SlideShare a Scribd company logo
Page 1Classification: Restricted
PMP Certification Training
Project Planning
Page 2Classification: Restricted
Agenda
• Develop Project Management Plan
• Plan Scope Management
• Collect Requirements
• Requirements Documentation
• Define Scope
• Create WBS
• Plan Schedule Management
• Define Activities
• Sequence Activities
• Estimate Activity Resources
• Estimate Activity Duration
• Develop Schedule
Page 3Classification: Restricted
Develop Project ManagementPlan
• Documenting the actions necessary to define, prepare, integrate, &
coordinateall subsidiary plans into a project management plan.
Page 4Classification: Restricted
Develop Project ManagementPlan
Page 5Classification: Restricted
Project Management Plan
• Integrates and consolidates all of the subsidiary management plans
and baselines from the planning processes.
• Includes but not limited to:
 Project management processes selected by the project
management team.
 Level of implementation of each selected process.
 Descriptions of tools & techniques
 How the selected processes will be selected to manage the specific
project
• How work will be executed to accomplish objectives
• A change management plan
Page 6Classification: Restricted
Project Management Plan contents
Page 7Classification: Restricted
PMP Certification Training
Plan Scope Management
Page 8Classification: Restricted
Scope Planning
Page 9Classification: Restricted
Project Scope Vs. ProductScope
• Project Scope: The work that needs to be accomplished to deliver a
product, service, or result with the specified features and functions
• Product Scope: The features and functions that characterize a
product, service, or result
Page 10Classification: Restricted
Plan Scope Management
Page 11Classification: Restricted
Plan Scope Management
• The process of creating a scope management plan that documents
how the project scope will be defined, validated and controlled.
• It provides guidance on how scope will be managed throughout the
project.
Page 12Classification: Restricted
Plan Scope Management
Page 13Classification: Restricted
Project Scope Management Plan
• Part of Develop Project Management Plan
• The outcome of a planning effort that precedes performing the
processes of project scope management
• Documents how the scope will be defined, verified, controlled, and
how the work breakdown structure (WBS) will be created and
defined.
• Can be formal or informal depending on needs of the project.
Page 14Classification: Restricted
It Includes:
• Processes for:
–Detailing the project scope statement.
–WBS creation, maintenance, and approval.
–Formal verification and acceptance of the completed project
deliverables.
–Control how requests to change the detailed project scope
statement will be processed.
Page 15Classification: Restricted
Requirements Management Plan (RQM)
• A Plan that documents how requirements will be analyzed, document
and managed (tracked, reported, prioritized…) throughout the project life
cycle.
Page 16Classification: Restricted
Requirements Management Plan (RQM) Components
• How Requirement activities will be planned, tracked and reported
• Configuration Management Activities
• Requirements Prioritization Process
• Product Metrics
• Traceability Structure
PMP Certification Training
Collect Requirements
Page 18Classification: Restricted
Collect Requirement
Page 19Classification: Restricted
Collect Requirement
• The process of defining and documenting stakeholders’ needs to meet
project
objectives.
• Requirements include the quantified and documented needs and
expectations of the sponsor, customer, and other stakeholders.
• WBS, cost, schedule and quality planning are all built upon these
requirements.
• Need to be elicited, analyzed, and recorded in enough detail to be
measured once project execution begins
• Project Requirements include business requirements, project
management
requirements, delivery requirements, etc.
• Product Requirements include information on technical requirements,
security requirements, performance requirements, etc.
Page 20Classification: Restricted
Collect Requirements
Page 21Classification: Restricted
Interviews
• Talking to stakeholders directly.
• Asking questions and recording answers
• “One-on-one”, or multiple interviewers and/ or interviewees.
• Interviewing:
Experienced participants
Stakeholders
Subject matter experts
Page 22Classification: Restricted
Focus Groups
• Bring together prequalified stakeholders and subject matter experts.
• Trained moderator guides the group through an interactive
discussion.
• More conservational than one-on-one
Page 23Classification: Restricted
Facilitated Workshops
• Focused sessions that bring key cross-functional stakeholders
together to define product requirements
• Helps in building trust, foster relationships, and improve
communication.
• Reveal and resolve issues more quickly than individual sessions.
• Examples: Joint Application Development (JAD) & Quality Function
Deployment (QFD)
Page 24Classification: Restricted
Group Creativity Techniques
• Brainstorming. A technique used to generate and collect multiple ideas
related to project
and product requirements.
• Nominal group technique. This technique enhances brainstorming with
a voting process used to rank the most useful ideas for further
