SlideShare a Scribd company logo
2012
A Strategy for Optimizing Networks




                     Akira Oyama, Principal Consultant
                     5/6/2012
Introduction
A leased network planner is responsible for a number of activities including interconnections, capacity
management, least cost network design and network optimizations. A company with large network operating
expenses tasks its leased network planners to achieve a certain level of network optimization. There is an
optimization target set each year to measure the plan's success.

Because a Key Performance Indicator (KPI) is based on the current year run rate savings for many organizations,
the planner’s network decision is generally based on the monthly cost reduction that can be measured.
Unfortunately, making an optimization decision solely on the measurable monthly savings will lead to mixed
results because the planner failed to address hidden costs that cannot be easily measured, cash flow beyond the
current year and risk factors incurred with the short-term level of cost savings

This paper's intent is to show additional elements needed in the planning decision process that enables the
planner to be able to make the better financial and risk management decisions.

Run Rate Savings
To illustrate a better planning process, I created a hypothetical arrangement where the planner is looking to
extend leased network hubs to minimize the individual circuit loop costs. These circuits are assumed to be under
the AT&T Managed Shared Network Service (MSNS) plan. I assumed the DS1 equivalent average cost is $100
with total DS1 equivalent count of 1,000 in this market. Because the planner, Ellen, is very good and diligent, she
was able to identify 20% of the total circuits with average per cost of $120 that for the extended Competitive
Local Exchange Carrier (CLEC) hubs. She expects per circuit savings of $60. She must also pay $3,000 a month to
establish the new CLEC hubs (10) for this project. To simplify the illustration, I assumed no termination liability
or non-recurring charges associated with this project. Under this scenario, Ellen is able to realize $108K
annualized net savings:

Gross monthly savings: $60 x 200 = $12,000
Net monthly savings: $12,000 - $3,000 = $9,000
Annualized net savings: $9,000 x 12 months = $108,000

Ellen thought that this is not a bad optimization project. The project is initiated and the run rate savings
eventually realized. Case closed. Unfortunately, the actually savings is not as great as Ellen originally thought.

Hidden cost
Ellen's first mistake is failing to understand the financial impact to the MSNS plan and overall cash flow as a
result of initiating the optimization project.

MSNS is a service in which the customer assigns to AT&T the responsibility for facility design and engineering and
routing of point-to-point circuits (DS0 through OC192) from serving wire centers to the aggregation point. 90%
of point-to-point circuits must be committed under this plan (total 900 DS1 equivalent circuits in this scenario).
Because establishing a CLEC transport will lead to the establishment of new demarcation points, 20% of 1,000
DS1 equivalent circuits in this market will result in a MSNS short fall of 100 DS1 equivalent circuits.



www.netstrategysolutions.com                                                                                  Page 1
Ellen now realizes that the optimization project will incur a MSNS shortfall penalty of $90,000 ($900 x 100 DS1
equivalent). The adjusted savings will only be $18,000 a year ($108K - $90K), hardly a good project to take on
when there will be additional resources required to extend the circuits and a new CLEC commitment must be
established with turning up the new hubs. If she had known the relationships between the AT&T embedded
plan and her optimization project, she likely would not have initiated the project.

Although it’s not always easy for any planner to incorporate the commitment based carrier plans in their overall
optimization analysis, it’s vital that they address the explicit as well as implicit financial impacts from making any
optimization and planning decisions. Thus, Ellen should

Always have a good understanding of embedded contracts and tariff plans as well as have an idea of how
these plans will be financially impacted as a result of optimization and planning decisions.

Out year Risk Assessment
Let’s assume that the AT&T MSNS plan has 3 years remaining. Ellen must assess the overall cash flow impact to
the MSNS plan for its remaining life as a result of initiating the optimization project. She will also need to
evaluate the potential cash flow risk based on the circuit demand and scale of the optimization project.

Although cash flow evaluation and risk assessment may sound like too much work for Ellen, she doesn’t need a
sophisticated tool to evaluate the multi-year cash flow under different forecast and optimization assumptions.

A simple forecasting tool, like regression analysis, can be applied to predict the future baseline demand. Once
the planner is able to capture the baseline forecast, she can project the multi-year cash flow impact as a result of
optimization decisions.

To illustrate this, I created a simple three-year cash flow projection based on different levels of optimization
project scope and forecast in Table 1. Although extending circuits by 20% will result in the highest financial
return over three year period when circuit growth is at 10% a year (+$397,800), this strategy will also lead to the
biggest financial loss if circuit growth decreases by -10% a year (-$415,800).

