SlideShare a Scribd company logo
1 of 8
by
Prof . V. V. Sasane (Assistant Professor)
Department of Civil Engineering
Sanjivani College of Engineering, Kopargaon, 423603
Subject: - Environmental Engineering-II
B.E. Civil
Sanjivani Rural Education Society’s
Sanjivani College of Engineering, Kopargaon, 423603.
An Autonomous Institute Affiliated to Savitribai Phule Pune University, Pune
ISO 9001-2015 Certified, Accredited by NAAC (A Grade)
UNIT-V: Onsite Sanitation Treatment System
5.4: Treatment and Disposal of Sludge
Content
• Method to Treat and Dispose of Sludge
• Thickening or concentration
• Digestion or stabilization
 Conditioning
 Dewatering
 Drying
• Incineration or thermal reduction
• Ultimate disposal
Sludge Conditioning
• Sledge conditioning is mainly to improve its dewatering characteristics. The two methods
most commonly used for sludge conditioning are
• Chemical conditioning
• Heat treatment
• Chemical conditioning:
It is the process of adding certain chemicals to the sludge which result in coagulation of solid
and release of absorb water;
• Heat treatment:
In this process sludge heated for a short period of time under pressure. As a result sludge
sterilized, deodorized, and is dewatered readily on vacuum filter.
Sludge Dewatering
• Sludge dewatering is a physical unit operation used to reduce the moisture content of the sludge. It is
carried out for one or more of the following reason:
• 1. The cost of the trucking sludge becomes substantially lower when volume is reduced by the
dewatering.
• 2. Dewatered sludge is generally is here to handle then thickened or liquid sludge.
• 3. Dewatered sludge have more calorific value due to removal of excess moisture.
• 4. Dewatering provide odourless and non perishable sludge.
• 5. Landfilling of the water reduces leachate production.
• The dewatering of digested sludge is a complete by either by one year drawing to open sludge drying
bed three mechanical method: 1. Air drying 2. Open sludge drying bed 3. Mechanical method
Open Sludge Drying Beds
• This method of dewatering and drying the sludge is
especially suitable for those location where temperature
are higher similar to the one prevailing in our country.
• The method consists of applying the sludge on specially
prepared open beds of land.
• A typical cross section of sludge drying bed is shown in
figure. %he sludge drying bed are usually consists of
bottom layer of gravel of uniform size over which is laid
clean sand
• Open jointed tiled underdrain are laid in the gravel layer
to provide positive drainage as the liquid pass through
the sand and gravel.
• Underdrains are made of vitrified clay pipes of at least
10 cm diameter laid with open joint.
• Underdrains are placed not more than 6 metre apart
around underdrain graded gravel is placed in layer upto 30
cm with a minimum of 15cm about the top of the under
trains.
• Atleast 3 cm of the top layer should consist of gravel of 3 to
6 mm size clean sand of effective size 0.5 to 0.75 mm and
uniformity coefficient not greater than 4 is placed over the
gravel depth of the sand may vary from 20 to 30 cm.
• The finished sand surface should be level.
• The drying beds are commonly 6 to 8 m wide and 30 to 45
m long.
• Multiple discharge points should be used with large sludge
bed to reduce the length of the wet sludge travel
• In order to have a feasibility in operations beds should be at
least 2 in number.
• The sludge inlet to the drying bed have minimum diameter 20 cm
terminating at least 30 cm above the sand surface.
• When digested sludge is deposited on well drained bed of sand and
gravel, the dissolved gases tends to buoy up and float the solid leaving
a clear liquid at the bottom which drains through the sand rapidly.
• The major portion of the liquid drains off in few hour after which
drying commences by evaporation.
• The sludge cakes shrinks producing cracks which accelerate
evaporation from the sludge surface. The dried sludge cakes can be
removed by the showel or fork when the moisture content is less than
70%.
• Some send cling to the bottom of the sludge cake result in reduction of
sand death, when this depth reduces to 10 cm; clean course sand used
to replenished the original death of the bed
4. Onsite sanitation system and disposal of sludge slide series (4) treatment and disposal of sludge

