Use venturi amplifier air nozzle instead of compressed air
Recommended Action
It is recommended to use an alternate method for supplying compressed air using venturi air
amplifier nozzles instead of spray nozzle. These nozzles use a small amount of compressed air
and produce high energy and high velocity air flow as output. Such nozzles have produced
significant savings for large manufacturing companies by reducing their compressed air usage.
Energy Cost Savings
Case 1:
For blow off nozzles:
We know, nozzle hole size = 3/32in., Pressure = 90 psi and total of 3 nozzles
From table 1, we calculate CFM based on the given information:
CFM v/s PSI For Nozzles
CFM Free Air Flow @ Nozzle Diameter (inch)
PSI 1/64 1/32 3/64 1/16 3/32 1/8 3/16 1/4
1 0.03 0.11 0.2 0.4 1 1.7 3.9 6.8
5 0.03 0.24 0.5 1 2.2 3.9 8.7 15.4
10 0.06 0.34 0.8 1.4 3.1 5.4 12.3 21.8
15 0.1 0.042 0.9 1.6 3.7 6.6 15 26.7
20 0.12 0.48 1.1 1.9 4.2 7.7 17.1 30.8
25 0.13 0.54 1.2 2.2 4.7 8.6 19.4 34.5
30 0.16 0.63 1.4 2.5 5.6 10 22.5 40
40 0.19 0.77 1.7 3.1 6.8 12.3 27.5 49.1
50 0.22 0.91 2 3.6 8.2 14.5 32.8 58.2
60 0.26 1.05 2.3 4.2 9.4 16.8 37.5 67
70 0.29 1.19 2.7 4.8 10.7 19 43 76
80 0.33 1.33 3 5.3 11.9 21.2 47.5 85
90 0.36 1.47 3.3 5.9 13.1 23.5 52.5 94
100 0.4 1.61 3.7 6.4 14.5 25.8 58.3 103
110 0.43 1.76 3.9 7 15.7 28 63 112
120 0.47 1.9 4.3 7.6 17 30.2 68 121
130 0.5 2.04 4.6 8.1 18.2 32.4 73 130
140 0.54 2.17 4.9 8.7 19.5 34.5 78 138
150 0.57 2.33 5.2 9.2 20.7 36.7 83 147
175 0.66 2.65 5.9 10.6 23.8 42.1 85 169
200 0.76 3.07 6.9 12.2 27.5 48.7 110 195
Table 1 (see reference)
Total no. of hours each nozzle is used per year = 6,840 hrs*0.5 = 3,420 hrs (Blow off is done
for 0.5 sec at every other second)
Current annual consumption in 1 nozzle = 13.1 cfm * 0.18 kW/cfm * 2,280 hours = 5,376.24
kWh/year (13.1 cfm from the table 1)
Annual consumption for 3 nozzles = 3* 5,376.24 kWh/year = 16,128.72 kWh/year
It is estimated that a typical venturi nozzle saves 60% of compressed air as it draws in
surrounding air. Therefore, annual usage savings for one spray nozzle with a venturi retrofit =
5,376.24 kWh/year * 0.60 = 3,225.74 kWh/year
Annual electric usage savings for 3 nozzles = 3 * 3,225.74 = 9,677.23 kWh/year
Annual electricity cost savings = 9,677.23 kWh/year * $0.043/ kWh = $416.12/year
Case 2:
For blow off nozzles used:
We know, nozzle hole size = 1/8in., Pressure = 90 psi and total of 50 nozzles
From table 1, we calculate CFM based on the given information:
Total no. of hours each nozzle is used per year = 3*6*3*285 days = 15,390 mins = 256.5 hrs
(Blow off is done for 3 minutes per use, 6 times per shift for a total of 3 shifts/day)
Current annual consumption in 1 nozzle = 23.5 cfm * 0.18 kW/cfm * 256.5 hours = 1,084.99
kWh/year (23.5 cfm from the table 1)
Annual consumption for 50 nozzles = 50*1,084.99 kWh/year = 54,249.75 kWh/year
It is estimated that a typical venturi nozzle saves 60% of compressed air as it draws in
surrounding air. Therefore, annual usage savings for one spray nozzle with a venturi retrofit =
1,084.99 kWh/year * 0.60 = 650.99 kWh/year
Annual electric usage savings for 50 nozzles = 50 * 650.99 = 32,549.70 kWh/year
Annual electricity cost savings = 32,549.70 kWh/year * $0.043/ kWh = $1,399.63/year
Total annual electric usage savings = 9,677.23 kWh/year + 32,549.70 kWh/year = 42,226.93
kWh/year
Total annual electricity cost savings = $416.12/year + $1,399.63/year = $1,815.75/year
Emissions Reduction Analysis
At these usage savings (42,226.93 kWh/year) the annual reduction in carbon dioxide is:
77,698 pounds (pounds of CO2 per kWh = 1.84)
Implementation Cost and Payback
Cost of 1 venturi nozzle = $20
Cost of 53 nozzles = 53 * $20 = $1,060
Estimating 53 hrs time to retrofit 53 nozzles at a unit labor cost of $40/hour, the total labor
cost is = 53 hr * $40/hr = $2,120
Implementation cost = $1,060 + $2,120 = $3,180
Payback period = $3,180/$1,815.75= 1.75 years
References:
http://azglassclasses.com/Reference/CFM-PSI.htm

