Marshall Smith, Systems Engineering and Integration Chief
 Barry Bryant, Deputy SE&I Chief

www.nasa.gov                      Used with permission
Outline

             ♦ SE&I Organization Evolution
                     • Increased scope
                     • Increased personnel integration

             ♦ Integrated Design and Analysis (ID&A)
                     • Distributed resources
                     • Tiger teams

             ♦ Vehicle Assembly and Integration
                     • Integration and testing

             ♦ Launch and Flight Integration
                     • Range and Operations

             ♦ Systems Requirements and Verification
                     • Requirements flow
                     • Verification process

             ♦ Summary
National Aeronautics and Space Administration                7465.2
Ares I-X Organization

                                                           Ares I-X Flight Test
                                                       Mission Management Office
           Safety & Mission                                       (MMO)                                Chief Engineers
          Assurance ( S& MA )                                  Mission Manager
                                                               Deputy Managers
                                                     Systems Engineering & Integration Chief
                                                          Project Integration Manager
                                                              Business Manager
                                                           Business Manager Deputy

               Project Integration (PI)                                                              Systems Engineering
                                                                                                     & Integration ( SE&I )




                                    Upper Stage                                      Roll Control   Ground            Ground
                                                   CM/LAS
      First Stage                    Simulator                      Avionics           System       Systems          Operations
                                                  Simulator
                                      ( USS )                                          ( RoCS )      ( GS )            ( GO )




National Aeronautics and Space Administration                                                                                     3
SE&I Evolution


             ♦ Established an SE&I Office (replaced AVIO) to include all
               aspects of mission

             ♦ Key organizational changes required to accommodate
               increased scope
                     • Need to incorporate key members of the GO and GS teams
                     • Increased scope of Range and Operations interactions
                     • Expanded Requirements and Verification to include ground activities
                     • Integrated Design and Analysis (ID&A) issues expanded to cover
                       ground related issues
                     • Established SE&I as the primary interface to GO and the Range during
                       integration




National Aeronautics and Space Administration                                                 7465.4
SE&I Organization
    Safety & Mission Assurance                           Systems Engineering & Integration Office                                  Engineering
                David Helfrich                                             Marshall Smith                                           Henry Wright
                S&MA Lead (TA)                                                     Chief                                          Lead Engineer (TA)

                 K.C. Johnson                                  Barry Bryant                       Jim Price
              Deputy S&MA Lead                                  Deputy Chief                Deputy for Operations

                                                              Stanley Ward                     Kurt Detweiler                      Mike Bangham
             Robert Decoursey                                 Deputy for PP&C              Lead Systems Engineer (LSE)               Deputy LSE
                  Software Lead
                                                                          Cynthia Weathers                                          Lanny Upton
                                                                                  Secretary                                          Deputy LSE


                Project Integration
           Paul Luz         Susie Johnston
          Vernet Mull         Dan Healey
        Donner Grigsby         Schedules
                CM/DM




      Vehicle Assembly                              Launch &           Systems Requirements                    Avionics &             Integrated Design
        & Integration                           Flight Integration         & Verification                  Software Integration           & Analysis
         Rami Intriago                            James Price                  Kevin Vipavetz                    Will Scott             Carey Buttrill
              Manager                               Manager                       Manager                         Manager                  Manager

         Rusty Jenkins                          Debbie Awtonomow               Kevin Kempton                     Jose Ortiz               Greg Hajos
       Deputy for Testing                             Deputy                       Deputy                         Deputy                    Deputy

        Chip Holloway                                                    Amy Houts-Gilfriche
      Deputy for Integration                                                       Deputy


National Aeronautics and Space Administration                                                                                                             5
Integration with the IPT’s


             ♦ Established a Lead Systems Engineer (LSE) as technical lead
               for the mission

             ♦ Established Systems Engineers (SE’s) in each IPT
                     • SE’s met regularly with the LSE to work issues as a group
                             − Allowed insight into another IPT’s issues
                             − Sometimes simple changes on one side of an interface saves major
                               changes