For example, establishing new CLEC hubs to minimize the mileage cost is a strategy based optimizing Time
Division Multiplexing (TDM). The AT&T MSNS plan is also a commitment plan based on point-to-point circuits.
Ellen will be taking a huge financial risk, if the customers decide to purchase Ethernet loops instead of TDM
circuits to support their data requirements. If she believes the circuit demand will be flat for the next 3 years as
a result of technology migration and after reviewing trends, scaling down to groom just 10% of circuits instead of
20% will result in the best return ($162,000).




www.netstrategysolutions.com                                                                                   Page 2
Annual Growth Projection (table 1)
 % of Extension         -10%                 -5%                 0%                  5%                 10%
            0%    $   (270,000)      $      (45,000)      $           -       $           -       $           -
            5%    $   (313,200)      $      (50,850)      $     81,000        $     89,100        $     97,200
           10%    $   (356,400)      $      (97,200)      $    162,000        $    178,200        $    194,400
           15%    $   (399,600)      $    (145,800)       $    108,000        $    260,550        $    291,600
           20%    $   (415,800)      $    (167,400)       $     81,000        $    311,400        $    397,800


Ellen must understand the overall demand of the network and be able to select the right planning strategy to
maximize short and long-term cash flow while minimizing risk. She can also introduce another project with
different risk and cash flow characteristics to help reduce the overall project risk while achieving the desired cash
flow. Thus, Ellen should remember that

Trying to achieve the highest short-term monthly savings may not always be a good strategy and may be
taking on too much risk for additional incremental savings. It’s very important to understand the planning
strategy options and impact to the long-term cash flow and risk. Just as in an investment selection, Ellen must
select a project with appropriate risk levels for the desired return and counter the project risk by considering
the right mix of projects that lower the overall risk while maintaining cash flow.

Conclusion
I have seen many cases where planners are asked to initiate additional optimization projects to achieve a run
rate savings goal. Unfortunately, the planning and optimization decisions based on the monthly circuit savings
figure often ends up in creating long-term issues that must be addressed in subsequent years. In addition,
planners may treat these issues in the future as another optimization savings opportunity even though these
issues were created by poor planning decisions made in prior years.

Planning beyond short-term savings through the effective use of forecast and risk analysis in addition to a holistic
network view will help uncover long-term cash flow effects and the sensitivity to change in the cash flow. This
strategy allows the network planner to truly optimize the network.




www.netstrategysolutions.com                                                                                      Page 3

More Related Content

Viewers also liked

4 metasturcture of nursing informatics
4 metasturcture of nursing informatics4 metasturcture of nursing informatics
4 metasturcture of nursing informaticsinfinite28generation
 
Jersonhernandez
JersonhernandezJersonhernandez
JersonhernandezALJEMI
 
Finalllllpp
FinalllllppFinalllllpp
Finalllllppmd03530
 
Lalalalalal powerpoints
Lalalalalal powerpointsLalalalalal powerpoints
Lalalalalal powerpointsmd03530
 
Human Trafficking Assessment Tool (HTAT) Report for Nepal 2011-12
Human Trafficking Assessment Tool (HTAT) Report for Nepal 2011-12Human Trafficking Assessment Tool (HTAT) Report for Nepal 2011-12
Human Trafficking Assessment Tool (HTAT) Report for Nepal 2011-12PaulaRudnicka
 
Bacterial recombination (1)
Bacterial recombination (1)Bacterial recombination (1)
Bacterial recombination (1)Baba Hiremath
 
Elaboracion de un disfraz
Elaboracion de un disfrazElaboracion de un disfraz
Elaboracion de un disfrazBryan Stiven
 

Viewers also liked (9)

4 metasturcture of nursing informatics
4 metasturcture of nursing informatics4 metasturcture of nursing informatics
4 metasturcture of nursing informatics
 
Quimica i
Quimica iQuimica i
Quimica i
 
Jersonhernandez
JersonhernandezJersonhernandez
Jersonhernandez
 
Finalllllpp
FinalllllppFinalllllpp
Finalllllpp
 
Lalalalalal powerpoints
Lalalalalal powerpointsLalalalalal powerpoints
Lalalalalal powerpoints
 
Fundraising trend
Fundraising trendFundraising trend
Fundraising trend
 
Human Trafficking Assessment Tool (HTAT) Report for Nepal 2011-12
Human Trafficking Assessment Tool (HTAT) Report for Nepal 2011-12Human Trafficking Assessment Tool (HTAT) Report for Nepal 2011-12
Human Trafficking Assessment Tool (HTAT) Report for Nepal 2011-12
 