More Related Content

What's hot (20)

Physical Unit Operations
Physical Unit OperationsPhysical Unit Operations
Physical Unit Operations
 
Water Treatment Method- Sedimentation
Water Treatment Method- SedimentationWater Treatment Method- Sedimentation
Water Treatment Method- Sedimentation
 
Module VI Rural Sanitation
Module VI Rural SanitationModule VI Rural Sanitation
Module VI Rural Sanitation
 
Water filtration plant
Water filtration plantWater filtration plant
Water filtration plant
 
Water treatment 2013 14 (2)
Water treatment 2013 14 (2)Water treatment 2013 14 (2)
Water treatment 2013 14 (2)
 
Filtration/slow sand filter
Filtration/slow sand filterFiltration/slow sand filter
Filtration/slow sand filter
 
PC202: Sand Filters
PC202: Sand FiltersPC202: Sand Filters
PC202: Sand Filters
 
Unit 3
Unit 3Unit 3
Unit 3
 
L 24 filtration
L 24 filtrationL 24 filtration
L 24 filtration
 
Septic tank
Septic tankSeptic tank
Septic tank
 
Troubules in rapid sand filters
Troubules in rapid sand filtersTroubules in rapid sand filters
Troubules in rapid sand filters
 
08 filtration
08 filtration08 filtration
08 filtration
 
Water Supply and Distribution of Water
Water Supply and Distribution of WaterWater Supply and Distribution of Water
Water Supply and Distribution of Water
 
Sewage Treatment: Primary Treatment
Sewage Treatment: Primary TreatmentSewage Treatment: Primary Treatment
Sewage Treatment: Primary Treatment
 
Sanitaion methods & technologies
Sanitaion methods & technologiesSanitaion methods & technologies
Sanitaion methods & technologies
 
SEDIMENTATION
SEDIMENTATIONSEDIMENTATION
SEDIMENTATION
 
L 13 grit chamber
L 13 grit chamberL 13 grit chamber
L 13 grit chamber
 
Filter study by vivek dwivedi
Filter study by vivek dwivediFilter study by vivek dwivedi
Filter study by vivek dwivedi
 
Filtration in water treatment
Filtration in water treatmentFiltration in water treatment
Filtration in water treatment
 
ENVIRONMENTAL ENGINEERING & POLLUTION CONTROL
ENVIRONMENTAL ENGINEERING & POLLUTION CONTROLENVIRONMENTAL ENGINEERING & POLLUTION CONTROL
ENVIRONMENTAL ENGINEERING & POLLUTION CONTROL
 

Similar to 4. Onsite sanitation system and disposal of sludge slide series (4) treatment and disposal of sludge

5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTUVATSAL PATEL
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsKHUSHBU SHAH
 
Control of ground water in excavation
Control of ground water in excavation Control of ground water in excavation
Control of ground water in excavation Aamir Patni
 
Phase separation
Phase separationPhase separation
Phase separationZobaerRony
 
Dust control measures
Dust control measuresDust control measures
Dust control measuresSafdar Ali
 
Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...A Makwana
 
Rate of extraction of water (RR&S)
 Rate of extraction of water (RR&S)  Rate of extraction of water (RR&S)
Rate of extraction of water (RR&S) RAMPRASAD KUMAWAT
 
Sludge Thickening and the process of ppt
Sludge Thickening and the process of pptSludge Thickening and the process of ppt
Sludge Thickening and the process of ppt0o24680p
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptxCarolTumaneng
 
Prevention & suppression of dust
Prevention & suppression of dustPrevention & suppression of dust
Prevention & suppression of dustAbhinandan Bedua
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniquesjamali husain
 
24. PRODUCER GAS CLEANING METHODS.pptx
24. PRODUCER GAS CLEANING METHODS.pptx24. PRODUCER GAS CLEANING METHODS.pptx
24. PRODUCER GAS CLEANING METHODS.pptxRENERGISTICS
 
Chapter 3 aggregates (part-2)
Chapter 3  aggregates (part-2)Chapter 3  aggregates (part-2)
Chapter 3 aggregates (part-2)Manoj Sharma
 
