SlideShare a Scribd company logo
1 of 41
Slide 110/02/2012 Slide 1
Field Test Kits
and Hot Socket
Repair Kits
Prepared by John Greenewald, TESCO
The Eastern Specialty Company
for Nebraska Meter Conference
Wednesday, February 12, 2020
9:00 a.m. – 10:00 a.m.
Slide 2
Premise
• Over much of the 20th century, utilities, regulators and customers each
relied upon lab and field meter testing efforts which were primarily focused
upon the accuracy of the watt-hour meter and demand register.
• This focus is now changing with overwhelming deployment of electronic
meters and significant deployment of AMR and AMI meters throughout the
installed base in North America.
• The focus has now shifted to the metering installation as a whole and not
the accuracy of the meter.
Slide 2
Slide 3
Field Testing
Common Features and Common Sources of Concern
Electro Mechanical meters were
subject to registration errors caused
by mechanical issues with moving
parts resulting in either the loss of
revenue to the utility or over billing
for the customer. Some of the more
common problems were:
• Friction wear
• Gear mesh misalignment
• Retarding magnet failure
• Timing motors
Slide 3
Slide 4
Electronic Meters – new failure modes require new testing
and inspection methods
Electronic meters fail as do electro mechanical meters but differently
• Their overall life expectancy is not nearly the same
• Failure modes include drift (unexpected)
• Failure modes include catastrophic (expected)
• Failure modes include non-catastrophic but significant measurement error
modes
• Failure modes can include non-measurement issues which render the meter
ineffective or inaccurate for billing purposes.
Slide 4
Slide 5
Best Practices
• Residential vs Commercial
• Self-Contained vs Transformer Rated
• Follow the money and be as proactive as possible
Slide 5
Slide 6
• Double check the meter number, the location the test result and the meter record
• Perform a visual safety inspection of the site. This includes utility and customer equipment.
Things to look for include intact down ground on pole, properly attached enclosure,
unwanted voltage on enclosure, proper trimming and site tidiness (absence of discarded
seals, etc.)
• Visually inspect for energy diversions (intentional and not). This includes broken or missing
wires, jumpers, open test switch, unconnected wires and foreign objects on meters or other
metering equipment. Broken or missing wires can seriously cause the under measurement
of energy. A simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the
registration on either 3 element or 2 element metering, respectively.
• Visually check lightning arrestors and transformers for damage or leaks.
• Check for proper grounding and bonding of metering equipment. Poor grounding and
bonding practices may result in inaccurate measurements that go undetected for long
periods of time. Implementing a single point ground policy and practice can reduce or
eliminate this type of issue.
• Burden test CTs and voltage check PTs.
Potential Site Check List
Slide 6
Slide 7
• Verify service voltage.
• Check that the transformers are wired correctly.
• Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires,
loose connections, etc.
• Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs are not cross
wired. Be sure CTs are grounded in one location (test switch) only.
• Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps
using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage).
• Check rotation by closing in one phase at a time at the test switch and observing the phase meter for
forward rotation. If forward rotation is not observed measurements may be significantly impacted as
the phases are most likely cancelling each other out.
• Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing
compensation (line and/or transformer losses) the compensation should be verified either through
direct testing at the site or by examining recorded pulse data.
Potential Site Check List (cont)
Slide 7
Slide 8
• Verify metering vectors. Traditionally this has been done using instruments such as a circuit
analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and
values using meter manufacturer software or meter displays. Many of these desired values are
programmed into the meters Alternate/Utility display. Examining these values can provide much
information about the metering integrity. It may also assist in determining if unbalanced loads are
present and if CTs are sized properly. The vendor software generally has the ability to capture
both diagnostic and vector information electronically. These electronic records should be kept in
the meter shop for future comparisons.
• If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for
totalization they also should be verified vs. the known load on the meter.
• Verify meter information including meter multiplier, serial number, dials/decimals, Mp, Ke, Primary
Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on
measured/reported values.
• Verify CT shunts are all opened.
Potential Site Check List (cont)
Slide 8
Slide 9
Field Testing
• Accuracy Testing
• Meter Communications Performance
• Software & Firmware Verification
• Setting Verification
• Functional Testing
• Disconnect/Reconnect Functionality
and as left setting
• Tamper Verification
• Site Audits appropriate to the type
of meter
Slide 10
Field Test Kits
GA-50 Field Test Kit with
Resistive Load
Cat. 2200 Field Test Interface
Kit
Cat. 630 Closed-Link Field
Test Kit
Cat. 621 Field Test Kit
Cat. 2210 Desktop Test
Interface Station
Slide 11
Field Test Accessories
Cat. 1210 Pure Sine Wave
Inverter
Cat. 1043 10 Amp
Current Transformer
Burden Set
Cat. 1047 CT Ratio/ Burden
Tester
Cat. 1039 Safety Disconnect
Device
K-280 Socket Tester K-281 Socket Tester
Slide 12
This document provides sensitive information concerning a utility’s practices.
TESCO and Landis+Gyr provide this document upon request for utilities to
facilitate thoughtful internal discussions and to help utilities discuss hot-
socket concerns with local fire departments and answering media inquiries.
