SlideShare a Scribd company logo
1 of 3
Download to read offline
DAMAGED AND COLLAPSED INTERLOCKING CONCRETE PAVEMENT IN OUTFALL 10
I. AN OVERVIEW
On 7th November 2012 at 10:56 AM a portion of an interlocking concrete pavement in
Outfall 10 was found to be damaged where concrete blocks had been eroded directly to
the seabed due to unknown cause. The said collapsed area had also resulted creating
an open hole which risked not only the public but the entire outfall structure as well.
A comprehensive Defect Notification Report No. 460 dated on 7th November 2012 with
Reference No. MU-DL-01-2717 (see Appendix –A) was immediately submitted to
Parsons International Limited by Dripco Contracting Company, detailing the present
conditions of Outfall 10 and how safety was ensured temporarily in the area.
II. MAJOR CAUSES OF CONCRETE PAVEMENT DISINTEGRATION
As instructed by our Consultants, Parsons International Limited, an actual site visit
was carried out on 11th November 2012 to re-verify the main causes of the sudden
collapse of Outfall structure, and these are as follows:
A. Soil sedimentation and water erosion
Soil sedimentation is the result of water erosion. Erosion removes soil from the land
and carries it away by water action. It is the process in which soil particles are
carried from its point of origin by either natural or human reasons-enhanced
processes is deposited elsewhere on land surfaces or in water bodies. When the
water drops the soil, it settles into the bottom of the waterway. The soil particles
that are accumulated in the bottom of the waterway are known as sediments. The
process of depositing the sediment is known as sedimentation.
The affected side and damaged area of Outfall 10 as shown in Appendix -A was built
near an open dock or harbor where sea water underneath cannot be controlled and
has direct contact with the soil supporting the outfall structure. The direct contact of
water to the soil has caused the foundation to be weak due to slow sedimentation
and erosion that have been going on through time of contact. The soil sediments are
deliberately washed out and subsequently eroded by the water leading to
disintegrate the outfall underlying groundwork or foundation, thus concluding to
weaken the support of the its structure in general.
1
B. Past construction of the new boundary wall
Soil Erosion is the process by which soil and rock are removed from the Earth's
surface by natural processes or factors such as wind or water flow, and
then transported and deposited in other locations.
While soil erosion is considered as natural process; however human activities have
seemingly increased and contributed to excessive problems brought by soil erosion
and further leading to disturbance and disintegration of the soil natural layer
through many ongoing industrial construction works such as excavations in
particular.
Relating to the above given facts, the past excavation work due to construction of
the new boundary wall within the perimeter of Outfall 10 area sometime on
September 2010 by Ghantoot Company cannot be denied as one contributory
factor to the cause as to why the outfall structure and its foundation had subsided
through time.
This site issue was reported to Parsons’ Site Office through Defect Notification
Report No. 285 dated on 18th September 2010, MU-DL-01-1860 (see Appendix –B).
III. SOLUTIONS AND RECOMMENDATIONS (refer to Appendix-C)
A. Installation of a temporary sheet pile to prevent the soil from further eroding or
collapse during excavation work as preparation to retaining wall construction.
B. Construction of retaining wall
A retaining wall has to be constructed beside the existing boundary wall to
protect the premises of Outfall 10. This wall will barrier and prevent the direct
contact between sea water and the underlying groundwork or foundation which
support the outfall structure.
C. Refilling of the displaced soil underneath
The large volume of the displaced soil must be refilled and compacted to create a
strong foundation or base for the reconstruction of the interlocking concrete
pavement.
D. Reconstruction of the interlocking concrete pavement
2
IV. CONCLUSION
The damaged and eroded interlocking concrete pavement in Outfall 10 was due to
natural reasons brought by the processes of soil sedimentation and erosion which
led to weaken the groundwork or the natural layer of soil supporting the entire
outfall structure.
The aftermath or effects of human activities in nearby areas of Outfall 10 due to past
construction and excavation work made on September 2010 had also enhanced the
natural processes of soil erosion and sedimentation to occur; the excessive
mechanical excavations had resulted to disintegrate and disturbed the natural
layers of the soil in the area.
Public safety is presently at risk and the degree of damage caused by the Earth’s
physical and natural processes brought by human activities will then lead to severe
level if not repaired immediately or no solutions shall be considered to counteract
the main cause of the problem. This site issue therefore calls for an urgent and
competent action from the concern authorities.
3