More Related Content

Similar to Venturi Nozzles

Turbine
TurbineTurbine
Turbine
ratangamit1
 
Reduction in Size of Vars by using Different Materials in Generator
Reduction in Size of Vars by using Different Materials in GeneratorReduction in Size of Vars by using Different Materials in Generator
Reduction in Size of Vars by using Different Materials in Generator
ijtsrd
 
Applied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement TheoryApplied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement Theory
Rekha Rani
 
Energy consumption of house
Energy consumption of houseEnergy consumption of house
Energy consumption of house
Designage Solutions
 
4.8.compressors
4.8.compressors4.8.compressors
4.8.compressors
ABHIJIT NAIR
 
Ah35190193
Ah35190193Ah35190193
Ah35190193
IJERA Editor
 
Consumo de aire cruz jose
Consumo de aire cruz joseConsumo de aire cruz jose
Consumo de aire cruz jose
Jose Cruz
 
Design of active summer cooling system
Design of active summer cooling systemDesign of active summer cooling system
Design of active summer cooling system
Ajay Singh Lodhi
 
Preformence of solar collector by zamir
Preformence of solar collector  by zamirPreformence of solar collector  by zamir
Preformence of solar collector by zamir
Zamir Fatemi
 
Episode 43 : DESIGN of Rotary Vacuum Drum Filter
Episode 43 :  DESIGN of Rotary Vacuum Drum Filter Episode 43 :  DESIGN of Rotary Vacuum Drum Filter
Episode 43 : DESIGN of Rotary Vacuum Drum Filter
SAJJAD KHUDHUR ABBAS
 
Dewatering project pit alam 1 3
Dewatering project pit alam 1   3Dewatering project pit alam 1   3
Dewatering project pit alam 1 3
Muhammad Ichsan
 
Compressed air and refrigeration system
Compressed air and refrigeration systemCompressed air and refrigeration system
Compressed air and refrigeration systemD.Pawan Kumar
 
An Minh Tran - Case 3 - Cheg 407
An Minh Tran - Case 3 - Cheg 407An Minh Tran - Case 3 - Cheg 407
An Minh Tran - Case 3 - Cheg 407AN TRAN
 
Energy Wastage Estimation of a Cold Storage
Energy Wastage Estimation of a Cold StorageEnergy Wastage Estimation of a Cold Storage
Energy Wastage Estimation of a Cold Storage
IJERA Editor
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
RidhoIrawan12
 