             ♦ SE&I avionics function was closely tied to Avionics IPT
                     • Many times SE&I supplemented Avionics workforce
                     • At the end of the Mission several SE&I personnel were assigned part
                       time to the Avionics IPT




National Aeronautics and Space Administration                                                     7465.6
Integrated Design and Analysis (ID&A)
                                                                                                                             Trajectory
                                                                                                                     -Range Data Package
                                                                                                                - Ascent 6 DoF Monte Carlo
                                                                                                                     -Stage Sep. Definitions
                                                                                                                       - USS Reentry Study



  Aerodynamics
  - Roll-Out and On Pad Aero
  -Lift-Off Aero
                                                                                                    Vibro-acoustics
  - Ascent and Buffet Aero
                                                                                                    -Vibro-acoustics Databook
  -Stage Separation Aero
                                                                                                    -Buffet and Aero Acoustics
  -Aero Databook
                                                                                                    - Shock environments
                                                              Structures
                      Integrated Design &                     -Structures Data Book
                                                              -Loads: Prelaunch, Liftoff, Ascent
                            Analysis                          -Modal Testing




 Thermal
 - Ascent on Pad                                                                                   Guidance, Navigation & Control
 - Thermal Prediction Report                                                                                               - Drift Analysis
   & Databook                                                                                                   -Stage Separation Analysis
                                                     Integrated Mass Properties
                                                                                                         - GN&C Simulation Comparisons
                                                    Mass Allocation Baseline
                                                    Mass Prop. Control Plan                           -Control Algorithm & Parameter Doc.


National Aeronautics and Space Administration                                                                                                  7c
ID&A Supporting Organizations

             ♦ Many organizations (Government and Contractor) supported
               the ID&A effort in developing requirements and evaluating
               analyses

             ♦ Major participants
                     • Guidance, Navigation & Control
                             − LaRC, MSFC, ULA, Aerospace Corp, Honeywell
                     • Trajectory
                             − LaRC, JSC, MSFC, JPL
                     • Thermal
                             − LaRC, MSFC, GRC, ATK, TBE
                     • Vibro-Acoustics
                             − Aerospace Corp, JSC
                     • Structures & Loads
                             − LaRC, Boeing, USA, GRC, MSFC, ATK, Aerospace
                     • Aerodynamics
                             − LaRC, Aerospace Corp.
                     • Mass Properties
                             − LaRC, ATK, GRC, Aerospace Corp.
                     • IV&V across all IDA – Aerospace Corp, Boeing
National Aeronautics and Space Administration                                   8
Numerous Tiger Teams

            ♦ Ignition Over Pressure
                    • Mobile Launch Platform cover requirements

            ♦ Transonic forcing function
                    • Transformation of wind tunnel results to I-X loads

            ♦ Vibro-Acoustics
                    • Resolve late buffet data from Ares I wind tunnel test

            ♦ USS secondary structure
                    • Independent review of analysis

            ♦ Loads & Environments
                    • Prelaunch
                    • Lift-Off (1st 6 seconds of flight)
                    • Ascent to separation

            ♦ Ground wind loads for roll-out and on-pad stay
                    • Multiple independent review teams, NESC IV&V

National Aeronautics and Space Administration                                 9
ID&A Integration Lessons

           ♦ NESC is an extremely valuable resource
                    • NESC has access to best Agency expertise
                    • Wears Agency hat – impartial - particularly useful if technical disagreement occurs
                      across center lines

           ♦ Recognize value of contractor technical leadership
                    • Technical experience and depth in industry provides significant capability

           ♦ Use multiple organizations to simulate and model the design
                    • Use a competitive environment to help scrub out errors
                    • Dictating one simulation architecture is a mistake

           ♦ Promote technical conference-like interchange between disciplines
                    • Numerous interchanges over the life of the project across IPTs and disciplines
                    • Important details regarding lift-off loads modeling and the GNC fly-away maneuver
                      unexpectedly discovered

           ♦ Use Multi-center Working Groups for analysis validation and verification
                    • Experience specific to launch vehicle analyses exists across centers and is quickly
                      infused into design process through working groups.