DO NOT provide this document directly to the public or media to avoid the
contents being misused or taken out of context.
Disclaimer – Sensitive Utility Information
Slide 13
The Issue
• Hot Sockets are not a new phenomenon. Virtually every meter man has pulled a meter with a
portion of the meter base around a blade melted and virtually every utility has been called to assist
in the investigation of a fire at a meter box.
• AMI deployments because of the volume of meters involved put a spot light on this issue.
– What causes a hot socket?
– Are the meters ever the cause of a meter box failure?
– What are the things to look for when inspecting an
existing meter installation?
– What are the best practices for handling potential hot
sockets?
• This presentation will cover the results of our lab
investigation into the sources for hot sockets, the
development of a fixture to simulate hot sockets,
the tests and data gleaned from hot sockets, and
a discussion of “best practices” regarding hot sockets.
• We will also cover new technology developed and patented by TESCO and L+G to use the meter
to sense a hot socket and forward an alarm in near real time to the head end system.
Slide 14
Why Do We Know Anything About
Hot Sockets?
• L+G has been investigating hot sockets and how to make their meters withstand hot socket
conditions for longer periods of time so the socket has a greater likelihood of being repaired prior to
catastrophic failure.
• L+G has also been investigating ways to utilize AMI communication to possibly alert head end
systems of hot socket incidences.
• TESCO has been fortunate enough to be involved in several meter deployments where we supplied
full time and part time meter engineers and project managers to our customer’s AMI deployment
teams. In this capacity we have been involved in evaluating hot socket issues and helping to
determine an appropriate response to actual or potential hot sockets.
• TESCO’s meter lab was contracted to develop a laboratory fixture that would simulate the various
features common to most hot sockets found in the field. TESCO was also contracted to develop test
protocols, gather data and benchmark various conditions and meters.
• TESCO has access to a large number of meters which have
been exposed to hot sockets both before and after
catastrophic failure as well as a limited number of sockets
that were hot sockets and did not yet fail catastrophically.
Slide 15
National Fire Prevention Association (NFPA) tracks sources of home electrical fires - 2013 report.
No NFPA data
1999-2001
Electrical Fires Generally Decreasing
Slide 16
610 fires/year in the
vicinity of the Meter or
Meter Box
Sources of Electrical Fires
Annualized Rate of Occurrence 2007-2011
Slide 17
• Approximately 141 million connected customers in the United
States with approximately 170 Million installed electric meters.
Using 610 fires at or near the meter per year yields 3.6 fires per
million meters per year without AMI deployments.
Electrical Fires Near the Meter
Annualized Rate of Occurrence 2007-2011
Slide 18
• Replacing a meter in an existing meter socket will weaken the
socket and if performed enough times this action will create a
hazardous condition. AMI deployments will increase the
incidence of hot sockets and meter fires unless precautionary
steps are taken as part of the meter deployment.
Electrical Fires Near the Meter
Annualized Rate of Occurrence 2007-2011
Slide 19
Searching for Hot Socket Sources
• Pitted and discolored meter blades
• Melted plastic around one or more of the
meter stabs (typically the plastic around
one stab is where the deformation starts)
• Pitted and discolored socket jaws
• Loss of spring tension in the socket jaws
Common Features and Common Sources of Concern
Slide 20
• Sprung/damaged jaw
• Loose wire termination at line or load
side jaw
• Meter blade beside and not into
socket jaw
• Worn line/load wire insulation arcing
over to grounded mounting box
• Total load exceeding socket capacity –
lots of older 100 amp services in the
field
What Are Likely Socket Concerns?
Slide 21
Tin plating on jaw “cooked”
Heat accelerates oxidation on lug wire
Note: Tin Melts at 232ºC (450ºF)
Hot Socket Causes – Sprung Jaws
Slide 22
Jaw completely separated - large gap resulting in poor connection
Example – “Sprung Jaw”
Slide 23
Hot Socket Simulation Fixture
Click to view video
Slide 24Slide 24
Slide 25
Expected & Unexpected Results
Expected:
• Hot Sockets are exactly that – hot sockets. The hot sockets are the source of the
problem and not hot meters.
• Electromechanical meters withstand hot sockets better than solid state meters
Unexpected:
• Current plays only a small role in how
quickly a meter will burn up. Meters were
burned up nearly as quickly at 3 amps, 30
amps, and 130 amps.
• Relatively small amounts of vibration can
be the catalyst in the beginning and
eventual catastrophic failure of a hot
socket. Note: Other catalysts include but
are not limited to power surges, debris,
humidity, salt water.
• Contact resistance plays no role in
creating a hot socket
And some newer solid state meters are
better than electromechanical meters.
Slide 26
Temperature Rise Data
Slide 27
Jaws with intermittent
connections will arc to
the meter blade resulting
in pitting on the blade.
Blade shows early signs
of arcing.
Tin Melts at 232ºC which
is lower than the 350ºC
base plate plastic.
Jaw to Blade Arcing
Slide 28
28
Tin burned off
Blade hole due to arcing
to jaw – Copper melts at
1040ºC (1984ºF)
AX-SD base thermoset
plastic melts at 960ºC
(1760ºF)
Severe Arcing Jaw to Blade
Slide 29
What Are the Necessary Ingredients
for a Hot Socket?
There are three necessary ingredients to create a hot socket (Note: We are
not suggesting that we have simulated or even understand all causes for all
hot sockets and meter related fires, but rather that we have simulated and
understand the causes behind most hot sockets and meter related fires):
• Loss of jaw tension in at least
one of the socket jaws.
• Vibration (or other catalyst
