SlideShare a Scribd company logo
Page 1 of 8
Md. Tanzeer Akhter
Mobile: +919540394540
Email: tanzeer.akhter@gmail.com
JOB OBJECTIVE
Aspiring for a technically challenging position where I would be able to utilize my strong
technical background in the field of civil and Telecommunication along with my internal
personal skills to develop & deploy various projects and serve the Telecom Industry with the
best of my efforts and help flourish the Telecom Technologies.
Professional Synopsis
A technocrat with more than 12.1 years of experience in the areas of Project Operation
Maintenance and Management, Civil Infrastructure (Active & Passive Activities) & CADD
(2D/3D) and Team Management, Material Management, Site Measurements Verification,
Vendor Selection & Billing Etc. Presently associated with Samax Telecom Pvt. Ltd.
As Assist Project Manager. Total more than 1 years of experience in TI expertise in deploying
project execution solutions by conducting project planning sessions with the project management
team to ensure Project / Program compliance to budget, quality standards and customer
requirements. Proficient in design, development, implementation, secure architecture and
management of Enterprise Applications. Strong management, collaboration & team building skills
with proficiency in grasping new technical concepts quickly.
AREAS OF EXPERTISE
Functional
Project Management
 Planning and networking with the project team and conducting periodic project progress review meetings
to ensure effective delivery of project solutions in line with time and quality parameters.
 Delivering and implementing the project as per scheduled deadlines; extending post-implementation and
maintenance support to the civil support team and clients.
Civil Management
 Telecommunication Office Building Construction and Maintenance Work like BSC, MSC,
Equipment rooms BTS Room of TSP Works, Civil, Electrical and Fabrication and Finishing works.
 Coordinate with Architect, Civil, Electrical, Municipal Corporation Department, Electricity Board,
Department of Pollution Control, Vendors and our Engineer in-charge etc.
 Documentation with Survey Report, Structural Drawing with PAT and FAT reports, with JMR and
CAD-As Built Drawing etc.
 Mapping client/business requirements and providing customized civil solutions involving finalization of
Civil Engineers survey with RF Engineers, project specifications and selection of appropriate techniques.
 Developing internal specifications outlining the overall design and functionality of the project.
Team Management
 Identifying and implementing strategies for building team effectiveness by promoting a spirit of
cooperation between our Team members and vendors teams Members.
 Determining training needs of analysts and conducting suitable training programs to enhance their
operational efficiency leading to increased productivity.
ORGANISATIONAL EXPERIENCE
Page 2 of 8
RESPONSIBILITIES / JOB PROFILES
SaMax Telecom Pvt. Ltd.
(June-2015 to Till Date)
Client:- Vodafone LTE (Delhi/NCR) & HUAWEI-Telenor (B&J and UPW).
Project:- I&C TI LTE, RF Survey, RFI Survey & EMF Survey.
Designation:- Assist Manager Projects (TI LEAD)
Job Profile:- Project Execution, Maintain Quality Work, EHS compliance , Customer Meeting, Site
surprise Visiting and Verifying all particulars are worked well, and it has on good
working condition like;- Indoor/ Outdoor compliance Etc.
Circle:- Delhi/NCR, B&J, and UPW,
Location:- Delhi/NCR, B&J, and UPW,
Period:- From June-2015 to Till.
Training:- EHS/Quality/CBTHR/RF/RFI/TI.
Team Strength..
⇔ I&C (TI all activity) RF, RFI, EMF, For Vodafone (Delhi/NCR) & Telenor (Bihar & Jharkhand / UPW)
⇔ TI Team size: 4 Teamth.
(4 Engineers (TL), 08 Technicians, 04 Riggers) for Vodafone 4G Delhi/NCR
⇔ TI Team size: 3 Teamth.
(3 Engineers (TL), 06 Technicians, 03 Riggers) for Telenor B&J.
⇔ RF Team 06 Engg. For Telenor (B&J)
⇔ DT Team 05 Engg. & 05 Rigger For Vodafone (Delhi/NCR)
⇔ DT Team 04 Engg. & 04 Rigger For Telenor (UPW)
⇔ Active participation in Project Roll-Out Planning with PM’s/Coordinators for proper execution of project.
⇔ Providing support to Optimizer Teams, implementation, planning & Manpower team for smooth operation of
project.
⇔ Vender Selection:- Vendor verification by his required document e.g. previous P.O., Work experience, Client
details, Yearly turnover, Financially strong.
⇔ Responsible for coordinating with the corporate and higher management for project execution.
⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities.
⇔ Manpower management for the execution of site activities.
PRIME SUPPORT & SERVICES PRIVATE LIMITED
Serving Excellence
(Dec-2010 to Till-2014)
Client:- IDEA, VODAFONE (India) & HUAWEI-NCELL (Nepal)
Project:- JSS, IMPLEMENTATION & MAINTENANCE OF MSC & BSC. NETWORK
SOLUTION (2G/3G, DT), & EMF SURVEY.
Designation:- Manager Projects.
Job Profile:- Project Execution, Client Meeting, Site Visiting and Verifying all particulars are worked
well, looking good and it has on good working condition like;- Indoor/ Outdoor Civil,
Electrical, AC, Fabrication works, Complaints & Customer Feedback Studies, Client
Meeting Etc.
Circle:- New Delhi, UP, HP, & Kathmandu, Dhualagiri, Maygdi, Beni.
Location:- India & Kathmandu (Nepal)
Period:- Dec-2010 to till
INDIA’s Project;
⇔ 01. RF& Drive Test Optimization FOR IDEA (Delhi/NCR, Haryana, Rajasthan, MP, UPE/UPW)
⇔ 02. EMF SURVEY & DOCUMENTATION FOR IDEA (DELHI/NCR, HARYANA, & UPW)
⇔ 03. JSS, IMPLEMENTATION & MAINTENANCE OF MSC & BSC
⇔ 04. Team size: 55th.
(03 Coordinator, 9 Civil, 17 RF, & 8 DT, 4 Supervisor, 4 Electrical, 10 Rigger).
⇔ Civil Maintenance Works :- Site visit for check all the Damaged, Pending, Missing and Unfinished works and rest
of the maintenance related works like Coloring, Plaster (Damage/Scratched/ Demolished), Plaster of Paris
(Sealant/ Damage/ Scratched), Ceiling, False Ceiling (Cracks/ Leveling & finishing), Flooring
(Tiles/Marbles/Wooden) fixing, finishing, polishing in Proper way, Doors & Windows (Steel/ Iron/ Aluminum/
Wooden/ Fiber etc), Bathrooms & Kitchen fit out, Glasses fit out, Fabrication works Railings, Stair case, are on
good, well and working condition,
Page 3 of 8
⇔ Electricals Maintenance Works :- Outdoor / Indoor Lighting system, False & Open wiring not used appears,
Fire Alarm systems, CC TV Cameras System, Control room Facilities are full fill, all electrical Switches MCB’s
are working Good,.
⇔ Our major client is IDEA of the PAN India, we have currently project of Drive Test Optimization Delhi/NCR,
Haryana, Rajasthan and Rx & Tx Survey in Hayana, and all UP’s circle (all activities).
⇔ Active participation in Project Roll-Out Planning with PM’s/Coordinators for proper execution of project.
⇔ Providing support to Optimizer Teams, implementation, planning & Manpower team for smooth operation of
project.
NEPAL’s Project:
⇔ 01. RF & TX SURVEY FOR HUAWEI-NCELL (NEPAL) - (Nos. of sites 185 Site).
⇔ Team size: 29th.
(01 APM, 02 Project Coordinator, 09 RF, 08 Civil & 06 DT, 03 Rigger). All Engg. are B.Tech.
⇔ RF BTS Survey for NCELL Joint Site Survey (JSS) New site survey in Hilly terrene by our Experience
engineer, which two Regions (Dhualagiri & Maygdi) are given by Huawei. Communicate/Coordinate with
Huawei coordinator & Circle In-charge for Examine the actual site condition Internal/External and after that his
approval preparing the site Reports which is three stage of the documentations, Photograph and CAD Drawing of
the softcopy formats given by NCELL.
⇔ Managing entire operations of the Networks Scopes; played a key role in establishing, organizing and starting
highly Confidential Department. Activities: - Business Promotion, Client Meeting, Issues resolving,
⇔ Preparation of all type of presentation and reports for corporate meetings.
⇔ Vender Selection:- Vendor verification by his required document e.g. previous P.O., Work experience, Client