National Aeronautics and Space Administration                                                               10
Assembly, Integration, & Test Plan

             ♦ Plan detailed IPT responsibilities
               for assemblies and interfaces
                     • Necessary for a large multi-center,
                       multi-location project

             ♦ Roles and Responsibility Matrix
               located in AIT Plan
                     • 68 X 17 matrix of agreements
                     • Approximately 1200 agreements


             ♦ Plan included the Drawing Tree

             ♦ Ares I-X FTV
                • 160 subsystems of flight hardware
                • 48 sub-assemblies




National Aeronautics and Space Administration                                        11
Assembly, Integration, & Test

      ♦ Top level chronological plan of assembly,
        integration, and test
               • Utilized when parts from more than one IPT
                 were assembled, integrated, or tested together
               • Plan covered activities beginning with DFI
                   installation at GRC, KSC, LaRC and ATK
               • Plan ended with initiation of countdown


      ♦ Plan was a useful tool to:
               • Encourage discussions on assembly & drawings
               • Develop agreements




National Aeronautics and Space Administration                                   12
Ares I-X Major Tests

             ♦ Channelization in HB4 of Stacks 1-5

             ♦ Weight and CG of each lift

             ♦ OML Measurement - alignment, parallelism, perpendicularity,
               profile straightness and cylindricity

             ♦ Stack 1, Stack 5, and FTV Modal tests

             ♦ Channelization in HB3 of SRB+Stack 1

             ♦ FTINU Optical Verification in HB 3

             ♦ LVRT – Launch Vehicle Readiness Test (Full Functional)
               before flight battery installation in HB3

             ♦ IST – Integrated Systems Test (Full Functional) at Pad 39B
National Aeronautics and Space Administration                                13
Range Safety Interfaces


             ♦ Though Lead by LaRC, Each Task Required Extensive
               Interactions with the Interfaces Indicated

             ♦ Launch Constellation Range Safety Panel – JSC, KSC, MSFC,
               HQ, 45th Space Wing (Air Force)

             ♦ Telemetry and ground station – WFF, KSC, 45th

             ♦ Program Requirements Document – KSC, MSFC, 45th

             ♦ Range safety waivers – KSC, MSFC, 45th

             ♦ Flight Termination System spectrum frequency management –
               MSFC, JSC

             ♦ Range Steering Panel – KSC, JSC, MSFC, 45th


National Aeronautics and Space Administration                              14
Launch and Mission Operations


             ♦ Added KSC deputy for launch and flight integration
             ♦ Developed launch commit criteria – KSC, MSFC, JSC
                     • Focused meetings with each IPT and working groups
             ♦ SE&I maintained close participation in KSC Operations forum
                     • Multiple daily meetings to resolve integration issues
             ♦ Developed Program Requirements Document – KSC, MSFC,
               JSC
             ♦ Launch Operations network interface development – KSC
             ♦ Hangar AF recovery operations – MSFC, KSC, 45th
                     • Explosive Site Plan
                     • Post-Fire Operations Development
             ♦ Post-flight data management plan – KSC, MSFC




National Aeronautics and Space Administration                                   15
Systems Requirements and Verification


             ♦ Requirements flow from the Mission Flight Test Plan

             ♦ The system level requirements were held in two documents
                     • System Requirements Document (SRD) – Contains the Flight Test
                       Vehicle (FTV) requirements
                     • Ground Systems Requirements Document (GSRD) – Contains the
                       Ground System (GS) requirements

             ♦ FTV System level requirements were decomposed to element
               requirement documents (ERD)
                     • Avionics (AVI)
                     • Crew Module/Launch Abort System Simulator (CMLAS)
                     • First Stage (FS)
                     • Roll Control System (RoCS)
                     • Upper Stage Simulator (USS)




National Aeronautics and Space Administration                                          16
Requirements and Verification