brainstorming or for prioritization.
• The Delphi Technique. A selected group of experts answers
questionnaires and provides feedback regarding the responses from
each round of requirements gathering. The responses are only available
to the facilitator to maintain anonymity
• ldea/mind mapping. Ideas created through individual brainstorming are
consolidated into a single map to reflect commonality and differences in
understanding, and generate new ideas.
• Affinity diagram. This technique allows large numbers of ideas to be
sorted into groups for review and analysis.
Page 25Classification: Restricted
Mind Map Example
Page 26Classification: Restricted
Group Decision
Page 27Classification: Restricted
Questionnaires & Surveys
• Written sets of questions.
• Aim to quickly accumulate information from a broad group of
respondents.
• Most appropriate with broad audience, when quick turnaround is
needed, and where statistical analysis is appropriate.
Page 28Classification: Restricted
Observations
• Viewing user performance
• Also called “Job shadowing”
• Helpful for detailed processes when people that use the product have
difficulty or reluctant to articulate their requirements
• Can uncover hidden requirements
Page 29Classification: Restricted
Prototypes
• Provide a working model of the expected product before actually
building it.
• Support the concept of progressive elaboration through use of
iterative cycles of mock-up creation, user experimentation, feedback
generation and prototype revision.
Page 30Classification: Restricted
Benchmarking
• Involves comparing actual or planned practices, such as processes
and operations, to those of comparable organizations to identify best
practices, generate ideas for improvement, and provide a basis for
measuring performance.
• Compared organizations can be external or internal.
Page 31Classification: Restricted
Context Diagrams
• Visually depict the product scope
by showing a business system
(process, equipment, computer
system…etc.), and how people and
other systems (actors) interact
with it.
• Context diagrams show inputs to
the business system, the actor(s)
providing the input, the outputs of
the business system, and the
actor(s) receiving the output.
Page 32Classification: Restricted
Requirements Documentation
• The document including the stakeholders’ requirements to meet the
business need for the project.
• Usually starts at a high level and then gets elaborated within the life
cycle of the project and according to the RQM
Page 33Classification: Restricted
Requirements Documentation Elements
• Business need or opportunity
• Functional requirements and non functional requirements
• Quality requirements
• Acceptance criteria
• Business rules
• Impacts to other organizational areas, and other entities inside or
outside
the performing organization
• Support and training requirements
• Requirements assumptions and constraints
Page 34Classification: Restricted
Requirements Traceability Matrix
• A tool that links project objectives to requirements to deliverables to
product features.
• The structure and level of details of the traceability matrix to be used
shall be documented in the RQM as different projects can use different
structures of traceability.
• This tool can be as simple as a table or as complex as a software
program.
Page 35Classification: Restricted
Requirements Traceability Matrix Contents
• Business needs, opportunities, goals, and objectives
• Project objectives
• Project scope, WBS deliverables
• Product design
• Product development
• Test strategy and test scenarios
• High level requirements to more detailed requirements
Page 36Classification: Restricted
RTM Sample Format
PMP Certification Training
Define Scope
Page 38Classification: Restricted
Define Scope
Page 39Classification: Restricted
Define Scope
• The process of developing a detailed description of the project and
the product
• Critical to project success.
• Builds upon the major deliverables, assumptions, and constraints
documented in the project initiation.
Page 40Classification: Restricted
Define Scope
Page 41Classification: Restricted
Product Analysis
• Translating high-level product description into tangible deliverables
• Includes techniques such as:
Product breakdown
System analysis
Requirements analysis
System engineering
Value engineering
Value analysis
Page 42Classification: Restricted
Alternatives Identification
• A technique to generate different approaches to execute and perform the
work of the project.
• Includes techniques such as:
Brainstorming
Lateral thinking
Pair wise comparison
Page 43Classification: Restricted
Project Scope Statement
• The project scope statement describes in details the project
deliverables, and the work required to create those deliverables.
Common understanding among stakeholders,
Enables more detailed planning,
Guides the project team’s work during execution,
Provides the baseline for evaluating changes.
Page 44Classification: Restricted
Project Scope Statement Contents
• Product scope description
• Product acceptance criteria
• Project deliverables
• Project exclusions
• Project constraints
• Project assumptions
Page 45Classification: Restricted
Constraints & Assumptions
• Constraints
• Applicable restrictions that will affect the performance of the project.