Bacterial recombination (1)
Bacterial recombination (1)Bacterial recombination (1)
Bacterial recombination (1)
 
Elaboracion de un disfraz
Elaboracion de un disfrazElaboracion de un disfraz
Elaboracion de un disfraz
 

Similar to White Paper A Strategy For Optimizing Networks

05_Life Cycle Costing.pptx
05_Life Cycle Costing.pptx05_Life Cycle Costing.pptx
05_Life Cycle Costing.pptx
Itxhamza
 
Risk & capital budgeting
Risk & capital  budgetingRisk & capital  budgeting
Risk & capital budgeting
lubnasadiyah
 
Financial Expense PowerPoint Presentation Slides
Financial Expense PowerPoint Presentation SlidesFinancial Expense PowerPoint Presentation Slides
Financial Expense PowerPoint Presentation Slides
SlideTeam
 
Schneider, Arnold, (2012) Managerial Accounting, United States, .docx
Schneider, Arnold, (2012) Managerial Accounting, United States, .docxSchneider, Arnold, (2012) Managerial Accounting, United States, .docx
Schneider, Arnold, (2012) Managerial Accounting, United States, .docx
anhlodge
 
Project_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.pptProject_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.ppt
ssdongre1
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Mihai Buta
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
Essam Lotffy, PMP®, CCP®
 
Operating Expense PowerPoint Presentation Slides
Operating Expense PowerPoint Presentation SlidesOperating Expense PowerPoint Presentation Slides
Operating Expense PowerPoint Presentation Slides
SlideTeam
 
Capital Budget Appraisal.
Capital Budget Appraisal.Capital Budget Appraisal.
Capital Budget Appraisal.
ArhamAli38
 
The Total Economic Impact Of NetApp Solutions For Cloud Service Providers
The Total Economic Impact Of NetApp Solutions For Cloud Service ProvidersThe Total Economic Impact Of NetApp Solutions For Cloud Service Providers
The Total Economic Impact Of NetApp Solutions For Cloud Service Providers
NetApp
 
Costing
CostingCosting
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
Ahmed Elshaboury,PMP,LEED GA
 
Capital Expense PowerPoint Presentation Slides
Capital Expense PowerPoint Presentation SlidesCapital Expense PowerPoint Presentation Slides
Capital Expense PowerPoint Presentation Slides
SlideTeam
 
lng 1at the 1g out rank-Jigh orma -atten-a li.docx
lng 1at the 1g out rank-Jigh orma -atten-a li.docxlng 1at the 1g out rank-Jigh orma -atten-a li.docx
lng 1at the 1g out rank-Jigh orma -atten-a li.docx
SHIVA101531
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppt
hass6
 
Market analysis of user-financed FTTP system in Palo Alto
Market analysis of user-financed FTTP system in Palo AltoMarket analysis of user-financed FTTP system in Palo Alto
Market analysis of user-financed FTTP system in Palo Alto
Stephen Blum
 
Introducing financial analysis
Introducing financial analysisIntroducing financial analysis
Introducing financial analysis
venkataramanan Thiru
 
Investment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation SlidesInvestment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation Slides
SlideTeam
 

Similar to White Paper A Strategy For Optimizing Networks (20)

05_Life Cycle Costing.pptx
05_Life Cycle Costing.pptx05_Life Cycle Costing.pptx
05_Life Cycle Costing.pptx
 
Risk & capital budgeting
Risk & capital  budgetingRisk & capital  budgeting
Risk & capital budgeting
 
Financial Expense PowerPoint Presentation Slides
Financial Expense PowerPoint Presentation SlidesFinancial Expense PowerPoint Presentation Slides
Financial Expense PowerPoint Presentation Slides
 
Schneider, Arnold, (2012) Managerial Accounting, United States, .docx
Schneider, Arnold, (2012) Managerial Accounting, United States, .docxSchneider, Arnold, (2012) Managerial Accounting, United States, .docx
Schneider, Arnold, (2012) Managerial Accounting, United States, .docx
 
Project_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.pptProject_selectionProject_selectionnn.ppt
Project_selectionProject_selectionnn.ppt
 
Primavera Monte Carlo[1]
Primavera Monte Carlo[1]Primavera Monte Carlo[1]
Primavera Monte Carlo[1]
 
Introduction to cost management & control in construction projects
Introduction to cost management & control in construction projectsIntroduction to cost management & control in construction projects
Introduction to cost management & control in construction projects
 
Operating Expense PowerPoint Presentation Slides
Operating Expense PowerPoint Presentation SlidesOperating Expense PowerPoint Presentation Slides
Operating Expense PowerPoint Presentation Slides
 
Capital Budget Appraisal.
Capital Budget Appraisal.Capital Budget Appraisal.
Capital Budget Appraisal.
 
