Field
Issue Purpose
Nghi Son Refinery and Petrochemical
Limited Liability Company
Employer Contract No.: XXXXX, Contractor JOB Code: 0
Page
None Issue for Construction
All First issue
Prepared by
H.Ishiga
Field Quality Control Procedure
1. NSRP
Complex
Nghi S
Employer Contract No.: XXXXX, Contractor JOB Code: 0
Rev
0
A
Operation Centre JOB Code:
Responsible Company
NSRP
Complex Project
Son, Vietnam
Employer Contract No.: XXXXX, Contractor JOB Code: 0
Date
30/SEP/13
20/AUG/13
Operation Centre JOB Code:
Responsible Company
JVD
Project
, Vietnam
Nghi Son
Employer Contract No.: XXXXX, Contractor JOB Code: 0
Page
30/SEP/13 None
/13 All
Operation Centre JOB Code:
Responsible Company Prepared
Field
Issue Purpose
Nghi Son Refinery and Petrochemical
Limited Liability Company
Employer Contract No.: XXXXX, Contractor JOB Code: 0
Page
None Issue for Construction
All First issue
Prepared by
H.Ishiga
Field Quality Control Procedure
Unit No.:
Document Class:
Issue Purpose
Refinery and Petrochemical
Limited Liability Company
Employer Contract No.: XXXXX, Contractor JOB Code: 0-6495-
Description
Issue for Construction
First issue
Operation Centre
H.Ishiga
Checked
Quality Control Procedure
Unit No.: Not Applicable
Document Class:
Issue Purpose
Refinery and Petrochemical
Limited Liability Company
-20
Description
Issue for Construction
Operation Centre
Checked by
Y.Ogawa
Quality Control Procedure
Not Applicable
Document Class: Z
For Construction
Refinery and Petrochemical
Employer Doc. No.
Contractor Doc. No.
Prep'd
Operation Centre Doc. No.:
Y.Ogawa
Quality Control Procedure
Not Applicable
Construction
Employer Doc. No.
Contractor Doc. No.
S-000-1670
Rev. 0
Date: 30
Prep'd Chk'd
H.I. Y.O.
H.I. Y.O.
Doc. No.:
Approved by
T.Hayashi
Quality Control Procedure
Employer Doc. No.
Contractor Doc. No.
670-0001V
Page 1 of 21
30/SEP/13
Chk'd App'd
Y.O. T.H.
Y.O. T.H.
Approved by
T.Hayashi
21
App'd
T.H.
T.H.
INDRA
02-OCT-2013
2. NSRP
Title: Field Quality Control Procedure
1 GENERAL
1.1 Scope
1.2 Purpose
1.3 Objective
2 ABBREVIATION AND DEF
3 REFERENCES
4 PROJECT STANDA
5 INSPECTION AND TEST
6 ORGANIZATION
6.1 Field
6.2 QC E
6.3 Inspector
6.4 Qualification of QC Personnel
7 REGULAR QUALITY CONT
7.1 Issuance of QC specifications
7.2 Kick
7.3 Review and Approval of Subcontractor’s documents
7.4 Pre
7.5 Material Receiving Inspection
7.6 Material Identification and Traceability
7.7 QC
7.8 Notification for Witness Inspection....................................................................................
7.9 Witness Insp
7.10 Disposition (Correction) and Corrective action of Nonconformity
7.11 C
7.12 System Handov
8 LIAISON WITH
8.1 Meeting
8.2 Reporting
8.3 Notification
A TTACHMENT
ATTACHMENT
NSRP Complex
Field Quality Control Procedure
GENERAL................................
Scope................................
Purpose................................
Objective................................
ABBREVIATION AND DEF
REFERENCES
PROJECT STANDA
INSPECTION AND TEST
ORGANIZATION
Field QC Manager
QC Engineer
Inspector................................
Qualification of QC Personnel
REGULAR QUALITY CONT
Issuance of QC specifications
Kick-off Meetings (After contract)
Review and Approval of Subcontractor’s documents
Pre-Inspection Meeting (PIM)
Material Receiving Inspection
Material Identification and Traceability
QC Monitoring
7.8 Notification for Witness Inspection....................................................................................
Witness Insp
Disposition (Correction) and Corrective action of Nonconformity
Confirmation and Control of QC Record
7.12 System Handov
LIAISON WITH
Meeting................................
Reporting................................
Notification
TTACHMENT-1 FIELD QC ORGANIZATIO
ATTACHMENT-2 A LIST OF ANTICIPATE
Complex Project
Field Quality Control Procedure
................................
................................
................................
................................
ABBREVIATION AND DEF
REFERENCES................................
PROJECT STANDARD QC PROCEDURES AND
INSPECTION AND TEST
ORGANIZATION................................
Manager ................................
ngineer……………………………………………………………………………………………
................................
Qualification of QC Personnel
REGULAR QUALITY CONT
Issuance of QC specifications
off Meetings (After contract)
Review and Approval of Subcontractor’s documents
Inspection Meeting (PIM)
Material Receiving Inspection
Material Identification and Traceability
Monitoring................................
7.8 Notification for Witness Inspection....................................................................................
Witness Inspection/Document Review
Disposition (Correction) and Corrective action of Nonconformity
onfirmation and Control of QC Record
7.12 System Handover...........................................................................................................................
LIAISON WITH EMPLOYER
................................
................................
Notification................................
FIELD QC ORGANIZATIO
A LIST OF ANTICIPATE
Field Quality Control Procedure
................................................................
................................................................
................................................................
................................................................
ABBREVIATION AND DEFINITION
................................................................
RD QC PROCEDURES AND
INSPECTION AND TEST PLAN (ITP)
................................
................................
……………………………………………………………………………………………
................................................................
Qualification of QC Personnel ................................
REGULAR QUALITY CONTROL ACTIVITIES IN CO
Issuance of QC specifications................................
off Meetings (After contract)
Review and Approval of Subcontractor’s documents
Inspection Meeting (PIM)................................
Material Receiving Inspection ................................
Material Identification and Traceability
................................................................
7.8 Notification for Witness Inspection....................................................................................
ection/Document Review
Disposition (Correction) and Corrective action of Nonconformity
onfirmation and Control of QC Record
er...........................................................................................................................
EMPLOYER ................................
................................................................
................................................................
................................................................
FIELD QC ORGANIZATIO
A LIST OF ANTICIPATED
CONTENTS
................................
................................................................
................................
................................
INITION................................
................................
RD QC PROCEDURES AND
PLAN (ITP)................................
................................................................
................................................................
……………………………………………………………………………………………
................................
................................
ROL ACTIVITIES IN CO
................................
off Meetings (After contract)................................
Review and Approval of Subcontractor’s documents
................................
................................
Material Identification and Traceability................................
................................
7.8 Notification for Witness Inspection....................................................................................
ection/Document Review................................
Disposition (Correction) and Corrective action of Nonconformity
onfirmation and Control of QC Record ................................
er...........................................................................................................................
................................
................................
................................
................................
FIELD QC ORGANIZATION……………………………………………………
D ITPs……………………………………………………
Employer Doc. No.
Contractor Doc. No.
S
CONTENTS
................................................................
................................
................................................................
................................................................
................................................................
................................................................
RD QC PROCEDURES AND SPECIFICATIONS
................................................................
................................................................
................................
……………………………………………………………………………………………
................................................................
................................................................
ROL ACTIVITIES IN CONSTRUCTION PHASE
................................................................
................................................................
Review and Approval of Subcontractor’s documents ................................
................................................................
................................................................
................................
................................................................
7.8 Notification for Witness Inspection....................................................................................
................................
Disposition (Correction) and Corrective action of Nonconformity
................................
er...........................................................................................................................
................................................................
................................................................
................................................................
................................................................
……………………………………………………
……………………………………………………
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
................................
................................................................
................................................................
................................................................
................................
................................
SPECIFICATIONS
................................
................................
................................................................
……………………………………………………………………………………………
................................................................
................................
NSTRUCTION PHASE
................................
................................
................................
................................................................
................................
................................................................
................................
7.8 Notification for Witness Inspection....................................................................................
................................................................
Disposition (Correction) and Corrective action of Nonconformity................................
................................................................
er...........................................................................................................................
................................................................
................................................................
................................................................
................................
……………………………………………………
……………………………………………………
Contractor Doc. No.
0001V
................................................................
................................
................................
................................
................................................................
................................................................
SPECIFICATIONS................................
...............................................................
................................................................
......................................................
……………………………………………………………………………………………
................................
................................................................
NSTRUCTION PHASE..............................
................................................................
................................................................
................................................................
................................
................................................................
..........................................................
................................................................
7.8 Notification for Witness Inspection....................................................................................
...........................................................
................................
.......................................................
er...........................................................................................................................
................................
................................
................................
................................................................
……………………………………………………………………10
……………………………………………………
Rev.0
Page 2 of 21
PAGE
...................................
....................................................
................................................
..............................................
................................
.....................................
..........................................
...............................
................................
......................
……………………………………………………………………………………………...
..............................................
.........................................
..............................
.........................................
................................
................................
...........................................
.........................................
..........................
.....................................
7.8 Notification for Witness Inspection...................................................................................................8
...........................
...........................................
.......................
er................................................................................................................................9
..............................................
.................................................
.............................................
..........................................
