SlideShare a Scribd company logo
1 of 1
Download to read offline
SharePoint 2010 Products: Virtualization Process
Using Hyper-V technology to virtualize servers                                                                                                                                                              Requirements
  Hyper-V™ hardware virtualization uses software to create a virtual machine that resembles the resources of a physical                                                                                     Virtualization server (Hyper-V host)                                                                                                           SharePoint 2010 Products virtual machine
  computer. The virtual machine has its own operating system environment that is logically isolated from the virtualization (host)                                                                          Before you can deploy Microsoft® SharePoint® Server 2010 or Microsoft® SharePoint®                                                             Before you can deploy SharePoint Server 2010 or SharePoint Foundation 2010, you must
  server. By providing multiple virtual machines at once, this approach allows different versions of the operating system to run                                                                            Foundation 2010 on a Hyper-V™ virtual machine, you must meet the following                                                                     meet the following requirements:
  simultaneously on a single physical machine. It provides strong isolation between the (independent) running virtual machines.                                                                             requirements for the virtualization server (host):                                                                                            Operating system requirement:                                             Database requirement: 64-bit SQL
                                                                                                                                                                                                            Hardware requirements                                                           Operating system requirements                                 Windows Server 2008 or Windows                                            Server 2005 or 64-bit SQL Server 2008

 Benefits                                                                               Constraints                                                                                                         Processor: x64 compatible processor with
                                                                                                                                                                                                            Intel VT or AMD-V technology enabled.
                                                                                                                                                                                                                                                                                            We recommend that you use Windows
                                                                                                                                                                                                                                                                                            Server® 2008 R2 or Microsoft Hyper-V™
                                                                                                                                                                                                                                                                                                                                                          Server 2008 R2

                                                                                                                                                                                                                                                                                                                                                          SharePoint Server 2010 and SharePoint                                     For farm installations of SharePoint Server
                                                                                                                                                                                                            Hardware Data Execution Prevention (DEP)                                        Server 2008 R2 for virtualization servers.                                                                                              2010 and SharePoint Foundation 2010, you
  · Consolidates multiple, underutilized physical servers on a                          · Number of virtual machines cannot exceed the capacity of the                                                      available and enabled.                                                          These software versions provide significant
                                                                                                                                                                                                                                                                                                                                                          Foundation 2010 must be run on a 64-bit
                                                                                                                                                                                                                                                                                                                                                          edition of Windows Server 2008 with Service                               must be running 64-bit versions of Microsoft
    single host                                                                           virtualization server (host).                                                                                     Adequate physical resources, particularly                                       improvements in virtual core support, power                                                                                             SQL Server® 2005 or Microsoft SQL Server
  · Reduces cabling and peripheral requirements                                         · Virtual processor limit of four processor per virtual machine.                                                    cores, RAM, and high performance disks with                                     management, live migration, performance
                                                                                                                                                                                                                                                                                                                                                          Pack 2 (SP2) or Windows Server 2008 R2.
                                                                                                                                                                                                                                                                                                                                                                                                                                    2008 (each with the appropriate service packs
  · Reduces space requirements and power consumption.                                   · A clustered environment requires enough free resources on each host to                                            the capacity to support the virtual machines                                    (virtual drives and networking), and general                                                                                            and updates) on the database servers.
  · Increases flexibility, speed, and ease of server                                      enable live migration.                                                                                            that are hosted. This includes an allowance                                     system performance.                                           Resources
    deployment                                                                          · In a SharePoint 2010 Products environment you have to monitor the                                                 for resource overhead on the host.
                                                                                                                                                                                                                                                                                                                                                          Planning and architecture for SharePoint Server 2010 (http://go.microsoft.com/fwlink/?LinkID=89404)
                                                                                          virtualization host as well as the virtual farm servers.
                                                                                        · For capacity-planning purposes, only physical cores should be taken into                                                                                                                                                                                        Virtualization planning for SharePoint Server 2010 (http://go.microsoft.com/fwlink/?LinkId=194755)
                                                                                          account, not possible hardware threads.



   Virtualization stages                                                                                                                                                                                      Architecture examples                                                                                                                                                                      Analysis
                1 - Planning
    Purpose                                   Tools                                              Steps                                                                 The following physical and virtual                                Illustration key:
                                                                                                 ·    Determine business goals and objectives.                         architectures, which feature SharePoint
                                                                                                                                                                                                                                             Virtual machine layer                                                    WFE: Web server                                                  Do                                                                      Do not
    Before you can deploy, you must           The Microsoft Assessment and Planning (MAP)        ·    Identify the type of farm and farm elements                      Server 2010, are shown for the purposes of
    plan the virtualization solution that     Toolkit for Hyper-V                                                                                                      illustration and discussion only. For the
                                                                                                                                                                                                                                                                                                                      APP: Application server                 ·   Plan for the worst case scenario on the host server.                     ·   Take a snapshot of a running virtual machine in a
                                                                                                      that you want to virtualize.                                                                                                                                                                                    DB: Database server
                                                                                                                                                                                                                                                                                                                                                              ·   Monitor host and virtual machine health and                                  production environment.
    you want to deploy. It is critical that   (http://go.microsoft.com/fwlink/?LinkId=194756)    ·    Determine virtualization server                                  purpose of this model, domain controller and                                                                                                   CA: Central Administration
                                                                                                                                                                                                                                                                                                                                                                                                                                           ·   Install anything on the host root partition except the
    everyone clearly understands the                                                                                                                                   firewall servers are physical servers.                                                         Front-end        Database      Application      Query: Query component                      performance data on an ongoing basis.
                                                                                                      requirements.
    goals and objectives for                                                                                                                                                                                                                                          Web server        server         server         Crawl: Crawl component                  ·   Plan for redundancy and growth on each host.                                 operating system and Hyper-V.
                                                                                                                                                                                                                                                                                                                      HOST: Virtualization server             ·   Use the same operating system version and patch                          ·   Overcommit host CPU resources.
    virtualization. Determine the type of                                                        Output                                                                Physical machine and virtual machine                                  Physical machine layer                                                   DC: Domain controller                       level on the hosts and the virtual machines.                             ·   Assume that all server applications have the same
    farm that you want to deploy and its                                                         ·                                                                     resources are provided for the purpose of:
                                                                                                      Virtualization plan                                                                                                                                                                                             FS: Firewall server                     ·   Be aware of differences in server hardware -                                 capacity characteristics.
    purpose. For example, test and                                                               ·    Topology and resource requirements                               · Showing the relationship between a                                                                                                           LP: Logical processor                                                                                                ·   Use snapshots as a backup strategy.
                                                                                                                                                                                                                                                                                                                                                                  especially processor architectures
    quality assurance, authoring, or                                                             ·    A benchmark for evaluating outcome                                  virtualization server and its virtual                                                                                                       VP: Virtual processor
    publishing portal.                                                                                                                                                    machines.                                                                                                                                   n GB = Amount of RAM in GB
                                                                                                      against goals and objectives                                                                                                          Virtualization server     Cores (4) on     Database      Application
                                                                                                                                                                       · Showing the distribution of farm servers                                                     Hyper-V host      server         server
                                                                                                                                                                          across virtualization servers.
                2 - Evaluation
    Purpose                                   Expected duration and stability                    Steps                                                                                                                                                                                                 WFE
                                                                                                                                                                                                                                                                                                                                                                    Virtual machine                                                               Virtualization server
                                                                                                                                                                                                                                                                                                       CA                                                           Farm A or Farm B:                                                             For this phase, the physical computer can be a laptop
    Used to deploy SharePoint 2010            ·   Not a stable environment – no service-         ·    Create virtual machines.                                                    WFE                                                         WFE
                                                                                                                                                                                                                                                                                                       Search                                                       · Dual processor virtual machine.                                             or workstation that has enough memory to support a
                                                                                                                                                                                  CA                                                          CA
    Products in a virtual environment to          level agreement for users                      ·    Deploy a single server or a two-server                                                                                                                                                                                    2xVP                                · Use 4 GB of RAM for each virtual machine that hosts the                     single virtual machine or two virtual machines in a two-
                                                                                                                                                                                  Search                                                      Search
    see if virtualization is feasible         ·   Typically a throw-away solution                     farm.                                                                       DB                                                          DB
                                                                                                                                                                                                                                                                                                                                2 GB                                   database.                                                                  server deployment. A quad core physical machine is
                                                                                                                                                                                                         2xVP                                                                                                                                                       · Use 40 GB dynamic virtual hard disks.
                                                                                                 ·    Evaluate the solution by configuring                         Farm A                                                                                             Farm B
                                                                                                                                                                                                                                                                                                                                                                                                                                                  preferred, but not required.
                                                                                                                                                                                                         4 GB                                                                                                                                                       · Use the snapshot feature to keep a clean image of the operating
                                                                                                      SharePoint Server 2010 and enabling                                                                                                    2xVP
                                                                                                                                                                   Small farm                                                                                         Small farm                                                                                       system for redeploying SharePoint Server 2010.
                                                                                                      the services.                                                                                                                          4 GB                                                          DB
                                                                                                                                                                   Farm installed on a single server                                                                  Farm installed on two servers
                                                                                                 ·    Collect initial benchmark data on virtual                                                                                                                                                           2xVP
                                                                                                      machines and virtualization host. For                                                                                                                                                               4 GB
                                                                                                      example, CPU use, memory use, hard
                                                                                                      disk space.                                                                                                                                                                                                                                                       Analysis

    Characteristics                           Topology                                           Output                                                                                                                                                                                                                                                              Assuming that there is 8 GB of RAM on the physical computer:
                                                                                                                                                                                       2xLP                             4xLP                                                                       4xLP
                                                                                                                                                                                       8 GB                             8 GB                                                                       8 GB                                                              · Allow a 2-GB reserve for the operating system and Hyper-V
                                              For evaluation purposes, the topology is           Information that will enable you to:                                                                                                                                                                                                                                    overhead.
    Initial deployment of the solution is
                                              usually a single-server deployment or a            · Decide to continue.                                                                                                                                                                                                                                               This leaves less than 6 GB for the virtual machines.
    followed by testing and refining the
                                              small farm that has the database on a              · Implement refinements that are required
    solution.
                                              separate server.                                       for testing proof of concept.

