This document contains information about the progress of water utility installation work for the Terrazas de Lima Norte development project. It includes details such as the total number of water utility boxes planned and installed, descriptions of the work completed, and metrics on the installation of water utility boxes for week 5 of the project. Key facts are that 86 out of a planned 283 water utility boxes have been installed, excavated, and covered as of the report date of April 5, 2021 for the development's Phase V.