An Introduction Software
       Engineering




                           1
Software Engineering

• Total lectures: 40
• Credit hours: 3 hrs
• Mentors:
  – Pre Mid Sem: Dr. Sonali Agarwal
  – Post Mid Sem: Prof. O.P. Vyas




                                      2
Course Objective

• This course gives a comprehensive analysis of software
  engineering techniques and the applications. Topic
  includes Software Development Life Cycle, Software
  processes management, requirement engineering,
  analysis and design, developing and testing of software
  integration, verification, validation, pattern based reuse,
  reliability  and      project    management       principles,
  techniques.


                                                              3
What is Software Crisis….




                            4
Software Crisis

 It was in late 1960’s.
 Many software projects failed.
 Many software projects late, over budget, providing unreliable
  software that is expensive to maintain.
 Many software projects produced software which did not satisfy
  the requirements of the customer.
 Complexities of software projects increased as hardware
  capability increased.




                                                               5
Software Crisis

• Larger software system is more difficult and expensive to
  maintain.
• Demand of new software increased faster than ability to
  generate new software.
• All the above attributes of what was called a ‘Software
  Crisis’.
• So the term ‘Software Engineering’ first introduced at a
  conference in late 1960’s to discuss the software crisis.




                                                          6
Why software engineering?




                            7
Why software engineering?

Once the need for software engineering was identified and software
  engineering recognized as a discipline--
• The late 1970’s saw the widespread evolution of software
  engineering principles.
• The 1980’s saw the automation of software engineering and
  growth of CASE (Computer Aided Software Engineering).




                                                                     8
Why software engineering

• The 1990’s have seen increased emphasis on the
  ‘management’ aspects of projects and the use of
  standard quality and ‘process’ models like ISO 9001 and
  the Software Engineering Institute’s Software Capability
  Maturity Model (CMM).

• These models help organizations put their software
  development and management processes in place




                                                             9
What is software Engineering?




                                10
What is software Engineering?

• In1969 Fritz Bauer defined software eng. as, ‘the establishment
  and use of sound engineering principles in order to obtain,
  economically, software that is reliable and works efficiently on real
  machines’.

• According to Boehm, software engineering involves, ‘the practical
  application of scientific knowledge to the design and construction
  of computer programs and the associated documentation required
  developing, operating and maintaining them’




                                                                     11
What is software Engineering?

• IEEE, in its standard 610.12-1990, defines software engineering
   as:
     (i) The application of a systematic, disciplined, quantifiable
   approach to the development, operation and maintenance of
   software; that is, the application of engineering to software.
 (ii) The study of approaches as in (i).

• By combining all the above definition we can define software
  engineering as, ‘Software engineering is the technological and
  managerial discipline concerned with systematic production and
  maintenance of software products that are developed and
  modified on time and within cost estimates.’


                                                                 12
What are the Goals of software
engineering….




                                 13
Goal of software engineering

The primary goals of software engineering are:
• To improve the quality of the software products.
• To increase the productivity &
• To give job satisfaction to the software engineers.




                                                        14
Foundation of Software engineering


Software engineering is a technological discipline
  distinct from, but based on the foundation of the
  following disciplines:

•   Computer Science
•   Management Science
•   Economics
•   System Engineering &
•   Communication Skills

                                                      15
The relationship of software
engineering with other disciplines




                                     16
The relationship of software engineering
with other disciplines

• Computer Science gives the scientific foundation to the
  software as electrical engineering relies on physics.
• Management Science provides the foundation for software
  project management. Since software engineering is labor
  intensive activity, it requires both technical and managerial
  control.
• Economics provides the foundation for resource estimation
  and cost control. Since, computing system must be developed
  and maintained on time and within cost estimates; thus
  economics plays an important role.




                                                                  17
The relationship of software
engineering with other disciplines

• System Engineering is the field concerned with
  studying complex systems. Software is often a
  component of a much larger system. For example, the
  software in a factory monitoring system or the flight
  software on an airplane; is just the component of more
  complex system. System engineering techniques can be
  applied to study of such systems




                                                       18
The relationship of software
engineering with other disciplines

• Good oral, written and interpersonal communication
  skills are crucial for the software engineers, because
  software engineering activities occur within an
  organizational context, and a high degree of
  communication is required among customers, managers,
  software engineers, hardware engineers and other
  technical workers.




                                                      19
Difference of s/w eng. with
traditional engineering….




                              20
Difference of s/w eng. with traditional
engineering

• Software is intangible. It has no mass, no volume, no color, no
  odor--- no physical properties. Source code is merely a static
  image of computer program, and while the effects produced by a
  program are often observable, the program itself not.
• Software doesn’t degrade with time as hardware does. Software
  failures are caused by design and implementation error, not by
  degradation over time
• There is always an obscurity in the interface between software
  modules. It is difficult to design a software system so that all the
  control and interfaces among modules are explicit, and so that the
  modules do not interact to produce unexpected side effects when
  they invoked one another.

                                                                    21
…. difference

• In classical engineering disciplines, the engineer is
  equipped with tools and the mathematical maturity to
  specify the properties of the product separately from
  those of design. The typical software engineering relies
  much more on experience and judgment rather than
  mathematical formula. While experience and judgment
  are necessary, formal analysis are also essential in the
  practice of engineering.


                                                         22
What is the role of software
engineer ….




                               23
The role of software engineer
The evolution of software engineering field has defined the role
  the software engineer. A software engineer should have the
  following qualities:
• Should be a good programmer, be well-versed in data
  structures and algorithms, and be fluent in one or more
  programming languages.
• Should be familiar with several design approaches, be able to
  translate vague requirements and desires into precise
  specifications and be able to converse with the use of a
  system in terms of applications.
• Needs the ability to move among several levels of abstraction
  at different stages of the project, from specific application
  procedures and requirements, to abstraction for software
  systems, to a specific design for system and finally to the
  detailed coding level.                                           24
What are the characteristics of
software engineer




                                  25
The characteristics of software engineer


• Should be able to build and use a model of the
  application to guide choices of the many trade-offs that
  he or she will face. The model is used to answer
  questions about both the behavior of the system and its
  performance.

• Needs communication skills and interpersonal skills. He
  also needs the ability to schedule work both of his own
  and that of others.

                                                         26
What is well engineered software?




                                    27
What is well engineered software?
If the software system does what the user wants, and
   can be made to continue to do what the user wants,
   it is well engineered .
• Any well engineered software system should have
   the following attributes:
• Be easy to maintain
• Be reliable
• Be efficient
• Provides an appropriate user interface

The development of software must make trade-offs
  between these attributes.                             28
Distribution of software effort ?




