1
Omar Mohamed El-Ezbawy
Building 126 – district 8 – side 3, 6th
of October
+20238895486 / +201277637762
omar.m.elezbawy@gmail.com
Objective
Aimingtobe employedinthefieldof Planning–ProjectsManagementfieldtocapitalize myprofessional
as well asmypersonal skills.Seekinganopportunitytodevelopmyexperience,toinvesthardworkinaposition
that further grows potential into a professional career.
Experience
January 2019 – Present Planning & Projects Control Manager (Mitsubishi Electric Co.)
 Planning and monitoring all company projects
 RiskAssessmentboardmember
 MS Project Server 2013 implementation process manager assistant
 Traineron MS Project& Primavera programs
 ReportingtoCEO
 Making Forecastingplansformanpowertooptimizeutilization
 ProcessimprovementandSafetyupdatingandtraining
 Maintenance MonitoringSystemimplementation
 2019 maintenance planandscheduling
 SAPImplementationProjectPlanner-coordinator
 ResourcesEfficiencyandEffectivenessMonitoring
 ProjectsCostControl
 Technical TrainingAdvisoraccordingtopersonnelworkanalysis
July2016 – Dec. 2018 Planning &Monitoring Section-Head (Mitsubishi Electric Co.)
 Planning and monitoring all company projects
 RiskAssessmentboardmember
 MS Project Server 2013 implementation process manager assistant
 Traineron MS Project& Primaveraprograms
 Making Forecastingplansformanpowertooptimizeutilization
 ProcessimprovementandSafetyupdatingandtraining
 Maintenance MonitoringSystemimplementation
 2018 maintenance planandscheduling
 SAPImplementationProjectPlanner-coordinator
2
Jan 2014 –July 2016 Senior Projects Engineer (Giza Projects Company)
 Head of Lockheed Martin Project in Egypt
o Architectural drawings review and monitoring over project
o Construction and infrastructure drawings review and monitoring
over project
o Assigning sub-contractors and following
 Designerof stainlesssteelfirefightingboundforFMcertificationat
PepsiCo “ChipsyTanash”facility
 Site engineer for Chipsy Tanash bound project
 ProjectengineerforSolarsystemsandUPS systemsintegrationtoall
companyoffices
 Site engineerforEgyptAirtraining centerproject.
June 2012 - Jan 2014 Production /Site Engineer (Kemet Industries)
 Facility re-planning and production line modification
 Full work analysis to man power
 Designing simulation to the production line
 Reducing time and scrap cost by 20%
 Designingmoduleaccordingto ISOsystemtomanage suppliers
relations
 Reducingleadtime andraw materialscost
 Installing30+ sitestelecommunicationtowersfrom9:80 meters
Feb 2011 – Nov 2011 Trainee (Aal-Kassem factory for metal Industries)
 Designing and making Workshop drawings using NX6
 Managing man power distribution
Education
 MBA Candidate at AASTM(2018-2020)
 MSA Universitygraduate validatedby Universityof Greenwich, UnitedKingdom(August2011)
 Bachelor of Industrial Systems Engineering
 GraduationProject:Designingandmanufacturingof Vertical Carousel Storage/Retrieval System
 Graduation Project Grade: Excellent
 Member at Federation of Arab Engineers
Technical training
 PMP ProjectManagementProfessionalE-learning,2013
 Six sigmawhite beltE-learning,2014
 PV off grid systemdesignercertifiedfromSEDA organization2014
 Fundamentalsof health,safetyandenvironmental control (OSHA 010) certifiedfromAUC –ESS
Department2015
 OSHA General industrysafetyandhealthtraining(OSHA 020) certifiedfromAUC –ESS Department
2015
3
Personal skills
 Computer:
 Excellentknowledge of MSoffice
 CNCprogramming-manufacturing
 CAD-CAMDesigningusingUGS6
 ArenaProcessSimulation
 MS Project& MS Projectserver
 Mini-Tab
 LinkPlanner
 Primavera
 SQL server
 Aggregate planning( supply –Demand)
 Language: Arabic: mothertongue
English:fluent
French:fair
Personal Information
 Birth date: 24/11/1988
 Birth place: Cairo
 Gender:Male
 Religion:Muslim
 Marital status: Married
 Militarystatus: Exempted

Resume

  • 1.