                3 - Proof of concept (POC)
    Purpose                                   Expected duration and stability                    Steps                                                                                                                                                                                                                                                              Virtual machine                                                               Virtualization server
                                                                                                                                                                                                    WFE-1                                                                      WFE-1                               WFE-2
    Used to determine whether a partial       ·   Set up, reviewed, and then discarded           ·    Scale up virtualization server or add                                                         Query                                                                      Query                               Query                                            Small or medium farm with farm servers deployed across three tiers:           The CPU for the Farm A host is slightly
                                                                                                                                                                                                                                                                                                                                                                    · Dual processor virtual machines.                                            oversubscribed (4 LP : 6 VP), but the CPU for Farm B
    or full SharePoint 2010 Products          ·   Not a stable environment – no service-level         virtualization server.
                                                                                                                                                                                                    2xVP                                                                        2xVP                                2xVP                                            · 4 GB of RAM for each front-end Web server and each                          is oversubscribed (4 LP : 10 VP) at a higher rate,
    virtualization solution will meet             agreement for users                            ·    Create virtual machines with adequate                                                                                                                                                                         4 GB                                               application server, 8 GB of RAM for database server.                       which will degrade performance. The virtual machines
                                                                                                                                                                                                    4 GB                                                                        4 GB
    business needs and to determine an                                                                capacity for running a farm with more servers                                                                                                                                                                                                                 · Use three 30 GB dynamic virtual hard disk drives for all servers            in Farm B require 24 GB of RAM without an operating
    appropriate infrastructure plan.                                                                  and more features.                                                                                                                                                                                                                                               to deploy SharePoint Server on the drive topology that is                  system reserve or Hyper-V overhead.
                                                                                                 ·    Deploy farm.                                                                                  CA                                                                                 App-1                                 App-2                                     typically used for farm servers.
                                                                                                                                                                                                                                                                                                                                                                    · Use Hyper-V snapshots to capture the state of the virtual
    Characteristics                           Topology                                           ·    Expand scope of benchmark data to include                                                     Crawl                                                                              CA                                    Crawl
                                                                                                                                                                                                                                                                                                                                                                       machine before you deploy SharePoint Server.
                                                                                                      farm servers and virtualization servers.                                                      2xVP                                                                                2xVP                                2xVP                                    · For Farm B, dedicate one application server for the crawl
    Environments for the POC phase            In order to better illustrate functionality and    ·    Expand user base.                                   Farm A                                                                                                     Farm B             4 GB                                4 GB
                                                                                                                                                                                                    4 GB                                                                                                                                                               component.
    can be created by deploying new           usage flow for the POC phase, a typical
                                                                                                 ·    Determine how you will manage the farm and          Small farm                                                                                                 Medium farm
    farms or by scaling the farm used for     topology is three-tier small or medium farm.                                                                Farm servers                                                                                               Farm servers
                                                                                                      supporting infrastructure.
    evaluation. In either case, the goal of                                                      ·    Evaluate proof of concept.                          distributed across                                                                                         distributed across                                                                                 Analysis
    POC is to demonstrate that the            Use this topology and scale to refine the vision                                                            three tiers                               DB                                                               three tiers                DB
                                                                                                 ·    Refine goals and infrastructure requirements.
    planning solution is feasible and         for the production farm as well as gather farm                                                                                                        2xVP                                                                                        2xVP                                                                Performance is not the focus for POC; however, perceived poor performance can affect the desired results.
    should be pursued. There can be           server and virtualization performance data.                                                                                                           6 GB                                                                                        8 GB                                                                The options, in order of priority are:
    continuous development and                This is a good phase to start establishing a       Output                                                                                                                                                                                                                                                             · Host the virtual machines on two virtualization servers to accommodate CPU and RAM issues.
                                                                                                                                                                                                                                                                                                                                                                    · Use a virtualization server that has 8 cores and at least 32 GB of RAM.
    tailoring during this phase to refine     benchmark that can be refined later in the         ·    Updated virtualization plan                                                                                                                                                                                                                                   · Use multiple physical hard disk drives to host the virtual machine hard disk drives.
    the proof of concept.                     cycle.                                             ·    Updated topology and resource
                                                                                                      requirements                                                                          4xLP                                                                                        4xLP                                                                        We recommend two virtualization hosts for user acceptance testing and production environments. If you have the capability for POC,
                                                                                                                                                                                            16 GB
                                                                                                 ·    Updated virtualization server resource                                                                                                                                            32 GB                                                    HOST 2             we recommend that you implement this architecture before going on to the next phase.
                                                                                                      requirements
                                                                                                                                                                                                                                                                                                                                                                    Unless the virtualization hosts are only going to be used for POC, you should implement a virtual architecture that will carry through to
                                                                                                 ·    Preliminary operations plan                                                                                                                                                                                                                                   subsequent stages. Evaluate the number of host cores and RAM to ensure that you have room to scale up or scale out during the pilot.


                4 - Pilot
    Purpose                                   Expected duration and stability                    Steps                                                                            WFE-1                                         WFE-2
                                                                                                                                                                                                                                                                                                                                                                    Virtual machine                                                               Virtualization server
                                                                                                                                                                                                                                                               WFE-1                                                  WFE-2              WFE-3
    Used to test a solution on a small        ·   Limited time frame                              ·   Determine the number of virtualization servers                              Query                                         Query                          Query                                                  Query              Query                      For a pilot, the number of users taking part in the project is                For the Farm A environment, the memory
                                                                                                                                                                                                                                                                                                                                                                    typical higher than POC participants. As a result, user activity is
    scale.                                    ·   Limited service-level agreement for solution        that are required to support the pilot farm.                                                                                                                                                                                                                                                                                                requirements, without any memory committed to the
                                                                                                                                                                                     2xVP                                        2xVP                                2xVP                                                2xVP               2xVP                    higher, which is reflected in a higher number of page hits,                   operating system or Hyper-V, is 20 GB of RAM. You
                                                  readiness testing                               ·   Create virtual machines to support farm                                        4 GB                                        4 GB                                4 GB                                                4 GB               4 GB                    increased document storage, more search queries, and                          need a single host with at least 32 GB of RAM. In
    Pilots are used to test solution          ·   Production service-level agreement for              requirements that are identified in POC.                                                                                                                                                                                                                      increased time to crawl the database. A small or medium farm                  addition, continuing with a single quad core physical
    readiness, typically without using            production testing                              ·   Deploy the pilot farm.                                                                  CA                                                                                    App-1                                       App-2
                                                                                                                                                                                                                                                                                                                                                                    with farm servers deployed across three tiers still provides a                server results in a logical to virtual processor ratio of
    real data because the focus is on                                                             ·   Refine benchmark data for collection for farm                                           Crawl                                                                                 CA                                          Crawl
                                                                                                                                                                                                                                                                                                                                                                    reasonable environment for pilots.                                            8:10, which exceeds the recommended 1:1 ratio. A
    functional testing.                                                                                                                                                                                                                                                                                                                                             Farm A is a small farm that has:                                              higher ratio increases CPU overcommitment and will
                                                                                                      servers and virtualization server.                                                                                                                                                                                                                            · Two processors for all the servers except the database
                                                                                                                                                                                              2xVP                                                                                                                                                                                                                                                likely affect performance. If you plan to use this farm
                                                                                                  ·   Evaluate pilot.                                                                         4 GB
                                                                                                                                                                                                                                                                                    2xVP                                        2xVP
                                                                                                                                                                                                                                                                                                                                                                        server, which has four processors.                                        for user acceptance testing, you need to add more
                                                                                                                                                          Farm A                                                                                            Farm B                  4 GB                                        4 GB
    However, a pilot can also be used to                                                          ·   Refine goals and infrastructure requirements.                                                                                                                                                                                                                 · 4 GB of RAM for each front-end Web server and each                          RAM to the virtualization server.
    test for production characteristics by                                                        ·   Determine operations plan for supporting            Small farm                                                                                        Medium farm                                                                                                 application server, 8 GB of RAM for the database server.
    using real data and having the pilot                                                              virtualization server and farm servers. Identify    Farm servers distributed                                                                          Farm servers                                                                                            Continue to use three 40-GB hard disk configurations, but mix                 For the Farm B environment, Host-1:
                                                                                                                                                                                              DB                                                                                                                   DB-2                                             dynamic, fixed size, and pass through to gather IOPS data.
    users do actual work in the                                                                       tools and processes for monitoring at both
                                                                                                                                                          across three tiers                                                                                distributed across      DB-1                                                                                                                                                          · Available memory, without any committed
                                                                                                                                                                                                                                                            three tiers                                                                                                                                                                               memory, is 8 GB of RAM, which leaves room to
    environment. We recommend this                                                                    levels.                                                                                 4xVP                                                                                                                                                                  Farm B is a medium farm running on two virtualization hosts.
                                                                                                                                                                                                                                                                                    4xVP                           4xVP                                                                                                                               scale up a farm server.
    approach.                                                                                     ·   Implement processes and tools for migrating                                             8 GB
                                                                                                                                                                                                                                                                                    8 GB                           8 GB                                             The virtual machines are configured as follows:                               · The logical to virtual processor ration is 1:1, which
                                                                                                      virtual machines between virtualization                                                                                                                                                                                                                       · Two processors for all the servers except the database                          is good for performance, but adding another virtual
                                                                                                      servers.                                                                                                                                                                                                                                                           servers, which each have four processors.                                    machine would oversubscribe the host CPU.
                                                                                                                                                                                                                                                                                                                                                                    · All the servers have 4 GB of RAM, except the database
                                                                                                                                                                                                                                                                                                                                                                         servers, which have 8 GB of RAM each.                                    For the Farm B environment, Host-2:
    Characteristics                           Topology                                           Output                                                                                                                                                                                                                                                             · 4 GB RAM for each front-end Web server and each                             · Available memory, without any committed
                                                                                                                                                                                                                                                                            HOST-1                               HOST-2                                                  application server, 8 GB RAM for the database server.                        memory, is 4 GB of RAM, which leaves no room to
    A limited set of users has access to      Topologies will vary according to the planned      ·    Updated virtualization plan                                                                                                                                                                                                                                   Determine storage requirements and implement them for the                         scale up a farm server.
                                                                                                                                                                                      8xLP                                                                                  8xLP                                 8xLP                                               pilot so they can be tested and you can use the benchmarks for                · The logical to virtual processor ratio is 8:10, which
    the environment to test the               solution, the number of pilot users, and the       ·    Updated topology and resource requirements
                                                                                                                                                                                      24 GB                                                                                 24 GB                                24 GB                                              user acceptance testing.                                                          will reduce performance and leaves no capacity to
    functionality and performance of the      scope of functional and capacity management             for virtualization server and farm servers.
                                                                                                                                                                                                                                                                                                                                                                        Analysis                                                                      add another virtual machine.
    solution and infrastructure.              testing.                                           ·    Verify whether or not a fully virtualized
                                                                                                      environment can met SharePoint business and
                                                                                                                                                                                                                                                                                                                                                                    ·   Before you start the pilot, determine if the databases need to be mirrored for high availability. If so, deploy them on two hosts.
                                              Pilot environments are typically a scaled-              capacity management requirements                                                                                                                                                                                                                              ·   Review your benchmark data for database server performance to decide whether to continue with virtual database servers. If so,
                                              down, but representative version of the            ·    A refined operations plan that you can test                                                                                                                                                                                                                       you must determine which of the following storage solutions you want to implement and test: fixed size virtual hard disks or pass
                                              planned production environment.                         during the pilot. This plan includes backup and                                                                                                                                                                                                                   through to shared storage. If you are going to switch to physical database servers, do it before starting UAT.
                                                                                                      recovery, adding, removing, and moving virtual                                                                                                                                                                                                                ·   The logical to virtual processor ratio is higher than the recommended 1:1. You can proceed with oversubscribed CPUs on the
                                                                                                                                                                                                                                                                                                                                                                        virtualization hosts, recognizing that you must implement changes during UAT. We recommend that you make host adjustments
                                                                                                      machines.
                                                                                                                                                                                                                                                                                                                                                                        before you start acceptance testing.
                                                                                                                                                                                                                                                                                                                                                                    ·   Load a substantive subset of actual content before you start UAT.
                                                                                                                                                                                                                                                                                                                                                                    ·   Determine whether or not to continue on to the next phase using the same physical servers as well as the same physical and
                                                                                                                                                                                                                                                                                                                                                                        virtual architectures.