………………10
……………………………………………………….……….11
21
PAGE
... 4
....................4
................4
..............4
..................................4
.....5
..........5
...............................5
..................................5
...................... 5
...5
..............6
.........6
..............................6
.........6
...................................6
................................6
...........6
.........7
..........................7
.....7
...............8
...........................8
...........8
.......................8
.....9
..............9
.................9
.............9
..........9
………………10
……….11
INDRA
02-OCT-2013
3. NSRP
Title: Field Quality Control Procedure
ATTACHMENT
ATTACHMENT
ATTACHMENT
NSRP Complex
Field Quality Control Procedure
ATTACHMENT-3 A TABLE OF ANTICIPAT
ATTACHMENT-4 NOTIFICATION
ATTACHMENT-5 DOCUMENT FLOW
Complex Project
Field Quality Control Procedure
A TABLE OF ANTICIPAT
NOTIFICATION
DOCUMENT FLOW
Field Quality Control Procedure
A TABLE OF ANTICIPATED QCR
NOTIFICATION FOR INSPECTION
DOCUMENT FLOW……………………………………………………
ED QCRs………………..………………………………
FOR INSPECTION FORM
……………………………………………………
Employer Doc. No.
Contractor Doc. No.
S
………………..………………………………
FORM… …………………………………………….19
……………………………………………………
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
………………..………………………………
…………………………………………….19
……………………………………………………
Contractor Doc. No.
0001V
………………..………………………………
…………………………………………….19
………………………………………………………………………………20
Rev.0
Page 3 of 21
………………..………………………………………….1
…………………………………………….19
…………………………20
21
………….13
…………………………………………….19
…………………………20
INDRA
02-OCT-2013
4. NSRP
Title: Field Quality Control Procedure
1
1.1
1.2
1.3
2
NSRP Complex
Field Quality Control Procedure
GENERAL
Scope
This Field Quality Control Procedure
activities for
This procedure covers planning, administration, and execution of project Quality Control
at construction site
“Project Quality Plan (
Purpose
The purpose of this procedure is to define the way for execution, responsibilities and interface
between the
Objective
The objective of this procedure is to maintain
Control Activities by all parties and personnel involved.
The objectives of Quality C
Only accepted facilities by co
No defects / troubles / nonconformities
Successful
budget and schedule.
2 ABBREVIATION AND DEF
Employer:
Contractor:
Subcontractor:
JVD:
FQCM:
PQCM:
KOM:
PIM:
ITP:
NDE:
QCR:
WPS/PQR:
NCR:
Complex Project
Field Quality Control Procedure
GENERAL
Quality Control Procedure
activities for construction work
This procedure covers planning, administration, and execution of project Quality Control
at construction site. This document is based on the
Quality Plan (Co
The purpose of this procedure is to define the way for execution, responsibilities and interface
between the Contractor
The objective of this procedure is to maintain
Control Activities by all parties and personnel involved.
The objectives of Quality C
nly accepted facilities by co
No defects / troubles / nonconformities
uccessful completion of construction and commissioning work will be achieved within agreed
budget and schedule.
ABBREVIATION AND DEF
:
Subcontractor:
WPS/PQR:
Field Quality Control Procedure
Quality Control Procedure
construction work for NSRP Complex
This procedure covers planning, administration, and execution of project Quality Control
. This document is based on the
Common)”and
The purpose of this procedure is to define the way for execution, responsibilities and interface
Contractor, Employer and Subcontractor for Quality Control
The objective of this procedure is to maintain
Control Activities by all parties and personnel involved.
The objectives of Quality Control for construction work are that;
nly accepted facilities by contract documents will be delivered to
No defects / troubles / nonconformities
completion of construction and commissioning work will be achieved within agreed
budget and schedule. – “First Time, Right
ABBREVIATION AND DEFINITION
: Nghi Son Refinery and Petrochemical Limites Liability Company
: A Joint Venture formed by JGC Corporation, Chiyoda Corporation, GS
Engineering &
Co.,Ltd, Technip France and Technip Geoproduction (m) Sdn.Bhd.
: The person, firm or corporation to whom the
: Joint Venture Directorate
Field QC
: Project QC Manager
: Kick-off Meeting
: Pre-inspection Meeting
: Inspection and Test Plan
: Non Destructive Examination
Quality Control Record
: Welding Procedure Specification/Procedure
: Nonconformity Report
Quality Control Procedure describes the procedure for Contractor’s Quality Control (QC)
NSRP Complex
This procedure covers planning, administration, and execution of project Quality Control
. This document is based on the
and S-000-1610
The purpose of this procedure is to define the way for execution, responsibilities and interface
and Subcontractor for Quality Control
The objective of this procedure is to maintain the
Control Activities by all parties and personnel involved.
ntrol for construction work are that;
ntract documents will be delivered to
No defects / troubles / nonconformities will be detected in
completion of construction and commissioning work will be achieved within agreed
Time, Right”
INITION
Nghi Son Refinery and Petrochemical Limites Liability Company
A Joint Venture formed by JGC Corporation, Chiyoda Corporation, GS
Engineering & Construction Corporation, SK Engineering & Construction
Co.,Ltd, Technip France and Technip Geoproduction (m) Sdn.Bhd.
The person, firm or corporation to whom the
Joint Venture Directorate
Field QC Manager
Project QC Manager
off Meeting
inspection Meeting
Inspection and Test Plan
Non Destructive Examination
Quality Control Record
Welding Procedure Specification/Procedure
Nonconformity Report
Employer Doc. No.
Contractor Doc. No.
S
describes the procedure for Contractor’s Quality Control (QC)
NSRP Complex Project.
This procedure covers planning, administration, and execution of project Quality Control
. This document is based on the Quality Plan
1610-0001V “Construction Execution Plan
The purpose of this procedure is to define the way for execution, responsibilities and interface
and Subcontractor for Quality Control
the uniformity and consistency of Contractor’s Quality
Control Activities by all parties and personnel involved.
ntrol for construction work are that;
ntract documents will be delivered to
will be detected in
completion of construction and commissioning work will be achieved within agreed
under good Quality Control.
Nghi Son Refinery and Petrochemical Limites Liability Company
A Joint Venture formed by JGC Corporation, Chiyoda Corporation, GS
Construction Corporation, SK Engineering & Construction
Co.,Ltd, Technip France and Technip Geoproduction (m) Sdn.Bhd.
The person, firm or corporation to whom the
Joint Venture Directorate
Project QC Manager
inspection Meeting
Inspection and Test Plan
Non Destructive Examination
Quality Control Record
Welding Procedure Specification/Procedure
Nonconformity Report
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
describes the procedure for Contractor’s Quality Control (QC)
This procedure covers planning, administration, and execution of project Quality Control
Quality Plan described in S
Construction Execution Plan
The purpose of this procedure is to define the way for execution, responsibilities and interface
and Subcontractor for Quality Control
uniformity and consistency of Contractor’s Quality
ntrol for construction work are that;
ntract documents will be delivered to Employer
will be detected in the facilities delivered.
completion of construction and commissioning work will be achieved within agreed
under good Quality Control.
Nghi Son Refinery and Petrochemical Limites Liability Company
A Joint Venture formed by JGC Corporation, Chiyoda Corporation, GS
Construction Corporation, SK Engineering & Construction
Co.,Ltd, Technip France and Technip Geoproduction (m) Sdn.Bhd.
The person, firm or corporation to whom the Subcontract
Welding Procedure Specification/Procedure Qualification Record
Contractor Doc. No.
0001V
describes the procedure for Contractor’s Quality Control (QC)
This procedure covers planning, administration, and execution of project Quality Control
described in S-000-
Construction Execution Plan
The purpose of this procedure is to define the way for execution, responsibilities and interface
and Subcontractor for Quality Control of construction work
uniformity and consistency of Contractor’s Quality
Employer.
facilities delivered.
completion of construction and commissioning work will be achieved within agreed
under good Quality Control.
Nghi Son Refinery and Petrochemical Limites Liability Company
A Joint Venture formed by JGC Corporation, Chiyoda Corporation, GS
Construction Corporation, SK Engineering & Construction
Co.,Ltd, Technip France and Technip Geoproduction (m) Sdn.Bhd.
Subcontract
Qualification Record
Rev.0
Page 4 of 21
describes the procedure for Contractor’s Quality Control (QC)
This procedure covers planning, administration, and execution of project Quality Control activities
-1139-0004V
Construction Execution Plan”.
The purpose of this procedure is to define the way for execution, responsibilities and interface
construction work.
uniformity and consistency of Contractor’s Quality
facilities delivered.
completion of construction and commissioning work will be achieved within agreed
Nghi Son Refinery and Petrochemical Limites Liability Company
A Joint Venture formed by JGC Corporation, Chiyoda Corporation, GS
Construction Corporation, SK Engineering & Construction
Co.,Ltd, Technip France and Technip Geoproduction (m) Sdn.Bhd.
is issued
Qualification Record
21
describes the procedure for Contractor’s Quality Control (QC)
activities
04V
uniformity and consistency of Contractor’s Quality
completion of construction and commissioning work will be achieved within agreed
A Joint Venture formed by JGC Corporation, Chiyoda Corporation, GS
Construction Corporation, SK Engineering & Construction
INDRA
02-OCT-2013
5. NSRP
Title: Field Quality Control Procedure
3
4
5
6
6.1
6.2
NSRP Complex
Field Quality Control Procedure
3 REFERENCES
S-000-1670
S-000-1670
S-000-1670
S-000-1520
3550-8440
S-000-1139
S-000-1610
4 PROJECT STANDARD QC
The documents which are listed in Section 3 will be utilized as project Standard Quality Control
procedures and specifications. These documents are minimum requirements of Contractor to
ensure Quality of
5 INSPECTION AND TEST PLA
Contractor requires
construction activities to be inspected or examined with reference document and acceptance criteria
for Contractor
specifications
described in S
anticipated ITPs is as per [Attachment
ORGANIZATION
Field QC organization for the project is provided as per
responsible for QC activities at construction site.