UNIT -II Treatment of water- aeration and sedimentation.ppt
UNIT -II  Treatment of water- aeration and sedimentation.pptUNIT -II  Treatment of water- aeration and sedimentation.ppt
UNIT -II Treatment of water- aeration and sedimentation.pptmadhukarjadhav10
 
Waste water treatment plant
Waste water treatment plantWaste water treatment plant
Waste water treatment plantAldrin Thambi R
 

Similar to 4. Onsite sanitation system and disposal of sludge slide series (4) treatment and disposal of sludge (20)

5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
5. CONTROL OF GROUND WATER IN EXCAVATION (ACE) 2160601 GTU
 
Chapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavationsChapter 4 control of ground water in excavations
Chapter 4 control of ground water in excavations
 
Control of ground water in excavation
Control of ground water in excavation Control of ground water in excavation
Control of ground water in excavation
 
Water treatment
Water treatmentWater treatment
Water treatment
 
Properties of Sand
Properties of SandProperties of Sand
Properties of Sand
 
Phase separation
Phase separationPhase separation
Phase separation
 
Dust control measures
Dust control measuresDust control measures
Dust control measures
 
Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...Control of ground water in excavations_Advanced Construction Technology (Seme...
Control of ground water in excavations_Advanced Construction Technology (Seme...
 
Rate of extraction of water (RR&S)
 Rate of extraction of water (RR&S)  Rate of extraction of water (RR&S)
Rate of extraction of water (RR&S)
 
Sludge Thickening and the process of ppt
Sludge Thickening and the process of pptSludge Thickening and the process of ppt
Sludge Thickening and the process of ppt
 
dewateringtechniques 2.pptx
dewateringtechniques 2.pptxdewateringtechniques 2.pptx
dewateringtechniques 2.pptx
 
Prevention & suppression of dust
Prevention & suppression of dustPrevention & suppression of dust
Prevention & suppression of dust
 
Dewatering techniques
Dewatering techniquesDewatering techniques
Dewatering techniques
 
Low Cost Sanitation Systems
Low Cost Sanitation SystemsLow Cost Sanitation Systems
Low Cost Sanitation Systems
 
24. PRODUCER GAS CLEANING METHODS.pptx
24. PRODUCER GAS CLEANING METHODS.pptx24. PRODUCER GAS CLEANING METHODS.pptx
24. PRODUCER GAS CLEANING METHODS.pptx
 
BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4BCT Module 5 ground water excavation PART 4
BCT Module 5 ground water excavation PART 4
 
Chapter 3 aggregates (part-2)
Chapter 3  aggregates (part-2)Chapter 3  aggregates (part-2)
Chapter 3 aggregates (part-2)
 
UNIT -II Treatment of water- aeration and sedimentation.ppt
UNIT -II  Treatment of water- aeration and sedimentation.pptUNIT -II  Treatment of water- aeration and sedimentation.ppt
UNIT -II Treatment of water- aeration and sedimentation.ppt
 
Waste water treatment plant
Waste water treatment plantWaste water treatment plant
Waste water treatment plant
 
Sludge Dewatering
Sludge DewateringSludge Dewatering
Sludge Dewatering
 

More from vvsasane

Geographical Indication.pptx
Geographical Indication.pptxGeographical Indication.pptx
Geographical Indication.pptxvvsasane
 
IPR Unit 2 Part 2 Patenting Procedure.ppt
IPR Unit 2 Part 2 Patenting  Procedure.pptIPR Unit 2 Part 2 Patenting  Procedure.ppt
IPR Unit 2 Part 2 Patenting Procedure.pptvvsasane
 
Unit-2 Part 1 Introduction to Patent.pptx
Unit-2 Part 1 Introduction to Patent.pptxUnit-2 Part 1 Introduction to Patent.pptx
Unit-2 Part 1 Introduction to Patent.pptxvvsasane
 
3. grit chamber
3. grit chamber3. grit chamber
3. grit chambervvsasane
 
2. screen chamber
 2. screen chamber 2. screen chamber
2. screen chambervvsasane
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tenderingvvsasane
 