More Related Content

What's hot

case study on types of falulier
case study on types of faluliercase study on types of falulier
case study on types of falulierAbhishek Mangukiya
 
Introduction to Geo technical engineering
Introduction to Geo technical engineeringIntroduction to Geo technical engineering
Introduction to Geo technical engineeringashsatya
 
Weathering, Erosion, Deposition, and Karst Topography
Weathering, Erosion, Deposition, and Karst TopographyWeathering, Erosion, Deposition, and Karst Topography
Weathering, Erosion, Deposition, and Karst Topographyrebelbrindley
 
Weathering and erosion
Weathering and erosionWeathering and erosion
Weathering and erosionAmmadkhan69
 
Soil formation
Soil formationSoil formation
Soil formationetu mony
 
Weathering, Erosion, Mass Wasting.
Weathering, Erosion, Mass Wasting.Weathering, Erosion, Mass Wasting.
Weathering, Erosion, Mass Wasting.Russel Corcino
 
The study on construction of artificial island by Ahmad Hussain
The study on construction of artificial island by Ahmad HussainThe study on construction of artificial island by Ahmad Hussain
The study on construction of artificial island by Ahmad HussainMohammad Ahmad Hussain
 
Geologicalprocesses
GeologicalprocessesGeologicalprocesses
Geologicalprocessesmartagar78
 
Erosion and transportation
Erosion  and transportationErosion  and transportation
Erosion and transportationMarsamkayee
 
Kiggo Stone Excavation Scoping Visit
Kiggo Stone Excavation Scoping VisitKiggo Stone Excavation Scoping Visit
Kiggo Stone Excavation Scoping VisitRobert Ddamulira
 
Weathering and erosion introduction
Weathering and erosion introductionWeathering and erosion introduction
Weathering and erosion introductionmrcoyleteach
 
Coastal Landscapes and How they Must Adapt to Climate Change
Coastal Landscapes and How they Must Adapt to Climate ChangeCoastal Landscapes and How they Must Adapt to Climate Change
Coastal Landscapes and How they Must Adapt to Climate ChangeCarter Craft
 
Research paper of leaning tower of pisa
Research paper of leaning tower of pisaResearch paper of leaning tower of pisa
Research paper of leaning tower of pisaRushabh shah
 
Impacts of Weathering and Erosion on Human Activities
Impacts of Weathering and Erosion on Human Activities Impacts of Weathering and Erosion on Human Activities
Impacts of Weathering and Erosion on Human Activities Hamna_Ahmed
 
Exogenic processes
Exogenic processesExogenic processes
Exogenic processesJohnEun4
 
Science Project - Chintan Shah 8-1
Science Project - Chintan Shah 8-1Science Project - Chintan Shah 8-1
Science Project - Chintan Shah 8-1Chintan Shah
 

What's hot (20)

case study on types of falulier
case study on types of faluliercase study on types of falulier
case study on types of falulier
 
Introduction to Geo technical engineering
Introduction to Geo technical engineeringIntroduction to Geo technical engineering
Introduction to Geo technical engineering
 
Weathering, Erosion, Deposition, and Karst Topography
Weathering, Erosion, Deposition, and Karst TopographyWeathering, Erosion, Deposition, and Karst Topography
Weathering, Erosion, Deposition, and Karst Topography
 
Weathering and erosion
Weathering and erosionWeathering and erosion
Weathering and erosion
 
Soil formation
Soil formationSoil formation
Soil formation
 
Weathering, Erosion, Mass Wasting.
Weathering, Erosion, Mass Wasting.Weathering, Erosion, Mass Wasting.
Weathering, Erosion, Mass Wasting.
 