details, Yearly turnover, Financially strong.
⇔ Responsible for coordinating with the corporate and higher management for project execution.
⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities.
⇔ Manpower management for the execution of site activities.
ZEPHYR SYSTEMS PRIVET LIMITED
(An ISO 9001:2000 Certify Company)
(July-2009 to Dec-2010)
Client:- ZTE - AIRCEL
Project:- TSP & O&M FOR ZTE-AIRCEL, RF BTS SURVEY (ZTE with AIRCEL)
Designation:- Infra Manager (Project Manager)
Job Profile:- Civil, Electrical, Tower erection & Maintenance of Site, Liasoning Activity (MCD, EB
PCB), Vendor Selection, Billing and Documentation Etc.
Circle:- UP-East.
Location:- Lucknow.
Period:- July-2009 to Dec-2010.
⇔ 01. OPERATION & MAINTENANCE FOR ZTE--AIRCEL (UP-East) - (Nos. of sites 305 Sites).
⇔ JSS, IMPLEMENTATION & MAINTENANCE OF SITE
⇔ Team size: 31st.
(12 Engg, And 19 Technician).
⇔ Our major client is AIRCEL of the UP-East circle, we have currently project of O&M for UP-East Circle (all
activities) e.g. Installation of BTS (I/O) and maintenance, Installation of OMCR & Monitoring, Installation
Microwave, Installation-Power system, Technical faults, & Site upgrading Etc.
⇔ 02. RF BTS SURVEY FOR ZTE-AIRCEL sharing with RELIANCE (UP-East) - (Nos. of sites 257 Site).
(Project Done)
⇔ Team size: 06 Engg. (B.Tech. in Electronics & Communication Engg.)
⇔ RF BTS Survey for AIRCEL sites of sharing with Reliance Existing sites survey by our Experience engineer that is
all UP-East. Communicate with reliance O&M coordinator and Circle In-charge for Examine, Survey & Execution
of the reliance existing sites and preparing the documentation, Photograph and CAD Drawing of the reliance
existing sites of his softcopy formats given by ZTE.
⇔ 03. TSP FOR ZTE – AIRCEL (UP-East) - (Nos. of sites P1-25+P2-29+P3-33= 87 Site)
⇔ Team size: 15, (01 PM-(Infra Manager), 01 Project Coordinator, 05 for Civil, 06 for Electrical, 01 for Tower
Expert, and 01 for Documentation Activities).
⇔ Managing entire operations of the TSP Scopes; played a key role in establishing, organizing and starting highly
Confidential Department. Activities: - Mostly is the GBT/RTT Sites completing all activities; Civil activities e.g.
Tower, Shelter/BTS, DG Foundation, Guard Room and Boundary wall with Main Gate including Barbed Wiring
with Punch Point clearance for RFI & FAT., Electrical Work: - External, Earth Pit, Rooting (Cable, GI Strip),
Internal Electrical wiring as per drawing, Tower Erection: - Tower erection team deployment with material
movement request (DO). Vender Selection:- Vendor verification by his required document e.g. previous P.O.,
Work experience, Client details, Yearly turnover, Financially strong.
Page 4 of 8
⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities.
⇔ Responsible for coordinating with the corporate and higher management for project execution.
⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities.
⇔ Manpower management for the execution of site activities.
VIHAAN INFRASYSTEMS INDIA LIMITED
(A DIVISION OF GOLDROCK TRADING LTD.)
(An ISO 9001:2000 Certify Company)
Client:- INDUS TOWER LIMITED, SPEL (WTTISL), GTL And BSNL.
Project:- TSP FOR INDUS TOWER & SPEL (WTTISL), Civil Activity for BSNL & GTL (Aircel).
Designation:- Civil Head
Job Profile:- Civil Activity & Maintenance, Vendor Dealing, Billing and Documentation Etc.
Circle:- UP-West.
Location:- Meerut.
Period:- Dec-2008 to May-2009.
⇔ 01. TSP FOR INDUS. – VODAFONE & IDEA (UP-West) - (Nos. of sites 25) Mostly is the GBT Sites completing
all civil activities with Punch Point clearance till RFI (Ready for Installation).
⇔ JSS, IMPLEMENTATION & MAINTENANCE OF SITE
⇔ Civil activities e.g. Tower, Shelter/BTS, DG Foundation, Guard Room and Boundary wall with Main Gate
including Barbed Wiring with Punch Point clearance for RFI & FAT., Electrical Work: - External, Earth Pit,
Rooting (Cable, GI Strip), Internal Electrical wiring as per drawing,
⇔ 02. TSP FOR SPEL (WTTISL-UP-West) - (Nos. of sites 27) The Sites mixed RTT and GBT completing all the
civil activities with Punch Point clearance till RFI (Ready for Installation).
⇔ 03. BSNL- UP-West- (Nos. of sites 11) Mostly is the GBT Sites completing only civil activities like Tower,
Shelter, DG Foundation, Guard Room and Boundary wall with Main Gate including barbed wiring with Punch
Point clearance for FAT.
⇔ 04. GTL Aircel (UP-West) - (Nos. of sites 14) Only Civil activities for his RTT And GBT sites like Tower,
Shelter, DG Foundation, Guard-Room and Boundary wall with Main Gate including barbed wiring with Punch
Point clearance for FAT.
⇔ Team size : 27, (01 PM, 01 APM, 01 Project Coordinator, 01 for Civil Head, 09 for Civil, 10 for Electrical, 02
for Tower Expert, 01 for Laisoning (EB & MC) and 01 for Documentation Activities)
⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting
highly Confidential Department.
⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities.
⇔ Responsible for coordinating with the corporate and higher management for project execution.
⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities.
⇔ Manpower management for the execution of site activities.
Case Cold Roll Forming Limited
(A Group Company of C&C Construction Ltd.)
An ISO 9001:2000 Certify Company
(Oct-2007to Dec.-2008.)
Client:- WTTISL
Project:- TSP for Dishnet Wireless Ltd. (DWL)
Designation:- Project Head
Job Profile:- TSP Activity, Site Survey, Operation & Maintenance, Vendor Dealing, Invoicing and
Documentation.
Circle:- West Bengal.
Location:- Kolkata.
Period:- April-2008 to Dec.-2008.
⇔ TTSL Dishnet Wireless Project –WTTISL, WB (Nos. of sites 77) Mostly are the GBT Sites completing all the
Civil and Electrical activities with Punch Point clearance till RFI (Ready for Installation).
⇔ SITE SURVEY, OPERATION & MAINTENANCE OF SITE.
⇔ Team size : 12, (01 PM, 01 Coordinator, 04 Civil, 05 Electrical, and 01 for Documentation Activities)
⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting
highly Confidential Department. Activities: - Mostly is the GBT/RTT Sites completing all activities; Civil
activities e.g. Tower, Shelter/BTS, DG Foundation, Guard Room and Boundary wall with Main Gate including
Barbed Wiring with Punch Point clearance for RFI & FAT., Electrical Work: - External, Earth Pit, Rooting
Page 5 of 8
(Cable, GI Strip), Internal Electrical wiring as per drawing, Tower Erection: - Tower erection team deployment
with material movement request (DO). Vender Selection:- Vendor verification by his required document e.g.
previous P.O., Work experience, Client details, Yearly turnover, Financially strong.
⇔ Performing all activities that are required to ensure implementation of Site Infrastructure as per the stipulated
Project Plan to make the Site ready for implementation of Telecom Equipment in all respects.
⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities.
⇔ Responsible for coordinating with the corporate and higher management for project execution.
⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities.
⇔ Manpower management for the execution of site activities.
⇔ Earth pit, Strip routing, Indoor / Outdoor Fit out and Cable routing Etc.
Case Cold Roll Forming Limited
Client:- TTSL (Tata Tele Services Limited)
Project:- Dishnet Wireless Ltd.
Designation:- Project Head
Job Profile:- TSP Activity, Manpower Management, Vendor Dealing, Invoicing and Documentations.
Circle:- Delhi & NCR.
Location:- Delhi.
Period:- Oct-2007 to March- 2008.
⇔ TTSL Dishnet Wireless Project -Delhi (Nos. of sites 35) All are the RTT Sites completing all the Civil and
Electrical works with Punch point clearance till RFI (Ready for Installation).
⇔ Team size : 09, (01 PM, 01 Project Coordinator, 03 for Civil, 03 for Electrical, and 01 for Documentation
Activities)
⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting
highly Confidential Department.
⇔ Performing all activities that are required to ensure implementation of Site Infrastructure as per the stipulated
