Interactive Powerpoint_How to Master effective communication
Project management
1. WELLCOME TO MY PRESENTATION
on
Project Management
Sm Mahmud Wali
ID: 142-35-736
2. The SC Web portal will impro0ve the online experience
of Employees by delivering online service to satisfy
their specific needs.
Web Portal for Smith Consulting
3. Plan in Written
1. Analyzes Demand
2. Environment Set Up
3. Web pages development
4. Add administrative data
5. Training Employee
6. Testing
7. Review system
8. Finalizing
4. Duration & Dependency
Project Start – 01/03/2016
Project Finish -10/06/0216
Activity Day Duration Dependency
1. Analyzes demand 9 days -
2. Environment setup 5 days Task – 1
3.Web pages development 42 days Task – 2
4. Add administrative data 12 days Task – 3
5.Training employee 14 days Task - 2
6.Testing 10 days Task – 3,4
7. Review system 7 days Task – 6
8. Finalizing 3 days Task - 7
6. Objectives of Activities
Analyzes Demand : Under standing problem and collect
requirement.
Environment setup : Setup software, database, server etc.
Web pages development : Start web programming step by step for
web platform.
Add administrative data : Enter all business data to the system.
Training employee :Training employer for run and control the
system.
Review system : review full process.
Finalizing :Closing project.