                5 - User acceptance test (UAT)
    Purpose                                   Expected duration and stability                    Steps                                                                                                                                                                                                                                                              Virtual machine                                                               Virtualization server
    A preproduction environment used          ·   Long-term availability – this is a stable      ·    Refine virtual machine distribution over            WFE-1                    WFE-2                     WFE-3                            WFE-1                 WFE-2                  WFE-3                            WFE-4               WFE-5
                                                                                                                                                                                                                                                                                                                                                                    During user acceptance testing there typically is a service-level
                                                                                                                                                                                                                                                                                                                                                                                                                                                  For the Farm A environment, HOST-1
                                                                                                                                                                                                                                                                                                                                                                    agreement. Ensure that:
    for testing solutions against a subset        preproduction environment.                          virtualization servers.                             Query                    Query                     Query                            Query                 Query                  Query                            Query               Query                                                                                             · Available memory, without committed memory, is 8
                                                                                                                                                                                                                                                                                                                                                                    · The farm servers are adequately sized and you can scale up
    or complete copy of production data.      ·   Limited service-level agreement for users.     ·    Scale up virtualization servers, scale out                                                                                                                                                                                                                        or scale out.
                                                                                                                                                                                                                                                                                                                                                                                                                                                      GB of RAM.
                                                                                                                                                         4xVP                      4xVP                      4xVP                             4xVP                   4xVP                   4xVP                            4xVP                 4xVP                                                                                             · The logical to virtual processor ratio is 8:16.
                                                                                                      farm servers, deploy farm servers on               12 GB                     12 GB                     12 GB                            8 GB                   8 GB                   8 GB                            8 GB                 8 GB               · You have a reasonable degree of high availability
                                                                                                                                                                                                                                                                                                                                                                                                                                                  For the Farm A environment, HOST-2
    Also used for validating the backups                                                              physical machines as appropriate.                                                                                                                                                                                                                                 implemented.
                                                                                                                                                                                                                                                                                                                                                                                                                                                  · Available memory, without committed memory, is 20
                                                                                                 ·    Deploy farm.                                                                                                                                                                                                                                                  · You have a backup and recovery strategy.
    or operational procedures.                                                                                                                                                                                                                                                                                                                                                                                                                        GB of RAM.
                                                                                                                                                                                                                                                                                                                                                                    · The virtual machines in Farm A and Farm B all have four
                                                                                                 ·    Implement operations plan along with in-                                                                                                                                                                                                                          virtual processors. The memory configurations are as follows:
                                                                                                                                                                                                                                                                                                                                                                                                                                                  · The logical to virtual processor ratio is 8:12.
                                              Topology                                                house or commercial monitoring product.                                                                            App-2
    Characteristics                                                                                                                                               App-1                                                  CA
                                                                                                                                                                                                                                                             App-1                   App-2                                App-3           App-4                         · Farm A: three front-end Web servers with 12 GB each, two
                                                                                                                                                                                                                                                                                                                                                                                                                                                  For the Farm B environment, HOST-1
                                                                                                 ·    Evaluate solution and operations plan.                                                                                                                 CA                      Crawl                                Crawl           CA                                 application servers with 8 GB each, and two database
    Topology should be as similar to                                                                                                                              CA                                                     Crawl                                                                                                                                                                                                                    · Available memory, without committed memory, is 16
                                              Topologies vary, and have been determined          ·    Test for capacity and performance.                                                                                                                                                                                                                                     servers, each with 32 GB of RAM.
                                                                                                                                                                                                                                                                                                                                                                                                                                                      GB of RAM.
    production environment as possible.       in the pilot phase. For acceptance testing, we                                                                        4xVP                                                 4xVP                                4xVP                    4xVP                                 4xVP             4xVP                         · Farm B: five front-end Web servers with 8 GB each, four
                                                                                                                                                                    8 GB                                                 8 GB                                16 GB                   16 GB                                16 GB            16 GB                                                                                                  · The logical to virtual processor ratio is 8:20.
                                              recommend that the farm servers be near the                                                                                                                                                                                                                                                                                    application servers with 16 GB each.
    Testers ensure that all solution                                                             Output                                                                                                                                                                                                                                                                                                                                           For the Farm B environment, HOST-2
    elements function as expected in          same scale as the production environment.                                                                                                                                                                                                                                                                                                                                                           · Available memory, without committed memory, is 24
    network and security conditions that                                                         ·    Revised virtual architecture.                                       DB-1                                               DB-2
                                                                                                                                                                                                                                                         Farm B                                                                                                                                                                                       GB of RAM.
                                                                                                                                                                          4xVP                                               4xVP                                                   DB-1                                 DB-2
    match the conditions of the               If load testing is the goal, then the virtual      ·    Updated operations plan.                           Farm A
                                                                                                                                                                                                                                                                                                                                                                                                                                                  · The logical to virtual processor ratio is 8:16.
                                                                                                                                                                          32 GB                                              32 GB                       Medium to large farm
    production environment.                   machine configurations should be identical to      ·    Implementation plan.                                                                                                                               Planned production
                                                                                                                                                         Medium farm
                                              the production environment and the                                                                                                                                                                         environment                                                                                                    Analysis
                                                                                                                                                         Planned production
                                              virtualization hosts should be the same as                                                                 environment
                                              the ones planned for production.                                                                                                                                                                                                                                                                                      The logical to virtual processor ratio is higher than the recommended 1:1. Both farms are seriously oversubscribed. We
                                                                                                                                                                                                                                                                                                                                                                    recommend that you address this issue before you start UAT. You can:
                                              The final production topology and farm server                                                                                                                                                                                                                                                                         · Scale back the virtual processor configuration on the front-end Web servers or application servers.
                                              configurations are tuned, refined, and                                                                                                                                                                HOST-1                                                                              HOST-2                      · Add additional hosts, shown in Farm A of the following production illustration.
                                                                                                                                                             HOST-1                                    HOST-2
                                                                                                                                                                                                                                                                                                                                                                    · Use hosts with more cores, shown in Farm B of the following production illustration.
                                              implemented by using the benchmarks                                                                                                                                                                                                              8xLP                        8xLP
                                                                                                                                                             8xLP                                        8xLP                                       8xLP                                       32 GB                       32 GB        8xLP
                                              obtained in preproduction testing.
                                                                                                                                                             72 GB                                       72 GB                                      72 GB                                                                               72 GB

