1 36(3) Register of appointment of Officials and
competent persons
As and when
required
Manager/
Office
2 38(2) Timing Register for below ground
employees
Shift wise Manway Clerk
3 41(3) Register for material requisition As and when
required
Manager/
Office
4 41(8) Fatal/Serious accidents enquiry report As and when
required
S.O.
5 41(1)(b) Manager’s Diary Daily Manager, Asst.
Manager, Under
Manager.
6 41A(3) Safety Officer’s Diary Daily S.O.
7 42A(3) Ventilation Officer’s Diary Daily V.O.
8 43(9) Report of Overman Daily Overman
9 47(b) Attendant’s report of Main mechanical
ventilator
Every shift Fan
attendant/Engin
eer
10 49(2) Mine Survey record As and when
required
Surveyor
11 56(b) Record of explosives(Receipts, Issues &
Stock)
Daily Incharge,
Magazine/S.O.
12 56(d) Record of explosives(Daily issues & returns) Daily -do-
13 63(4) Record of list of plans & other survey
material
As and when
required
Surveyor
14 70(1) Examination of outlets Weekly S.O.
15 89(1)(d) Examination of buffer, draw bar and other
attachment
Fortnight Engineer
16 89(3) List of persons authorised to ride on tub As and when
required
S.O.
17 90(5) Examination of haulage rope Monthly Engineer
18 91(3) Haulage rope record As and when
required
Engineer
19 93(1)(a) Examination of haulage engine Daily Engineer
20 93(1)(d) Examination of track line Weekly S.O.
21 94 Examination of haulage & travelling
roadways
Weekly S.O.
22 100(6)
(1)(F)
Convergence record book Daily S.O.
23 103A(1) Register of contrivances pointed out by
Inspector
As and when
required
Manager/Office
24 105(1) Examination of workings under Reg. 105, if
any
As specified in
the DMS
condition.
S.O.
25 108(6) Code of standing orders on SSR - Manager
26 110 Code of standing orders for withdrawal of
supports
- Manager
Sl.
No.
Reg./
Cir.No.
Name of the Register/Report Periodicity Maintained by
27 113(3) Daily report of mining sirdar Daily S.O.
28 114(3) Avoidance of danger As and when
required
S.O.
29 116(5) Analysis report of general body of air Monthly VO/SO
30 117(5) Permissions to light a fire within 15 mtrs.
from any entrance of the mine
Monthly SO/Engineer
31 117(6) Examination for surface fire that may have
broken out/any indications thereon
Weekly S.O.
32 118(2)
(i)
Permissions to light a fire below ground As and when
required
S.O.
33 118(5) Inspections of un-used workings for signs of
illicit distillation of liquor
Monthly S.O.
34 118A(3)
(a)(i)
Tests for percentage of CO at goaf edge and
return air of every depillaring dist.
Weekly VO/SO
35 118A(3)
(a)(ii)
Analysis report of Air samples drawn from
return air and goaf edge of depillaring dist.
Monthly VO/SO
36 118A(3)
(c)
Idle day inspection of depillaring dist. &
unused workings
Weekly S.O.
37 119(1)
(a)
Examination after fire has broken out As and when
required
VO/SO
38 120(3)
(a)
Examination of fire fighting stations Monthly S.O.
39 120(3)
(c)
Examination of Fire Extinguishers Monthly Engineer
40 122(5) Examination of isolation stoppings Weekly S.O.
41 123(3)
(a)
Record of Air born respirable dust survey Every 6 months V.O.
42 123(6)
(h)
Inspection of dust respirators and other
devices used for prevention and suppression
of dust
Weekly V.O.
43 123A(2) Stone dust and treatment record Daily V.O.
44 123B(8) Dust sampling record(All sections to be
completed within 30 days)
30 days V.O.
45 126(5)
(a)
Examination of protective measure against
inrush of surface water
Every 14 days
in rainy season,
30 days in other
season
S.O.
46 127(6)
(b)
Record of particulars related to drivage
towards water bearing strata or water-logged
area
As and when
required
S.O.
47 130(2)
(v)
Record of air samples and temp. readings 30 days V.O.
48 133(2) Shiftwise report of mechanical ventilator Every shift Engineer
49 133(3) Weekly examination of mechanical
ventilator
Weekly Engineer
50 133(4){a) Record of air measurements Monthly V.O.
51 134(3) Standing orders for main mechanical
ventilator
- V.O.
Sl.
No.
Reg./
Cir.No.
Name of the Register/Report Periodicity Maintained by
52 136(6) Examination of Ventilation devices For every 14
days
V.O.
53 141(2)
Examination of the mine or part reopened
after a discontinuance or being dewatered.
As and when
required
S.O.
54 142(6) Occurrence of Gas
As and when
required
S.O.
55 145 Record of Gas Survey in I degree gassy
mines
Monthly V.O.
56 155(3) Daily examination of Safety lamps on its
being returned after use
Daily Engineer