The study on construction of artificial island by Ahmad Hussain
The study on construction of artificial island by Ahmad HussainThe study on construction of artificial island by Ahmad Hussain
The study on construction of artificial island by Ahmad Hussain
 
Geologicalprocesses
GeologicalprocessesGeologicalprocesses
Geologicalprocesses
 
Exogenic Processes
Exogenic Processes Exogenic Processes
Exogenic Processes
 
Kabaka’S Lake
Kabaka’S LakeKabaka’S Lake
Kabaka’S Lake
 
Erosion and transportation
Erosion  and transportationErosion  and transportation
Erosion and transportation
 
Exogenic processe sppt
Exogenic processe spptExogenic processe sppt
Exogenic processe sppt
 
Kiggo Stone Excavation Scoping Visit
Kiggo Stone Excavation Scoping VisitKiggo Stone Excavation Scoping Visit
Kiggo Stone Excavation Scoping Visit
 
Weathering and erosion introduction
Weathering and erosion introductionWeathering and erosion introduction
Weathering and erosion introduction
 
Coastal Landscapes and How they Must Adapt to Climate Change
Coastal Landscapes and How they Must Adapt to Climate ChangeCoastal Landscapes and How they Must Adapt to Climate Change
Coastal Landscapes and How they Must Adapt to Climate Change
 
Research paper of leaning tower of pisa
Research paper of leaning tower of pisaResearch paper of leaning tower of pisa
Research paper of leaning tower of pisa
 
Impacts of Weathering and Erosion on Human Activities
Impacts of Weathering and Erosion on Human Activities Impacts of Weathering and Erosion on Human Activities
Impacts of Weathering and Erosion on Human Activities
 
Exogenic processes
Exogenic processesExogenic processes
Exogenic processes
 
Science Project - Chintan Shah 8-1
Science Project - Chintan Shah 8-1Science Project - Chintan Shah 8-1
Science Project - Chintan Shah 8-1
 
EXOGENIC PROCESS PPT
EXOGENIC PROCESS PPTEXOGENIC PROCESS PPT
EXOGENIC PROCESS PPT
 

Similar to TECHNICAL REPORT.OUTFALL 10

soil Liquefaction in Geotechnical Engineering
soil Liquefaction in Geotechnical Engineeringsoil Liquefaction in Geotechnical Engineering
soil Liquefaction in Geotechnical EngineeringTalha Khokhar
 
Foundation treatment for concrete dams1.pptx
Foundation treatment for concrete dams1.pptxFoundation treatment for concrete dams1.pptx
Foundation treatment for concrete dams1.pptxMekuanintShitaw
 
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...THE NORTHCAP UNIVERSITY
 
Understanding soil risks and hazards
Understanding soil risks and hazardsUnderstanding soil risks and hazards
Understanding soil risks and hazardsSuper Arc Consultant
 
Ge ch.1 introduction.pptx
Ge ch.1 introduction.pptxGe ch.1 introduction.pptx
Ge ch.1 introduction.pptxsjshukla
 
C Sachpazis: Soil liquefaction potential assessment for a ccgt power plant in...
C Sachpazis: Soil liquefaction potential assessment for a ccgt power plant in...C Sachpazis: Soil liquefaction potential assessment for a ccgt power plant in...
C Sachpazis: Soil liquefaction potential assessment for a ccgt power plant in...Dr.Costas Sachpazis
 
Factors to considered in foundation design and numerical based on bis method
Factors to considered in foundation design and numerical based on bis methodFactors to considered in foundation design and numerical based on bis method
Factors to considered in foundation design and numerical based on bis methodErankajKumar
 
Design_and_Construction_of_Embankment_Da (2).pdf
Design_and_Construction_of_Embankment_Da (2).pdfDesign_and_Construction_of_Embankment_Da (2).pdf
Design_and_Construction_of_Embankment_Da (2).pdfYeshiharegAlemu
 
Design_and_Construction_of_Embankment_Da (1).pdf
Design_and_Construction_of_Embankment_Da (1).pdfDesign_and_Construction_of_Embankment_Da (1).pdf
Design_and_Construction_of_Embankment_Da (1).pdfYeshiharegAlemu
 
Factors to consider in foundation design
Factors to consider in foundation designFactors to consider in foundation design
Factors to consider in foundation designMushtaq Zaib
 