                                    29
Distribution of software effort
The typical life-span for a typical software product is 1 to 3 years in
  development and 5 to 15 years in use. The distribution of effort between
  development and maintenance has been variously reported depending on
  the type of software as 40/60, 30/70 and 10/90.
Maintenance:
• Corrective: Even with the best quality of software, it is likely that customer
  will uncover defect in software. Corrective maintenance changes the
  software to correct the defects.

•   Adaptive: Over time, the original environment (CPU, OS, business rules,
    external product character etc.) for which the software was developed may
    change. Adaptive maintenance results in modification to the software to
    accommodate the change to its environment.

•   Perfective: As the software is used, the customer / user will recognize
    additional function that will provide benefit. Perfective maintenance
    extends the software beyond its original functional requirements.


                                                                                   30
Types of software product




                            31
The software product

The objective of software engineering is to produce software
     products. Computer software is the product that software
     engineers design and built. software products are software
     systems delivered to a customer with the documentation which
     describes how to install and use the system.
Software products fall into two broad classes:
•    Generic products: These are stand alone systems which are
     produced by a software development organizations/firms and
     sold on the open market to any customer who is able to buy
     them.
•    Customized products: These are systems which are
     commissioned by a particular customer. The software is
     developed specially for that customer by some developer.

                                                               32
…. Software products

• Until the 1980’s, the vast majority of software systems which were
  sold that were customized and specially designed systems which
  run on large computers. They are expensive because all the
  development cost had to be met by a single client.

• After the development of PCs, this situation has completely
  changed. The PC market is totally dominated by software products
  produces by companies such as Microsoft. These account for the
  vast majority of software sales. These are usually relatively cheap
  because their development cost is spread across hundred or
  thousands of different customers.


                                                                   33
Difference between generic and
customized software




                                 34
Difference between generic and customized software


 • The generic software product specifications are
   produced internally by the marketing department of the
   product company. They reflect what they think will sell.
   They are usually flexible and non-prescriptive.

 • For customized systems are often the basis for the
   contract between customer and developer. They are
   usually defined in detail and changes have to be
   negotiated and carefully costed.


                                                              35
Software product attributes




                              36
Software product attributes
The attributes of a software product are the
  characteristics displayed by the product, once it is
  installed and put in use. They are not the services
  provided by the product. Rather, they are
  concerned with the products dynamic behavior and
  the use made of the product. Examples of these
  attributes are therefore, efficiency, reliability,
  maintainability, robustness, portability and so on.
  The relative importance of these characteristics
  obviously varies from system to system.



                                                         37
… product attributes
   Product                                  Description
characteristics
Maintainability   It should be possible to evolve software to meet the changing
                  needs of the customer.

Dependability     Software dependability includes a range of characteristics
                  including reliability, security and safety. Dependable software
                  should not cause physical or economic damage in the event of
                  system failure.

Efficiency        Software should not make wasteful use of system resources
                  such as memory and processor cycle

Usability         Software should have an appropriate user interface and
                  documentation

                                                                                  38
..product attributes

Optimizing the above attribute is difficult as some are
 exclusive. For example, providing a better user
 interface may reduce system efficiency. The
 relationship between cost and improvement in each of
 the attribute is not linear one. Small improvement in
 any of these attributes may be devoted to optimizing
 particular attribute.



                                                          39
Importance of the course

• For the development of Successful software
  – Correct identification of Requirement and Estimation is
    important.




                                                              40
Unit 1: Introduction to Software
Engineering [ 2 Hours]

• Role of Software Engineering, Software Evolution,
  Legacy system structures, Legacy system design,
  Legacy System Assessment, Software Development
  Life Cycle.




                                                  41
Unit 2: Software Process Models
[6 Hours]

• Software process models, Software Specification,
  Software design and implementation, Software
  validation, Automated process support, Prescriptive
  Models, The Waterfall Model, Incremental Process
  Models, Evolutionary Process Models, Specialized
  process models, Extreme Programming, Agile
  Methodology, Scrum, The Unified Process.



                                                    42
Unit 3: Project Management and
Requirement Engineering [ 5 Hours]

• Project Planning and Scheduling, Risk Management,
  Functional and Non Functional Requirements, Users
  Requirement, System Requirements, SRS Document
  Generation, Feasibility Studies, Types of Feasibilities,
  Requirement Analysis, Requirement Validation,
  Requirement Management, Software Measurement
  and Matrices.



                                                             43
Unit 4: System Modeling and
Prototyping. [5 Hours]

• Context models, Behavioral models, Data models,
  Object models, CASE Workbenches, Prototyping in
  the Software Process, Rapid Prototyping Techniques,
  Interface Specification, Behavioral Specification




                                                    44
Unit 5: Design Engineering.
[ 6 Hours]


• Architectural Design, System Structuring, Control
  Models, Modular Decomposition, Domain-Specific
  Architectures, Object Oriented Design Process, Design
  with    Reuse,    Component-Based       Development,
  Application Families, Design Patterns, User interface
  Design Principles, User interaction, Information
  presentation.


                                                      45
Unit 6: Verification and validation.
[6 Hours]


• Verification and Validation Planning, Software
  Inspections, Clean room Software Development,
  Software Testing, Black Box Testing, White Box
  Testing, Integration Testing, Object-Oriented Testing,
  Writing test cases, Testing tools, Configuration
  Management and Version control



                                                       46
Recommended Books


Text Book
• Software Engineering, Ian Sommerville
• Software Engineering, A Practitioner’s Approach,
  Roger S. Pressman

Reference Books
• An Integrated Approach to Software Engineering –
  Pankaj Jalota
• Journals and Papers
                                                     47
FAQs about software engineering

• What is software?
• What is software engineering?
• What is the difference between software engineering
  and computer science?
• What is the difference between software engineering
  and system engineering?
• What is a software process?
• What is a software process model?

                                                        48
FAQs about software engineering

• What are the costs of software engineering?
• What are software engineering methods?
• What is CASE (Computer-Aided Software
  Engineering)
• What are the attributes of good software?
• What are the key challenges facing software
  engineering?


                                                49
What is software?




                    50
What is software?

• Computer programs and associated documentation such as
  requirements, design models and user manuals.
• Software products may be developed for a particular customer or
  may be developed for a general market.
• Software products may be
   – Generic - developed to be sold to a range of different customers e.g. PC
     software such as Excel or Word.
   – Custom - developed for a single customer according to their specification.
• New software can be created by developing new programs,
  configuring generic software systems or reusing existing software.