• Factors that affect a scheduled activity or when an activity can be
scheduled.
• Assumptions
• Are factors that, for planning purposes, are considered to be true, real, or
certain.
• Affect all aspects of project planning.
• Part of the project’s progressive elaboration.
• Generally involve a degree of RISK.
• Must be identified, documented and validated.
PMP Certification Training
Create WBS
Page 47Classification: Restricted
Create WBS
Page 48Classification: Restricted
Create WBS
• The process of subdividing project deliverables and project work into
smaller, more manageable components.
• WBS is a deliverable-oriented hierarchical decomposition of the work to
be executed by the project team to accomplish the project objectives,
and create the required deliverables.
• Each descending level represents an increasingly detailed definition of
the project work.
• Organizes and defines the total scope of the project.
Page 49Classification: Restricted
Example WBS
Page 50Classification: Restricted
Example WBS
Page 51Classification: Restricted
Create WBS
Page 52Classification: Restricted
Decomposition
• Subdivision of project deliverables into smaller, more manageable
components until the work and deliverables are defined to the work
package level.
• The level of composition varies per deliverable/ phase with the size
and complexity of project.
Page 53Classification: Restricted
Work Package
• The “Work Package” level is the lowest level in the WBS.
• Work Package is the point at which the cost and activity duration can
be reliable, estimated and packaged.
Page 54Classification: Restricted
Decomposition Involves
• Identifying deliverables and related work.
• Structuring and organizing the WBS.
• Decomposing upper levels into lower level detailed components.
• Developing and assigning identification codes.
• Verifying that the degree of decomposition is necessary and
sufficient.
Page 55Classification: Restricted
WBS Dictionary Content
• Code of account identifier
• Statement of work
• Responsible organization
• Schedule milestones
• Associated activities
• Resources required
• Cost estimates
• Quality requirements
• Acceptance criteria
• Technical references
• Contract information
Page 56Classification: Restricted
Scope Baseline
• Scope statement
• WBS
• WBS dictionary
Page 57Classification: Restricted
WBS Dictionary
• A document generated by the “Create WBS” process that supports
the WBS.
• Provides more detailed description of the components in the WBS.,
including work packages and control accounts.
Page 58Classification: Restricted
WBS is not
• Organizational Breakdown Structure (OBS)
• Bill Of Materials (BOM)
• Risk Breakdown Structure (RBS)
• Resource Breakdown Structure (RBS)
PMP Certification Training
Plan Schedule Management
Page 60Classification: Restricted
Project Time Planning
Page 61Classification: Restricted
Plan Schedule Management
Page 62Classification: Restricted
Plan Schedule Management
• The process of establishing policies, procedures, and documentation for
planning, developing, managing, executing, and controlling the project
schedule.
• The key benefit of the process is that it provides guidance and
direction on how the project schedule will be managed throughout
the project.
Page 63Classification: Restricted
Plan Schedule Management
Page 64Classification: Restricted
Analytical Techniques
• Scheduling Methodology
• Scheduling Tools & Techniques
• Estimating Approaches
• Formats
• Project Management Software
Page 65Classification: Restricted
Schedule Management Plans
• A component of the project management plan.
• Establishes the criteria and activities for developing, monitoring, and
controlling the schedule.
• Can be formal or informal
• Can be highly detailed or broadly defined based on the needs of the
project
Page 66Classification: Restricted
Schedule Management Plans
• Can include the following:
Project schedule model development
Level of accuracy
Units of measure
Organizational procedures links
Project schedule management
maintenance
Control schedule
Rules of performance measurement
Reporting formats
Process description
PMP Certification Training
Define Activities
Page 68Classification: Restricted
Define Activities
Page 69Classification: Restricted
Define Activities
• The process of identifying the specific actions to be performed to
produce the project deliverables.
• Decomposed from the “work packages” at the WBS.
• Activities are the smaller components that represent the work
necessary to complete the work package.
• Activities provide basis for estimating, scheduling, executing, and
monitoring and controlling the project work.
Page 70Classification: Restricted
Define Activities
Page 71Classification: Restricted
Rolling Wave Planning
• Progressive detailing of the project management plan
Page 72Classification: Restricted
Activity List
• A comprehensive list including all schedule activities required for the
project.
• Includes:
• Activity identifier
• Description of each activity
PMP Certification Training
Sequence Activities
Page 74Classification: Restricted
Sequence Activities
Page 75Classification: Restricted
Sequence Activity
• Identifying & documenting dependencies among schedule activities
• Can be done using software or manually.
Page 76Classification: Restricted
Sequencing Activities
Page 77Classification: Restricted