             ♦ System level requirements (FTV and GS)
                     • Each system requirements is owned by an System Requirement Owner
                       (SRO)
                     • Throughout the mission the SRO is accountable for definition,
                       implementation and verification of the requirement
                     • All system level verifications reviewed by Ares I-X (Chief Engineer,
                       S&MA, Lead System Engineer) and very experienced independent review
                       team

             ♦ FTV Element requirements
                     • Element requirement owner (ERO) identified and accountable for each
                       element level requirement
                     • Element verification performed by each ERO
                     • Element verifications reviewed by SE&I SRO, Ares I-X (Chief Engineer,
                       SMA, Lead System Engineer) and by other IPTs
                             − SRO: The element verification “Meets the need of the system verification”
                             − Other elements: Interfaces and consistency

             ♦ SRO’s and ERO’s work together to develop and verify the
               components and system
National Aeronautics and Space Administration                                                              17
Verification Bow Wave


             ♦ Ares I-X experienced a verification crush prior to FTRR due to:
                     • Carefully selected subset of verifications completed prior to integration
                     • Project accepted risk: future verification might require some de-
                       integration
                     • Ares I-X pace led to late completion of element and system verifications

             ♦ What we did to help
                     • Engineering surge support team to help write and review verifications
                     • Traveled to IPTs to work verification issues
                     • Developed training package for verification writers and reviewers
                     • Incorporated key IPT players to review and revise system level
                       verifications

             ♦ Maintained process integrity
                     • Review maintained extremely high standards
                     • Knowledgeable independent team highly engaged
                     • All comments dispositioned with full and equal consideration


National Aeronautics and Space Administration                                                      18
Verification Burn-Down

             ♦ Ares I-X achieved 100% element and system requirement
               verification prior to launch
                                     140
                                           132             130       130            130        130                                                L-1
                                     120                                                                     121

                                                         115
                                     100                       105

                                                                      93




                                                                                                                                                                 FTV VRDS Closed
                     FTV VRDS Open




                                                                                                                   83
                                     80
                                                                               82

                                                                                          71
                                     60                                                                                59
                                                                                                     63
                                                                                                                             52
                                                                                                              53
                                     40                                                                                           38
                                                                                                                  42    33
                                                                                                                       30
                                     20                                                                                                  21
                                                                                                                            18
                                                                                                                                          7
                                                                                                                                 7
                                                                                                                                     3
                                      0                                                                                                       0
                                      28-Aug     4-Sep     11-Sep    18-Sep   25-Sep       2-Oct          9-Oct        16-Oct            23-Oct         30-Oct
                                                 Actual Remain to Submit CR                          Actual Remain to Close XCB
                                                 L-1                                                 Element Data



National Aeronautics and Space Administration                                                                                                                                      19
Summary


             ♦ Successful utilization of diverse resources
                     • Multiple center engineering teams (GN&C, thermal, aero, …)
                     • Project oriented personnel (Requirements, document development, …)
                     • Contractors
                     • NESC

             ♦ Successfully integrated cultures from multiple centers
                     • Human space flight vs science and robotic missions
                     • Development vs research

             ♦ Successfully integrated contractors and civil servants
                     • Contractors in key positions

             Bottom line
              When we needed to get something done – we got
              the right person to do it

National Aeronautics and Space Administration                                               20
http://WWW.NASA.GOV
http://www.nasa.gov/aresIX