                                                                                  51
What is software engineering?




                                52
What is software engineering?

• Software engineering is an engineering discipline that
  is concerned with all aspects of software production.
• Software engineers should adopt a systematic and
  organised approach to their work and use appropriate
  tools and techniques depending on the problem to be
  solved, the development constraints and the resources
  available.



                                                       53
Software engineering

• The economies of ALL developed nations are
  dependent on software.
• More and more systems are software controlled
• Software engineering is concerned with theories,
  methods and tools for professional software
  development.




                                                     54
What are the main ingredients of
Software Engineering.




                                   55
What are the main ingredients of
Software Engineering

•   Principle
•   Methods and Techniques
•   Methodology
•   Tools

• How above are correlated…



                                   56
• Relationship Between Principal, Methods and
  Techniques, Methodology and Tools




                                                57
What is the difference between software
engineering and computer science?




                                          58
What is the difference between software
engineering and computer science?

• Computer science is concerned with theory and
  fundamentals; software engineering is concerned with
  the practicalities of developing and delivering useful
  software.




                                                           59
What is the difference between software
engineering and system engineering?




                                          60
What is the difference between software
engineering and system engineering?

System engineering is concerned with all aspects of
 computer-based systems development including
 hardware, software and process engineering. Software
 engineering is part of this process concerned with
 developing the software infrastructure, control,
 applications and databases in the system.
System engineers are involved in system
 specification, architectural design, integration and
 deployment.


                                                    61
What is a software process?




                              62
What is a software process?

A set of activities whose goal is the development or
 evolution of software.
Generic activities in all software processes are:
 ◦ Specification - what the system should do and its
   development constraints
 ◦ Development - production of the software system
 ◦ Validation - checking that the software is what the customer
   wants
 ◦ Evolution - changing the software in response to changing
   demands.

                                                                  63
What is a software process model?




                                    64
What is a software process model?

• A simplified representation of a software process, presented from
  a specific perspective.
• Examples of process perspectives are
   – Workflow perspective - sequence of activities;
   – Data-flow perspective - information flow;
   – Role/action perspective - who does what.
• Generic process models
   – Waterfall;
   – Iterative development;
   – Component-based software engineering.


                                                                      65
How we Determine Software costs




                                  66
Software costs

• Software costs often dominate computer system costs.
  The costs of software on a PC are often greater than
  the hardware cost.
• Software costs more to maintain than it does to
  develop. For systems with a long life, maintenance
  costs may be several times development costs.
• Software engineering is concerned with cost-effective
  software development.

                                                      67
What are the costs of software
engineering?

Roughly 60% of costs are development costs, 40%
 are testing costs. For custom software, evolution costs
 often exceed development costs.
Costs vary depending on the type of system being
 developed and the requirements of system attributes
 such as performance and system reliability.
Distribution of costs depends on the development
 model that is used.

                                                       68
What are software engineering
methods?

• Structured approaches to software development which include
  system models, notations, rules, design advice and process
  guidance.
• Model descriptions
   – Descriptions of graphical models which should be produced;
• Rules
   – Constraints applied to system models;
• Recommendations
   – Advice on good design practice;
• Process guidance
   – What activities to follow.


                                                                  69
What is CASE (Computer-Aided
Software Engineering)




                               70
What is CASE (Computer-Aided
Software Engineering)

• Software systems that are intended to provide automated support
  for software process activities.
• Upper-CASE
   – Tools to support the early process activities of requirements and design;
• Lower-CASE
   – Tools to support later activities such as programming, debugging and
     testing.




                                                                                 71
What are the attributes of good
software?




                                  72
What are the attributes of good
software?

• The software should deliver the required functionality and
  performance to the user and should be maintainable, dependable
  and acceptable.
• Maintainability
   – Software must evolve to meet changing needs;
• Dependability
   – Software must be trustworthy;
• Efficiency
   – Software should not make wasteful use of system resources;
• Acceptability
   – Software must accepted by the users for which it was designed. This means
     it must be understandable, usable and compatible with other systems.

                                                                             73
What are the key challenges facing
software engineering?




                                     74
What are the key challenges facing
software engineering?

• Heterogeneity, delivery and trust.
• Heterogeneity
   – Developing techniques for building software that can cope with
     heterogeneous platforms and execution environments;
• Delivery
   – Developing techniques that lead to faster delivery of software;
• Trust
   – Developing techniques that demonstrate that software can be trusted by its
     users.




                                                                                  75
Phases of Software Engineering




                                 76
Phases of Software Engineering

1.   System identification
2.   System modelling
3.   System integration
4.   System installation
5.   System growth
6.   System decommissioning



                                 77
What is a system?

 • A purposeful collection of inter-related components
   working together to achieve some common objective.
 • A system may include software, mechanical, electrical and
   electronic hardware and be operated by people.
 • System components are dependent on other
   system components
 • The properties and behaviour of system components are
   inextricably inter-mingled




                                                               78
System categories

• Technical computer-based systems
  – Systems that include hardware and software but where the
    operators and operational processes are not normally
    considered to be part of the system. The system is not self-
    aware.
• Socio-technical systems
  – Systems that include technical systems but also operational
    processes and people who use and interact with the
    technical system. Socio-technical systems are governed by
    organisational policies and rules.


                                                                   79
Systems engineering

• Specifying, designing, implementing, validating,
  deploying and maintaining socio-technical systems.
• Concerned with the services provided by the system,
  constraints on its construction and operation and the
  ways in which it is used.




                                                          80
System modelling

• An architectural model presents an abstract view of the
  sub-systems making up a system
• May include major information flows between sub-
  systems
• Usually presented as a block diagram
• May identify different types of functional component in
  the model


                                                        81
System integration

The process of putting hardware, software and
 people together to make a system.
Should be tackled incrementally so that sub-systems
 are integrated one at a time.
Interface problems between sub-systems are usually
 found at this stage.
May be problems with uncoordinated deliveries
 of system components.

                                                       82
System installation

• After completion, the system has to be installed in the
  customer’s environment
  – Environmental assumptions may be incorrect;
  – May be human resistance to the introduction of
    a new system;
  – System may have to coexist with alternative
    systems for some time;
  – May be physical installation problems (e.g.
    cabling problems);
  – Operator training has to be identified.