                                                                                                                                                                                                                                                                                                          Database:
                                                                                                                                                                                                                                                                                                          Clustered or mirrored



                6 - Production
    Purpose                                   Expected duration and stability                    Steps                                                             HOST-2
                                                                                                                                                                                                                                                                                                                                                                    Virtual machine                                                               Virtualization server
                                                                                                                                                          WFE-1                   WFE-2                                WFE-3                           WFE-1                        WFE-2                           WFE-3                WFE-4
    This is the live environment              ·   Long-term availability – this should be a                                                               Query                   Query                                Query                           Query                        Query                           Query                Query                      The production environment typically matches that of the user                 The virtualization hosts for Farm A and Farm B
    that your users interact with.                stable environment.                            ·    Deploy production farm.                                                                                                                                                                                                                                       acceptance testing environment. In some cases it may reflect                  illustrate two approaches to increasing host capacity.
                                              ·   Full service-level agreement for users,        ·    Deploy services farm.                              4xVP                     4xVP                                 4xVP                             4xVP                         4xVP                            4xVP                 4xVP                      required changes that are a result of user acceptance testing.                Farm A uses four 8 core hosts, each with 64 GB of
                                                                                                                                                                                                                                                                                                                                                                    Farm A has the following virtual machine configurations:                      RAM. Host-3 only has one virtual machine, a crawl
                                                  appropriate to the solution and business       ·    Deploy production solution.                        16 GB                    16 GB                                16 GB                            8 GB                         8 GB                            8 GB                 8 GB
                                                                                                                                                                                                                                                                                                                                                                    · Three front-end Web servers, each with four processors and                  server; and there is capacity to add another four-
                                                  requirements.                                  ·    Implement operations plan.                                                                                                                                                                                                                                        16 GB of RAM                                                              processor virtual machine without oversubscribing
                                                                                                                                                                                                                                                                                                                                                                    · Two application servers, each with four processors. Central                 the CPU. In all cases, there is adequate memory to
                                                                                                                                                                 App-1                                       App-2                                                                                                                                                      Administration (CA) is installed on App-1, which has 16 GB of             scale up the virtual machines. The advantage of
                                                                                                                                                                                                                                                             App-1                   App-2                          App-3               App-4
    Characteristics                           Topology                                           Output                                                          CA                                          Crawl                                           CA                      Crawl                          Crawl               CA                              RAM. The Search Crawl component is installed on App-2,                    using four hosts is that you have the flexibility to
                                                                                                                                                                                                                              HOST-4                                                                                                                                    which has 32 GB of RAM. Note that Central Administration is               move virtual machines around on the hosts. The
    It is business critical, and              Topologies vary, and have been determined in       ·    Final operations plan                                       4xVP                                      4xVP
                                                                                                                                                                                                                                                                                                                                                                                                                                                  disadvantage is that you have twice as many
                                                                                                                                                                                                                                                             4xVP                    4xVP                            4xVP               4xVP                            also installed on App-2.
    appropriate service-level                 the pilot phase. For acceptance testing, we        ·    Implementation plan                                         16 GB                                     32 GB
                                                                                                                                                                                                                                                             16 GB                   16 GB                           16 GB              16 GB                       · The database servers are mirrored; each has four processors                 physical servers to manage.
    agreements are in place.                  recommend that the farm servers be near the                                                                                                                                                                                                                                                                               and 32 GB of RAM.
                                              same scale as the production environment.                                                                              DB-1                                                            DB-2                                                                                                                           Farm B has the following virtual machine configurations:                      Farm B uses two 16-core hosts, each with 64 GB of
                                                                                                                                                                                                                                                                                                                                                                    · Four front-end Web servers, each with four processors and 8                 RAM. The ratio of logical to virtual processors is 1:1
                                                                                                                                                                     4xVP                                                            4xVP               Farm B                                                                                                          GB of RAM (scale out rather than scale up).                               for both hosts. Adding an additional virtual machine
                                              If load testing is the goal, then the virtual                                                                          32 GB                       HOST-3                              32 GB                                                                                                                          · Four application servers, each with four processors and 16 GB               would oversubscribe either of the hosts, as would
                                              machine configurations should be identical to                                                                                                                                                             Large farm
                                                                                                                                                                                                                                                                                                                                                                        of RAM. Two servers are dedicated to crawl and the other two              moving a virtual machine from one host to the other.
                                                                                                                                                              HOST-1                                                                                    Planned production
                                              the production environment.                                                                                                                                                                               environment
                                                                                                                                                                                                                                                                                                                                                                        host CA.
                                                                                                                                                                                   Medium to large farm                                                                                                                                                             · The database servers are installed on physical machines.
                                                                                                                                                                    Farm A
                                              The final production topology and farm server                                                                                        Planned production environment
                                              configurations are tuned, refined, and                                                                                                                                                                                                                                                                                    Analysis
                                              implemented by using the benchmarks                                                                        8xLP                8xLP             8xLP                   8xLP                                                           16xLP                                               16xLP
                                              obtained in preproduction testing.                                                                         64 GB               64 GB            64 GB                  64 GB                                                          64 GB     8xLP                         8xLP         64 GB
                                                                                                                                                                                                                                                                                              32 GB                        32 GB                                    Oversubscribing a virtualization host in response to a performance issue or a failed virtual machine is acceptable as a
                                                                                                                                                                                                                                                                                                                                                                    short-term solution. The recommended approach is to ensure that you mitigate this scenario by having adequate host
                                                                                                                                                                                                                                                                                                                                                                    capacity before putting the farm into production. There are several ways to ensure that you have extra capacity on
                                                                                                                                                                                                                                                                                                                                                                    the hosts, such as:
                                                                                                                                                                                                                                                                                                          Database:                                                 · Deploy hosts with 16 or more processor cores.
                                                                                                                                                             HOST-1                HOST-2              HOST-3                HOST-4                                    HOST-1                             Clustered or mirrored                  HOST-2             · Add one or more 8-core hosts to the environment.
                                                                                                                                                                                                                                                                                                                                                                    · Consider deploying a dedicated services farm to offload services that have high resource requirements, such as

More Related Content

What's hot

Java EE Technical Keynote at JavaOne Latin America 2011
Java EE Technical Keynote at JavaOne Latin America 2011Java EE Technical Keynote at JavaOne Latin America 2011
Java EE Technical Keynote at JavaOne Latin America 2011Arun Gupta
 
WAS Support & Monitoring Tools
WAS Support & Monitoring ToolsWAS Support & Monitoring Tools
WAS Support & Monitoring ToolsRoyal Cyber Inc.
 
Building a Novell Data Synchronizer Connector: A Developer's Guide
Building a Novell Data Synchronizer Connector: A Developer's GuideBuilding a Novell Data Synchronizer Connector: A Developer's Guide
Building a Novell Data Synchronizer Connector: A Developer's GuideNovell
 
Managing Windows Server Systems For Midsize Organizations
Managing Windows Server Systems For Midsize OrganizationsManaging Windows Server Systems For Midsize Organizations
Managing Windows Server Systems For Midsize OrganizationsMicrosoft TechNet
 
Virtualization for Development
Virtualization for DevelopmentVirtualization for Development
Virtualization for Developmentelliando dias
 
Introduction to VMware Infrastructure
Introduction to VMware  Infrastructure  Introduction to VMware  Infrastructure
Introduction to VMware Infrastructure aktivfinger
 
Infraestructure WMWARE
Infraestructure  WMWAREInfraestructure  WMWARE
Infraestructure WMWAREaktivfinger
 
System Center 2012 ve Microsoft Cloud Senaryoları
System Center 2012 ve Microsoft Cloud SenaryolarıSystem Center 2012 ve Microsoft Cloud Senaryoları
System Center 2012 ve Microsoft Cloud SenaryolarıMustafa
 
Getting Started with ESXServer3iEmbedded
Getting Started with  ESXServer3iEmbedded  Getting Started with  ESXServer3iEmbedded
Getting Started with ESXServer3iEmbedded aktivfinger
 
LS11 SHOW202 - Enterprise 2.0 Hero - a Beginner's Guide to Installing IBM Lot...
LS11 SHOW202 - Enterprise 2.0 Hero - a Beginner's Guide to Installing IBM Lot...LS11 SHOW202 - Enterprise 2.0 Hero - a Beginner's Guide to Installing IBM Lot...
LS11 SHOW202 - Enterprise 2.0 Hero - a Beginner's Guide to Installing IBM Lot...Stuart McIntyre
 
Jfokus 2012 : The Java EE 7 Platform: Developing for the Cloud
Jfokus 2012 : The Java EE 7 Platform: Developing for the CloudJfokus 2012 : The Java EE 7 Platform: Developing for the Cloud
Jfokus 2012 : The Java EE 7 Platform: Developing for the CloudArun Gupta
 

What's hot (13)

Java EE Technical Keynote at JavaOne Latin America 2011
Java EE Technical Keynote at JavaOne Latin America 2011Java EE Technical Keynote at JavaOne Latin America 2011
Java EE Technical Keynote at JavaOne Latin America 2011
 