Smith.marshall.bryant

  • 1.
    Marshall Smith, SystemsEngineering and Integration Chief Barry Bryant, Deputy SE&I Chief www.nasa.gov Used with permission
  • 2.
    Outline ♦ SE&I Organization Evolution • Increased scope • Increased personnel integration ♦ Integrated Design and Analysis (ID&A) • Distributed resources • Tiger teams ♦ Vehicle Assembly and Integration • Integration and testing ♦ Launch and Flight Integration • Range and Operations ♦ Systems Requirements and Verification • Requirements flow • Verification process ♦ Summary National Aeronautics and Space Administration 7465.2
  • 3.
    Ares I-X Organization Ares I-X Flight Test Mission Management Office Safety & Mission (MMO) Chief Engineers Assurance ( S& MA ) Mission Manager Deputy Managers Systems Engineering & Integration Chief Project Integration Manager Business Manager Business Manager Deputy Project Integration (PI) Systems Engineering & Integration ( SE&I ) Upper Stage Roll Control Ground Ground CM/LAS First Stage Simulator Avionics System Systems Operations Simulator ( USS ) ( RoCS ) ( GS ) ( GO ) National Aeronautics and Space Administration 3
  • 4.
    SE&I Evolution ♦ Established an SE&I Office (replaced AVIO) to include all aspects of mission ♦ Key organizational changes required to accommodate increased scope • Need to incorporate key members of the GO and GS teams • Increased scope of Range and Operations interactions • Expanded Requirements and Verification to include ground activities • Integrated Design and Analysis (ID&A) issues expanded to cover ground related issues • Established SE&I as the primary interface to GO and the Range during integration National Aeronautics and Space Administration 7465.4
  • 5.
    SE&I Organization Safety & Mission Assurance Systems Engineering & Integration Office Engineering David Helfrich Marshall Smith Henry Wright S&MA Lead (TA) Chief Lead Engineer (TA) K.C. Johnson Barry Bryant Jim Price Deputy S&MA Lead Deputy Chief Deputy for Operations Stanley Ward Kurt Detweiler Mike Bangham Robert Decoursey Deputy for PP&C Lead Systems Engineer (LSE) Deputy LSE Software Lead Cynthia Weathers Lanny Upton Secretary Deputy LSE Project Integration Paul Luz Susie Johnston Vernet Mull Dan Healey Donner Grigsby Schedules CM/DM Vehicle Assembly Launch & Systems Requirements Avionics & Integrated Design & Integration Flight Integration & Verification Software Integration & Analysis Rami Intriago James Price Kevin Vipavetz Will Scott Carey Buttrill Manager Manager Manager Manager Manager Rusty Jenkins Debbie Awtonomow Kevin Kempton Jose Ortiz Greg Hajos Deputy for Testing Deputy Deputy Deputy Deputy Chip Holloway Amy Houts-Gilfriche Deputy for Integration Deputy National Aeronautics and Space Administration 5
  • 6.
    Integration with theIPT’s ♦ Established a Lead Systems Engineer (LSE) as technical lead for the mission ♦ Established Systems Engineers (SE’s) in each IPT • SE’s met regularly with the LSE to work issues as a group − Allowed insight into another IPT’s issues − Sometimes simple changes on one side of an interface saves major changes ♦ SE&I avionics function was closely tied to Avionics IPT • Many times SE&I supplemented Avionics workforce • At the end of the Mission several SE&I personnel were assigned part time to the Avionics IPT National Aeronautics and Space Administration 7465.6
  • 7.
    Integrated Design andAnalysis (ID&A) Trajectory -Range Data Package - Ascent 6 DoF Monte Carlo -Stage Sep. Definitions - USS Reentry Study Aerodynamics - Roll-Out and On Pad Aero -Lift-Off Aero Vibro-acoustics - Ascent and Buffet Aero -Vibro-acoustics Databook -Stage Separation Aero -Buffet and Aero Acoustics -Aero Databook - Shock environments Structures Integrated Design & -Structures Data Book -Loads: Prelaunch, Liftoff, Ascent Analysis -Modal Testing Thermal - Ascent on Pad Guidance, Navigation & Control - Thermal Prediction Report - Drift Analysis & Databook -Stage Separation Analysis Integrated Mass Properties - GN&C Simulation Comparisons Mass Allocation Baseline Mass Prop. Control Plan -Control Algorithm & Parameter Doc. National Aeronautics and Space Administration 7c