to initiate arcing)
• Minimal load present
Slide 30
Reviewing the Data and Learning From the
Data
• Repeated meter insertions degrades the tension in the socket jaws (see graph), but
not to dangerous levels
• Exposure to elevated temperatures rapidly degrades the socket jaw tension to
dangerous levels (see graph)
• Visual inspection will catch some but not all dangerous socket jaws
• Arcing creates the heat
• Exposure to elevated temperatures has a cumulative effect on the meter socket jaw
• Relatively small vibration can initiate arcing
Slide 31Slide 31
Slide 32
Field Inspection of Sockets
Best Practices
• Example field check list
– Gaps in meter socket jaws
– Discoloration of one jaw vs. the other three
– Signs of melted or deformed plastic on meter
base
– Pitting of either meter blade or socket jaw
– Loss of tension in meter socket jaws
– Check condition of wire insulation and
connections to meter jaws
– Check the overall condition of the box, socket,
meter and how they attach to each other and
the building.
– Look for signs of tampering
– Look for signs of water or debris inside of the
meter can
Slide 33
• Most AMI deployments utilize third party contractors to handle residential
and some self contained non-2S services.
• After to or prior to AMI deployments, Utility personnel typically see these
sockets
• Transformer rated meters typically handled by the meter service department
of the utility.
• Hot socket concerns with lever by-pass sockets used on 3-phase meters are
extremely rare.
Who Sees Hot Sockets?
Slide 34
• Easiest resolution is to replace the damaged jaw.
• Never try and repair a damaged jaw by simply “squeezing” the
damaged jaw with a pair of pliers or other tool. The metallurgical
properties of the jaw will not magically return and the jaws will
simply spread again as soon as a meter is put into the socket.
• If the other jaws are deemed to be in good repair, the box and
wiring are in good condition and appropriate Socket Blocks are
available to effect a repair, then replacing the damaged socket
block with a new one is the most expedient and cost effective
solution. If any of these conditions do not exist then replacing the
box is the best solution.
What Can Be Done Once a Hot
Docket Is Identified?
Slide 35
Hot Socket Equipment
Top: Cat. 300 Hot Socket Gap
Indicator; Right: Hot Socket Repair
Kit (Cat. 304-Basic; Cat. 305-Pro);
Below, left: Cat. 301 Socket Safety
Clip; Below, right: Cat. 302 Hot
Socket Gap Indicator Calibration
Fixture
Slide 36
Base Line Data Electro Mechanical Meters vs Solid State vs the Latest
Generation of Meters Designed with Hot Sockets in Mind
• At the start of our laboratory investigation the oldest electro mechanical
meters withstood hot sockets the best
• The latest vintage solid state meters withstood hot sockets the least.
• Over the course of the past twenty four months virtually every meter
manufacturer has begun to release 2S meters designed to withstand hot
sockets.
Slide 37
In Search of Hot Sockets
• The meter manufacturer’s and various electric utilities have also been looking at a
variety of ways to better sense hot sockets.
• Utilities who have deployed are looking for a set of alarms that when taken together
may give them a better idea that there is a hot socket
• Meter Manufacturers have worked on evaluating a variety of temperature levels to
send an alarm, disconnecting the meter if there are sustained elevated temperatures,
using increased impedance to signify a hot socket, improving the temperature sensors
and putting additional temperature sensors on the blades of the meters.
Slide 38
Finding a Hot Socket with a Meter – What is
Known and Keys to These New Technologies
1. Temperature Sensing – sensing the temperature at the metrology board and at the meter stab(s).
2. Impedance Sensing – detecting a change in impedance in the meter circuit.
3. Detecting the RF signature of a micro Arc with a near field sensor - Arcing emits broadband
energy in the form of radio waves. Launching radio waves requires a disturbance in the electric
and magnetic fields near where the arc occurs (the near-field space).
Slide 39
Summary of the Problem
• Hot sockets start with a loss of tension in at least one of the meter socket jaws. This
loss of tension can be from a variety of sources that start as early as improper
installation or even “tight sockets”.
• Loss of tension is necessary to create the initial micro-arcing conditions.
• Sockets with repeated meter exchanges observed to have higher incidence of hot
socket issues and “booting” a meter may spring jaws even more.
• Vibration appears to be the most common catalyst to the micro-arcing that creates
the initial heat in a “hot socket”.
• The meter must have some power, but current is not a significant factor in how
quickly or dramatically a hot socket occurs
• The effects of vibration and weakened jaw are cumulative
Slide 40
Summary of the Potential Solutions
• Meter Manufacturers have all been working on the design of their meters to better
withstand a hot socket. These new meters have better baseline performance than
even the older electro mechanical meters, but a hot socket will eventually burn up
even the most robust meter.
• Thorough visual inspections of all services when replacing a meter whether for AMI or
not
• Hot Socket Indicator inspection for all jaws. This is a non-invasive way to check that
the minimum safe holding force or greater is present in all socket jaws.
• Hot Socket clips. Allows for the meter tech to leave the service as safe or safer than
when the problem jaw has been identified.
• In Meter circuit for near real time detection and alarm to the head end allows the
utility to identify compromised jaws before they damage the meter and before they
become dangerous to the rate payer or tenant.
Slide 41
Questions and Discussion
John Greenewald
john.greenewald@tescometering.com
TESCO – The Eastern Specialty Company
Bristol, PA
215-785-2338
This presentation can also be found under Meter Conferences
and Schools on the TESCO website:
www.tescometering.com

