lib/exe/fetch.php?medi a=m%E0%A4%BEr%E0%A5%8Dc_march_2013:a chuta_rao.pdf  http://www.concreteconstruction.net/Images/Demoli tion%20of%20Concrete%20Structures_tcm45- 341335.pdf