4. Plot Plan KAN
1
2
3
4
5
6
1. Substation
2. Water Supply, Cooling Water, and Drainage & Emergency Station
3. Nitric Acid
4. Amonium Nitrate
5. AN Bagging and AN Warehouse
6. Central Control Building and Maintenance
Building
7. ANCP
6. Electrical Equipment Layout
1. Temporary Generator required
for charged the battery and
supply power for Temporary
Air Conditioner
2. Temporary Air Conditioner
required for Energize activity
since HVAC permanent isn’t
ready
1
2
3
4 5 6
7. 14 Aug ‘22
SAT/ Function Test
Switchgear MV and LV
13 Aug ‘22
SAT/ Function
Test
Battery Charger
Relay Protection Test
Upstream and
Downstream
16 Aug ‘22 17 Aug ‘22
Function Test
TPP
Joint Walkthrough
KDM and KAN
18 Aug ‘22
ENERGIZE
20 Aug ‘22
Road to Energize Plan
17. Executive Summary
Electrical Equipment Test
SAT Switchgear MV
Electrical and Mechanical Test
FAT Switchgear MV
Electrical and Mechanical Test
ON PROGRESS
18. Executive Summary
Electrical Equipment Test
SAT Switchgear LV
Electrical and Mechanical Test
FAT Switchgear LV
Electrical and Mechanical Test
ON PROGRESS