57 156(2) Record of Safety lamps(Daily issues &
returns)
Daily Engineer
58 162(4)
Record of Explosives(Shiftwise issues &
returns)
Every shift S.O.
59 164A(5)
Examination of vehicle used for transport
of explosives(from Area Stores to Pit
magazine)
Whenever
applicable
S.O.
60 169(2) Overhauling, tests and repairs of
Exploders.
Every 3 months Engineer
61 177(8) Report of misfires
As and when
required
S.O.
62 179(b) Daily report of Shotfirer Every shift S.O.
63 186(5) Examination of Plant & Machinery Weekly Engineer
64 187(9) Examination of Surface fences Weekly S.O.
65 199A Approved Emergency Organisation Plan - S.O.
66
2/1981
59/1967
Record of mock rehearsals
a) In depillaring districts
b) For danger from inundation
c) Standing orders for fire
d) Stoppage of main mechanical ventilator
e) Emergency Organisation Plan
Regularly
Monthly
Quarterly
Quarterly
Quarterly
S.O.
S.O.
S.O.
S.O.
S.O.
67 12/1962
4/1988
Subsidence record As and when
required
Survey Officer
68 9/1963 Local and main fall record -do- -do-
69
Pal
committee
Recomme
ndation
Anchorage Testing record
10% of the
installed bolts
S.O.
70
Sec.
23(1A)
Register of reportable accidents in form “J” Quarterly S.O.
71 Sec. 23(3) Register of minor accidents in form “K” Annually S.O.
72
CGM(S) Cir.
No. CS/44
(b)/92/1197,
dt. 10.12.76
Record of Steel Supports Monthly S.O.
Sl.
No.
Reg./
Cir.No.
Name of the Register/Report Periodicity Maintained by
73
Special Training on SSR for Timberman &
Support Mazdoor
Once in 2 years S.O.
74
3(Gen.)
of 1978
Minor accidents and analysis record
As and when
required
S.O.
75 6/1976
Gas survey in I degree Gassy seams:
a) General body of air
b) Bore holes’ samples
30 days
Quarterly
V.O.
V.O.
76 30/1964
Analysis report of air samples drawn behind
isolation stoppings
Monthly S.O.
77 1/1960
Examination of workings beneath Structure
a) Rivers and Jores, etc.
b) Roads & Railways
C). Dwellings & other structures
Monthly or any
other period as
mentioned in
DMS
permission.
S.O.
78 Record of examination of Transformer oil Every 6 months Engineer
79 E/L record of HT and LT switches Monthly Engineer
80
Examination of physical & electrical
condition of flexible cables
Monthly Engineer
81 Earth electrode resistance record Monthly Engineer
82 E/L testing record of drill panels Monthly Engineer
83
IER
131(5)
Log sheet for elec. Supervisors Daily Engineer
84 Breakdown analysis record
As and when
required
Engineer
85
11/1974
(16)(a)
Shiftwise inspection report of belt conveyor Every shift Engineer
86
11/1974
19(b)
Examination of belt conveyor Daily Engineer
87
11/1974
20(b)
Examination of Electrical installations of belt
conveyor
Weekly Engineer
88 14/1979
Examination of electrical installations in
lamp cabin
Weekly Engineer
89
M.Rules
29R(2)
Workmen’s Inspector report book in form
“U”
Twice in a
week
S.O./Engineer
90
49/1964
21/1966
Record of Pit Safety Committee Monthly S.O.
91
M.Rules
34(h)
Record of white washing for interior walls,
ceilings and partitions of latrines & urinals
Every 4 months S.O.
92
M.Rules
42(3)
Upto-date list of First Aiders
As and when
required
S.O.
93
M.
Rules
44(3)
Upto-date list of all First Aid Stations -do- S.O.
94
M.Rules
49(4)
Register of Compensatory days of Rest in
form “F”
Weekly W.O.
95
M.Rules
51
Termination of Employment in form “B”
As and when
required
W.O.
Sl.
No.
Reg./
Cir.No.
Name of the Register/Report Periodicity Maintained by
96
M.Rules
53(1)
Register of Leave with wages in form “G/H”
As and when
required
W.O.
97
M.Rules
59
Register of Over Time in form “I” -do- Office
98
M.Rules
69(4)
Minutes book of Canteen Committee
meeting
Monthly W.O.
99
M.Rules
73(3)
Diary of Welfare Officer Daily W.O.
100 Record of refresher training
101 Record of change of Job training
INDUCED BLASTING
PUBLIC ADDRESS SYSTEM
ROOF FALL
FORT NIGHT INSPECTION OF MAGAZINE
EXPERIENCE RECORD
DAILY REPORT OF REPORTABLE ACCIDENT
Sl.
No.
Reg./
Cir.No.
Name of the Register/Report Periodicity Maintained by
96
M.Rules
53(1)
Register of Leave with wages in form “G/H”
As and when
required
W.O.
97
M.Rules
59
Register of Over Time in form “I” -do- Office
98
M.Rules
69(4)
Minutes book of Canteen Committee
meeting
Monthly W.O.
99
M.Rules
73(3)
Diary of Welfare Officer Daily W.O.
100 Record of refresher training
101 Record of change of Job training
INDUCED BLASTING
PUBLIC ADDRESS SYSTEM
ROOF FALL
FORT NIGHT INSPECTION OF MAGAZINE
EXPERIENCE RECORD
DAILY REPORT OF REPORTABLE ACCIDENT