Roles and responsibilities of each
Field QC Manager
Field QC Manager (FQCM) is responsible for all direction, definition and coordination in order to
ensure that Quality Control Activities are completed in accordance with the Project specifications,
budget and schedule. Project QC Manager (PQCM) will suppor
construction work.
QC Engineer(s)
If necessary, FQCM will assign QC Engineers
Activities under FQCM. They are also responsible for control of inspectors.
Complex Project
Field Quality Control Procedure
REFERENCES
1670-0002V
1670-0003V
1670-0004V
520-0106V
8440-SP-0030
139-0004V
1610-0001V
PROJECT STANDARD QC
The documents which are listed in Section 3 will be utilized as project Standard Quality Control
procedures and specifications. These documents are minimum requirements of Contractor to
ensure Quality of construction work at
PECTION AND TEST PLA
Contractor requires Subcontractor
construction activities to be inspected or examined with reference document and acceptance criteria
for Contractor’s approval. ITP shall identify all inspections and tests required
specifications in the sequential
described in S-000-1670
anticipated ITPs is as per [Attachment
ORGANIZATION
Field QC organization for the project is provided as per
responsible for QC activities at construction site.
Roles and responsibilities of each
QC Manager
Field QC Manager (FQCM) is responsible for all direction, definition and coordination in order to
ensure that Quality Control Activities are completed in accordance with the Project specifications,
budget and schedule. Project QC Manager (PQCM) will suppor
construction work.
ngineer(s)
If necessary, FQCM will assign QC Engineers
Activities under FQCM. They are also responsible for control of inspectors.
Field Quality Control Procedure
Quality Control Requirements
Nonconformity Contr
Material
Control
Positive Material
Fabrication
Project
Construction Execution Plan
PROJECT STANDARD QC PROCEDURES AND SPECI
The documents which are listed in Section 3 will be utilized as project Standard Quality Control
procedures and specifications. These documents are minimum requirements of Contractor to
construction work at
PECTION AND TEST PLAN (ITP)
Subcontractor to submit an Inspection and Test Plan (ITP)
construction activities to be inspected or examined with reference document and acceptance criteria
approval. ITP shall identify all inspections and tests required
in the sequential manner of construction work
1670-0002V “Quality
anticipated ITPs is as per [Attachment
Field QC organization for the project is provided as per
responsible for QC activities at construction site.
Roles and responsibilities of each personnel engaged in QC Activities are detailed as the below.
Field QC Manager (FQCM) is responsible for all direction, definition and coordination in order to
ensure that Quality Control Activities are completed in accordance with the Project specifications,
budget and schedule. Project QC Manager (PQCM) will suppor
If necessary, FQCM will assign QC Engineers
Activities under FQCM. They are also responsible for control of inspectors.
Quality Control Requirements
onconformity Contr
Material Traceability Control Procedure
Control of Monitoring
Positive Materials Identification
Fabrication and Erection
Project Quality Plan (
Construction Execution Plan
PROCEDURES AND SPECI
The documents which are listed in Section 3 will be utilized as project Standard Quality Control
procedures and specifications. These documents are minimum requirements of Contractor to
construction work at construction
N (ITP)
to submit an Inspection and Test Plan (ITP)
construction activities to be inspected or examined with reference document and acceptance criteria
approval. ITP shall identify all inspections and tests required
manner of construction work
Quality Control Requirements
anticipated ITPs is as per [Attachment-2].
Field QC organization for the project is provided as per
responsible for QC activities at construction site.
personnel engaged in QC Activities are detailed as the below.
Field QC Manager (FQCM) is responsible for all direction, definition and coordination in order to
ensure that Quality Control Activities are completed in accordance with the Project specifications,
budget and schedule. Project QC Manager (PQCM) will suppor
If necessary, FQCM will assign QC Engineers(QCE)
Activities under FQCM. They are also responsible for control of inspectors.
Employer Doc. No.
Contractor Doc. No.
S
Quality Control Requirements t
onconformity Control Procedure
Traceability Control Procedure
f Monitoring and Measuring Devices,
Identification
and Erection
Quality Plan (Common)
Construction Execution Plan
PROCEDURES AND SPECIFICATIONS
The documents which are listed in Section 3 will be utilized as project Standard Quality Control
procedures and specifications. These documents are minimum requirements of Contractor to
construction site.
to submit an Inspection and Test Plan (ITP)
construction activities to be inspected or examined with reference document and acceptance criteria
approval. ITP shall identify all inspections and tests required
manner of construction work
Control Requirements
Field QC organization for the project is provided as per [Attachment
responsible for QC activities at construction site.
personnel engaged in QC Activities are detailed as the below.
Field QC Manager (FQCM) is responsible for all direction, definition and coordination in order to
ensure that Quality Control Activities are completed in accordance with the Project specifications,
budget and schedule. Project QC Manager (PQCM) will suppor
(QCE). QCE are responsible for Quality Control
Activities under FQCM. They are also responsible for control of inspectors.
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
to Subcontractor
ol Procedure for Construction Work
Traceability Control Procedure for Piping
suring Devices,
Identification (PMI) of Alloy Materials during Site
)
FICATIONS
The documents which are listed in Section 3 will be utilized as project Standard Quality Control
procedures and specifications. These documents are minimum requirements of Contractor to
to submit an Inspection and Test Plan (ITP)
construction activities to be inspected or examined with reference document and acceptance criteria
approval. ITP shall identify all inspections and tests required
manner of construction work. The detail requirements of ITP are
Control Requirements to Subcontractor
[Attachment-1].
personnel engaged in QC Activities are detailed as the below.
Field QC Manager (FQCM) is responsible for all direction, definition and coordination in order to
ensure that Quality Control Activities are completed in accordance with the Project specifications,
budget and schedule. Project QC Manager (PQCM) will support FQCM for Quality Control in
QCE are responsible for Quality Control
Activities under FQCM. They are also responsible for control of inspectors.
Contractor Doc. No.
0001V
o Subcontractor
Construction Work
or Piping Construction Work
suring Devices,
(PMI) of Alloy Materials during Site
The documents which are listed in Section 3 will be utilized as project Standard Quality Control
procedures and specifications. These documents are minimum requirements of Contractor to
to submit an Inspection and Test Plan (ITP) describing
construction activities to be inspected or examined with reference document and acceptance criteria
approval. ITP shall identify all inspections and tests required by the contract
. The detail requirements of ITP are
to Subcontractor ”.
Field QC group is
personnel engaged in QC Activities are detailed as the below.
Field QC Manager (FQCM) is responsible for all direction, definition and coordination in order to
ensure that Quality Control Activities are completed in accordance with the Project specifications,
t FQCM for Quality Control in
QCE are responsible for Quality Control
Activities under FQCM. They are also responsible for control of inspectors.
Rev.0
Page 5 of 21
Construction Work
Construction Work
(PMI) of Alloy Materials during Site
The documents which are listed in Section 3 will be utilized as project Standard Quality Control
procedures and specifications. These documents are minimum requirements of Contractor to
describing
construction activities to be inspected or examined with reference document and acceptance criteria
by the contract
. The detail requirements of ITP are
A list of
Field QC group is
personnel engaged in QC Activities are detailed as the below.
Field QC Manager (FQCM) is responsible for all direction, definition and coordination in order to
ensure that Quality Control Activities are completed in accordance with the Project specifications,
t FQCM for Quality Control in
QCE are responsible for Quality Control
21
Construction Work
construction activities to be inspected or examined with reference document and acceptance criteria
ensure that Quality Control Activities are completed in accordance with the Project specifications,
INDRA
02-OCT-2013
6. NSRP
Title: Field Quality Control Procedure
6.3
6.4 Qualification of QC Personnel
All QC activities for construction work shall be implemented by competent QC personnel in each
to keep acceptable quality level during all project period in construction.
training for Contractor QC personnel at the following time, but not limited to
(1) First engagement of project site
(2) Commencement of new insp
(3) Upon Employer
Contractor
personnel such that QCRs cannot be completed or amended by unauthorised persons.
Requirement of Subcont
Control Requirements to Subcontractor
7 REGULAR QUALITY CONT
7.1 Issuance of QC specifications
7.2
7.3
7.4
NSRP Complex
Field Quality Control Procedure
Inspector
Inspection will be carried out by inspectors of Contractor. They are responsible for all field inspection
in accordance with Inspection and Test Plan (ITP) approved by
Subcontractor’s activity from quality point of view,
immediately, and coordination with Subcontractor to close any nonconformity.
Qualification of QC Personnel
All QC activities for construction work shall be implemented by competent QC personnel in each
to keep acceptable quality level during all project period in construction.
training for Contractor QC personnel at the following time, but not limited to
(1) First engagement of project site
(2) Commencement of new insp
(3) Upon Employer
Contractor’s QC personnel shall be issued with Inspection Stamps that are unique to
personnel such that QCRs cannot be completed or amended by unauthorised persons.
Requirement of Subcont
Control Requirements to Subcontractor
REGULAR QUALITY CONT
Issuance of QC specifications
FQCM prepare
all project quality requirements. These documents are forwarded to
applicable documents to
7.2 Kick-off Meetings (After
FQCM may
critical construction
(1) To make sure
were in charge of
Subcontractor
(2) To confirm that
contract
Subcontractor
requirements.
7.3 Review and Approval of
Field QC Team
and Personnel
Subcontractor
Subcontractor
before related activity is
7.4 Pre-Inspection
Complex Project
Field Quality Control Procedure
Inspection will be carried out by inspectors of Contractor. They are responsible for all field inspection
in accordance with Inspection and Test Plan (ITP) approved by
Subcontractor’s activity from quality point of view,
immediately, and coordination with Subcontractor to close any nonconformity.