The Total Economic Impact Of NetApp Solutions For Cloud Service Providers
The Total Economic Impact Of NetApp Solutions For Cloud Service ProvidersThe Total Economic Impact Of NetApp Solutions For Cloud Service Providers
The Total Economic Impact Of NetApp Solutions For Cloud Service Providers
 
Capital budgeting
Capital budgetingCapital budgeting
Capital budgeting
 
Costing
CostingCosting
Costing
 
Pmp integration chapter 4
Pmp integration chapter 4Pmp integration chapter 4
Pmp integration chapter 4
 
Capital Expense PowerPoint Presentation Slides
Capital Expense PowerPoint Presentation SlidesCapital Expense PowerPoint Presentation Slides
Capital Expense PowerPoint Presentation Slides
 
lng 1at the 1g out rank-Jigh orma -atten-a li.docx
lng 1at the 1g out rank-Jigh orma -atten-a li.docxlng 1at the 1g out rank-Jigh orma -atten-a li.docx
lng 1at the 1g out rank-Jigh orma -atten-a li.docx
 
FN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.pptFN6033-CORP FIN-LECTURE 5A.ppt
FN6033-CORP FIN-LECTURE 5A.ppt
 
Course03
Course03Course03
Course03
 
Market analysis of user-financed FTTP system in Palo Alto
Market analysis of user-financed FTTP system in Palo AltoMarket analysis of user-financed FTTP system in Palo Alto
Market analysis of user-financed FTTP system in Palo Alto
 
Introducing financial analysis
Introducing financial analysisIntroducing financial analysis
Introducing financial analysis
 
Investment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation SlidesInvestment on Fixed Assets PowerPoint Presentation Slides
Investment on Fixed Assets PowerPoint Presentation Slides
 

