Risk assessment ‘The Move’
Hazard What is at risk Likelihood of
hazard
1 = least likely
Severity of
outcome
1= least likely
Risk level
(1-5)
Likelihood
+severity +2
Measure to
control risk
Person responsible
for controlling risk
Car park:
Active cars
Cast
Crew
Equipment 4 2 6
Keeping an eye of
the surrounding
at all times
Everyone
Bedroom:
Wires/
Doors/
Cameras/
Cast/
Crew/
Equipment 2 1 4
Watch the
surroundings
carefully, mostly
lights and
tripping hazards
Tuck and hide
wires avoid
tripping hazards
Everyone
Woods/lake:
Branches
Dogs/animals
Water
Cast/
Crew/
Equipment 5 2 7
Keep eyes out for
any animals about.
Move tripping
hazards
Everyone

The move risk assessment

  • 1.
    Risk assessment ‘TheMove’ Hazard What is at risk Likelihood of hazard 1 = least likely Severity of outcome 1= least likely Risk level (1-5) Likelihood +severity +2 Measure to control risk Person responsible for controlling risk Car park: Active cars Cast Crew Equipment 4 2 6 Keeping an eye of the surrounding at all times Everyone Bedroom: Wires/ Doors/ Cameras/ Cast/ Crew/ Equipment 2 1 4 Watch the surroundings carefully, mostly lights and tripping hazards Tuck and hide wires avoid tripping hazards Everyone Woods/lake: Branches Dogs/animals Water Cast/ Crew/ Equipment 5 2 7 Keep eyes out for any animals about. Move tripping hazards Everyone