WAS Support & Monitoring Tools
WAS Support & Monitoring ToolsWAS Support & Monitoring Tools
WAS Support & Monitoring Tools
 
Building a Novell Data Synchronizer Connector: A Developer's Guide
Building a Novell Data Synchronizer Connector: A Developer's GuideBuilding a Novell Data Synchronizer Connector: A Developer's Guide
Building a Novell Data Synchronizer Connector: A Developer's Guide
 
Oracle 11g R2 Live Part 2
Oracle 11g R2 Live Part 2Oracle 11g R2 Live Part 2
Oracle 11g R2 Live Part 2
 
Managing Windows Server Systems For Midsize Organizations
Managing Windows Server Systems For Midsize OrganizationsManaging Windows Server Systems For Midsize Organizations
Managing Windows Server Systems For Midsize Organizations
 
11g R2 Live Part 1
11g R2 Live Part 111g R2 Live Part 1
11g R2 Live Part 1
 
Virtualization for Development
Virtualization for DevelopmentVirtualization for Development
Virtualization for Development
 
Introduction to VMware Infrastructure
Introduction to VMware  Infrastructure  Introduction to VMware  Infrastructure
Introduction to VMware Infrastructure
 
Infraestructure WMWARE
Infraestructure  WMWAREInfraestructure  WMWARE
Infraestructure WMWARE
 
System Center 2012 ve Microsoft Cloud Senaryoları
System Center 2012 ve Microsoft Cloud SenaryolarıSystem Center 2012 ve Microsoft Cloud Senaryoları
System Center 2012 ve Microsoft Cloud Senaryoları
 
Getting Started with ESXServer3iEmbedded
Getting Started with  ESXServer3iEmbedded  Getting Started with  ESXServer3iEmbedded
Getting Started with ESXServer3iEmbedded
 
LS11 SHOW202 - Enterprise 2.0 Hero - a Beginner's Guide to Installing IBM Lot...
LS11 SHOW202 - Enterprise 2.0 Hero - a Beginner's Guide to Installing IBM Lot...LS11 SHOW202 - Enterprise 2.0 Hero - a Beginner's Guide to Installing IBM Lot...
LS11 SHOW202 - Enterprise 2.0 Hero - a Beginner's Guide to Installing IBM Lot...
 
Jfokus 2012 : The Java EE 7 Platform: Developing for the Cloud
Jfokus 2012 : The Java EE 7 Platform: Developing for the CloudJfokus 2012 : The Java EE 7 Platform: Developing for the Cloud
Jfokus 2012 : The Java EE 7 Platform: Developing for the Cloud
 

Viewers also liked (20)

Cauja carmen citasapa
Cauja carmen citasapaCauja carmen citasapa
Cauja carmen citasapa
 
Bannerteste
BannertesteBannerteste
Bannerteste
 
CSS Antenna XDU04-80-R
CSS Antenna XDU04-80-RCSS Antenna XDU04-80-R
CSS Antenna XDU04-80-R
 
Apresentação1
Apresentação1Apresentação1
Apresentação1
 
Script
Script Script
Script
 
flah de oftalmologia
flah de  oftalmologiaflah de  oftalmologia
flah de oftalmologia
 
Kim Candidate Presentation
Kim Candidate PresentationKim Candidate Presentation
Kim Candidate Presentation
 
Dibujo
DibujoDibujo
Dibujo
 
El sistema nervioso
El sistema nerviosoEl sistema nervioso
El sistema nervioso
 
January 2012 cd review flyer
January 2012 cd review flyerJanuary 2012 cd review flyer
January 2012 cd review flyer
 
Ig ppt
Ig pptIg ppt
Ig ppt
 
--RB--
--RB----RB--
--RB--
 
Carta 2
Carta 2Carta 2
Carta 2
 
Organizational Dyanmics Confrerence Orlando, FL
Organizational Dyanmics Confrerence Orlando, FLOrganizational Dyanmics Confrerence Orlando, FL
Organizational Dyanmics Confrerence Orlando, FL
 
Presentación1
Presentación1Presentación1
Presentación1
 
German III Chapter 4 Jeopardy
German III Chapter 4 JeopardyGerman III Chapter 4 Jeopardy
German III Chapter 4 Jeopardy
 
READING LONDON OLYMPICS 2012
READING LONDON OLYMPICS 2012 READING LONDON OLYMPICS 2012
READING LONDON OLYMPICS 2012
 
ακτίνες X
ακτίνες    Xακτίνες    X
ακτίνες X
 
Entrevista de Frei Beto ao O Globo
Entrevista de Frei Beto ao O GloboEntrevista de Frei Beto ao O Globo
Entrevista de Frei Beto ao O Globo
 
German II Jeopardy Chap 10
German II Jeopardy Chap 10German II Jeopardy Chap 10
German II Jeopardy Chap 10
 

Similar to Share point2010 servervirtualization

Introduction to SharePoint 2010
Introduction to SharePoint 2010Introduction to SharePoint 2010
Introduction to SharePoint 2010SharePointKE
 
Virtualization technologies - Windows Server 2008 R2 Hyper-V
Virtualization technologies - Windows Server 2008 R2 Hyper-VVirtualization technologies - Windows Server 2008 R2 Hyper-V
Virtualization technologies - Windows Server 2008 R2 Hyper-Vsolsoft
 
Ready for cloud computing with hyper v
Ready for cloud computing with hyper vReady for cloud computing with hyper v
Ready for cloud computing with hyper vAndik Susilo
 
SharePoint 2010 Architecture - TechEd Brasil 2010
SharePoint 2010 Architecture - TechEd Brasil 2010SharePoint 2010 Architecture - TechEd Brasil 2010
SharePoint 2010 Architecture - TechEd Brasil 2010Michael Noel
 
SharePoint 2010’s Virtual Reality - SharePoint Saturday Vietnam
SharePoint 2010’s Virtual Reality - SharePoint Saturday VietnamSharePoint 2010’s Virtual Reality - SharePoint Saturday Vietnam
SharePoint 2010’s Virtual Reality - SharePoint Saturday VietnamOfficience
 
Ws08 r2 hyper v overview r2
Ws08 r2 hyper v overview r2Ws08 r2 hyper v overview r2
Ws08 r2 hyper v overview r2Omid Koushki
 
1.1 plan your_cloud_final
1.1 plan your_cloud_final1.1 plan your_cloud_final
1.1 plan your_cloud_finalPaulo Freitas
 
Private cloud server virtualization
Private cloud server virtualization Private cloud server virtualization
Private cloud server virtualization Pierre-Juan Labeyrie
 
Hyper V Version2 Update
Hyper V Version2 UpdateHyper V Version2 Update
Hyper V Version2 UpdateBlauge
 
Windows Server 2016 First Look (Part 1)
Windows Server 2016 First Look (Part 1)Windows Server 2016 First Look (Part 1)
Windows Server 2016 First Look (Part 1)Tuan Yang
 
Microsoft India - Windows Server 2008 R2 Hyper - V Live Migration Whitepaper
Microsoft India - Windows Server 2008 R2 Hyper - V Live Migration Whitepaper Microsoft India - Windows Server 2008 R2 Hyper - V Live Migration Whitepaper
Microsoft India - Windows Server 2008 R2 Hyper - V Live Migration Whitepaper Microsoft Private Cloud
 
Securitatea virtualizarii
Securitatea virtualizariiSecuritatea virtualizarii
Securitatea virtualizariiTudor Damian
 
Windows 7 and Windows Server 2008 R2 SP1 Overview
Windows 7 and Windows Server 2008 R2 SP1 OverviewWindows 7 and Windows Server 2008 R2 SP1 Overview
Windows 7 and Windows Server 2008 R2 SP1 OverviewAmit Gatenyo
 
Virtualization Map Tech Ed2009
Virtualization Map Tech Ed2009Virtualization Map Tech Ed2009
Virtualization Map Tech Ed2009rsnarayanan
 
Upgrading from Windows Server 2008 / 2008 R2 to Windows Server 2012
Upgrading from Windows Server 2008 / 2008 R2 to Windows Server 2012Upgrading from Windows Server 2008 / 2008 R2 to Windows Server 2012
Upgrading from Windows Server 2008 / 2008 R2 to Windows Server 2012Harold Wong
 
Virtualizing SharePoint Components
Virtualizing SharePoint ComponentsVirtualizing SharePoint Components
Virtualizing SharePoint Componentswebhostingguy
 
SharePoint 2010's Virtual Reality - SPC2C
SharePoint 2010's Virtual Reality - SPC2CSharePoint 2010's Virtual Reality - SPC2C
SharePoint 2010's Virtual Reality - SPC2CMichael Noel
 
SharePoint 2010's Virtual Reality
SharePoint 2010's Virtual RealitySharePoint 2010's Virtual Reality
SharePoint 2010's Virtual RealityMichael Noel
 
Introduction to Hyper-V
Introduction to Hyper-VIntroduction to Hyper-V
Introduction to Hyper-VMark Wilson
 

Similar to Share point2010 servervirtualization (20)

Introduction to SharePoint 2010
Introduction to SharePoint 2010Introduction to SharePoint 2010
Introduction to SharePoint 2010
 
Virtualization technologies - Windows Server 2008 R2 Hyper-V
Virtualization technologies - Windows Server 2008 R2 Hyper-VVirtualization technologies - Windows Server 2008 R2 Hyper-V
Virtualization technologies - Windows Server 2008 R2 Hyper-V
 