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
IRJET Journal
 
Experimental Analysis of Refrigeration system using Microchannel condenser & ...
Experimental Analysis of Refrigeration system using Microchannel condenser & ...Experimental Analysis of Refrigeration system using Microchannel condenser & ...
Experimental Analysis of Refrigeration system using Microchannel condenser & ...
AM Publications
 

Similar to Venturi Nozzles (20)

Turbine
TurbineTurbine
Turbine
 
Reduction in Size of Vars by using Different Materials in Generator
Reduction in Size of Vars by using Different Materials in GeneratorReduction in Size of Vars by using Different Materials in Generator
Reduction in Size of Vars by using Different Materials in Generator
 
Air Compressors
Air CompressorsAir Compressors
Air Compressors
 
Applied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement TheoryApplied Operation Research (AOR) Replacement Theory
Applied Operation Research (AOR) Replacement Theory
 
Energy consumption of house
Energy consumption of houseEnergy consumption of house
Energy consumption of house
 
4.8.compressors
4.8.compressors4.8.compressors
4.8.compressors
 
4.8.compressors
4.8.compressors4.8.compressors
4.8.compressors
 
Ah35190193
Ah35190193Ah35190193
Ah35190193
 
Consumo de aire cruz jose
Consumo de aire cruz joseConsumo de aire cruz jose
Consumo de aire cruz jose
 
Design of active summer cooling system
Design of active summer cooling systemDesign of active summer cooling system
Design of active summer cooling system
 
Preformence of solar collector by zamir
Preformence of solar collector  by zamirPreformence of solar collector  by zamir
Preformence of solar collector by zamir
 
Episode 43 : DESIGN of Rotary Vacuum Drum Filter
Episode 43 :  DESIGN of Rotary Vacuum Drum Filter Episode 43 :  DESIGN of Rotary Vacuum Drum Filter
Episode 43 : DESIGN of Rotary Vacuum Drum Filter
 
Dewatering project pit alam 1 3
Dewatering project pit alam 1   3Dewatering project pit alam 1   3
Dewatering project pit alam 1 3
 
Aeration of storage structures
Aeration of storage structuresAeration of storage structures
Aeration of storage structures
 
Compressed air and refrigeration system
Compressed air and refrigeration systemCompressed air and refrigeration system
Compressed air and refrigeration system
 
An Minh Tran - Case 3 - Cheg 407
An Minh Tran - Case 3 - Cheg 407An Minh Tran - Case 3 - Cheg 407
An Minh Tran - Case 3 - Cheg 407
 
Energy Wastage Estimation of a Cold Storage
Energy Wastage Estimation of a Cold StorageEnergy Wastage Estimation of a Cold Storage
Energy Wastage Estimation of a Cold Storage
 
Proposal Wide Blower No.1 & 2 with inverter
Proposal Wide Blower No.1 & 2  with inverterProposal Wide Blower No.1 & 2  with inverter
Proposal Wide Blower No.1 & 2 with inverter
 
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
IRJET- Experimental Investigation of Flow through Perforated Plate in Conical...
 
Experimental Analysis of Refrigeration system using Microchannel condenser & ...
Experimental Analysis of Refrigeration system using Microchannel condenser & ...Experimental Analysis of Refrigeration system using Microchannel condenser & ...
Experimental Analysis of Refrigeration system using Microchannel condenser & ...
 

Recently uploaded

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
Pratik Pawar
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
Robbie Edward Sayers
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
ViniHema
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
Kamal Acharya
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation & Control
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
Pipe Restoration Solutions
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
Kamal Acharya
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
seandesed
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Sreedhar Chowdam
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
Intella Parts
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
obonagu
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
TeeVichai
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
ShahidSultan24
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
Kamal Acharya
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
bakpo1
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
AJAYKUMARPUND1
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
gdsczhcet
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
AafreenAbuthahir2
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
SamSarthak3
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Teleport Manpower Consultant
 

Recently uploaded (20)

weather web application report.pdf
weather web application report.pdfweather web application report.pdf
weather web application report.pdf
 
HYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generationHYDROPOWER - Hydroelectric power generation
HYDROPOWER - Hydroelectric power generation
 
power quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptxpower quality voltage fluctuation UNIT - I.pptx
power quality voltage fluctuation UNIT - I.pptx
 
Student information management system project report ii.pdf
Student information management system project report ii.pdfStudent information management system project report ii.pdf
Student information management system project report ii.pdf
 
Water Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdfWater Industry Process Automation and Control Monthly - May 2024.pdf
Water Industry Process Automation and Control Monthly - May 2024.pdf
 
The Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdfThe Benefits and Techniques of Trenchless Pipe Repair.pdf
The Benefits and Techniques of Trenchless Pipe Repair.pdf
 
Courier management system project report.pdf
Courier management system project report.pdfCourier management system project report.pdf
Courier management system project report.pdf
 
Architectural Portfolio Sean Lockwood
Architectural Portfolio Sean LockwoodArchitectural Portfolio Sean Lockwood
Architectural Portfolio Sean Lockwood
 
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&BDesign and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
Design and Analysis of Algorithms-DP,Backtracking,Graphs,B&B
 
Forklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella PartsForklift Classes Overview by Intella Parts
Forklift Classes Overview by Intella Parts
 
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
在线办理(ANU毕业证书)澳洲国立大学毕业证录取通知书一模一样
 
Railway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdfRailway Signalling Principles Edition 3.pdf
Railway Signalling Principles Edition 3.pdf
 
addressing modes in computer architecture
addressing modes  in computer architectureaddressing modes  in computer architecture
addressing modes in computer architecture
 
Automobile Management System Project Report.pdf
Automobile Management System Project Report.pdfAutomobile Management System Project Report.pdf
Automobile Management System Project Report.pdf
 
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
一比一原版(SFU毕业证)西蒙菲莎大学毕业证成绩单如何办理
 
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
Pile Foundation by Venkatesh Taduvai (Sub Geotechnical Engineering II)-conver...
 
Gen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdfGen AI Study Jams _ For the GDSC Leads in India.pdf
Gen AI Study Jams _ For the GDSC Leads in India.pdf
 
WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234WATER CRISIS and its solutions-pptx 1234
WATER CRISIS and its solutions-pptx 1234
 
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdfAKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
AKS UNIVERSITY Satna Final Year Project By OM Hardaha.pdf
 
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdfTop 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
Top 10 Oil and Gas Projects in Saudi Arabia 2024.pdf
 