Precedence Diagramming Method (PDM)
• Also known as Activity-On-Node
• Activities are represented in
boxes (Nodes), and arrows show
dependencies
Page 78Classification: Restricted
Dependencies Relationships
• Finish-to-Start
• Finish-to-Finish
• Start-to-Start
• Start-to-Finish
Page 79Classification: Restricted
Dependencies Relationships
• Use the following Rule of Thumb to understand the relationships
better:
• Activity A should _ _ _ _ _ _ Before activity B can _ _ _ _ _ _
Page 80Classification: Restricted
Types of Dependencies
• Mandatory
• Discretionary
• External
• Internal
Page 81Classification: Restricted
Applying Leads & Lags
• Lead: The overlapping time
• Lag: The waiting time
• Float/ Slack: The time an
activity can be delayed (wait)
without affecting the project
finish date
• A lead allows an acceleration of
the successor activity.
• A lag directs a delay in
the successor activity.
Page 82Classification: Restricted
Applying Leads & Lags
PMP Certification Training
Estimate Activity Resources
Page 84Classification: Restricted
Estimate Activity Resources
Page 85Classification: Restricted
Estimate Activity Resources
• Estimating the type and quantities of resources required to perform
each schedule activity
Page 86Classification: Restricted
Types of Resources
• Material
• People
• Equipment
Page 87Classification: Restricted
Estimate Activity Resources
PMP Certification Training
Estimate Activity Duration
Page 89Classification: Restricted
Estimate Activity Durations
Page 90Classification: Restricted
Estimate Activity Durations
• Approximating the number of work periods needed to complete
individual
activities with estimated resources.
• Uses information on:
Activity scope of work
Required resource types
Estimated resource quantities
Resource calendar
• Progressively elaborative
• Takes elapsed time into account
Page 91Classification: Restricted
Estimate Activity Durations
Page 92Classification: Restricted
Estimate Activity Durations: Tools and Techniques
Page 93Classification: Restricted
Estimate Activity Durations: Tools and Techniques
Page 94Classification: Restricted
Estimate Activity Durations: Tools and Techniques
• Three-Point Estimating
• The accuracy of activity duration estimates can be improved by
considering
estimation uncertainty and risk.
• Triangular Distribution. tE= (tO+ tM+ tP) / 3
• Beta Distribution (from the traditional PERT technique). tE= (tO+ 4tM
+ tP) / 6
• Time Expected (tE)= (tO+4xtM+tP)/6
• tO: Optimistic Estimate
• tM= Average Estimate
• tP= Pessimistic Estimate
Page 95Classification: Restricted
Beta Distribution
Page 96Classification: Restricted
Activity Optimistic Duration
• The total number of work periods in calendar units assigned to
perform the schedule activity, considering all of the variables that
could affect performance, and is determined to be the shortest
possible activity duration
• It is determined by answering the question
• How long will it take in the best case scenario?
Page 97Classification: Restricted
Activity Pessimistic Duration
• The total number of work periods in calendar units assigned to
perform the schedule activity, considering all of the variables that
could affect performance, and is determined to be the longest
possible activity duration
• It is determined by answering the question
• How long will it take in the worst case scenario?
Page 98Classification: Restricted
Activity Most LikelyDuration
• The total number of work periods in calendar units assigned to perform
the schedule activity, considering all of the variables that could affect
performance, and is determined to be the most probable activity
duration
• It is determined by answering the question:
• How long will it most likely take?
Page 99Classification: Restricted
Standard Deviation &Variance
Page 100Classification: Restricted
Estimates Certainty
• Confidence level in the value is approximately 50%
• Confidence level in the value + SD is approximately 85%
• Confidence level in the value + 1.645 ×SD is approximately 95%
• Confidence level in the value + 2 ×SD is approximately 98%
• Confidence level in the value + 3 ×SD is approximately 99.9%
Page 101Classification: Restricted
3-Point Estimate (PERT)
Page 102Classification: Restricted
3-Point Estimate (PERT)
Page 103Classification: Restricted
3-Point Estimate (PERT)
Page 104Classification: Restricted
Exercise
Page 105Classification: Restricted
Heading 1
• See that the question says that Duration Uncertainty is Pessimistic minus
Optimistic in other words P-O. We know that SD is (P-O ) / 6 , thus SD is
"duration Certainty " / 6
• Thus For Path 1:
• SD = 18/6 = 3
• Variance = 3*3 = 9
• For path 2:
• SD = 24 /6 = 4
• Variance = 4*4 = 16
• Total Path Variance = 16 + 9 = 25
• Sqrt (25) = 5
• Meaning (P-O) / 6 = 5
• (p-O) = 5 * 6
• DURATION UNCERTAINTY = 30
Page 106Classification: Restricted
Schedule Uncertainty & Risk AnalysisProcess
• Schedule risk analysis uses information about the uncertainty of
activity durations to help answer the following questions:
• What is the likelihood of finishing project as scheduled?
• How much contingency is needed to establish a completion date
with a
probability of success that is acceptable to the stakeholders?
• Which activities are the most likely to delay the project?
• What actions can be taken to control risks in the schedule?