More Related Content

What's hot

Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 
AMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsAMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...TESCO - The Eastern Specialty Company
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...TESCO - The Eastern Specialty Company
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationTESCO - The Eastern Specialty Company
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018TESCO - The Eastern Specialty Company
 
Instrumentation
InstrumentationInstrumentation
InstrumentationSharib Ali
 

What's hot (20)

Field Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best PracticesField Verification: Test Equipment and Best Practices
Field Verification: Test Equipment and Best Practices
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
 
Field Testing
Field TestingField Testing
Field Testing
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Hands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter TestingHands-On Transformer Rated Polyphase Meter Testing
Hands-On Transformer Rated Polyphase Meter Testing
 
DC Metering and Traceability
DC Metering and TraceabilityDC Metering and Traceability
DC Metering and Traceability
 
Meter Testing 101
Meter Testing 101Meter Testing 101
Meter Testing 101
 
Site Verification for Newer Employees
Site Verification for Newer EmployeesSite Verification for Newer Employees
Site Verification for Newer Employees
 
AMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering InstallationsAMI Site Verification - Protocols & Tools for Complex Metering Installations
AMI Site Verification - Protocols & Tools for Complex Metering Installations
 
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
Site Verification: Tools and Best Practices to Accurately Meter Complex, High...
 
Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability Standards - Accuracy, Precision & Traceability
Standards - Accuracy, Precision & Traceability
 
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
Instrument Transformers - Following the Money: Best Practices in a Post AMI W...
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site VerificationFundamentals of Transformer Rated Field Meter Testing and Site Verification
Fundamentals of Transformer Rated Field Meter Testing and Site Verification
 
21st Century Power Measurements
21st Century Power Measurements21st Century Power Measurements
21st Century Power Measurements
 
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
Electric Meter and Transformer Testing in an AMI World - AclaraConnect 2018
 
ANSI Standards & Updates
ANSI Standards & UpdatesANSI Standards & Updates
ANSI Standards & Updates
 
ANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing ChangesANSI C12.20 and Proposed Field Testing Changes
ANSI C12.20 and Proposed Field Testing Changes
 
Instrumentation
InstrumentationInstrumentation
Instrumentation
 

Similar to Field Test Kits and Hot Socket Repair Kits

Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsTESCO - The Eastern Specialty Company
 
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect BillingSite Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect BillingTESCO - The Eastern Specialty Company
 
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationFundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationTESCO - The Eastern Specialty Company
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023TESCO - The Eastern Specialty Company
 

Similar to Field Test Kits and Hot Socket Repair Kits (20)

Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Site Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering InstallationsSite Verification - Protocols & Tools for Complex Metering Installations
Site Verification - Protocols & Tools for Complex Metering Installations
 
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect BillingSite Inspections - Looking for Dangerous Installations or Incorrect Billing
Site Inspections - Looking for Dangerous Installations or Incorrect Billing
 
TESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI WorldTESCO Site Verification in a Pre and Post AMI World
TESCO Site Verification in a Pre and Post AMI World
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
 
Site Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket DetectionSite Verification for Self-Contained Hot Socket Detection
Site Verification for Self-Contained Hot Socket Detection
 
TechAdvantage 2017 Hot Socket Issues - Causes and Best Practices
TechAdvantage 2017 Hot Socket Issues - Causes and Best PracticesTechAdvantage 2017 Hot Socket Issues - Causes and Best Practices
TechAdvantage 2017 Hot Socket Issues - Causes and Best Practices
 
NYSEMEC 2017 Hot Socket Detector 10.11.17
NYSEMEC 2017 Hot Socket Detector 10.11.17NYSEMEC 2017 Hot Socket Detector 10.11.17
NYSEMEC 2017 Hot Socket Detector 10.11.17
 
