Presentation on scrum methodology in March 2009 to train the team at Fifth Third to start using this agile methodology. Details have been blurred to protect confidentiality.
An agile methodoloy, will do both iterative and incremental in balance
Time boxing is important, spec will be divided into multiple time boxing
Visualizing activities in Sprint #1
Visualizing activities in Sprint #2
Visualizing activities in Sprint #3 etc
Visualizing final sprint
Product backlog is where you list all of the stories, which can be taken from use cases as well. Defined whether the story can be demo-ed, what is the priority, estimation, how to demo it and other necessary notes
(Available Man Days) * Focus Factor = (Estimated Velocity) Define how to allocate time for the sprint planning. This will be more as a guidelines. Insert break after 1 to 1.5 hours of meeting.
Sprint backlog: story id, brief description, total story points, and individual days for daily sprint call