Page 107Classification: Restricted
Critical Path
• The longest path from the beginning to the end of the project. Activities
on the critical path cannot be delayed without delaying the project.
• There can be more than one critical path (riskier)
• Project Manager should focus on critical path.
Page 108Classification: Restricted
Network Diagram
Page 109Classification: Restricted
Calculating Critical Path
• Specify the individual activities.
• Determine the sequence of activities.
• Draw the network diagram.
• Estimate activity completion time.
• Identify critical path.
PMP Certification Training
Develop Schedule
Page 111Classification: Restricted
Develop Schedule
Page 112Classification: Restricted
Develop Schedule
• The process of analyzing activity sequences, durations, resource
requirements, and schedule constraints.
• Provides specific start and end dates for activities.
• Iterative process.
Page 113Classification: Restricted
Develop Schedule
Page 114Classification: Restricted
Resource Optimization Techniques
• Resource Leveling
• Resource Smoothing
Page 115Classification: Restricted
Resource leveling
Page 116Classification: Restricted
Resource leveling
Page 117Classification: Restricted
Modeling Techniques
• What-If Scenario Analysis
• Simulation
Page 118Classification: Restricted
Develop Schedule
• Resource Smoothing. A technique that adjusts the activities of a
schedule model such that the requirements for resources on the project
do not exceed certain predefined resource limits. In resource smoothing,
as opposed to resource leveling, the project’s critical path is not changed
and the completion date may not be delayed. In other words, activities
may only be delayed within their free and total float. Thus resource
smoothing may not be able to optimize all resources.
Page 119Classification: Restricted
What-If Scenario Analysis
• An analysis of the question “what if the situation represented by
scenario ‘X’ happens”.
• Can be used to assess the feasibility of the schedule under adverse
conditions, and in preparing contingency and response plans.
Page 120Classification: Restricted
Schedule Compression
• Fast Tracking- A schedule compression technique in which phases or
activities normally performed in sequence are performed in parallel. It
can result in rework and increased risks.
• Crashing- A schedule compression technique in which cost and schedule
tradeoffs are analyzed to determine how to obtain the greatest amount
of compression for the latest incremental cost. It can result in increased
cost.
Page 121Classification: Restricted
Critical Chain Method
• A schedule network analysis
technique that modifies the
project schedule to account for
limited resources (according to
PMBOK…).
• Combines deterministic and
probabilistic approaches.
Page 122Classification: Restricted
Project schedule
• Milestone Chart
• Bar Chart
• Project schedule network chart
Page 123Classification: Restricted
Schedule Baseline
• Project schedule with baseline start dates and baseline finish dates.
• Start & Finish Dates
• ES: Earliest start time.
• EF: Earliest finish time.
• LF: Latest finish time.
• LS: Latest start time.
Page 124Classification: Restricted
Critical Path Basic Method
Page 125Classification: Restricted
Calculating Early and Late Start and Finish Dates
Page 126Classification: Restricted
Calculating Forward & Backward Pass
• Forward Pass
• Schedule Calculations That Identify The Early Start and Finish Dates of
Tasks
and The Project.
• ES = EF of Preceding Task (latest if more than one).
• EF = ES + Duration.
• Backward Pass
• Schedule Calculations That Identify The Late Start and Finish Dates of
Tasks
and The Project.
• LF = LS of succeeding Task (earliest if more than one).
• LS = LF -Duration
Page 127Classification: Restricted
Float
• Float or slack is the amount of time that a task in a project network
can be delayed without causing a delay to:
• Subsequent tasks (free float)
• Project completion date (total float)
Total Float = LF –EF
 OR
 LS -ES
• Free Float = Min ES (Succeeding Task) –EF
Page 128Classification: Restricted
Critical Path
Page 129Classification: Restricted
Critical Path
Page 130Classification: Restricted
Critical Path
Page 131Classification: Restricted
Critical Path
Page 132Classification: Restricted
Using Critical Path Analysis to Make Schedule
Trade-offs
• Free slack or free float is the amount of time an activity can be
delayed without delaying the early start of any immediately following
activities.
• Total slack or total float is the amount of time an activity can be
delayed from its early start without delaying the planned project
finish date.
Page 133Classification: Restricted
Gantt Chart
• Graph or bar chart with a bar for each project activity that shows
passage of time
• Provides visual display of project schedule
• Slack- amount of time an activity can be delayed without delaying the
project
Page 134Classification: Restricted
Topics to be covered in next session
• Project Execution Process
• Project Execution - Acquire Project Team
• Project Execution - Develop Project Team
• Project Execution - Manage Project Team
• Communications Manage Communications
• Procurement Conduct Procurement
• Stakeholder Manage Stakeholders Engagement
Page 135Classification: Restricted
Thank You