Project Plan to make the Site ready for implementation of Telecom Equipment in all respects.
⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities.
⇔ Responsible for coordinating with the corporate and higher management for project execution.
⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities.
⇔ Manpower management for the execution of site activities.
⇔ Earth pit, Strip routing, Indoor / Outdoor Fit out and Cable routing Etc.
Nutek India Limited
(A Telecom Solution Company)
(March-2004 to Sep.-2007.)
Nutek India Ltd.
Client:- Aircel
Project:- ZTE (Civil & Electrical Works)
Designation:- Asst. Project Manager
Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Liasoning Dept., Local Issues Etc.
Circle:- Bihar.
Location:- Saharsa, Madhepura & Supaul.
Period:- Aug-2007 to Sep. 2007.
⇔ ZTE AirCell Project (Nos. of sites 55) No. of RTT Sites 07 and No. of GBT Sites 48, Completed all the Civil and
Electrical works with Punch point clearance till RFI (Ready for Installation).
⇔ Team size : 15, (01 PM, 01 APM, 05 for Civil, 07 For Electrical, and 01 for documentation Activities)
⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting
highly Confidential Department.
⇔ Supervising and monitoring the activities of 8 Civil Engineers, 04 Electrical Engineers and 01 Staff for MIS
(Documentation).
⇔ Performing all activities that are required to ensure implementation of Site Infrastructure as per the stipulated
Project Plan to make the Site ready for implementation of Telecom Equipment in all respects.
⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities.
⇔ Responsible for coordinating with the corporate and higher management for project execution.
⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities.
⇔ Designing ABD’s (layout) preparing along with hand back documents.
⇔ Manpower management for the execution of site activities.
⇔ Earth pit, Strip routing, Indoor / Outdoor Fit out and Cable routing Etc.
Page 6 of 8
⇔ We have working Bihar Zone for GSM –ZTE (AirCell) Project, Bihar.
Nutek India Ltd.
Client:- TTSL (Tata Tele Services Limited)
Project:- Dishnet Wireless Ltd. (TSP Scope).
Designation:- Project Coordinator
Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Liasoning Dept., Local Issues Etc.
Circle:- Delhi and NCR.
Location:- Delhi.
Period:- Aug-2006 to July-2007.
⇔ Tata Dishnet – PMC (Nos. of sites 127) No. of RTT Sites 80 and No. of GBT Sites 47, completed all the Civil and
Electrical works with Punch point clearance till RFI (Ready for Installation).
⇔ Team size : 21, (08 for Civil, 10 For Electrical, 01 for EB And 01 for documentation Activities)
⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting
highly Confidential Department.
⇔ Supervising and monitoring the activities of 8 Civil Engineers, 10 Electrical Engineers and 1 Staff for liaison and
MIS (Documentation).
⇔ Performing all activities that are required to ensure implementation of Site Infrastructure as per the stipulated
Project Plan to make the Site ready for implementation of Telecom Equipment in all respects.
⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities.
⇔ Responsible for coordinating with the corporate and higher management for project execution.
⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities.
⇔ CDMA cell site survey & implementation (Ground base tower, Roof top, Pole site & Wall mount poles).
⇔ Designing ABD’s (layout) preparing along with hand back documents and documentation EB Connection and
MCD Permission also.
⇔ Manpower management for the execution of site activities.
Nutek India Ltd.
Client:- Ericsson India Pvt. Ltd.
Project:- Bharti (Airtel).
Designation:- Project Coordinator
Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Liasoning Dept., Local Issues Etc.
Circle:- UP-West.
Location:- Meerut.
Period:- March-2006, Aug.-2006.
⇔ Team Lead engineers and Circle Head for the new site survey with RF engineer, Civil survey (Building Analysis),
BTS site survey, BTS Expansion survey, sharing site BTS survey, Micro site survey.
⇔ Coordinate with Local Contractor and his worker for the casting of the foundation of the Tower Shelter, DG and
Servo Pad also. We have done 200 Sites On Air in the May month 2006. Including BTS Installation and
Commissioning with team work.
⇔ Documentation of Civil Report/Tracker Report, Site installation, C-modular (Hand Over) documents and site
Structure Drawing RTT/GBT as per site structural and Preparing Sites ABD’s along with hand back documents.
Nutek India Ltd.
Client:- Ericsson India Pvt. Ltd.
Project:- Bharti (AirTel), Dishnet, MTNL, BSNL, Idea, Shyam Telecom.
Designation:- Civil Coordinator and CAD Engineer.
Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Verify Civil Structural Drawing and Site
Layout Etc.
Circle:- Delhi, UP-East/West, Haryana, Punjab, Himanchal Pradesh, Madhya Pradesh, Bihar,
West Bengal, Orissa, Assam and North East etc.
Location:- Gurgaon, Haryana.
Period:- Sep. 2004 to March - 2006.
⇔ Coordination with Civil engineers and Circle Head for the new site survey with RF engineer, civil survey (Building
Analysis), BTS site survey, BTS Expansion survey, sharing site BTS survey, Micro site survey.
⇔ Documentation of civil report/tracker report, Site installation, C-modular (hand over) documents and CAD ABD’s
RTT/GBT as per site structural and site, (As Built Drawing) Preparing along with hand back documents.
Page 7 of 8
⇔ Coordination with Local Contractor & his worker for the casting of the foundation of the Tower Shelter, DG.
Nutek India Ltd.
Client :- Motorola India Pvt. Ltd.
Project: - MTNL Delhi.
Designation:- Sr. Civil and CAD Engineer.
Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Verify Structural Drawing and Layout Etc.
Circle :- DELHI/NCR.
Location:- Gurgaon – Delhi.
Period: - 23rd.
May to Aug. 2004.
⇔ We have (Lat / Long) given by client (MOTOROLA) then we have following that coordinate by using GPS
(Global Positioning System- Garmin 12) Device at the sites. Searching new three options for new site limited
searching area 50-100 Mtrs. radius for installation of Tower, Shelter, DG and other Equipment also, Preparing all
three candidates structural layouts with Tower, Shelter, DG, IP switch, Servo, Earth pit location and cable routing.
⇔ We have done 112 sites of GSM –MTNL Project in the Delhi/NCR.
Nutek India Ltd.
Client: - TTSL (Tata Tele Services Limited)
Project: - (CDMA –TTSL) Dishnet Project.
Designation:- Civil and CAD Engineer.
Job Profile:- New Site Survey with RF & Acquisition team, and Verify Site Layout.
Circle: - UP-East.
Location:- (Lucknow, Kanpur, Barelly, Faizabad ).
Period: - 15th.
March to 22nd.
May 2004.
⇔ We have done 120 sites of (CDMA –TTSL) Dishnet Project in the All UP East Circle.
⇔ We have using following coordinates by GPS for searching new site Select three options for site in the search ring
50 or 100Mtrs. for the installation of Tower, Shelter, DG, IP Switch, LT Panel & Earth Pit Place, Preparing report
& layouts as per location and cable routing.
PROFESSIONAL CREDENTIALS
⇔ Diploma In Civil Engineering with effects 69.11 % marks from A. M. U. Aligarh, in 2004 (UP).
⇔ Professional Diploma Certificate Course in AutoCAD 2004 from CADD Centre, New Delhi.
Using: - 2D Wire frame and 3D Graphics design.
TECHNICAL CREDENTIALS
⇔ Computer Software One year Diploma in Application from “Advance Computer Centre” in 1996,
Muzaffarpur, Bihar.
⇔ Operating System : Windows Family, Office Suite : Office XP/2003, 2007.
⇔ Software Packages : AutoCAD 2004, 2006 (Civil).
⇔ Diploma Hardware Engineering from “Beltron Institute of Technology” in 1998. Patna, Bihar.
PERSONAL DETAILS
Address : WZ-542-A, Gali No-02, Shri Nagar, Shakur Basti, New Delhi-110034.
DOB : 11 July 1978.
Marital Status : Married
Passport No. : “H4347253”
Area of interest : Making Good Relationship.
Page 8 of 8
Md. Tanzeer Akhter
New Delhi.