Meter Operations During and After AMI Deployment
Meter Operations During and After AMI DeploymentMeter Operations During and After AMI Deployment
Meter Operations During and After AMI Deployment
 
Ny psc 2017 hot socket issues causes and best practices 1-26-17
Ny psc 2017 hot socket issues causes and best practices 1-26-17Ny psc 2017 hot socket issues causes and best practices 1-26-17
Ny psc 2017 hot socket issues causes and best practices 1-26-17
 
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site VerificationFundamentals of Transformer-Rated Field Meter Testing and Site Verification
Fundamentals of Transformer-Rated Field Meter Testing and Site Verification
 
Instrument Transformer Testing
Instrument Transformer TestingInstrument Transformer Testing
Instrument Transformer Testing
 
Hot Socket Issues - Causes & Best Practices
Hot Socket Issues - Causes & Best PracticesHot Socket Issues - Causes & Best Practices
Hot Socket Issues - Causes & Best Practices
 
Single Phase Meter Testing Overview
Single Phase Meter Testing OverviewSingle Phase Meter Testing Overview
Single Phase Meter Testing Overview
 
Safety Topics - Hot Socket Issues, Causes & Best Practices
Safety Topics - Hot Socket Issues, Causes & Best PracticesSafety Topics - Hot Socket Issues, Causes & Best Practices
Safety Topics - Hot Socket Issues, Causes & Best Practices
 
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
Instrument Transformer Testing in them Shop and Field_Tom Lawton 2023
 
Technotoy 7
Technotoy 7Technotoy 7
Technotoy 7
 
Instrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and FieldInstrument Transformer Testing in the Shop and Field
Instrument Transformer Testing in the Shop and Field
 
New Tools for a Next Generation of Metering - TESCO Solutions
New Tools for a Next Generation of Metering - TESCO SolutionsNew Tools for a Next Generation of Metering - TESCO Solutions
New Tools for a Next Generation of Metering - TESCO Solutions
 
TESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the FieldTESCO Tuesday: Meter Testing in the Field
TESCO Tuesday: Meter Testing in the Field
 

Recently uploaded

#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024BookNet Canada
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptxLBM Solutions
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Wonjun Hwang
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupFlorian Wilhelm
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDGMarianaLemus7
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsMemoori
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsHyundai Motor Group
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsPrecisely
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions
 

Recently uploaded (20)

#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
#StandardsGoals for 2024: What’s new for BISAC - Tech Forum 2024
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
The transition to renewables in India.pdf
The transition to renewables in India.pdfThe transition to renewables in India.pdf
The transition to renewables in India.pdf
 
Key Features Of Token Development (1).pptx
Key  Features Of Token  Development (1).pptxKey  Features Of Token  Development (1).pptx
Key Features Of Token Development (1).pptx
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
Bun (KitWorks Team Study 노별마루 발표 2024.4.22)
 
Streamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project SetupStreamlining Python Development: A Guide to a Modern Project Setup
Streamlining Python Development: A Guide to a Modern Project Setup
 
APIForce Zurich 5 April Automation LPDG
APIForce Zurich 5 April  Automation LPDGAPIForce Zurich 5 April  Automation LPDG
APIForce Zurich 5 April Automation LPDG
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
AI as an Interface for Commercial Buildings
AI as an Interface for Commercial BuildingsAI as an Interface for Commercial Buildings
AI as an Interface for Commercial Buildings
 
Pigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food ManufacturingPigging Solutions in Pet Food Manufacturing
Pigging Solutions in Pet Food Manufacturing
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power Systems
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
Pigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping ElbowsPigging Solutions Piggable Sweeping Elbows
Pigging Solutions Piggable Sweeping Elbows
 