More from vvsasane (6)

Geographical Indication.pptx
Geographical Indication.pptxGeographical Indication.pptx
Geographical Indication.pptx
 
IPR Unit 2 Part 2 Patenting Procedure.ppt
IPR Unit 2 Part 2 Patenting  Procedure.pptIPR Unit 2 Part 2 Patenting  Procedure.ppt
IPR Unit 2 Part 2 Patenting Procedure.ppt
 
Unit-2 Part 1 Introduction to Patent.pptx
Unit-2 Part 1 Introduction to Patent.pptxUnit-2 Part 1 Introduction to Patent.pptx
Unit-2 Part 1 Introduction to Patent.pptx
 
3. grit chamber
3. grit chamber3. grit chamber
3. grit chamber
 
2. screen chamber
 2. screen chamber 2. screen chamber
2. screen chamber
 
Tenders and procedure of tendering
Tenders and procedure of tenderingTenders and procedure of tendering
Tenders and procedure of tendering
 

Recently uploaded

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxDeepakSakkari2
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024Mark Billinghurst
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile servicerehmti665
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxbritheesh05
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfAsst.prof M.Gokilavani
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxvipinkmenon1
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSCAESB
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionDr.Costas Sachpazis
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130Suhani Kapoor
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2RajaP95
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZTE
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learningmisbanausheenparvam
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...VICTOR MAESTRE RAMIREZ
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.eptoze12
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )Tsuyoshi Horigome
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AIabhishek36461
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerAnamika Sarkar
 

Recently uploaded (20)

Biology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptxBiology for Computer Engineers Course Handout.pptx
Biology for Computer Engineers Course Handout.pptx
 
IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024IVE Industry Focused Event - Defence Sector 2024
IVE Industry Focused Event - Defence Sector 2024
 
Call Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile serviceCall Girls Delhi {Jodhpur} 9711199012 high profile service
Call Girls Delhi {Jodhpur} 9711199012 high profile service
 
Artificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptxArtificial-Intelligence-in-Electronics (K).pptx
Artificial-Intelligence-in-Electronics (K).pptx
 
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdfCCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
CCS355 Neural Network & Deep Learning UNIT III notes and Question bank .pdf
 
Introduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptxIntroduction to Microprocesso programming and interfacing.pptx
Introduction to Microprocesso programming and interfacing.pptx
 
GDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentationGDSC ASEB Gen AI study jams presentation
GDSC ASEB Gen AI study jams presentation
 
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective IntroductionSachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
Sachpazis Costas: Geotechnical Engineering: A student's Perspective Introduction
 
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
VIP Call Girls Service Hitech City Hyderabad Call +91-8250192130
 
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2HARMONY IN THE HUMAN BEING - Unit-II UHV-2
HARMONY IN THE HUMAN BEING - Unit-II UHV-2
 
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
ZXCTN 5804 / ZTE PTN / ZTE POTN / ZTE 5804 PTN / ZTE POTN 5804 ( 100/200 GE Z...
 
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
VICTOR MAESTRE RAMIREZ - Planetary Defender on NASA's Double Asteroid Redirec...
 
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Serviceyoung call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
young call girls in Rajiv Chowk🔝 9953056974 🔝 Delhi escort Service
 
chaitra-1.pptx fake news detection using machine learning
chaitra-1.pptx  fake news detection using machine learningchaitra-1.pptx  fake news detection using machine learning
chaitra-1.pptx fake news detection using machine learning
 
Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...Software and Systems Engineering Standards: Verification and Validation of Sy...
Software and Systems Engineering Standards: Verification and Validation of Sy...
 
Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.Oxy acetylene welding presentation note.
Oxy acetylene welding presentation note.
 
