This document discusses the proper interpretation of clause 11.3 of IS-456-2000 regarding when to strip formwork from concrete slabs. It notes that both following the time guidelines in the clause's table and requiring a certain strength percentage are incorrect approaches. The key criteria is that formwork should not be removed until the concrete has achieved at least twice the stress it will experience upon removal. A simple calculation method is provided to determine the required concrete strength based on factors like slab thickness, span length, and imposed loads. Following this clause correctly allows for reduced project timelines and costs compared to the alternative incorrect interpretations.