Field Test Kits and Hot Socket Repair Kits

  • 1. Slide 110/02/2012 Slide 1 Field Test Kits and Hot Socket Repair Kits Prepared by John Greenewald, TESCO The Eastern Specialty Company for Nebraska Meter Conference Wednesday, February 12, 2020 9:00 a.m. – 10:00 a.m.
  • 2. Slide 2 Premise • Over much of the 20th century, utilities, regulators and customers each relied upon lab and field meter testing efforts which were primarily focused upon the accuracy of the watt-hour meter and demand register. • This focus is now changing with overwhelming deployment of electronic meters and significant deployment of AMR and AMI meters throughout the installed base in North America. • The focus has now shifted to the metering installation as a whole and not the accuracy of the meter. Slide 2
  • 3. Slide 3 Field Testing Common Features and Common Sources of Concern Electro Mechanical meters were subject to registration errors caused by mechanical issues with moving parts resulting in either the loss of revenue to the utility or over billing for the customer. Some of the more common problems were: • Friction wear • Gear mesh misalignment • Retarding magnet failure • Timing motors Slide 3
  • 4. Slide 4 Electronic Meters – new failure modes require new testing and inspection methods Electronic meters fail as do electro mechanical meters but differently • Their overall life expectancy is not nearly the same • Failure modes include drift (unexpected) • Failure modes include catastrophic (expected) • Failure modes include non-catastrophic but significant measurement error modes • Failure modes can include non-measurement issues which render the meter ineffective or inaccurate for billing purposes. Slide 4
  • 5. Slide 5 Best Practices • Residential vs Commercial • Self-Contained vs Transformer Rated • Follow the money and be as proactive as possible Slide 5
  • 6. Slide 6 • Double check the meter number, the location the test result and the meter record • Perform a visual safety inspection of the site. This includes utility and customer equipment. Things to look for include intact down ground on pole, properly attached enclosure, unwanted voltage on enclosure, proper trimming and site tidiness (absence of discarded seals, etc.) • Visually inspect for energy diversions (intentional and not). This includes broken or missing wires, jumpers, open test switch, unconnected wires and foreign objects on meters or other metering equipment. Broken or missing wires can seriously cause the under measurement of energy. A simple broken wire on a CT or VT can cause the loss of 1/3 to 1/2 of the registration on either 3 element or 2 element metering, respectively. • Visually check lightning arrestors and transformers for damage or leaks. • Check for proper grounding and bonding of metering equipment. Poor grounding and bonding practices may result in inaccurate measurements that go undetected for long periods of time. Implementing a single point ground policy and practice can reduce or eliminate this type of issue. • Burden test CTs and voltage check PTs. Potential Site Check List Slide 6
  • 7. Slide 7 • Verify service voltage. • Check that the transformers are wired correctly. • Verify condition of metering control wire. This includes looking for cracks in insulation, broken wires, loose connections, etc. • Compare the test switch wiring with the wiring at the CTs and VTs. Verify CTs and VTs are not cross wired. Be sure CTs are grounded in one location (test switch) only. • Check for bad test switch by examining voltage at the top and bottom of the switch. Also verify amps using amp probe on both sides of the test switch. Verify neutral connection to cabinet (voltage). • Check rotation by closing in one phase at a time at the test switch and observing the phase meter for forward rotation. If forward rotation is not observed measurements may be significantly impacted as the phases are most likely cancelling each other out. • Test meter for accuracy. Verify demand if applicable with observed load. If meter is performing compensation (line and/or transformer losses) the compensation should be verified either through direct testing at the site or by examining recorded pulse data. Potential Site Check List (cont) Slide 7
  • 8. Slide 8 • Verify metering vectors. Traditionally this has been done using instruments such as a circuit analyzer. Many solid state meters today can provide vector diagrams along with volt/amp/pf and values using meter manufacturer software or meter displays. Many of these desired values are programmed into the meters Alternate/Utility display. Examining these values can provide much information about the metering integrity. It may also assist in determining if unbalanced loads are present and if CTs are sized properly. The vendor software generally has the ability to capture both diagnostic and vector information electronically. These electronic records should be kept in the meter shop for future comparisons. • If metering is providing pulses/EOI pulse to customers, SCADA systems or other meters for totalization they also should be verified vs. the known load on the meter. • Verify meter information including meter multiplier, serial number, dials/decimals, Mp, Ke, Primary Kh, Kr and Rate. Errors in this type of information can also cause a adverse impact on measured/reported values. • Verify CT shunts are all opened. Potential Site Check List (cont) Slide 8
  • 9. Slide 9 Field Testing • Accuracy Testing • Meter Communications Performance • Software & Firmware Verification • Setting Verification • Functional Testing • Disconnect/Reconnect Functionality and as left setting • Tamper Verification • Site Audits appropriate to the type of meter
  • 10. Slide 10 Field Test Kits GA-50 Field Test Kit with Resistive Load Cat. 2200 Field Test Interface Kit Cat. 630 Closed-Link Field Test Kit Cat. 621 Field Test Kit Cat. 2210 Desktop Test Interface Station
  • 11. Slide 11 Field Test Accessories Cat. 1210 Pure Sine Wave Inverter Cat. 1043 10 Amp Current Transformer Burden Set Cat. 1047 CT Ratio/ Burden Tester Cat. 1039 Safety Disconnect Device K-280 Socket Tester K-281 Socket Tester