Mitigation strategies for flooding pdf
Mitigation strategies for flooding pdfMitigation strategies for flooding pdf
Mitigation strategies for flooding pdfDhanashri Mirajkar
 
Civil Engineering-Revision
Civil Engineering-RevisionCivil Engineering-Revision
Civil Engineering-RevisionPATRICK MAELO
 
What are 3 engineering applications of the coefficient of permeabili.pdf
What are 3 engineering applications of the coefficient of permeabili.pdfWhat are 3 engineering applications of the coefficient of permeabili.pdf
What are 3 engineering applications of the coefficient of permeabili.pdfanandtradingco
 

Similar to TECHNICAL REPORT.OUTFALL 10 (20)

soil Liquefaction in Geotechnical Engineering
soil Liquefaction in Geotechnical Engineeringsoil Liquefaction in Geotechnical Engineering
soil Liquefaction in Geotechnical Engineering
 
Foundation treatment for concrete dams1.pptx
Foundation treatment for concrete dams1.pptxFoundation treatment for concrete dams1.pptx
Foundation treatment for concrete dams1.pptx
 
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
Review of Causes of Foundation Failures and Their Possible Preventive and Rem...
 
Understanding soil risks and hazards
Understanding soil risks and hazardsUnderstanding soil risks and hazards
Understanding soil risks and hazards
 
Liquefaction of soil
Liquefaction of soilLiquefaction of soil
Liquefaction of soil
 
Ge ch.1 introduction.pptx
Ge ch.1 introduction.pptxGe ch.1 introduction.pptx
Ge ch.1 introduction.pptx
 
C Sachpazis: Soil liquefaction potential assessment for a ccgt power plant in...
C Sachpazis: Soil liquefaction potential assessment for a ccgt power plant in...C Sachpazis: Soil liquefaction potential assessment for a ccgt power plant in...
C Sachpazis: Soil liquefaction potential assessment for a ccgt power plant in...
 
Dam engineering i 5
Dam engineering i 5Dam engineering i 5
Dam engineering i 5
 
Embankment lecture 3
Embankment lecture 3Embankment lecture 3
Embankment lecture 3
 
Factors to considered in foundation design and numerical based on bis method
Factors to considered in foundation design and numerical based on bis methodFactors to considered in foundation design and numerical based on bis method
Factors to considered in foundation design and numerical based on bis method
 
Design_and_Construction_of_Embankment_Da (2).pdf
Design_and_Construction_of_Embankment_Da (2).pdfDesign_and_Construction_of_Embankment_Da (2).pdf
Design_and_Construction_of_Embankment_Da (2).pdf
 
Design_and_Construction_of_Embankment_Da (1).pdf
Design_and_Construction_of_Embankment_Da (1).pdfDesign_and_Construction_of_Embankment_Da (1).pdf
Design_and_Construction_of_Embankment_Da (1).pdf
 
coffer Dam.pptx
coffer Dam.pptxcoffer Dam.pptx
coffer Dam.pptx
 
Factors to consider in foundation design
Factors to consider in foundation designFactors to consider in foundation design
Factors to consider in foundation design
 
Mitigation strategies for flooding pdf
Mitigation strategies for flooding pdfMitigation strategies for flooding pdf
Mitigation strategies for flooding pdf
 
MP.pptx
MP.pptxMP.pptx
MP.pptx
 
Breakwater
BreakwaterBreakwater
Breakwater
 
Ceng chapter 1
Ceng chapter 1Ceng chapter 1
Ceng chapter 1
 
Civil Engineering-Revision
Civil Engineering-RevisionCivil Engineering-Revision
Civil Engineering-Revision
 
What are 3 engineering applications of the coefficient of permeabili.pdf
What are 3 engineering applications of the coefficient of permeabili.pdfWhat are 3 engineering applications of the coefficient of permeabili.pdf
What are 3 engineering applications of the coefficient of permeabili.pdf
 