Venturi Nozzles

  • 1. Use venturi amplifier air nozzle instead of compressed air Recommended Action It is recommended to use an alternate method for supplying compressed air using venturi air amplifier nozzles instead of spray nozzle. These nozzles use a small amount of compressed air and produce high energy and high velocity air flow as output. Such nozzles have produced significant savings for large manufacturing companies by reducing their compressed air usage. Energy Cost Savings Case 1: For blow off nozzles: We know, nozzle hole size = 3/32in., Pressure = 90 psi and total of 3 nozzles From table 1, we calculate CFM based on the given information: CFM v/s PSI For Nozzles CFM Free Air Flow @ Nozzle Diameter (inch) PSI 1/64 1/32 3/64 1/16 3/32 1/8 3/16 1/4 1 0.03 0.11 0.2 0.4 1 1.7 3.9 6.8 5 0.03 0.24 0.5 1 2.2 3.9 8.7 15.4 10 0.06 0.34 0.8 1.4 3.1 5.4 12.3 21.8 15 0.1 0.042 0.9 1.6 3.7 6.6 15 26.7 20 0.12 0.48 1.1 1.9 4.2 7.7 17.1 30.8 25 0.13 0.54 1.2 2.2 4.7 8.6 19.4 34.5 30 0.16 0.63 1.4 2.5 5.6 10 22.5 40 40 0.19 0.77 1.7 3.1 6.8 12.3 27.5 49.1 50 0.22 0.91 2 3.6 8.2 14.5 32.8 58.2 60 0.26 1.05 2.3 4.2 9.4 16.8 37.5 67 70 0.29 1.19 2.7 4.8 10.7 19 43 76 80 0.33 1.33 3 5.3 11.9 21.2 47.5 85 90 0.36 1.47 3.3 5.9 13.1 23.5 52.5 94 100 0.4 1.61 3.7 6.4 14.5 25.8 58.3 103 110 0.43 1.76 3.9 7 15.7 28 63 112 120 0.47 1.9 4.3 7.6 17 30.2 68 121 130 0.5 2.04 4.6 8.1 18.2 32.4 73 130 140 0.54 2.17 4.9 8.7 19.5 34.5 78 138
  • 2. 150 0.57 2.33 5.2 9.2 20.7 36.7 83 147 175 0.66 2.65 5.9 10.6 23.8 42.1 85 169 200 0.76 3.07 6.9 12.2 27.5 48.7 110 195 Table 1 (see reference) Total no. of hours each nozzle is used per year = 6,840 hrs*0.5 = 3,420 hrs (Blow off is done for 0.5 sec at every other second) Current annual consumption in 1 nozzle = 13.1 cfm * 0.18 kW/cfm * 2,280 hours = 5,376.24 kWh/year (13.1 cfm from the table 1) Annual consumption for 3 nozzles = 3* 5,376.24 kWh/year = 16,128.72 kWh/year It is estimated that a typical venturi nozzle saves 60% of compressed air as it draws in surrounding air. Therefore, annual usage savings for one spray nozzle with a venturi retrofit = 5,376.24 kWh/year * 0.60 = 3,225.74 kWh/year Annual electric usage savings for 3 nozzles = 3 * 3,225.74 = 9,677.23 kWh/year Annual electricity cost savings = 9,677.23 kWh/year * $0.043/ kWh = $416.12/year Case 2: For blow off nozzles used: We know, nozzle hole size = 1/8in., Pressure = 90 psi and total of 50 nozzles From table 1, we calculate CFM based on the given information: Total no. of hours each nozzle is used per year = 3*6*3*285 days = 15,390 mins = 256.5 hrs (Blow off is done for 3 minutes per use, 6 times per shift for a total of 3 shifts/day) Current annual consumption in 1 nozzle = 23.5 cfm * 0.18 kW/cfm * 256.5 hours = 1,084.99 kWh/year (23.5 cfm from the table 1) Annual consumption for 50 nozzles = 50*1,084.99 kWh/year = 54,249.75 kWh/year It is estimated that a typical venturi nozzle saves 60% of compressed air as it draws in surrounding air. Therefore, annual usage savings for one spray nozzle with a venturi retrofit = 1,084.99 kWh/year * 0.60 = 650.99 kWh/year Annual electric usage savings for 50 nozzles = 50 * 650.99 = 32,549.70 kWh/year Annual electricity cost savings = 32,549.70 kWh/year * $0.043/ kWh = $1,399.63/year
  • 3. Total annual electric usage savings = 9,677.23 kWh/year + 32,549.70 kWh/year = 42,226.93 kWh/year Total annual electricity cost savings = $416.12/year + $1,399.63/year = $1,815.75/year Emissions Reduction Analysis At these usage savings (42,226.93 kWh/year) the annual reduction in carbon dioxide is: 77,698 pounds (pounds of CO2 per kWh = 1.84) Implementation Cost and Payback Cost of 1 venturi nozzle = $20 Cost of 53 nozzles = 53 * $20 = $1,060 Estimating 53 hrs time to retrofit 53 nozzles at a unit labor cost of $40/hour, the total labor cost is = 53 hr * $40/hr = $2,120 Implementation cost = $1,060 + $2,120 = $3,180 Payback period = $3,180/$1,815.75= 1.75 years References: http://azglassclasses.com/Reference/CFM-PSI.htm