More Related Content

What's hot

What's hot (20)

social profile.
social profile.social profile.
social profile.
 
SENIOR ENGINEER_Saroj
SENIOR ENGINEER_SarojSENIOR ENGINEER_Saroj
SENIOR ENGINEER_Saroj
 
CV-SHAJEER(23-02-2015).PDF
CV-SHAJEER(23-02-2015).PDFCV-SHAJEER(23-02-2015).PDF
CV-SHAJEER(23-02-2015).PDF
 
CV_FERNANDO LUNAS
CV_FERNANDO LUNASCV_FERNANDO LUNAS
CV_FERNANDO LUNAS
 
RHODORA UY TAN CV
RHODORA UY TAN CVRHODORA UY TAN CV
RHODORA UY TAN CV
 
Resume 2015
Resume 2015Resume 2015
Resume 2015
 
Estimation Engineer
Estimation EngineerEstimation Engineer
Estimation Engineer
 
Goldman Resourcing Top Candidates and Vacancies
Goldman Resourcing Top Candidates and VacanciesGoldman Resourcing Top Candidates and Vacancies
Goldman Resourcing Top Candidates and Vacancies
 
CV - Electrical Estimation Engineer
CV - Electrical Estimation EngineerCV - Electrical Estimation Engineer
CV - Electrical Estimation Engineer
 
Rajeev tiwari
Rajeev tiwariRajeev tiwari
Rajeev tiwari
 
Curriculum Vitae QS
Curriculum Vitae QSCurriculum Vitae QS
Curriculum Vitae QS
 
Resume abhishek
Resume abhishekResume abhishek
Resume abhishek
 
Resume
ResumeResume
Resume
 
CV (Document Controller)
CV (Document Controller)CV (Document Controller)
CV (Document Controller)
 
Elie2016-cv
Elie2016-cvElie2016-cv
Elie2016-cv
 
Atta Demetre - General 16062015
Atta Demetre - General 16062015Atta Demetre - General 16062015
Atta Demetre - General 16062015
 
Rana muhammad z ahid cv Fire Alarm Engineer
Rana muhammad z ahid cv Fire Alarm Engineer Rana muhammad z ahid cv Fire Alarm Engineer
Rana muhammad z ahid cv Fire Alarm Engineer
 
JD-Estimation Engineer
JD-Estimation EngineerJD-Estimation Engineer
JD-Estimation Engineer
 
JSM Document Controller CV
JSM Document Controller CVJSM Document Controller CV
JSM Document Controller CV
 