Qualification of QC Personnel
All QC activities for construction work shall be implemented by competent QC personnel in each
to keep acceptable quality level during all project period in construction.
training for Contractor QC personnel at the following time, but not limited to
(1) First engagement of project site
(2) Commencement of new insp
(3) Upon Employer’s request
s QC personnel shall be issued with Inspection Stamps that are unique to
personnel such that QCRs cannot be completed or amended by unauthorised persons.
Requirement of Subcontractor QC personnel shall be addressed in S
Control Requirements to Subcontractor
REGULAR QUALITY CONT
Issuance of QC specifications
QCM prepares and issue
all project quality requirements. These documents are forwarded to
applicable documents to
off Meetings (After
may participate in Kick
construction after
To make sure Subcontractor
n charge of th
Subcontractor’s Project Manager
To confirm that Subcontractor
contract, understand
Subcontractor will start the
requirements.
Review and Approval of
Team reviews
and Personnel Qualification,
Subcontractor.
Subcontractor is requested to submit these documents
before related activity is
Inspection Meeting (PIM)
Field Quality Control Procedure
Inspection will be carried out by inspectors of Contractor. They are responsible for all field inspection
in accordance with Inspection and Test Plan (ITP) approved by
Subcontractor’s activity from quality point of view,
immediately, and coordination with Subcontractor to close any nonconformity.
Qualification of QC Personnel
All QC activities for construction work shall be implemented by competent QC personnel in each
to keep acceptable quality level during all project period in construction.
training for Contractor QC personnel at the following time, but not limited to
(1) First engagement of project site
(2) Commencement of new inspection activity
s request
s QC personnel shall be issued with Inspection Stamps that are unique to
personnel such that QCRs cannot be completed or amended by unauthorised persons.
ractor QC personnel shall be addressed in S
Control Requirements to Subcontractor
REGULAR QUALITY CONTROL ACTIVITIES IN
Issuance of QC specifications
and issues QC documents listed in section 3
all project quality requirements. These documents are forwarded to
applicable documents to subcontract
off Meetings (After contract)
ticipate in Kick-off Meeting (KOM) with
after its subcontract is placed
Subcontractor’s Application Engineers / Sales Engineers, who
their proposals, correctly transfer the requirements to
’s Project Manager
Subcontractor’s Project Manager who actually execute the
, understand project requirements correctly and to ensure
will start the Subcontract
Review and Approval of Subcontractor
reviews Subcontractor
Qualification, to ensure that the Project requirements are correctly documented by
is requested to submit these documents
before related activity is commenced.
Meeting (PIM)
Inspection will be carried out by inspectors of Contractor. They are responsible for all field inspection
in accordance with Inspection and Test Plan (ITP) approved by
Subcontractor’s activity from quality point of view,
immediately, and coordination with Subcontractor to close any nonconformity.
All QC activities for construction work shall be implemented by competent QC personnel in each
to keep acceptable quality level during all project period in construction.
training for Contractor QC personnel at the following time, but not limited to
ection activity
s QC personnel shall be issued with Inspection Stamps that are unique to
personnel such that QCRs cannot be completed or amended by unauthorised persons.
ractor QC personnel shall be addressed in S
Control Requirements to Subcontractor”.
ROL ACTIVITIES IN
QC documents listed in section 3
all project quality requirements. These documents are forwarded to
subcontract.
off Meeting (KOM) with
its subcontract is placed
’s Application Engineers / Sales Engineers, who
proposals, correctly transfer the requirements to
’s Project Manager.
’s Project Manager who actually execute the
requirements correctly and to ensure
Subcontract based on the correct understanding of
Subcontractor’s documents
Subcontractor’s QC documents
to ensure that the Project requirements are correctly documented by
is requested to submit these documents
commenced.
Employer Doc. No.
Contractor Doc. No.
S
Inspection will be carried out by inspectors of Contractor. They are responsible for all field inspection
in accordance with Inspection and Test Plan (ITP) approved by
Subcontractor’s activity from quality point of view, reporting any finding during inspection to FQCM
immediately, and coordination with Subcontractor to close any nonconformity.
All QC activities for construction work shall be implemented by competent QC personnel in each
to keep acceptable quality level during all project period in construction.
training for Contractor QC personnel at the following time, but not limited to
s QC personnel shall be issued with Inspection Stamps that are unique to
personnel such that QCRs cannot be completed or amended by unauthorised persons.
ractor QC personnel shall be addressed in S
ROL ACTIVITIES IN CONSTRUCTION
QC documents listed in section 3
all project quality requirements. These documents are forwarded to
off Meeting (KOM) with Subcontractor
its subcontract is placed. The purpose of KOM is as follows
’s Application Engineers / Sales Engineers, who
proposals, correctly transfer the requirements to
’s Project Manager who actually execute the
requirements correctly and to ensure
based on the correct understanding of
’s documents
’s QC documents such as WPS/PQR, ITP, Method Statement,
to ensure that the Project requirements are correctly documented by
is requested to submit these documents early enough so that they are approved
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
Inspection will be carried out by inspectors of Contractor. They are responsible for all field inspection
in accordance with Inspection and Test Plan (ITP) approved by Employer
reporting any finding during inspection to FQCM
immediately, and coordination with Subcontractor to close any nonconformity.
All QC activities for construction work shall be implemented by competent QC personnel in each
to keep acceptable quality level during all project period in construction. Contractor will develop the
training for Contractor QC personnel at the following time, but not limited to
s QC personnel shall be issued with Inspection Stamps that are unique to
personnel such that QCRs cannot be completed or amended by unauthorised persons.
ractor QC personnel shall be addressed in S-000
CONSTRUCTION PHASE
QC documents listed in section 3. These documents include and reflect
all project quality requirements. These documents are forwarded to Subcontractor
Subcontractor, which
. The purpose of KOM is as follows
’s Application Engineers / Sales Engineers, who
proposals, correctly transfer the requirements to
’s Project Manager who actually execute the
requirements correctly and to ensure that
based on the correct understanding of
such as WPS/PQR, ITP, Method Statement,
to ensure that the Project requirements are correctly documented by
early enough so that they are approved
Contractor Doc. No.
0001V
Inspection will be carried out by inspectors of Contractor. They are responsible for all field inspection
Employer, monitoring of
reporting any finding during inspection to FQCM
immediately, and coordination with Subcontractor to close any nonconformity.
All QC activities for construction work shall be implemented by competent QC personnel in each
Contractor will develop the
training for Contractor QC personnel at the following time, but not limited to.
s QC personnel shall be issued with Inspection Stamps that are unique to a
personnel such that QCRs cannot be completed or amended by unauthorised persons.
000-1670-0002V
PHASE
These documents include and reflect
Subcontractor as parts of
, which is held for major or
. The purpose of KOM is as follows
’s Application Engineers / Sales Engineers, who
proposals, correctly transfer the requirements to
’s Project Manager who actually execute the
that
based on the correct understanding of
such as WPS/PQR, ITP, Method Statement,
to ensure that the Project requirements are correctly documented by
early enough so that they are approved
Rev.0
Page 6 of 21
Inspection will be carried out by inspectors of Contractor. They are responsible for all field inspection
, monitoring of
reporting any finding during inspection to FQCM
All QC activities for construction work shall be implemented by competent QC personnel in each party
Contractor will develop the
authorized QC
personnel such that QCRs cannot be completed or amended by unauthorised persons.
0002V”Quality
These documents include and reflect
as parts of
held for major or
. The purpose of KOM is as follows :
such as WPS/PQR, ITP, Method Statement,
to ensure that the Project requirements are correctly documented by
early enough so that they are approved
21
Inspection will be carried out by inspectors of Contractor. They are responsible for all field inspection
reporting any finding during inspection to FQCM
party
Contractor will develop the
QC
These documents include and reflect
such as WPS/PQR, ITP, Method Statement,
to ensure that the Project requirements are correctly documented by
INDRA
02-OCT-2013
7. NSRP
Title: Field Quality Control Procedure
7.5
7.6
7.7
NSRP Complex
Field Quality Control Procedure
Pre-Inspection Meeting (PIM)
otherwise agreed.
confirm that Subcontractor
PIM is final confirmation of
construction work
Requirement
Minutes of Meeting (MOM) for PIM should be completed, reviewed and signed by participants
before leaving
submitted to
Material Receiving I
Material receiving inspection at construction warehouse shall be carried out by material
in accordance with applicable specification. If
found, Contractor
Report (MER
“Nonconformity Control Procedure
Only materials accepted by the r
construction work, and such materials shall be handled with proper storage and preservation to
prevent unexpected damage, lost, deterioration, and substitution.
6 Material Identification a
Materials, parts, and components shall be clearly identified by marking, stencil, or
throughout fabrication, field assembly and installation in accordance with S
“Material Traceability
All piping bulk materials supplied by Contractor shall be
S-000-1360
including gaskets, stud bolts and nuts
pre-fabrication, installation, and completion.
Positive Material Identifi
3550-8440
Erection”to avoid
7.7 QC Monitoring
Contractor organize periodical QC
detail QC activity implemented at job site com
monitoring
(1) QC Personnel Control
(2) QC Document Control
(3) QC Record Control
(4) NCR Control
(5) Material Control
(6) Welding Control
Complex Project
Field Quality Control Procedure
Inspection Meeting (PIM)
otherwise agreed. The
confirm that Subcontractor
PIM is final confirmation of
construction work starts. Typical agenda of PIM is specified in S
Requirements to Subcontractor
Minutes of Meeting (MOM) for PIM should be completed, reviewed and signed by participants
before leaving meeting. A copy of MOM will be distributed to relevant sections, as well as
submitted to Employer.
Material Receiving Inspection
Material receiving inspection at construction warehouse shall be carried out by material
accordance with applicable specification. If
found, Contractor’s material control section will handle such
MER )or Field QC section will issue NCR in
onconformity Control Procedure
Only materials accepted by the r
construction work, and such materials shall be handled with proper storage and preservation to
prevent unexpected damage, lost, deterioration, and substitution.