                                                            83
System growth

• Large systems have a long lifetime. They must evolve to meet
  changing requirements.
• Evolution is inherently costly
   –   Changes must be analysed from a technical and business perspective;
   –   Sub-systems interact so unanticipated problems can arise;
   –   There is rarely a rationale for original design decisions;
   –   System structure is corrupted as changes are made to it.




                                                                             84
System decommissioning

• Taking the system out of service after its useful
  lifetime.
• May require removal of materials (e.g. dangerous
  chemicals) which pollute the environment
  – Should be planned for in the system design by
    encapsulation.
• May require data to be restructured and converted to
  be used in some other system.


                                                         85
A Software Process is

A structured set of activities
 required to develop a software
 system




                                  86
Ad hoc Software Development

• Developing software without planning for each phase,
  and without specifying tasks, deliverables, or time
  constraints.
• Relies entirely on the skills and experience of the
  individual staff for performing the work.
• The software process is constantly changed or
  modified as the work progresses.



                                                     87
Software Process Model

A Software process Model which is
“an abstract representation of a process. It presents a
   description of a process from some particular
   perspective.”
It provides guidelines to organize how software process
   activities should be performed and in what order.




                                                          88
SW Process Models
•   Waterfall model
•   Evolutionary models
•   Component-based development model
•   Iterative Model




                                        89
The Waterfall Model


•   Oldest model, it’s been around since 1970.
•   Called “Linear Sequential Model”.
•   Most widely used model for SW engineering
•   Documentation is produced at each stage.




                                                 90
Phases

1.   Requirements analysis and definition
2.   System and software design
3.   Implementation and unit testing
4.   Integration and system testing
5.   Operation and maintenance




                                            91
Waterfall model diagram




                          92
Disadvantages

• Inflexible partitioning of the project into distinct stages
  makes it difficult to respond to changing customer
  requirements.
• Only appropriate when the requirements are well-
  understood and changes will be fairly limited during
  the design process.
• The waterfall model is mostly used for large systems
  engineering projects.

                                                                93
Evolutionary Models




                      94
The Exploratory Model



 Objective is to work with customers and evolve a
  final system from an initial outline specification.
 Should start with well-understood requirements
  and add new features as proposed by the
  customer.



                                                    95
The Exploratory Model


                         Concurr ent
                          activities


                                             Initial
                        Specification       version



            Outline                     Intermedia te
          description   Development        versions



                                             Final
                         Valida tion        version




                                                        96
The Exploratory Model

• Problems
  – Lack of process visibility;
  – Systems are often poorly structured;
• Applicability
  – For small or medium-size interactive systems;
  – For parts of large systems (e.g. the user interface);
  – For short-lifetime systems.



                                                            97
The Prototyping Model

When a customer defines a set of general objectives
 for a software but does not identify detailed input,
 processing, or output requirement.
It consists of the iterating phases:
 1.   Requirements gathering
 2.   Design and build SW prototype
 3.   Evaluate prototype with customer
 4.   Refine requirements



                                                        98
The Prototyping Model




                        99
The Prototyping Model

• Advantages
  – Users get a feel for the actual system
  – Developers get to build something immediately
  – Specifications can be developed incrementally
• Disadvantages
  – The developer may make implementation compromises in
    order to get a prototype working quickly.
  – The process in not visible (few documents that reflect every
    version of the system)
  – Systems poorly structured

                                                                   100
Component Based Software
Engineering (CBSE)

• Based on systematic reuse where systems are
  integrated from existing components.
• Process stages
  –   Component analysis;
  –   Requirements modification;
  –   System design with reuse;
  –   Development and integration.
• This approach is becoming increasingly used as
  component standards have emerged.


                                                   101
Component Based Software
Engineering (CBSE)


    Requirements    Component     Requirements             System design
    specification     analy sis   modification              with reuse




                                                  Development               Sy stem
                                                 and integ ration          validation




                                                                               102
Component Based Software
Engineering (CBSE)

• Advantages:
  – Reduce amount of software to be developed
  – Reduce costs and risks
  – Faster delivery
• Disadvantages:
  – Requirements compromises, system does not meet real
    needs of users
  – Limited features


                                                          103
Iterative Models




                   104
The Incremental Model

Rather than deliver the system as a single delivery, the
 development and delivery is broken down into
 increments with each increment delivering part of the
 required functionality.
User requirements are prioritised and the highest priority
 requirements are included in early increments.
Once the development of an increment is started, the
 requirements are frozen though requirements for later
 increments can continue to evolve.


                                                             105
The Incremental Model



     Define outline   Assign requirements             Design sy stem
     requirements        to increments                 architectur e




    Develop sy stem       Valida te                  Integ rate        Validate
      increment          increment                  increment          sy stem
                                                                                   Final
                                                                                  sy stem
                               Sy stem incomplete




                                                                                       106
The Incremental Model

Advantages:
• Customer value can be delivered with each increment so
  system functionality is available earlier.
• Early increments act as a prototype to help elicit
  requirements for later increments.
• Lower risk of overall project failure.
• The highest priority system services tend to receive the
  most testing.

                                                        107
The Incremental Model

Disadvantages:
• Increments should be relatively small (20,000 lines of
  code)
• Can be difficult to map the customer’s requirements
  onto increments of the right size
• Hard to identify common functions




                                                           108
The Spiral Model

• Defined by Barry Boehm in his 1988 article A Spiral
  Model of Software Development and Enhancement.
• Process is represented as a spiral rather than as a
  sequence of activities with backtracking.
• Each loop in the spiral represents a phase in the
  process.
• Suitable for large, expensive and complicated projects



                                                           109
The Spiral Model

      Deter mine objecti ves,
                                                                                           Evalua te alterna tives,
         alterna tives and
                                                                                           identify, resolv e risks
            constr aints                                                     Risk
                                                                           anal ysis

                                                                     Risk
                                                                   anal ysis

                                                          Risk
                                                                                                             Oper a-
                                                        anal ysis
                                                                                       Pr ototype 3          tional
                                                                    Prototype 2                              protoype
                                                       Risk
                                          REVIEW     anal ysis Proto-
                                                               type 1
                                Requir ements plan                             Simula tions , models , benchmar ks
                                  Life-cy cle plan   Concept of
                                                     Oper a tion         S/W
                                                                    requir ements          Product
                                                                                           design        Detailed
                                                     Requir ement                                         design
                                    De velopment
                                         plan         valida tion                                     Code
                                                                                           Unit test
                                     Integ ra tion     Design
                                                        V&V                       Integ ra tion
                                    and test plan
          Plan ne xt phase                                                            test
                                                                Acceptance
                                                     Service        test                   De velop , verify
                                                                                           ne xt-le vel pr oduct




                                                                                                                        110
The Spiral Model

• Objective setting
   – Specific objectives for the phase are identified.
• Risk assessment and reduction
   – Risks are assessed and activities put in place to reduce the key risks.
• Development and validation
   – A development model for the system is chosen which can be any of
     the generic models.
• Planning
   – The project is reviewed and the next phase of the spiral is planned.