More Related Content

What's hot

23 richard a. hall - 5287265 - interfacing methods for use in inputting ope...
23   richard a. hall - 5287265 - interfacing methods for use in inputting ope...23   richard a. hall - 5287265 - interfacing methods for use in inputting ope...
23 richard a. hall - 5287265 - interfacing methods for use in inputting ope...Mello_Patent_Registry
 
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology... Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...hydrologyproject0
 
Semiconductor equipment in USA May 26 2020
Semiconductor equipment in USA May 26 2020Semiconductor equipment in USA May 26 2020
Semiconductor equipment in USA May 26 2020Emily Tan
 

What's hot (8)

23 richard a. hall - 5287265 - interfacing methods for use in inputting ope...
23   richard a. hall - 5287265 - interfacing methods for use in inputting ope...23   richard a. hall - 5287265 - interfacing methods for use in inputting ope...
23 richard a. hall - 5287265 - interfacing methods for use in inputting ope...
 
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology... Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
Download-manuals-surface water-manual-sw-volume3fieldmanualhydro-meteorology...
 
Notam 01-01-17
Notam 01-01-17Notam 01-01-17
Notam 01-01-17
 
Trspred
TrspredTrspred
Trspred
 
854 f wiring
854 f wiring854 f wiring
854 f wiring
 
Hilux abs sist. 2011
Hilux abs sist. 2011Hilux abs sist. 2011
Hilux abs sist. 2011
 
Semiconductor equipment in USA May 26 2020
Semiconductor equipment in USA May 26 2020Semiconductor equipment in USA May 26 2020
Semiconductor equipment in USA May 26 2020
 
Report
ReportReport
Report
 

Similar to SCCL Safety Check list of records

Pipeline Operations & Maintenance Corrosion Field Testing - Where, When & How
Pipeline Operations & Maintenance Corrosion  Field Testing - Where, When & HowPipeline Operations & Maintenance Corrosion  Field Testing - Where, When & How
Pipeline Operations & Maintenance Corrosion Field Testing - Where, When & HowAudubon Engineering Company
 
Aircriaf turbin Engine Reliability and Inspection Investigations.pdf
Aircriaf turbin Engine Reliability and Inspection Investigations.pdfAircriaf turbin Engine Reliability and Inspection Investigations.pdf
Aircriaf turbin Engine Reliability and Inspection Investigations.pdfssuser5cb52c
 