Material Identification a
Materials, parts, and components shall be clearly identified by marking, stencil, or
throughout fabrication, field assembly and installation in accordance with S
Traceability Control Procedure for
All piping bulk materials supplied by Contractor shall be
1360-0004V “Specification
including gaskets, stud bolts and nuts
fabrication, installation, and completion.
Positive Material Identifi
8440-SP-0030 “Positive Material Identification
to avoid misuse
Monitoring
Contractor organize periodical QC
detail QC activity implemented at job site com
includes, but not limited to,
QC Personnel Control
QC Document Control
cord Control
NCR Control
Material Control
Welding Control
Field Quality Control Procedure
Inspection Meeting (PIM) shall be conducted
The PIM shall be conducted prior to the start of
confirm that Subcontractor understand
PIM is final confirmation of Subcontractor
starts. Typical agenda of PIM is specified in S
Subcontractor ”.
Minutes of Meeting (MOM) for PIM should be completed, reviewed and signed by participants
. A copy of MOM will be distributed to relevant sections, as well as
.
nspection
Material receiving inspection at construction warehouse shall be carried out by material
accordance with applicable specification. If
s material control section will handle such
or Field QC section will issue NCR in
onconformity Control Procedure for
Only materials accepted by the receiving inspection can be issued to Subcontractor for their
construction work, and such materials shall be handled with proper storage and preservation to
prevent unexpected damage, lost, deterioration, and substitution.
Material Identification and Traceability
Materials, parts, and components shall be clearly identified by marking, stencil, or
throughout fabrication, field assembly and installation in accordance with S
Control Procedure for
All piping bulk materials supplied by Contractor shall be
Specification for Identification
including gaskets, stud bolts and nuts
fabrication, installation, and completion.
Positive Material Identification (PMI) is performed at
Positive Material Identification
misuse of welding consumable.
Contractor organize periodical QC monitoring
detail QC activity implemented at job site com
includes, but not limited to,
QC Personnel Control
QC Document Control
shall be conducted
shall be conducted prior to the start of
understands all the quality requirements specified in the
Subcontractor’s understanding on project requirements before
starts. Typical agenda of PIM is specified in S
Minutes of Meeting (MOM) for PIM should be completed, reviewed and signed by participants
. A copy of MOM will be distributed to relevant sections, as well as
Material receiving inspection at construction warehouse shall be carried out by material
accordance with applicable specification. If any nonconformity, discrepancy
s material control section will handle such
or Field QC section will issue NCR in
for Construction Work
eceiving inspection can be issued to Subcontractor for their
construction work, and such materials shall be handled with proper storage and preservation to
prevent unexpected damage, lost, deterioration, and substitution.
nd Traceability
Materials, parts, and components shall be clearly identified by marking, stencil, or
throughout fabrication, field assembly and installation in accordance with S
Control Procedure for Piping
All piping bulk materials supplied by Contractor shall be
or Identification
including gaskets, stud bolts and nuts shall be checked by
fabrication, installation, and completion.
cation (PMI) is performed at
Positive Material Identification
of welding consumable.
monitoring to Subcontractor to verify whether Subcontractor
detail QC activity implemented at job site comply with
includes, but not limited to,
Employer Doc. No.
Contractor Doc. No.
S
shall be conducted with Subcontractors for construction work unless
shall be conducted prior to the start of
the quality requirements specified in the
’s understanding on project requirements before
starts. Typical agenda of PIM is specified in S
Minutes of Meeting (MOM) for PIM should be completed, reviewed and signed by participants
. A copy of MOM will be distributed to relevant sections, as well as
Material receiving inspection at construction warehouse shall be carried out by material
any nonconformity, discrepancy
s material control section will handle such
or Field QC section will issue NCR in accordance
Construction Work”.
eceiving inspection can be issued to Subcontractor for their
construction work, and such materials shall be handled with proper storage and preservation to
prevent unexpected damage, lost, deterioration, and substitution.
Materials, parts, and components shall be clearly identified by marking, stencil, or
throughout fabrication, field assembly and installation in accordance with S
Piping Construction Work
All piping bulk materials supplied by Contractor shall be colour
or Identification of Piping Materials
shall be checked by colour
cation (PMI) is performed at construction
Positive Material Identification of Alloy mate
of welding consumable.
to Subcontractor to verify whether Subcontractor
ply with project requirements.
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
with Subcontractors for construction work unless
shall be conducted prior to the start of work. The Purpose of
the quality requirements specified in the
’s understanding on project requirements before
starts. Typical agenda of PIM is specified in S-000-1670
Minutes of Meeting (MOM) for PIM should be completed, reviewed and signed by participants
. A copy of MOM will be distributed to relevant sections, as well as
Material receiving inspection at construction warehouse shall be carried out by material
any nonconformity, discrepancy
s material control section will handle such materials and issue
accordance with S-000
eceiving inspection can be issued to Subcontractor for their
construction work, and such materials shall be handled with proper storage and preservation to
prevent unexpected damage, lost, deterioration, and substitution.
Materials, parts, and components shall be clearly identified by marking, stencil, or
throughout fabrication, field assembly and installation in accordance with S
Construction Work”.
colour coded in accordance with
f Piping Materials”. Usage of correct materials
colour coding throughout piping
construction site in accordance with
of Alloy materials during Site Fabrication and
to Subcontractor to verify whether Subcontractor
project requirements.
Contractor Doc. No.
0001V
with Subcontractors for construction work unless
. The Purpose of
the quality requirements specified in the subcontract
’s understanding on project requirements before
1670-0002V “Quality
Minutes of Meeting (MOM) for PIM should be completed, reviewed and signed by participants
. A copy of MOM will be distributed to relevant sections, as well as
Material receiving inspection at construction warehouse shall be carried out by material
any nonconformity, discrepancy and/or
and issue Material Ex
000-1670-00
eceiving inspection can be issued to Subcontractor for their
construction work, and such materials shall be handled with proper storage and preservation to
Materials, parts, and components shall be clearly identified by marking, stencil, or colour
throughout fabrication, field assembly and installation in accordance with S-000-1670
coded in accordance with
. Usage of correct materials
coding throughout piping
site in accordance with
rials during Site Fabrication and
to Subcontractor to verify whether Subcontractor
project requirements. Each theme of QC
Rev.0
Page 7 of 21
with Subcontractors for construction work unless
. The Purpose of PIM is to
subcontract.
’s understanding on project requirements before
Quality Control
Minutes of Meeting (MOM) for PIM should be completed, reviewed and signed by participants
. A copy of MOM will be distributed to relevant sections, as well as
Material receiving inspection at construction warehouse shall be carried out by material controller
and/or damage are
Material Exception
0003V
eceiving inspection can be issued to Subcontractor for their
construction work, and such materials shall be handled with proper storage and preservation to
colour coding
1670-0004V
coded in accordance with
. Usage of correct materials
coding throughout piping
site in accordance with
rials during Site Fabrication and
to Subcontractor to verify whether Subcontractor’s
Each theme of QC
21
with Subcontractors for construction work unless
PIM is to
.
Control
controller
are
ception
coding
. Usage of correct materials
rials during Site Fabrication and
s
INDRA
02-OCT-2013
8. NSRP
Title: Field Quality Control Procedure
7.8
7.9
7.10
7.11 C
NSRP Complex
Field Quality Control Procedure
(7) NDE Control
FQCM makes a plan in
S-000-1670
against Subcontractor
7.8 Notification for Witness
Contractor requires
as specified in the approved ITP
Witness items
at site. In case that the inspection is planned
required, such as the
7.9 Witness Inspection
All inspection shall be conducted by Subcontractor and witnessed by Contractor and/or
Employer’s inspector in
Inspection, measuring, and test equipments shall be properly controlled by Subcontractor in
accordance with their procedure including storage, calibration, maintenance, and recording
approved by Contractor and
Inspection record for the witness in
completion of the inspection.
In case of reviewing documents instead of physical inspections, Subcontractor submits the
required documents to confirm acceptance of the applicable activity on time.
responsibility of submitting/coordinating to
7.10 Disposition
When nonconformity is found during the construction, Contractor instructs Subcontractor to
with such nonconformity in accordance with S
for Construction Work”. Subcontractor is required to submit the Nonconformity Report (NCR) to
Contractor for approval.
approval on NCR by
Subcontractor
nonconformities.
Confirmation and Control of QC Record
All QC record
developed system such as CMS and TOMAS.
(1) Construction Management System (CMS)
- Welding Status for Piping
- NDE and PWHT Status for Piping
- NDE Repair Ratio for Piping
- Piping Test Package Status
(2) Turnover Management System (TOMAS)
- Inspection Status for All Categories except Piping
- System Punch List
Complex Project
Field Quality Control Procedure
NDE Control
FQCM makes a plan in
1670-0002V “Quality Control
against Subcontractor’s construction activity and its status.
Notification for Witness
Contractor requires Subcontractor
as specified in the approved ITP
Witness items and 2 working days
In case that the inspection is planned
such as the inspection
itness Inspection / Document Review
All inspection shall be conducted by Subcontractor and witnessed by Contractor and/or
s inspector in
Inspection, measuring, and test equipments shall be properly controlled by Subcontractor in
accordance with their procedure including storage, calibration, maintenance, and recording
by Contractor and
Inspection record for the witness in
completion of the inspection.