                                                                            111
The Spiral Model

• Risk driven process model
  – Different risk patterns can lead to choosing different process
    models
• What is a risk?
  – Situations or possible events that may cause a project to fail to
    meet its goal.
  – Example risks:
     • Experienced staff leave the project
     • Hardware which is essential for the system will not be delivered on
       schedule
  – (more about risks in Chapter 3)
                                                                             112
The Spiral Model

Advantages:
• Risks are explicitly assessed and resolved throughout
  the process.
• Software engineers can start working on the project
  earlier rather than wading through a lengthy early
  design process.




                                                      113
The Spiral Model

Disadvantages:
• Requires highly skilled people in risk analysis and
  planning
• Requires more time, and is more expensive
• Estimates of budget and time are harder to judge at
  the beginning of the project since the requirements
  evolve through the process


                                                        114

Se lect1 btech

  • 1.
  • 2.
    Software Engineering • Totallectures: 40 • Credit hours: 3 hrs • Mentors: – Pre Mid Sem: Dr. Sonali Agarwal – Post Mid Sem: Prof. O.P. Vyas 2
  • 3.
    Course Objective • Thiscourse gives a comprehensive analysis of software engineering techniques and the applications. Topic includes Software Development Life Cycle, Software processes management, requirement engineering, analysis and design, developing and testing of software integration, verification, validation, pattern based reuse, reliability and project management principles, techniques. 3
  • 4.
    What is SoftwareCrisis…. 4
  • 5.
    Software Crisis  Itwas in late 1960’s.  Many software projects failed.  Many software projects late, over budget, providing unreliable software that is expensive to maintain.  Many software projects produced software which did not satisfy the requirements of the customer.  Complexities of software projects increased as hardware capability increased. 5
  • 6.
    Software Crisis • Largersoftware system is more difficult and expensive to maintain. • Demand of new software increased faster than ability to generate new software. • All the above attributes of what was called a ‘Software Crisis’. • So the term ‘Software Engineering’ first introduced at a conference in late 1960’s to discuss the software crisis. 6
  • 7.
  • 8.
    Why software engineering? Oncethe need for software engineering was identified and software engineering recognized as a discipline-- • The late 1970’s saw the widespread evolution of software engineering principles. • The 1980’s saw the automation of software engineering and growth of CASE (Computer Aided Software Engineering). 8
  • 9.
    Why software engineering •The 1990’s have seen increased emphasis on the ‘management’ aspects of projects and the use of standard quality and ‘process’ models like ISO 9001 and the Software Engineering Institute’s Software Capability Maturity Model (CMM). • These models help organizations put their software development and management processes in place 9
  • 10.
    What is softwareEngineering? 10
  • 11.
    What is softwareEngineering? • In1969 Fritz Bauer defined software eng. as, ‘the establishment and use of sound engineering principles in order to obtain, economically, software that is reliable and works efficiently on real machines’. • According to Boehm, software engineering involves, ‘the practical application of scientific knowledge to the design and construction of computer programs and the associated documentation required developing, operating and maintaining them’ 11
  • 12.
    What is softwareEngineering? • IEEE, in its standard 610.12-1990, defines software engineering as: (i) The application of a systematic, disciplined, quantifiable approach to the development, operation and maintenance of software; that is, the application of engineering to software. (ii) The study of approaches as in (i). • By combining all the above definition we can define software engineering as, ‘Software engineering is the technological and managerial discipline concerned with systematic production and maintenance of software products that are developed and modified on time and within cost estimates.’ 12
  • 13.
    What are theGoals of software engineering…. 13
  • 14.
    Goal of softwareengineering The primary goals of software engineering are: • To improve the quality of the software products. • To increase the productivity & • To give job satisfaction to the software engineers. 14
  • 15.
    Foundation of Softwareengineering Software engineering is a technological discipline distinct from, but based on the foundation of the following disciplines: • Computer Science • Management Science • Economics • System Engineering & • Communication Skills 15
  • 16.
    The relationship ofsoftware engineering with other disciplines 16
  • 17.
    The relationship ofsoftware engineering with other disciplines • Computer Science gives the scientific foundation to the software as electrical engineering relies on physics. • Management Science provides the foundation for software project management. Since software engineering is labor intensive activity, it requires both technical and managerial control. • Economics provides the foundation for resource estimation and cost control. Since, computing system must be developed and maintained on time and within cost estimates; thus economics plays an important role. 17
  • 18.
    The relationship ofsoftware engineering with other disciplines • System Engineering is the field concerned with studying complex systems. Software is often a component of a much larger system. For example, the software in a factory monitoring system or the flight software on an airplane; is just the component of more complex system. System engineering techniques can be applied to study of such systems 18
  • 19.
    The relationship ofsoftware engineering with other disciplines • Good oral, written and interpersonal communication skills are crucial for the software engineers, because software engineering activities occur within an organizational context, and a high degree of communication is required among customers, managers, software engineers, hardware engineers and other technical workers. 19
  • 20.
    Difference of s/weng. with traditional engineering…. 20
  • 21.
    Difference of s/weng. with traditional engineering • Software is intangible. It has no mass, no volume, no color, no odor--- no physical properties. Source code is merely a static image of computer program, and while the effects produced by a program are often observable, the program itself not. • Software doesn’t degrade with time as hardware does. Software failures are caused by design and implementation error, not by degradation over time • There is always an obscurity in the interface between software modules. It is difficult to design a software system so that all the control and interfaces among modules are explicit, and so that the modules do not interact to produce unexpected side effects when they invoked one another. 21
  • 22.
    …. difference • Inclassical engineering disciplines, the engineer is equipped with tools and the mathematical maturity to specify the properties of the product separately from those of design. The typical software engineering relies much more on experience and judgment rather than mathematical formula. While experience and judgment are necessary, formal analysis are also essential in the practice of engineering. 22
  • 23.
    What is therole of software engineer …. 23
  • 24.
    The role ofsoftware engineer The evolution of software engineering field has defined the role the software engineer. A software engineer should have the following qualities: • Should be a good programmer, be well-versed in data structures and algorithms, and be fluent in one or more programming languages. • Should be familiar with several design approaches, be able to translate vague requirements and desires into precise specifications and be able to converse with the use of a system in terms of applications. • Needs the ability to move among several levels of abstraction at different stages of the project, from specific application procedures and requirements, to abstraction for software systems, to a specific design for system and finally to the detailed coding level. 24