More Related Content

What's hot

Project Management: How the MBA Can Help You Succeed
Project Management: How the MBA Can Help You SucceedProject Management: How the MBA Can Help You Succeed
Project Management: How the MBA Can Help You SucceedDavid Edgerton, Jr.
 
Business analysis planning and monitoring
Business analysis planning and monitoringBusiness analysis planning and monitoring
Business analysis planning and monitoring
nyasha charumbira
 
Top Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad ThaljiTop Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad Thalji
Top Pillars
 
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaOnline PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
GlobalSkillup
 
Project management 1
Project management 1Project management 1
Project management 1bnettel
 
Vendor management using COBIT 5
Vendor management using COBIT 5Vendor management using COBIT 5
Vendor management using COBIT 5
Robert Stroud
 
Pmo cks
Pmo cksPmo cks
Pmo cks
Ravi Roestam
 
9- PMP Training - Communication Management
9- PMP Training - Communication Management9- PMP Training - Communication Management
9- PMP Training - Communication Management
Qais Ur Rehman Rasooli, PMP
 

What's hot (9)

Project Management: How the MBA Can Help You Succeed
Project Management: How the MBA Can Help You SucceedProject Management: How the MBA Can Help You Succeed
Project Management: How the MBA Can Help You Succeed
 
Business analysis planning and monitoring
Business analysis planning and monitoringBusiness analysis planning and monitoring
Business analysis planning and monitoring
 
Top Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad ThaljiTop Pillars | PMP training I Mr. Riad Thalji
Top Pillars | PMP training I Mr. Riad Thalji
 
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge AreaOnline PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
Online PMP Training Material for PMP Exam - StakeholderManagement Knowledge Area
 
BAs IIBA and the BABOK
BAs IIBA and the BABOKBAs IIBA and the BABOK
BAs IIBA and the BABOK
 
Project management 1
Project management 1Project management 1
Project management 1
 
Vendor management using COBIT 5
Vendor management using COBIT 5Vendor management using COBIT 5
Vendor management using COBIT 5
 
Pmo cks
Pmo cksPmo cks
Pmo cks
 
9- PMP Training - Communication Management
9- PMP Training - Communication Management9- PMP Training - Communication Management
9- PMP Training - Communication Management
 

Similar to Session 04 - Project Planning

Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
Agus Suhanto
 
Introduction to Business Analysis
Introduction to Business AnalysisIntroduction to Business Analysis
Introduction to Business Analysis
Sunil-QA
 