In case of reviewing documents instead of physical inspections, Subcontractor submits the
required documents to confirm acceptance of the applicable activity on time.
responsibility of submitting/coordinating to
Disposition (Correction)
When nonconformity is found during the construction, Contractor instructs Subcontractor to
with such nonconformity in accordance with S
for Construction Work”. Subcontractor is required to submit the Nonconformity Report (NCR) to
Contractor for approval.
approval on NCR by Contractor
Subcontractor shall also take corrective actions to prevent recurrence of same or similar
nonconformities.
onfirmation and Control of QC Record
All QC records with Contractor and/or
developed system such as CMS and TOMAS.
Construction Management System (CMS)
Welding Status for Piping
NDE and PWHT Status for Piping
NDE Repair Ratio for Piping
Piping Test Package Status
Turnover Management System (TOMAS)
Inspection Status for All Categories except Piping
System Punch List
Field Quality Control Procedure
FQCM makes a plan in accordance
Quality Control
s construction activity and its status.
Notification for Witness Inspection
Subcontractor to submit the inspection notice for inspection and test activities
as specified in the approved ITP 1 working day in advance for an inspection
and 2 working days in advance for
In case that the inspection is planned
inspection and test
Document Review
All inspection shall be conducted by Subcontractor and witnessed by Contractor and/or
s inspector in accordance
Inspection, measuring, and test equipments shall be properly controlled by Subcontractor in
accordance with their procedure including storage, calibration, maintenance, and recording
by Contractor and Employer
Inspection record for the witness inspection is reviewed and signed by the inspector soon after
completion of the inspection.
In case of reviewing documents instead of physical inspections, Subcontractor submits the
required documents to confirm acceptance of the applicable activity on time.
responsibility of submitting/coordinating to
(Correction) and Corrective
When nonconformity is found during the construction, Contractor instructs Subcontractor to
with such nonconformity in accordance with S
for Construction Work”. Subcontractor is required to submit the Nonconformity Report (NCR) to
Contractor for approval. Subcontractors shall perform correction
Contractor.
shall also take corrective actions to prevent recurrence of same or similar
onfirmation and Control of QC Record
ntractor and/or
developed system such as CMS and TOMAS.
Construction Management System (CMS)
Welding Status for Piping
NDE and PWHT Status for Piping
NDE Repair Ratio for Piping
Piping Test Package Status
Turnover Management System (TOMAS)
Inspection Status for All Categories except Piping
System Punch List
accordance with the detailed elements of QC
Quality Control Requirements
s construction activity and its status.
Inspection
to submit the inspection notice for inspection and test activities
1 working day in advance for an inspection
in advance for
In case that the inspection is planned out of job site
and test at the piping
Document Review
All inspection shall be conducted by Subcontractor and witnessed by Contractor and/or
accordance with applicable ITP.
Inspection, measuring, and test equipments shall be properly controlled by Subcontractor in
accordance with their procedure including storage, calibration, maintenance, and recording
Employer.
spection is reviewed and signed by the inspector soon after
In case of reviewing documents instead of physical inspections, Subcontractor submits the
required documents to confirm acceptance of the applicable activity on time.
responsibility of submitting/coordinating to Employer
and Corrective Action of Nonconformity
When nonconformity is found during the construction, Contractor instructs Subcontractor to
with such nonconformity in accordance with S-000
for Construction Work”. Subcontractor is required to submit the Nonconformity Report (NCR) to
Subcontractors shall perform correction
shall also take corrective actions to prevent recurrence of same or similar
onfirmation and Control of QC Record
ntractor and/or Employer
developed system such as CMS and TOMAS. T
Construction Management System (CMS)
NDE and PWHT Status for Piping
Turnover Management System (TOMAS)
Inspection Status for All Categories except Piping
Employer Doc. No.
Contractor Doc. No.
S
the detailed elements of QC
equirements to Subcontractor
s construction activity and its status.
to submit the inspection notice for inspection and test activities
1 working day in advance for an inspection
in advance for an inspection
out of job site
the piping pre-fabrication area
All inspection shall be conducted by Subcontractor and witnessed by Contractor and/or
with applicable ITP.
Inspection, measuring, and test equipments shall be properly controlled by Subcontractor in
accordance with their procedure including storage, calibration, maintenance, and recording
spection is reviewed and signed by the inspector soon after
In case of reviewing documents instead of physical inspections, Subcontractor submits the
required documents to confirm acceptance of the applicable activity on time.
Employer of those documents.
ction of Nonconformity
When nonconformity is found during the construction, Contractor instructs Subcontractor to
000-1670-0003V
for Construction Work”. Subcontractor is required to submit the Nonconformity Report (NCR) to
Subcontractors shall perform correction
shall also take corrective actions to prevent recurrence of same or similar
Employer’s approval shall be
The following data is controlled in each system.
Inspection Status for All Categories except Piping
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
the detailed elements of QC monitoring
Subcontractor”considering suitable time
to submit the inspection notice for inspection and test activities
1 working day in advance for an inspection
an inspection for Employer
out of job site , Notification 1 week in advance is
fabrication area
All inspection shall be conducted by Subcontractor and witnessed by Contractor and/or
Inspection, measuring, and test equipments shall be properly controlled by Subcontractor in
accordance with their procedure including storage, calibration, maintenance, and recording
spection is reviewed and signed by the inspector soon after
In case of reviewing documents instead of physical inspections, Subcontractor submits the
required documents to confirm acceptance of the applicable activity on time.
of those documents.
ction of Nonconformity
When nonconformity is found during the construction, Contractor instructs Subcontractor to
0003V “Nonconformity Control Procedure
for Construction Work”. Subcontractor is required to submit the Nonconformity Report (NCR) to
Subcontractors shall perform correction (implement disposition) only after
shall also take corrective actions to prevent recurrence of same or similar
shall be registered into Contractor
he following data is controlled in each system.
Contractor Doc. No.
0001V
monitoring specified in 7.
considering suitable time
to submit the inspection notice for inspection and test activities
1 working day in advance for an inspection for only Contractor
for Employer’s Witness/Hold items
, Notification 1 week in advance is
fabrication area.
All inspection shall be conducted by Subcontractor and witnessed by Contractor and/or
Inspection, measuring, and test equipments shall be properly controlled by Subcontractor in
accordance with their procedure including storage, calibration, maintenance, and recording
spection is reviewed and signed by the inspector soon after
In case of reviewing documents instead of physical inspections, Subcontractor submits the
required documents to confirm acceptance of the applicable activity on time. Contractor has a
of those documents.
When nonconformity is found during the construction, Contractor instructs Subcontractor to
“Nonconformity Control Procedure
for Construction Work”. Subcontractor is required to submit the Nonconformity Report (NCR) to
(implement disposition) only after
shall also take corrective actions to prevent recurrence of same or similar
registered into Contractor
he following data is controlled in each system.
Rev.0
Page 8 of 21
specified in 7.4
considering suitable time
to submit the inspection notice for inspection and test activities
for only Contractor
s Witness/Hold items
, Notification 1 week in advance is
All inspection shall be conducted by Subcontractor and witnessed by Contractor and/or
Inspection, measuring, and test equipments shall be properly controlled by Subcontractor in
accordance with their procedure including storage, calibration, maintenance, and recording
spection is reviewed and signed by the inspector soon after
In case of reviewing documents instead of physical inspections, Subcontractor submits the
Contractor has a
When nonconformity is found during the construction, Contractor instructs Subcontractor to deal
“Nonconformity Control Procedure
for Construction Work”. Subcontractor is required to submit the Nonconformity Report (NCR) to
(implement disposition) only after
shall also take corrective actions to prevent recurrence of same or similar
registered into Contractor’s own
he following data is controlled in each system.
21
of
to submit the inspection notice for inspection and test activities
s Witness/Hold items
deal
“Nonconformity Control Procedure
(implement disposition) only after
s own
INDRA
02-OCT-2013
9. NSRP
Title: Field Quality Control Procedure
7.12
8
8.1
(1)
(2)
(3)
(4)
(5)
8.2
8.3
NSRP Complex
Field Quality Control Procedure
Detailed handling procedure for each system is specified separately.
All original QC
Subcontractor after registration into related system, and submitted to
review as final documentation in accordance with applicable specification.
QCRs are as per [ Attachment
7.12 System Handover
After all construction work is completed, all inspection is completed, and all outstanding such as
NCR and system punch items are closed, Contractor issue system handover notice to
accordance with applicable specification
8 LIAISON WITH
8.1 Meeting
The periodical QC coordination meeting
points, to share
issues related to quality control.
(1) Inspection Schedule
(2) Subcontractor Document
(3) Welder Qualification
(4) Open NCR
(5) Other Area of Concern
8.2 Reporting
The following reports
(1) NCR Status
(2) Quality Status (NDE reject ratio, NDE backlog, Test Package) Report
8.3 Notification
For Employer
1 working day
inspection out of
Inspection Notification Form is as [ Attachment
Complex Project
Field Quality Control Procedure
Detailed handling procedure for each system is specified separately.
All original QC records with Contractor and/or
Subcontractor after registration into related system, and submitted to
review as final documentation in accordance with applicable specification.
QCRs are as per [ Attachment
System Handover
After all construction work is completed, all inspection is completed, and all outstanding such as
NCR and system punch items are closed, Contractor issue system handover notice to
accordance with applicable specification
LIAISON WITH EMPLOYER
The periodical QC coordination meeting
share their status, and to exchange views on inspection, quality control, and general
issues related to quality control.
Inspection Schedule
Subcontractor Document
Welder Qualification
Open NCR
Other Area of Concern
ollowing reports are
NCR Status
Quality Status (NDE reject ratio, NDE backlog, Test Package) Report
Notification
Employer’s witness and hold points, Contractor submits the
1 working day in advance
inspection out of construction
Inspection Notification Form is as [ Attachment
Field Quality Control Procedure
Detailed handling procedure for each system is specified separately.
records with Contractor and/or
Subcontractor after registration into related system, and submitted to
review as final documentation in accordance with applicable specification.