  • 25.
    What are thecharacteristics of software engineer 25
  • 26.
    The characteristics ofsoftware engineer • Should be able to build and use a model of the application to guide choices of the many trade-offs that he or she will face. The model is used to answer questions about both the behavior of the system and its performance. • Needs communication skills and interpersonal skills. He also needs the ability to schedule work both of his own and that of others. 26
  • 27.
    What is wellengineered software? 27
  • 28.
    What is wellengineered software? If the software system does what the user wants, and can be made to continue to do what the user wants, it is well engineered . • Any well engineered software system should have the following attributes: • Be easy to maintain • Be reliable • Be efficient • Provides an appropriate user interface The development of software must make trade-offs between these attributes. 28
  • 29.
  • 30.
    Distribution of softwareeffort The typical life-span for a typical software product is 1 to 3 years in development and 5 to 15 years in use. The distribution of effort between development and maintenance has been variously reported depending on the type of software as 40/60, 30/70 and 10/90. Maintenance: • Corrective: Even with the best quality of software, it is likely that customer will uncover defect in software. Corrective maintenance changes the software to correct the defects. • Adaptive: Over time, the original environment (CPU, OS, business rules, external product character etc.) for which the software was developed may change. Adaptive maintenance results in modification to the software to accommodate the change to its environment. • Perfective: As the software is used, the customer / user will recognize additional function that will provide benefit. Perfective maintenance extends the software beyond its original functional requirements. 30
  • 31.
  • 32.
    The software product Theobjective of software engineering is to produce software products. Computer software is the product that software engineers design and built. software products are software systems delivered to a customer with the documentation which describes how to install and use the system. Software products fall into two broad classes: • Generic products: These are stand alone systems which are produced by a software development organizations/firms and sold on the open market to any customer who is able to buy them. • Customized products: These are systems which are commissioned by a particular customer. The software is developed specially for that customer by some developer. 32
  • 33.
    …. Software products •Until the 1980’s, the vast majority of software systems which were sold that were customized and specially designed systems which run on large computers. They are expensive because all the development cost had to be met by a single client. • After the development of PCs, this situation has completely changed. The PC market is totally dominated by software products produces by companies such as Microsoft. These account for the vast majority of software sales. These are usually relatively cheap because their development cost is spread across hundred or thousands of different customers. 33
  • 34.
    Difference between genericand customized software 34
  • 35.
    Difference between genericand customized software • The generic software product specifications are produced internally by the marketing department of the product company. They reflect what they think will sell. They are usually flexible and non-prescriptive. • For customized systems are often the basis for the contract between customer and developer. They are usually defined in detail and changes have to be negotiated and carefully costed. 35
  • 36.
  • 37.
    Software product attributes Theattributes of a software product are the characteristics displayed by the product, once it is installed and put in use. They are not the services provided by the product. Rather, they are concerned with the products dynamic behavior and the use made of the product. Examples of these attributes are therefore, efficiency, reliability, maintainability, robustness, portability and so on. The relative importance of these characteristics obviously varies from system to system. 37
  • 38.
    … product attributes Product Description characteristics Maintainability It should be possible to evolve software to meet the changing needs of the customer. Dependability Software dependability includes a range of characteristics including reliability, security and safety. Dependable software should not cause physical or economic damage in the event of system failure. Efficiency Software should not make wasteful use of system resources such as memory and processor cycle Usability Software should have an appropriate user interface and documentation 38
  • 39.
    ..product attributes Optimizing theabove attribute is difficult as some are exclusive. For example, providing a better user interface may reduce system efficiency. The relationship between cost and improvement in each of the attribute is not linear one. Small improvement in any of these attributes may be devoted to optimizing particular attribute. 39
  • 40.
    Importance of thecourse • For the development of Successful software – Correct identification of Requirement and Estimation is important. 40
  • 41.
    Unit 1: Introductionto Software Engineering [ 2 Hours] • Role of Software Engineering, Software Evolution, Legacy system structures, Legacy system design, Legacy System Assessment, Software Development Life Cycle. 41
  • 42.
    Unit 2: SoftwareProcess Models [6 Hours] • Software process models, Software Specification, Software design and implementation, Software validation, Automated process support, Prescriptive Models, The Waterfall Model, Incremental Process Models, Evolutionary Process Models, Specialized process models, Extreme Programming, Agile Methodology, Scrum, The Unified Process. 42
  • 43.
    Unit 3: ProjectManagement and Requirement Engineering [ 5 Hours] • Project Planning and Scheduling, Risk Management, Functional and Non Functional Requirements, Users Requirement, System Requirements, SRS Document Generation, Feasibility Studies, Types of Feasibilities, Requirement Analysis, Requirement Validation, Requirement Management, Software Measurement and Matrices. 43
  • 44.
    Unit 4: SystemModeling and Prototyping. [5 Hours] • Context models, Behavioral models, Data models, Object models, CASE Workbenches, Prototyping in the Software Process, Rapid Prototyping Techniques, Interface Specification, Behavioral Specification 44
  • 45.
    Unit 5: DesignEngineering. [ 6 Hours] • Architectural Design, System Structuring, Control Models, Modular Decomposition, Domain-Specific Architectures, Object Oriented Design Process, Design with Reuse, Component-Based Development, Application Families, Design Patterns, User interface Design Principles, User interaction, Information presentation. 45
  • 46.
    Unit 6: Verificationand validation. [6 Hours] • Verification and Validation Planning, Software Inspections, Clean room Software Development, Software Testing, Black Box Testing, White Box Testing, Integration Testing, Object-Oriented Testing, Writing test cases, Testing tools, Configuration Management and Version control 46
  • 47.
    Recommended Books Text Book •Software Engineering, Ian Sommerville • Software Engineering, A Practitioner’s Approach, Roger S. Pressman Reference Books • An Integrated Approach to Software Engineering – Pankaj Jalota • Journals and Papers 47
  • 48.
    FAQs about softwareengineering • What is software? • What is software engineering? • What is the difference between software engineering and computer science? • What is the difference between software engineering and system engineering? • What is a software process? • What is a software process model? 48
  • 49.