Requirement Elicitation Techniques
Requirement Elicitation TechniquesRequirement Elicitation Techniques
Requirement Elicitation Techniques
Shwetha-BA
 
Requirement Elicitation Techniques
Requirement Elicitation Techniques   Requirement Elicitation Techniques
Requirement Elicitation Techniques
Lakshmi-BA
 
SDLC Training for Business Analysts
SDLC Training for Business AnalystsSDLC Training for Business Analysts
SDLC Training for Business Analysts
SwatiS-BA
 
Fundamentals of SDLC for Business Analysts
Fundamentals of SDLC for Business AnalystsFundamentals of SDLC for Business Analysts
Fundamentals of SDLC for Business Analysts
Veneet-BA
 
Introduction to Business Analysis
Introduction to Business Analysis Introduction to Business Analysis
Introduction to Business Analysis
Sunil-QA
 
Introduction to Business Analysis
Introduction to Business AnalysisIntroduction to Business Analysis
Introduction to Business Analysis
Shwetha-BA
 
Software Development Life Cycle – SDLC
Software Development Life Cycle – SDLCSoftware Development Life Cycle – SDLC
Software Development Life Cycle – SDLC
SwatiS-BA
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
Ahmed Elshaboury,PMP,LEED GA
 
Requirement Elicitation Techniques
Requirement Elicitation Techniques Requirement Elicitation Techniques
Requirement Elicitation Techniques
Shwetha-BA
 
Topic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdfTopic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdf
HuyNguyen657394
 
Project Formulation and Management - Project Scope Management
Project Formulation and Management - Project Scope ManagementProject Formulation and Management - Project Scope Management
Project Formulation and Management - Project Scope Management
Hrishikesh Satpute
 
Introduction to Business Analysis
Introduction to Business AnalysisIntroduction to Business Analysis
Introduction to Business Analysis
Mihika-QA
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
Zaur Ahmadov, PMP
 
PMP Exam Preparation Course: 04 Project Scope Management
PMP Exam Preparation Course: 04 Project Scope ManagementPMP Exam Preparation Course: 04 Project Scope Management
PMP Exam Preparation Course: 04 Project Scope Management
B M Shahrier Majumder, PMP, CSM
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
Abdullah Ahmed, PMP, RMP
 
Req.Management & Analysis.pptx
Req.Management & Analysis.pptxReq.Management & Analysis.pptx
Req.Management & Analysis.pptx
KYaghi1
 
Software Development Life Cycle - SDLC
Software Development Life Cycle - SDLCSoftware Development Life Cycle - SDLC
Software Development Life Cycle - SDLC
Shwetha-BA
 
Introduction to Business Analysis
Introduction to Business AnalysisIntroduction to Business Analysis
Introduction to Business Analysis
Shwetha-BA
 

Similar to Session 04 - Project Planning (20)

Project Scope Management - PMBOK6
Project Scope Management - PMBOK6Project Scope Management - PMBOK6
Project Scope Management - PMBOK6
 
Introduction to Business Analysis
Introduction to Business AnalysisIntroduction to Business Analysis
Introduction to Business Analysis
 
Requirement Elicitation Techniques
Requirement Elicitation TechniquesRequirement Elicitation Techniques
Requirement Elicitation Techniques
 
Requirement Elicitation Techniques
Requirement Elicitation Techniques   Requirement Elicitation Techniques
Requirement Elicitation Techniques
 
SDLC Training for Business Analysts
SDLC Training for Business AnalystsSDLC Training for Business Analysts
SDLC Training for Business Analysts
 
Fundamentals of SDLC for Business Analysts
Fundamentals of SDLC for Business AnalystsFundamentals of SDLC for Business Analysts
Fundamentals of SDLC for Business Analysts
 
Introduction to Business Analysis
Introduction to Business Analysis Introduction to Business Analysis
Introduction to Business Analysis
 
Introduction to Business Analysis
Introduction to Business AnalysisIntroduction to Business Analysis
Introduction to Business Analysis
 
Software Development Life Cycle – SDLC
Software Development Life Cycle – SDLCSoftware Development Life Cycle – SDLC
Software Development Life Cycle – SDLC
 
Pmp scope chapter 5
Pmp scope chapter 5Pmp scope chapter 5
Pmp scope chapter 5
 
Requirement Elicitation Techniques
Requirement Elicitation Techniques Requirement Elicitation Techniques
Requirement Elicitation Techniques
 