White Paper A Strategy For Optimizing Networks

  • 1. 2012 A Strategy for Optimizing Networks Akira Oyama, Principal Consultant 5/6/2012
  • 2. Introduction A leased network planner is responsible for a number of activities including interconnections, capacity management, least cost network design and network optimizations. A company with large network operating expenses tasks its leased network planners to achieve a certain level of network optimization. There is an optimization target set each year to measure the plan's success. Because a Key Performance Indicator (KPI) is based on the current year run rate savings for many organizations, the planner’s network decision is generally based on the monthly cost reduction that can be measured. Unfortunately, making an optimization decision solely on the measurable monthly savings will lead to mixed results because the planner failed to address hidden costs that cannot be easily measured, cash flow beyond the current year and risk factors incurred with the short-term level of cost savings This paper's intent is to show additional elements needed in the planning decision process that enables the planner to be able to make the better financial and risk management decisions. Run Rate Savings To illustrate a better planning process, I created a hypothetical arrangement where the planner is looking to extend leased network hubs to minimize the individual circuit loop costs. These circuits are assumed to be under the AT&T Managed Shared Network Service (MSNS) plan. I assumed the DS1 equivalent average cost is $100 with total DS1 equivalent count of 1,000 in this market. Because the planner, Ellen, is very good and diligent, she was able to identify 20% of the total circuits with average per cost of $120 that for the extended Competitive Local Exchange Carrier (CLEC) hubs. She expects per circuit savings of $60. She must also pay $3,000 a month to establish the new CLEC hubs (10) for this project. To simplify the illustration, I assumed no termination liability or non-recurring charges associated with this project. Under this scenario, Ellen is able to realize $108K annualized net savings: Gross monthly savings: $60 x 200 = $12,000 Net monthly savings: $12,000 - $3,000 = $9,000 Annualized net savings: $9,000 x 12 months = $108,000 Ellen thought that this is not a bad optimization project. The project is initiated and the run rate savings eventually realized. Case closed. Unfortunately, the actually savings is not as great as Ellen originally thought. Hidden cost Ellen's first mistake is failing to understand the financial impact to the MSNS plan and overall cash flow as a result of initiating the optimization project. MSNS is a service in which the customer assigns to AT&T the responsibility for facility design and engineering and routing of point-to-point circuits (DS0 through OC192) from serving wire centers to the aggregation point. 90% of point-to-point circuits must be committed under this plan (total 900 DS1 equivalent circuits in this scenario). Because establishing a CLEC transport will lead to the establishment of new demarcation points, 20% of 1,000 DS1 equivalent circuits in this market will result in a MSNS short fall of 100 DS1 equivalent circuits. www.netstrategysolutions.com Page 1
  • 3. Ellen now realizes that the optimization project will incur a MSNS shortfall penalty of $90,000 ($900 x 100 DS1 equivalent). The adjusted savings will only be $18,000 a year ($108K - $90K), hardly a good project to take on when there will be additional resources required to extend the circuits and a new CLEC commitment must be established with turning up the new hubs. If she had known the relationships between the AT&T embedded plan and her optimization project, she likely would not have initiated the project. Although it’s not always easy for any planner to incorporate the commitment based carrier plans in their overall optimization analysis, it’s vital that they address the explicit as well as implicit financial impacts from making any optimization and planning decisions. Thus, Ellen should Always have a good understanding of embedded contracts and tariff plans as well as have an idea of how these plans will be financially impacted as a result of optimization and planning decisions. Out year Risk Assessment Let’s assume that the AT&T MSNS plan has 3 years remaining. Ellen must assess the overall cash flow impact to the MSNS plan for its remaining life as a result of initiating the optimization project. She will also need to evaluate the potential cash flow risk based on the circuit demand and scale of the optimization project. Although cash flow evaluation and risk assessment may sound like too much work for Ellen, she doesn’t need a sophisticated tool to evaluate the multi-year cash flow under different forecast and optimization assumptions. A simple forecasting tool, like regression analysis, can be applied to predict the future baseline demand. Once the planner is able to capture the baseline forecast, she can project the multi-year cash flow impact as a result of optimization decisions. To illustrate this, I created a simple three-year cash flow projection based on different levels of optimization project scope and forecast in Table 1. Although extending circuits by 20% will result in the highest financial return over three year period when circuit growth is at 10% a year (+$397,800), this strategy will also lead to the biggest financial loss if circuit growth decreases by -10% a year (-$415,800). For example, establishing new CLEC hubs to minimize the mileage cost is a strategy based optimizing Time Division Multiplexing (TDM). The AT&T MSNS plan is also a commitment plan based on point-to-point circuits. Ellen will be taking a huge financial risk, if the customers decide to purchase Ethernet loops instead of TDM circuits to support their data requirements. If she believes the circuit demand will be flat for the next 3 years as a result of technology migration and after reviewing trends, scaling down to groom just 10% of circuits instead of 20% will result in the best return ($162,000). www.netstrategysolutions.com Page 2
  • 4. Annual Growth Projection (table 1) % of Extension -10% -5% 0% 5% 10% 0% $ (270,000) $ (45,000) $ - $ - $ - 5% $ (313,200) $ (50,850) $ 81,000 $ 89,100 $ 97,200 10% $ (356,400) $ (97,200) $ 162,000 $ 178,200 $ 194,400 15% $ (399,600) $ (145,800) $ 108,000 $ 260,550 $ 291,600 20% $ (415,800) $ (167,400) $ 81,000 $ 311,400 $ 397,800 Ellen must understand the overall demand of the network and be able to select the right planning strategy to maximize short and long-term cash flow while minimizing risk. She can also introduce another project with different risk and cash flow characteristics to help reduce the overall project risk while achieving the desired cash flow. Thus, Ellen should remember that Trying to achieve the highest short-term monthly savings may not always be a good strategy and may be taking on too much risk for additional incremental savings. It’s very important to understand the planning strategy options and impact to the long-term cash flow and risk. Just as in an investment selection, Ellen must select a project with appropriate risk levels for the desired return and counter the project risk by considering the right mix of projects that lower the overall risk while maintaining cash flow. Conclusion I have seen many cases where planners are asked to initiate additional optimization projects to achieve a run rate savings goal. Unfortunately, the planning and optimization decisions based on the monthly circuit savings figure often ends up in creating long-term issues that must be addressed in subsequent years. In addition, planners may treat these issues in the future as another optimization savings opportunity even though these issues were created by poor planning decisions made in prior years. Planning beyond short-term savings through the effective use of forecast and risk analysis in addition to a holistic network view will help uncover long-term cash flow effects and the sensitivity to change in the cash flow. This strategy allows the network planner to truly optimize the network. www.netstrategysolutions.com Page 3