  • 12. Slide 12 This document provides sensitive information concerning a utility’s practices. TESCO and Landis+Gyr provide this document upon request for utilities to facilitate thoughtful internal discussions and to help utilities discuss hot- socket concerns with local fire departments and answering media inquiries. DO NOT provide this document directly to the public or media to avoid the contents being misused or taken out of context. Disclaimer – Sensitive Utility Information
  • 13. Slide 13 The Issue • Hot Sockets are not a new phenomenon. Virtually every meter man has pulled a meter with a portion of the meter base around a blade melted and virtually every utility has been called to assist in the investigation of a fire at a meter box. • AMI deployments because of the volume of meters involved put a spot light on this issue. – What causes a hot socket? – Are the meters ever the cause of a meter box failure? – What are the things to look for when inspecting an existing meter installation? – What are the best practices for handling potential hot sockets? • This presentation will cover the results of our lab investigation into the sources for hot sockets, the development of a fixture to simulate hot sockets, the tests and data gleaned from hot sockets, and a discussion of “best practices” regarding hot sockets. • We will also cover new technology developed and patented by TESCO and L+G to use the meter to sense a hot socket and forward an alarm in near real time to the head end system.
  • 14. Slide 14 Why Do We Know Anything About Hot Sockets? • L+G has been investigating hot sockets and how to make their meters withstand hot socket conditions for longer periods of time so the socket has a greater likelihood of being repaired prior to catastrophic failure. • L+G has also been investigating ways to utilize AMI communication to possibly alert head end systems of hot socket incidences. • TESCO has been fortunate enough to be involved in several meter deployments where we supplied full time and part time meter engineers and project managers to our customer’s AMI deployment teams. In this capacity we have been involved in evaluating hot socket issues and helping to determine an appropriate response to actual or potential hot sockets. • TESCO’s meter lab was contracted to develop a laboratory fixture that would simulate the various features common to most hot sockets found in the field. TESCO was also contracted to develop test protocols, gather data and benchmark various conditions and meters. • TESCO has access to a large number of meters which have been exposed to hot sockets both before and after catastrophic failure as well as a limited number of sockets that were hot sockets and did not yet fail catastrophically.
  • 15. Slide 15 National Fire Prevention Association (NFPA) tracks sources of home electrical fires - 2013 report. No NFPA data 1999-2001 Electrical Fires Generally Decreasing
  • 16. Slide 16 610 fires/year in the vicinity of the Meter or Meter Box Sources of Electrical Fires Annualized Rate of Occurrence 2007-2011
  • 17. Slide 17 • Approximately 141 million connected customers in the United States with approximately 170 Million installed electric meters. Using 610 fires at or near the meter per year yields 3.6 fires per million meters per year without AMI deployments. Electrical Fires Near the Meter Annualized Rate of Occurrence 2007-2011
  • 18. Slide 18 • Replacing a meter in an existing meter socket will weaken the socket and if performed enough times this action will create a hazardous condition. AMI deployments will increase the incidence of hot sockets and meter fires unless precautionary steps are taken as part of the meter deployment. Electrical Fires Near the Meter Annualized Rate of Occurrence 2007-2011
  • 19. Slide 19 Searching for Hot Socket Sources • Pitted and discolored meter blades • Melted plastic around one or more of the meter stabs (typically the plastic around one stab is where the deformation starts) • Pitted and discolored socket jaws • Loss of spring tension in the socket jaws Common Features and Common Sources of Concern
  • 20. Slide 20 • Sprung/damaged jaw • Loose wire termination at line or load side jaw • Meter blade beside and not into socket jaw • Worn line/load wire insulation arcing over to grounded mounting box • Total load exceeding socket capacity – lots of older 100 amp services in the field What Are Likely Socket Concerns?
  • 21. Slide 21 Tin plating on jaw “cooked” Heat accelerates oxidation on lug wire Note: Tin Melts at 232ºC (450ºF) Hot Socket Causes – Sprung Jaws
  • 22. Slide 22 Jaw completely separated - large gap resulting in poor connection Example – “Sprung Jaw”
  • 23. Slide 23 Hot Socket Simulation Fixture Click to view video
  • 25. Slide 25 Expected & Unexpected Results Expected: • Hot Sockets are exactly that – hot sockets. The hot sockets are the source of the problem and not hot meters. • Electromechanical meters withstand hot sockets better than solid state meters Unexpected: • Current plays only a small role in how quickly a meter will burn up. Meters were burned up nearly as quickly at 3 amps, 30 amps, and 130 amps. • Relatively small amounts of vibration can be the catalyst in the beginning and eventual catastrophic failure of a hot socket. Note: Other catalysts include but are not limited to power surges, debris, humidity, salt water. • Contact resistance plays no role in creating a hot socket And some newer solid state meters are better than electromechanical meters.
  • 27. Slide 27 Jaws with intermittent connections will arc to the meter blade resulting in pitting on the blade. Blade shows early signs of arcing. Tin Melts at 232ºC which is lower than the 350ºC base plate plastic. Jaw to Blade Arcing
  • 28. Slide 28 28 Tin burned off Blade hole due to arcing to jaw – Copper melts at 1040ºC (1984ºF) AX-SD base thermoset plastic melts at 960ºC (1760ºF) Severe Arcing Jaw to Blade
  • 29. Slide 29 What Are the Necessary Ingredients for a Hot Socket? There are three necessary ingredients to create a hot socket (Note: We are not suggesting that we have simulated or even understand all causes for all hot sockets and meter related fires, but rather that we have simulated and understand the causes behind most hot sockets and meter related fires): • Loss of jaw tension in at least one of the socket jaws. • Vibration (or other catalyst to initiate arcing) • Minimal load present