    1 Omar Mohamed El-Ezbawy Building126 – district 8 – side 3, 6th of October +20238895486 / +201277637762 omar.m.elezbawy@gmail.com Objective Aimingtobe employedinthefieldof Planning–ProjectsManagementfieldtocapitalize myprofessional as well asmypersonal skills.Seekinganopportunitytodevelopmyexperience,toinvesthardworkinaposition that further grows potential into a professional career. Experience January 2019 – Present Planning & Projects Control Manager (Mitsubishi Electric Co.)  Planning and monitoring all company projects  RiskAssessmentboardmember  MS Project Server 2013 implementation process manager assistant  Traineron MS Project& Primavera programs  ReportingtoCEO  Making Forecastingplansformanpowertooptimizeutilization  ProcessimprovementandSafetyupdatingandtraining  Maintenance MonitoringSystemimplementation  2019 maintenance planandscheduling  SAPImplementationProjectPlanner-coordinator  ResourcesEfficiencyandEffectivenessMonitoring  ProjectsCostControl  Technical TrainingAdvisoraccordingtopersonnelworkanalysis July2016 – Dec. 2018 Planning &Monitoring Section-Head (Mitsubishi Electric Co.)  Planning and monitoring all company projects  RiskAssessmentboardmember  MS Project Server 2013 implementation process manager assistant  Traineron MS Project& Primaveraprograms  Making Forecastingplansformanpowertooptimizeutilization  ProcessimprovementandSafetyupdatingandtraining  Maintenance MonitoringSystemimplementation  2018 maintenance planandscheduling  SAPImplementationProjectPlanner-coordinator
  • 2.
    2 Jan 2014 –July2016 Senior Projects Engineer (Giza Projects Company)  Head of Lockheed Martin Project in Egypt o Architectural drawings review and monitoring over project o Construction and infrastructure drawings review and monitoring over project o Assigning sub-contractors and following  Designerof stainlesssteelfirefightingboundforFMcertificationat PepsiCo “ChipsyTanash”facility  Site engineer for Chipsy Tanash bound project  ProjectengineerforSolarsystemsandUPS systemsintegrationtoall companyoffices  Site engineerforEgyptAirtraining centerproject. June 2012 - Jan 2014 Production /Site Engineer (Kemet Industries)  Facility re-planning and production line modification  Full work analysis to man power  Designing simulation to the production line  Reducing time and scrap cost by 20%  Designingmoduleaccordingto ISOsystemtomanage suppliers relations  Reducingleadtime andraw materialscost  Installing30+ sitestelecommunicationtowersfrom9:80 meters Feb 2011 – Nov 2011 Trainee (Aal-Kassem factory for metal Industries)  Designing and making Workshop drawings using NX6  Managing man power distribution Education  MBA Candidate at AASTM(2018-2020)  MSA Universitygraduate validatedby Universityof Greenwich, UnitedKingdom(August2011)  Bachelor of Industrial Systems Engineering  GraduationProject:Designingandmanufacturingof Vertical Carousel Storage/Retrieval System  Graduation Project Grade: Excellent  Member at Federation of Arab Engineers Technical training  PMP ProjectManagementProfessionalE-learning,2013  Six sigmawhite beltE-learning,2014  PV off grid systemdesignercertifiedfromSEDA organization2014  Fundamentalsof health,safetyandenvironmental control (OSHA 010) certifiedfromAUC –ESS Department2015  OSHA General industrysafetyandhealthtraining(OSHA 020) certifiedfromAUC –ESS Department 2015
  • 3.
    3 Personal skills  Computer: Excellentknowledge of MSoffice  CNCprogramming-manufacturing  CAD-CAMDesigningusingUGS6  ArenaProcessSimulation  MS Project& MS Projectserver  Mini-Tab  LinkPlanner  Primavera  SQL server  Aggregate planning( supply –Demand)  Language: Arabic: mothertongue English:fluent French:fair Personal Information  Birth date: 24/11/1988  Birth place: Cairo  Gender:Male  Religion:Muslim  Marital status: Married  Militarystatus: Exempted