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptxExploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
Exploring_Network_Security_with_JA3_by_Rakesh Seal.pptx
 
SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )SPICE PARK APR2024 ( 6,793 SPICE Models )
SPICE PARK APR2024 ( 6,793 SPICE Models )
 
Past, Present and Future of Generative AI
Past, Present and Future of Generative AIPast, Present and Future of Generative AI
Past, Present and Future of Generative AI
 
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube ExchangerStudy on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
Study on Air-Water & Water-Water Heat Exchange in a Finned Tube Exchanger
 

4. Onsite sanitation system and disposal of sludge slide series (4) treatment and disposal of sludge

  • 1. by Prof . V. V. Sasane (Assistant Professor) Department of Civil Engineering Sanjivani College of Engineering, Kopargaon, 423603 Subject: - Environmental Engineering-II B.E. Civil Sanjivani Rural Education Society’s Sanjivani College of Engineering, Kopargaon, 423603. An Autonomous Institute Affiliated to Savitribai Phule Pune University, Pune ISO 9001-2015 Certified, Accredited by NAAC (A Grade) UNIT-V: Onsite Sanitation Treatment System 5.4: Treatment and Disposal of Sludge
  • 2. Content • Method to Treat and Dispose of Sludge • Thickening or concentration • Digestion or stabilization  Conditioning  Dewatering  Drying • Incineration or thermal reduction • Ultimate disposal
  • 3. Sludge Conditioning • Sledge conditioning is mainly to improve its dewatering characteristics. The two methods most commonly used for sludge conditioning are • Chemical conditioning • Heat treatment • Chemical conditioning: It is the process of adding certain chemicals to the sludge which result in coagulation of solid and release of absorb water; • Heat treatment: In this process sludge heated for a short period of time under pressure. As a result sludge sterilized, deodorized, and is dewatered readily on vacuum filter.
  • 4. Sludge Dewatering • Sludge dewatering is a physical unit operation used to reduce the moisture content of the sludge. It is carried out for one or more of the following reason: • 1. The cost of the trucking sludge becomes substantially lower when volume is reduced by the dewatering. • 2. Dewatered sludge is generally is here to handle then thickened or liquid sludge. • 3. Dewatered sludge have more calorific value due to removal of excess moisture. • 4. Dewatering provide odourless and non perishable sludge. • 5. Landfilling of the water reduces leachate production. • The dewatering of digested sludge is a complete by either by one year drawing to open sludge drying bed three mechanical method: 1. Air drying 2. Open sludge drying bed 3. Mechanical method
  • 5. Open Sludge Drying Beds • This method of dewatering and drying the sludge is especially suitable for those location where temperature are higher similar to the one prevailing in our country. • The method consists of applying the sludge on specially prepared open beds of land. • A typical cross section of sludge drying bed is shown in figure. %he sludge drying bed are usually consists of bottom layer of gravel of uniform size over which is laid clean sand • Open jointed tiled underdrain are laid in the gravel layer to provide positive drainage as the liquid pass through the sand and gravel. • Underdrains are made of vitrified clay pipes of at least 10 cm diameter laid with open joint.
  • 6. • Underdrains are placed not more than 6 metre apart around underdrain graded gravel is placed in layer upto 30 cm with a minimum of 15cm about the top of the under trains. • Atleast 3 cm of the top layer should consist of gravel of 3 to 6 mm size clean sand of effective size 0.5 to 0.75 mm and uniformity coefficient not greater than 4 is placed over the gravel depth of the sand may vary from 20 to 30 cm. • The finished sand surface should be level. • The drying beds are commonly 6 to 8 m wide and 30 to 45 m long. • Multiple discharge points should be used with large sludge bed to reduce the length of the wet sludge travel
  • 7. • In order to have a feasibility in operations beds should be at least 2 in number. • The sludge inlet to the drying bed have minimum diameter 20 cm terminating at least 30 cm above the sand surface. • When digested sludge is deposited on well drained bed of sand and gravel, the dissolved gases tends to buoy up and float the solid leaving a clear liquid at the bottom which drains through the sand rapidly. • The major portion of the liquid drains off in few hour after which drying commences by evaporation. • The sludge cakes shrinks producing cracks which accelerate evaporation from the sludge surface. The dried sludge cakes can be removed by the showel or fork when the moisture content is less than 70%. • Some send cling to the bottom of the sludge cake result in reduction of sand death, when this depth reduces to 10 cm; clean course sand used to replenished the original death of the bed