  • 8.
    ID&A Supporting Organizations ♦ Many organizations (Government and Contractor) supported the ID&A effort in developing requirements and evaluating analyses ♦ Major participants • Guidance, Navigation & Control − LaRC, MSFC, ULA, Aerospace Corp, Honeywell • Trajectory − LaRC, JSC, MSFC, JPL • Thermal − LaRC, MSFC, GRC, ATK, TBE • Vibro-Acoustics − Aerospace Corp, JSC • Structures & Loads − LaRC, Boeing, USA, GRC, MSFC, ATK, Aerospace • Aerodynamics − LaRC, Aerospace Corp. • Mass Properties − LaRC, ATK, GRC, Aerospace Corp. • IV&V across all IDA – Aerospace Corp, Boeing National Aeronautics and Space Administration 8
  • 9.
    Numerous Tiger Teams ♦ Ignition Over Pressure • Mobile Launch Platform cover requirements ♦ Transonic forcing function • Transformation of wind tunnel results to I-X loads ♦ Vibro-Acoustics • Resolve late buffet data from Ares I wind tunnel test ♦ USS secondary structure • Independent review of analysis ♦ Loads & Environments • Prelaunch • Lift-Off (1st 6 seconds of flight) • Ascent to separation ♦ Ground wind loads for roll-out and on-pad stay • Multiple independent review teams, NESC IV&V National Aeronautics and Space Administration 9
  • 10.
    ID&A Integration Lessons ♦ NESC is an extremely valuable resource • NESC has access to best Agency expertise • Wears Agency hat – impartial - particularly useful if technical disagreement occurs across center lines ♦ Recognize value of contractor technical leadership • Technical experience and depth in industry provides significant capability ♦ Use multiple organizations to simulate and model the design • Use a competitive environment to help scrub out errors • Dictating one simulation architecture is a mistake ♦ Promote technical conference-like interchange between disciplines • Numerous interchanges over the life of the project across IPTs and disciplines • Important details regarding lift-off loads modeling and the GNC fly-away maneuver unexpectedly discovered ♦ Use Multi-center Working Groups for analysis validation and verification • Experience specific to launch vehicle analyses exists across centers and is quickly infused into design process through working groups. National Aeronautics and Space Administration 10
  • 11.
    Assembly, Integration, &Test Plan ♦ Plan detailed IPT responsibilities for assemblies and interfaces • Necessary for a large multi-center, multi-location project ♦ Roles and Responsibility Matrix located in AIT Plan • 68 X 17 matrix of agreements • Approximately 1200 agreements ♦ Plan included the Drawing Tree ♦ Ares I-X FTV • 160 subsystems of flight hardware • 48 sub-assemblies National Aeronautics and Space Administration 11
  • 12.
    Assembly, Integration, &Test ♦ Top level chronological plan of assembly, integration, and test • Utilized when parts from more than one IPT were assembled, integrated, or tested together • Plan covered activities beginning with DFI installation at GRC, KSC, LaRC and ATK • Plan ended with initiation of countdown ♦ Plan was a useful tool to: • Encourage discussions on assembly & drawings • Develop agreements National Aeronautics and Space Administration 12
  • 13.
    Ares I-X MajorTests ♦ Channelization in HB4 of Stacks 1-5 ♦ Weight and CG of each lift ♦ OML Measurement - alignment, parallelism, perpendicularity, profile straightness and cylindricity ♦ Stack 1, Stack 5, and FTV Modal tests ♦ Channelization in HB3 of SRB+Stack 1 ♦ FTINU Optical Verification in HB 3 ♦ LVRT – Launch Vehicle Readiness Test (Full Functional) before flight battery installation in HB3 ♦ IST – Integrated Systems Test (Full Functional) at Pad 39B National Aeronautics and Space Administration 13
  • 14.
    Range Safety Interfaces ♦ Though Lead by LaRC, Each Task Required Extensive Interactions with the Interfaces Indicated ♦ Launch Constellation Range Safety Panel – JSC, KSC, MSFC, HQ, 45th Space Wing (Air Force) ♦ Telemetry and ground station – WFF, KSC, 45th ♦ Program Requirements Document – KSC, MSFC, 45th ♦ Range safety waivers – KSC, MSFC, 45th ♦ Flight Termination System spectrum frequency management – MSFC, JSC ♦ Range Steering Panel – KSC, JSC, MSFC, 45th National Aeronautics and Space Administration 14