  • 30. Slide 30 Reviewing the Data and Learning From the Data • Repeated meter insertions degrades the tension in the socket jaws (see graph), but not to dangerous levels • Exposure to elevated temperatures rapidly degrades the socket jaw tension to dangerous levels (see graph) • Visual inspection will catch some but not all dangerous socket jaws • Arcing creates the heat • Exposure to elevated temperatures has a cumulative effect on the meter socket jaw • Relatively small vibration can initiate arcing
  • 32. Slide 32 Field Inspection of Sockets Best Practices • Example field check list – Gaps in meter socket jaws – Discoloration of one jaw vs. the other three – Signs of melted or deformed plastic on meter base – Pitting of either meter blade or socket jaw – Loss of tension in meter socket jaws – Check condition of wire insulation and connections to meter jaws – Check the overall condition of the box, socket, meter and how they attach to each other and the building. – Look for signs of tampering – Look for signs of water or debris inside of the meter can
  • 33. Slide 33 • Most AMI deployments utilize third party contractors to handle residential and some self contained non-2S services. • After to or prior to AMI deployments, Utility personnel typically see these sockets • Transformer rated meters typically handled by the meter service department of the utility. • Hot socket concerns with lever by-pass sockets used on 3-phase meters are extremely rare. Who Sees Hot Sockets?
  • 34. Slide 34 • Easiest resolution is to replace the damaged jaw. • Never try and repair a damaged jaw by simply “squeezing” the damaged jaw with a pair of pliers or other tool. The metallurgical properties of the jaw will not magically return and the jaws will simply spread again as soon as a meter is put into the socket. • If the other jaws are deemed to be in good repair, the box and wiring are in good condition and appropriate Socket Blocks are available to effect a repair, then replacing the damaged socket block with a new one is the most expedient and cost effective solution. If any of these conditions do not exist then replacing the box is the best solution. What Can Be Done Once a Hot Docket Is Identified?
  • 35. Slide 35 Hot Socket Equipment Top: Cat. 300 Hot Socket Gap Indicator; Right: Hot Socket Repair Kit (Cat. 304-Basic; Cat. 305-Pro); Below, left: Cat. 301 Socket Safety Clip; Below, right: Cat. 302 Hot Socket Gap Indicator Calibration Fixture
  • 36. Slide 36 Base Line Data Electro Mechanical Meters vs Solid State vs the Latest Generation of Meters Designed with Hot Sockets in Mind • At the start of our laboratory investigation the oldest electro mechanical meters withstood hot sockets the best • The latest vintage solid state meters withstood hot sockets the least. • Over the course of the past twenty four months virtually every meter manufacturer has begun to release 2S meters designed to withstand hot sockets.
  • 37. Slide 37 In Search of Hot Sockets • The meter manufacturer’s and various electric utilities have also been looking at a variety of ways to better sense hot sockets. • Utilities who have deployed are looking for a set of alarms that when taken together may give them a better idea that there is a hot socket • Meter Manufacturers have worked on evaluating a variety of temperature levels to send an alarm, disconnecting the meter if there are sustained elevated temperatures, using increased impedance to signify a hot socket, improving the temperature sensors and putting additional temperature sensors on the blades of the meters.
  • 38. Slide 38 Finding a Hot Socket with a Meter – What is Known and Keys to These New Technologies 1. Temperature Sensing – sensing the temperature at the metrology board and at the meter stab(s). 2. Impedance Sensing – detecting a change in impedance in the meter circuit. 3. Detecting the RF signature of a micro Arc with a near field sensor - Arcing emits broadband energy in the form of radio waves. Launching radio waves requires a disturbance in the electric and magnetic fields near where the arc occurs (the near-field space).
  • 39. Slide 39 Summary of the Problem • Hot sockets start with a loss of tension in at least one of the meter socket jaws. This loss of tension can be from a variety of sources that start as early as improper installation or even “tight sockets”. • Loss of tension is necessary to create the initial micro-arcing conditions. • Sockets with repeated meter exchanges observed to have higher incidence of hot socket issues and “booting” a meter may spring jaws even more. • Vibration appears to be the most common catalyst to the micro-arcing that creates the initial heat in a “hot socket”. • The meter must have some power, but current is not a significant factor in how quickly or dramatically a hot socket occurs • The effects of vibration and weakened jaw are cumulative
  • 40. Slide 40 Summary of the Potential Solutions • Meter Manufacturers have all been working on the design of their meters to better withstand a hot socket. These new meters have better baseline performance than even the older electro mechanical meters, but a hot socket will eventually burn up even the most robust meter. • Thorough visual inspections of all services when replacing a meter whether for AMI or not • Hot Socket Indicator inspection for all jaws. This is a non-invasive way to check that the minimum safe holding force or greater is present in all socket jaws. • Hot Socket clips. Allows for the meter tech to leave the service as safe or safer than when the problem jaw has been identified. • In Meter circuit for near real time detection and alarm to the head end allows the utility to identify compromised jaws before they damage the meter and before they become dangerous to the rate payer or tenant.
  • 41. Slide 41 Questions and Discussion John Greenewald john.greenewald@tescometering.com TESCO – The Eastern Specialty Company Bristol, PA 215-785-2338 This presentation can also be found under Meter Conferences and Schools on the TESCO website: www.tescometering.com