QCRs are as per [ Attachment-3].
After all construction work is completed, all inspection is completed, and all outstanding such as
NCR and system punch items are closed, Contractor issue system handover notice to
accordance with applicable specification
EMPLOYER
The periodical QC coordination meeting
status, and to exchange views on inspection, quality control, and general
issues related to quality control.
Inspection Schedule
Subcontractor Document e.g. ITP, WPS/PQR and Method Statement
Welder Qualification
Other Area of Concern
are submitted
Quality Status (NDE reject ratio, NDE backlog, Test Package) Report
’s witness and hold points, Contractor submits the
in advance for an inspection at
construction site as mentioned in above Para.
Inspection Notification Form is as [ Attachment
Detailed handling procedure for each system is specified separately.
records with Contractor and/or Employer
Subcontractor after registration into related system, and submitted to
review as final documentation in accordance with applicable specification.
After all construction work is completed, all inspection is completed, and all outstanding such as
NCR and system punch items are closed, Contractor issue system handover notice to
accordance with applicable specification.
The periodical QC coordination meeting with Employer
status, and to exchange views on inspection, quality control, and general
e.g. ITP, WPS/PQR and Method Statement
submitted periodically
Quality Status (NDE reject ratio, NDE backlog, Test Package) Report
’s witness and hold points, Contractor submits the
for an inspection at construction
site as mentioned in above Para.
Inspection Notification Form is as [ Attachment-4] and its documen
Employer Doc. No.
Contractor Doc. No.
S
Detailed handling procedure for each system is specified separately.
Employer’s approval shall be compiled by
Subcontractor after registration into related system, and submitted to
review as final documentation in accordance with applicable specification.
After all construction work is completed, all inspection is completed, and all outstanding such as
NCR and system punch items are closed, Contractor issue system handover notice to
Employer is held to discuss and address the
status, and to exchange views on inspection, quality control, and general
e.g. ITP, WPS/PQR and Method Statement
to Emplyer
Quality Status (NDE reject ratio, NDE backlog, Test Package) Report
’s witness and hold points, Contractor submits the
construction site and
site as mentioned in above Para.
4] and its documen
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
Detailed handling procedure for each system is specified separately.
s approval shall be compiled by
Subcontractor after registration into related system, and submitted to Empl
review as final documentation in accordance with applicable specification.
After all construction work is completed, all inspection is completed, and all outstanding such as
NCR and system punch items are closed, Contractor issue system handover notice to
held to discuss and address the
status, and to exchange views on inspection, quality control, and general
e.g. ITP, WPS/PQR and Method Statement
Quality Status (NDE reject ratio, NDE backlog, Test Package) Report
’s witness and hold points, Contractor submits the NOTIFICATION for INSPECTION
site and 1 week
site as mentioned in above Para.7.8.
4] and its document flow is shown in [ Attachment
Contractor Doc. No.
0001V
s approval shall be compiled by
Employer through Contractor
review as final documentation in accordance with applicable specification. A table of anticipated
After all construction work is completed, all inspection is completed, and all outstanding such as
NCR and system punch items are closed, Contractor issue system handover notice to
held to discuss and address the
status, and to exchange views on inspection, quality control, and general
e.g. ITP, WPS/PQR and Method Statement
Quality Status (NDE reject ratio, NDE backlog, Test Package) Report
OTIFICATION for INSPECTION
1 week in advance for an
t flow is shown in [ Attachment
Rev.0
Page 9 of 21
s approval shall be compiled by
through Contractor
e of anticipated
After all construction work is completed, all inspection is completed, and all outstanding such as
NCR and system punch items are closed, Contractor issue system handover notice to Employer
held to discuss and address the following
status, and to exchange views on inspection, quality control, and general
OTIFICATION for INSPECTION
in advance for an
t flow is shown in [ Attachment
21
through Contractor’s
e of anticipated
After all construction work is completed, all inspection is completed, and all outstanding such as
yer in
following
OTIFICATION for INSPECTION
t flow is shown in [ Attachment-5].
INDRA
02-OCT-2013
10. NSRP
Title: Field Quality Control Procedure
HSSE Mgr
J. Furumoto
FIELD ENG'G
Field En
NSRP Complex
Field Quality Control Procedure
HSSE
HSSE Mgr
J. Furumoto
FIELD ENG'G
Field Eng'g Mgr
Complex Project
Field Quality Control Procedure
TECHNICAL
Field Technical Mgr
FIELD QC
Field QC Mgr
Field Quality Control Procedure
ATTACHMENT
TECHNICAL
Field Technical Mgr
FIELD QC
Field QC Mgr
H. Ishiga
ATTACHMENT-1 ORGANIZATION
SITE DIRECTOR
T.Hayashi
CONTROL
Field CTRL Mgr
K. Inoue
QC Engineers
Welding Controller
System Operator
ZONE Contractor's QC
Employer Doc. No.
Contractor Doc. No.
S
ORGANIZATION
SITE DIRECTOR
T.Hayashi
CONTROL
Field CTRL Mgr
K. Inoue
HAND OVER
Hand Over Mgr
QC Engineers
Welding Controller
System Operator
ZONE Contractor's QC
Subcontractor's QC
NDE Subcontractor
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
ORGANIZATION
OPERATION
Business Mgr
T. Hirano
HAND OVER
Hand Over Mgr
QC Engineers
Welding Controller
System Operator
ZONE Contractor's QC
Subcontractor's QC
NDE Subcontractor
Contractor Doc. No.
0001V
OPERATION
Business Mgr
T. Hirano
Subcontractor's QC
NDE Subcontractor
Rev.0
Page 10 of
COMMISSIONING
Commissioning
Mgr
of 21
COMMISSIONING
Commissioning
INDRA
02-OCT-2013
11. NSRP
Title: Field Quality Control Procedure
Category
Sewer & Drainage
Civil
Steel Structure
Fireproofing
Building
Building
Building
Building
Static Equipment
Tank
Rotary Machinery
Piping
Piping
Piping
Piping
Instrumentation
Instrumentation
Instrumentation
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
NSRP Complex
Field Quality Control Procedure
Category
Sewer & Drainage
Steel Structure
Fireproofing
Building
Building
Building
Building
Static Equipment
Rotary Machinery
Instrumentation
Instrumentation
Instrumentation
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Electrical
Complex Project
Field Quality Control Procedure
ATTACHMENT
ITP for Sewer & Drainages
ITP for Civil Works
ITP for Steel Structure Erection
ITP for Fireproofing
ITP for Building Exterior Finishing Works
ITP for Building Interior Finishing Works
ITP for Plumbing Installation
ITP for HVAC Installation
ITP for Static Equipment Erection
ITP for Tank
ITP for Installation Of Rotary Machinery
ITP for Piping Work
ITP for Pressure Relief Valve
ITP for FRP Piping
ITP for Installation of GRE Piping
ITP for Instrument Installation
ITP for Instrument Calibration and Testing
ITP for Fabrication of Instrument Stanchion &
panel Support Frame
ITP for Electrical Work
ITP for Installation,
Cables
ITP for Installation of Cable Trays and U/G Conduits
ITP for Gounding and Lighting Protection System
ITP for Cathodic Protection for U/G Piping
ITP for Lighting System
ITP for Small Power Distribution System
ITP for Testing of Electrical Motors
ITP for Capacitor Bank
ITP for Installation and Testing of Power Transformer
Field Quality Control Procedure
ATTACHMENT
ITP for Sewer & Drainages
ITP for Civil Works
ITP for Steel Structure Erection
Fireproofing
ITP for Building Exterior Finishing Works
ITP for Building Interior Finishing Works
ITP for Plumbing Installation
ITP for HVAC Installation
ITP for Static Equipment Erection
ITP for Tank
ITP for Installation Of Rotary Machinery
ITP for Piping Work
ITP for Pressure Relief Valve
ITP for FRP Piping
ITP for Installation of GRE Piping
ITP for Instrument Installation
ITP for Instrument Calibration and Testing
ITP for Fabrication of Instrument Stanchion &
panel Support Frame
ITP for Electrical Work
ITP for Installation, Jointing,
ITP for Installation of Cable Trays and U/G Conduits
ITP for Gounding and Lighting Protection System
ITP for Cathodic Protection for U/G Piping
ITP for Lighting System
ITP for Small Power Distribution System
ITP for Testing of Electrical Motors
ITP for Capacitor Bank
ITP for Installation and Testing of Power Transformer
ATTACHMENT-2 A LIST OF ANTICIPATE
Title
ITP for Sewer & Drainages
ITP for Steel Structure Erection
ITP for Building Exterior Finishing Works
ITP for Building Interior Finishing Works
ITP for Plumbing Installation
ITP for HVAC Installation
ITP for Static Equipment Erection
ITP for Installation Of Rotary Machinery
ITP for Pressure Relief Valve
ITP for Installation of GRE Piping
ITP for Instrument Installation
ITP for Instrument Calibration and Testing
ITP for Fabrication of Instrument Stanchion &
panel Support Frame
ITP for Electrical Work
Jointing, Termination and Testing of Electrical
ITP for Installation of Cable Trays and U/G Conduits
ITP for Gounding and Lighting Protection System
ITP for Cathodic Protection for U/G Piping
ITP for Lighting System
ITP for Small Power Distribution System
ITP for Testing of Electrical Motors
ITP for Capacitor Bank
ITP for Installation and Testing of Power Transformer
Employer Doc. No.
Contractor Doc. No.