51410-55S00.pdf
51410-55S00.pdf51410-55S00.pdf
51410-55S00.pdfMian Majid
 
Petronas drilling operations guideline
Petronas drilling operations guidelinePetronas drilling operations guideline
Petronas drilling operations guidelineEaswaran Kanason
 
02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATSMary Calkins
 
final-herbst-ogp-05-01-14.pptx
final-herbst-ogp-05-01-14.pptxfinal-herbst-ogp-05-01-14.pptx
final-herbst-ogp-05-01-14.pptxAnithaDas6
 
Summary of Significant Aspects and Controls - ISO 14001
Summary of Significant Aspects and Controls - ISO 14001Summary of Significant Aspects and Controls - ISO 14001
Summary of Significant Aspects and Controls - ISO 14001James Charles
 
Rencana kerja dan pemeliharaan peralatan
Rencana kerja dan pemeliharaan peralatan Rencana kerja dan pemeliharaan peralatan
Rencana kerja dan pemeliharaan peralatan hero1964
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)hepemod733
 
RTG19_CircuitDiagram_REVB (2).pdf
RTG19_CircuitDiagram_REVB (2).pdfRTG19_CircuitDiagram_REVB (2).pdf
RTG19_CircuitDiagram_REVB (2).pdfJrMerlinCabato2
 
Raw mill bridge welding & inspection(frm) acl-mundwa
Raw mill bridge welding & inspection(frm) acl-mundwaRaw mill bridge welding & inspection(frm) acl-mundwa
Raw mill bridge welding & inspection(frm) acl-mundwaHaresh Nakum
 
Gas Turbine Basics.pdf
Gas Turbine Basics.pdfGas Turbine Basics.pdf
Gas Turbine Basics.pdfyusuf699644
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Emeka Ngwobia
 
20070088 eia4 en
20070088 eia4 en20070088 eia4 en
20070088 eia4 enali sabouri
 

Similar to SCCL Safety Check list of records (20)

Well test procedures manual
Well test procedures manualWell test procedures manual
Well test procedures manual
 
Well test-procedures-manual
Well test-procedures-manualWell test-procedures-manual
Well test-procedures-manual
 
testing formats
testing formatstesting formats
testing formats
 
Pipeline Operations & Maintenance Corrosion Field Testing - Where, When & How
Pipeline Operations & Maintenance Corrosion  Field Testing - Where, When & HowPipeline Operations & Maintenance Corrosion  Field Testing - Where, When & How
Pipeline Operations & Maintenance Corrosion Field Testing - Where, When & How
 
JG Smit - CV
JG Smit - CVJG Smit - CV
JG Smit - CV
 
Changing world of maintenance - AXYS Consulting
Changing world of maintenance - AXYS ConsultingChanging world of maintenance - AXYS Consulting
Changing world of maintenance - AXYS Consulting
 
Aircriaf turbin Engine Reliability and Inspection Investigations.pdf
Aircriaf turbin Engine Reliability and Inspection Investigations.pdfAircriaf turbin Engine Reliability and Inspection Investigations.pdf
Aircriaf turbin Engine Reliability and Inspection Investigations.pdf
 
51410-55S00.pdf
51410-55S00.pdf51410-55S00.pdf
51410-55S00.pdf
 
Petronas drilling operations guideline
Petronas drilling operations guidelinePetronas drilling operations guideline
Petronas drilling operations guideline
 
02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS02 QUALITY CONTROL TEST REPORTS FORMATS
02 QUALITY CONTROL TEST REPORTS FORMATS
 
final-herbst-ogp-05-01-14.pptx
final-herbst-ogp-05-01-14.pptxfinal-herbst-ogp-05-01-14.pptx
final-herbst-ogp-05-01-14.pptx
 
Summary of Significant Aspects and Controls - ISO 14001
Summary of Significant Aspects and Controls - ISO 14001Summary of Significant Aspects and Controls - ISO 14001
Summary of Significant Aspects and Controls - ISO 14001
 
Saudi Aramco Engineering Procedures (SAEP)3
Saudi Aramco Engineering Procedures (SAEP)3Saudi Aramco Engineering Procedures (SAEP)3
Saudi Aramco Engineering Procedures (SAEP)3
 
Rencana kerja dan pemeliharaan peralatan
Rencana kerja dan pemeliharaan peralatan Rencana kerja dan pemeliharaan peralatan
Rencana kerja dan pemeliharaan peralatan
 