MAIN RESUME
MAIN RESUMEMAIN RESUME
MAIN RESUME
 

Similar to Tanzeer Akhter (3) (20)

CHANDER PRAKASH
CHANDER PRAKASHCHANDER PRAKASH
CHANDER PRAKASH
 
CV_NARENDRA_RAWAT_EXP-10_YEARS_TELECOM_OPS._AND_PROJECT
CV_NARENDRA_RAWAT_EXP-10_YEARS_TELECOM_OPS._AND_PROJECTCV_NARENDRA_RAWAT_EXP-10_YEARS_TELECOM_OPS._AND_PROJECT
CV_NARENDRA_RAWAT_EXP-10_YEARS_TELECOM_OPS._AND_PROJECT
 
Pawan_cv
Pawan_cvPawan_cv
Pawan_cv
 
Birendra -Kumar-Yadav_Resume
Birendra -Kumar-Yadav_ResumeBirendra -Kumar-Yadav_Resume
Birendra -Kumar-Yadav_Resume
 
Dhiru singh
Dhiru singhDhiru singh
Dhiru singh
 
Project Incharge -
Project Incharge -Project Incharge -
Project Incharge -
 
Zaheer cv latest
Zaheer cv latestZaheer cv latest
Zaheer cv latest
 
CV_Zafar_Telecom O&M_RF Engineer-Coordinator_Business Development Manager (22...
CV_Zafar_Telecom O&M_RF Engineer-Coordinator_Business Development Manager (22...CV_Zafar_Telecom O&M_RF Engineer-Coordinator_Business Development Manager (22...
CV_Zafar_Telecom O&M_RF Engineer-Coordinator_Business Development Manager (22...
 
ASHWANI KUMAR
ASHWANI KUMARASHWANI KUMAR
ASHWANI KUMAR
 
SAHEEM CV
SAHEEM CVSAHEEM CV
SAHEEM CV
 
irshadali_CV
irshadali_CVirshadali_CV
irshadali_CV
 
Divaker resume updated
Divaker resume updatedDivaker resume updated
Divaker resume updated
 
Joel Sedeski-Resume
Joel Sedeski-ResumeJoel Sedeski-Resume
Joel Sedeski-Resume
 
mathy 2015
mathy 2015mathy 2015
mathy 2015
 
M.athar malik
M.athar malikM.athar malik
M.athar malik
 
Abhishek CV
Abhishek CVAbhishek CV
Abhishek CV
 
Aslam fahmi CV
Aslam fahmi CVAslam fahmi CV
Aslam fahmi CV
 
Aslam fahmi cv
Aslam fahmi cvAslam fahmi cv
Aslam fahmi cv
 
JAGDISH Updated
JAGDISH UpdatedJAGDISH Updated
JAGDISH Updated
 
niladri-2014
niladri-2014niladri-2014
niladri-2014
 

Tanzeer Akhter (3)