Topic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdfTopic 7 - Project Scope Management.pdf
Topic 7 - Project Scope Management.pdf
 
Project Formulation and Management - Project Scope Management
Project Formulation and Management - Project Scope ManagementProject Formulation and Management - Project Scope Management
Project Formulation and Management - Project Scope Management
 
Introduction to Business Analysis
Introduction to Business AnalysisIntroduction to Business Analysis
Introduction to Business Analysis
 
PMP-Scope Management area
PMP-Scope Management areaPMP-Scope Management area
PMP-Scope Management area
 
PMP Exam Preparation Course: 04 Project Scope Management
PMP Exam Preparation Course: 04 Project Scope ManagementPMP Exam Preparation Course: 04 Project Scope Management
PMP Exam Preparation Course: 04 Project Scope Management
 
PMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope managementPMP PMBok 5th ch 5 scope management
PMP PMBok 5th ch 5 scope management
 
Req.Management & Analysis.pptx
Req.Management & Analysis.pptxReq.Management & Analysis.pptx
Req.Management & Analysis.pptx
 
Software Development Life Cycle - SDLC
Software Development Life Cycle - SDLCSoftware Development Life Cycle - SDLC
Software Development Life Cycle - SDLC
 
Introduction to Business Analysis
Introduction to Business AnalysisIntroduction to Business Analysis
Introduction to Business Analysis
 

Recently uploaded

Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
Safe Software
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
RTTS
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi
Fwdays
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Product School
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Product School
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
DianaGray10
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Product School
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
Product School
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
Laura Byrne
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Tobias Schneck
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Thierry Lestable
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Inflectra
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
DanBrown980551
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
ThousandEyes
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
Alan Dix
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
Sri Ambati
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
UiPathCommunity
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance
 

Recently uploaded (20)

Essentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with ParametersEssentials of Automations: Optimizing FME Workflows with Parameters
Essentials of Automations: Optimizing FME Workflows with Parameters
 
JMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and GrafanaJMeter webinar - integration with InfluxDB and Grafana
JMeter webinar - integration with InfluxDB and Grafana
 
"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi"Impact of front-end architecture on development cost", Viktor Turskyi
"Impact of front-end architecture on development cost", Viktor Turskyi
 
Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...Mission to Decommission: Importance of Decommissioning Products to Increase E...
Mission to Decommission: Importance of Decommissioning Products to Increase E...
 
Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...Designing Great Products: The Power of Design and Leadership by Chief Designe...
Designing Great Products: The Power of Design and Leadership by Chief Designe...
 
UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3UiPath Test Automation using UiPath Test Suite series, part 3
UiPath Test Automation using UiPath Test Suite series, part 3
 
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
Unsubscribed: Combat Subscription Fatigue With a Membership Mentality by Head...
 
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdfFIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
FIDO Alliance Osaka Seminar: FIDO Security Aspects.pdf
 
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
From Siloed Products to Connected Ecosystem: Building a Sustainable and Scala...
 
The Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and SalesThe Art of the Pitch: WordPress Relationships and Sales
The Art of the Pitch: WordPress Relationships and Sales
 
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
Kubernetes & AI - Beauty and the Beast !?! @KCD Istanbul 2024
 
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
Empowering NextGen Mobility via Large Action Model Infrastructure (LAMI): pav...
 
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdfFIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
FIDO Alliance Osaka Seminar: Passkeys at Amazon.pdf
 
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered QualitySoftware Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
Software Delivery At the Speed of AI: Inflectra Invests In AI-Powered Quality
 
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
LF Energy Webinar: Electrical Grid Modelling and Simulation Through PowSyBl -...
 
Assuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyesAssuring Contact Center Experiences for Your Customers With ThousandEyes
Assuring Contact Center Experiences for Your Customers With ThousandEyes
 
Epistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI supportEpistemic Interaction - tuning interfaces to provide information for AI support
Epistemic Interaction - tuning interfaces to provide information for AI support
 
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
GenAISummit 2024 May 28 Sri Ambati Keynote: AGI Belongs to The Community in O...
 
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
Dev Dives: Train smarter, not harder – active learning and UiPath LLMs for do...
 
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdfFIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
FIDO Alliance Osaka Seminar: The WebAuthn API and Discoverable Credentials.pdf
 

Session 04 - Project Planning