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)23.  CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
23. CIWPF-MPT-WPR-0023_21-Mar-24.pptx (SMARK)
 
RTG19_CircuitDiagram_REVB (2).pdf
RTG19_CircuitDiagram_REVB (2).pdfRTG19_CircuitDiagram_REVB (2).pdf
RTG19_CircuitDiagram_REVB (2).pdf
 
Raw mill bridge welding & inspection(frm) acl-mundwa
Raw mill bridge welding & inspection(frm) acl-mundwaRaw mill bridge welding & inspection(frm) acl-mundwa
Raw mill bridge welding & inspection(frm) acl-mundwa
 
Gas Turbine Basics.pdf
Gas Turbine Basics.pdfGas Turbine Basics.pdf
Gas Turbine Basics.pdf
 
Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.Hydrotest REPORT FOR 4'' 158m Line.
Hydrotest REPORT FOR 4'' 158m Line.
 
20070088 eia4 en
20070088 eia4 en20070088 eia4 en
20070088 eia4 en
 

More from mallareddy1975

Company administration & functioning of board
Company administration & functioning of boardCompany administration & functioning of board
Company administration & functioning of boardmallareddy1975
 
Accident reporting ,investigation & analysis (cif&b)
Accident reporting ,investigation & analysis (cif&b)Accident reporting ,investigation & analysis (cif&b)
Accident reporting ,investigation & analysis (cif&b)mallareddy1975
 
SCCL Corporate safety accident analysis 2006 2011 may
SCCL Corporate safety accident analysis 2006   2011 maySCCL Corporate safety accident analysis 2006   2011 may
SCCL Corporate safety accident analysis 2006 2011 maymallareddy1975
 
SCCL Executive Leave rules with amendments upto 01.06.2013
SCCL Executive Leave rules  with amendments upto 01.06.2013SCCL Executive Leave rules  with amendments upto 01.06.2013
SCCL Executive Leave rules with amendments upto 01.06.2013mallareddy1975
 
Ktk1 incline cost review meeting 24 09-2015
Ktk1 incline cost review meeting 24 09-2015Ktk1 incline cost review meeting 24 09-2015
Ktk1 incline cost review meeting 24 09-2015mallareddy1975
 

More from mallareddy1975 (6)

Company administration & functioning of board
Company administration & functioning of boardCompany administration & functioning of board
Company administration & functioning of board
 
Accident analysis
Accident analysisAccident analysis
Accident analysis
 
Accident reporting ,investigation & analysis (cif&b)
Accident reporting ,investigation & analysis (cif&b)Accident reporting ,investigation & analysis (cif&b)
Accident reporting ,investigation & analysis (cif&b)
 
SCCL Corporate safety accident analysis 2006 2011 may
SCCL Corporate safety accident analysis 2006   2011 maySCCL Corporate safety accident analysis 2006   2011 may
SCCL Corporate safety accident analysis 2006 2011 may
 
SCCL Executive Leave rules with amendments upto 01.06.2013
SCCL Executive Leave rules  with amendments upto 01.06.2013SCCL Executive Leave rules  with amendments upto 01.06.2013
SCCL Executive Leave rules with amendments upto 01.06.2013
 
Ktk1 incline cost review meeting 24 09-2015
Ktk1 incline cost review meeting 24 09-2015Ktk1 incline cost review meeting 24 09-2015
Ktk1 incline cost review meeting 24 09-2015
 

Recently uploaded

Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Miguel Araújo
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreternaman860154
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...Neo4j
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsRoshan Dwivedi
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Igalia
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEarley Information Science
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...Martijn de Jong
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationRadu Cotescu
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘RTylerCroy
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationMichael W. Hawkins
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking MenDelhi Call girls
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Enterprise Knowledge
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsMaria Levchenko
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024The Digital Insurer
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsEnterprise Knowledge
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...apidays
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfEnterprise Knowledge
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Allon Mureinik
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...gurkirankumar98700
 

Recently uploaded (20)

Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
Mastering MySQL Database Architecture: Deep Dive into MySQL Shell and MySQL R...
 
Presentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreterPresentation on how to chat with PDF using ChatGPT code interpreter
Presentation on how to chat with PDF using ChatGPT code interpreter
 
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...Workshop - Best of Both Worlds_ Combine  KG and Vector search for  enhanced R...
Workshop - Best of Both Worlds_ Combine KG and Vector search for enhanced R...
 
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live StreamsTop 5 Benefits OF Using Muvi Live Paywall For Live Streams
Top 5 Benefits OF Using Muvi Live Paywall For Live Streams
 
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
Raspberry Pi 5: Challenges and Solutions in Bringing up an OpenGL/Vulkan Driv...
 
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptxEIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
EIS-Webinar-Prompt-Knowledge-Eng-2024-04-08.pptx
 
2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...2024: Domino Containers - The Next Step. News from the Domino Container commu...
2024: Domino Containers - The Next Step. News from the Domino Container commu...
 
Scaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organizationScaling API-first – The story of a global engineering organization
Scaling API-first – The story of a global engineering organization
 
🐬 The future of MySQL is Postgres 🐘
🐬  The future of MySQL is Postgres   🐘🐬  The future of MySQL is Postgres   🐘
🐬 The future of MySQL is Postgres 🐘
 
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
Neo4j - How KGs are shaping the future of Generative AI at AWS Summit London ...
 
GenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day PresentationGenCyber Cyber Security Day Presentation
GenCyber Cyber Security Day Presentation
 
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men08448380779 Call Girls In Greater Kailash - I Women Seeking Men
08448380779 Call Girls In Greater Kailash - I Women Seeking Men
 
Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...Driving Behavioral Change for Information Management through Data-Driven Gree...
Driving Behavioral Change for Information Management through Data-Driven Gree...
 
Handwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed textsHandwritten Text Recognition for manuscripts and early printed texts
Handwritten Text Recognition for manuscripts and early printed texts
 
Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024Finology Group – Insurtech Innovation Award 2024
Finology Group – Insurtech Innovation Award 2024
 
IAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI SolutionsIAC 2024 - IA Fast Track to Search Focused AI Solutions
IAC 2024 - IA Fast Track to Search Focused AI Solutions
 
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
Apidays Singapore 2024 - Building Digital Trust in a Digital Economy by Veron...
 
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdfThe Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
The Role of Taxonomy and Ontology in Semantic Layers - Heather Hedden.pdf
 
Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)Injustice - Developers Among Us (SciFiDevCon 2024)
Injustice - Developers Among Us (SciFiDevCon 2024)
 
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
Kalyanpur ) Call Girls in Lucknow Finest Escorts Service 🍸 8923113531 🎰 Avail...
 