  • 1. Page 1 of 8 Md. Tanzeer Akhter Mobile: +919540394540 Email: tanzeer.akhter@gmail.com JOB OBJECTIVE Aspiring for a technically challenging position where I would be able to utilize my strong technical background in the field of civil and Telecommunication along with my internal personal skills to develop & deploy various projects and serve the Telecom Industry with the best of my efforts and help flourish the Telecom Technologies. Professional Synopsis A technocrat with more than 12.1 years of experience in the areas of Project Operation Maintenance and Management, Civil Infrastructure (Active & Passive Activities) & CADD (2D/3D) and Team Management, Material Management, Site Measurements Verification, Vendor Selection & Billing Etc. Presently associated with Samax Telecom Pvt. Ltd. As Assist Project Manager. Total more than 1 years of experience in TI expertise in deploying project execution solutions by conducting project planning sessions with the project management team to ensure Project / Program compliance to budget, quality standards and customer requirements. Proficient in design, development, implementation, secure architecture and management of Enterprise Applications. Strong management, collaboration & team building skills with proficiency in grasping new technical concepts quickly. AREAS OF EXPERTISE Functional Project Management  Planning and networking with the project team and conducting periodic project progress review meetings to ensure effective delivery of project solutions in line with time and quality parameters.  Delivering and implementing the project as per scheduled deadlines; extending post-implementation and maintenance support to the civil support team and clients. Civil Management  Telecommunication Office Building Construction and Maintenance Work like BSC, MSC, Equipment rooms BTS Room of TSP Works, Civil, Electrical and Fabrication and Finishing works.  Coordinate with Architect, Civil, Electrical, Municipal Corporation Department, Electricity Board, Department of Pollution Control, Vendors and our Engineer in-charge etc.  Documentation with Survey Report, Structural Drawing with PAT and FAT reports, with JMR and CAD-As Built Drawing etc.  Mapping client/business requirements and providing customized civil solutions involving finalization of Civil Engineers survey with RF Engineers, project specifications and selection of appropriate techniques.  Developing internal specifications outlining the overall design and functionality of the project. Team Management  Identifying and implementing strategies for building team effectiveness by promoting a spirit of cooperation between our Team members and vendors teams Members.  Determining training needs of analysts and conducting suitable training programs to enhance their operational efficiency leading to increased productivity. ORGANISATIONAL EXPERIENCE
  • 2. Page 2 of 8 RESPONSIBILITIES / JOB PROFILES SaMax Telecom Pvt. Ltd. (June-2015 to Till Date) Client:- Vodafone LTE (Delhi/NCR) & HUAWEI-Telenor (B&J and UPW). Project:- I&C TI LTE, RF Survey, RFI Survey & EMF Survey. Designation:- Assist Manager Projects (TI LEAD) Job Profile:- Project Execution, Maintain Quality Work, EHS compliance , Customer Meeting, Site surprise Visiting and Verifying all particulars are worked well, and it has on good working condition like;- Indoor/ Outdoor compliance Etc. Circle:- Delhi/NCR, B&J, and UPW, Location:- Delhi/NCR, B&J, and UPW, Period:- From June-2015 to Till. Training:- EHS/Quality/CBTHR/RF/RFI/TI. Team Strength.. ⇔ I&C (TI all activity) RF, RFI, EMF, For Vodafone (Delhi/NCR) & Telenor (Bihar & Jharkhand / UPW) ⇔ TI Team size: 4 Teamth. (4 Engineers (TL), 08 Technicians, 04 Riggers) for Vodafone 4G Delhi/NCR ⇔ TI Team size: 3 Teamth. (3 Engineers (TL), 06 Technicians, 03 Riggers) for Telenor B&J. ⇔ RF Team 06 Engg. For Telenor (B&J) ⇔ DT Team 05 Engg. & 05 Rigger For Vodafone (Delhi/NCR) ⇔ DT Team 04 Engg. & 04 Rigger For Telenor (UPW) ⇔ Active participation in Project Roll-Out Planning with PM’s/Coordinators for proper execution of project. ⇔ Providing support to Optimizer Teams, implementation, planning & Manpower team for smooth operation of project. ⇔ Vender Selection:- Vendor verification by his required document e.g. previous P.O., Work experience, Client details, Yearly turnover, Financially strong. ⇔ Responsible for coordinating with the corporate and higher management for project execution. ⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities. ⇔ Manpower management for the execution of site activities. PRIME SUPPORT & SERVICES PRIVATE LIMITED Serving Excellence (Dec-2010 to Till-2014) Client:- IDEA, VODAFONE (India) & HUAWEI-NCELL (Nepal) Project:- JSS, IMPLEMENTATION & MAINTENANCE OF MSC & BSC. NETWORK SOLUTION (2G/3G, DT), & EMF SURVEY. Designation:- Manager Projects. Job Profile:- Project Execution, Client Meeting, Site Visiting and Verifying all particulars are worked well, looking good and it has on good working condition like;- Indoor/ Outdoor Civil, Electrical, AC, Fabrication works, Complaints & Customer Feedback Studies, Client Meeting Etc. Circle:- New Delhi, UP, HP, & Kathmandu, Dhualagiri, Maygdi, Beni. Location:- India & Kathmandu (Nepal) Period:- Dec-2010 to till INDIA’s Project; ⇔ 01. RF& Drive Test Optimization FOR IDEA (Delhi/NCR, Haryana, Rajasthan, MP, UPE/UPW) ⇔ 02. EMF SURVEY & DOCUMENTATION FOR IDEA (DELHI/NCR, HARYANA, & UPW) ⇔ 03. JSS, IMPLEMENTATION & MAINTENANCE OF MSC & BSC ⇔ 04. Team size: 55th. (03 Coordinator, 9 Civil, 17 RF, & 8 DT, 4 Supervisor, 4 Electrical, 10 Rigger). ⇔ Civil Maintenance Works :- Site visit for check all the Damaged, Pending, Missing and Unfinished works and rest of the maintenance related works like Coloring, Plaster (Damage/Scratched/ Demolished), Plaster of Paris (Sealant/ Damage/ Scratched), Ceiling, False Ceiling (Cracks/ Leveling & finishing), Flooring (Tiles/Marbles/Wooden) fixing, finishing, polishing in Proper way, Doors & Windows (Steel/ Iron/ Aluminum/ Wooden/ Fiber etc), Bathrooms & Kitchen fit out, Glasses fit out, Fabrication works Railings, Stair case, are on good, well and working condition,
  • 3. Page 3 of 8 ⇔ Electricals Maintenance Works :- Outdoor / Indoor Lighting system, False & Open wiring not used appears, Fire Alarm systems, CC TV Cameras System, Control room Facilities are full fill, all electrical Switches MCB’s are working Good,. ⇔ Our major client is IDEA of the PAN India, we have currently project of Drive Test Optimization Delhi/NCR, Haryana, Rajasthan and Rx & Tx Survey in Hayana, and all UP’s circle (all activities). ⇔ Active participation in Project Roll-Out Planning with PM’s/Coordinators for proper execution of project. ⇔ Providing support to Optimizer Teams, implementation, planning & Manpower team for smooth operation of project. NEPAL’s Project: ⇔ 01. RF & TX SURVEY FOR HUAWEI-NCELL (NEPAL) - (Nos. of sites 185 Site). ⇔ Team size: 29th. (01 APM, 02 Project Coordinator, 09 RF, 08 Civil & 06 DT, 03 Rigger). All Engg. are B.Tech. ⇔ RF BTS Survey for NCELL Joint Site Survey (JSS) New site survey in Hilly terrene by our Experience engineer, which two Regions (Dhualagiri & Maygdi) are given by Huawei. Communicate/Coordinate with Huawei coordinator & Circle In-charge for Examine the actual site condition Internal/External and after that his approval preparing the site Reports which is three stage of the documentations, Photograph and CAD Drawing of the softcopy formats given by NCELL. ⇔ Managing entire operations of the Networks Scopes; played a key role in establishing, organizing and starting highly Confidential Department. Activities: - Business Promotion, Client Meeting, Issues resolving, ⇔ Preparation of all type of presentation and reports for corporate meetings. ⇔ Vender Selection:- Vendor verification by his required document e.g. previous P.O., Work experience, Client details, Yearly turnover, Financially strong. ⇔ Responsible for coordinating with the