S
A LIST OF ANTICIPATE
Title
ITP for Building Exterior Finishing Works
ITP for Building Interior Finishing Works
ITP for Static Equipment Erection
ITP for Installation Of Rotary Machinery
ITP for Instrument Calibration and Testing
ITP for Fabrication of Instrument Stanchion &
Termination and Testing of Electrical
ITP for Installation of Cable Trays and U/G Conduits
ITP for Gounding and Lighting Protection System
ITP for Cathodic Protection for U/G Piping
ITP for Small Power Distribution System
ITP for Testing of Electrical Motors
ITP for Installation and Testing of Power Transformer
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
A LIST OF ANTICIPATED ITPs
ITP for Fabrication of Instrument Stanchion & Junction Box/Local
Termination and Testing of Electrical
ITP for Installation of Cable Trays and U/G Conduits
ITP for Gounding and Lighting Protection System
ITP for Installation and Testing of Power Transformer
Contractor Doc. No.
0001V
Junction Box/Local
Termination and Testing of Electrical
Rev.0
Page 11 of
Sample ITP No.
1000-001
2000-001
3000-001
3000-101
4000-101
4000-201
4000-301
4000-401
5000-301
5000-401
5000-501
6000-001
6000-101
6000-201
6000-301
7000-001
7000-002
7000-003
8000-001
8000-002
8000-003
8000-004
8000-005
8000-006
8000-007
8000-008
8000-009
8000-010
of 21
Sample ITP No.
001
001
001
101
101
201
301
401
301
401
501
001
101
201
301
001
002
003
001
002
003
004
005
006
007
008
009
010
INDRA
02-OCT-2013
12. NSRP
Title: Field Quality Control Procedure
Category
Electrical
Electrical
Electrical
Electrical
Insulation
Paint
NSRP Complex
Field Quality Control Procedure
Category
Electrical
Electrical
Electrical
Electrical
Insulation
Complex Project
Field Quality Control Procedure
ITP for Switchgear and Motor Control Centers
ITP for Installation of Busducts
ITP for Batteries , Charger and UPS
ITP for Grounding Resister
ITP for Insulation Work
ITP for Painting Work
Field Quality Control Procedure
ITP for Switchgear and Motor Control Centers
ITP for Installation of Busducts
ITP for Batteries , Charger and UPS
ITP for Grounding Resister
ITP for Insulation Work
ITP for Painting Work
Title
ITP for Switchgear and Motor Control Centers
ITP for Installation of Busducts
ITP for Batteries , Charger and UPS
ITP for Grounding Resister
ITP for Insulation Work
ITP for Painting Work
Employer Doc. No.
Contractor Doc. No.
S
Title
ITP for Switchgear and Motor Control Centers
ITP for Batteries , Charger and UPS
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
ITP for Switchgear and Motor Control Centers
Contractor Doc. No.
0001V
Rev.0
Page 12 of
Sample ITP No.
8000-011
8000-012
8000-013
8000-014
9000-101
9000-201
of 21
Sample ITP No.
011
012
013
014
101
201
INDRA
02-OCT-2013
13. NSRP
Title: Field Quality Control Procedure
Category
Sewer & Drainage
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Civil
Steel Structure
Steel Structure
Steel Structure
Fireproofing
Fireproofing
Fireproofing
Building
Building
Building
Building
Building
Building
Building
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
NSRP Complex
Field Quality Control Procedure
Category
Sewer & Drainage
Steel Structure
Steel Structure
Steel Structure
Fireproofing
Fireproofing
Fireproofing
Building
Building
Building
Building
Building
Building
Building
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Static Equipment
Equipment
Complex Project
Field Quality Control Procedure
ATTACHMENT
Inspection Report for Sewer Piping and Wrapping
Inspection Report for Pre
Concrete Docket
Test Report for
Inspection Report for Concrete Strength
Inspection Report Field Density Test
Inspection Report for Paving
Inspection Report for Excavation
Inspection Report
Inspection Report for Backfilling
Inspection Report for Grouting Work
Civil Release Notice for Equipment Foundation
Inspection Report for Steel Structures (1/2)
Inspection Report for Steel Structures (2/2) (Floor, Ladder,
Star, Handrail)
Inspection Report for Steel Structures (Inclination, Elevat’n)
Inspection Report for
Inspection Report Pouring Concrete of Fire
Inspection Report for After
Celling Inspection Report
Wall/Partition Inspection Report
Floor Inspection Report
Door & Window Inspection Report
External Wall Inspection Report
Piping Inspection Report
HVAC Inspection
Inspection Report for Vessel (Vertical)
Inspection Report for Vessel (Horizontal)
Inspection Report for Heat Exchanger (Horizontal)
Inspection Report for Stacked Heat Exchanger
Inspection Report for Heat Exchanger (Vertical)
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Air Cooled
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Equipment Internal
Inspection Report for Tray Installation
Field Quality Control Procedure
ATTACHMENT
Inspection Report for Sewer Piping and Wrapping
Inspection Report for Pre
Concrete Docket
Test Report for Compression Test
Inspection Report for Concrete Strength
Inspection Report Field Density Test
Inspection Report for Paving
Inspection Report for Excavation
Inspection Report for Excavation
Inspection Report for Backfilling
Inspection Report for Grouting Work
Civil Release Notice for Equipment Foundation
Inspection Report for Steel Structures (1/2)
Inspection Report for Steel Structures (2/2) (Floor, Ladder,
Star, Handrail)
Inspection Report for Steel Structures (Inclination, Elevat’n)
Inspection Report for Pre
Inspection Report Pouring Concrete of Fire
Inspection Report for After
Celling Inspection Report
Wall/Partition Inspection Report
Floor Inspection Report
Door & Window Inspection Report
External Wall Inspection Report
Piping Inspection Report
HVAC Inspection Report
Inspection Report for Vessel (Vertical)
Inspection Report for Vessel (Horizontal)
Inspection Report for Heat Exchanger (Horizontal)
Inspection Report for Stacked Heat Exchanger
Inspection Report for Heat Exchanger (Vertical)
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Air Cooled
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Equipment Internal
Inspection Report for Tray Installation
ATTACHMENT-3 A TABLE OF ANTICIPAT
Title
Inspection Report for Sewer Piping and Wrapping
Inspection Report for Pre-Concreting
Compression Test
Inspection Report for Concrete Strength
Inspection Report Field Density Test
Inspection Report for Paving
Inspection Report for Excavation
for Excavation
Inspection Report for Backfilling
Inspection Report for Grouting Work
Civil Release Notice for Equipment Foundation
Inspection Report for Steel Structures (1/2)
Inspection Report for Steel Structures (2/2) (Floor, Ladder,
Inspection Report for Steel Structures (Inclination, Elevat’n)
Pre-Pouring Fire
Inspection Report Pouring Concrete of Fire
Inspection Report for After-Pouring Fire
Celling Inspection Report
Wall/Partition Inspection Report
Floor Inspection Report
Door & Window Inspection Report
External Wall Inspection Report
Piping Inspection Report
Report
Inspection Report for Vessel (Vertical)
Inspection Report for Vessel (Horizontal)
Inspection Report for Heat Exchanger (Horizontal)
Inspection Report for Stacked Heat Exchanger
Inspection Report for Heat Exchanger (Vertical)
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Equipment Internal
Inspection Report for Tray Installation
Employer Doc. No.
Contractor Doc. No.
S
A TABLE OF ANTICIPAT
Inspection Report for Sewer Piping and Wrapping
Concreting
Inspection Report for Concrete Strength
Inspection Report Field Density Test
Inspection Report for Grouting Work
Civil Release Notice for Equipment Foundation
Inspection Report for Steel Structures (1/2) (Main Frame)
Inspection Report for Steel Structures (2/2) (Floor, Ladder,
Inspection Report for Steel Structures (Inclination, Elevat’n)
Pouring Fire-Proofing Concrete
Inspection Report Pouring Concrete of Fire-Proofing
Pouring Fire-Proofing Concrete
Inspection Report for Vessel (Vertical)
Inspection Report for Vessel (Horizontal)
Inspection Report for Heat Exchanger (Horizontal)
Inspection Report for Stacked Heat Exchanger
Inspection Report for Heat Exchanger (Vertical)
Inspection Report for Air Cooled Heat Exchanger
Heat Exchanger
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Equipment Internal
Inspection Report for Tray Installation
Employer Doc. No.
Contractor Doc. No.
S-000-1670-0001V
A TABLE OF ANTICIPATED QCR
Inspection Report for Sewer Piping and Wrapping
(Main Frame)
Inspection Report for Steel Structures (2/2) (Floor, Ladder,
Inspection Report for Steel Structures (Inclination, Elevat’n)
Proofing Concrete
Proofing
Proofing Concrete
Inspection Report for Heat Exchanger (Horizontal)
Inspection Report for Heat Exchanger (Vertical)
Inspection Report for Air Cooled Heat Exchanger
Heat Exchanger
Inspection Report for Air Cooled Heat Exchanger
Inspection Report for Air Cooled Heat Exchanger
Contractor Doc. No.
0001V
ED QCRs
Report Form No.
1000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
2000
3000
3000
Inspection Report for Steel Structures (Inclination, Elevat’n) 3000
3000
3000
3000
4000
4000
4000
4000
4000
4000
4000
5000
5000
5000
5000
5000
5000
5000
5000
5000
5000
5000
Rev.0
Page 13 of
Report Form No.
1000-001
2000-001
2000-002
2000-003
2000-004
2000-005
2000-006
2000-007
2000-008
2000-009
2000-010
2000-011
3000-001
3000-002
3000-003
3000-101
3000-102
3000-103
4000-003
4000-004
4000-005
4000-006
4000-101
4000-201
4000-301
5000-101
5000-105
5000-301
5000-303
5000-305
5000-307
5000-308
5000-309
5000-310
5000-201
5000-202
of 21
Report Form No.
INDRA
02-OCT-2013