    FAQs about softwareengineering • What are the costs of software engineering? • What are software engineering methods? • What is CASE (Computer-Aided Software Engineering) • What are the attributes of good software? • What are the key challenges facing software engineering? 49
  • 50.
  • 51.
    What is software? •Computer programs and associated documentation such as requirements, design models and user manuals. • Software products may be developed for a particular customer or may be developed for a general market. • Software products may be – Generic - developed to be sold to a range of different customers e.g. PC software such as Excel or Word. – Custom - developed for a single customer according to their specification. • New software can be created by developing new programs, configuring generic software systems or reusing existing software. 51
  • 52.
    What is softwareengineering? 52
  • 53.
    What is softwareengineering? • Software engineering is an engineering discipline that is concerned with all aspects of software production. • Software engineers should adopt a systematic and organised approach to their work and use appropriate tools and techniques depending on the problem to be solved, the development constraints and the resources available. 53
  • 54.
    Software engineering • Theeconomies of ALL developed nations are dependent on software. • More and more systems are software controlled • Software engineering is concerned with theories, methods and tools for professional software development. 54
  • 55.
    What are themain ingredients of Software Engineering. 55
  • 56.
    What are themain ingredients of Software Engineering • Principle • Methods and Techniques • Methodology • Tools • How above are correlated… 56
  • 57.
    • Relationship BetweenPrincipal, Methods and Techniques, Methodology and Tools 57
  • 58.
    What is thedifference between software engineering and computer science? 58
  • 59.
    What is thedifference between software engineering and computer science? • Computer science is concerned with theory and fundamentals; software engineering is concerned with the practicalities of developing and delivering useful software. 59
  • 60.
    What is thedifference between software engineering and system engineering? 60
  • 61.
    What is thedifference between software engineering and system engineering? System engineering is concerned with all aspects of computer-based systems development including hardware, software and process engineering. Software engineering is part of this process concerned with developing the software infrastructure, control, applications and databases in the system. System engineers are involved in system specification, architectural design, integration and deployment. 61
  • 62.
    What is asoftware process? 62
  • 63.
    What is asoftware process? A set of activities whose goal is the development or evolution of software. Generic activities in all software processes are: ◦ Specification - what the system should do and its development constraints ◦ Development - production of the software system ◦ Validation - checking that the software is what the customer wants ◦ Evolution - changing the software in response to changing demands. 63
  • 64.
    What is asoftware process model? 64
  • 65.
    What is asoftware process model? • A simplified representation of a software process, presented from a specific perspective. • Examples of process perspectives are – Workflow perspective - sequence of activities; – Data-flow perspective - information flow; – Role/action perspective - who does what. • Generic process models – Waterfall; – Iterative development; – Component-based software engineering. 65
  • 66.
    How we DetermineSoftware costs 66
  • 67.
    Software costs • Softwarecosts often dominate computer system costs. The costs of software on a PC are often greater than the hardware cost. • Software costs more to maintain than it does to develop. For systems with a long life, maintenance costs may be several times development costs. • Software engineering is concerned with cost-effective software development. 67
  • 68.
    What are thecosts of software engineering? Roughly 60% of costs are development costs, 40% are testing costs. For custom software, evolution costs often exceed development costs. Costs vary depending on the type of system being developed and the requirements of system attributes such as performance and system reliability. Distribution of costs depends on the development model that is used. 68
  • 69.
    What are softwareengineering methods? • Structured approaches to software development which include system models, notations, rules, design advice and process guidance. • Model descriptions – Descriptions of graphical models which should be produced; • Rules – Constraints applied to system models; • Recommendations – Advice on good design practice; • Process guidance – What activities to follow. 69
  • 70.
    What is CASE(Computer-Aided Software Engineering) 70
  • 71.
    What is CASE(Computer-Aided Software Engineering) • Software systems that are intended to provide automated support for software process activities. • Upper-CASE – Tools to support the early process activities of requirements and design; • Lower-CASE – Tools to support later activities such as programming, debugging and testing. 71
  • 72.
    What are theattributes of good software? 72
  • 73.
    What are theattributes of good software? • The software should deliver the required functionality and performance to the user and should be maintainable, dependable and acceptable. • Maintainability – Software must evolve to meet changing needs; • Dependability – Software must be trustworthy; • Efficiency – Software should not make wasteful use of system resources; • Acceptability – Software must accepted by the users for which it was designed. This means it must be understandable, usable and compatible with other systems. 73
  • 74.
    What are thekey challenges facing software engineering? 74
  • 75.
    What are thekey challenges facing software engineering? • Heterogeneity, delivery and trust. • Heterogeneity – Developing techniques for building software that can cope with heterogeneous platforms and execution environments; • Delivery – Developing techniques that lead to faster delivery of software; • Trust – Developing techniques that demonstrate that software can be trusted by its users. 75
  • 76.
    Phases of SoftwareEngineering 76
  • 77.
    Phases of SoftwareEngineering 1. System identification 2. System modelling 3. System integration 4. System installation 5. System growth 6. System decommissioning 77
  • 78.
    What is asystem? • A purposeful collection of inter-related components working together to achieve some common objective. • A system may include software, mechanical, electrical and electronic hardware and be operated by people. • System components are dependent on other system components • The properties and behaviour of system components are inextricably inter-mingled 78
  • 79.
    System categories • Technicalcomputer-based systems – Systems that include hardware and software but where the operators and operational processes are not normally considered to be part of the system. The system is not self- aware. • Socio-technical systems – Systems that include technical systems but also operational processes and people who use and interact with the technical system. Socio-technical systems are governed by organisational policies and rules. 79
  • 80.
    Systems engineering • Specifying,designing, implementing, validating, deploying and maintaining socio-technical systems. • Concerned with the services provided by the system, constraints on its construction and operation and the ways in which it is used. 80
  • 81.
    System modelling • Anarchitectural model presents an abstract view of the sub-systems making up a system • May include major information flows between sub- systems • Usually presented as a block diagram • May identify different types of functional component in the model 81
  • 82.
    System integration The processof putting hardware, software and people together to make a system. Should be tackled incrementally so that sub-systems are integrated one at a time. Interface problems between sub-systems are usually found at this stage. May be problems with uncoordinated deliveries of system components. 82
  • 83.