corporate and higher management for project execution. ⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities. ⇔ Manpower management for the execution of site activities. ZEPHYR SYSTEMS PRIVET LIMITED (An ISO 9001:2000 Certify Company) (July-2009 to Dec-2010) Client:- ZTE - AIRCEL Project:- TSP & O&M FOR ZTE-AIRCEL, RF BTS SURVEY (ZTE with AIRCEL) Designation:- Infra Manager (Project Manager) Job Profile:- Civil, Electrical, Tower erection & Maintenance of Site, Liasoning Activity (MCD, EB PCB), Vendor Selection, Billing and Documentation Etc. Circle:- UP-East. Location:- Lucknow. Period:- July-2009 to Dec-2010. ⇔ 01. OPERATION & MAINTENANCE FOR ZTE--AIRCEL (UP-East) - (Nos. of sites 305 Sites). ⇔ JSS, IMPLEMENTATION & MAINTENANCE OF SITE ⇔ Team size: 31st. (12 Engg, And 19 Technician). ⇔ Our major client is AIRCEL of the UP-East circle, we have currently project of O&M for UP-East Circle (all activities) e.g. Installation of BTS (I/O) and maintenance, Installation of OMCR & Monitoring, Installation Microwave, Installation-Power system, Technical faults, & Site upgrading Etc. ⇔ 02. RF BTS SURVEY FOR ZTE-AIRCEL sharing with RELIANCE (UP-East) - (Nos. of sites 257 Site). (Project Done) ⇔ Team size: 06 Engg. (B.Tech. in Electronics & Communication Engg.) ⇔ RF BTS Survey for AIRCEL sites of sharing with Reliance Existing sites survey by our Experience engineer that is all UP-East. Communicate with reliance O&M coordinator and Circle In-charge for Examine, Survey & Execution of the reliance existing sites and preparing the documentation, Photograph and CAD Drawing of the reliance existing sites of his softcopy formats given by ZTE. ⇔ 03. TSP FOR ZTE – AIRCEL (UP-East) - (Nos. of sites P1-25+P2-29+P3-33= 87 Site) ⇔ Team size: 15, (01 PM-(Infra Manager), 01 Project Coordinator, 05 for Civil, 06 for Electrical, 01 for Tower Expert, and 01 for Documentation Activities). ⇔ Managing entire operations of the TSP Scopes; played a key role in establishing, organizing and starting highly Confidential Department. Activities: - Mostly is the GBT/RTT Sites completing all activities; Civil activities e.g. Tower, Shelter/BTS, DG Foundation, Guard Room and Boundary wall with Main Gate including Barbed Wiring with Punch Point clearance for RFI & FAT., Electrical Work: - External, Earth Pit, Rooting (Cable, GI Strip), Internal Electrical wiring as per drawing, Tower Erection: - Tower erection team deployment with material movement request (DO). Vender Selection:- Vendor verification by his required document e.g. previous P.O., Work experience, Client details, Yearly turnover, Financially strong.
  • 4. Page 4 of 8 ⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities. ⇔ Responsible for coordinating with the corporate and higher management for project execution. ⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities. ⇔ Manpower management for the execution of site activities. VIHAAN INFRASYSTEMS INDIA LIMITED (A DIVISION OF GOLDROCK TRADING LTD.) (An ISO 9001:2000 Certify Company) Client:- INDUS TOWER LIMITED, SPEL (WTTISL), GTL And BSNL. Project:- TSP FOR INDUS TOWER & SPEL (WTTISL), Civil Activity for BSNL & GTL (Aircel). Designation:- Civil Head Job Profile:- Civil Activity & Maintenance, Vendor Dealing, Billing and Documentation Etc. Circle:- UP-West. Location:- Meerut. Period:- Dec-2008 to May-2009. ⇔ 01. TSP FOR INDUS. – VODAFONE & IDEA (UP-West) - (Nos. of sites 25) Mostly is the GBT Sites completing all civil activities with Punch Point clearance till RFI (Ready for Installation). ⇔ JSS, IMPLEMENTATION & MAINTENANCE OF SITE ⇔ Civil activities e.g. Tower, Shelter/BTS, DG Foundation, Guard Room and Boundary wall with Main Gate including Barbed Wiring with Punch Point clearance for RFI & FAT., Electrical Work: - External, Earth Pit, Rooting (Cable, GI Strip), Internal Electrical wiring as per drawing, ⇔ 02. TSP FOR SPEL (WTTISL-UP-West) - (Nos. of sites 27) The Sites mixed RTT and GBT completing all the civil activities with Punch Point clearance till RFI (Ready for Installation). ⇔ 03. BSNL- UP-West- (Nos. of sites 11) Mostly is the GBT Sites completing only civil activities like Tower, Shelter, DG Foundation, Guard Room and Boundary wall with Main Gate including barbed wiring with Punch Point clearance for FAT. ⇔ 04. GTL Aircel (UP-West) - (Nos. of sites 14) Only Civil activities for his RTT And GBT sites like Tower, Shelter, DG Foundation, Guard-Room and Boundary wall with Main Gate including barbed wiring with Punch Point clearance for FAT. ⇔ Team size : 27, (01 PM, 01 APM, 01 Project Coordinator, 01 for Civil Head, 09 for Civil, 10 for Electrical, 02 for Tower Expert, 01 for Laisoning (EB & MC) and 01 for Documentation Activities) ⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting highly Confidential Department. ⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities. ⇔ Responsible for coordinating with the corporate and higher management for project execution. ⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities. ⇔ Manpower management for the execution of site activities. Case Cold Roll Forming Limited (A Group Company of C&C Construction Ltd.) An ISO 9001:2000 Certify Company (Oct-2007to Dec.-2008.) Client:- WTTISL Project:- TSP for Dishnet Wireless Ltd. (DWL) Designation:- Project Head Job Profile:- TSP Activity, Site Survey, Operation & Maintenance, Vendor Dealing, Invoicing and Documentation. Circle:- West Bengal. Location:- Kolkata. Period:- April-2008 to Dec.-2008. ⇔ TTSL Dishnet Wireless Project –WTTISL, WB (Nos. of sites 77) Mostly are the GBT Sites completing all the Civil and Electrical activities with Punch Point clearance till RFI (Ready for Installation). ⇔ SITE SURVEY, OPERATION & MAINTENANCE OF SITE. ⇔ Team size : 12, (01 PM, 01 Coordinator, 04 Civil, 05 Electrical, and 01 for Documentation Activities) ⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting highly Confidential Department. Activities: - Mostly is the GBT/RTT Sites completing all activities; Civil activities e.g. Tower, Shelter/BTS, DG Foundation, Guard Room and Boundary wall with Main Gate including Barbed Wiring with Punch Point clearance for RFI & FAT., Electrical Work: - External, Earth Pit, Rooting
  • 5. Page 5 of 8 (Cable, GI Strip), Internal Electrical wiring as per drawing, Tower Erection: - Tower erection team deployment with material movement request (DO). Vender Selection:- Vendor verification by his required document e.g. previous P.O., Work experience, Client details, Yearly turnover, Financially strong. ⇔ Performing all activities that are required to ensure implementation of Site Infrastructure as per the stipulated Project Plan to make the Site ready for implementation of Telecom Equipment in all respects. ⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities. ⇔ Responsible for coordinating with the corporate and higher management for project execution. ⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities. ⇔ Manpower management for the execution of site activities. ⇔ Earth pit, Strip routing, Indoor / Outdoor Fit out and Cable routing Etc. Case Cold Roll Forming Limited Client:- TTSL (Tata Tele Services Limited) Project:- Dishnet Wireless Ltd. Designation:- Project Head Job Profile:- TSP Activity, Manpower Management, Vendor Dealing, Invoicing and Documentations. Circle:- Delhi & NCR. Location:- Delhi. Period:- Oct-2007 to March- 2008. ⇔ TTSL Dishnet Wireless Project -Delhi (Nos. of sites 35) All are the RTT Sites completing all the Civil and Electrical works with Punch point clearance till RFI (Ready for Installation). ⇔ Team size : 09, (01 PM, 01 Project Coordinator, 03 for Civil, 03 for Electrical, and 01 for Documentation Activities) ⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting highly Confidential Department. ⇔ Performing all activities that are required to ensure implementation of Site Infrastructure as per the stipulated Project Plan to make the Site ready for implementation of Telecom Equipment in all respects. ⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities. ⇔ Responsible for coordinating with the corporate and higher management for project execution. ⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities. ⇔ Manpower management for the execution of site activities. ⇔ Earth pit, Strip routing, Indoor / Outdoor Fit out and Cable routing Etc. Nutek India Limited (A Telecom Solution Company) (March-2004 to Sep.