  • 15.
    Launch and MissionOperations ♦ Added KSC deputy for launch and flight integration ♦ Developed launch commit criteria – KSC, MSFC, JSC • Focused meetings with each IPT and working groups ♦ SE&I maintained close participation in KSC Operations forum • Multiple daily meetings to resolve integration issues ♦ Developed Program Requirements Document – KSC, MSFC, JSC ♦ Launch Operations network interface development – KSC ♦ Hangar AF recovery operations – MSFC, KSC, 45th • Explosive Site Plan • Post-Fire Operations Development ♦ Post-flight data management plan – KSC, MSFC National Aeronautics and Space Administration 15
  • 16.
    Systems Requirements andVerification ♦ Requirements flow from the Mission Flight Test Plan ♦ The system level requirements were held in two documents • System Requirements Document (SRD) – Contains the Flight Test Vehicle (FTV) requirements • Ground Systems Requirements Document (GSRD) – Contains the Ground System (GS) requirements ♦ FTV System level requirements were decomposed to element requirement documents (ERD) • Avionics (AVI) • Crew Module/Launch Abort System Simulator (CMLAS) • First Stage (FS) • Roll Control System (RoCS) • Upper Stage Simulator (USS) National Aeronautics and Space Administration 16
  • 17.
    Requirements and Verification ♦ System level requirements (FTV and GS) • Each system requirements is owned by an System Requirement Owner (SRO) • Throughout the mission the SRO is accountable for definition, implementation and verification of the requirement • All system level verifications reviewed by Ares I-X (Chief Engineer, S&MA, Lead System Engineer) and very experienced independent review team ♦ FTV Element requirements • Element requirement owner (ERO) identified and accountable for each element level requirement • Element verification performed by each ERO • Element verifications reviewed by SE&I SRO, Ares I-X (Chief Engineer, SMA, Lead System Engineer) and by other IPTs − SRO: The element verification “Meets the need of the system verification” − Other elements: Interfaces and consistency ♦ SRO’s and ERO’s work together to develop and verify the components and system National Aeronautics and Space Administration 17
  • 18.
    Verification Bow Wave ♦ Ares I-X experienced a verification crush prior to FTRR due to: • Carefully selected subset of verifications completed prior to integration • Project accepted risk: future verification might require some de- integration • Ares I-X pace led to late completion of element and system verifications ♦ What we did to help • Engineering surge support team to help write and review verifications • Traveled to IPTs to work verification issues • Developed training package for verification writers and reviewers • Incorporated key IPT players to review and revise system level verifications ♦ Maintained process integrity • Review maintained extremely high standards • Knowledgeable independent team highly engaged • All comments dispositioned with full and equal consideration National Aeronautics and Space Administration 18
  • 19.
    Verification Burn-Down ♦ Ares I-X achieved 100% element and system requirement verification prior to launch 140 132 130 130 130 130 L-1 120 121 115 100 105 93 FTV VRDS Closed FTV VRDS Open 83 80 82 71 60 59 63 52 53 40 38 42 33 30 20 21 18 7 7 3 0 0 28-Aug 4-Sep 11-Sep 18-Sep 25-Sep 2-Oct 9-Oct 16-Oct 23-Oct 30-Oct Actual Remain to Submit CR Actual Remain to Close XCB L-1 Element Data National Aeronautics and Space Administration 19
  • 20.
    Summary ♦ Successful utilization of diverse resources • Multiple center engineering teams (GN&C, thermal, aero, …) • Project oriented personnel (Requirements, document development, …) • Contractors • NESC ♦ Successfully integrated cultures from multiple centers • Human space flight vs science and robotic missions • Development vs research ♦ Successfully integrated contractors and civil servants • Contractors in key positions Bottom line When we needed to get something done – we got the right person to do it National Aeronautics and Space Administration 20
  • 21.