SCCL Safety Check list of records

  • 1. THE SINGARENI COLLIERIES COMPANY LIMITED BHUPALPALLI AREA List of Statutory Records/Reports to be maintained at Mine Level (Check list) Name of Mine/Dept.__________________________________
  • 2. THE SINGARENI COLLIERIES COMPANY LIMITED, BHUPALPALLI AREA List of Statutory records/reports to be maintained at mine level (Check list) Sl. No. Reg./ Cir.No. Name of the Register/Report Periodicity Maintained by 1 36(3) Register of appointment of Officials and competent persons As and when required Manager/ Office 2 38(2) Timing Register for below ground employees Shift wise Manway Clerk 3 41(3) Register for material requisition As and when required Manager/ Office 4 41(8) Fatal/Serious accidents enquiry report As and when required S.O. 5 41(1)(b) Manager’s Diary Daily Manager, Asst. Manager, Under Manager. 6 41A(3) Safety Officer’s Diary Daily S.O. 7 42A(3) Ventilation Officer’s Diary Daily V.O. 8 43(9) Report of Overman Daily Overman 9 47(b) Attendant’s report of Main mechanical ventilator Every shift Fan attendant/Engin eer 10 49(2) Mine Survey record As and when required Surveyor 11 56(b) Record of explosives(Receipts, Issues & Stock) Daily Incharge, Magazine/S.O. 12 56(d) Record of explosives(Daily issues & returns) Daily -do- 13 63(4) Record of list of plans & other survey material As and when required Surveyor 14 70(1) Examination of outlets Weekly S.O. 15 89(1)(d) Examination of buffer, draw bar and other attachment Fortnight Engineer 16 89(3) List of persons authorised to ride on tub As and when required S.O. 17 90(5) Examination of haulage rope Monthly Engineer 18 91(3) Haulage rope record As and when required Engineer 19 93(1)(a) Examination of haulage engine Daily Engineer 20 93(1)(d) Examination of track line Weekly S.O. 21 94 Examination of haulage & travelling roadways Weekly S.O. 22 100(6) (1)(F) Convergence record book Daily S.O. 23 103A(1) Register of contrivances pointed out by Inspector As and when required Manager/Office 24 105(1) Examination of workings under Reg. 105, if any As specified in the DMS condition. S.O. 25 108(6) Code of standing orders on SSR - Manager 26 110 Code of standing orders for withdrawal of supports - Manager
  • 3. Sl. No. Reg./ Cir.No. Name of the Register/Report Periodicity Maintained by 27 113(3) Daily report of mining sirdar Daily S.O. 28 114(3) Avoidance of danger As and when required S.O. 29 116(5) Analysis report of general body of air Monthly VO/SO 30 117(5) Permissions to light a fire within 15 mtrs. from any entrance of the mine Monthly SO/Engineer 31 117(6) Examination for surface fire that may have broken out/any indications thereon Weekly S.O. 32 118(2) (i) Permissions to light a fire below ground As and when required S.O. 33 118(5) Inspections of un-used workings for signs of illicit distillation of liquor Monthly S.O. 34 118A(3) (a)(i) Tests for percentage of CO at goaf edge and return air of every depillaring dist. Weekly VO/SO 35 118A(3) (a)(ii) Analysis report of Air samples drawn from return air and goaf edge of depillaring dist. Monthly VO/SO 36 118A(3) (c) Idle day inspection of depillaring dist. & unused workings Weekly S.O. 37 119(1) (a) Examination after fire has broken out As and when required VO/SO 38 120(3) (a) Examination of fire fighting stations Monthly S.O. 39 120(3) (c) Examination of Fire Extinguishers Monthly Engineer 40 122(5) Examination of isolation stoppings Weekly S.O. 41 123(3) (a) Record of Air born respirable dust survey Every 6 months V.O. 42 123(6) (h) Inspection of dust respirators and other devices used for prevention and suppression of dust Weekly V.O. 43 123A(2) Stone dust and treatment record Daily V.O. 44 123B(8) Dust sampling record(All sections to be completed within 30 days) 30 days V.O. 45 126(5) (a) Examination of protective measure against inrush of surface water Every 14 days in rainy season, 30 days in other season S.O. 46 127(6) (b) Record of particulars related to drivage towards water bearing strata or water-logged area As and when required S.O. 47 130(2) (v) Record of air samples and temp. readings 30 days V.O. 48 133(2) Shiftwise report of mechanical ventilator Every shift Engineer 49 133(3) Weekly examination of mechanical ventilator Weekly Engineer 50 133(4){a) Record of air measurements Monthly V.O. 51 134(3) Standing orders for main mechanical ventilator - V.O.