-2007.) Nutek India Ltd. Client:- Aircel Project:- ZTE (Civil & Electrical Works) Designation:- Asst. Project Manager Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Liasoning Dept., Local Issues Etc. Circle:- Bihar. Location:- Saharsa, Madhepura & Supaul. Period:- Aug-2007 to Sep. 2007. ⇔ ZTE AirCell Project (Nos. of sites 55) No. of RTT Sites 07 and No. of GBT Sites 48, Completed all the Civil and Electrical works with Punch point clearance till RFI (Ready for Installation). ⇔ Team size : 15, (01 PM, 01 APM, 05 for Civil, 07 For Electrical, and 01 for documentation Activities) ⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting highly Confidential Department. ⇔ Supervising and monitoring the activities of 8 Civil Engineers, 04 Electrical Engineers and 01 Staff for MIS (Documentation). ⇔ Performing all activities that are required to ensure implementation of Site Infrastructure as per the stipulated Project Plan to make the Site ready for implementation of Telecom Equipment in all respects. ⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities. ⇔ Responsible for coordinating with the corporate and higher management for project execution. ⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities. ⇔ Designing ABD’s (layout) preparing along with hand back documents. ⇔ Manpower management for the execution of site activities. ⇔ Earth pit, Strip routing, Indoor / Outdoor Fit out and Cable routing Etc.
  • 6. Page 6 of 8 ⇔ We have working Bihar Zone for GSM –ZTE (AirCell) Project, Bihar. Nutek India Ltd. Client:- TTSL (Tata Tele Services Limited) Project:- Dishnet Wireless Ltd. (TSP Scope). Designation:- Project Coordinator Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Liasoning Dept., Local Issues Etc. Circle:- Delhi and NCR. Location:- Delhi. Period:- Aug-2006 to July-2007. ⇔ Tata Dishnet – PMC (Nos. of sites 127) No. of RTT Sites 80 and No. of GBT Sites 47, completed all the Civil and Electrical works with Punch point clearance till RFI (Ready for Installation). ⇔ Team size : 21, (08 for Civil, 10 For Electrical, 01 for EB And 01 for documentation Activities) ⇔ Managing entire operations of the Civil Department; played a key role in establishing, organizing and starting highly Confidential Department. ⇔ Supervising and monitoring the activities of 8 Civil Engineers, 10 Electrical Engineers and 1 Staff for liaison and MIS (Documentation). ⇔ Performing all activities that are required to ensure implementation of Site Infrastructure as per the stipulated Project Plan to make the Site ready for implementation of Telecom Equipment in all respects. ⇔ Contractor management, material planning and scheduling, logistic for the projects & certification of quantities. ⇔ Responsible for coordinating with the corporate and higher management for project execution. ⇔ Preparing detailed timeline schedule for implementation of Site Infrastructure indicating sub-activities. ⇔ CDMA cell site survey & implementation (Ground base tower, Roof top, Pole site & Wall mount poles). ⇔ Designing ABD’s (layout) preparing along with hand back documents and documentation EB Connection and MCD Permission also. ⇔ Manpower management for the execution of site activities. Nutek India Ltd. Client:- Ericsson India Pvt. Ltd. Project:- Bharti (Airtel). Designation:- Project Coordinator Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Liasoning Dept., Local Issues Etc. Circle:- UP-West. Location:- Meerut. Period:- March-2006, Aug.-2006. ⇔ Team Lead engineers and Circle Head for the new site survey with RF engineer, Civil survey (Building Analysis), BTS site survey, BTS Expansion survey, sharing site BTS survey, Micro site survey. ⇔ Coordinate with Local Contractor and his worker for the casting of the foundation of the Tower Shelter, DG and Servo Pad also. We have done 200 Sites On Air in the May month 2006. Including BTS Installation and Commissioning with team work. ⇔ Documentation of Civil Report/Tracker Report, Site installation, C-modular (Hand Over) documents and site Structure Drawing RTT/GBT as per site structural and Preparing Sites ABD’s along with hand back documents. Nutek India Ltd. Client:- Ericsson India Pvt. Ltd. Project:- Bharti (AirTel), Dishnet, MTNL, BSNL, Idea, Shyam Telecom. Designation:- Civil Coordinator and CAD Engineer. Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Verify Civil Structural Drawing and Site Layout Etc. Circle:- Delhi, UP-East/West, Haryana, Punjab, Himanchal Pradesh, Madhya Pradesh, Bihar, West Bengal, Orissa, Assam and North East etc. Location:- Gurgaon, Haryana. Period:- Sep. 2004 to March - 2006. ⇔ Coordination with Civil engineers and Circle Head for the new site survey with RF engineer, civil survey (Building Analysis), BTS site survey, BTS Expansion survey, sharing site BTS survey, Micro site survey. ⇔ Documentation of civil report/tracker report, Site installation, C-modular (hand over) documents and CAD ABD’s RTT/GBT as per site structural and site, (As Built Drawing) Preparing along with hand back documents.
  • 7. Page 7 of 8 ⇔ Coordination with Local Contractor & his worker for the casting of the foundation of the Tower Shelter, DG. Nutek India Ltd. Client :- Motorola India Pvt. Ltd. Project: - MTNL Delhi. Designation:- Sr. Civil and CAD Engineer. Job Profile:- Co-ordinate with Clients, Vendor, Engineers, Verify Structural Drawing and Layout Etc. Circle :- DELHI/NCR. Location:- Gurgaon – Delhi. Period: - 23rd. May to Aug. 2004. ⇔ We have (Lat / Long) given by client (MOTOROLA) then we have following that coordinate by using GPS (Global Positioning System- Garmin 12) Device at the sites. Searching new three options for new site limited searching area 50-100 Mtrs. radius for installation of Tower, Shelter, DG and other Equipment also, Preparing all three candidates structural layouts with Tower, Shelter, DG, IP switch, Servo, Earth pit location and cable routing. ⇔ We have done 112 sites of GSM –MTNL Project in the Delhi/NCR. Nutek India Ltd. Client: - TTSL (Tata Tele Services Limited) Project: - (CDMA –TTSL) Dishnet Project. Designation:- Civil and CAD Engineer. Job Profile:- New Site Survey with RF & Acquisition team, and Verify Site Layout. Circle: - UP-East. Location:- (Lucknow, Kanpur, Barelly, Faizabad ). Period: - 15th. March to 22nd. May 2004. ⇔ We have done 120 sites of (CDMA –TTSL) Dishnet Project in the All UP East Circle. ⇔ We have using following coordinates by GPS for searching new site Select three options for site in the search ring 50 or 100Mtrs. for the installation of Tower, Shelter, DG, IP Switch, LT Panel & Earth Pit Place, Preparing report & layouts as per location and cable routing. PROFESSIONAL CREDENTIALS ⇔ Diploma In Civil Engineering with effects 69.11 % marks from A. M. U. Aligarh, in 2004 (UP). ⇔ Professional Diploma Certificate Course in AutoCAD 2004 from CADD Centre, New Delhi. Using: - 2D Wire frame and 3D Graphics design. TECHNICAL CREDENTIALS ⇔ Computer Software One year Diploma in Application from “Advance Computer Centre” in 1996, Muzaffarpur, Bihar. ⇔ Operating System : Windows Family, Office Suite : Office XP/2003, 2007. ⇔ Software Packages : AutoCAD 2004, 2006 (Civil). ⇔ Diploma Hardware Engineering from “Beltron Institute of Technology” in 1998. Patna, Bihar. PERSONAL DETAILS Address : WZ-542-A, Gali No-02, Shri Nagar, Shakur Basti, New Delhi-110034. DOB : 11 July 1978. Marital Status : Married Passport No. : “H4347253” Area of interest : Making Good Relationship.
  • 8. Page 8 of 8 Md. Tanzeer Akhter New Delhi.