Ready for cloud computing with hyper v
Ready for cloud computing with hyper vReady for cloud computing with hyper v
Ready for cloud computing with hyper v
 
SharePoint 2010 Architecture - TechEd Brasil 2010
SharePoint 2010 Architecture - TechEd Brasil 2010SharePoint 2010 Architecture - TechEd Brasil 2010
SharePoint 2010 Architecture - TechEd Brasil 2010
 
SharePoint 2010’s Virtual Reality - SharePoint Saturday Vietnam
SharePoint 2010’s Virtual Reality - SharePoint Saturday VietnamSharePoint 2010’s Virtual Reality - SharePoint Saturday Vietnam
SharePoint 2010’s Virtual Reality - SharePoint Saturday Vietnam
 
Ws08 r2 hyper v overview r2
Ws08 r2 hyper v overview r2Ws08 r2 hyper v overview r2
Ws08 r2 hyper v overview r2
 
1.1 plan your_cloud_final
1.1 plan your_cloud_final1.1 plan your_cloud_final
1.1 plan your_cloud_final
 
Private cloud server virtualization
Private cloud server virtualization Private cloud server virtualization
Private cloud server virtualization
 
Hyper V Version2 Update
Hyper V Version2 UpdateHyper V Version2 Update
Hyper V Version2 Update
 
Windows Server 2016 First Look (Part 1)
Windows Server 2016 First Look (Part 1)Windows Server 2016 First Look (Part 1)
Windows Server 2016 First Look (Part 1)
 
Microsoft India - Windows Server 2008 R2 Hyper - V Live Migration Whitepaper
Microsoft India - Windows Server 2008 R2 Hyper - V Live Migration Whitepaper Microsoft India - Windows Server 2008 R2 Hyper - V Live Migration Whitepaper
Microsoft India - Windows Server 2008 R2 Hyper - V Live Migration Whitepaper
 
Securitatea virtualizarii
Securitatea virtualizariiSecuritatea virtualizarii
Securitatea virtualizarii
 
Microsoft Hyper-V
Microsoft Hyper-VMicrosoft Hyper-V
Microsoft Hyper-V
 
Windows 7 and Windows Server 2008 R2 SP1 Overview
Windows 7 and Windows Server 2008 R2 SP1 OverviewWindows 7 and Windows Server 2008 R2 SP1 Overview
Windows 7 and Windows Server 2008 R2 SP1 Overview
 
Virtualization Map Tech Ed2009
Virtualization Map Tech Ed2009Virtualization Map Tech Ed2009
Virtualization Map Tech Ed2009
 
Upgrading from Windows Server 2008 / 2008 R2 to Windows Server 2012
Upgrading from Windows Server 2008 / 2008 R2 to Windows Server 2012Upgrading from Windows Server 2008 / 2008 R2 to Windows Server 2012
Upgrading from Windows Server 2008 / 2008 R2 to Windows Server 2012
 
Virtualizing SharePoint Components
Virtualizing SharePoint ComponentsVirtualizing SharePoint Components
Virtualizing SharePoint Components
 
SharePoint 2010's Virtual Reality - SPC2C
SharePoint 2010's Virtual Reality - SPC2CSharePoint 2010's Virtual Reality - SPC2C
SharePoint 2010's Virtual Reality - SPC2C
 
SharePoint 2010's Virtual Reality
SharePoint 2010's Virtual RealitySharePoint 2010's Virtual Reality
SharePoint 2010's Virtual Reality
 
Introduction to Hyper-V
Introduction to Hyper-VIntroduction to Hyper-V
Introduction to Hyper-V
 

Recently uploaded

Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsHyundai Motor Group
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersThousandEyes
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsPrecisely
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraDeakin University
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr LapshynFwdays
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsMark Billinghurst
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machinePadma Pradeep
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphNeo4j
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticscarlostorres15106
 
Bluetooth Controlled Car with Arduino.pdf
Bluetooth Controlled Car with Arduino.pdfBluetooth Controlled Car with Arduino.pdf
Bluetooth Controlled Car with Arduino.pdfngoud9212
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationSafe Software
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):comworks
 
Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfjimielynbastida
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024The Digital Insurer
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024BookNet Canada
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Enterprise Knowledge
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesSinan KOZAK
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentationphoebematthew05
 

Recently uploaded (20)

Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter RoadsSnow Chain-Integrated Tire for a Safe Drive on Winter Roads
Snow Chain-Integrated Tire for a Safe Drive on Winter Roads
 
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for PartnersEnhancing Worker Digital Experience: A Hands-on Workshop for Partners
Enhancing Worker Digital Experience: A Hands-on Workshop for Partners
 
Unlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power SystemsUnlocking the Potential of the Cloud for IBM Power Systems
Unlocking the Potential of the Cloud for IBM Power Systems
 
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
Transcript: New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Artificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning eraArtificial intelligence in the post-deep learning era
Artificial intelligence in the post-deep learning era
 
The transition to renewables in India.pdf
The transition to renewables in India.pdfThe transition to renewables in India.pdf
The transition to renewables in India.pdf
 
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
"Federated learning: out of reach no matter how close",Oleksandr Lapshyn
 
Human Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR SystemsHuman Factors of XR: Using Human Factors to Design XR Systems
Human Factors of XR: Using Human Factors to Design XR Systems
 
Install Stable Diffusion in windows machine
Install Stable Diffusion in windows machineInstall Stable Diffusion in windows machine
Install Stable Diffusion in windows machine
 
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge GraphSIEMENS: RAPUNZEL – A Tale About Knowledge Graph
SIEMENS: RAPUNZEL – A Tale About Knowledge Graph
 
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmaticsKotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
Kotlin Multiplatform & Compose Multiplatform - Starter kit for pragmatics
 
Bluetooth Controlled Car with Arduino.pdf
Bluetooth Controlled Car with Arduino.pdfBluetooth Controlled Car with Arduino.pdf
Bluetooth Controlled Car with Arduino.pdf
 
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry InnovationBeyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
Beyond Boundaries: Leveraging No-Code Solutions for Industry Innovation
 
CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):CloudStudio User manual (basic edition):
CloudStudio User manual (basic edition):
 
Science&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdfScience&tech:THE INFORMATION AGE STS.pdf
Science&tech:THE INFORMATION AGE STS.pdf
 
My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024My INSURER PTE LTD - Insurtech Innovation Award 2024
My INSURER PTE LTD - Insurtech Innovation Award 2024
 
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
New from BookNet Canada for 2024: BNC BiblioShare - Tech Forum 2024
 
Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024Designing IA for AI - Information Architecture Conference 2024
Designing IA for AI - Information Architecture Conference 2024
 
Unblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen FramesUnblocking The Main Thread Solving ANRs and Frozen Frames
Unblocking The Main Thread Solving ANRs and Frozen Frames
 
costume and set research powerpoint presentation
costume and set research powerpoint presentationcostume and set research powerpoint presentation
costume and set research powerpoint presentation
 