  • 4. Sl. No. Reg./ Cir.No. Name of the Register/Report Periodicity Maintained by 52 136(6) Examination of Ventilation devices For every 14 days V.O. 53 141(2) Examination of the mine or part reopened after a discontinuance or being dewatered. As and when required S.O. 54 142(6) Occurrence of Gas As and when required S.O. 55 145 Record of Gas Survey in I degree gassy mines Monthly V.O. 56 155(3) Daily examination of Safety lamps on its being returned after use Daily Engineer 57 156(2) Record of Safety lamps(Daily issues & returns) Daily Engineer 58 162(4) Record of Explosives(Shiftwise issues & returns) Every shift S.O. 59 164A(5) Examination of vehicle used for transport of explosives(from Area Stores to Pit magazine) Whenever applicable S.O. 60 169(2) Overhauling, tests and repairs of Exploders. Every 3 months Engineer 61 177(8) Report of misfires As and when required S.O. 62 179(b) Daily report of Shotfirer Every shift S.O. 63 186(5) Examination of Plant & Machinery Weekly Engineer 64 187(9) Examination of Surface fences Weekly S.O. 65 199A Approved Emergency Organisation Plan - S.O. 66 2/1981 59/1967 Record of mock rehearsals a) In depillaring districts b) For danger from inundation c) Standing orders for fire d) Stoppage of main mechanical ventilator e) Emergency Organisation Plan Regularly Monthly Quarterly Quarterly Quarterly S.O. S.O. S.O. S.O. S.O. 67 12/1962 4/1988 Subsidence record As and when required Survey Officer 68 9/1963 Local and main fall record -do- -do- 69 Pal committee Recomme ndation Anchorage Testing record 10% of the installed bolts S.O. 70 Sec. 23(1A) Register of reportable accidents in form “J” Quarterly S.O. 71 Sec. 23(3) Register of minor accidents in form “K” Annually S.O. 72 CGM(S) Cir. No. CS/44 (b)/92/1197, dt. 10.12.76 Record of Steel Supports Monthly S.O.
  • 5. Sl. No. Reg./ Cir.No. Name of the Register/Report Periodicity Maintained by 73 Special Training on SSR for Timberman & Support Mazdoor Once in 2 years S.O. 74 3(Gen.) of 1978 Minor accidents and analysis record As and when required S.O. 75 6/1976 Gas survey in I degree Gassy seams: a) General body of air b) Bore holes’ samples 30 days Quarterly V.O. V.O. 76 30/1964 Analysis report of air samples drawn behind isolation stoppings Monthly S.O. 77 1/1960 Examination of workings beneath Structure a) Rivers and Jores, etc. b) Roads & Railways C). Dwellings & other structures Monthly or any other period as mentioned in DMS permission. S.O. 78 Record of examination of Transformer oil Every 6 months Engineer 79 E/L record of HT and LT switches Monthly Engineer 80 Examination of physical & electrical condition of flexible cables Monthly Engineer 81 Earth electrode resistance record Monthly Engineer 82 E/L testing record of drill panels Monthly Engineer 83 IER 131(5) Log sheet for elec. Supervisors Daily Engineer 84 Breakdown analysis record As and when required Engineer 85 11/1974 (16)(a) Shiftwise inspection report of belt conveyor Every shift Engineer 86 11/1974 19(b) Examination of belt conveyor Daily Engineer 87 11/1974 20(b) Examination of Electrical installations of belt conveyor Weekly Engineer 88 14/1979 Examination of electrical installations in lamp cabin Weekly Engineer 89 M.Rules 29R(2) Workmen’s Inspector report book in form “U” Twice in a week S.O./Engineer 90 49/1964 21/1966 Record of Pit Safety Committee Monthly S.O. 91 M.Rules 34(h) Record of white washing for interior walls, ceilings and partitions of latrines & urinals Every 4 months S.O. 92 M.Rules 42(3) Upto-date list of First Aiders As and when required S.O. 93 M. Rules 44(3) Upto-date list of all First Aid Stations -do- S.O. 94 M.Rules 49(4) Register of Compensatory days of Rest in form “F” Weekly W.O. 95 M.Rules 51 Termination of Employment in form “B” As and when required W.O.
  • 6. Sl. No. Reg./ Cir.No. Name of the Register/Report Periodicity Maintained by 96 M.Rules 53(1) Register of Leave with wages in form “G/H” As and when required W.O. 97 M.Rules 59 Register of Over Time in form “I” -do- Office 98 M.Rules 69(4) Minutes book of Canteen Committee meeting Monthly W.O. 99 M.Rules 73(3) Diary of Welfare Officer Daily W.O. 100 Record of refresher training 101 Record of change of Job training INDUCED BLASTING PUBLIC ADDRESS SYSTEM ROOF FALL FORT NIGHT INSPECTION OF MAGAZINE EXPERIENCE RECORD DAILY REPORT OF REPORTABLE ACCIDENT
  • 7. Sl. No. Reg./ Cir.No. Name of the Register/Report Periodicity Maintained by 96 M.Rules 53(1) Register of Leave with wages in form “G/H” As and when required W.O. 97 M.Rules 59 Register of Over Time in form “I” -do- Office 98 M.Rules 69(4) Minutes book of Canteen Committee meeting Monthly W.O. 99 M.Rules 73(3) Diary of Welfare Officer Daily W.O. 100 Record of refresher training 101 Record of change of Job training INDUCED BLASTING PUBLIC ADDRESS SYSTEM ROOF FALL FORT NIGHT INSPECTION OF MAGAZINE EXPERIENCE RECORD DAILY REPORT OF REPORTABLE ACCIDENT