TECHNICAL REPORT.OUTFALL 10

  • 1. DAMAGED AND COLLAPSED INTERLOCKING CONCRETE PAVEMENT IN OUTFALL 10 I. AN OVERVIEW On 7th November 2012 at 10:56 AM a portion of an interlocking concrete pavement in Outfall 10 was found to be damaged where concrete blocks had been eroded directly to the seabed due to unknown cause. The said collapsed area had also resulted creating an open hole which risked not only the public but the entire outfall structure as well. A comprehensive Defect Notification Report No. 460 dated on 7th November 2012 with Reference No. MU-DL-01-2717 (see Appendix –A) was immediately submitted to Parsons International Limited by Dripco Contracting Company, detailing the present conditions of Outfall 10 and how safety was ensured temporarily in the area. II. MAJOR CAUSES OF CONCRETE PAVEMENT DISINTEGRATION As instructed by our Consultants, Parsons International Limited, an actual site visit was carried out on 11th November 2012 to re-verify the main causes of the sudden collapse of Outfall structure, and these are as follows: A. Soil sedimentation and water erosion Soil sedimentation is the result of water erosion. Erosion removes soil from the land and carries it away by water action. It is the process in which soil particles are carried from its point of origin by either natural or human reasons-enhanced processes is deposited elsewhere on land surfaces or in water bodies. When the water drops the soil, it settles into the bottom of the waterway. The soil particles that are accumulated in the bottom of the waterway are known as sediments. The process of depositing the sediment is known as sedimentation. The affected side and damaged area of Outfall 10 as shown in Appendix -A was built near an open dock or harbor where sea water underneath cannot be controlled and has direct contact with the soil supporting the outfall structure. The direct contact of water to the soil has caused the foundation to be weak due to slow sedimentation and erosion that have been going on through time of contact. The soil sediments are deliberately washed out and subsequently eroded by the water leading to disintegrate the outfall underlying groundwork or foundation, thus concluding to weaken the support of the its structure in general. 1
  • 2. B. Past construction of the new boundary wall Soil Erosion is the process by which soil and rock are removed from the Earth's surface by natural processes or factors such as wind or water flow, and then transported and deposited in other locations. While soil erosion is considered as natural process; however human activities have seemingly increased and contributed to excessive problems brought by soil erosion and further leading to disturbance and disintegration of the soil natural layer through many ongoing industrial construction works such as excavations in particular. Relating to the above given facts, the past excavation work due to construction of the new boundary wall within the perimeter of Outfall 10 area sometime on September 2010 by Ghantoot Company cannot be denied as one contributory factor to the cause as to why the outfall structure and its foundation had subsided through time. This site issue was reported to Parsons’ Site Office through Defect Notification Report No. 285 dated on 18th September 2010, MU-DL-01-1860 (see Appendix –B). III. SOLUTIONS AND RECOMMENDATIONS (refer to Appendix-C) A. Installation of a temporary sheet pile to prevent the soil from further eroding or collapse during excavation work as preparation to retaining wall construction. B. Construction of retaining wall A retaining wall has to be constructed beside the existing boundary wall to protect the premises of Outfall 10. This wall will barrier and prevent the direct contact between sea water and the underlying groundwork or foundation which support the outfall structure. C. Refilling of the displaced soil underneath The large volume of the displaced soil must be refilled and compacted to create a strong foundation or base for the reconstruction of the interlocking concrete pavement. D. Reconstruction of the interlocking concrete pavement 2
  • 3. IV. CONCLUSION The damaged and eroded interlocking concrete pavement in Outfall 10 was due to natural reasons brought by the processes of soil sedimentation and erosion which led to weaken the groundwork or the natural layer of soil supporting the entire outfall structure. The aftermath or effects of human activities in nearby areas of Outfall 10 due to past construction and excavation work made on September 2010 had also enhanced the natural processes of soil erosion and sedimentation to occur; the excessive mechanical excavations had resulted to disintegrate and disturbed the natural layers of the soil in the area. Public safety is presently at risk and the degree of damage caused by the Earth’s physical and natural processes brought by human activities will then lead to severe level if not repaired immediately or no solutions shall be considered to counteract the main cause of the problem. This site issue therefore calls for an urgent and competent action from the concern authorities. 3