Share point2010 servervirtualization

  • 1. SharePoint 2010 Products: Virtualization Process Using Hyper-V technology to virtualize servers Requirements Hyper-V™ hardware virtualization uses software to create a virtual machine that resembles the resources of a physical Virtualization server (Hyper-V host) SharePoint 2010 Products virtual machine computer. The virtual machine has its own operating system environment that is logically isolated from the virtualization (host) Before you can deploy Microsoft® SharePoint® Server 2010 or Microsoft® SharePoint® Before you can deploy SharePoint Server 2010 or SharePoint Foundation 2010, you must server. By providing multiple virtual machines at once, this approach allows different versions of the operating system to run Foundation 2010 on a Hyper-V™ virtual machine, you must meet the following meet the following requirements: simultaneously on a single physical machine. It provides strong isolation between the (independent) running virtual machines. requirements for the virtualization server (host): Operating system requirement: Database requirement: 64-bit SQL Hardware requirements Operating system requirements Windows Server 2008 or Windows Server 2005 or 64-bit SQL Server 2008 Benefits Constraints Processor: x64 compatible processor with Intel VT or AMD-V technology enabled. We recommend that you use Windows Server® 2008 R2 or Microsoft Hyper-V™ Server 2008 R2 SharePoint Server 2010 and SharePoint For farm installations of SharePoint Server Hardware Data Execution Prevention (DEP) Server 2008 R2 for virtualization servers. 2010 and SharePoint Foundation 2010, you · Consolidates multiple, underutilized physical servers on a · Number of virtual machines cannot exceed the capacity of the available and enabled. These software versions provide significant Foundation 2010 must be run on a 64-bit edition of Windows Server 2008 with Service must be running 64-bit versions of Microsoft single host virtualization server (host). Adequate physical resources, particularly improvements in virtual core support, power SQL Server® 2005 or Microsoft SQL Server · Reduces cabling and peripheral requirements · Virtual processor limit of four processor per virtual machine. cores, RAM, and high performance disks with management, live migration, performance Pack 2 (SP2) or Windows Server 2008 R2. 2008 (each with the appropriate service packs · Reduces space requirements and power consumption. · A clustered environment requires enough free resources on each host to the capacity to support the virtual machines (virtual drives and networking), and general and updates) on the database servers. · Increases flexibility, speed, and ease of server enable live migration. that are hosted. This includes an allowance system performance. Resources deployment · In a SharePoint 2010 Products environment you have to monitor the for resource overhead on the host. Planning and architecture for SharePoint Server 2010 (http://go.microsoft.com/fwlink/?LinkID=89404) virtualization host as well as the virtual farm servers. · For capacity-planning purposes, only physical cores should be taken into Virtualization planning for SharePoint Server 2010 (http://go.microsoft.com/fwlink/?LinkId=194755) account, not possible hardware threads. Virtualization stages Architecture examples Analysis 1 - Planning Purpose Tools Steps The following physical and virtual Illustration key: · Determine business goals and objectives. architectures, which feature SharePoint Virtual machine layer WFE: Web server Do Do not Before you can deploy, you must The Microsoft Assessment and Planning (MAP) · Identify the type of farm and farm elements Server 2010, are shown for the purposes of plan the virtualization solution that Toolkit for Hyper-V illustration and discussion only. For the APP: Application server · Plan for the worst case scenario on the host server. · Take a snapshot of a running virtual machine in a that you want to virtualize. DB: Database server · Monitor host and virtual machine health and production environment. you want to deploy. It is critical that (http://go.microsoft.com/fwlink/?LinkId=194756) · Determine virtualization server purpose of this model, domain controller and CA: Central Administration · Install anything on the host root partition except the everyone clearly understands the firewall servers are physical servers. Front-end Database Application Query: Query component performance data on an ongoing basis. requirements. goals and objectives for Web server server server Crawl: Crawl component · Plan for redundancy and growth on each host. operating system and Hyper-V. HOST: Virtualization server · Use the same operating system version and patch · Overcommit host CPU resources. virtualization. Determine the type of Output Physical machine and virtual machine Physical machine layer DC: Domain controller level on the hosts and the virtual machines. · Assume that all server applications have the same farm that you want to deploy and its · resources are provided for the purpose of: Virtualization plan FS: Firewall server · Be aware of differences in server hardware - capacity characteristics. purpose. For example, test and · Topology and resource requirements · Showing the relationship between a LP: Logical processor · Use snapshots as a backup strategy. especially processor architectures quality assurance, authoring, or · A benchmark for evaluating outcome virtualization server and its virtual VP: Virtual processor publishing portal. machines. n GB = Amount of RAM in GB against goals and objectives Virtualization server Cores (4) on Database Application · Showing the distribution of farm servers Hyper-V host server server across virtualization servers. 2 - Evaluation Purpose Expected duration and stability Steps WFE Virtual machine Virtualization server CA Farm A or Farm B: For this phase, the physical computer can be a laptop Used to deploy SharePoint 2010 · Not a stable environment – no service- · Create virtual machines. WFE WFE Search · Dual processor virtual machine. or workstation that has enough memory to support a CA CA Products in a virtual environment to level agreement for users · Deploy a single server or a two-server 2xVP · Use 4 GB of RAM for each virtual machine that hosts the single virtual machine or two virtual machines in a two- Search Search see if virtualization is feasible · Typically a throw-away solution farm. DB DB 2 GB database. server deployment. A quad core physical machine is 2xVP · Use 40 GB dynamic virtual hard disks. · Evaluate the solution by configuring Farm A Farm B preferred, but not required. 4 GB · Use the snapshot feature to keep a clean image of the operating SharePoint Server 2010 and enabling 2xVP Small farm Small farm system for redeploying SharePoint Server 2010. the services. 4 GB DB Farm installed on a single server Farm installed on two servers · Collect initial benchmark data on virtual 2xVP machines and virtualization host. For 4 GB example, CPU use, memory use, hard disk space. Analysis Characteristics Topology Output Assuming that there is 8 GB of RAM on the physical computer: 2xLP 4xLP 4xLP 8 GB 8 GB 8 GB · Allow a 2-GB reserve for the operating system and Hyper-V For evaluation purposes, the topology is Information that will enable you to: overhead. Initial deployment of the solution is usually a single-server deployment or a · Decide to continue. This leaves less than 6 GB for the virtual machines. followed by testing and refining the small farm that has the database on a · Implement refinements that are required solution. separate server. for testing proof of concept. 3 - Proof of concept (POC) Purpose Expected duration and stability Steps Virtual machine Virtualization server WFE-1 WFE-1 WFE-2 Used to determine whether a partial · Set up, reviewed, and then discarded · Scale up virtualization server or add Query Query Query Small or medium farm with farm servers deployed across three tiers: The CPU for the Farm A host is slightly · Dual processor virtual machines. oversubscribed (4 LP : 6 VP), but the CPU for Farm B or full SharePoint 2010 Products · Not a stable environment – no service-level virtualization server. 2xVP 2xVP 2xVP · 4 GB of RAM for each front-end Web server and each is oversubscribed (4 LP : 10 VP) at a higher rate, virtualization solution will meet agreement for users · Create virtual machines with adequate 4 GB application server, 8 GB of RAM for database server. which will degrade performance. The virtual machines 4 GB 4 GB business needs and to determine an capacity for running a farm with more servers · Use three 30 GB dynamic virtual hard disk drives for all servers in Farm B require 24 GB of RAM without an operating appropriate infrastructure plan. and more features. to deploy SharePoint Server on the drive topology that is system reserve or Hyper-V overhead. · Deploy farm. CA App-1 App-2 typically used for farm servers. · Use Hyper-V snapshots to capture the state of the virtual Characteristics Topology · Expand scope of benchmark data to include Crawl CA Crawl machine before you deploy SharePoint Server. farm servers and virtualization servers. 2xVP 2xVP 2xVP · For Farm B, dedicate one application server for the crawl Environments for the POC phase In order to better illustrate functionality and · Expand user base. Farm A Farm B 4 GB 4 GB 4 GB component. can be created by deploying new usage flow for the POC phase, a typical · Determine how you will manage the farm and Small farm Medium farm farms or by scaling the farm used for topology is three-tier small or medium farm. Farm servers Farm servers supporting infrastructure. evaluation. In either case, the goal of · Evaluate proof of concept. distributed across distributed across Analysis POC is to demonstrate that the Use this topology and scale to refine the vision three tiers DB three tiers DB · Refine goals and infrastructure requirements. planning solution is feasible and for the production farm as well as gather farm 2xVP 2xVP Performance is not the focus for POC; however, perceived poor performance can affect the desired results. should be pursued. There can be server and virtualization performance data. 6 GB 8 GB The options, in order of priority are: continuous development and This is a good phase to start establishing a Output · Host the virtual machines on two virtualization servers to accommodate CPU and RAM issues. · Use a virtualization server that has 8 cores and at least 32 GB of RAM. tailoring during this phase to refine benchmark that can be refined later in the · Updated virtualization plan · Use multiple physical hard disk drives to host the virtual machine hard disk drives. the proof of concept. cycle. · Updated topology and resource requirements 4xLP 4xLP We recommend two virtualization hosts for user acceptance testing and production environments. If you have the capability for POC, 16 GB · Updated virtualization server resource 32 GB HOST 2 we recommend that you implement this architecture before going on to the next phase. requirements Unless the virtualization hosts are only going to be used for POC, you should implement a virtual architecture that will carry through to · Preliminary operations plan subsequent stages. Evaluate the number of host cores and RAM to ensure that you have room to scale up or scale out during the pilot. 4 - Pilot Purpose Expected duration and stability Steps WFE-1 WFE-2 Virtual machine Virtualization server WFE-1 WFE-2 WFE-3 Used to test a solution on a small · Limited time frame · Determine the number of virtualization servers Query Query Query Query Query For a pilot, the number of users taking part in the project is For the Farm A environment, the memory typical higher than POC participants. As a result, user activity is scale. · Limited service-level agreement for solution that are required to support the pilot farm. requirements, without any memory committed to the 2xVP 2xVP 2xVP 2xVP 2xVP higher, which is reflected in a higher number of page hits, operating system or Hyper-V, is 20 GB of RAM. You readiness testing · Create virtual machines to support farm 4 GB 4 GB 4 GB 4 GB 4 GB increased document storage, more search queries, and need a single host with at least 32 GB of RAM. In Pilots are used to test solution · Production service-level agreement for requirements that are identified in POC. increased time to crawl the database. A small or medium farm addition, continuing with a single quad core physical readiness, typically without using production testing · Deploy the pilot farm. CA App-1 App-2 with farm servers deployed across three tiers still provides a server results in a logical to virtual processor ratio of real data because the focus is on · Refine benchmark data for collection for farm Crawl CA Crawl reasonable environment for pilots. 