    System installation • Aftercompletion, the system has to be installed in the customer’s environment – Environmental assumptions may be incorrect; – May be human resistance to the introduction of a new system; – System may have to coexist with alternative systems for some time; – May be physical installation problems (e.g. cabling problems); – Operator training has to be identified. 83
  • 84.
    System growth • Largesystems have a long lifetime. They must evolve to meet changing requirements. • Evolution is inherently costly – Changes must be analysed from a technical and business perspective; – Sub-systems interact so unanticipated problems can arise; – There is rarely a rationale for original design decisions; – System structure is corrupted as changes are made to it. 84
  • 85.
    System decommissioning • Takingthe system out of service after its useful lifetime. • May require removal of materials (e.g. dangerous chemicals) which pollute the environment – Should be planned for in the system design by encapsulation. • May require data to be restructured and converted to be used in some other system. 85
  • 86.
    A Software Processis A structured set of activities required to develop a software system 86
  • 87.
    Ad hoc SoftwareDevelopment • Developing software without planning for each phase, and without specifying tasks, deliverables, or time constraints. • Relies entirely on the skills and experience of the individual staff for performing the work. • The software process is constantly changed or modified as the work progresses. 87
  • 88.
    Software Process Model ASoftware process Model which is “an abstract representation of a process. It presents a description of a process from some particular perspective.” It provides guidelines to organize how software process activities should be performed and in what order. 88
  • 89.
    SW Process Models • Waterfall model • Evolutionary models • Component-based development model • Iterative Model 89
  • 90.
    The Waterfall Model • Oldest model, it’s been around since 1970. • Called “Linear Sequential Model”. • Most widely used model for SW engineering • Documentation is produced at each stage. 90
  • 91.
    Phases 1. Requirements analysis and definition 2. System and software design 3. Implementation and unit testing 4. Integration and system testing 5. Operation and maintenance 91
  • 92.
  • 93.
    Disadvantages • Inflexible partitioningof the project into distinct stages makes it difficult to respond to changing customer requirements. • Only appropriate when the requirements are well- understood and changes will be fairly limited during the design process. • The waterfall model is mostly used for large systems engineering projects. 93
  • 94.
  • 95.
    The Exploratory Model Objective is to work with customers and evolve a final system from an initial outline specification. Should start with well-understood requirements and add new features as proposed by the customer. 95
  • 96.
    The Exploratory Model Concurr ent activities Initial Specification version Outline Intermedia te description Development versions Final Valida tion version 96
  • 97.
    The Exploratory Model •Problems – Lack of process visibility; – Systems are often poorly structured; • Applicability – For small or medium-size interactive systems; – For parts of large systems (e.g. the user interface); – For short-lifetime systems. 97
  • 98.
    The Prototyping Model Whena customer defines a set of general objectives for a software but does not identify detailed input, processing, or output requirement. It consists of the iterating phases: 1. Requirements gathering 2. Design and build SW prototype 3. Evaluate prototype with customer 4. Refine requirements 98
  • 99.
  • 100.
    The Prototyping Model •Advantages – Users get a feel for the actual system – Developers get to build something immediately – Specifications can be developed incrementally • Disadvantages – The developer may make implementation compromises in order to get a prototype working quickly. – The process in not visible (few documents that reflect every version of the system) – Systems poorly structured 100
  • 101.
    Component Based Software Engineering(CBSE) • Based on systematic reuse where systems are integrated from existing components. • Process stages – Component analysis; – Requirements modification; – System design with reuse; – Development and integration. • This approach is becoming increasingly used as component standards have emerged. 101
  • 102.
    Component Based Software Engineering(CBSE) Requirements Component Requirements System design specification analy sis modification with reuse Development Sy stem and integ ration validation 102
  • 103.
    Component Based Software Engineering(CBSE) • Advantages: – Reduce amount of software to be developed – Reduce costs and risks – Faster delivery • Disadvantages: – Requirements compromises, system does not meet real needs of users – Limited features 103
  • 104.
  • 105.
    The Incremental Model Ratherthan deliver the system as a single delivery, the development and delivery is broken down into increments with each increment delivering part of the required functionality. User requirements are prioritised and the highest priority requirements are included in early increments. Once the development of an increment is started, the requirements are frozen though requirements for later increments can continue to evolve. 105
  • 106.
    The Incremental Model Define outline Assign requirements Design sy stem requirements to increments architectur e Develop sy stem Valida te Integ rate Validate increment increment increment sy stem Final sy stem Sy stem incomplete 106
  • 107.
    The Incremental Model Advantages: •Customer value can be delivered with each increment so system functionality is available earlier. • Early increments act as a prototype to help elicit requirements for later increments. • Lower risk of overall project failure. • The highest priority system services tend to receive the most testing. 107
  • 108.
    The Incremental Model Disadvantages: •Increments should be relatively small (20,000 lines of code) • Can be difficult to map the customer’s requirements onto increments of the right size • Hard to identify common functions 108
  • 109.
    The Spiral Model •Defined by Barry Boehm in his 1988 article A Spiral Model of Software Development and Enhancement. • Process is represented as a spiral rather than as a sequence of activities with backtracking. • Each loop in the spiral represents a phase in the process. • Suitable for large, expensive and complicated projects 109
  • 110.
    The Spiral Model Deter mine objecti ves, Evalua te alterna tives, alterna tives and identify, resolv e risks constr aints Risk anal ysis Risk anal ysis Risk Oper a- anal ysis Pr ototype 3 tional Prototype 2 protoype Risk REVIEW anal ysis Proto- type 1 Requir ements plan Simula tions , models , benchmar ks Life-cy cle plan Concept of Oper a tion S/W requir ements Product design Detailed Requir ement design De velopment plan valida tion Code Unit test Integ ra tion Design V&V Integ ra tion and test plan Plan ne xt phase test Acceptance Service test De velop , verify ne xt-le vel pr oduct 110
  • 111.
    The Spiral Model •Objective setting – Specific objectives for the phase are identified. • Risk assessment and reduction – Risks are assessed and activities put in place to reduce the key risks. • Development and validation – A development model for the system is chosen which can be any of the generic models. • Planning – The project is reviewed and the next phase of the spiral is planned. 111
  • 112.
    The Spiral Model •Risk driven process model – Different risk patterns can lead to choosing different process models • What is a risk? – Situations or possible events that may cause a project to fail to meet its goal. – Example risks: • Experienced staff leave the project • Hardware which is essential for the system will not be delivered on schedule – (more about risks in Chapter 3) 112
  • 113.
    The Spiral Model Advantages: •Risks are explicitly assessed and resolved throughout the process. • Software engineers can start working on the project earlier rather than wading through a lengthy early design process. 113
  • 114.