8:10, which exceeds the recommended 1:1 ratio. A functional testing. Farm A is a small farm that has: higher ratio increases CPU overcommitment and will servers and virtualization server. · Two processors for all the servers except the database 2xVP likely affect performance. If you plan to use this farm · Evaluate pilot. 4 GB 2xVP 2xVP server, which has four processors. for user acceptance testing, you need to add more Farm A Farm B 4 GB 4 GB However, a pilot can also be used to · Refine goals and infrastructure requirements. · 4 GB of RAM for each front-end Web server and each RAM to the virtualization server. test for production characteristics by · Determine operations plan for supporting Small farm Medium farm application server, 8 GB of RAM for the database server. using real data and having the pilot virtualization server and farm servers. Identify Farm servers distributed Farm servers Continue to use three 40-GB hard disk configurations, but mix For the Farm B environment, Host-1: DB DB-2 dynamic, fixed size, and pass through to gather IOPS data. users do actual work in the tools and processes for monitoring at both across three tiers distributed across DB-1 · Available memory, without any committed three tiers memory, is 8 GB of RAM, which leaves room to environment. We recommend this levels. 4xVP Farm B is a medium farm running on two virtualization hosts. 4xVP 4xVP scale up a farm server. approach. · Implement processes and tools for migrating 8 GB 8 GB 8 GB The virtual machines are configured as follows: · The logical to virtual processor ration is 1:1, which virtual machines between virtualization · Two processors for all the servers except the database is good for performance, but adding another virtual servers. servers, which each have four processors. machine would oversubscribe the host CPU. · All the servers have 4 GB of RAM, except the database servers, which have 8 GB of RAM each. For the Farm B environment, Host-2: Characteristics Topology Output · 4 GB RAM for each front-end Web server and each · Available memory, without any committed HOST-1 HOST-2 application server, 8 GB RAM for the database server. memory, is 4 GB of RAM, which leaves no room to A limited set of users has access to Topologies will vary according to the planned · Updated virtualization plan Determine storage requirements and implement them for the scale up a farm server. 8xLP 8xLP 8xLP pilot so they can be tested and you can use the benchmarks for · The logical to virtual processor ratio is 8:10, which the environment to test the solution, the number of pilot users, and the · Updated topology and resource requirements 24 GB 24 GB 24 GB user acceptance testing. will reduce performance and leaves no capacity to functionality and performance of the scope of functional and capacity management for virtualization server and farm servers. Analysis add another virtual machine. solution and infrastructure. testing. · Verify whether or not a fully virtualized environment can met SharePoint business and · Before you start the pilot, determine if the databases need to be mirrored for high availability. If so, deploy them on two hosts. Pilot environments are typically a scaled- capacity management requirements · Review your benchmark data for database server performance to decide whether to continue with virtual database servers. If so, down, but representative version of the · A refined operations plan that you can test you must determine which of the following storage solutions you want to implement and test: fixed size virtual hard disks or pass planned production environment. during the pilot. This plan includes backup and through to shared storage. If you are going to switch to physical database servers, do it before starting UAT. recovery, adding, removing, and moving virtual · The logical to virtual processor ratio is higher than the recommended 1:1. You can proceed with oversubscribed CPUs on the virtualization hosts, recognizing that you must implement changes during UAT. We recommend that you make host adjustments machines. before you start acceptance testing. · Load a substantive subset of actual content before you start UAT. · Determine whether or not to continue on to the next phase using the same physical servers as well as the same physical and virtual architectures. 5 - User acceptance test (UAT) Purpose Expected duration and stability Steps Virtual machine Virtualization server A preproduction environment used · Long-term availability – this is a stable · Refine virtual machine distribution over WFE-1 WFE-2 WFE-3 WFE-1 WFE-2 WFE-3 WFE-4 WFE-5 During user acceptance testing there typically is a service-level For the Farm A environment, HOST-1 agreement. Ensure that: for testing solutions against a subset preproduction environment. virtualization servers. Query Query Query Query Query Query Query Query · Available memory, without committed memory, is 8 · The farm servers are adequately sized and you can scale up or complete copy of production data. · Limited service-level agreement for users. · Scale up virtualization servers, scale out or scale out. GB of RAM. 4xVP 4xVP 4xVP 4xVP 4xVP 4xVP 4xVP 4xVP · The logical to virtual processor ratio is 8:16. farm servers, deploy farm servers on 12 GB 12 GB 12 GB 8 GB 8 GB 8 GB 8 GB 8 GB · You have a reasonable degree of high availability For the Farm A environment, HOST-2 Also used for validating the backups physical machines as appropriate. implemented. · Available memory, without committed memory, is 20 · Deploy farm. · You have a backup and recovery strategy. or operational procedures. GB of RAM. · The virtual machines in Farm A and Farm B all have four · Implement operations plan along with in- virtual processors. The memory configurations are as follows: · The logical to virtual processor ratio is 8:12. Topology house or commercial monitoring product. App-2 Characteristics App-1 CA App-1 App-2 App-3 App-4 · Farm A: three front-end Web servers with 12 GB each, two For the Farm B environment, HOST-1 · Evaluate solution and operations plan. CA Crawl Crawl CA application servers with 8 GB each, and two database Topology should be as similar to CA Crawl · Available memory, without committed memory, is 16 Topologies vary, and have been determined · Test for capacity and performance. servers, each with 32 GB of RAM. GB of RAM. production environment as possible. in the pilot phase. For acceptance testing, we 4xVP 4xVP 4xVP 4xVP 4xVP 4xVP · Farm B: five front-end Web servers with 8 GB each, four 8 GB 8 GB 16 GB 16 GB 16 GB 16 GB · The logical to virtual processor ratio is 8:20. recommend that the farm servers be near the application servers with 16 GB each. Testers ensure that all solution Output For the Farm B environment, HOST-2 elements function as expected in same scale as the production environment. · Available memory, without committed memory, is 24 network and security conditions that · Revised virtual architecture. DB-1 DB-2 Farm B GB of RAM. 4xVP 4xVP DB-1 DB-2 match the conditions of the If load testing is the goal, then the virtual · Updated operations plan. Farm A · The logical to virtual processor ratio is 8:16. 32 GB 32 GB Medium to large farm production environment. machine configurations should be identical to · Implementation plan. Planned production Medium farm the production environment and the environment Analysis Planned production virtualization hosts should be the same as environment the ones planned for production. The logical to virtual processor ratio is higher than the recommended 1:1. Both farms are seriously oversubscribed. We recommend that you address this issue before you start UAT. You can: The final production topology and farm server · Scale back the virtual processor configuration on the front-end Web servers or application servers. configurations are tuned, refined, and HOST-1 HOST-2 · Add additional hosts, shown in Farm A of the following production illustration. HOST-1 HOST-2 · Use hosts with more cores, shown in Farm B of the following production illustration. implemented by using the benchmarks 8xLP 8xLP 8xLP 8xLP 8xLP 32 GB 32 GB 8xLP obtained in preproduction testing. 72 GB 72 GB 72 GB 72 GB Database: Clustered or mirrored 6 - Production Purpose Expected duration and stability Steps HOST-2 Virtual machine Virtualization server WFE-1 WFE-2 WFE-3 WFE-1 WFE-2 WFE-3 WFE-4 This is the live environment · Long-term availability – this should be a Query Query Query Query Query Query Query The production environment typically matches that of the user The virtualization hosts for Farm A and Farm B that your users interact with. stable environment. · Deploy production farm. acceptance testing environment. In some cases it may reflect illustrate two approaches to increasing host capacity. · Full service-level agreement for users, · Deploy services farm. 4xVP 4xVP 4xVP 4xVP 4xVP 4xVP 4xVP required changes that are a result of user acceptance testing. Farm A uses four 8 core hosts, each with 64 GB of Farm A has the following virtual machine configurations: RAM. Host-3 only has one virtual machine, a crawl appropriate to the solution and business · Deploy production solution. 16 GB 16 GB 16 GB 8 GB 8 GB 8 GB 8 GB · Three front-end Web servers, each with four processors and server; and there is capacity to add another four- requirements. · Implement operations plan. 16 GB of RAM processor virtual machine without oversubscribing · Two application servers, each with four processors. Central the CPU. In all cases, there is adequate memory to App-1 App-2 Administration (CA) is installed on App-1, which has 16 GB of scale up the virtual machines. The advantage of App-1 App-2 App-3 App-4 Characteristics Topology Output CA Crawl CA Crawl Crawl CA RAM. The Search Crawl component is installed on App-2, using four hosts is that you have the flexibility to HOST-4 which has 32 GB of RAM. Note that Central Administration is move virtual machines around on the hosts. The It is business critical, and Topologies vary, and have been determined in · Final operations plan 4xVP 4xVP disadvantage is that you have twice as many 4xVP 4xVP 4xVP 4xVP also installed on App-2. appropriate service-level the pilot phase. For acceptance testing, we · Implementation plan 16 GB 32 GB 16 GB 16 GB 16 GB 16 GB · The database servers are mirrored; each has four processors physical servers to manage. agreements are in place. recommend that the farm servers be near the and 32 GB of RAM. same scale as the production environment. DB-1 DB-2 Farm B has the following virtual machine configurations: Farm B uses two 16-core hosts, each with 64 GB of · Four front-end Web servers, each with four processors and 8 RAM. The ratio of logical to virtual processors is 1:1 4xVP 4xVP Farm B GB of RAM (scale out rather than scale up). for both hosts. Adding an additional virtual machine If load testing is the goal, then the virtual 32 GB HOST-3 32 GB · Four application servers, each with four processors and 16 GB would oversubscribe either of the hosts, as would machine configurations should be identical to Large farm of RAM. Two servers are dedicated to crawl and the other two moving a virtual machine from one host to the other. HOST-1 Planned production the production environment. environment host CA. Medium to large farm · The database servers are installed on physical machines. Farm A The final production topology and farm server Planned production environment configurations are tuned, refined, and Analysis implemented by using the benchmarks 8xLP 8xLP 8xLP 8xLP 16xLP 16xLP obtained in preproduction testing. 64 GB 64 GB 64 GB 64 GB 64 GB 8xLP 8xLP 64 GB 32 GB 32 GB Oversubscribing a virtualization host in response to a performance issue or a failed virtual machine is acceptable as a short-term solution. The recommended approach is to ensure that you mitigate this scenario by having adequate host capacity before putting the farm into production. There are several ways to ensure that you have extra capacity on the hosts, such as: Database: · Deploy hosts with 16 or more processor cores. HOST-1 HOST-2 HOST-3 HOST-4 HOST-1 Clustered or mirrored HOST-2 · Add one or more 8-core hosts to the environment. · Consider deploying a dedicated services farm to offload services that have high resource requirements, such as